Public procurement and innovation - Suzan Ikävalko (Culminatum Innovation)
Innovation in Procurement: a Public sector case study
Transcript of Innovation in Procurement: a Public sector case study
![Page 1: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/1.jpg)
Innovation in Procurement: a
Public sector case study
Professor Danny Samson
University of Melbourne
Agenda
1. What works? … Diggerworks!
2. Some core requirements for procurement
innovation in complex ‘public’ circumstances
![Page 2: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/2.jpg)
UNCLASSIFIED
DIGGERWORKS Three key elements to moving public sector procurement to best practices
Strong and clear leadership (of the opportunity)
Alignment of numerous parties with the outcome goal
Process Integration of stakeholders (goals, activities, measures)
And don’t forget the governance too…
![Page 3: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/3.jpg)
UNCLASSIFIED
The presentation is based on Cebon, P., & Samson, D. 2013. Diggerworks: Driving innovation and effectiveness
in the defence sector: DSTO-GD-0738. Canberra: Defence Science and Technology Organisation.
Governing innovation in an extremely constraining environment – lessons from Diggerworks
![Page 4: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/4.jpg)
UNCLASSIFIED
The Problem
ADF Combatant
1999
ADF Combatant
2010 (Xmas tree)
Insert Picture
![Page 5: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/5.jpg)
UNCLASSIFIED
On the surface
Troops frustrated
– Soldiers in Iraq equipped for East Timor
– Soldiers in Afghanistan equipped for Iraq
Troops over-burdened
– Walking loads up to 80 kg
Local manufacturers upset at imported equipment
Troops didn’t trust DMO
Chief of Army inundated with complaints
DMO had large stores of obsolete equipment
Quality problems with equipment
![Page 6: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/6.jpg)
UNCLASSIFIED
A little deeper
Strategic environment and technology change faster than procurement cycle
– Timor Aceh Solomon Islands Iraq Afghanistan
![Page 7: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/7.jpg)
UNCLASSIFIED
Deeper still – firing on all cylinders: separately
ARMY
Sets requirements and soldiers
on
DMO
Procures and
sustains
DSTO
Researches
• Best available components– for a different time and place • Components were not integrated
• Soldiers, politicians and local industry lose confidence in system
![Page 8: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/8.jpg)
UNCLASSIFIED
The Stakeholders
Army Capability Development
Group
Defence Materiel
Organisation
Defence Science &
Technology Organisation
As the capability manager, Army had an imperative to provide close combat soldiers with the best possible equipment.
CDG have a responsibility to define the future capability requirements on behalf of Army and needed a more effective means of delivering real Soldier System enhancements through DCP funding.
Simply sustaining the existing Soldier system was not meeting the needs of soldiers and DMO needed find a way to deliver incremental enhancement of the Soldier System.
DSTO needed a stronger link to the Soldier System stakeholders to be able to influence capability development and acquisition decisions and to guide iterative development through user centred design.
![Page 9: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/9.jpg)
UNCLASSIFIED
![Page 10: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/10.jpg)
UNCLASSIFIED
The Strategy
- Stakeholder Partnership - Adaptive Acquisition - Innovation Strategy
- User Centred - Threat Directed - Evidence Based - Research Enabled
![Page 11: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/11.jpg)
UNCLASSIFIED
Integrated Team
Army
CDG
DMO/LEA
DSTO
Adaptive Acquisition
Delivery
Champions for
Partnership
Top Down
Partnership Director
Partnership
AHQ – MAJGEN Caligari
DMO – MAJGEN Cavanaugh
DSTO – Dr Oldfield
CDG – BRIG Rerden
Army Capability
Integration Board
AHQ – COL Gabriel
DMO – COL Blain
DSTO – Dr Beagley
CDG – COL Saddington
JOC – COL Goodyer
Diggerworks Stakeholder
Group
DMO – BRIG Phelps
Integrated Soldier
Systems Branch
Navy, Air, JHC, CIED
Governance
DSTO - Radtke
CEO – Dr Hodge
DSTO – Radtke
DMO – Foreman
Dr Humphries
Combined S&T Plan
Dr Patterson [LOD,WSD, etc]
Innovation
Deliver Enhanced
Combat Ensemble
to the Soldier
S&T
Capability
![Page 12: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/12.jpg)
UNCLASSIFIED UNCLASSIFIED
Army
DMO DSTO CDG
Partnership Principles: • Shared Goals • Trust & Respect • Risk Acceptance
Other
Stakeholder Partnership
![Page 13: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/13.jpg)
UNCLASSIFIED
Partnership Memorandum of Understanding
![Page 14: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/14.jpg)
UNCLASSIFIED
No longer is everyone equipped the same:
Tier 1 – Specialists
Tier 2 – Close Combatants
Tier 3 – General Combatants
The close combatant is treated differently.
Adaptive Acquisition Buy Less, More Often
![Page 15: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/15.jpg)
UNCLASSIFIED
Force Generation Cycle = Fixed Delivery Deadlines
Yr
0
Yr
1
Yr
2
Yr
3 Force
Generation
Cycle
Adaptive
Acquisition
High Readiness &
Operations
Reconstitute &
Individual Training
Collective Training &
Force Preparation
Battle Group on
Operations
Op
Feedback
Integration
& Testing @
Diggerworks
Refined
Tender
Spec
Acquire &
deliver new
System
2 Yr Turnaround
Ready Reset Readying
User Need
Refined
Trg Feedback
Modify
Plan Plan Plan Plan Plan
Adaptive Acquisition:
![Page 16: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/16.jpg)
UNCLASSIFIED
Support the User The system must be integrated with the soldier. Fitting, training and adapting the system to user feedback is vital to soldier system success.
Evidence based Capability decisions must be based on the best available evidence gathered and assessed in a timely manner.
Adaptive Acquisition
Respond & Adapt Monitor and adapt to the threats being encountered and emerging technological opportunities to improve the performance/burden balance
Learn from Operations Gather and respond to insights from real users, conducting real tasks and confronting real world threats
User Centred Cycle
![Page 17: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/17.jpg)
UNCLASSIFIED
Casualty & Protective Equipment Analysis Returned Armour Assessment Tailored Models SCE Targeted Individual & Team Deployments Returned Personnel Debriefs
Threat Directed
![Page 18: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/18.jpg)
UNCLASSIFIED
Advanced Materials Cognitive Load, DBMS Interaction
Anthropometry Returned Armour Ballistic Vulnerability
Performance Measurement & Modelling
Physical Capacity Signature Management
Ergonomics/ Field Evaluation
Etc ………
Injury Mechanisms
Burden: Thermal, Load, etc
Evidence Based & Research Enabled
![Page 19: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/19.jpg)
UNCLASSIFIED
Defence Technology Innovation Space S
ys
tem
Re
ad
ine
ss
Le
ve
l (S
RL
)
Technology Readiness Level (TRL)
IMMATURE MATURE
Matu
re
Imm
atu
re
RPDE CDG
PIC IP DMO
CTD DSTO
DMTC DMO
CERP DSTO
5 9 1
Diggerworks DMO
IQ1 IQ2
IQ3 IQ4
Defence Minors
CTDE DSTO
![Page 20: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/20.jpg)
UNCLASSIFIED
DMTC Project TRL Map
Majority of DMTC
projects look to
develop technology
from TRL 3-4 up to
around 6-8
DMTC also
conducts
fundamental
research projects
that feed into larger
programs
e.g. new material
characteristics
DMTC also
conducts projects
that feed directly
into platforms and
production lines
e.g. automated
welding
![Page 21: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/21.jpg)
UNCLASSIFIED
DMTC Personnel Survivability Program 7 DMTC Program 7 has been established and funded $7.5M cash leveraging
$20M in-kind, 5 years Currently 4 technical thrust areas: Technology Outputs
7.4.2 Power and Data Integrated T-BAS
7.4Power Generation and
Mgt
Individual Power Generation
Individual Power & Data Distribution
Individual Power Storage.
Integration of Power and Data Systems
7.4.1Portable Power Generation and
Storage
Improved Anti-Ballistic Soft
Armour
7.3Advanced Fabric
Technologies
Physical Protection
Habitability
CBR
7.3.1High Strength Fabrics for
Combat Clothing
7.3.2Fabric Treatment for Improved
Habitability
7.2 Soft Armour SystemsEnhanced Ballistic Protection
Lighter Weight Ballistic Protection7.2.1
7.1.2 High Curvature Body Armour
Technology Group Project Number & Name
7.1 Hard Armour SystemsPlate Technologies
Helmet Technologies
7.1.1 Ceramic Armour Technology
![Page 22: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/22.jpg)
UNCLASSIFIED
The Result
ADF Combatant
2012
^ so far
ADF Combatant
2010
Went from
worst
equipped to
best
![Page 23: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/23.jpg)
UNCLASSIFIED
TBAS – Tier 2 (6.8 kg) MCBAS (11.0 kg)
![Page 24: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/24.jpg)
UNCLASSIFIED
Integrated removable knee pads
Current Version 5 Terra Combat Boot
2013 Afghanistan Equipment
AMP Combat Trousers
Stretch panels to facilitate body
movement (rear waist, crotch, knees)
Pelvic Protection System: Tier
1 (under garment, not visible)
Tier 2 (over garment, not shown)
LA 5 Aiming Device
Integrated removable elbow pads
Australian F88 Advanced Combat Optical
Gun Sight
AMP Combat Shirt
Enhanced Combat Helmet Upgrade 2
(VAS Shroud, OPSCORE retention
system, Team Wendy Pads) Ballistic and Laser Ocular Protection
System (Sunglasses)
Hydration System (on back)
Tiered Body Armour System (includes
load carriage, ammunition pouches and
belt)
F88SA2 Rifle
Combat Gloves
Soldier Personal Radio, Switch Pack and
Headset
NINOX NVG and WILCOX mount (not
shown)
Garmin Foretrex GPS (under shirt
sleeve)
MultiBand Inter/Intra Team Radio, Whip
Antenna, Holster, Battery and Headset
(on back, whip antenna visible)
Field Packs available for use (not shown): Sniper/Spec Packs (new), Medium Assault Pack, Small Assault Pack
(Special Forces only) and Large Field Pack 05
AMP Hat (not shown)
AMP Field Shirt (not shown)
![Page 25: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/25.jpg)
UNCLASSIFIED
Outcomes delivered through ^ Some of the
![Page 26: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/26.jpg)
UNCLASSIFIED
Integrated Team
Army
CDG
DMO/LEA
DSTO
Adaptive Acquisition
Delivery
Champions for
Partnership
Top Down
Partnership Director
Partnership
AHQ – MAJGEN Caligari
DMO – MAJGEN Cavanaugh
DSTO – Dr Oldfield
CDG – BRIG Rerden
Army Capability
Integration Board
AHQ – COL Gabriel
DMO – COL Blain
DSTO – Dr Beagley
CDG – COL Saddington
JOC – COL Goodyer
Diggerworks Stakeholder
Group
DMO – BRIG Phelps
Integrated Soldier
Systems Branch
Navy, Air, JHC, CIED
Governance
DSTO - Radtke
CEO – Dr Hodge
DSTO – Radtke
DMO – Foreman
Dr Humphries
Combined S&T Plan
Dr Patterson [LOD,WSD, etc]
Innovation
Deliver Enhanced
Combat Ensemble
to the Soldier
S&T
Capability
![Page 27: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/27.jpg)
UNCLASSIFIED
The problem:
Innovators must balance knowledge creation and control
– Low control – knowledge-creation lacks direction
– High control – kills creativity
The military has high barriers to innovation
– High control culture
– Complex organisational environment
– Hierarchical – Three agencies with three ministers
![Page 28: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/28.jpg)
UNCLASSIFIED
Technical Innovation:
•Import components
•Innovate components
•Configure components
From Mass Production (trench warfare) to Flexible Specialisation (local teams)
e.g. Boxer shorts
e.g. Kinetic batteries
e.g. Tiered armor
![Page 29: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/29.jpg)
UNCLASSIFIED
Technical Innovation:
•Import components
•Innovate components
•Configure components
From Mass Production (trench warfare) to Flexible Specialisation (local teams)
Management Practices:
• Delivery system (Ops and innovation)
• Governance system
• Leadership
![Page 30: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/30.jpg)
UNCLASSIFIED
Delivery and innovation systems
•Knowledge creation
•Communication
•Bureaucratic barriers
![Page 31: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/31.jpg)
UNCLASSIFIED
Technical Innovation:
•Import components
•Innovate components
•Configure components
Management Innovation:
•Import practices
•Innovate practices
•Configure practices
From Mass Production (trench warfare) to Flexible Specialisation (local teams)
Management Practices:
• Operations delivery
• Innovation delivery
• Governance
Gruntworks
Adaptive acquisition
Reclassification
A package that fits
the constraints
![Page 32: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/32.jpg)
UNCLASSIFIED
Governance system and leadership
• Objectives and approach
• Knowledge management
• Procurement
• Climate
• Leadership
![Page 33: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/33.jpg)
UNCLASSIFIED
Beyond the military
Critical role of leadership
• Frame the problem
• Create the solution environment • Structural arrangements
• Knowledge management
• Communications
• Barriers
• Climate
• Maintain the solution environment
Critical role of governance • Manage difficult decisions and relationships
• Push responsibility up and credit down
![Page 34: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/34.jpg)
UNCLASSIFIED BALANCE AND INTEGRATION
Development of an Integrated
Soldier System through successive
and considered enhancement
Lethality
Survivability
DSA Sustainability
Mobility
![Page 35: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/35.jpg)
UNCLASSIFIED
DIGGERWORKS Three key elements to moving public sector procurement to best practices
Strong and clear leadership (of the opportunity)
Alignment of numerous parties with the outcome goal
Process Integration of stakeholders (goals, activities, measures)
And don’t forget the governance too…
(These are common to public sector best procurement practices, eg Sydney Olympics, NSW government public housing maintenance)
![Page 36: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/36.jpg)
Procurement Innovation: a modern approach
![Page 37: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/37.jpg)
STRATEGY
What is your
competitive
positioning?
OPERATING PRACTICES
What is key do delivering
the strategy?
MEASURES OF
PERFORMANCE
Are we measuring
and reporting the
right things? REWARDS &
RECOGNITION
Do they reinforce
the strategy?
BEHAVIOUR
AND CULTURE
Do they drive the
operations in the right
(strategic) direction?
Business Building Blocks: The connections matter!
![Page 38: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/38.jpg)
PROCUREMENT
STRATEGY
What is your
competitive
positioning?
PROCUREMENT
OPERATING PRACTICES
What is key do delivering
the strategy?
MEASURES OF
PROCUREMENT
PERFORMANCE
Are we measuring
and reporting the
right things?
REWARDS &
RECOGNITION
OF
PROCUREMENT
Do they reinforce
the strategy?
PROCUREMENT
BEHAVIOUR
AND CULTURE
Do they drive the
operations in the right
(strategic) direction?
Business Building Blocks: The connections matter!
![Page 39: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/39.jpg)
PROCUREMENT
STRATEGY
What is your
competitive
positioning?
PROCUREMENT
OPERATING PRACTICES
What is key do delivering
the strategy?
MEASURES OF
PROCUREMENT
PERFORMANCE
Are we measuring
and reporting the
right things?
REWARDS &
RECOGNITION
OF
PROCUREMENT
Do they reinforce
the strategy?
PROCUREMENT
BEHAVIOUR
AND CULTURE
Do they drive the
operations in the right
(strategic) direction?
Business Building Blocks: The connections matter!
Innovation in
procurement?
Set up and resource for
Innovation in
procurement practices!
Measure/ KPIs for
Innovation in
procurement practices?
Recognise/ Reward
Innovation in
procurement practices?
Behaviour/ culture of
Innovation in
procurement practices!
![Page 40: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/40.jpg)
Innovation: Why collaborate?
Reduce costs
Deliver consistent quality
Increase resilience
Pool scarce resources/expertise
Migrate to best technology platforms
Share risks: reduce risks!
Increase purchasing power
![Page 41: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/41.jpg)
Collaborative procurement options
![Page 42: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/42.jpg)
Consortia
The Market
Buyer Buyer Buyer Buyer
Central Procurement
![Page 43: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/43.jpg)
Collaboration strategy
Conversation (networking)
Coordination
Cooperation
Collaboration
(Derived from Huxham, 1996)
![Page 44: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/44.jpg)
So lets examine 10 Fundamental Strategies and
Best Practices to consider embracing to “ Achieve
Procurement & Supply Chain Excellence”
1. Establish a governing council
2. Align the supply chain
organization
3. Recruit procurement / supply
chain professionals
4. Set the Strategic Sourcing
strategy
5. Establish key supplier alliances
6. Manage Total Cost of Ownership
7. Manage compliance and Risk
8. Optimize owned inventory
9. Gather / report information on a
timely basis
10. Establish processes and
controls
44
Many of these introduce opportunities to innovate!
![Page 45: Innovation in Procurement: a Public sector case study](https://reader031.fdocuments.net/reader031/viewer/2022012421/6175fa76e92f7f0384625b0a/html5/thumbnails/45.jpg)
UNCLASSIFIED
Questions