Infrastructure Economics and Finance
date post
04-Apr-2018Category
Documents
view
217download
0
Embed Size (px)
Transcript of Infrastructure Economics and Finance
7/29/2019 Infrastructure Economics and Finance
1/36
Infrastructure Planning and
ManagementInfrastructure Economics and Finance
7/29/2019 Infrastructure Economics and Finance
2/36
Agenda
Principles of Finance Infrastructure Economics
Developing Financial Models forInfrastructure
Introduction to Project Finance
7/29/2019 Infrastructure Economics and Finance
3/36
Present Value
Present value is the value today of moneytomorrow. It is denoted by the formula below,where C is the future cash flow, r is the discountrate and n is the number of years in the future
when this cash flow will present itself
PV = C / (1+r)n
Selecting the discount rate is often a difficult taskand is determined by the riskiness of theinvestment
7/29/2019 Infrastructure Economics and Finance
4/36
Net Present Value
NPV = PV Required Investment
NPV = C0 + Cn/(1+r)n
Cash Outflow is negative
Cash Inflow is positive
7/29/2019 Infrastructure Economics and Finance
5/36
IRR, Risk and Opportunity Cost IRR is the Internal Rate of Return
The rate of return where the NPV is zero
The rate of return on an investment What is the risk free rate?
Typically it is the bank interest rate
Why cant I use the risk free rate always todiscount cash flows? The risk facing your project might be larger. You may
be supporting an infeasible project
So how do I decide what r to use? r represents the risk in the venture not the risk of
the venture Use the same r you use for a venture of comparable
risk use the Opportunity Cost of Capital
7/29/2019 Infrastructure Economics and Finance
6/36
Discounted Cash Flows
NPV = Ct / (1+r)t The time period t for which the NPV is zero is
often called the break-even point
The rates of return can vary over different timeperiods. If this is so, the above formula shouldbe broken down into a sequential stream of cashflows.
Generally you should invest in a project whenthe NPV is positive or the IRR is greater than theopportunity cost of capital.
7/29/2019 Infrastructure Economics and Finance
7/36
Perpetuities
What are they?Cash-flows over an infinite time period
What equation governs static perpetuity?PV = C/r
What equation governs growingperpetuities?
PV = C / (r-g), where g is the rate of growth
7/29/2019 Infrastructure Economics and Finance
8/36
Annuities
What are they?Cash-flows for a certain period of time
Whats the present value of an annuity?
PV = C [ 1/r 1/r(1+r)t ]
7/29/2019 Infrastructure Economics and Finance
9/36
Funding
2 major componentsDebt
Equity
Weighted Average Cost of Capital
WACC = Kd (D/D+E) + Ke (E/D+E)
D and E are the relative proportion of Debtand Equity respectively
7/29/2019 Infrastructure Economics and Finance
10/36
Infrastructure Economics
The concepts in the previous slides areoften used to evaluate the viability of aninfrastructure project or to compare
infrastructure alternatives. This analysis is a key part of the project
preparation and analysis process
7/29/2019 Infrastructure Economics and Finance
11/36
Problem 1 Adapted fromInfrastructure Planning Handbook2007
An agency obtains Rs, 2,00,00,000 in order to constructa project by borrowing five equal beginning-of-yearamounts. The project is then operated for 20 years. Atthe end of the first year of operation, the project iscredited with Rs, 50,00,000 of revenues and therevenues increase by Rs. 1,00,000 per year for eachyear of operation. Estimate the present worth of therevenues and costs, and the average net revenues (withthe effect of interest) over the twenty-five years ofconstruction and operation. Take 7 percent interest intoaccount for all calculations
7/29/2019 Infrastructure Economics and Finance
12/36
Assumptions
Costs are incurred at the beginning of theyear while revenues are realized at theend of the year
Standard NPV formula is used to discountcash flows
NPV = Ct / (1+r)t
7/29/2019 Infrastructure Economics and Finance
13/36
580000014
570000013
560000012
550000011
540000010
53000009
52000008
51000007
50000006
040000005
040000004
040000003
040000002
040000001
RevenuesCostsYear
7/29/2019 Infrastructure Economics and Finance
14/36
Rs.25,744,372.53Net Revenues
Rs. 43,293,217.56Rs. 17,548,845.03NPV
690000025
680000024
670000023
660000022
650000021
640000020
630000019
620000018
610000017
600000016
590000015
7/29/2019 Infrastructure Economics and Finance
15/36
Problem 2 Adapted fromInfrastructure Planning Handbook2007
1. A new pipeline is to be installed. Alternativesizes considered are 8, 12 and 16 diameter.For 8, the construction cost is Rs. 20,000 and
the annual OMR including pumping cost is Rs.5,000. For 12 the costs are Rs. 25,000 and Rs.800 respectively and for 6 they are Rs. 40,000and Rs. 200. What is the most economic size ofpipeline if it is needed for 10 years and there isno salvage value at the end of that time? Theapplicable discount rate is 10%.
7/29/2019 Infrastructure Economics and Finance
16/36
O tion 2 is the best o tion
Rs.41,228.91
Rs.29,915.65
Rs.50,722.84Total NPV
Rs.1,228.9140000$4,915.6525000
Rs.30,722.8420000NPV
11
200800500010
20080050009
20080050008
20080050007
20080050006
20080050005
20080050004
20080050003
20080050002
20040000800250005000200001
VariableFixedVariableFixedVariableFixed
Option 3 - 16"Option 2 - 12"Option 1 - 8"Year
7/29/2019 Infrastructure Economics and Finance
17/36
Problem 3 Adapted from
Infrastructure Planning Handbook2007 Projects A and B are to be compared in terms of the
present worth of their net benefits. Project A requiresone year for construction and costs Rs. 1,00,000. Itinvolves an annual O&M cost of Rs. 10,000 per year of
operation and provides benefits for five years afterconstruction. These benefits start from Rs. 20,000 andincrease by Rs. 20,000 annually. Project B requires twoyears for construction and costs Rs. 2,00,000. It involvesan annual O&M cost of Rs. 20,000 per year of operation
and provides benefits for ten years after construction.These benefits start from Rs. 40,000 and increase byRs. 20,000 annually, capping out at Rs. 2,00,000. Allamounts are end-of-year values. Which project is better?
Assume a discount rate of 10%
7/29/2019 Infrastructure Economics and Finance
18/36
Rs. 300,006.05 Better ProjectRs. 68,312.64Overall NPV
Rs.
575,122.86
Rs.
101,563.09
Rs.
173,553.72
Rs.
193,683.42
Rs.
34,461.70
Rs.
90,909.09NPV
2000002000012
20000020000111800002000010
160000200009
140000200008
120000200007
10000020000100000100006
800002000080000100005
600002000060000100004
400002000040000100003
0010000020000100002
00100000001000001
RevenuesOMR CostConst CostRevenuesOMR CostConstCost
Project BProject AYear
7/29/2019 Infrastructure Economics and Finance
19/36
Problem 4 Adapted from
Infrastructure Planning Handbook2007 A municipal agency is considering building an exhibition
hall. Its feasibility will depend on whether the averagecost per visitor is reasonable. Investment cost includinginterest during construction is Rs 5,00,00,000;
repayment is done by 5 percent bonds over a 20 yearoperating period. Annual OMR is Rs. 2,50,000. Annualvisitors are projected to be 500,000 the first year andincreasing by 50,000 per year. Perform an analysis todetermine the annual cost of the facility for each year
over a twenty-year period of operation, the unadjustedcost per visitor for each year, and the levelized cost pervisitor over the operating period based on a discount rateof 5 percent
7/29/2019 Infrastructure Economics and Finance
20/36
$53,115,552.68($3,115,552.59)($50,000,000.00)NPV6903982.152.941,450,000-250000($4,012,129.36)20
6665913.83.041,400,000-250000($4,012,129.36)19
6427845.453.161,350,000-250000($4,012,129.36)18
6189777.13.281,300,000-250000($4,012,129.36)17
5951708.753.411,250,000-250000($4,012,129.36)165713640.43.551,200,000-250000($4,012,129.36)15
5475572.053.711,150,000-250000($4,012,129.36)14
5237503.73.871,100,000-250000($4,012,129.36)13
4999435.354.061,050,000-250000($4,012,129.36)12
47613674.261,000,000-250000($4,012,129.36)114523298.654.49950,000-250000($4,012,129.36)10
4285230.34.74900,000-250000($4,012,129.36)9
4047161.955.01850,000-250000($4,012,129.36)8
3809093.65.33800,000-250000($4,012,129.36)7
3571025.255.68750,000-250000($4,012,129.36)63332956.96.09700,000-250000($4,012,129.36)5
3094888.556.56650,000-250000($4,012,129.36)4
2856820.27.10600,000-250000($4,012,129.36)3
2618751.857.75550,000-250000($4,012,129.36)2
2380683.58.52500,000-250000($4,012,129.36)1
Levelized Cost Per
YearCost Per Visitor per yearAnnual VisitorsOMRConst CostYear
7/29/2019 Infrastructure Economics and Finance
21/36
Methodology
Rs 5,00,00,000 is paid back over 20 years a