Industrial Training Report (Construction Sector)

download Industrial Training Report (Construction Sector)

of 26

Transcript of Industrial Training Report (Construction Sector)

  • 7/26/2019 Industrial Training Report (Construction Sector)

    1/26

    INDUSTRIAL TRAINING REPORT II

    TRAINING ORGANIZATION : SANKEN CONSTRUCTION (PVT) LTD

    PERIOD OF TRAINING : FROM : 26/10/2015 TO : 03/01/2016

    FIELD OF SPECIALIZATION : CIVILENGINEERING

    H.M.HASAN

    E/11/146

  • 7/26/2019 Industrial Training Report (Construction Sector)

    2/26i

    ACKNOWLEDGEMENTS

    I would like to convey my gratitude to the Industrial Training and Career Guidance Unit (ITCGU),

    Faculty of Engineering, University of Peradeniya, National Apprentice and Industrial Training Authority

    (NAITA) and the Sanken Construction (Pvt) Ltd for providing me the opportunity to have industrial

    training experience in my field of study.I am pleased to be trained in Sanken Construction (Pvt) Ltd one of the largest functioning body

    construction sector in Sri Lanka. My thanks go to the Project Manager Engineer Mr Nalin Senadeera for

    being the greatest support and guidance during the period of my industrial training. I must also thank

    Technical officer, Mr Kalpana and Engineer Mr Sampath and Assistant Engineering Mr Piyarathna for

    their effort in the fields to guide me towards the proper technical experience.

    Finally I would like to add all the technical officers and staff who helped me immensely to make my

    training a success.

  • 7/26/2019 Industrial Training Report (Construction Sector)

    3/26ii

    CONTENTS

    Acknowledgements i

    Contents ii

    List of Figures iii

    List of Tables iv

    List of Abbreviations v

    Chapter 1: INTRODUCTION 1

    1.1 A Brief Account About the Training 1

    1.2 A Description About The Establishment 1

    1.3 Account On The Project 3

    Chapter 2: RESOURCES OF THE CONTRACTOR 4

    2.1 Concrete Mixing plant (Batch plant) 4

    2.2 Workshop 5

    2.3 Laboratory 5

    2.4 Machinery 6

    2.5 Human Resources 9

    Chapter 3: CONSTRUCTION 10

    3.1 Introduction 10

    3.2 Construction of columns 11

    3.3Construction of beams and slab 12

    3.4 Brick work 14

    3.5 Plastering 15

    3.6 Puttying 15

    3.7 Painting 16

    3.8 Tile Installation 16

    Chapter 4: WASTEWATER TREATMENT 17

    4.1 Soakage pit 17

    4.2 Seepage Bed 18

    Chapter 5: PROBLEMS ENCOUNTERED 19

    Chapter 6: CONCLUSION 20

  • 7/26/2019 Industrial Training Report (Construction Sector)

    4/26iii

    LIST OF FIGURES

    Figure 1.1 Organizational structure 2

    Figure 2.1 Concrete Mixing plant (Batch plant) 4

    Figure 2.2 Concrete Cube Testing Machine and Test cubes 5

    Figure 2.3 Truck Mixer 6

    Figure 2.4 Backhoe loader 6

    Figure 2.5 Excavator 7

    Figure 2.6 Jumping Jack compactor and Walk-behind roller 7

    Figure 2.7 Electric drill 7

    Figure 2.8 Circular power saw 8

    Figure 2.9 Bar cutter 8

    Figure 2.10 Sander 8

    Figure 2.11 Water bowser 9

    Figure 3.1 Lap length & Crank length of a column 11

    Figure 3.2 Formwork of beams and slab 12

    Figure 3.3 Reinforcement for beams and slab 12

    Figure 3.4 Concreting beams and slab 13

    Figure 3.5 Setting out for brick work 14

    Figure 3.6 Construction of brick walls 14

    Figure 3.7 Plastering 14Figure 3.8 Puttying 15

    Figure 3.9 Tile Installation 16

    Figure 4.1 Soakage pit construction 17

    Figure 4.2 Seepage Bed Dimensions 18

    Figure 4.3 Perforated Distributer Pipes and its Layout dimensions 18

    Figure 5.1 Heavy Rainy day in the site 19

  • 7/26/2019 Industrial Training Report (Construction Sector)

    5/26iv

    LIST OF TABLES

    Table 3.1 Sticking time of formwork 13

  • 7/26/2019 Industrial Training Report (Construction Sector)

    6/26v

    LIST OF ABRIVIATION

    Abbreviation Description

    ITCGU Industrial Training and Career Guidance Unit

    NAITA National Apprentice and Industrial Training Authority

    SKPA Relocation of Thangalle prison to Eraminiyaya Angunakolapalassa (SKPA) Project

  • 7/26/2019 Industrial Training Report (Construction Sector)

    7/261

    Chapter 1: INTRODUCTION

    1.1A Brief Account about the Training

    This report holds detailed aspects of the industrial training I obtained in the Sanken Construction (Pvt)

    Ltd for a period of 10 weeks commencing from 26thof October 2015 to 3rdof January 2016 through the

    National Apprentice and Industrial Training Authority (NAITA) and the Industrial Training and Career

    Guidance Unit (ITCGU), Faculty of Engineering, University of Peradeniya as a six credit and non-GPA

    course followed in the Department of Civil Engineering, University of Peradeniya.

    1.2A Description about the Establishment

    Sanken Construction is an ICTAD C1 Graded (Highest Rank) company, with ISO 9001:2008 QMS

    Certification.2013 : Sanken Construction certified with OHSAS 18001:2007 Certification.2014 : Sanken

    Construction is in process to obtain ISO 14001:2004- EMS Certification

    The functions performed by the Sanken Construction (Pvt) Ltd consist mainly on Construction

    Contracts, Property development, Ready-mix concrete, Hiring of Scaffoldings, Design & Build,

    Consultancy, Hiring & leasing of machinery, Trading of Products & Materials, Piling, Skill training &

    Management.

    1.2.1 Vision

    Tobe Sri Lankas premier construction service provider

    1.2.2 Mission

    To provide a quality professional service exceeding customer expectations by the effective utilization of

    all resources, with the best practice of the industry

  • 7/26/2019 Industrial Training Report (Construction Sector)

    8/262

    1.2.3 Organizational Structure

    Project Manager

    Seinear Q.S

    Q.S Main Bill

    Q.S Extra Work

    Asst. Q.SPlaning Manager

    Q/A Manager

    M and E/SaftyManager

    Site Manager

    Drawing Incharge Draftmens

    Engineer RebarIncharge

    T.O

    Engineer inLandscape,Water

    Proofing

    T.O

    Engineer Zone 1Incharge

    Asst. EngineerBuilding Incharge

    T.O

    Engineer Zone 2Incharge

    Asst. EngineerBuilding Incharge

    Trainee BuildingIncharge

    Engineer Zone 3Incharge

    Asst. EngineerBuilding Incharge

    T.O BuildingIncharge

    Engineer DetailingIncharge

    Engineer Finishing

    Incharge

    T.Os

    Asst. Engineer

    AdministrativeOfficer

    Store keepers

    Timekeeper

    ConcreteSupervisor

    Safty Officer

    M & E Engineer

    Figure 1.1 Organizational structure

  • 7/26/2019 Industrial Training Report (Construction Sector)

    9/263

    1.3Account on the Project

    Name : Relocation of Thangalle prison to Eraminiyaya

    Angunakolapalassa (SKPA) Project

    Location : Eraminiyaya Angunakolapalassa

    Area of the project : 58 acres

    Amount of the project :Rs.4996 million

    Client :Democratic Socialist Republic Of Sri Lanka Ministry of

    Rehabilitation and Prison Reforms

    Contractor : Sanken Construction (Pvt) Ltd

    Consultant : Central Engineering Consultancy Bureau.

    Date of commencement : 26thof November 2013

    Duration : 22 months

    After completion of this project all inmates in Thangalle remand prison and about 1000 inmates presently

    detain in Welikada prison will be shifted to the new prison where approximately 2000 detainees can be

    conveniently detain. This new prison consists with prison hospital, vocational training center, separate

    building for industries, 140 quarters for officers, and quarters for single officers. Moreover it consists of

    a playground with 400m track, swimming pool with the length of 25m, indoor stadium and trade complex

    to sell prison productions.

  • 7/26/2019 Industrial Training Report (Construction Sector)

    10/264

    Chapter 2: RESOURCES OF THE CONTRACTOR

    In order to foster and promote development of the construction works in the project the contractor shall

    have a collection of adequate resources. As a multinational company, Sanken Construction (Pvt) Ltd

    also has a set of modern utensils such as:

    Concrete Mixing plant

    Workshop

    Laboratory

    Machinery

    Human resources

    2.1Concrete Mixing plant (Batch plant)

    The material such as cement, water, fine aggregate (sand) and coarse aggregate mixed for the preparation

    of ready-mix concrete in the concrete mixing plant and it is in the worksite for easy accessibility.Ready

    mix concrete is used almost every concreting. Concrete is mixed at batch plant and then transported to

    site by truck mixers with rotating drum.

    Figure 2.1 Concrete Mixing plant (Batch plant)

  • 7/26/2019 Industrial Training Report (Construction Sector)

    11/265

    Advantages of ready mix concrete,

    Labour associated with mixing concrete is saved.

    Reduction in the wastage of basic materials.

    Noise and dust pollution created at site is reduced.

    Ready mix concrete has better quality.

    2.2Workshop

    All the maintenance work of the machines used for the construction is done in the workshop allocated

    to the contractor. This is situated closer to the project offices in order to serve the project efficiently.

    2.3Laboratory

    All the tests needed to be done to ensure a standard of work is conducted in the laboratory. This location

    established in the site closer to the project office.Mostly 28 & 7 days concrete cube test done for the concrete strength measurements, Slump test

    done before put to the formwork in the site.

    Figure 2.2 Concrete Cube Testing Machine and Test cubes

  • 7/26/2019 Industrial Training Report (Construction Sector)

    12/266

    Fig. 2.3. Truck Mixer

    Fig. 2.4 Backhoe loader

    2.4Machinery

    The machinery needed to serve the project will be discussed in this section.

    2.4.1 Truck Mixer

    Ready-mix concrete transported by truck Mixer. Almost every time Ready-mix concrete used for the

    concreting works.

    2.4.2 Backhoe loaderBackhoe is used for site clearances, light transportation of material, provide shifted materials for

    construction work in upper levels and excavation perposes, etc.

  • 7/26/2019 Industrial Training Report (Construction Sector)

    13/267

    Fig. 2.5 Excavator

    Fig. 2.9 Electric drill

    2.4.3 Excavator

    Excavator used to the excavate earth up to the required level.

    2.4.4 Compactors

    The jumping jack compactors and Walk-behind rollers are used for compacting perposes in the site.

    2.4.5. Electric drill

    Electric drill contains of removable bit from which drilling can be done. This is used for drill wood,

    concrete etc. Bits changed according to the purpose.

    Fig. 2.6 Jumping Jack compactor and Walk-behind roller

  • 7/26/2019 Industrial Training Report (Construction Sector)

    14/268

    Fig. 2.8 Circular power saw

    Fig. 2.9 Bar cutter

    Fig. 2.10 Sander

    2.4.6 Circular power saw

    Power saw is an electric machine that is used for cutting wood. It consists of a rotating serrated circular

    blade. This is used to cut formworks and adjust door window slashes etc.

    2.4.7 Bar cutter

    Bar cutter is also an electric machine from which steel bars can be cut efficiently.

    2.4.8 Sander

    Wooden surfaces are grinded using sander. This also is an electric machine

  • 7/26/2019 Industrial Training Report (Construction Sector)

    15/269

    Fig. 2.11 Water bowser

    2.4.9 Water Bowser Water is supplied for the site for construction and day today use by bowsers and

    separately drinking water also supplied

    2.4.10Poker vibrator

    Poker vibrator is a machine powered by petrol, and consists of a cable with vibrating edge. Vibrating cable is put

    in to green concrete to be compacted it well.

    2.4.11 Dump Trucks

    Vehicles used for transportation of loose material needed for construction

    2.5 Human Resources

    Road construction work is most commonly done by unskilled laborers. Workers can specialize in certain

    types of work. Diligent and responsible workers are usually promoted to supervisory positions; to train

    and supervise other workers.

    The types of workers are distinguished using skill levels.

    General workersThese kinds of workers are necessary to perform general excavation with picks and

    shovels and clean the sides of roads for better working environment.

    Masonry workersFor the building of structures such as culverts, retaining walls, etc.

    Machine operators For a better efficient way of finishing up the project work, skillful machine

    operators are needed with specific talents in operating the machineries used in the construction

    DriversFor transportation purposes, drivers are necessary for a construction project.

    Construction supervisorsSupervision of the construction work is done by supervisors.

    StaffStaff working in the project office for the functioning of the project.

  • 7/26/2019 Industrial Training Report (Construction Sector)

    16/2610

    Chapter 3: CONSTRUCTION

    3.1Introduction

    Initial survey is conducted and according to the design of the buildings and get approved by the consultant.

    After the Site clearance setting out is done. Then following process is followed for the construct a building

    and in every finished work approved by consultant for next level. But the works carried out by deferent

    buildings in parallel.

    Construction Process

    Excavation

    Foundation

    Concrete Structure (Load bearing )

    Columns

    Beams

    Stairs

    Slab

    Brick work (Non load bearing)

    Roofing

    Rough Plumbing

    Wiring

    Plastering

    Flooring Tiling

    Painting

    Finish Plumbing

    Finish Electrical and Lighting

    Modifications

  • 7/26/2019 Industrial Training Report (Construction Sector)

    17/2611

    3.2 Construction of columns

    3.2.1 Setting out for columns

    Setting out for columns was done accurately using theodolite and steel tape to avoid buckle or fail due

    to eccentric loads applied on them. Marking lines was done using marking chord. Columns.

    3.2.2 Laying kickers

    Kickers were laid in to 75 mm thickness. Plywood sheet boxes were used for its formwork. Curing

    kickers was done at least for 7 days.

    3.2.3 Reinforcement for columns

    Overlapping and cranking main bars and tying stirrups into correct spacing were done according to the

    design. Checked whether correct bar type is used, correct spacing were left between stirrups, lap length

    and crank length is corrected and good quality reinforcement is used. Column formwork required 30

    mm covering blocks are attached.

    Lap length (LL) = D2 x 50

    Crank length (CL) = (D1 + D2+ 5) x 10

    3.2.4 Formwork for columns

    Column formwork was fixed to kickers. Formwork done by plywood sheets and their internal surfaces

    are covered with form oil. Sponge sheets were placed in joints of formwork to avoid leakage of grout.

    After fixing jacks and props and placing cover blocks were done. Then verticality of column formwork

    was checked. Checking verticality was done at two edges of each face, to avoid twisting of column.

    3.2.5 Concerting columns

    Existing surface of concrete chipped and wet with grout in order to have strong bond. Concreting was

    done using grade 25 machine-mixed concrete and free fall height of concrete is less than 1200 mm.

    Poker vibrator was used for compact concrete well.

    3.2.6 Striking column formwork & curing

    Column formwork was removed after a day (24 hr) from concreting. Then curing was done for 7 days

    applying moist gunny bags.

    Figure 3.1 Lap length & Crank length of a column

  • 7/26/2019 Industrial Training Report (Construction Sector)

    18/2612

    3.3 Construction of beams and slab

    3.3.1 Setting out for beams & slab

    1000 mm height level of columns was marked on column surfaces. Level instrument was used there.

    Level of beam bottom was marked using that level.

    3.3.2 Formwork of beams and slab

    Beam and column formwork was fixed using plywood sheets, 2 x 2 wooden bars, galvanized iron

    pipes, separates, p-cones and form ties. Props were placed at 600 mm x 600 mm distances to support

    beam and slab formwork. A U-head or T-headwas placed on each prop and then galvanized iron

    pipes or 2 x 2 wooden bars were laid horizontally and tied them. Power saw was used for cutting

    plywood sheets and then fixed side boards for beams and formwork for slab. Verticality of side boards

    and dimensions were checked. Form oil was applied. Form ties, P-cones and separates were placed at

    600 mm distance, after laying reinforcement.

    3.3.3 Reinforcement for beams and slab

    Steel bars for beam reinforcement were bended and tied above the beam formwork. They were placed

    on 2 x 2 wooden bars laid at beam formwork and they were jointed at columns. They were lowered in

    to beam formwork after tying cover blocks. Slab reinforcement was laid on slab formwork.

    Figure 3.2 Formwork of beams and slab

    Figure 3.3 Reinforcement for beams and slab

  • 7/26/2019 Industrial Training Report (Construction Sector)

    19/2613

    Figure 3.4 Concreting beams and slab

    3.3.4 Concreting beams and slab

    After the Levels checking Concreting slab and beams was done using ready mix concrete. Slump test

    and preparing concrete cubes to test compressive strength are done for concrete transferred by each truck

    mixer.

    3.3.5 Striking beam and slab formwork & curing

    The striking time of formwork depends on type of cement, grade of concrete, dimension of the section

    and the temperature of the concrete. Minimum striking time for side formwork of beams, under side

    formwork of slabs according to its span is mentioned in table 2.1. Curing was done for slab and beams

    for 7 days using moist gunny bags and water ponding.

    Table 3.1 Sticking time of formwork

    Type of formwork Striking time

    Side formworks of beams, columns or walls 24 hrs

    Slab formwork up to 4.5 m span 7 days

    Slab formwork above 4.5 m span & under side of beams up to 6 m span 14 days

    Under sides of beams and arches over 6 m and up to 9 m span 21 days

    Cantilever slab and beams 21 days

  • 7/26/2019 Industrial Training Report (Construction Sector)

    20/2614

    3.4 Brick work

    Walls were constructed by burnt clay bricks using 1:5 cement sand mortar. External walls were constructed

    into 225 mm thickness and internal walls into 112.5 mm thickness.

    3.4.1 Setting out for brickwork

    Above figure elaborates how setting out lines should be marked for brickwork. Two offset lines should

    be marked on either sides of brick wall. When the wall plaster is done, correct measurements can be

    taken from those offset lines. 25 mm allowance should be left on both sides of a door or an opening.

    3.4.2 Construction of brick walls

    None load bearing type masonry brick wall is used to build the walls. English bond is used for walls as

    considered to be strongest bond. 1:5, Cement sand is used for bonding mixture. One skilled labour and

    a mason can build more than 800 brick wall in a day (8h) work but due to inconsistency of brick

    dimensions and cement mixtures, water amount they build around 600 to 700 brick wall in a day (8h)and also height of a brick wall constructed is limited to maximum of 1.5m Mortar layers should be 10

    mm in thickness but practically it was higher than that. That causes to over consumption of cement and

    sand for brick work than the designed. Bricks should be wetted with water before use in brick work.

    The blocks should not be wetted before use. Verticality of walls is checked with the plumb bob and

    straight edge.

    Figure 3.5 Setting out for brick work

    Figure 3.6 Construction of brick walls

  • 7/26/2019 Industrial Training Report (Construction Sector)

    21/2615

    3.5Plastering

    Cement to sand 1:5 mixture is used for plastering work. Water appropriately used for proper mixture

    and usability. Plumb bob and spirit level and feather edges are used and got a good finishing. After few

    more days the wall preparation (cleaning) was done

    3.6Puttying

    After the plastering work, 1stcoat puttying done and kept for drying and then second coat of puttying

    done and kept to dry. To puttying stainless steel Trowels and Skimming Spatulas and for get a goodlevel of finishing Feather Edges are used. Then sanding was done by using 180 grit sandpapers for

    further finishing.

    Figure 3.7 Plastering

    Figure 3.8 Puttying

  • 7/26/2019 Industrial Training Report (Construction Sector)

    22/2616

    3.7Painting

    After the puttying Filler coat applied and patch work done. For patch worked areas sanding and

    application of filler coat was done.

    3.8 Tile Installation

    1:5, Cement: sand mixture is used for the tile bedding preparation and appropriate water amount is used

    for workability. After placing the bedding up to given level, kept it for one day and damped the surface

    to reduce suction to avoid debonding the tile mortar and bed.

    Tiles are soaked in clean water more than 30min (to prevent drawing water from cement mortar and get

    debonding).

    Cement water mixed mortar is used as adhesive and placed it ait on the back side of the tile it is fixed by

    using tapping method tile was placed onto uniform position. Then level of tile was checked using spirit

    level and plastic spacers are used to get the proper spacing. Finally grout was spread by using a soft

    trowel and excess grout removed and tile surface was cleaned.

    Figure 3.9 Tile Installation

  • 7/26/2019 Industrial Training Report (Construction Sector)

    23/2617

    Chapter 4: WASTEWATER TREATMENT

    4.1Soakage pit

    In the beginning of soakage pit construction the earth was excavated using backhoe loader up to required

    level and C25 grade concrete laid for screed and formwork and reinforcement work began for base and

    covering blocks are placed then C25 grade ready-mix concrete was placed then 1 ststage and 2ndstage

    reinforcement, covering and formworks and soakage holes (100mm PVC pipes) kept and concreted

    according to the stage. Finally the slab reinforcement and formwork and coverings are placed according

    to drawings and concreted. In every stage the pokering and curing was done.

    Figure 4.1 Soakage pit construction

  • 7/26/2019 Industrial Training Report (Construction Sector)

    24/2618

    4.2Seepage Bed

    Firstly the located place excavated 8000mm below the ground level. Dimensions and geotextile laying

    are shown below and 70mm drop was maintained between longitudinal ends.

    300mm was filed with metal type 20mm-40mm layer was laid. Then six 160mm diameter perforated

    distributer pipes are laid with pipe axis to axix span is 1000mm and 1stand 6thaxis to embackment is

    500mm.

    After that 200mm same rock type placed and the geotextile cover folded to get a 5000mm lap to avoid

    water infiltration from above. On top of this 250mm sandy soil placed then 50mm of normal soil placed

    up to the Ground level.

    6m

    800mm

    Figure 4.2 Seepage Bed Dimensions

    Figure 4.3 Perforated Distributer Pipes and its Layout dimensions

  • 7/26/2019 Industrial Training Report (Construction Sector)

    25/2619

    Chapter 5: PROBLEMS ENCOUNTERED

    Heavy rain delayed most of works.

    Identification of weather pattern early and prepare accurate time schedules will help to perform well but

    project like this its impossible to maintain works like excavation only in dry period because the parallel

    works of different buildings with limited resources in a remote area like Angunakolapalassa. Hence

    building a proper drainage system is the way to overcome this effects by reducing the waiting time to

    drain water.

    Less resources delayed the works.

    This mainly occurs in the finishing stages of most buildings arrived in same period. The inefficient

    management of resources and delays in resource arrival to the site. This can overcome very easily by

    proper and direct communication and make the schedule of buildings arrival of finishing stages are little

    different from buildings to building.

    Figure 5.1

    Heavy Rainy day in the site

  • 7/26/2019 Industrial Training Report (Construction Sector)

    26/26

    Chapter 6: CONCLUSION

    During my training period of 12 weeks I was able to gather a good experience in building construction

    and it helped me to understand what is happening on the site apart from the theoretical aspects. In the

    site, I gained practical, technical knowledge and experience regarding situations of the working site and

    how to overcome the difficulties and also got supervision and communication skills within the site. The

    industrial training is important and valuable experience as an apprentice in the field of Civil Engineering.

    The engineers in the site induced and guided me to go with the process in progress. The management of

    conflicts occurred between staff and labors or in between them, arrangement of facilities to support the

    work proposed, adjustment for the scarce resources and labors, taking decisions depends on the forth

    coming problems and avoidance of unnecessary work to reduce the cost. Not only that, by exposing to

    the field I was being got to know the people from various organizations, and this environment helped

    me to express my interest, intensions and suggestion Finally confident to state that the training I got is

    more than I really expected to get and I hope that the future undergraduates coming for the internship

    will find their training even more beneficial to their future career.