    Innovations in

    Supercritical Boiler DesignCoal Gen 2010

    August 10, 2010

    Scott L. Darling and Edward S. Sadlon

  • 8/8/2019 Innovation in Super Critical Boiler

    2/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 2

    Agenda

    Introduction/Background

    Supercritical Boiler Design Features

    Case Study - Comanche

    Case Study - Iatan

    Summary

  • 8/8/2019 Innovation in Super Critical Boiler

    3/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 3

    Supercritical cycles offerincreased plant efficiency

    Steam conditionsat boiler exit

    2520 psi1005F1005F

    +5.5%

    subcriticalcycle

    supercriticalcycle

    ultra-supercriticalcycle

    +6.2%

    base line

    +4.2%

    ch

    angeinoverallp

    lantnetefficie

    ncy(relative)

    3900 psi1055F1100F

    3900 psi1117F1130F

    4134 psi1117F1150F

    state of the art

  • 8/8/2019 Innovation in Super Critical Boiler

    4/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 4

    Alstom is a world leader insupercritical boiler design

    Pioneered the Worlds First Ultra-Supercritical Steam Plant (Eddystone Unit 1)

    - 1954 design phase to 1960 startup- Initial steam conditions: 5293 psig/1210/1050/1050F- Current steam conditions: 5000 psig/1130/1050/1050F

    Fifty years after its initial operation, the steam generator for Eddystone 1operates at the most advanced conditions of any coal-fired boiler in the world.

  • 8/8/2019 Innovation in Super Critical Boiler

    5/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 5

    Supercritical Experience:

    113 Alstom directly executedsupercritical units in operation orunder construction, worldwide

    Over 70,000 MWe

    Most units in operation forover 30 years

    200 units supplied by licensees,

    using Alstom technology 132,000 MWe

    Alstom is a world leader insupercritical boiler design

  • 8/8/2019 Innovation in Super Critical Boiler

    6/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 6

    Agenda

    Introduction/Background

    Innovative Design Features

    Case Study - Comanche

    Case Study - Iatan

    Summary

  • 8/8/2019 Innovation in Super Critical Boiler

    7/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 7

    Alstom continues innovation insupercritical boiler design

    Key Alstom innovations include;- Vertical tube furnace wall for sliding pressure

    Combined Circulation PlusTM

    -

    Improved tangential firing system TFS XPTM

    Other Alstom state-of-the-art features include;

    -Alstom HP pulverizers with dynamic classifiers

    - Alstom regenerative air heater- Alstom SSC for bottom ash removal- Spiral-finned economizer

    - Furnace water cannons

  • 8/8/2019 Innovation in Super Critical Boiler

    8/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 8

    Modern supercritical boilers:once-through, sliding pressure

    Operating mode at boiler outlet

    4350

    3625

    2900

    2175

    1450

    725

    0

    psi

    1

    2

    3 1. Constant Pressure2. Modified Sliding Pressure3. Pure Sliding Pressure

    Once-through provides sufficient cooling at full load- recirculation required at part load

    Sliding pressure improves part-load efficiency,

    plant economics

  • 8/8/2019 Innovation in Super Critical Boiler

    9/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 9

    Spiral tube furnace wallsallow sliding pressure but add cost *

    SupportFingers

    Spiral to Vertical Transition Area Load Transfer

    More complex furnace support

    More complex windboxes

    Spiral tube furnace walls have fewer tubes:simplifies cooling but adds cost *

    * Fabrication, construction, maintenance

  • 8/8/2019 Innovation in Super Critical Boiler

    10/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 10

    Early vertical tube furnace wall designsrequired constant pressure operation

    ToSH

    BT Valves

    Waterwalls

    (smoothtube)

    Orifices

    Pump

    Economizer Recirc.Line

    Combined Circulation

    Feedwate

    rInlet

    Insufficient cooling for the 2-phase flow atpart load with sliding pressure Supercritical pressure maintained infurnace walls via valves at furnace outlet;

    Reduced efficiency Added complexity

  • 8/8/2019 Innovation in Super Critical Boiler

    11/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 11

    Alstoms new vertical tube furnace designallows sliding pressure operation

    Economizer

    Waterwalls

    (rifledtube)

    Recirculation Line

    Pump

    Orifices

    Separator

    ToSH

    Combined Circulation PlusTM

    Feedwater

    Inlet

    Sufficient cooling for 2-phase flow atpart load with sliding pressure No valves required at furnace outlet

    Maximized efficiency

    Reduced complexity

  • 8/8/2019 Innovation in Super Critical Boiler

    12/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 12

    Vertical tube furnace walls:Simplified support, construction, maintenance

    FeaturesFeatures

    Simplified furnacesupport

    Simplified furnaceconstruction

    Simplified furnacemaintenance

    Rifled tubing

    Combined Circulation PlusTM

  • 8/8/2019 Innovation in Super Critical Boiler

    13/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 13

    Vertical tube furnace walls: Orifices ensurecooling by matching flow to heat flux

    Combined Circulation PlusTM

    Heat flux varies acrossfurnace walls

    Orifices match fluid flowto heat flux Proper tube metaltemperatures maintained

    N i l fi i

  • 8/8/2019 Innovation in Super Critical Boiler

    14/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 14

    New tangential firing systemimproves furnace performance

    Fuel/air nozzles and

    lower level SOFA nozzlesin furnace corners

    Upper levelSOFA nozzles

    on furnace walls

    * Separated Overfire Air

    Fuel/air nozzles in corners generate counter-clockwise swirl Furnace wall SOFA* nozzles add flexibility to adjust furnace outlet swirl

    TFS XPTM

  • 8/8/2019 Innovation in Super Critical Boiler

    15/29

  • 8/8/2019 Innovation in Super Critical Boiler

    16/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 16

    Agenda

    Introduction/Background

    Supercritical Boiler Design Features

    Case Study - Comanche

    Case Study - Iatan

    Summary

    C h U it 3

  • 8/8/2019 Innovation in Super Critical Boiler

    17/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 17

    Owner = Xcel EnergyPlant output = 820 MWe (gross)

    Boiler design parameters;Main steam:

    3935 psi1055 F5,560,000 lb/hr

    Reheat steam:

    729 psi1105 F4,423,000 lb/hr

    Feedwater:

    580 FFuel:Sub-bituminous coal(PRB)

    Comanche Unit 3Key design parameters

    All data at BMCR, operating data

    Comanche Unit 3

  • 8/8/2019 Innovation in Super Critical Boiler

    18/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 18

    Comanche Unit 3Boiler design features

    Boiler type Two pass, sliding pressure supercritical

    Operating mode Base load and two-shift

    Start-up system Pump recirculation (< 30% load)

    Furnace cleaning Water cannons

    Economizer Spiral finned

    NOx reduction SCR

    Circulation system Once-through

    Furnace walls Vertical tube (Combined Circulation PlusTM)

    Firing system Improved tangential firing (TFS XPTM)

    Coal mills 6 x Alstom HP mills with dynamic classifiers

    Air Fans 2 x 60% PA, 2 x 60% FD

    Air Heaters 2 x Alstom regenerative tri-sector

    Alstom scopeBoiler island supply plus construction

    (boiler, mills, air fans, SCR, air heater, bottom ash, etc. )

    Design Features

    Alstom Scope

    Comanche Unit 3

  • 8/8/2019 Innovation in Super Critical Boiler

    19/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 19

    Comanche Unit 3Fuel

    Design Range

    Type PRB PRB

    Proximate, % wt.

    - Moisture 28.9 25.9-31.1

    - Volatiles 31.4 29.5-34.0

    - Fixed Carbon 35.2 32.3-36.0

    - Ash 4.5 4.3-7.2

    - Sulfur 0.26 0.2-0.7

    HHV, BTU/lb 8603 8234-8987

    Comanche Unit 3

  • 8/8/2019 Innovation in Super Critical Boiler

    20/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 20

    T-23

    T-12

    Comanche Unit 3Furnace wall tubing

    Note: no mixing/pressureequalizing headers requiredwithin furnace walls

  • 8/8/2019 Innovation in Super Critical Boiler

    21/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 21

    Comanche Unit 3

    Comanche Unit 3:

  • 8/8/2019 Innovation in Super Critical Boiler

    22/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 22

    Comanche Unit 3:Boiler performance matches design

    Comanche performance at full load:

    Design Actual #1 Actual #2

    MWe 820 835 828

    SH Steam 5,456,000

    3596

    1053

    693

    1104

    575

  • 8/8/2019 Innovation in Super Critical Boiler

    23/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 23

    Substantial completion: May 2010

    Performance tests: May/June 2010

    Reliability run: May/June 2010

    Commercial operation: July 2010

    Comanche Unit 3:Major milestones achieved

  • 8/8/2019 Innovation in Super Critical Boiler

    24/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 24

    Agenda

    Introduction/Background

    Supercritical Boiler Design Features

    Case Study - Comanche

    Case Study - Iatan

    Summary

    Iatan Unit 2

  • 8/8/2019 Innovation in Super Critical Boiler

    25/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 25

    Owner = KCP&LPlant output = 920 MWe (gross)

    Boiler design parametersLive steam:

    3786 psi1085 F6,246,000 lb/hr

    Reheat steam:

    1030 psi1085 F5,072,000 lb/hr

    Feedwater:

    568 FFuel:Sub-bituminous coal(PRB)

    All data at BMCR, operating data

    Same design features as Comanche Unit 3

    Iatan Unit 2Key design parameters

    Iatan Unit 2:

  • 8/8/2019 Innovation in Super Critical Boiler

    26/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 26

    First coal fire: July, 2010

    Commissioning: In progress; currently

    operating at 80% load

    Commercial operation Planned late 2010

    Iatan Unit 2:Major milestones achieved

  • 8/8/2019 Innovation in Super Critical Boiler

    27/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 27

    Agenda

    Introduction/Background

    Supercritical Boiler Design Features

    Case Study - Comanche

    Case Study - Iatan

    Summary

  • 8/8/2019 Innovation in Super Critical Boiler

    28/29

    ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to anyparticular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, withoutexpress written authority, is strictly prohibited.

    Innovations in Supercritical Boiler Design - Coal Gen 2010 - August 10, 2010 - P 28

    Alstom continues to develop innovative designfeatures for supercritical boilers;- Combined Circulation PlusTM

    -

    TFS XPTM

    These features provide;- Reduced capital cost- Reduced maintenance cost

    -Improved performance

    Two recent applications demonstrate these benefits;- Comanche (in commercial operation)-

    Iatan (in commissioning) Alstom can bring those benefits to future projects,

    worldwide- Including ultra-supercritical applications

    Summary