INJECTOR TEST FACILITY UPGRADE
PHASE I: 5-10 MEV INJECTOR
Feb. 7, 2014
![Page 2: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/2.jpg)
PEOPLE
Accelerator DivisionAndrew Hutton, Evelyn Akers, Arne Freyberger, James Henry, Reza Kazimi,
Geoff Krafft, Fulvia Pilat, Matt Poelker, Joe Preble, Robert Rimmer
Physics DivisionRolf Ent, Patrizia Rossi, Javier Gomez, Walt Akers, Chris Keith, David
Meekins, Andy Sandorfi, Xiangdong Wei
Engineering DivisionTrent Allison, Greg Arnold, Omar Garza, Curt Hovater, Andrew Kimber,
John Musson
2
![Page 3: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/3.jpg)
PREVIOUS CONFIGURATION
The next three slides show the ITFU configuration shown in October, 2013
3
![Page 4: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/4.jpg)
4
160 KEV SECTION- CEBAF TUNNEL
![Page 5: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/5.jpg)
5
500 KEV SECTION AND SRF ACCELERATION
![Page 6: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/6.jpg)
6
EXPERIMENTAL AREA
![Page 7: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/7.jpg)
WHAT IS NEW?(SINCE OCTOBER, 2013)
• After careful evaluation, we concluded that a 350 KV gun is a better choice than replicating the present CEBAF injector• Fewer Components• Shorter beamline• Easier radiation controls• Eliminates the capture section• Tests for precision parity experiments can be made
within the present enclose cave
7
![Page 8: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/8.jpg)
SCOPE
• 350 KV Gun• High current beam confined to the well shielded cave
• 5-10 MeV Injector• Limited to 100 nA average beam during tune• 1 nA CW in experimental area for HdIce
Completion by end of FY 2015
8
![Page 9: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/9.jpg)
9
Buncher
Chopper
WienFilter
Polarimeter/Spectrometer
¼ cryo
Present Cave wall
Slits
Harp
Solenoid BPM Faraday Cup/Beam Dump
Corrector Dipole
350 KV Gun
![Page 10: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/10.jpg)
10
Present Cave wall
HDice
Harp
BCM
Raster
QuadsSolenoid BPM Faraday Cup/Beam Dump
Corrector Dipole
![Page 11: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/11.jpg)
11
TEST CAVE – OPENING IN WALL (OCTOBER 2013)
![Page 12: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/12.jpg)
12
TEST CAVE – CLOSED WALL (NEW)
![Page 13: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/13.jpg)
LAYOUT INSIDE THE CAVE (OCTOBER, 2013)
13
Note the length of the beam line and the position of ¼ cryomodule
![Page 14: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/14.jpg)
14
New Layout Inside the Cave
![Page 15: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/15.jpg)
15
EXPERIMENTAL AREA (OCTOBER, 2013)
![Page 16: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/16.jpg)
16
New Layout of ITFU
![Page 17: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/17.jpg)
NEW LAYOUT OF ITFU
17
![Page 18: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/18.jpg)
ITFU WITH SHIELDING
18
![Page 19: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/19.jpg)
TOTAL PROJECT COST
• Cost of the entire project: $2650 • Includes the cost of facilities which is: $477
FTEs: 6.1Includes facilities: 0.4
19
![Page 20: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/20.jpg)
COST - SUMMARY
• Total procurement-direct(loaded): $766K ($1100K)• Total Labor – direct (loaded): $723K ($1071K)
• 2014 Procurement-direct(loaded): $357K ($491K)• 2014 Labor – direct(loaded): $445K ($657K)
• 2015 Procurement-direct(loaded): $409K ($609K)• 2015 Labor – direct(loaded): $278K ($414k)
20
![Page 21: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/21.jpg)
FACILITIES COST - SUMMARY
• Total Procurement-direct (loaded): $270K ($401)• Total Labor-direct(loaded): $51K ($76K)
• 2014 Procurement-direct(loaded): $122K ($180K)• 2014 Labor – direct(loaded): $17K ($25K)
• 2015 Procurement-direct(loaded): $148K ($221K)• 2015 Labor – direct(loaded): $34K ($51K)
21
![Page 22: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/22.jpg)
22
![Page 23: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/23.jpg)
23
![Page 24: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/24.jpg)
SCOPE - 2014
• Installation of • 350 KeV Gun• Laser systems• AC Power • Beamline an vacuum components• Racks for Electronics
• Acquisition• Beamline elements
• Removal of Labyrinth and hole in the wallCompletion of the straight 350 KV section
No Beam24
![Page 25: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/25.jpg)
25
1. Begin procurements2. Civil work, removal of labyrinth, hole in the wall3. AC Power4. Laser System5. Component Layout6. LCW and Instrument Air7. Install Instrumentation Racks8. Commence PSS and MPS Design9. Radiation Assessment10. Fire Safety Assessment11. Control System Design12. ¼ cryo stand design13. Begin instrumentation wiring14. Install beam line to ¼ cryo15. Survey and alignment to ¼ cryo16. Cryoline installation
No Beam
2014 Major Tasks List
![Page 26: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/26.jpg)
2014
PROCUREMENTS
![Page 27: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/27.jpg)
2014
LABOR
![Page 28: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/28.jpg)
SCOPE-2015
• Installation• Cryolines• ¼ Cryomodules• RF Systems• Shield Wall• HdIce beamline
• Acquisition• Beamline elements
28
![Page 29: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/29.jpg)
SCOPE-2015
• Commissioning• Control System• Safety Systems• Cryomodule• 350 KeV Beamline• 5 MeV Beamline
Tune mode and CW beam operations
29
![Page 30: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/30.jpg)
30
1. Remaining procurement2. Cryostand and 1/4cryomodule installation3. Cryoline and RF hook up4. Beam line from ¼ Hdice5. Beam line Instrumentation6. HdIce installation begins7. PSS and MPS installed8. Radiation controls installed9. Fire protection installed10. Control Software installed11. Shielding in the Experimental area
Commissioning of individual systems and the entire ITFU
Tune mode and 1 nA CW Beam
2015 Major Task List
![Page 31: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/31.jpg)
2015
PROCUREMENTs
![Page 32: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/32.jpg)
2015
LABOR
![Page 33: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/33.jpg)
33
1. Begin procurements2. Civil work, removal of labyrinth, hole in the wall3. AC Power4. Laser System5. Component Layout6. LCW and Instrument Air7. Install Instrumentation Racks8. Commence PSS and MPS Design9. Radiation Assessment10. Fire Safety Assessment11. Control System Design12. ¼ cryo stand design13. Begin instrumentation wiring14. Install beam line to ¼ cryo15. Survey and alignment to ¼ cryo16. Cryoline installation
No Beam
2014 Task List
![Page 34: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/34.jpg)
34
1. Remaining procurement2. Cryostand and 1/4cryomodule installation3. Cryoline and RF hook up4. Beam line from ¼ Hdice5. Beam line Instrumentation6. HdIce installation begins7. PSS and MPS installed8. Radiation controls installed9. Fire protection installed10. Control Software installed11. Shielding in the Experimental area
Commissioning of individual systems and the entire ITFU
Tune mode and 1 nA CW Beam
2015 Task List
![Page 35: INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.](https://reader030.fdocuments.net/reader030/viewer/2022032517/56649ca35503460f949630f6/html5/thumbnails/35.jpg)
We expect the project to be completed by the end of FY15
35