Ingeniería sostenible de fundaciones profundas alessandro mandolini

107
Prof. Ing. Alessandro Mandolini, Ph.D. SUSTANAIBLE PILING ENGINEERING

Transcript of Ingeniería sostenible de fundaciones profundas alessandro mandolini

Prof. Ing. Alessandro Mandolini, Ph.D.

SUSTANAIBLE PILING ENGINEERING

SUSTAINABILITY

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

2

SUSTAINABILITY FOR FOUNDATION ENGINEERING

It contributes to social growth by means of cost-effective and environmentally-friendly foundation system for different structures and infrastructures.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

3

It contributes to social growth by means of cost-effective and environmentally-friendly foundation system for different structures and infrastructures. When dealing with pile foundations, the more suitable foundation system is that where piles are: - EFFECTIVE - PRACTICAL - ECONOMIC

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

4

SUSTAINABILITY FOR FOUNDATION ENGINEERING

REQUIREMENTS FOR A GOOD PILE DESIGN

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

5

Effective, Practical, Economic Piles must carry the loads that the supported structure imparts to them, together with any additional forces that may result from deformations of the soil mass in which they are embedded. Piles must also be sound, durable and free from significant defects. Their design must recognize fully the properties of the ground and the implications of groundwater movements so that deformations or settlements will not cause unacceptable strains in the supported or adjacent structures.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

6

Effective, Practical, Economic Piles must be of a type that will permit access for piling equipment to the locations where they are required. The design must recognize the limits of what is possible in current practice with regard to the equipment available. The method of construction must recognize and seek to minimize difficulties related to ground conditions that could impede proper construction.

REQUIREMENTS FOR A GOOD PILE DESIGN

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

7

Effective, Practical, Economic Design should maximize the bearing capacity of each pile while at the same time providing for an adequate margin of safety against failure or excessive deformation of either individual piles or pile groups. The materials of the pile need also to be reasonably stressed and not used wastefully.

REQUIREMENTS FOR A GOOD PILE DESIGN

EXAMPLE OF UNECONOMIC PILES

Schmertmann & Hayes (1997)

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

8

EXAMPLE OF UNECONOMIC PILES

Schmertmann & Hayes (1997)

Underestimated ultimate load values lead to higher overall costs for the foundation ......

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

9

Schmertmann & Hayes (1997)

...... as well as wasted energy for piling equipment (not environmentally-friendly).

EXAMPLE OF UNECONOMIC PILES

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

10

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

11

Effective, Practical, Economic Design should maximize the bearing capacity of each pile while at the same time providing for an adequate margin of safety against failure or excessive displacement of either individual piles or pile groups. The materials of the pile need also to be reasonably stressed and not used wastefully.

REQUIREMENTS FOR A GOOD PILE DESIGN

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

12

Effective, Practical, Economic Design should maximize the bearing capacity of each pile while at the same time providing for an adequate margin of safety against failure or excessive displacement of either individual piles or pile groups. The materials of the pile need also to be reasonably stressed and not used wastefully. “Maximize” has not to be intended as “the maximum possible bearing capacity” but as “the bearing capacity needed for a given project with a minimum cost”. At the same time, the settlement should not be as low as possible but simply smaller than some acceptable value.

REQUIREMENTS FOR A GOOD PILE DESIGN

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

13

Effective, Practical, Economic Design should maximize the bearing capacity of each pile while at the same time providing for an adequate margin of safety against failure or excessive displacement of either individual piles or pile groups. The materials of the pile need also to be reasonably stressed and not used wastefully.

“bearing capacity” RESISTANCE

“displacement” STIFFNESS

REQUIREMENTS FOR A GOOD PILE DESIGN

SUGGESTIONS BY THEORY

lim,so

lim,bpp

lim

2opp

2op

lim,blim,slim

2olim,blim,b

olim,slim,s

qr

L2q

L

1

W

R

rLWrLV

RRR

rqR

Lr2qR

Rlim

qs,lim

qb,lim

Axial soil-pile resistance, Rlim

Specific pile capacity = pile capacity per unit pile weight

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

14

SUGGESTIONS BY THEORY

Rlim

qs,lim

qb,lim

Axial soil-pile resistance, Rlim

It can be shown that the ratio Rlim/Vp attains a maximum when L/ro 0 or . It implies that longer and/or slender piles are more effective in terms of specific capacity.

lim,s

olim,b

pp

lim qr

L2q

L

1

W

R

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

15

SUGGESTIONS BY THEORY

Axial soil-pile stiffness, K = Q/w

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

16

SUGGESTIONS BY THEORY

Axial soil-pile stiffness, K = Q/w

dLL22L

dr2ln

L25.015.225.0r

GE

GG

GG

dd

d

L

L

Ltanh

1

81

d

L

L

Ltanh2

1

2

Gdw

Q

m

m

Lp

L

bL

b

L

Ratio of underream:

Soil stiffness ratio at pile base:

Degree of soil stiffness homogeneity:

Pile-soil relative stiffness:

Radius of influence of pile:

Measure of radius of influence of pile:

Measure of pile compressibility:

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

17

Randolph & Wroth (1978); Fleming et al. (1992)

SUGGESTIONS BY THEORY

Axial soil-pile stiffness, K = Q/w

There are combinations of slenderness ratio (L/d) and stiffness ratio () beyond which very little load is transmitted to the pile base. Further increase in pile length yields no corresponding increase in the load settlement ratio of the pile.

Q/(w

dG

L)

L/d

Qb/Q

L/d

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

18

Randolph & Wroth (1978); Fleming et al. (1992)

SUGGESTIONS BY THEORY

Axial soil-pile stiffness, K = Q/w

Q/(w

dG

L)

L/d

Qb/Q

L/d

A critical pile length Lc (or a critical slenderness ratio Lc/d) exists beyond which extending pile is useless in practice if settlement has to be reduced.

25.1d

Lc

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

19

Randolph & Wroth (1978); Fleming et al. (1992)

SUGGESTIONS BY THEORY

Axial soil-pile stiffness, K = Q/w

Q/(w

dG

L)

L/d

Qb/Q

L/d

%5Q

Q4025,1

d

L

MPa 30G

MPa 30000Ebc

L

p

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

20

Randolph & Wroth (1978); Fleming et al. (1992)

VALIDATION BY EXPERIMENTS

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

21

Non Displacement pile: CFA type (L = 24 m; d = 0,60 m)

0.0

1.0

2.0

3.0

0 20 40 60 80

settlement, w [mm]lo

ad

[M

N]Mandolini et al. (2002)

Non Displacement pile: CFA type (L = 24 m; d = 0,60 m)

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

22

0.0

1.0

2.0

3.0

0 20 40 60 80

settlement, w [mm]lo

ad

[M

N]

wlim = 10% d = 60 mm

Q = 1,2 MN FS = 2.7

Rlim = 3,2 MN

Mandolini et al. (2002)

VALIDATION BY EXPERIMENTS

0.0

1.0

2.0

3.0

0 20 40 60 80

settlement, w [mm]lo

ad

[M

N]

Santa Cruz, Bolivia, 2015 Alessandro Mandolini – Sustainable Piling Engineering

23

Non Displacement pile: CFA type (L = 24 m; d = 0,60 m)

wlim = 10% d = 60 mm

Q = 1,2 MN FS = 2.7

Rlim = 3,2 MN

0

5

10

15

20

25

0.0 1.0 2.0 3.0

axial load, N [MN]

de

pth

, z [m

]

Lc

FS = 2,7 m 19L3225,1d

L

MPa 40G

MPa 26500Ec

c

L

p

Mandolini et al. (2002)

VALIDATION BY EXPERIMENTS

0.0

1.0

2.0

3.0

0 20 40 60 80

settlement, w [mm]lo

ad

[M

N]

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

24

Non Displacement pile: CFA type (L = 24 m; d = 0,60 m)

wlim = 10% d = 60 mm

Q = 1,2 MN FS = 2.7

Rlim = 3,2 MN

0

5

10

15

20

25

0.0 1.0 2.0 3.0

axial load, N [MN]

de

pth

, z [m

]

Lc

FS = 2,7

0

5

10

15

20

25

0.0 1.0 2.0 3.0

axial load, N [MN]

de

pth

, z [m

]

Rb,lim

Rs,lim

FS = 1

Mandolini et al. (2002)

VALIDATION BY EXPERIMENTS

Longer and/or slender piles more effective in terms of specific capacity.

lim,s

olim,b

pp

lim qr

L2q

L

1

W

R

CONFLICTING NEEDS

d

L

L

Ltanh

1

81

d

L

L

Ltanh2

1

2

Gdw

Q

L

Shorter and/or stubby piles more effective in terms of load-settlement ratio.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

25

REMARKS

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

26

REMARKS

Fulfilling the opposite needs becomes more and more

complicated if installation effects are considered.

It offers a great number of pile types, forcing engineers to be continuously updated about new available technologies.

WORLD PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

27

It offers a great number of pile types, forcing engineers to be continuously updated about new available technologies.

“SOME” PILE TYPE (source www.geoforum.com)

Alpha Pile, Atlas Pile, Bade System, Benoto System, Brechtl System, Button-bottom Pile, Casagrande System, Compressol Pile, Continuous Flight Auger (CFA) System, Daido SS Pile, Delta Pile, Drill-and-drive Pile, Franki Composite Pile, Franki Excavated Pile, Franki Pile, Franki Pile with casing top driven, Franki VB Pfahl, Fundex Pile, Held-Franke System, Hochstrasser-Weise System, Hollow precast concrete pile with timber/steel core, Icos Veder System, Jointed Concrete Pile, Lacor Pile, Large diameter bored pile, Lind-Calweld Pile, Lorenz Pile, Mast System, Millgard Shell Pile, Mini pile, Monierbau Pile, Multiton Pile, MV-pile, Omega Pile, Pieux Choc, Precast Concrete Pile, Precast Reinforced Concrete Pile, Pressodrill, Prestcore, Prestressed Concrete Pile, Raymond Pile, Rolba Pile, Sheet Pile, Simplex System, Small diameter bored pile, Soilex System, Starsol Pile, Steel Box Pile, Steel pile, Steel Tube Pile, Steel-concrete (SC) Composite Pile, Steel-H Pile, SVB Pile, SVV Pile, Timber Pile, Tubex Pile, Westpile Shell Pile, Vibrex Cast-In-Situ Pile, Wolfholz System, X-pile, Zeissl System, …………

WORLD PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

28

WORLD PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

29

PILE CLASSIFICATION

Modified from Fleming et al., 2009

WORLD PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

30

PILE CLASSIFICATION

Modified from Fleming et al., 2009

WORLD PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

31

PILE CLASSIFICATION

Soil is laterally displaced during the insertion of pile, increasing total stress into

the surrounding soil

Soil is removed and substituted by the pile, decreasing (at the best,

leaving practically unchanged) total stress into

the surrounding soil

WORLD PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

32

PILE CLASSIFICATION

DP tends to exhibit much greater resistance than NDP due to the improvements into the surrounding soil (greater effective stresses lower porosity and greater strength)

SANDY OR GRAVELLY SOILS (drained response)

WORLD PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

33

PILE CLASSIFICATION

DP and NDP tends to exhibit comparable resistance due to limited changes in effective stresses and constant porosity condition

CLAYEY AND SILTY SOILS

(undrained response)

Poulos et al. (2001)

Some “distilled” suggestions!!!!

-method qs,lim = v

-method: qs,lim = cu

LITERATURE REVIEW: SHAFT RESISTANCE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

34

LITERATURE REVIEW: SHAFT RESISTANCE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

35

-method

= 0.5k0v for ND piles in sand = 2.0k0v for D piles in sand 400%

LITERATURE REVIEW: SHAFT RESISTANCE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

36

-method

-method

= 0.5k0v for ND piles in sand = 2.0k0v for D piles in sand

D/ND = 1.4 piles in clay

400%

40%

LITERATURE REVIEW: BASE RESISTANCE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

37

Test data: qb,lim(D) = (2.43.0)qb,lim(ND) at w = 5%d qb,lim(D) = (1.61.8)qb,lim(ND) at w = 10%d 160300%

Lee and Salgado, 1999: piles in sand

LITERATURE REVIEW: BASE RESISTANCE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

38

Test data: qb,lim(D) = (2.43.0)qb,lim(ND) at w = 5%d qb,lim(D) = (1.61.8)qb,lim(ND) at w = 10%d 160300%

Lee and Salgado, 1999: piles in sand

Any piles in fine grained soils: qb,lim = 9cu + vL

REMARKS

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

39

DP installed in coarse grained soils (gravel/sand) are expected to have greater axial resistance than NDP due to positive effects both at the pile shaft and at the pile base. Independently from the installation method, piles embedded in fine grained soils (clay/silt) are expected to have similar axial resistance.

REMARKS

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

40

DP installed in coarse grained soils (gravel/sand) are expected to have greater axial resistance than NDP due to positive effects both at the pile shaft and at the pile base.

MORE ATTENTION ON PILE TECHNOLOGY Independently from the installation method, piles embedded in fine grained soils (clay/silt) are expected to have similar axial resistance.

MORE ATTENTION TO SOIL PROPERTIES

Santa Cruz, Bolivia, 2015 Alessandro Mandolini – Sustainable Piling Engineering

41

VESUVIO BAY OF NAPLES

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

42

VESUVIO

CENTRO DIREZIONALE DI NAPOLI

BAY OF NAPLES

145 load tests on different piles installed in rather uniform subsoil conditions (SANDY SOILS)

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

43

VESUVIO

CENTRO DIREZIONALE DI NAPOLI

BAY OF NAPLES

20 load tests at failure (w 10%d) on trial piles 125 load tests on production piles

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

44

20 load tests to failure on trial cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Franki

d = 0.35 2.00 m L = 9.5 42.0 m L/d = 16 61

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

45

d = 0.35 2.00 m L = 9.5 42.0 m L/d = 16 61

Pile type (Rlim/Wp)av COV(Rlim/Wp) ND – Bored 12,1 (1) 0,26 Rlim as measured at w = 10%d

20 load tests to failure on trial cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Franki

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

46

d = 0.35 2.00 m L = 9.5 42.0 m L/d = 16 61

Pile type (Rlim/Wp)av COV(Rlim/Wp) ND – Bored 12,1 (1) 0,26 ND – CFA 37,5 ( 3) 0,25 Rlim as measured at w = 10%d

20 load tests to failure on trial cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Franki

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

47

d = 0.35 2.00 m L = 9.5 42.0 m L/d = 16 61

Pile type (Rlim/Wp)av COV(Rlim/Wp) ND – Bored 12,1 (1) 0,26 ND – CFA 37,5 ( 3) 0,25 D - Franki 73,1 ( 6) 0,08 Rlim as measured at w = 10%d

20 load tests to failure on trial cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Franki

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

48

REMARKS

The method of installation strongly affects pile response to

axial loading at failure due to remarkable changes induced into a thin soil volume close to the pile

In the quoted example, till to 6 times on the average !!

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

49

REMARKS

The method of installation strongly affects pile response to

axial loading at failure due to remarkable changes induced into a thin soil volume close to the pile

IS IT STILL VALID FOR AXIAL PILE STIFFNESS ?

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

50

VESUVIO

CENTRO DIREZIONALE DI NAPOLI

BAY OF NAPLES

20 load tests at failure (w 10%d) on trial piles 125 load tests on production piles

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

51

125 proof load tests on production cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Screw -Franki

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

52

The experimentally determined axial soil-pile stiffness K = Q/w under working load was compared with that of an equivalent column having a structural axial stiffness Kc = (EpAp)/Lc. Critical length Lc was chosen in order to compare the stiffness of the column with that of a pile having only that reduced length over which it is transferring the applied load to the surrounding soil.

125 proof load tests on production cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Screw -Franki

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

0

20

40

60

80

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

DR

IVE

N

DR

IVE

N

BO

RE

D

CO

V(K

/ K

C)

[%]

0,0

0,5

1,0

1,5

2,0

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

DR

IVE

N

DR

IVE

N

BO

RE

D

K / K

C

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

53

0

20

40

60

80

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

DR

IVE

N

DR

IVE

N

BO

RE

D

CO

V(K

/ K

C)

[%]

0,0

0,5

1,0

1,5

2,0

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

DR

IVE

N

DR

IVE

N

BO

RE

D

K / K

C

125 proof load tests on production cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Screw -Franki

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Data grouped within homogeneous geotechnical area

0

20

40

60

80

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

DR

IVE

N

DR

IVE

N

BO

RE

D

CO

V(K

/ K

C)

[%]

0,0

0,5

1,0

1,5

2,0

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

DR

IVE

N

DR

IVE

N

BO

RE

D

K / K

C

0

20

40

60

80

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

DR

IVE

N

DR

IVE

N

BO

RE

D

CO

V(K

/ K

C)

[%]

0,0

0,5

1,0

1,5

2,0

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

CF

A

DR

IVE

N

DR

IVE

N

BO

RE

D

K / K

C

1,4

35%

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

54

125 proof load tests on production cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Screw -Franki

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Data grouped within homogeneous geotechnical area

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

55

Pile type (Q/w)av COV(Q/w) ND – Bored 1,46 (1) 0,28 ND – CFA 1,44 ( 1) 0,46 D – Screw, Franki 1,29 ( 0.9) 0,42 Q/w measured at working load

125 proof load tests on production cast in situ piles (Mandolini et al., 2005) Non Displacement type: - bored (dry, bentonite, temporary steel casing) - CFA Displacement type: - Screw -Franki

EXPERIMENTAL EVIDENCE COLLECTED IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

56

REMARKS

The method of installation strongly affects pile response to axial loading at failure due to

remarkable changes induced into a thin soil volume close to the pile

IS IT STILL VALID FOR AXIAL PILE STIFFNESS ?

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

57

REMARKS

The method of installation strongly affects pile response to axial loading at failure due to

remarkable changes induced into a thin soil volume close to the pile

IS IT STILL VALID FOR AXIAL PILE STIFFNESS ?

AT MUCH LESSER EXTENT More details, also substantiated by theory, are given in Mandolini et al. (2005)

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

58

A QUESTION

HOW TO GET THE BEST FOR A GIVEN COMBINATION OF

PILE AND SOIL TYPE ?

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

59

A QUESTION

HOW TO GET THE BEST FOR A GIVEN COMBINATION OF

PILE AND SOIL TYPE ?

Two examples: CFA and FDP

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

60

CFA PILES – RESEARCH IN ITALY

SUN won a national competition for a research funding by Italian Government (about 900.000 €) Piling Contractor Partner: Società Italiana Fondazioni S.p.A. 4 experimental sites (n.c. and o.c clayey; loose and dense sandy soils) For each experimental site: detailed geotechnical investigations 5 load tests at failure on fully instrumented trial piles installed with a different set of installation parameters different concrete mix

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

61

Results of loading tests on two identical CFA piles (L = 24 m; d = 0,8 m) installed by the same piling contractor with the same operator in the same subsoil at less than 5 m ( 6d) distance

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

Top soil Alluvial Soils Base formation

GWL

EXPERIMENTAL RESULTS: POGGIOMARINO SITE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

62

Results of loading tests on two identical CFA piles (L = 24 m; d = 0,8 m) installed by the same piling contractor with the same operator in the same subsoil at less than 5 m ( 6d) distance

0,0

1,0

2,0

3,0

4,0

5,0

0 20 40 60 80

load [M

N]

settlement, w [mm]

total load

shaft load

base load

0,0

1,0

2,0

3,0

4,0

5,0

0 20 40 60 80

load [M

N]

settlement, w [mm]

4.08 MN

2.81 MN

1.55 MN

5.30 MN

3.94 MN

1.36 MN

w > 10%d failure

w << 10%d no failure

EXPERIMENTAL RESULTS: POGGIOMARINO SITE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

63

Results of loading tests on two identical CFA piles (L = 24 m; d = 0,8 m) installed by the same piling contractor with the same operator in the same subsoil at less than 5 m ( 6d) distance

0,0

1,0

2,0

3,0

4,0

5,0

0 20 40 60 80

load [M

N]

settlement, w [mm]

total load

shaft load

base load

0,0

1,0

2,0

3,0

4,0

5,0

0 20 40 60 80

load [M

N]

settlement, w [mm]

4.08 MN

2.81 MN

1.55 MN

5.30 MN

3.94 MN

1.36 MN

w > 10%d failure

w << 10%d no failure

EXPERIMENTAL RESULTS: POGGIOMARINO SITE

? ?

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

64

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0,0

1,0

2,0

3,0

4,0

5,0

0 20 40 60 80

load [M

N]

settlement, w [mm]

total load

shaft load

base load

0,0

1,0

2,0

3,0

4,0

5,0

0 20 40 60 80

load [M

N]

settlement, w [mm]

4.08 MN

2.81 MN

1.55 MN

5.30 MN

3.94 MN

1.36 MN

w > 10%d failure

w << 10%d no failure

EXPERIMENTAL RESULTS: POGGIOMARINO SITE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

65

CFA PILES – RESEARCH IN ITALY

65

Concrete

Pump

PENETRATION STAGE Rate of penetration, vP

Rate of revolution, ωP

Viggiani (1989, 1993) Kinematic analysis: in order not to decompress surrounding soils: VP > VP,CR = P[1-(d0/dN)2] = pitch of the screw d0 = outer diameter of the central hollow stem dN = overall diameter of the auger

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

66

CFA PILES – RESEARCH IN ITALY

Concrete

Pump

“net” compressed soil: vP > x

“net” decompressed soil: vP < x

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

67

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0 10

20

[ r .p .m .]

0 25

0

50

0

VP

[m /h ]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0

10

20

30

0 10

20

30

qc [M Pa]

de

pth

[m

]

0,0

1,0

2,0

3,0

4,0

5,0

0 20 40 60 80

load [M

N]

settlement, w [mm]

total load

shaft load

base load

0,0

1,0

2,0

3,0

4,0

5,0

0 20 40 60 80

load [M

N]

settlement, w [mm]

4.08 MN

2.81 MN

1.55 MN

5.30 MN

3.94 MN

1.36 MN

w > 10%d failure

w << 10%d no failure

De

co

mp

ressio

n a

lon

g t

he

en

tire

p

ile

sh

aft

an

d a

t th

e p

ile

ba

se

C

om

pe

nsa

tion

alo

ng

the

en

tire p

ile s

ha

ft a

nd

de

co

mp

ressio

n a

t the

pile

ba

se

EXPERIMENTAL RESULTS: POGGIOMARINO SITE

qs,lim = s qc,s

qb,lim = b qc,b

0.02

0.03

0.04

0.0 1.0 2.0VP/VP,CR

S

0.15

0.20

0.25

0.0 1.0 2.0VP/VP,CR

B

s = 0,026 x (VP/VP,CR) + 0,004 b = 0,115 x (VP/VP,CR) + 0,153

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

68

EXPERIMENTAL RESULTS: POGGIOMARINO SITE

+50%

+40%

qs,lim = s qc,s

qb,lim = b qc,b

b = 0,115 x (VP/VP,CR) + 0,153

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

69

EXPERIMENTAL RESULTS: POGGIOMARINO SITE

Lee and Salgado, 1999: piles in sand

0.15

0.20

0.25

0.0 1.0 2.0VP/VP,CR

B

Velocity index, IV = VP / VP,crit Low values for IV determine a net effect of soil decompression, thus CFA piles badly installed. It has to be expected, under other same conditions, low shaft and base resistances “ND pile”

High values for IV determine a net effect of soil compression, thus CFA piles conveniently installed. It has to be expected, under other same conditions, high shaft and base resistances “D pile”

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

70

CFA PILES – RESEARCH IN ITALY

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

71

CATEGORY TYPE PERCENTAGE TOTAL

DP

SCREW 7

51 PREFABRICATED 33

DRIVEN CAST IN PLACE 11

NDP BORED 26

49 CFA 23

WORLD PILE MARKET (Source DFI, 2006)

Remarkable differences countries by countries

0

20

40

60

80

100

1984 1985 1986 1987 1988 1989 1990 1991 1992

% o

f pile t

ype

non displ. piles

auger piles

displ. piles

ITALIAN PILE MARKET Trevisani, 1992

“In the next future, auger piles will probably gain the market against the smaller size (d = 80120 cm) of the large diameter bored piles”

30%

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

72

CATEGORY TYPE PERCENTAGE TOTAL

DP

SCREW 7

51 PREFABRICATED 33

DRIVEN CAST IN PLACE 11

NDP BORED 26

49 CFA 23

WORLD PILE MARKET (Source DFI, 2006)

0

20

40

60

80

100

1984 1985 1986 1987 1988 1989 1990 1991 1992

% o

f pile t

ype

non displ. piles

auger piles

displ. piles

ITALIAN PILE MARKET Trevisani, 1992

CATEGORY TYPE PERCENTAGE TOTAL

DP

SCREW 7

51 PREFABRICATED 33

DRIVEN CAST IN PLACE 11

NDP BORED 26

49 CFA 23

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

73

0

20

40

60

80

100

2000 2001 2002 2003 2004

Mandolini, 2004

55%

WORLD PILE MARKET (Source DFI, 2006)

30%

Report n. FHWA-HIF-07-03

PREFACE: “CFA piles have been used in the U.S. commercial market but have not been used frequently for support of transportation structures in the United States. This underutilization of a viable technology is a result of perceived difficulties in quality control, and the difficulties associated with incorporating a rapidly developing (and often proprietary) technology into the traditional, prescriptive design-bid-build concept……”

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

74

REPERCUSSION IN OTHER PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

75

+50% +40%

REPERCUSSION IN OTHER PILE MARKET

Report n. FHWA-HIF-07-03

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

76

REPERCUSSION IN OTHER PILE MARKET

Report n. FHWA-HIF-07-03

PREFACE: “CFA piles have been used in the U.S. commercial market but have not been used frequently for support of transportation structures in the United States. This underutilization of a viable technology is a result of perceived difficulties in quality control, and the difficulties associated with incorporating a rapidly developing (and often proprietary) technology into the traditional, prescriptive design-bid-build concept. Recent advances in automated monitoring and recording devices will alleviate concerns of quality control, as well as provide an essential tool for a performance-based contracting process.”

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

77

REPERCUSSION IN OTHER PILE MARKET

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

78

A QUESTION

HOW TO GET THE BEST FOR A GIVEN COMBINATION OF

PILE AND SOIL TYPE ?

Two examples: CFA and FDP

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

79

CATEGORY TYPE PERCENTAGE TOTAL

DP

SCREW 7

51 PREFABRICATED 33

DRIVEN CAST IN PLACE 11

NDP BORED 26

49 CFA 23

DISCREPILE FDP FUNDEX OMEGA

WORLD PILE MARKET (Source DFI, 2006)

Remarkable differences countries by countries

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

80

CATEGORY TYPE PERCENTAGE TOTAL

DP

SCREW 7

51 PREFABRICATED 33

DRIVEN CAST IN PLACE 11

NDP BORED 26

49 CFA 23

DISCREPILE FDP FUNDEX OMEGA

WORLD PILE MARKET (Source DFI, 2006)

Increasingly used in European (for instance, Belgium over 60%) and Asian market

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

81

CATEGORY TYPE PERCENTAGE TOTAL

DP

SCREW 7

51 PREFABRICATED 33

DRIVEN CAST IN PLACE 11

NDP BORED 26

49 CFA 23

DISCREPILE FDP FUNDEX OMEGA

vibration and noise free; no soil support; no soil removal no dumping

WORLD PILE MARKET (Source DFI, 2006)

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

82

CATEGORY TYPE PERCENTAGE TOTAL

DP

SCREW 7

51 PREFABRICATED 33

DRIVEN CAST IN PLACE 11

NDP BORED 26

49 CFA 23

DISCREPILE FDP FUNDEX OMEGA

MORE ENVIRONMENTALLY-FRIENDLY

WORLD PILE MARKET (Source DFI, 2006)

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

83

CATEGORY TYPE PERCENTAGE TOTAL

DP

SCREW 7

51 PREFABRICATED 33

DRIVEN CAST IN PLACE 11

NDP BORED 26

49 CFA 23

DISCREPILE FDP FUNDEX OMEGA

WORLD PILE MARKET (Source DFI, 2006)

Lehane B. (2005): “It is only a matter of time before they will dominate the market of medium scale bored piles”

Particle Flow Code 3D v. 3.00

Itasca

Valentino F (2014). Analysis of installation and loading process for displacement piles by Discrete Element Model Ph.D. Thesis, Seconda Università degli Studi di Napoli.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

84

FDP - RESEARCH IN ITALY

Reseaarch Agreement between: - SUN (Second University of Naples) - ICOTEKNE S.p.A. (Piling Contractor) - BAUER – ITALIA (Piling Equipment)

BAUER FDP JACKED

Compaction

Stabilisation

Compaction

Perforation

Jacked and Screw piles L = 8,45 m; D = 0,60 m Horizontal stress changes at the end of insertion h,INS/h0

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

85

FDP - RESEARCH IN ITALY

Jacked pile L = 8,45 m; D = 0,60 m Horizontal stress changes: - at the end of insertion (INS) - after removal of jacking load, i.e. End Of Construction (EOC) - after loading (L) at w = 10%D

loose medium dense

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

86

FDP - RESEARCH IN ITALY

Lesson learned from experiments and theoretical studies about D-pile (jacked). On the overall: in medium to dense sand, the soil changes occurred during

the construction envisage the amount of available skin friction during subsequent loading.

loose medium dense

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

87

FDP - RESEARCH IN ITALY

Lesson learned from experiments and theoretical studies about D-pile (jacked). On the overall, in loose sand, the increase of h during the pile insertion over

most of the pile length ......

loose medium dense

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

88

FDP - RESEARCH IN ITALY

Lesson learned from experiments and theoretical studies about D-pile (jacked). On the overall, ...... then reduces to values smaller than geostatic ......

loose medium dense

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

89

FDP - RESEARCH IN ITALY

Lesson learned from experiments and theoretical studies about D-pile (jacked). On the overall, ...... and partially recovered during loading stage, often

resulting in values which are close to geostatic (no significant advantages vs ND-pile in terms of shaft capacity)

loose medium dense

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

90

FDP - RESEARCH IN ITALY

Installation energy for jacked and screw piles

vA

TvFE

b

(Van Impe 1994)

Jacked ( = 0):

Screw FDP:

vA

TvF

vA

TvFE

bb

bb A

F

vA

vFE

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

91

FDP - RESEARCH IN ITALY

Specific Installation Energy (E/Qlim)

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

0.40 0.41 0.42 0.43 0.44 0.45 0.46

E /

Qlim

(kN

m/m

3/

kN)

n (-)

Infisso

FDP

For looser sandy soils (n), jacked piles are less effective (E/Qlim )

porosity, n (-)

jacked

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

92

FDP - RESEARCH IN ITALY

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

0.40 0.41 0.42 0.43 0.44 0.45 0.46

E /

Qlim

(kN

m/m

3/

kN)

n (-)

Infisso

FDP

jacked

screw FDP

porosity, n (-)

For looser sandy soils (n), jacked piles are less effective (E/Qlim ) The contrary is true for screw FDP (E/Qlim)

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

93

FDP - RESEARCH IN ITALY

Specific Installation Energy (E/Qlim)

Theoretical studies like those here presented can greatly help piling industry in conceiving more convenient installation procedure and design methods (i.e., CFA piles) as well as more productive piling equipment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

94

REMARKS

Theoretical studies like those here presented can greatly help piling industry in conceiving more convenient installation procedure and design methods (i.e., CFA piles) as well as more productive piling equipment. Moreover, different shape and size of perforation tools can be “explored” in advance instead of relying on trial and error site procedure often managed by site engineers (and not specialists) to solve a specific problem on a specific type (not exportable experience).

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

95

REMARKS

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

96

CONCLUDING REMARKS #1

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

97

CONCLUDING REMARKS #1

Scientific approaches to pile design have advanced enormously in recent decades.

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

98

CONCLUDING REMARKS #1

Scientific approaches to pile design have advanced enormously in recent decades. Significant improvements have been made in identifying the mechanisms developing at soil-pile interface either during the installation or during loading, allowing for selection of the pile also on the basis of specific energy consumption economic, environmentally-friendly.

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

99

CONCLUDING REMARKS #1

Scientific approaches to pile design have advanced enormously in recent decades. Significant improvements have been made in identifying the mechanisms developing at soil-pile interface either during the installation or during loading, allowing for selection of the pile also on the basis of specific energy consumption economic, environmentally-friendly. Design of piled foundation based on stiffness consideration is more reliable because much less affected by technological and site-construction aspects.

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

100

CONCLUDING REMARKS #2

When favorable circumstances occur, the number of piles needed to guarantee satisfactory response of the overall foundation system significantly reduces (piled raft concept) economic.

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

101

CONCLUDING REMARKS #2

When favorable circumstances occur, the number of piles needed to guarantee satisfactory response of the overall foundation system significantly reduces (piled raft concept) economic. Less piles, strategically located beneath raft (3070% less) even more economic and environmentally-friendly design.

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

102

CONCLUDING REMARKS #2

When favorable circumstances occur, the number of piles needed to guarantee satisfactory response of the overall foundation system significantly reduces (piled raft concept) economic. Less piles, strategically located beneath raft (3070% less) even more economic and environmentally-friendly design. If properly selected, piles can ensure high specific capacities (pile resistance/pile weight); a trend is observed where displacement (screw) piles are gaining market due to high specific capacities and low impact on environment.

Sustainable development consists of balancing local and global efforts to meet basic human needs (social, economic) without destroying or degrading the natural environment.

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

103

CONCLUDING REMARKS #3

Piles can also play an “active” role in reducing seismic demand or producing energy satisfy needs social, economic, environment.

EN

ER

GY

PR

OD

UC

ER

S

SE

ISM

IC D

EM

AN

D R

ED

UC

ER

S

New Hospital in Monselice, Italy

Full Displacement Screw Piles conceived as a part of piled raft in a seismic area

and equipped with geothermal pipes

FOR A BETTER AND SUSTANAIBLE

FUTURE

JOINING NOVELTIES

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

104

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

105

Despite adverse comments by some of the Pioneers in Soil Mechanics (and despite attitude of Civil Engineers to not modify their daily practice), there is a significant role for scientific methods in pile design.

(Randolph, 2003) (Mandolini, now)

CONCLUDING REMARKS #4

Santa Cruz, Bolivia, May 2015 Alessandro Mandolini – Sustainable Piling Engineering

106

Despite adverse comments by some of the Pioneers in Soil Mechanics (and despite attitude of Civil Engineers to not modify their daily practice), there is a significant role for scientific methods in pile design.

(Randolph, 2003) (Mandolini, now)

CONCLUDING REMARKS #4

MORE “PURE” APPLIED SCIENCE

MORE SUSTANAIBILITY

Prof. Ing. Alessandro Mandolini, Ph.D.

SUSTANAIBLE PILING ENGINEERING