Injector/Re-injection Chicane
Michael Bevins
May 17, 2007
12GeV Upgrade - Beam Transport
Injection, Linac, Extraction, & Correctors
Preliminary Design and Safety Review
Outline
• Introduction & Scope• Requirements & Specifications• New/Modified Elements/Girder Count• Beam Transport Layouts• Safety Considerations• Cost Estimates• Risk Assessment• Summary
• 12GeV field strength requirements force us to replace the dipoles on the re-injection chicane girder with higher strength magnets
• Songsheet level machine layouts will be presented along with cost estimates
Introduction & Scope• To accommodate the new arc 10 line the injector line will need to be shifted over
the transfer lines beginning 20.51m upbeam of the current position
– Two existing quad girders will move over the transfer lines
– Three girders already over the transfer lines will be shifted to suit the new optics design
• Existing quad girders and diagnostics will be reused
• Two new quad girders will be installed
• The 45MeV spectrometer will need to be upgraded and relocated upbeam
– Upgrades & final location TBD
Injector & Reinjection
Requirements & Specifications
• Alignment specs
– Quads positioned to +/-0.5mm in x & y, +/- 1.0mm in z
• Vacuum specs
– Beam line partial pressure of hydrogen <10-6 torr
– Total average pressure of all other constituents less than 5x10-7 torr
• Fabrication, welding, cleaning & handling, and leak checking specs still apply
– 22631-S-001 Fabrication of Ultra-High Vacuum Equipment
– 22632-S-001 Cleaning and Handling of U.H.V. Components
– 22633-S-001 Welding Specification For U.H.V. Components
– 22634-S-001 Helium Leak Test For U.H.V. Components
– Note an update and modernization of our vacuum specs is underway
New/Modified Elements/Girder Count
• Preliminary - pending CASA review and more detailed vacuum study
• Elements in red are part of I&C WBS
Element Qty Element QtyQuads 11 Diagnostics
QD 11 BPM 11Correctors 25 ISC (scraper) 2
AT 18 ISR 1IM 2 Harp 5HC 1 Viewer 3DB Horizontal 2 Vacuum
DJ Vertical 2 Ion Pump 6Dipoles 7 Convectron Gauge 1
CB 3BL 4
QtySingle Quad Girders 11
Beam Transport Layouts – Injector Line
Spectrometer shifted upbeam
Arc 10 four meter dipoles
Four Quad Girders (2 new, 2 rebuilt on short girders) BL dipole shifted
20.51m upbeam
Arc 10 quad girder
12GeV Configuration
Current Configuration
Existing injector line running under arc 8
Shift quad girders upbeam with dipoles
VERY congested area– Documentation of existing
stand positions & configuration is incomplete
– Plan to work closely with alignment group to gather as-built machine configuration
Beam Transport Layouts – Injector Line
BL dipole to replace DK (moved 20.51m upbeam)
Shift existing girders
Current Configuration
12GeV Configuration
BL dipole Quad girders
Existing injector line girders relocated over transfer line
No change to this BL dipole or girder
Beam Transport Layouts – Injector Line
Modified re-injection chicane girder
Current Configuration
12GeV Configuration
No changes between dipoles
Beam Transport Layouts – Re-injection Chicane
• Re-injection chicane girder modifications– Replace dipoles with
higher strength magnets
– Use existing support stand
– Modify plate to accommodate new magnets
Beam Transport Layouts – Selected Images
View looking downbeam
Spectrometer lineArc 8 dipole
Injector line quad girder
Safety Considerations
• Personnel Training
– Jlab & sub-contractor
• Radiation
– Designated areas for containment and radiation survey of material that will be removed from the tunnel
• Material handling
– Provide provisions for lifting
• Electrical Hazards
– Package and support electronics, power leads and terminal blocks to control electrical hazards
Cost Estimates –Injector/Re-Injection WBS Rollup
WBS Elements I have covered today
12GeV Beam Transport Scope, Labor & Procurement Estimate
D/PM & J Material
1.3.4.4INJECTOR & RE-INJECTION 23.5 16.1 25.2 64.8 14.1 94.0 32.0 2.0 0.0 0.0
1.3.4.4.1 DIPOLES 7.0 3.7 0.5 11.2 2.8 32.1 11.2 2.0 0.0 0.0
1.3.4.4.2QUADS &CORRECTORS
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.3.4.4.4GIRDERS & STANDS
8.2 8.9 1.4 18.5 4.5 50.4 17.5 0.0 0.0 0.0
1.3.4.4.6 VACUUM 1.5 1.5 3.3 6.3 1.2 9.4 2.6 0.0 0.0 0.0
1.3.4.4.7INSTALLATION &ALIGNMENT
6.9 2.0 20.0 28.9 5.6 2.0 0.7 0.0 0.0 0.0
TotalContingency
Total Contingency
LABOR [Man Wks] PROCUREMENTS [$k] EXPENSES [$k]
WBS ELEMENT ME MD MT Total Contingency
Cost Estimates - Highlighted WBS
Girders & Stands - Procurements
WBSELEMENT /Activity ID
ACTIVITY DEFINITION / SCOPE ITEMS Basis D/PM JD/PM & JTotal [$k]
1.3.4.4.4GIRDERS &
STANDS50.4 17.5
2 Proc/Vend Fab New ReInjection Stands (INJ/RE-INJ Stands) 5.4 1.9
m Procure pedestal style stands for QDs upstream of first BL 900 4 3.6 eng jud 0.35 1.3
m Procure stands to support new girders over the transfer lines 900 2 1.8 eng jud 0.35 0.63 Proc Alignment Cartridges (INJ/RE-INJ Stands) 0.9 0.1
m Procure new short alignment cartridges for (2) new QD girders 150 6 0.9 eng jud 0.15 0.1
4Procurem/Vend Fab Modifications for Spectrometer (INJ/RE-INJ Stands)
30.0 10.5
45 MeV spectrometer move and upgrade 30000.0 1 30.0 eng jud 0.35 10.5
5 Proc/Vend Fab New Girder for Chicane (INJ/RE-INJ Girders) 14.1 5.0
m Procure (4) new girders (upstream of first BL) 3349 4 13.4 eng jud 0.35 4.7
m Modify re-injection chicane girder for new corrector style dipoles 750 1 0.8 eng jud 0.35 0.3
ContingencyQTY
Total [$k]
PROCUREMENTS
Unit Cost [$]
Risk Assessment
• Technical - Low
– Girders & Supports – very similar designs exist and are already proven
– Alignment - same as existing machine
• Procurement Schedule - Low
– No long-lead items identified
• Cost – Low– Good cost estimates for machined parts
• Vendor & Jlab shop budgetary estimates
Summary
• Preliminary injector and re-injection beam transport layouts and cost and installation estimates are complete based on present scope
• We are in a good position to support our DOE External Project Reviews this summer
• We will continue to work closely with our friends throughout the lab (safety, CASA, installation, vacuum, alignment, RadCon, I&C, magnet measurement, operations, procurement & facilities) as we move forward
• Detailed design will be completed to support assembly and installation schedules
• We look forward to comments & recommendations from the committee