1 12-13 October 2006 C.E. Rago Injector / Linac Installation Current Status Manager-Kathleen Ratcliffe Project Schedule R.M. Boyce Major Partner-Mechanical Fabrication Department Installation Underway!

description

Injector / Linac Installation Current Status. Manager-Kathleen Ratcliffe Project Schedule R.M. Boyce Major Partner-Mechanical Fabrication Department Installation Underway!. 2006 Installation. Sector 21. Sector 20. Laser. BC1 Out. Bunch Compressor 1. Vault. X-Band Compressor. L1. - PowerPoint PPT Presentation

Transcript of Injector / Linac Installation Current Status

Page 1: Injector / Linac Installation  Current Status

112-13 October 2006C.E. Rago

Injector / Linac Installation Current Status

Manager-Kathleen RatcliffeProject Schedule R.M. Boyce

Major Partner-Mechanical Fabrication Department

Installation Underway!

Page 2: Injector / Linac Installation  Current Status

212-13 October 2006C.E. Rago

2006 Installation

Bunch Compressor 1

BC1 Out

X-Band Compressor

L1

Insertion/SAB

Wall

Laser

Sector 20

Sector 21

Vault

Page 3: Injector / Linac Installation  Current Status

312-13 October 2006C.E. Rago

Linac Status

Downtime Installation 8/~20 Weeks of Linac AccessPrep and Removal CompleteInstallation Priority

Linac Housing / Return to A-Line Operation January 07Vacuum Envelope & All Safety SystemsInjection Vault / Laser Schedule and ControlsSLAC Resources / MFD and OthersHardware ReadySystem Schedule / Commissioning

Good Design, Teamwork, Control

Page 4: Injector / Linac Installation  Current Status

412-13 October 2006C.E. Rago

Linac Housing

E-

Page 5: Injector / Linac Installation  Current Status

512-13 October 2006C.E. Rago

BC 1 Out

TD11 (Stopper)

BL11/12

Future EO/BL

Wire Scanner / PMT

Page 6: Injector / Linac Installation  Current Status

612-13 October 2006C.E. Rago

Bunch Compressor 1

4 DipolesBC1 Diagnostics Chambers & Supports

2 Tweeker Quads

Page 7: Injector / Linac Installation  Current Status

712-13 October 2006C.E. Rago

Bunch Compressor 1 Sub-Assembly

Page 8: Injector / Linac Installation  Current Status

812-13 October 2006C.E. Rago

X-Band Compressor

WC 293Removable 60cm X-Band

Page 9: Injector / Linac Installation  Current Status

912-13 October 2006C.E. Rago

The X-band accelerator section

Klystron, modulator being power tested prior to installation.

Page 10: Injector / Linac Installation  Current Status

1012-13 October 2006C.E. Rago

L 1

2ea 9 ½ Ft DLWG

Page 11: Injector / Linac Installation  Current Status

1112-13 October 2006C.E. Rago

Page 12: Injector / Linac Installation  Current Status

1212-13 October 2006C.E. Rago

Linac Accelerator Section Removal

Before

After

Making room for the Insertion, L-1 and L-X regions

Page 13: Injector / Linac Installation  Current Status

1312-13 October 2006C.E. Rago

Insertion / SABBX 02 Dipole

SDMP / Stopper

OTRS1 / ANL

SAB Dipole

Page 14: Injector / Linac Installation  Current Status

1412-13 October 2006C.E. Rago

Page 15: Injector / Linac Installation  Current Status

1512-13 October 2006C.E. Rago

Injection Vault

E-

Page 16: Injector / Linac Installation  Current Status

1612-13 October 2006C.E. Rago

The Injector Vault

Cable plant, vault ready for beamline components.

Page 17: Injector / Linac Installation  Current Status

1712-13 October 2006C.E. Rago

Wall

BBS Radiation Stopper

3 Wire Scanners BX 01 Dipole

Page 18: Injector / Linac Installation  Current Status

1812-13 October 2006C.E. Rago

Heater Phase 1

Heater Table

Page 19: Injector / Linac Installation  Current Status

1912-13 October 2006C.E. Rago

L0A / L0B

L0AL0B

Page 20: Injector / Linac Installation  Current Status

2012-13 October 2006C.E. Rago

L0A on the MMF CMM

Page 21: Injector / Linac Installation  Current Status

2112-13 October 2006C.E. Rago

Gun / GTLLaser Table

Gun

SAB Dipole

Page 22: Injector / Linac Installation  Current Status

2212-13 October 2006C.E. Rago

Gun-to-Linac area

Gun

Laser table

Spectrometer

L0a

GTL

uv

Page 23: Injector / Linac Installation  Current Status

2312-13 October 2006C.E. Rago

The LCLS photocathode electron gun

Page 24: Injector / Linac Installation  Current Status

2412-13 October 2006C.E. Rago

Linac Downtime IssuesBPM feed-through 10-9 He leak

Old problem / New again (~3/23 BPMs On Temporary Hold)

BC 1 Diagnostics2/3 Assemblies close with Fab. SLA BPM is probably late for January.

Late components:BLM 11 (BLM 12 will be in)Toroids (All Locations / Vendor Failure)Vacuum chambers in insertion region. (next slide)

Spool pieces are being fabricated to not prevent Commissioning Start.Scheduled Downtime will be needed to install these components

January : March to support current Commissioning schedule.

Page 25: Injector / Linac Installation  Current Status

2512-13 October 2006C.E. Rago

LCLS Insertion region

Vac Chambers late for January

Linac integrity needed for ESA program in Jan.

Linac beam

LCLS Injection

Page 26: Injector / Linac Installation  Current Status

2612-13 October 2006C.E. Rago

Injector Installation Status

Injector installation has taken second priority to Linac installation.

Injector vault:Floor and cable plant installed

Injector beamline:Accelerator structures, L0a ready, L0b in final bakeRF waveguide needs to go through bakeGun in hot test at Klystron Mfg

2nd gun is in pre-braze cold-test.Vault Supports & Tables waiting DB start.

except for the GTL supports & table

Page 27: Injector / Linac Installation  Current Status

2712-13 October 2006C.E. Rago

Injector Installation Issues

Water system under pressure to make schedule!1 BPM in GTL waiting feedthrough resolution.

Late:Torroids are not delivered from Vendor The GTL stand is out for quote

Estimate it will be here 11/16 for installation 11/20.

Laser table installation begins 11/27 The Gun will be ready by Laser Table install. GTL is late, released for machining.

Working all issues with MFD to expedite schedule. Improve on 2/15/07 Date.

Page 28: Injector / Linac Installation  Current Status

2812-13 October 2006C.E. Rago

Some Good Stuff

Good Design with Solid Documentation.

Active Data BaseInterconnect Control

Component Histories

Non-Compliance

Effective Teamwork MFD/MD/KLY/AD

Downstream Linac under design!