    Haul Road Upgrade Project

    1 | P a g e

    ENTREPRENEURSHIP, COMMERCIALISATION & INNOVATION CENTRE

    TECHCOMM5012

    APPLIED PROJECT MANAGEMENT

    HAUL ROAD UPGRADE PROJECT

    Stephen James McKnight

    26, May 2012

  • 8/12/2019 Individual Project Assignment

    2/109

    Haul Road Upgrade Project

    2 | P a g e

    ENTREPRENEURSHIP, COMMERCIALISATION & INNOVATION CENTRE

    TECHCOMM5012

    HAUL ROAD UPGRADE PROJECT

    CONTENTS

    EXECUTIVE SUMMARY10

    INTEGRATION...11

    SCOPE...12

    TIME..16

    COST..18

    QUALITY20

    RISK22

    HUMAN RESOURCES24

    COMMUNICATIONS.26

    PROCUREMENT.28

    APPENDIX

    Appendix.1 THE MINE MANGEMENT PLAN50

    AFE Authorisation For Expenditure Request, OZ Minerals Business Case Submission

    Thiess Contract Quote & Rates for requested equipment & resources Wet Weather delays business case & supporting evidence presentation

    LEAN SIX SIGMA DMAIC Business case presentation

    Business Improvement Posters & Monthly data progress presentations

    Thiess Road Design & Standards Criteria Document

    REFERENCES

    References....103

  • 8/12/2019 Individual Project Assignment

    3/109

    Haul Road Upgrade Project

    3 | P a g e

    The University of Adelaide - TECHCOMM5021

    Course Lecturer: John Sing

    Major Project:

    HAUL ROAD UPGRADE PROJECT

    Executive Summary

    Up to 10 words description of what the project is.

    Upgrade mine roads to an all-weather haul road system

    Where is the Project Located?

    OZ Minerals, Prominent Hill, South Australia

    Who is the Owner and Sponsor

    The owner is Dave Way (Deputy Operations Manager, OZ Minerals)

    The sponsor is Robert Boyd (Open Pit Manager, OZ Minerals )

    The Key Stakeholders are OZ Minerals & Thiess

    The name of the Project Manager

    Stephen McKnight & also the Expert Road Consultant

    Your picture, vision or dream of the projects outcome

    A total of 20% of all excavators downtime is attributed to wet weather rainfall events and

    subsequent delays. The vision or dream is to minimise this figure by some 25%-50%.

    To put this loss into perspective on average each excavator loses some 370 operating hours per

    year per digger to wet weather events and subsequent delays, which is equivalent to 480,000

    BCMs per excavator per year in lost productivity at $43.00 per BCM, which is some

    $20,000,000.00 multiplied by 5 excavators giving $100,000,000.00 in total potential saving costs

    on notional EBIDTA values (Earnings Before Interest, Taxes and Amortization).

    This project will potentially save $25,000,000.00 up to $50,000,000.00 depending on thesuccessful implementation of the key deliverables outlined in the Project Management Plan.

    Historically, over the last 4 years the Mine has had on average 4 times the predicted annual

    rainfall, which has produced a loss of 920 hours of production per year per digger. These rainfall

    events typically occur during the months of November to April. Therefore, it is critical to complete

    the project before November 2012

    The ultimate target is to achieve a minim of 6000 hours production per year per digger. The Haul

    Road Upgrade Project will go some way to achieving this target (20%) in conjunction with other

    site based initiatives including: a LOM dewatering strategy, blasting increases in pattern size/drill

  • 8/12/2019 Individual Project Assignment

    4/109

    Haul Road Upgrade Project

    4 | P a g e

    bit size and a 10% increase in powder factors and hot seat changes in all production equipment,

    with staggered fly-in-out days for maximum coverage and finally vertical advance heights of

    flitch/bench versus digger movement along wider and deeper benches

    The Phase of the project

    Due to the fluid and nonlinear nature of such a project we have been pushing every phase possible

    at once because of the tight deadline involved, i.e. this project needs to be completed by the next

    significant rain events predicted from November 2012 until April 2013.

    Therefore, the phase progressions are as follows;

    a. Define, identify a problem or opportunity, which has been completed

    b. Measurethe baseline of the process has been implemented and started January 2012

    c. Analyse,identify and validate root causes. A fishbone analysis has been completed,

    problem analysis brainstorming completed, root cause prioritisation implemented, 5W

    root cause analysis completed, root cause validation established by RTS Friction testcarried out on site to find baseline, a Traffic Light Friction Risk model has been

    implemented and various other Project Management Tools have also been implemented,

    which will be outlined in the body of this presentation.

    d. Improve, find and evaluate best improvements. The best solution was to adopt the use

    of a traffic light system for remediation of mine haul roads with some 25 interrelated

    criteria across the 3 lights. However, the primary criteria is outlined below;

    i. Red light = high priority site requiring immediate remediation with associated

    plan and methodology

    ii. Amber Light = less intense remediation but significant nonetheless and finally

    iii. Green Light = a 200mm wearing course needs to be established to make the road

    compliant with the all-weather upgrade specifications

    iv. Red Light requires sub-base of up to 1000mm

    v. Amber Light requires base of 600mm

    vi. Green Light Running surface 200mm

    vii. Crossfall of 2% on in pit and mine haul roads

    viii. Centre camber with 2% crossfall on dump ramps and roads

    ix. Establish significant drainage and run-off sumps

    e. Control, execute and maintain improvement.

    i. Cost

    ii. Schedule

    iii. Process Controliv. SOPS

    v. Training

    vi. Communications

    The project is now in the execution phase

    a. All equipment for the project will be on-site by the end of April 2012

    b. The T8 supervisors from Thiess have been executing the plan with limited equipment,

    resources and material

    c. The project is 38% complete to this date regardless the above constraints

    Who is the client Representative?

  • 8/12/2019 Individual Project Assignment

    5/109

    Haul Road Upgrade Project

    5 | P a g e

    Leidy Alvarado, OZ Minerals Mine Improvement Project Engineer

    Who are the Stakeholders?

    OZ Minerals Senior Management Team

    OZ Minerals Open Cut Management Team

    MIT OZ Minerals Project Team

    Thiess earth moving contractors

    Independent Road Expert Consultant

    Purpose of the Project:

    Site Description

    OZ Minerals operates both an open cut and underground copper/gold mine and

    processing plant at the Prominent Hill Mine site. Prominent Hill is a remote site

    with a FIFO and limited DIDO out workforce supporting the mining, production

    and exploration activities. A permanent accommodation village located 3 kmsfrom the mining operations supports some 1500 workers. Processing of ore

    commenced in February 2009. Ore averaging 1.5% Cu and 0.5g/t Au is processed

    at a nominal rate of 8Mt per annum to produce copper concentrate via both

    Darwin and Port Adelaide by both rail and road

    Site Location and Access

    The mine site is located 650km north-west of Adelaide, South Australia, some

    100km south east of Coober Pedy and 150km north-west of Roxby Downs. The

    site is accessible via an unsealed road off the Stuart Highway 100km south of

    Copper Pedy. Daily charter flights from Adelaide, Melbourne and Port Augusta

    service the FIFO workers

    Site Observations

    The access ramps are generally in poor condition at higher elevations

    recommended by geological element profiles. The majority of access ramps do

    not indicate any crossfall. No drainage or facility for run-off from the haul roads

    seems to be in place, except for water running along the full length of access

    ramps from higher levels to lower levels. This is one of the major causes of

    uncontrolled water runoff during major rainfall events. The majority of access

    ramps are graded and compacted. The use of inappropriate material selection on

    some ramps. There are many cases of wheel rutting on ramp corners due to poor

    material selection. Gradients on most active in-pit ramps are between 8%-10%.

    Waste dump ramps vary from 5%, 8% and 10% depending on dumping criteria andpoor design. Steely Haematite, Andesite and Dolomite are the best material to

    source for the remediation project. Large oversized material has been deposited

    on windrows

    The existing access ramps make up 3.5km of the total 10km mine haul road

    system. The width of ramps are currently 23m being used for 48 haul road trucks,

    CAT 793D. Other equipment on-site is made up of some 5 graders CAT 24H,

    another 6 Dozers D10T and 4 Liebher 996 excavators with numerous other

    ancillary equipment

    Some recommendations based on the observations are;

  • 8/12/2019 Individual Project Assignment

    6/109

    Haul Road Upgrade Project

    6 | P a g e

    Create a dedicated road maintenance project team

    1 x Project Manager

    1 x Project Engineer

    4 x Various Independent Consultants required during execution phase

    and peer review (Expert Road Engineer, Geotechnical Engineer, Friction

    Loss Engineer, Surveyor and Peer Review Engineer)

    2 x Supervisors (T8)

    10 x Operators

    Source appropriate equipment

    1 x Wheel Loader CAT 992D

    2 x Komatsu 785 dump trucks

    1 x Grader CAT24H

    1 x Komatsu 300 Digger (Contract digger to supplement fleet) 1 x CAT 777 Water Truck

    1 x CAT D10 Dozer

    And other ancillary equipment as required; Compactors or Impactors

    Source appropriate material

    Steely Haematite

    Haematite

    Andesite

    Dolomite

    Greywacke

    Granitites Engage a dedicated survey team to control and monitor the daily works

    supervised by the T8 Thiess operator in charge of implementing the traffic light

    system management plan

    Purchase the friction testing unit to verify when roads are safe to be driven on

    after all rain events

    Follow the rain event flow diagram to minimise downtime

    The Objectives:

    Scope

    To address the issue of unsealed roads and the downtime associated with them

    during and after rainfall events. This includes, road surfaces, remediation

    configurations, floodways, cuts, fills, drainage and mine haul road design, the

    identification of unsealed roads and suitable material selection for remediation

    including in-pit material and engineered commercially produced material. This

    remediation program will include the determination of sub base, base and

    wearing course thickness, drainage and erosion protection, environmental

    considerations, performance expectations, including surface condition

    assessment.

    Time

  • 8/12/2019 Individual Project Assignment

    7/109

    Haul Road Upgrade Project

    7 | P a g e

    The estimated scheduler for this project is 12 months starting January 2012 until

    January 2013

    The schedule is broken up into phases which will be elaborated on at a future

    date and location in this document

    Cost

    The estimated cost will be divided between OP EX and CAP EX the expenditure is

    in the vicinity of $1.3M CAP EX and $4M OP EX, giving a total of some $5.3M spend

    OP EX will pay for the machine, operator utilisation and some occasional day

    work nominated activities

    CAP EX will pay for material, Consultants and other yet to be identified costs

    Requirements to be satisfied:

    With the new contract model the Company has accepted the responsibility to upgrade

    the haul roads in the open pit to a standard to assist in decreasing the operational delaysand risk involved in friction loss, with respect to the deterioration of the haul roads,

    evident during wet weather.

    Situation: The mine operates 24/7 365 days per annum. Excavator productivity is now seriously limited

    by the fact that the pit is closed off when it starts raining, and then it takes a long time to

    reopen the pit after the rain. This is because mine operations wait for roads to be dry again,

    to avoid possibility of track slides. Overall wet weather causes circa 370 hours of downtime

    per excavator per annum. The mining contract currently states that the contractor is

    accountable to maintain all-weather roads.

    Complication: The mining contractor is not confident that an all-weather pit is possible at Prominent Hill,claiming that the quality of the material available on site for road-sheeting. The is no clarity

    also on the type of materials to be used, size of materials, current quality of design, use of

    reagents, maintenance practices, etc. The road maintenance practices for managing haul

    roads before, during and after wet weather events are also not clear and codified (e.g.

    scarifying, sheeting, grading, etc.)

    Resolution: OZ Minerals is willing to engage an experienced contractor on road design and maintenance

    to perform a review of the current haul roads. This will include: design, road sampling, wet

    weather performance, dust suppression, material quality & sizes, maintenance practices. The

    scope of the report though should primarily be focused on providing OZ Minerals with a

    recommendation on how to keep the mining operations running as long as possible duringand after wet weather events. To achieve this scope we would engage a contractor that has

    previous experience in such projects and issues, especially in all weather mines or in mines

    in tropical areas.

    The Roles & Responsibilities

    The roles Identified for the project are

    Project Manager (Stephen McKnight)

    Project Engineer ( Leidy Alvarado)

  • 8/12/2019 Individual Project Assignment

    8/109

    Haul Road Upgrade Project

    8 | P a g e

    Road Maintenance Supervisors ( David Kurtzer & Chris Carroll)

    2 x 992 Loader Operator

    2 x 24H Grader Operators

    4 x 785 Truck Operators

    2 x 773 Water Cart Operators

    1 x Ancillary Operator from independent contractor

    The Benefits

    What are we trying to achieve

    To reduce the wet weather delays associated with Excavator utilisation by at

    least 25% representing 370 hours per year for each excavator

    Why we should implement the project

    This 25% reduction in lost excavator hours represents a potential minimum

    $25,000,000.00 EBITA saving to the company annually The value proposition for the sponsor

    At least a 25% EBITA saving per annumrepresenting some $25,000,000.00 saving from a

    capital outlay of $5,3000,000.00

    Constraints and assumptions

    Equipment availability

    It has been identified that there is a lack of suitable and available equipment to

    implement the project

    Material availability

    It has been identified that there is not enough suitable or available appropriate

    material crushed or screened or stockpiled for the project

    Resource availability

    Ramping up to the 16 people required for the continuous implementation of the

    six month execution phase

    Scope, Time & Cost

    Even though the project was identified some 1.5 years ago there was no

    political will to implement the project due to a lack of consistent direction,

    scope, funds and a dedicated champion to drive the project forward.

    The implementation strategy including Critical Success Factors (Targets, KPIs and Tolerances)

    The project requires completion before the next expected rainfall events, which are

    usually expected in November 2012 until April 2013.

    Implementation occurred on the 5/12/2011 when the road expert was engaged inanticipation for the contract change reflecting the haul road upgrade project as a key

    strategy for increased productivity of a potential 20% of total Excavator increased

    utilisation.

    From implementation key actions were identified and progressively introduce; ancillary

    equipment, appropriate material, scientific measurement of friction loss and finally

    execution of appropriate design criteria for successful completion of the projects targets

    mentioned in previous sections of the executive summary.

    Risk and treatment

  • 8/12/2019 Individual Project Assignment

    9/109

    Haul Road Upgrade Project

    9 | P a g e

    The issue of wet weather delays is very complex and there are no one size fits all solutions

    in play. Regardless the fact that there are civil engineering solutions that can and will be

    applied; this site has specific requirements for the appropriate solution and outcomes

    desired

    Lack of basement material or crushed/screened or stockpiled material available when

    required

    Equipment availability from Thiess

    HV & LV, HV & HV interactions during construction/execution phase of project

    Resource availability from Thiess for HV requirements

    Impact of road maintenance team during construction on production team

    Natural disasters

    Wet weather rainfall events

    How phases can facilitate delivery of future phases (particular design or constructability) Once the construction/execution phase of the project is completed there will be an

    emphasis on maintaining the newly constructed roads on a regular basis so that the

    current situation is not revisited during the remaining 6 years of the mines life

    The implementation of a road maintenance team will facilitate the continuous upgrade

    and improvement of the haul road system without the re-introduction of a sustained

    initial haul road upgrade campaign, which is in progress at this time

    From the RA all necessary steps have been implemented to negate and mitigate this

    phase occurring again in the LOM strategy, this phase is a once off action of the project

    leading to a continuous improvement phase

    Work Breakdown Structure Suffice to say that the 5 key areas of the WBS have been defined

    Define the situation

    Implement/Establish the action plan

    Acquire the;

    Resources

    Material

    Equipment

    Execute the action plan

    Close out the project

    The impact of the project on stakeholders

    OZ Minerals will have a significant increase in productivity

    This will provide increases in share value for stakeholders

    The increased productivity will impact the companys bottom line

    This will provide extra capital for future project development

    Thiess will have multiple benefits

    Increased productivity

    Reduced wear & tear on equipment

    Reduced soft tissue issues for operators

    Maintain compliance with the LOM Contract introduced in January 2012

  • 8/12/2019 Individual Project Assignment

    10/109

    Haul Road Upgrade Project

    10 | P a g e

    Milestone and an activity schedule

    5/12/2011 Independent Road Expert engaged to implement project

    5/1/2012 Project needs identified and implemented

    5/2/2012 Execution phase begun with limited; resources, equipment and material

    5/3/2012 Scientific validation of friction loss assessed and measured

    5/4/2012 Resources, Equipment and Material in place and beginning execution phase

    5/5/2012 Execution in full swing, all elements on-site and in play

    5/6/2012 to 5/11/2012 Haul Road Maintenance Plan following PMBOK project cycles until

    conclusion of project in November 2012

    Budget

    $5.3M have been committed to the Haul Road Upgrade Project

    The $5.3M will be divided into CAPEX $1.3M, which includes payment of expert engineers

    and surveyors, material all in 75mm for wearing course, friction testing module, uplift ofequipment and any other costs outside the committed OPEX money

    OPEX is committed at $4M this pays for equipment hire for the six months of the

    execution phase of the project

    There is a further contingency fund available, but to this point a final figure has not been

    negotiated with the OZ Minerals BI and financial Departments, suffice to say a top end

    figure of $1M extra funds could be available if required. However, the current budget is on

    track with no need for a contingency to be anticipated

    The CAPEX is well within budget with only some $350,000.00 committed thus far,

    however the cost of the material (75mm all in) will eat into this fund significantly, some

    $1M over the 6 months The OPEX has an anticipated burn rate of $550,000.00 per month for 6 months coming

    in at $3.3M, leaving a $700,000.00 contingency fund if required

    Are there Enterprise Environmental Factors or Organisational Process Assets which can be used?

    Refer to the body of this document with emphasis on the PMBOK processes

    The Management structure of both OZ Minerals Thiess have been utilised in the initial

    stages of the projects development, until the project produced its own organisational

    chart and resources

    All material has been sourced from the PIT

    All resources and equipment have been sourced from Thiess

    Road design criteria has been sourced from Thiess and previous champions of the project

    Further development of the road design criteria have been introduced from the Expert

    Road Consultant working in concert with both site based knowledge groups and the

    adoption of industry best practise applications to the specific and unique site

    requirements

  • 8/12/2019 Individual Project Assignment

    11/109

    Haul Road Upgrade Project

    11 | P a g e

    PMBOK MANAGEMENT PLAN

    Plans for managing (planning, monitoring & controlling- If Areas not already covered)

    Integration

    Scope

    Time

    Cost

    Quality

    Risk

    Human Resources

    Communications

    Procurement

  • 8/12/2019 Individual Project Assignment

    12/109

    Haul Road Upgrade Project

    12 | P a g e

    INTEGRATION

    Up to 10 words description of what the project is.

    Upgrade mine roads to an all-weather haul road system

    Where is the Project Located?

    OZ Minerals, Prominent Hill, South Australia

    Who is the Owner and Sponsor

    The owner is Dave Way (Deputy Operations Manager, OZ Minerals)

    The sponsor is Robert Boyd (Open Pit Manager, OZ Minerals )

    The Key Stakeholders are OZ Minerals & Thiess

    The name of the Project Manager

    Stephen McKnight & also the Expert Road Consultant

    Your picture, vision or dream of the projects outcome

    A total of 20% of all excavators downtime is attributed to wet weather rainfall events andsubsequent delays. The vision or dream is to minimise this figure by some 25%-50%.

    To put this loss into perspective on average each excavator loses some 370 operating hours per

    year per digger to wet weather events and subsequent delays, which is equivalent to 480,000

    BCMs per excavator per year in lost productivity at $43.00 per BCM, which is some

    $20,000,000.00 multiplied by 5 excavators giving $100,000,000.00 in total potential saving costs

    on notional EBIDTA values (Earnings Before Interest, Taxes and Amortization).

    This project will potentially save $25,000,000.00 up to $50,000,000.00 depending on the

    successful implementation of the key deliverables outlined in the Project Management Plan.

  • 8/12/2019 Individual Project Assignment

    13/109

    Haul Road Upgrade Project

    13 | P a g e

    Historically, over the last 4 years the Mine has had on average 4 times the predicted annual

    rainfall, which has produced a loss of 920 hours of production per year per digger. These rainfall

    events typically occur during the months of November to April. Therefore, it is critical to complete

    the project before November 2012

    The ultimate target is to achieve a minim of 6000 hours production per year per digger. The Haul

    Road Upgrade Project will go some way to achieving this target (20%) in conjunction with other

    site based initiatives including: a LOM dewatering strategy, blasting increases in pattern size/drill

    bit size and a 10% increase in powder factors and hot seat changes in all production equipment,

    with staggered fly-in-out days for maximum coverage and finally vertical advance heights of

    flitch/bench versus digger movement along wider and deeper benches

    Site Description

    OZ Minerals operates both an open cut and underground copper/gold mine and

    processing plant at the Prominent Hill Mine site. Prominent Hill is a remote sitewith a FIFO and limited DIDO out workforce supporting the mining, production

    and exploration activities. A permanent accommodation village located 3 kms

    from the mining operations supports some 1500 workers. Processing of ore

    commenced in February 2009. Ore averaging 1.5% Cu and 0.5g/t Au is processed

    at a nominal rate of 8Mt per annum to produce copper concentrate via both

    Darwin and Port Adelaide by both rail and road

    Site Location and Access

    The mine site is located 650km north-west of Adelaide, South Australia, some

    100km south east of Coober Pedy and 150km north-west of Roxby Downs. The

    site is accessible via an unsealed road off the Stuart Highway 100km south of

    Copper Pedy. Daily charter flights from Adelaide, Melbourne and Port Augusta

    service the FIFO workers

    Site Observations

    The access ramps are generally in poor condition at higher elevations

    recommended by geological element profiles. The majority of access ramps do

    not indicate any crossfall. No drainage or facility for run-off from the haul roads

    seems to be in place, except for water running along the full length of access

    ramps from higher levels to lower levels. This is one of the major causes of

    uncontrolled water runoff during major rainfall events. The majority of access

    ramps are graded and compacted. The use of inappropriate material selection on

    some ramps. There are many cases of wheel rutting on ramp corners due to poormaterial selection. Gradients on most active in-pit ramps are between 8%-10%.

    Waste dump ramps vary from 5%, 8% and 10% depending on dumping criteria and

    poor design. Steely Haematite, Andesite and Dolomite are the best material to

    source for the remediation project. Large oversized material has been deposited

    on windrows

    The existing access ramps make up 3.5km of the total 10km mine haul road

    system. The width of ramps are currently 23m being used for 48 haul road trucks,

    CAT 793D. Other equipment on-site is made up of some 5 graders CAT 24H,

  • 8/12/2019 Individual Project Assignment

    14/109

    Haul Road Upgrade Project

    14 | P a g e

    another 6 Dozers D10T and 4 Liebher 996 excavators with numerous other

    ancillary equipment

    Some recommendations based on the observations are;

    Create a dedicated road maintenance project team

    1 x Project Manager

    1 x Project Engineer

    4 x Various Independent Consultants required during execution phase

    and peer review (Expert Road Engineer, Geotechnical Engineer, Friction

    Loss Engineer, Surveyor and Peer Review Engineer)

    2 x Supervisors (T8)

    10 x Operators

    Source appropriate equipment

    1 x Wheel Loader CAT 992D 2 x Komatsu 785 dump trucks

    1 x Grader CAT24H

    1 x Komatsu 300 Digger (Contract digger to supplement fleet)

    1 x CAT 777 Water Truck

    1 x CAT D10 Dozer

    And other ancillary equipment as required; Compactors or Impactors

    Source appropriate material

    Steely Haematite

    Haematite

    Andesite Dolomite

    Greywacke

    Granitites

    Engage a dedicated survey team to control and monitor the daily works

    supervised by the T8 Thiess operator in charge of implementing the traffic light

    system management plan

    Purchase the friction testing unit to verify when roads are safe to be driven on

    after all rain events

    Follow the rain event flow diagram to minimise downtime

  • 8/12/2019 Individual Project Assignment

    15/109

    Haul Road Upgrade Project

    15 | P a g e

    SCOPE

    To sheet existing haul roads utilising the traffic light system for remediation. This concept has beenpreviously and briefly explained in both the Executive Summary and Project Management Plan. This form

    of remediation identifies 3 different remediation criteria once they are satisfied and competent material is

    placed in-situ to design this will facilitate quicker resumption of heavy vehicle activity after wet weather

    stoppages. Site based crushing/screened material will be utilised to provide the 3 necessary types of

    engineered rock identified in the remediation process. This material will be sourced from in pit basement

    material with properties consistent within optimum design tolerances. This material has been successfully

    utilised on other in pit ramps (SO8, Beach Ramp, parts of the Western Ring Road, Upper Rom and

    Southern Dump access) The new road design has performed better on these areas than on areas yet to

    receive the remediation such as ( NO7 ramp, Northern Dump ramp, NO3 running track and Eastern Ring

    Road.

    In some cases heavy vehicle operations will be able to continue in low level rain events; if the following

    factors have been considered and completed; new material in-situ, correct design parameters installed,

    such as 2% crossfall, sufficient wearing course, drains and drainage construction all under survey control.

    This design veracity will potentially provide in excess of a 25% improvement in digger availability and

    utilisation rates during wet weather events. The EDITA data has been outlined in both the Executive

    Summary and Project Management Plan. This data will also be available in the cost section of this

    document in the PMBOK knowledge area.

    In addition, the road maintenance crew lead by the Thiess T8 Supervisor will focus on the design

    management with an embedded dedicated survey contractor employed expressly for the project. Their

    remit, together is to focus on performance managing the wet weather aspect of the project and its

    mitigation. The focus will change after the initial six month construction period to one of daily maintenance

    as opposed to daily remediation tasks.

    The inclusion of a friction monitoring devise mounted in the T8s vehicle will add some scientific veracity to

    the experience based assessment currently being utilised by site personnel. This issue was highlighted in

    the flow diagram exercise for determining the wet weather delay process assessment matrix. This

    monitoring devise helps to mitigate risk between the differing risk tolerances based on personnel levels of

    experience when determining return to work practises after rain events

    In Scope: Priority and critical causes of wet weather delays: Poor surface material, insufficient road

    maintenance and no crossfall, no drainage.

    Project would be considered successful if 25% of delays have been decreased and Extra BCMs have been

    produced due to this improvement.

    Out of Scope: Other benefits will be achieved simultaneously such as productivity increase, tyres

    conservation, HV and machinery maintenance reduction, decrease of uncontrolled vehicles movements,

    safer work conditions environment and driver comfort.

  • 8/12/2019 Individual Project Assignment

    16/109

    Haul Road Upgrade Project

    16 | P a g e

    SCR ANALYSIS

    SITUATION:

    Some 20% of total excavator downtime is due to wet weather events. On average each excavator

    loses 370 operating hours per year due to wet weather, which is equivalent to 480,000 BCM per

    excavator.

    COMPLICATION:

    To sheet existing haul roads with competent material to enable quicker resumption of heavy

    vehicle activity after wet weather stoppages. In addition to sheeting crossfall and drainage also

    needs to be included in the remediation process to rain water from the newly constructed roads.

    To make this happen there are 3 necessary elements required; Equipment, Material & Resources

    RESOLUTION:

    Equipment has been ordered to create a dedicated ancillary road maintenance team. Appropriate

    material is being stockpiled and crushed and screened as required. The necessary road

    maintenance team has been formed to implement the already established Project Management

    Plan

    STAKEHOLDER COMMENTS

    Stephen McKnight: Project Manager & Expert Road Design Engineer

    After some considerable background analysis of current designs, requisite rock types, equipment

    requirements, resource levels, civil engineered drawings, available material types and rock sizing required;

    the project is now at the stage of committing funds and progressing to execution phase. Engineered

    drawings have been commissioned. Quotes have been sourced for equipment and material. Human

    resourcing levels have been identified and committed to the daily execution of the project. Budgets are

    being evaluated and implemented as required. A comprehensive Project Management Plan has been

    established and communicated to all the key stakeholders. The plan looks at people, culture, training,

    equipment, material and competency based evaluation for driving on remediated haul roads. A traffic light

    remediation system that incorporates the necessary design criteria for the identification of the 3 road

    mediation types is now in place. A friction analysis of the haul roads has been completed by RTS.

    Leidy Alvarado: Project Engineer BI Team

    The new approach to tackle Wet Weather Delays is realistic and achievable. The expected improvement

    will be guaranteed by completing the 3 proposed project generations. (Road remediation, Road

    Maintenance Plan and Rain Management). The project has been re-scoped in order to meet costs, time

    and quality requirements of the project deliverables and the stakeholders. In addition, the new contract

    has facilitated the communication within both parties and has also enhanced the interest and enthusiasm

    of Thiess and Oz projects team by their mutual cooperation. e.g. Quick fixes implemented so far such as

    S08 ramp correlates with new roads design and performance tolerances when rain event occur.

  • 8/12/2019 Individual Project Assignment

    17/109

    Haul Road Upgrade Project

    17 | P a g e

    The Project implementation stage will be managed by Contract Consultant Engineer (Stephen McKnight)

    until completion and it is estimated to be completed within 6 months. It is suggested also to have Road

    Maintenance Supervisors (T8s) in order to work in conjunction with Oz Project Engineer. The Road

    remediation and Maintenance Plan will be incorporated into 36hrs and Weekly Plan to make sure the

    project progress is communicated to all required mine personnel and followed successfully on a daily basis

    incorporated into the production planning cycle.

    Mitigation steps of Risks identified (see tab 2.1 Risk Mgmt.) within the proposed approach such as Lack of

    Equipment and Crushed material have been incorporated into the Implementation Plan.

  • 8/12/2019 Individual Project Assignment

    18/109

    Haul Road Upgrade Project

    18 | P a g e

    TIME

    WORK BREAKDOWN STRUCTURE

    Define the situation

    Implement/Establish the action plan

    Acquire the;

    Resources

    Material

    Equipment

    Execute the action plan

    Close out the project

    PROJECT MILESTONES

    5/12/2011 Independent Road Expert engaged to implement project

    5/1/2012 Project needs identified and implemented

    5/2/2012 Execution phase begun with limited; resources, equipment and material

    5/3/2012 Scientific validation of friction loss assessed and measured

    5/4/2012 Resources, Equipment and Material in place and beginning execution phase

    5/5/2012 Execution in full swing, all elements on-site and in play

    5/6/2012 to 5/11/2012 Haul Road Maintenance Plan following PMBOK project cycles until

    conclusion of project in November 2012

    PROJECT SCHEDULE

    THE 75mm ALL IN SCHEDULE

    OZ MINERALS

    ALL WEATHER HAUL ROAD UPGRADE PROJECT

    MATERIAL CRUSHING/SCREENING SCHEDULE

    MATERIAL SIZE TOTAL TONNAG E TOTAL VOLUME MONTHLY MATERI AL W EEKLY MATERIAL DAILY MATERI AL DES IRED MATERIAL TY PES TRAF FIC LI GHT SYS TEM DEPTHS

    mm t m3 t t t Rock type Colour mm & m

    75mm 146,000 67,000 24333 6083 869 Hae mati te , A nd es it e, Sk ar n, Gr ey wack e or Gr an ito id G REE N 200m m + 2% CR OS SF ALL

    150mm 240,000 109,000 40000 10000 1428 And es it e, Skarn, Grey wa cke, Se dime nt s o r Gra ni to id AMBER & RED u p t o 1. 5m

    300mm 395,000 181,000 65833 16458 2351 Andesite, Skarn, Greywacke, sediments or Granitoid RED up to 2.0m

    TOTALS 781,000 357,000 130166 32541 4648

    These figures are based on a 6 month crushing/screening schedule

    We are assuming a start date of early March 2012 completing August 2012; giving a 2 month buffer bef ore our next "wet weather" window begins from November 2012 to March 2013

  • 8/12/2019 Individual Project Assignment

    19/109

    Haul Road Upgrade Project

    19 | P a g e

    COST

  • 8/12/2019 Individual Project Assignment

    20/109

    Haul Road Upgrade Project

    20 | P a g e

    QUALITY

    Attached are the majority of QAQC documents associated with the project. There are a wide variety ofdocuments included in this section; ranging from the traffic light design criteria, the actual map of the sites

    requiring the traffic light system remediation, correspondence with the world leader in haul road design RJ

    Thompson on negative superelevation design, a working haul road assessment document, a flow diagram

    on how to mitigate delays in returning to work after wet weather rain events, etc. This section does not go

    into the true depth of detail associated with the issues of maintaining quality, but gives a representation of

    the thought and knowledge being implied to make the haul road design as robust and relevant to the site.

    During the course of this project a number of specific haul road design documents, white papers and books

    have been consulted, which can be found in the reference section of this presentation. Suffice to say

    quality on this project was identified as one of the most contingent aspects of the projects potential for

    success, hence the amount of effort applied to achieve the quality required

    THE ALL-WEATHER HAUL ROAD UPGRADE PROJECT (AWHRUP)

    TRAFFIC LIGHT SYSTEM

    OZ MINERALS PROMINENT HILL JANUARY

    2012

    DESIGN CRITERIA GREEN AMBER RED

    1. Road Design Types Design #1 Design #2 Design #3

    200mm wearing

    course

    200mm wearing

    course

    200mm wearing

    course

    passing @ 75mm passing 75mm passing 75mm

    400mm Base 600mm Base

    passing 150mm passing 150mm

    500m Sub Base 1000mm Sub Base

    passing 300mm passing 300mm

    2. Rock Type Steely Haematite Granitoids Mudstone

    Greywacke Andesite Silcrete

    Skarn Bulldog Shales

    Sedimentary Hornfels Fresh

    Weathered3.MPa (UCS) >81 >47 80 >60 80% >50%

  • 8/12/2019 Individual Project Assignment

    21/109

    Haul Road Upgrade Project

    21 | P a g e

    10. Definition Green Amber RED

    Road Condition Road Condition Road Condition

    VERY GOOD FAIR BAD

    DAILY INSPECTION WORK REQUIRED IMMEDIATE WORK

    DAILY INSPECTION REQUIRED

    DAILY INSPECTION

    11. Crossfall 2% 3% 4%

    12. Crown 2% 3% 4%

    13. Drainage .5m .3m >.3m

    14. Berms 1.8m 1.5m 700Kpa

    20. Water Truck

    Spray 50m on 50m off 50m on 50m off

    21. Dust Block

    Agents Tar/Bitumen Petrol/Polymer Wetting Agents

    22. Road

    Maintenance

    Managed

    Maintenance Scheduled Blading Ad-hoc Blading

  • 8/12/2019 Individual Project Assignment

    22/109

    Haul Road Upgrade Project

    22 | P a g e

    23. Design Approach Integrated Design Empirical Design Just build a Road

    24. Gradients 10% 12.5%

  • 8/12/2019 Individual Project Assignment

    23/109

    Haul Road Upgrade Project

    23 | P a g e

  • 8/12/2019 Individual Project Assignment

    24/109

    Haul Road Upgrade Project

    24 | P a g e

  • 8/12/2019 Individual Project Assignment

    25/109

    Haul Road Upgrade Project

    25 | P a g e

  • 8/12/2019 Individual Project Assignment

    26/109

    Haul Road Upgrade Project

    26 | P a g e

  • 8/12/2019 Individual Project Assignment

    27/109

    Haul Road Upgrade Project

    27 | P a g e

  • 8/12/2019 Individual Project Assignment

    28/109

    Haul Road Upgrade Project

    28 | P a g e

  • 8/12/2019 Individual Project Assignment

    29/109

    Haul Road Upgrade Project

    29 | P a g e

  • 8/12/2019 Individual Project Assignment

    30/109

    Haul Road Upgrade Project

    30 | P a g e

  • 8/12/2019 Individual Project Assignment

    31/109

    Haul Road Upgrade Project

    31 | P a g e

  • 8/12/2019 Individual Project Assignment

    32/109

    Haul Road Upgrade Project

    32 | P a g e

    Correspondence with Roger J Thompson regarding the issue of introducing negative superelevation to the

    road design and QC of the project in relation to crossfall of the in pit haul road design. This situation came

    about due to the road design standards Thiess have in their coal operations and as such is in their working

    haul road design document, which needed to be addressed so the appropriate run off design could be

    implemented in this site specific circumstance.

    Excellent Steve, an educational read too. Thank you Rob

    From:Stephen McKnight

    Sent:Wednesday, 4 January 2012 3:41 PM

    To:Robert Boyd; Jarrad Dodson; Richard Turnbull; Leidy Alvarado

    Cc:David Way

    Subject:FW: HAUL ROAD DESIGN

    FYI Gents

    Steve McKnightContract Mining Engineer Mine Improvement Team

    OZ Prominent Hill | Respect Integrity Action Results Ground Floor, 170 Greenhill Road

    Parkside, South Australia, 5063, Australia

    T61 8 8672 8148F 61 8 86728101M 04 350 29 [email protected]

    Please consider the environment before printing this e-mail

    From:Roger Thompson[mailto:[email protected]]

    Sent:Wednesday, 4 January 2012 3:02 PM

    To:Stephen McKnight

    Subject:RE: HAUL ROAD DESIGN

    Steve

    Sounds like a good approach some changes or modifications to designs can have far reaching

    effects on operation and maintenance best to explore these before implementation.

    http://www.ozminerals.com/http://www.ozminerals.com/mailto:[email protected]:[email protected]:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[email protected]://www.ozminerals.com/
  • 8/12/2019 Individual Project Assignment

    33/109

    Haul Road Upgrade Project

    33 | P a g e

    Have worked with iron-ore discard roads wearing course material before at a few sites (overseas)

    and it tends to make an excellent wearing course if it does not slake (and obviously has no fibrous

    material content). Only issue is sometimes too little fine fractions or binder. Bituminous emulsion

    treatment also generally an excellent option with this material type, mixed-in if well compacted road

    with low void ratio, or spray on IF depth of penetration can be assured (last thing you want is a thin

    crust of treatment bit like a sheet of glass on top of a sponge).

    Friction/skid resistance testing always good info (Dave Tulloch RTS? excellent for this evaluation

    work) but Id also suggest sampling and evaluating the wearing course material at the locations you

    do these tests too otherwise you dont have such a good idea of what influence the wearing course

    material (as opposed to moisture/rainfall) has on friction supply. Ditto any treatment you

    apply. Shave off top 10-20mm max of wearing course where you do the tests and evaluate following

    AS1289.

    Would be happy to act as your third party peer review and quarterly inspection consultant (haulroad

    design aspects safety audits best handled by Damir Vagaja of ARRB). I can run this work through

    WASM Consulting who provide liability cover, Admin and invoicing etc. as part of their service. As

    and when the work transpires, I can provide a Scope of Works Quote and take it from there.

    Regards

    Roger

    From:Stephen McKnight[mailto:[email protected]]

    Sent:Tuesday, 3 January 2012 12:00 PM

    To:Roger Thompson

    Subject:RE: HAUL ROAD DESIGN

    Hi Roger,

    First off really appreciate your prompt reply and considered response

    Over the last month I have been reading everything you have published to get up to speed with thisproject

    I am glad you agree with the negative crossfall of 2% with qualifications, of course

    We are working with Thiess our Open Pit Hauling Contractor

    They have a high turn-over of staff so there are a significant number of newbies on-site at any one

    time, hence our difficulties with the fleet working in wet weather, among other reasons

    mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]
  • 8/12/2019 Individual Project Assignment

    34/109

    Haul Road Upgrade Project

    34 | P a g e

    I take on board your central corridor berm idea and will pass it on to the team for discussion

    And yes we need to consider drainage in such cases

    We are looking at introducing HPGPS & LPGPS systems on both graders and dozers

    We are also looking at applying Dust Bloc as well to the wearing course; this is a bitumen type

    palliative

    The wearing course will be made of steely haematite, MPa >150 passing through up to 75mm @

    200mm depth close to or above 80% CBA

    With regards friction analysis we are bring in a team to do the whole mine on the 24-26 January, to

    establish a baseline

    I fully appreciate the negative superelevation on the downward journey into the pit. This will be

    and has been discussed with the Thiess team, but will be further enforced

    We are constructing a simulation ramp at 10% to begin training the operators

    A constructed ramp with a crossfall of 2% appropriate wearing course and drainage

    With another ramp with no controls in place

    Yes, I totally agree with the civil/geotech analysis and intend to follow your specifications to theletter

    Roger would you consider being our third party peer review and quarterly inspection consultant?

    Im not sure if you would be available, but your experience and technical background are second to

    none in this field

    It would be a privilege and a pleasure if you were interested in assisting our team over the course of

    this project

    Cheers,

    Steve McKnightContract Mining Engineer Mine Improvement Team

    OZ Prominent Hill | Respect Integrity Action Results Ground Floor, 170 Greenhill Road

    Parkside, South Australia, 5063, Australia

    http://www.ozminerals.com/http://www.ozminerals.com/http://www.ozminerals.com/
  • 8/12/2019 Individual Project Assignment

    35/109

    Haul Road Upgrade Project

    35 | P a g e

    T61 8 8672 8148F 61 8 86728101M 04 350 29 [email protected]

    Please consider the environment before printing this e-mail

    From:Roger Thompson[mailto:[email protected]]Sent:Tuesday, 3 January 2012 2:03 PM

    To:Stephen McKnight

    Subject:RE: HAUL ROAD DESIGN

    Steve

    In principal, a construction width of 35m for a 30m running surface (4x6.64m body width of 793C)

    appears fine. The cross-fall of 2% also typical but would depend on the type of wearing course

    (surfacing) material you have too. The only recurrent problem with a constant crossfall is thepotential of trucks to wander across lanes into the direction of on-coming traffic. If you have

    operating experience and safety/accident data, it may be worth looking at the type of

    accidents/near-misses at the site to see if truck misalignment/skidding, etc. is an issue for whatever

    reason. Centre berms have been used in some operations to split traffic lanes, but with a constant

    crossfall, this complicates drainage (and road and berm maintenance).

    Blading a road with a constant crossfall is also more difficult than a crowned road, with the added

    problem of debris, spillage, etc. being pushed to the drain-side where it could cause tyre damage,

    etc. Good grading practice should remedy this.

    Further, where the road is required to change direction against the cross-fall, care will be needed to

    specify speed limits (especially down-grade unladen) since on these curves, the super-elevation will

    be in the wrong sense and road surface friction supply needs to be maximised here to prevent

    skidding. An incorrect super-elevation may lead to truck instability at speed, and the misalignment

    problems outlined above.

    This also raises the issue of the wearing course material itself. A good quality material is required,

    with a CBR ideally >80%, to help reduce the likelihood of cross-erosion or run-off channels being

    mailto:[email protected]:[email protected]:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[email protected]
  • 8/12/2019 Individual Project Assignment

    36/109

    Haul Road Upgrade Project

    36 | P a g e

    eroded from the wearing course on the down-slope edge of the road. The majority of even the best

    specified wearing course materials are sensitive to rain, and the road will go down eventually. You

    may want to look at adding a stabiliser or other similar treatment to the wearing course to enhance

    its ability to shed water as opposed to absorb it. In doing this, youll need to ensure the road

    structure is well built and can support a long-lasting surface treatment otherwise youll end up

    blading it off the road as you blade the surface due to poor support problems in the structure

    itself.

    Good starting point would be to sample actual/proposed wearing course materials and get a civil

    eng lab to run a road indicator test on them according to AS1289 (grading to 0.075, Atterburg limits,

    MDD, OMC and CBR at say 97% Mod AS1289) to see what youve got and what options you have if

    you need to fix it up (reduce clay by adding aggregates, increase fine fraction to improve binding,

    etc.). Treatment suppliers would also look at this info to determine how and at what rate of

    application their product may work.

    Let me know if you need more info happy to assist.

    Roger

    From:Stephen McKnight[mailto:[email protected]]

    Sent:Monday, 2 January 2012 4:59 AM

    To:Roger Thompson

    Subject:HAUL ROAD DESIGN

    Hi RJ,

    I am currently working on an all-weather haul road upgrade project here in South Australia

    I have been applying many of your thoughts, concepts and principles to this project

    The project consists of approximately 10kms of road work; in pit haul roads, outer ring roads and

    waste dump/ROM pad roads

    The projects focus is to reduce the downtime we experience from rainfall events

    It has been determined that with rain events between 1mm 5mm we lose up to 80% productivity

    due to truck downtime

    Some 470 hrs per year per digger, we have 5 Diggers; 996 Liebher

    Our aim is to achieve 6000 hrs per digger per year and the all-weather haul road upgrade project has

    been put in place to achieve a high percentage of this target

    mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]mailto:[mailto:[email protected]]
  • 8/12/2019 Individual Project Assignment

    37/109

    Haul Road Upgrade Project

    37 | P a g e

    Currently, there are no crossfalls, no road designs or competent material utilised in the construction

    of the roads.

    I have developed a traffic light system that identifies these conditions and we are working our way

    through the work required

    However, I require your thoughts on the following situation

    We are developing a design for a negative superelevation for the in pit curved roads, which will

    spiral down to some 480m at the end of the pits life

    We are considering the following ideas;

    Up 2% crossfall from the in-pit side of the road out to the highwall side We will install the drainage on the highwall side of the pit and pump it out from sumps

    The width of the total road is 35m

    The working surface is up to 30m

    We are using 973 Cat Dump Trucks (payload 220t)

    My question is related to the negative superelevation

    Therefore, what we are proposing, is it safe and feasible or do you have better: thoughts, comments,

    ideas or suggestions

    We need to make sure the rain water runs off the wearing course into the drains so we do not lose

    truck availability

    Cheers,

    Steve McKnightContract Mining Engineer Mine Improvement Team

    OZ Prominent Hill | Respect Integrity Action Results Ground Floor, 170 Greenhill Road

    Parkside, South Australia, 5063, Australia

    T61 8 8672 8148F 61 8 86728101M 04 350 29 [email protected]

    http://www.ozminerals.com/http://www.ozminerals.com/mailto:[email protected]:[email protected]:[email protected]://www.ozminerals.com/
  • 8/12/2019 Individual Project Assignment

    38/109

  • 8/12/2019 Individual Project Assignment

    39/109

    Haul Road Upgrade Project

    39 | P a g e

    These 5 categories have been further calculated in the below risk register matrix

  • 8/12/2019 Individual Project Assignment

    40/109

    Haul Road Upgrade Project

    40 | P a g e

    HUMAN RESOURCES

    Project Manager: Steve McKnight

    Mine Project Engineer: Leidy Alvarado

    T8 Supervisors: David Kurtzer / Chris Carroll

    Road Crew A & B

    2 x CAT 992 Wheel Loader Operators

    2 x CAT 16 H Grader Operators

    2 x CAT D10 Dozer Operators

    4 x KOMATSU 785 Truck Operators

    Expert Consultants on an as required basis

    (Friction Test Engineer, Geotechnical Engineer, Surveyors & Peer Review Principal Engineer)

    ProjectManager

    T8 Road

    MaintenanceSupervisors

    Road Crew A Road Crew B

    Project

    Engineer

    ExpertConsultants

  • 8/12/2019 Individual Project Assignment

    41/109

    Haul Road Upgrade Project

    41 | P a g e

    COMMUNICATIONS

  • 8/12/2019 Individual Project Assignment

    42/109

    Haul Road Upgrade Project

    42 | P a g e

    PROCUREMENT

  • 8/12/2019 Individual Project Assignment

    43/109

    Haul Road Upgrade Project

    43 | P a g e

    APPENDIX.1

    THE PROJECT MANAGEMENT PLAN

  • 8/12/2019 Individual Project Assignment

    44/109

    Haul Road Upgrade Project

    44 | P a g e

  • 8/12/2019 Individual Project Assignment

    45/109

    Haul Road Upgrade Project

    45 | P a g e

  • 8/12/2019 Individual Project Assignment

    46/109

    Haul Road Upgrade Project

    46 | P a g e

  • 8/12/2019 Individual Project Assignment

    47/109

    Haul Road Upgrade Project

    47 | P a g e

  • 8/12/2019 Individual Project Assignment

    48/109

    Haul Road Upgrade Project

    48 | P a g e

  • 8/12/2019 Individual Project Assignment

    49/109

    Haul Road Upgrade Project

    49 | P a g e

  • 8/12/2019 Individual Project Assignment

    50/109

    Haul Road Upgrade Project

    50 | P a g e

  • 8/12/2019 Individual Project Assignment

    51/109

    Haul Road Upgrade Project

    51 | P a g e

  • 8/12/2019 Individual Project Assignment

    52/109

    Haul Road Upgrade Project

    52 | P a g e

  • 8/12/2019 Individual Project Assignment

    53/109

    Haul Road Upgrade Project

    53 | P a g e

  • 8/12/2019 Individual Project Assignment

    54/109

    Haul Road Upgrade Project

    54 | P a g e

  • 8/12/2019 Individual Project Assignment

    55/109

    Haul Road Upgrade Project

    55 | P a g e

  • 8/12/2019 Individual Project Assignment

    56/109

    Haul Road Upgrade Project

    56 | P a g e

  • 8/12/2019 Individual Project Assignment

    57/109

    Haul Road Upgrade Project

    57 | P a g e

  • 8/12/2019 Individual Project Assignment

    58/109

    Haul Road Upgrade Project

    58 | P a g e

  • 8/12/2019 Individual Project Assignment

    59/109

    Haul Road Upgrade Project

    59 | P a g e

  • 8/12/2019 Individual Project Assignment

    60/109

    Haul Road Upgrade Project

    60 | P a g e

  • 8/12/2019 Individual Project Assignment

    61/109

    Haul Road Upgrade Project

    61 | P a g e

  • 8/12/2019 Individual Project Assignment

    62/109

    Haul Road Upgrade Project

    62 | P a g e

  • 8/12/2019 Individual Project Assignment

    63/109

    Haul Road Upgrade Project

    63 | P a g e

  • 8/12/2019 Individual Project Assignment

    64/109

    Haul Road Upgrade Project

    64 | P a g e

  • 8/12/2019 Individual Project Assignment

    65/109

    Haul Road Upgrade Project

    65 | P a g e

  • 8/12/2019 Individual Project Assignment

    66/109

    Haul Road Upgrade Project

    66 | P a g e

  • 8/12/2019 Individual Project Assignment

    67/109

    Haul Road Upgrade Project

    67 | P a g e

  • 8/12/2019 Individual Project Assignment

    68/109

    Haul Road Upgrade Project

    68 | P a g e

  • 8/12/2019 Individual Project Assignment

    69/109

    Haul Road Upgrade Project

    69 | P a g e

  • 8/12/2019 Individual Project Assignment

    70/109

    Haul Road Upgrade Project

    70 | P a g e

  • 8/12/2019 Individual Project Assignment

    71/109

    Haul Road Upgrade Project

    71 | P a g e

  • 8/12/2019 Individual Project Assignment

    72/109

    Haul Road Upgrade Project

    72 | P a g e

  • 8/12/2019 Individual Project Assignment

    73/109

    Haul Road Upgrade Project

    73 | P a g e

    DESIGN ANDCONSTRUCTION OF

    MINE ROADS

    1.0 GENERAL .......................................................... 75

    2.0 CONTROLS ........................................................ 75

    2.1 Road Classification ................................................... 75

    2.1.1 Permanent Haulroads ................................................. 752.1.2 Pit Haulroads (Short or Medium Term Haulroads) ........... 762.1.3 Light Vehicle Roads .................................................... 76

    2.2 Mine Road Design & Construction Process ................... 76

    2.3 Rolling Resistance.................................................... 78

    2.4 Geometric Design Phase ........................................... 79

    2.4.1 Stopping Distance ...................................................... 792.4.2 Sight Distance ........................................................... 792.4.3 Alignment ................................................................. 802.4.4 Roadway Width ......................................................... 812.4.5 Cross Fall ................................................................. 822.4.6 Gradient ................................................................... 832.4.7 Super-elevation ......................................................... 842.4.8 Road Side Drainage .................................................... 862.4.9 Road Shoulders ......................................................... 872.4.10Bundwalls ................................................................. 872.4.11Intersections ............................................................. 89

    2.4.12Intersection Traffic Control .......................................... 932.4.13Runaway Vehicle Control............................................. 942.4.14Heavy Equipment Go-lines .......................................... 96

    2.5 Structural Design Phase ........................................... 99

    2.5.1 General Road Construction .......................................... 992.5.2 In-situ Surface Preparation ....................................... 1002.5.3 Sub-base Requirements ............................................ 1002.5.3 Base Course Requirements ........................................ 101

  • 8/12/2019 Individual Project Assignment

    74/109

    Haul Road Upgrade Project

    74 | P a g e

    2.6 Functional Design Phase ......................................... 101

    2.6.1 Running Surface Requirements .................................. 102

    2.7 Maintenance Design ............................................... 102

    2.7.1 General Road Maintenance ........................................ 1042.7.2 Road Furniture Signs ............................................. 1042.7.3 Road Furniture Sign Positioning ............................... 1052.7.4 Road Furniture Delineators ..................................... 106

    3.0 MONITORING & REVIEW ................................ 106

    4.0 RESPONSIBILITIES ........................................ 107

    4.1 Mineworkers ........................................................... 107

    4.2 Supervisors ............................................................ 107

    4.4 Superintendents / Project Manager ............................ 107

    5.0 USEFUL REFERENCES & FORMS ...................... 108

  • 8/12/2019 Individual Project Assignment

    75/109

    Haul Road Upgrade Project

    75 | P a g e

    PROCEDURE & INFORMATION

    Procedure Information

    1.0 General

    Mine roads shall be designed and constructed to appropriate specifications

    to allow the safe and efficient movement of vehicles around the mine site.

    The specifications must have regard to the particular conditions at the mine,

    including the following:

    The characteristics of the mine vehicles;

    The types of materials available for road construction;

    The methods of working the mine;

    Relevant legislation.

    Good design and construction of mine roads will enable:

    Safe movement of vehicles;

    Optimal haulage cycle times;

    Increased tyre life;

    Less stress to mechanical components of vehicles;

    Less structural damage to vehicle chassis;

    Reduced operator fatigue.

    PRINTING INFORMATION

    Due to the graphicsincluded within the

    body of this document

    it must be printed inhigh resolution

    2.0 Controls

    2.1 Road Classification

    Mine roads should be designed and constructed to a standard in accordance

    with the road classification which is dependent on:

    The expected life span of the road;

    The primary purpose of the road;

    The frequency of usage of the road.

    2.1.1 Permanent Haulroads

    Permanent haulroads are major arterial roads used by haul trucks and the

    majority of mine traffic. The basic criteria for permanent haulroads are as

  • 8/12/2019 Individual Project Assignment

    76/109

    Haul Road Upgrade Project

    76 | P a g e

    Procedure Informationfollows:

    Long term existence;

    Used by haul trucks and other mine vehicles;

    High frequency usage;

    Formed construction profile;

    Delineated.

    2.1.2 Pit Haulroads (Short or Medium Term Haulroads)

    Pit haulroads are roads that are used by haul trucks and other mine trafficin and around pit areas including, in pit haulroads and ramps, bench roads,

    dump roads and ramps, etc. The basic criteria for pit haulroads are as

    follows:

    Short to long term existence depending on particular road function;

    Used by haul trucks and other mine vehicles;

    High frequency usage (may be periodic);

    Formed or non-formed construction profile;

    Delineated.

    2.1.3 Light Vehicle Roads

    Light vehicle roads are roads that are used by light and medium vehicles for

    access around the perimeter of the pit, within pit areas and on the surface.

    The basic criteria for light vehicle roads are as follows:

    Short to long term existence depending on particular road function;

    Used by light and medium vehicles only;

    Low to medium frequency usage;

    Basic construction profile only;

    Delineated on more permanent light vehicle roads.

    2.2 Mine Road Design & Construction Process

  • 8/12/2019 Individual Project Assignment

    77/109

    Haul Road Upgrade Project

    77 | P a g e

    Procedure Information

    Mine road design and construction can be thought of as 4 distinct steps orphases:

    Alignment

    Super-elevation

    Gradient

    Sight Distance, Etc.

    General road construction

    In-situ surface preparation

    Sub-base requirements

    Base course requirements

    Running surface requirements

    Haulroad maintenance

    Road furniture signage

    Road furniture delineators

    Inspections / audits

    Design &

    Construct

  • 8/12/2019 Individual Project Assignment

    78/109

    Haul Road Upgrade Project

    78 | P a g e

    2.3 Rolling Resistance

    Rolling resistance is the resistance that occurs when a tyre rolls on a

    surface.

    Rolling resistance can significantly impact on the efficiency of vehicles

    travelling on a mine road and associated haulage costs.

    It is caused by any combination of the following:

    Deformation of the road (may be at any depth in the road profile)under the tyre;

    Penetration of the tyre into the road surface;

    Tyre deformation caused by the road surface resulting in energyrequired to lift the vehicle as opposed to propel it forward.

    Rolling resistance of a haulroad shall be considered throughout all 4 phases

    of the design and construction process to maximise haulage efficiency and

    safety.

    Poor geometric design resulting in significant

    or sharp changes to vehicle direction andspeed may result in deformation of the road,

    tyre deformation and/or tyre penetration intothe road surface;

    Poor structural design (as a result of poor in-situ surface, insufficient structural layerthickness, inappropriate structural materialand/or poorly constructed structural layers)may result in deformation of the road profile;

    Poor functional design (as a result ofinappropriate running surface material and/orpoorly constructed running surface layer) mayresult in tyre penetration;

    Poor maintenance design (as a result of poormaintenance practices and/or insufficient

    maintenance frequency) may result in aninability to minimise all types of rollingresistance.

    In order to maximise haulage efficiency rolling resistance should be

    minimised where possible.

    Refer to AM-PH-HS-IF-0832.8 Information

    Sheet Rolling

    Resistance Table

  • 8/12/2019 Individual Project Assignment

    79/109

    Haul Road Upgrade Project

    79 | P a g e

    2.4 Geometric Design Phase

    The geometric parameters of the mine road shall be designed to ensure the

    safe and efficient travel of mine vehicles at normal operating speeds.

    2.4.1 Stopping Distance

    Mine roads shall be designed to accommodate the stopping distance of thelargest fully laden haul truck regularly using the road (using emergencybraking).

    Theoretical stopping distances may be determined from a series of StoppingDistance Characteristic Graphs developed by the Society of Automotive

    Engineers (SAE).OEMs utilise these standards to design their vehicle brake systems.

    Tests carried out by Dawson in 1975 indicate that to preclude brake fade or

    failure, 61m braking distance should be considered the minimum allowable(this is under test conditions). However, adopted stopping distance needs toaccommodate a number of variables (e.g. driver reaction time, road surfaceconditions, traction loss, etc) as well as the vehicle braking capability. As aresult, a minimum stopping distance of 100m should be utilised.

    Refer toAM-PH-HS-IF-0832.10 Information

    Sheet SAE Stopping

    Distance Graphs

    2.4.2 Sight Distance

    Sight distance is the extent of peripheral area visible to the vehicle

    operator, and is dictated by:

    The design speed of the road;

    The driver eye height of the lowest vehicle using the road;

    The stopping distance of the largest vehicle using the mine road inthe worst case driving conditions.

    The distance ahead of the driver to an unforeseen hazard shall always be

    greater than the distance required to bring the vehicle to a stop.

    On hill crests, the sight distance may be restricted by the vertical curve or

    crest of the hill, in this instance the crest may need to be flattened.

    At horizontal curves or intersections of the road the sight distance may be

    restricted by batters, vegetation, signs or other obstructions. Wherepossible horizontal curves and intersections should have all sight

    restrictions removed or minimised.

  • 8/12/2019 Individual Project Assignment

    80/109

    Haul Road Upgrade Project

    80 | P a g e

    2.4.3 Alignment

    Road alignment refers to the road direction in both the horizontal and

    vertical planes.

    The following elements should be considered when designing the mine road

    alignment:

    All curves (horizontal and vertical) should be designed with thelargest radius possible;

    The alignment should be smooth and consistent;

    Compound curves (curves where the radius changes) shall not beused;

  • 8/12/2019 Individual Project Assignment

    81/109

    Haul Road Upgrade Project

    81 | P a g e

    Horizontal and vertical alignments should complement each otherand the following should be considered when combining horizontal

    and vertical curves:

    o Avoid sharp horizontal curves at the crest of vertical curvesas sight distance is generally restricted and it is difficult for

    drivers to perceive the curves in such a situation;

    o Avoid sharp horizontal curves at the base of ramps or longsustained downhill grades as vehicles are typically at theirhighest speed at these locations;

    o If switchbacks are required they should be designed with thelargest radius possible and should be placed on flat sections,avoid placing them on grade as the inside of the curve mayexceed the design gradient specification.

    2.4.4 Roadway Width

    Mine roads should be designed and constructed to suit the Operating Width

    of the largest vehicle that will be using the road regularly.

    The following table summarises the roadway width for various road types:

    StraightSingle Lane Roadway 2 x Operating Width

    StraightDouble Lane Roadway 3.5 x Operating Width

    CurvedSingle Lane Roadway 2 x Operating Width x 1.18

    CurvedDouble Lane Roadway 3.5 x Operating Width x 1.18

    (1.18 represents an overhang/vehicle tracking multiplier)

    Consideration should be given to separate roadways where possible

    particularly in high hazard areas (e.g. fog zones). In such circumstances the

    roadways should be separated by a median (separation) bund or other

    physical barrier. The height of the median bund or physical barrier must be

    appropriately selected to ensure that sight distance is not affected (typically

    median bundwall height should be restricted to 1m unless otherwise

    required for risk control).

    In areas where roadway width criteria cannot be met, an assessment of risk

    shall be undertaken and appropriate controls put in place.

    Straight Double Lane Roadway Schematic

    The Roadwayof a mine

    road refers to the running

    surface of the road.

    The Operating Width of a

    vehicle is the maximum

    width of the vehicle during

    normal operation. The

    measurement must be

    taken from outer

    extremity (for examplemirrors, tray, rock

    deflectors, etc) on one

    side to the outer extremity

    (for example mirrors, tray,

    rock deflectors, etc) on the

    other side.

    Refer toAM-PH-HS-TP-0832.6 Template Site Specification

    Sheet (Site Version)

    Refer to AM-PH-HS-FO-0501.6 Job Safety and

    Environmental Analysis

  • 8/12/2019 Individual Project Assignment

    82/109

    Haul Road Upgrade Project

    82 | P a g e

    Cat Graphics reproduced with permission from Caterpillar Inc.

    Straight Separated Double Lane Roadway Schematic

    Cat Graphics reproduced with permission from Caterpillar Inc.

    Separated Roadways are

    treated as two single lane

    roadways whendetermining roadway

    width.

    2.4.5 Cross Fall

    Cross fall is the cross road gradient perpendicular to the road direction and Refer toAM-PH-HS-

    TP-0832.6 Template

    Site Specification

    Sheet (Site Version)

  • 8/12/2019 Individual Project Assignment

    83/109

    Haul Road Upgrade Project

    83 | P a g e

    should be utilised in order to divert water away from the road surface.

    The rate of cross fall should allow rapid water runoff without adverselyaffecting the drivers steering control or increasing Position 1 tyre wear.

    The degree of cross fall is dependent and directly related to:

    Road gradient;

    Expected rainfall (during normal weather conditions);

    Construction materials used on the running surface.

    The following table details typical cross fall for various applications:

    Road Gradient

    Min Cross fall

    Low Rainfall or Smooth

    Surface

    Max Cross fall

    High Rainfall or Rough

    Surface

    0 to 4% 1 in 25 1.0% 3%

    5 to 9% 1 in 11 1.0% 2.5%

    10 to 12.5% 1 in 8 0.5% 2%

    Refer toAM-PH-HS-IF-

    0832.11 InformationSheet GradientConversion

    2.4.6 Gradient

    The gradient on a ramp is the grade line profile along the road centre line,

    in the vertical plane.

    Vertical curves should be utilised to provide smooth transitions from onegrade to another. The vertical curves utilised shall ensure that the sight

    distance is sufficient at the design speed for the vehicles using the road.

    Gradient should be kept as constant as possible (avoid unnecessary grade

    changes) to reduce the tendency of trucks to change through gears (hunt)

    on the up-grade hauls. This affects:

    Haulage cycle times;

    Fuel consumption;

    Stress on the mechanical components of the vehicle e.g.

    transmissions and torque converters;

    Excessive chassis flexing due to uneven surfaces (Racking);

    Damage to the road surface.

    Gradient should be selected in accordance with manufacturers

    specifications to suit the particular vehicle that is expected to utilise the

    road.

    Both the uphill (rimpull) and downhill (retarding/brake capability) of the

    vehicle should be considered when determining the most appropriate grade.

    Refer toAM-PH-HS-IF-0832.11 Information

    Sheet Gradient

    Conversion

    Refer toAM-PH-HS-TP-0832.6 Template Site Specification

    Sheet (Site Version)

  • 8/12/2019 Individual Project Assignment

    84/109

    Haul Road Upgrade Project

    84 | P a g e

    Particular attention needs to be paid to loaded downhill haulage and/or long

    sustained downhill grades (for both loaded and unloaded operations) to

    ensure that the braking capability of the vehicle is not compromised.

    Consideration must also be given to possible mine design impacts when

    selecting gradients.

    Typically grades up to 10% (1in10) should be utilised on haulage ramps.

    An assessment of risk shall be undertaken for grades ranging from 10%

    (1in10) to 12.5% (1in8).

    Gradients exceeding 12.5% (1in8) shall not be utilised.

    Median bundwalls should be utilised to separate traffic where there is a

    horizontal curve on grade. Horizontal curves on ramps may increase the

    potential for vehicles travelling down the ramp to lose control and slide into

    vehicles travelling up the ramp (this is particularly the case when the down

    grade curve is to the left).

    2.4.7 Super-elevation

    Super-elevation is the cross fall applied to switchbacks, corners and curves.

    It allows the vehicle taking the corner to counteract the centrifugal forces

    by directing the vehicle weight towards the centre of radius of the curve.

    All horizontal curves shall be appropriately super-elevated and/or speed

    restricted.

    The amount of super-elevation on the corner is directly related to the radius

    of the corner and the desired vehicle speed through the corner.

    Under no circumstance shall negative super-elevation be used.

    Typically super-elevation for a normal mine road application is between 3%

    and 5%. Super-elevation rates above 5% are not recommended.

    The following table details recommended super-elevation rates and proper

    curve and speed relationship:

    Recommended super-elevation rates in % for given vehicle speeds and curve radii

    Curve

    RadiusVehicle Speed (km/hr)

    20 30 40 50 60 70

    50m 6% - - - - -

    Refer toAM-PH-HS-IF-0832.11 InformationSheet Gradient

    Conversion

  • 8/12/2019 Individual Project Assignment

    85/109

    Haul Road Upgrade Project

    85 | P a g e

    75m 4% 9% - - - -

    100m 3% 7% - - - -

    200m 2% 4% 6% 10% - -

    300m 2% 2% 4% 7% 8% -

    400m 2% 2% 3% 5% 6% 6%

    500m+ 2% 2% 3% 5% 5% 5%

    Outside of recommended specification

    The portion of the road used to transform a cross slope section into a super-

    elevated section is termed the run-out length.

    The purpose of the run-out is to assist the driver in the manoeuvring of avehicle through the curve.

    Run-out lengths vary with the design speed and total change in cross slope.

    The following table enables the correct run-out length to be determined and

    at what rate the cross slope transitions:

    Cross slope change in % for 1 0 mof roadway length

    Vehicle Speed (km/hr)

    15 20 25 30 35 40 45 50 55

    2.5% 2.5% 2.5% 2.1% 1.8% 1.6% 1.4% 1.3% 1.1%

    Example:

    To illustrate the calculation of run-out assume a vehicle is travelling at

    50km/hr. The roadway has a normal cross fall of 3% to the left. The vehicle

    encounters a curve to the right that requires a super-elevation of 5% to the

    right. The total change in cross slope is 3%+5%=8%. From the above table

    the rate of change per 10m of roadway at 50km/hr is 1.3%. Thus the run-

    out length required is:

    = (8% / 1.3%) x 10m

    = 61.54m (use 62m)

    Run-out shall be applied such that 1/3 occurs in the curve and 2/3 in the

    tangent (straight section).

    Application of Super-elevation and Run-out

  • 8/12/2019 Individual Project Assignment

    86/109

    Haul Road Upgrade Project

    86 | P a g e

    2.4.8 Road Side Drainage

    Road side drains should be installed to rapidly drain surface water from the

    road. This will reduce unsafe driving conditions and damage to the road

    due to water saturation of the road surface and/or structural layers.

    All drainage shall comply with the site Environmental Management Plan

    (EMP).

    V-drains are recommended due to ease of construction, basic maintenance

    and design. The following design parameters are recommended where

    possible:

    If possible the drain should be located in undisturbed material rather

    than fill; The side slopes shall be 4:1 or flatter;

    The drain should be a minimum of 0.5 metres in depth;

    Drains should be cleaned out and/or re-established when the depthhas been reduced by 50%;

    Drain gradient should be sufficient to ensure no ponding occurswithin the drain and water flows freely during rain events.

    Flat bottom drains require more construction effort however provide greater

    Radius

    TP -Tangent Point

    TP -Tangent Point

    2/3

    1/3

    1/3

    2/3Run-out

    Run-out

  • 8/12/2019 Individual Project Assignment

    87/109

    Haul Road Upgrade Project

    87 | P a g e

    flexibility in handling greater water flow without excessive depth providing a

    safer alternative in the event of a vehicle accidentally leaving the roadway.

    Rock check dams should be installed at nominal intervals along drainage

    paths and should be constructed with suitable rock to reduce flow velocity

    and aid in sedimentation capture.

    Where culverts are required under roads they should be built to suit

    individual design requirement specifications and flood study data. Culverts

    should be protected by installation of a headwalls both upstream and

    downstream. Where possible concrete headwalls should be used. As

    concrete headwalls are expensive, rock lined headwalls with rock

    mattresses in the stream beds and keyed into the road surface may be an

    appropriate alternative.

    Permanent drains and culverts that form an integral part of the

    Environmental Management Plan (EMP)shall be designed in accordance

    with industry accepted engineering methods and standards taking into

    consideration catchment areas, rainfall intensity and other accepted

    engineering criteria to ensure drain dimensions are adequate.

    2.4.9 Road Shoulders

    Road shoulders shall be designed to appropriately address the risk of a

    vehicle accidentally leaving the roadway.

    In areas where there is a vertical drop (>0.5m) along the road edge or avery steep (or sustained) shoulder grade, one or more of the followingcontrols shall be put in place:

    A suitable bundwall be constructed in the affected area;

    The shoulder be constructed at a maximum grade of 1V in 4H ratio;

    Delineators and/or signage be put in place to highlight the road edgeand potential drop off hazard;

    Training and education be undertaken to highlight the issue to roadusers.

    2.4.10 Bundwalls

    Bundwalls or bunds are a standard safety feature on mine roads, dump

    crests, pit wall crests or other areas where a vertical drop hazard exists.

    They may also be used to provide protection for various items in parking

    areas and/or to provide traffic separation on road networks and within

    intersections.

    They are typically flat topped triangular mounds used to redirect wandering

    Other commonly used

    terminology to describebundwalls includes, but is

    not limited to safety

    bunds, windrows, berms,safety berms, rills and

    earthen barriers.

  • 8/12/2019 Individual Project Assignment

    88/109

    Haul Road Upgrade Project

    88 | P a g e

    vehicles on the haulroad or to absorb some of the impact energy if the

    vehicle hits the bundwall.

    The following items should be considered when designing and constructingbundwalls:

    Unconsolidated material that will resist weathering should be usedfor construction;

    The risk associated with a hazard shall be considered in selecting theheight of a bundwall:

    o For standard bundwalls the height shall be equal to or greaterthan the height of the largest vehicle tyre ( inflateddiameter);

    o In areas where there is a high risk associated with asignificant edge drop off, where high haul speeds occurand/or other high risk situations, bundwall heights shall beincreased to the equivalent wheel diameter of the largestvehicle tyre (1x inflated diameter);

    In areas where bundwalls are used to define traffic separation withinan intersection, they shall be adequately sized to allow for maximumsight distance throughout the intersection. Bundwall height shall belimited to 1m in this application;

    The integrity of the bundwall is paramount, bunds should be aminimum of 1m wide across the top;

    The side slope of the bundwall shall be no flatter than 37 (repose,rill angle) so that the bundwall does not act as a ramp. Converselythe side slope of the bundwall should not be steeper than 45 (1to1)as the bundwall will lose integrity (stopping mass). If side slopes are

    made steeper than 45 then the thickness of the bundwall shall beincreased in order to maintain integrity;

    Bundwalls shall be kept clean of sizeable rocks capable of cuttingtyres, in areas where this is not possible old haul truck tyres shouldbe used on corner apex points;

    Small breaks in the bund should be left at regular points particularlywhere water will pool to allow for drainage of water off the road

    surface;

    Bundwalls shall be inspected and maintained regularly as they can

    be eroded due to rain, plant activity and road maintenanceactivities.

    Standardtrucks refers to

    equipment dimensions

    (tyre size) as specified by

    OEM (Original EquipmentManufacturer).

    The footprint dimensions(Y values) within the

    adjacent table have beencalculated with the

  • 8/12/2019 Individual Project Assignment

    89/109

    Haul Road Upgrade Project

    89 | P a g e

    The following table details bundwall dimension specifications for standard

    trucks:

    Vehicle

    ClassTyre Size

    Inflated

    Diameter

    Inflated Diameter

    Bundwall

    Specifications

    High Risk Area

    Bundwall

    Specifications

    X Y Z X Y Z

    Cat 777 27.00R49 2.694m 1.4m 4.8m 1m 2.7m 8.2m 1m

    Cat 785 33.00R51 3.061m 1.6m 5.3m 1m 3.1m 9.3m 1m

    Cat 789 37.00R57 3.456m 1.8m 5.8m 1m 3.5m 10.3m 1m

    Cat 793 40.00R57 3.557m 1.8m 5.8m 1m 3.6m 10.6m 1m

    Cat 797 59/80R63 4.025m 2.1m 6.6m 1m 4.1m 11.9m 1m

    EH 4500 50/90R57 3.825m 2.0m 6.4m 1m 3.9m 11.4m 1m

    Cat Graphics reproduced with permission from Caterpillar Inc.