INDIA: Accelerating Infrastructure Investment Facility in India … · 2019. 12. 26. · Ujjain...
Transcript of INDIA: Accelerating Infrastructure Investment Facility in India … · 2019. 12. 26. · Ujjain...
Environmental and Social Due Diligence Report
Project Number: 47083-004 December 2019
INDIA: Accelerating Infrastructure Investment
Facility in India – Tranche 3 Dewas Bypass Tollway Private Limited (Part 1 of 5)
Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance
Company Limited and the Asian Development Bank.
This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 1
Due Diligence Report on Environment and Social Safeguards
By
India Infrastructure Finance Company Limited (IIFCL)
(A Govt. of India Enterprise)
Sub-Project: 4/6 Laning of Dewas Bypass commencing from Km 0+000
(Ujjain-Dewas junction) to Km 19+800 (total length 19.800 km), in the State of
Madhya Pradesh on Build, Operate and Transfer (BOT) basis
November 2019
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 2
SUB PROJECT: 4/6 Laning of Dewas Bypass commencing from Km 0+000
(Ujjain-Dewas junction) to Km 19+800 (total length 19.800 km), in the State of
Madhya Pradesh on Build, Operate and Transfer (BOT) basis
Dewas Bypass Tollway Private Limited (DBTPL)
Environment and Social Safeguards Due Diligence Report
(ESDDR)
Prepared by Dr. Rashmi Kadian
Assistant General Manager
(Environmental Specialist)
ESMU, IIFCL
Mr. Krupasindhu Guru
Assistant General Manager
(Social Specialist)
ESMU, IIFCL
Mr. Ashok Suyal
Consultant - Social Safeguards
Reviewed and Approved
by
Dr. S. S. Garg
General Manager & Head, ESMU
IIFCL
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 3
CONTENTS
PROJECT BACKGROUND ....................................................................................................... 5
1. PURPOSE OF THE REPORT ........................................................................................... 6
2. SUB-PROJECT TITLE ..................................................................................................... 6
3. SUB-PROJECT BACKGROUND ...................................................................................... 6
4. SUB-PROJECT LOCATION & DESCRIPTION ................................................................ 7
5. CONCESSIONAIRE ......................................................................................................... 8
6. EPC CONTRACTORS ...................................................................................................... 8
7. INDEPENDENT ENGINEER ............................................................................................ 8
8. IIFCL FUNDING .............................................................................................................. 9
9. STATUS OF PROJECT IMPLEMENTATION .................................................................. 9
DUE DILIGENCE ON ENVIRONMENTAL SAFEGUARDS .................................................... 10
10. ENVIRONMENT SAFEGUARDS COMPLIANCE REVIEW .......................................... 11
11. APPLICABILITY OF ENVIRONMENTAL IMPACT ASSESSMENT NOTIFICATION .. 11
12. APPROACH TO THE ENVIRONMENT SAFEGUARDS DUE DILIGENCE REPORT: .. 11
13. COMPLIANCE OF DBTPL TO THE ESSF OF IIFCL: ................................................... 12
14. POLICY, LEGAL AND REGULATORY REQUIREMENT: ............................................ 12
15. IMPACT ASSESSMENT OF SUB-PROJECT .................................................................. 14
16. ENVIRONMENTAL MANAGEMENT PLANS ............................................................... 15
17. HEALTH AND SAFETY ................................................................................................. 16
18. GRIEVANCE REDRESSAL MECHANISM .................................................................... 22
19. ENVIRONMENTAL SENSITIVITY ................................................................................ 22
20. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST ............... 23
21. CATEGORIZATION OF SUB-PROJECT ....................................................................... 23
22. SITE VISIT OBSERVATIONS ........................................................................................ 23
23. CONCLUSIONS AND RECOMMENDATIONS .............................................................. 25
DUE DILIGENCE ON SOCIAL SAFEGUARDS ....................................................................... 27
24. PURPOSE OF THE SOCIAL SAFEGUARDS DUE DILIGENCE .................................... 28
25. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST ............... 28
26. OBJECTIVE OF SOCIAL SAFEGUARDS DUE DILIGENCE ......................................... 28
27. APPROACH AND METHODOLOGY ............................................................................. 28
28. SOCIAL IMPACT OF THE PROJECT ........................................................................... 29
27.1 LAND ACQUISITION IN THE PROJECT ...................................................................... 29
27.2 IMPACT ON STRUCTURE ............................................................................................ 30
27.3 REHABILITATION AND RESETTLEMENT IMPACT IN THE SUB-PROJECT ............ 30
27.4 IMPACT ON INDIGENOUS PEOPLE ............................................................................ 30
29. GREIVANCE REDRESSAL MECHANISM FOR THE SUB-PROJECT .......................... 30
30. EMPLOYMENT GENERATION .................................................................................... 30
31. THE COMMUNITY ENGAGEMENT ACTIVITIES ....................................................... 31
32. LABOUR LICENSE OBTAINED BY THE SUBPROJECT DEVELOPER ....................... 31
33. DISCLOSURE ................................................................................................................ 31
34. SITE VISIT OBSERVATION .......................................................................................... 31
LIST OF FIGURES
Figure 1: DBTPL road and proposed toll plaza location………………………………………………7
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 4
LIST OF TABLES
Table 1: Salient Features of Dewas Bypass Tollway Private Limited……………….…………………7
Table 2: Status of Regulatory Permits/ Clearances Obtained related to Environmental Safeguards…..13
Table 3: Proposed EMP and its Implementation status during Construction Phase at DBTPL……......17
Table 4: Proposed EMP for Operation of DBTPL……………………………………………………….20
Table 5: Status of Land available at DBTPL……………………………………………………………...29
ANNEXURES
Annexure I Copy of Tree Implantation Permission
Annexure II A & B Copies of Consent to Establish
Annexure III Consent to Operate
Annexure IV Environmental Clearance for Quarry Area
Annexure V Environmental Clearance for Borrow Area
Annexure VI Labour License
Annexure VII Insurance Copy
Annexure VIII Permission for using water
Annexure IX NOC from Village Panchayat for Camp site
Annexure X License for Explosives
Annexure XI Sample Copy Toll Box Meeting
Annexure XII Sample Copy Safety Training Programme
Annexure XIII Sample Copy On Job Safety Awareness Programme
Annexure XIV Organization chart HSE
Annexure XV Safety Audit Report by Independent Engineer
Annexure XVI Safety Audit Compliance submitted to IE
Annexure XVII CTO Compliance submission to MP PCB
Annexure XVIII Approved Diversion Plan
Annexure XIX ROW Handover Letter
PHOTOPLATE
Photoplate I : Site Visit Photographs
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 5
PROJECT BACKGROUND
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 6
1. PURPOSE OF THE REPORT
1. This Environmental and Social Due Diligence Report (ESDDR) has been carried out by India
Infrastructure Finance Company Limited (IIFCL) in consultation with the Concessionaire,
Dewas Bypass Tollway Private Limited (DBTPL) to assess the adequacy of the project with the
applicable National, IIFCL’s ESSF and ADB’s safeguard compliance. The report has been
prepared as per the documents/information received from the Concessionaire and on the basis
of site visit observations.
2. SUB-PROJECT TITLE
2. The sub-project includes - Four laning of existing road from Dewas Bypass (km 0.000) to
intersection of NH-3 and Dewas bypass (km 7.000) and six laning of part of bypass from NH-3 and
bypass intersection (km 7.000) until the intersection of the bypass and AB Road (km 19.800) in the
State of Madhya Pradesh on Design, Build, Finance, Operate and Transfer (DBFOT) basis.
3. SUB-PROJECT BACKGROUND
2. Madhya Pradesh Road Development Corporation (MPRDC) in the year 2016, invited detailed bid
proposals for widening and upgradation of Dewas Bypass from km 0.00 to km 19.80 on Build,
Operate and Transfer (Toll) basis. The project envisages four laning of 7.00 km stretch of Dewas
Bypass from Ujjain Dewas Junction (km 0.00) to km 7.00 and six laning of remaining section from
km 7.00 till end of bypass at Indore Dewas Junction (km 19.80).
3. The project stretch, Dewas Bypass, starts from the north western side of Dewas city and ends at AB
Road in south western side of the city. AB Road is a part of Mumbai Agra National Highway which
witnesses a high traffic movement. The existing two lanes forms a vital link in this region connecting
the northern Indian states to the Eastern Indian states and also caters to the Mumbai and Pune bound
traffic. It serves the long distance traffic which is majorly plying from UP, Agra and beyond to
Mumbai and beyond. Apart from long distance traffic, it also serves the short distance traffic which
is mainly generated between Ujjain, Gwalior, Indore, Bhopal and surrounding areas.
4. MPRDC awarded the project to Dewas Bypass Tollway Private Limited, an SPV formed by IJM
Corporation Berhad and the Concession Agreement was signed on February 27, 2017. The
concession period is of twenty five (25) years from Appointed Date (180 days from signing of
Concession Agreement) including construction period of 730 days (2 years).
5. The scope of the project includes performance & execution of all design, engineering, financing,
procurement, construction, completion, operation & maintenance (O&M) of the project corridor as
set out in the Concession Agreement (CA).
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 7
4. SUB-PROJECT LOCATION & DESCRIPTION
6. The project road comprises a 19.8 km stretch on State Highway 18 commencing from Ujjain Dewas
junction. The project road would be a rigid pavement. There is one level crossing on the existing
project road. The project scope includes construction of a railway over bridge, three vehicular
underpasses, 2 grade separators and widening of one minor bridge. For the initial 7 km stretch from
Ujjain Dewas Bypass junction, the paved carriage way shall be four lane and balance 12.8 km upto
Dewas bypass - AB road junction will be six lane. The proposed toll plaza will be located at 16.5
kms from Ujjain Dewas bypass junction. The location of DBTPL is given in Figure 1 and salient
features of the sub-project are given in Table 1.
Figure 1: DBTPL road and proposed toll plaza location
Table 1: Salient Features of Dewas Bypass Tollway Private Limited
Particulars Features
Name of Project 4/6 Laning of Dewas Bypass commencing from
Km 0+000 (Ujjain-Dewas junction) to Km 19+800
(Total Length 19.800 km.), in the State of Madhya
Pradesh on Build, Operate and Transfer (BOT) basis. State Madhya Pradesh
District Dewas
Concessioning Authority Madhya Pradesh Road Development Corporation
Concessionaire M/s Dewas Bypass Tollway Private Limited
Terrain Plain
Project Length 19.800 km
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 8
5. CONCESSIONAIRE
7. Incorporated in February 2017, Dewas Bypass Tollway Private Limited (DBTPL) is a
special purpose vehicle (SPV) promoted by the Malaysian construction firm IJM
Corporation Berhad and its investment companies to undertake the project of widening &
up-gradation of Dewas Bypass Road from Km 0.00 at Ujjain Dewas Junction and ending at
Km 19.80 at Indore Junction from two-lane to a four/six-lane highway in Madhya Pradesh
on a Design, Build, Operate and Transfer (DBOT) basis. The project was awarded by
Madhya Pradesh Road Development Corporation Limited (MPRDCL) based on
competitive bidding on February 27, 2017, with a concession period of 25 years
commencing from October 10, 2017 including the two year construction period.
6. EPC CONTRACTORS
8. IJM (India) Infrastructure Limited, Hyderabad is the EPC contractor for the sub-project. EPC
agreement has been signed between IJM (India) and DBTPL on April 21, 2017.
7. INDEPENDENT ENGINEER
9. Lion Engineering Consultant has been signed to monitor the sub-project as Independent Engineer
(IE).
Toll Plaza 1 at KM 16+050 Flyover (Nos.) 2 nos.
Vehicular Under Pass (Nos.) 3 nos.
ROB 1
Minor Bridges 1 nos.
Box Culverts 9 nos.
Pipe Culverts 35 nos.
Truck Laybye 1
Bus Shelter (Nos.) 19
Service roads 4 Km X 2
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 9
8. IIFCL FUNDING
10. The total project cost of DBTPL is ₹ 280.28 crores. The project is financed by IIFCL under Direct
Lending Scheme. IIFCL has sanctioned an amount of ₹ 56 crore towards DBTPL and disbursed ₹ 39.21 crores as on 31.10.2019.
9. STATUS OF PROJECT IMPLEMENTATION
11. The sub-project is under construction and the Scheduled Commercial Operations Date (SCOD) was
in October 2019. At the time of site visit during 15th October, 2019, DBTPL informed that
approximately 83% physical progress has been achieved. The sub project is expected to achieve
commercial operation by December 2019.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 10
DUE DILIGENCE ON ENVIRONMENTAL SAFEGUARDS
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 11
10. ENVIRONMENT SAFEGUARDS COMPLIANCE REVIEW
12. The environmental due diligence (EDD) report focuses on the status and review of the applicable
environmental regulatory requirements, compliance to the regulatory requirements, review of the
environment related sub-project documents, implementation of environmental management
measures at site, institutional arrangements for implementation and monitoring of environmental
measures, environment, health & safety (EHS) related clauses in agreements, health and safety
measures at work place, status of plantations and emergency preparedness.
11. APPLICABILITY OF ENVIRONMENTAL IMPACT ASSESSMENT NOTIFICATION
13. It is required that the project meets the applicable national guidelines / regulations relating to the
environment, occupational health and safety and social issues. The project should have necessary
clearances as well as permits and approvals for project implementation and suitable environmental
management plans.
14. National Highway projects up to 100 Kms involving additional right of way or land acquisition upto
40 meters on existing alignments and 60 meters on re-alignments or by-passes are exempted from
the scope of the Environmental Impact Assessment Notification, 2006 of Government of India. The
total length of the sub-projects is approximately 19.80 Kms; therefore, DBTPL does not require
environmental clearance and is not required to conduct an Environmental Impact Assessment (EIA)
as a statutory requirement. EIA study has not been conducted for the sub-project DBTPL.
12. APPROACH TO THE ENVIRONMENT SAFEGUARDS DUE DILIGENCE REPORT:
15. The Environmental Due Diligence Report (EDDR) reviews the available documents and assesses the
compliance of the sub-project with respect to environmental safeguards; regulatory clearances;
environmental impacts and management measures; Health, Safety and Environment (HSE)
measures; and categorization of sub-project on the basis of above review.
16. The following documents were referred in order to prepare Environmental Safeguards Due-
Diligence Report:
Project Information Memorandum (PIM)
Concession Agreement
Traffic study report
Independent Engineer Report (September 2019)
Safety Audit Report by Independent Engineer
Lender’s Independent Engineer (LIE) Reports
Project Statutory Approvals/Permits
Project HSE Documents
Labour License & insurance
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 12
Contract Documents
Emergency Response Plan
Grievance Redressal Mechanism
17. The environmental safeguard due-diligence study was carried out for the sub-project on the basis of
site visit observations and understanding project scope based on information and documents
provided by Concessionaire. A detailed discussion on the environmental and social safeguards
related issues was also carried out with the team of the sub-project at site.
18. On review of the documents / information related to the sub-project and on the basis of site visit, the
impacts of the DBTPL on environment are envisaged, which are given in section 15 of the ESDDR.
The sub-project is mitigating the environmental impacts at the site with various measures. An EMP
is proposed for DBTPL in concurrence with the developer (Section 16).
13. COMPLIANCE OF DBTPL TO THE ESSF OF IIFCL:
19. The Environmental and Social Safeguard Framework (ESSF) provides the enabling mechanism to
IIFCL to deliver its policy objectives and applies to projects funded by IIFCL throughout the project
cycle. The ESSF defines procedures, roles, and responsibilities, at various project milestones for
managing the adverse environmental impacts.
20. The environmental due diligence for DBTPL has been done as per requirements of direct lending
scheme. The environmental safeguard risks during construction phase have been assessed and risks
during operational phase have been evaluated. DBTPL is under construction and following the
regulations and guidelines. There does not seem to be any significant risk for either IIFCL or DFI
involved. The environmental measures being implemented at the sub project are proposed in the
form of structured EMP with monitoring indicators to DBTPL for both construction and operational
phase of sub-project. It can be concluded that DBTPL is compliant to the requirements of IIFCL’s ESSF under direct lending scheme and has adequate management measures implementation on site.
14. POLICY, LEGAL AND REGULATORY REQUIREMENT:
21. DBTPL does not fall under the schedule of EIA Notification, 2006 that lists projects or activities
requiring prior environmental clearance and hence these are exempt from obtaining environmental
clearance. DBTPL is required to comply with the applicable guidelines relating to the environment,
occupational health and safety in addition to complying with local pollution control board
regulations. The statutory permits/clearances related to environmental aspects obtained/to be
obtained from regulatory authorities as part of DBTPL development were assessed and current status
of availability of such permits/clearances are given in Table 2 below:
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 13
Table 2: Status of Regulatory Permits/ Clearances Obtained related to Environmental Safeguards
S.No. Permits/Clearances Statutory Authority Current Status
1. Environmental
Clearance
Ministry of
Environment, Forests &
Climate Change
(MoEF&CC), New
Delhi
Not Applicable. As the sub-project length is below
100 kms (19.8 Kms), this is exempted from
obtaining environmental clearance and conducting
EIA.
2. Forest Clearance MoEF&CC and State
Forest Department
The sub-project does not involve any forest land.
3. Wildlife Clearance MoEF&CC The Project area does not lie within an
ecologically sensitive area and is not located close
to any National Park/Wildlife Sanctuary. The
location of Project does not contravene any
international biodiversity or ecosystem
conservation conventions. Therefore, it does not
require wildlife clearance or permission.
4. Tree permissions Revenue Department,
Madhya Pradesh
Approximately 1354 nos of trees were coming in
ROW. These trees were on revenue land.
Permission from tree transplantation has been
taken from the Collector, District Dewas, Madhya
Pradesh. All the 1354 trees have been transplanted
on the proposed ROW. Copy of tree implantation
permission is attached as Annexure I.
5. Consent to Establish
Madhya Pradesh
Pollution Control Board
(MPPCB), Madhya
Pradesh State
Consent to Establish under section 25 of Water
(Prevention & Control of Pollution) Act, 1974 and
under section 21 of Air (Prevention & Control of
Pollution) Act 1981 was obtained from Madhya
Pradesh Pollution Control Board for RMC plant,
Crusher plant, etc have been obtained. Sample
copies are attached as Annexure II A & B.
6. Consent to Operate Madhya Pradesh
Pollution Control Board
(MPPCB), Madhya
Pradesh State
Consent to Operate under section 25/26 of the
Water (Prevention & Control of Pollution) Act,
1974 and under section 21 of Air (Prevention &
Control of Pollution) Act 1981 and amendments
thereof has been obtained from MPPCB
(Annexure III).
7. Quarry and Borrow
Area Permissions
District level
Environment Impact
Assessment Authority
(DEIAA), Dewas,
Madhya Pradesh
Prior Environmental Clearance has been taken
from DEIAA, Dewas for the quarry/borrow being
used for DBTPL sub-project. Sample copies of
environmental clearances taken by the contractor
are attached as Annexure IV and Annexure V.
8. Labour & Insurance
Licensing Officer,
Dewas, Government of
Madhya Pradesh
DBTPL has taken Labour License under the
Contract Labour (Regulation and Abolition) Act,
1970. The establishment has valid labour license
which is enclosed as Annexure VI. Insurance
policy for DBTPL is enclosed as Annexure VII.
The EPC contractor also has a valid labour license
and insurance.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 14
15. IMPACT ASSESSMENT OF SUB-PROJECT
22. EIA study was not conducted for the sub-project as the project does not fall under the purview of
EIA Notification and subsequent amendments as explained in Section 11 of the EDDR.
23. As the bypass has already been constructed with two lanes, adequate land was acquired along with
original two-lane construction. The width of existing ROW is 60 m and length of the sub project is
19.800 km. Therefore, the impacts of the proposed project are limited because of the land acquisition
during two lane construction. The entire length of the project road runs through plain terrain and
passes across agricultural land and villages. The existing 2 lane pavement is rigid for the entire
stretch.
24. Description of Environment: The project road comprises a 19.8 km stretch on State Highway 18
commencing from Ujjain Dewas junction. It falls under the jurisdiction of Dewas District in the state
of Madhya Pradesh. The project area falls in the Malwa Plateau zone. The major soil group found in
the area is deep medium black soil. Soyabean, wheat and gram are the major crop of the area. The
rainfall in the district is approximately 1000 mm annually. The land use pattern in the sub-project
section is agricultural. The climate of the project area is characterized by hot dry summer, followed
by well distributed rainfall in monsoon and winter. There is no forest land involved in DBTPL. The
sub-project does not pass through any protected area. 1354 number of trees were coming in the
ROW of the project. No archaeological and historical monuments are located along the project road.
25. The main impacts envisaged due to various activities at the sub-project are summarised in the
paragraphs below:
26. Impact on Land Environment: The sub-project involves strengthening and widening of the
existing two to four/six lane bypass. The sub-project involves widening/reconstruction of existing
road within available ROW without any substantial land acquisition, impact on the physiography of
the area is not significant. During construction phase the topography at sub-project location will
9. Tube-well Permissions Commissioner,
Municipal Corporation,
Dewas
The tube wells are located on revenue land, which
are being utilised by DBTPL. DBTPL has taken
permissions for tube wells for drawing water for
construction purpose sample copies are attached as
Annexure VIII.
10. NOC for setting up
camp
Village Panchayat DBTPL has taken NOC from village panchayat for
setting up of camp with RMC and Crusher plant
(Annexure IX).
11. License for Explosives Joint Chief Controller of
Explosives
Central Circle office,
Agra, Government of
India
DBTPL has taken license for explosive transport,
storage and use from the licensing authority - Joint
Chief Controller of Explosives Central Circle
office, Agra (Annexure X)
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 15
change due to excavation of borrow areas, cuts and fills for project road and construction of project
related structures. Risk of contamination of soil exists from construction material and oil spills. The
impacts are temporary and are manageable with mitigation measures which are given in Section 16.
27. Impact on Water Resources: The sub project is not crossing any perennial river. Water resources
may be impacted near the construction camp. This can be minimized by proper handling of material
and proper disposal of sewage and proper erosion control. During the operation stage the leakage or
spillage from damaged vehicles or badly maintained vehicles may lead to contamination of water
bodies. EMP has been proposed to manage these impacts.
28. Impact on Air Quality: The setting up of camp including ready mix concrete plant, hot mix plant,
and crusher plant. Up-gradation works at sub-project stretch shall involve generation of dust and
release of other pollutants leading to the localised degradation of air quality. All the belt conveyors
are to be covered with canopy to control the dust pollution. Ready mix concrete plant to be well
equipped with the cartage filters. All aggregate stock yards are provided with water sprinkling
system. Mitigation measures are in place to manage these temporary impacts.
29. Impact on Noise Environment: Impact on noise environment is envisaged during both construction
and operation phases. During construction phase, noise is generated due to use of heavy equipment
and processing facilities. Adequate distance from sensitive sites is to be kept for controlling noise
disturbances.
30. Impact on Biological Environment: No National Park or Wildlife Sanctuary is located within
close proximity of the project road and there is no notified animal corridor/migration route is present
in the project area. No Protected / Reserve Forest are located along the project road. About 1354 trees
falling in revenue land were coming in the ROW expansion. Permission for transplanting these trees
has been obtained from respective authority. All the trees have been transplanted in a scientific
manner in the proposed ROW. No significant impacts on other flora and fauna are anticipated at the
sub-project. Necessary mitigation measures have been recommended where
construction/maintenance is proposed.
16. ENVIRONMENTAL MANAGEMENT PLANS
31. The sub-project does not require EIA as a statutory requirement. The project is being developed on
the existing ROW as far as possible. The sub-project has been implementing various mitigation
measures to minimize risk to environment. A project specific Environment Management Plan (EMP)
has been formulated and proposed to the developer as part of due diligence which consists of a set of
mitigation measures; monitoring and institutional measures applicable to construction and operation
stages of the project. The EMP also defines roles and responsibilities of various parties.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 16
32. The proposed EMP has been formulated on the on the basis of documents/information shared by
developer and site visit. The status of EMP implementation during construction phase is also given in
Table 3 on the basis of site visit observations. The EMP proposed for operation phase is given in
Table 4.
17. HEALTH AND SAFETY
33. DBTPL has deployed route patrolling vehicles, etc with requisite staff for incident management as
per Concession Agreement for maintenance of the project highway during construction and ensures
the project highway is in trafficable & motorable condition.
34. The Traffic Safety Arrangements during execution of works is being carried out by the Contractor
for safe movement of vehicles on the project highway. The Contractor has provided sufficient road
signs, temporary barriers, gunny bags filled with soil with reflective stickers etc. at the construction
sites.
35. DBTPL follows the safety guidelines and conducts safety training programmes for staff at site
including labour. The records for the same are maintained at the sub-project site. Sample copies of
toll box meetings, safety training programmes and on job safety awareness are attached as Annexure
XI, XII and XIII.
36. First aid boxes and fire fighting systems are maintained at sub-project camp sites.
37. DBTPL has adequate institutional arrangement to look after HSE related aspects. The organizational
chart for HSE is given as Annexure XIV.
38. Safety Consultant has been appointed for the sub-project as per Article 18 of the Concession
Agreement. The consultant conducts road safety audit on periodic basis. Sample report is attached as
Annexure XV. DBTPL submits compliance report to the audit observations to the Safety Consultant
(Annexure XVI).
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 17
Table 3: Proposed EMP and its Implementation status during Construction Phase at DBTPL
Impact/Issues EMP Responsibility Monitoring
indicators
Status of EMP Implementation
Impact on air environment due
to fugitive emissions and dust
generation due to construction
activities
All the vehicles deployed for
construction of the project will have to
keep “Pollution under Control” (PUC) certificates.
DG sets will also emit air pollutants in
the area during construction period. The
emission generated during construction
will be temporary and localized in
nature.
Vehicles carrying construction material
shall be covered to avoid spilling.
Paved approach roads to be maintained
Water sprinkling in dust prone areas
Personal protective equipment for
workers
RMC and Batching plants to possess
valid CTO
DBTPL Dust pollution
measurements/obser
vations or complaint
of locals
Compliance report
submission to
MPPCB
Approach roads in project area are
paved and water sprinkling is being
done at the sub-project to control
dust
Vehicles have restricted speed in
camp area
All vehicles used for DBTPL have
valid pollution control certificate
Workers are provided with PPEs
Camp site is located away from
settlements
Plants at camp are having CTO
from Madhya Pradesh Pollution
Control Board and compliance to
the conditions of PCB is being
submitted by DBTPL on regular
basis (Sample copy attached as
Annexure XVII).
RMC plant is equipped with dust
collector to control emissions
DBTPL has informed during site
visit that the MP PCB officials
regularly visit project site
Noise from construction
vehicles, machinery and
equipment
Construction equipment to be properly
maintained.
Noisy construction activity to be avoided
during night and close to sensitive
receptors
Traffic management and re-routing during
construction to avoid the accumulation of
noise
Honking restrictions on project vehicles
PPEs to be provided to workers
DBTPL; Contractor;
Sub contractor
Complaint from locals Equipment and vehicles are
properly maintained at site
Vehicles have restricted speed in
camp area
Workers are provided with PPEs
Training is provided to staff
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 18
Impact/Issues EMP Responsibility Monitoring
indicators
Status of EMP Implementation
Borrow Area Management Topsoil to be stockpiled and protected for
use
Borrow areas to be rehabilitated by
levelling or converted to pond in
consultation with the owner
DBTPL; Contractor Rehabilitation records To be done after project construction is
over
Contamination of soil / water Vehicles and equipment to be maintained
at project site
Fuel storage to be kept away from
drainage and on impervious surface
Waste oil to be stored appropriately and
disposed to authorized vendors
Water to be sourced from authorised /
permitted sources
DBTPL; Contractor Records of fuel and
waste oil to be
maintained
During site visit it is informed by
the developer that fuel is not stored
at camp site, as there if a fuelling
station opposite camp site and fuel
is taken from the fuelling station as
per requirement.
Waste oil to be sold to SPCB
authorised vendors as and when
required
Water is sourced from authorised
suppliers through tankers
Impact on water resources Storm water drains in the entire stretch
except service roads at DBTPL is
proposed
Runoff drainage provided at service roads,
flyovers etc.
Rain water harvesting pits are proposed at
culverts
DBTPL Records and
maintenance of
drainage and rain
water harvesting pits
Drainage system is under
construction
Rain water harvesting pits will be
constructed once the alignment is
complete
Avenue trees
1354 number of trees on revenue land
were coming in the ROW up gradation.
Permission was taken by DBTPL for
shifting all trees in the proposed ROW
All 1354 trees have been transplanted in a
scientific manner.
Avenue plants are proposed along the
project stretches as per IRC-SP-21:2011.
Approximately 5000 trees are planned to
be planted in avenue plantation, which
will begin in next monsoon.
DBTPL Records of trees
planted and
transplantation to
be maintained at
site
Survival records to
be maintained at
site
Tree transplantation permissions
were obtained
Videography of the tree shifting
activity was done by developer
Survival records are maintained at
site. In first six months the survival
record of implanted trees was about
90%.
Avenue plantation will begin from
the year 2020.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 19
Impact/Issues EMP Responsibility Monitoring
indicators
Status of EMP Implementation
The avenue plants proposed to be planted
on either side of the road in two rows.
Median Plantation Median planation to be done as per IRC.
Approximately 667 plants will be planted every
km.
DBTPL Survival records to be
maintained at site
Median plantation has been done
on 50% of stretch.
Median plantation is being
maintained at site
Site for storage and
construction camp
Camp to be maintained at minimum
distance of 500 m from habitation
Emergency response plan will be in place
towards meeting unforeseen
emergencies.
Workers to be trained for handling
materials
DBTPL; Contractor Training records to be
maintained at site
Camp site is away from habitation
Storage is done at designated areas,
with markings and signboards.
Emergency response plan is in
place for DBTPL
Trainings are imparted to labour
and staff and records maintained at
site
Sewerage and solid waste
disposal
For sewage disposal, septic tanks with
soak pits will be provided at campsites.
Proper sanitation facilities at the camp to
be provided.
Salvage material/ demolition wastes will
be reused to the possible extent in
embankments, shoulders, slopes,
approach roads and temporary campsites
DBTPL; Contractor On site observation Septic tanks with soak pits are
provided at site.
Proper toilets are provided at camp.
Camp haul roads are maintained
with salvage material / demolition
wastes
There is no labour camp at site, the
labour are staying in rented
accommodation and commuting
from villages nearby
Traffic management & safety Secure traffic control during construction
Safety measures to be undertaken by
installing road signs and markings for
safe and smooth movement of traffic.
DBTPL; Contractor On site observations;
accident incident
records
Contractor has provided sufficient
road signs, temporary barriers,
gunny bags filled with soil with
reflective stickers etc. at the
construction sites
All traffic diversions are approved.
Diversion Plan is attached as
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 20
Impact/Issues EMP Responsibility Monitoring
indicators
Status of EMP Implementation
Annexure XVIII
Sufficient light arrangement has
been done at construction zone and
diverted areas
Marshalls are deployed 24 *6 at all
junctions for traffic management.
Concessionaire has deployed route
patrolling vehicles, etc with
requisite crew for incident
management as per Concession
Agreement for maintenance of the
project highway during
construction and ensures the
project highway is in trafficable &
motorable condition
Occupational Health and
Safety Labourers shall be equipped with
proper safety gears like helmets, gloves
and gum boots.
Training of workers to be ensured
Drinking water to be supplied to
workers
DBTPL; Contractor Training records to
be maintained at site All workers and labourers are
equipped with appropriate PPE’s
HSE induction trainings are
organized for labour and staff.
RO plant is installed at the camp
site for drinking water for staff
and workers
Table 4: Proposed EMP for Operation of DBTPL
Impact/Issues EMP Responsibility Monitoring indicators
Noise Multi layered plantation to serve as mitigation option
for operation phase
Effective traffic management and good road condition
shall be maintained to reduce the noise level
Speed limitation and honking restrictions may be
enforced near sensitive locations.
Create awareness in locals and drivers through
DBTPL On site observations
Records of safety week
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 21
Impact/Issues EMP Responsibility Monitoring indicators
programmes
Embankment protection Periodic maintenance of stabilizing measures at
embankments like turfing etc.
DBTPL On site checks & observations
Water logging Regular maintenance and cleaning of drains DBTPL On site checks & observations
Maintenance of Safety Traffic control measures to be enforced strictly
Monitor and ensure that all safety provisions included
in design and construction phase are properly
maintained
2 Highway patrol units for round the clock patrolling to
be available at site
One ambulance to be available at toll plaza
One tow-away facility for the break down vehicles
DBTPL Safety signage to be displayed and
maintained at site
Accident incident reports to be
maintained at site
Avenue / Median Plantation &
Maintenance Avenue plants are proposed along the project stretches as
per IRC-SP-21:2011. Approximately 5000 trees are
planned to be planted in avenue plantation, which will
begin in next monsoon.
The avenue plants proposed to be planted on either side of
the road in two rows.
Planted trees and shrubs in Avenue and Median
Plantation to be properly maintained
Tree survival list to be maintained for planation
effectiveness
DBTPL Records of trees planted and
transplantation to be maintained at
site
Survival records to be maintained
at site
Redressal of public grievances DBTPL shall maintain a complaint register at toll plaza
DBTPL shall define a mechanism to handle and manage
grievances raised by road users, project affected persons
and employees/workers including those of sub-
contractors.
DBTPL shall send copy of the register to Concessioning
Authority and Independent Engineer
DBTPL Complaint Record register
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 22
18. GRIEVANCE REDRESSAL MECHANISM
39. Developer has confirmed that they are maintaining a register at site for grievances. Record of
any grievance or demand received from locals is maintained at the site office.
40. Redressal of Public Grievances will be done during operation phase as per Article 46 of the
Concession Agreement. The Concessionaire has to maintain complaint register at the toll
plaza for recording public grievances. The complaint register will be shared with the
Concessioning Authority every 7 days for review.
41. The Grievance Redress Mechanism should outline mechanism to handle and manage
grievances raised by road users, project affected persons and employees/workers including
those of sub-contractors.
19. ENVIRONMENTAL SENSITIVITY
42. The environmental sensitivity of DBTPL has been assessed by reviewing various documents,
supplemented by field visit and consultation with the developer.
43. The environmental sensitivity assessment is given below:
The sub-project is being developed on the existing right of way. At certain places
(vehicle under pass, flyover and administrative block for toll plaza) additional land is
required. Developer has informed that this additional land requirement for toll plaza
building is 1.2 Ha, which is private land and acquisition is in process.
The sub-project sites are not located in any protected area like wildlife sanctuary /
national park or in close proximity of any eco-sensitive area.
During site visit and as per discussions with the sub-project staff, it was informed that
no wild animals are sighted in and around the sub-project area.
No forest area is getting affected due to the sub-project.
1354 trees were coming in the ROW, which are shifted to the proposed ROW.
As informed by the concessionaire, no important cultural or heritage sites are getting
affected due to the sub-project.
The sub-project has the necessary approvals and permits from regulatory authorities.
The impacts of the sub-project are temporary in nature and are manageable with
EMPs.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 23
20. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST
44. The sub - project does not involve any prohibited activity as per the Prohibited Investment
Activities List (PIAL) of ADB.
21. CATEGORIZATION OF SUB-PROJECT
45. The sub-project can be classified as Category B based upon ADB’s EA requirements as per their Safeguard Policy Statement (2009). This classification is based on the review of the
available documents and site visit with respect to the environmental sensitivity due to project
activities.
22. SITE VISIT OBSERVATIONS
46. A site visit was undertaken by IIFCL’s Environmental and Social Safeguard Specialists and
Social Safeguard Consultant on 15th October 2019. The site visit was undertaken to review the
implementation of the project’s environmental and social safeguards. During the site visit, following staff were mainly consulted regarding environmental safeguards related measures
implemented at the project site:
(a) Mr N Ramesh Narendra, Team Leader
(b) Mr T Subramanyam, Team Leader, IJM (India) Infrastructure Ltd.
(c) Mr Mahesh Chandra, Senior Vice President, IJM (India) Infrastructure Ltd.
(d) Mr Shekh Josaif Hussain, EHS Officer
47. The sub-project is under construction and more than 83% works are complete at the site. Based
on the discussions with above mentioned officials and visit, the site observations are given below:
The sub-project has obtained necessary clearances/permits from the State Pollution
Control Board and other regulatory organizations and is complying with the
reporting / monitoring requirements.
The sub-project is involves strengthening and widening of highway in the existing
ROW.
Tree shifting is complete at site. The trees are maintained and in the initial six
months survival of 90% was recorded. Avenue plantation will begin during
monsoon of 2020. Median plantation in about 50% of the stretch is complete and is
being maintained. Developer has been informed to keep a record of plantations and
survival rate.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 24
Utility shifting at site is almost complete. 100% of land is available for highway
up-gradation.
The workers and staff at the site were seen wearing personal protective equipment
such as helmets, jackets, boots, gloves etc.
Regulatory signs, warning signs and direction signs were available at all relevant
places at site.
Traffic marshals could be seen at all junctions.
There is one camp site at the sub-project.
There is no labour camp at sub project. Developer has informed that most labour is
local and are commuting from nearby villages. The other workers are also housed
in rented accommodations. Good standards of health and hygiene were maintained
at camp. Dust bins were placed at different locations. Toilets were available at the
camp site for staff with continuous water supply. Good housekeeping was
maintained at the site.
Pantry is being run at the camp site.
All waste water being generated at the sub-project premises is disposed in septic
tanks/soak pits.
RO water purifier of large capacity is available at camp for drinking water purpose.
Adequate EHS staff was present at the site and understood their commitments.
On discussions with the site staff, it was observed that tool box talk, safety
induction trainings are done for labour as well as staff.
Vehicle movement in the administrative premises was very limited and control by
Security at entrance of camp.
No oil spillage was observed at the site. Developer has informed that they are not
storing fuel at the camp site as a fuelling station is available across the road and
fuel is procured as and when required.
Concrete demolition waste is kept at secured and identified location and is being
utilized for low laying area development and leveling purpose by local community.
The permits and NOCs required for the project are in place.
Fire extinguishers and first aid kits were available at camp site.
Emergency contact numbers have been displayed at appropriate locations.
Records of safety trainings, mock drills and various inspections/audits are
maintained at site office.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 25
48. The site visit photographs are given in Photoplate - I.
23. CONCLUSIONS AND RECOMMENDATIONS
49. It is concluded on the basis of review of the available information, reconnaissance site visit and
interaction with sub-project staff it can be concluded that the concessionaire DBTPL is
complying with the requirements as per the national and state guidelines and regulations. The
19.8 km road strengthening and widening project in the State of Madhya Pradesh is unlikely to
pose any adverse environmental risks given the nature of the activities.
50. There are no legally protected areas, cultural heritage sites and forest land located within and/or
in close proximity to the sub-project. However, the sub-project activities have reversible
environmental impacts which have been managed.
51. Based upon the available documents and site visit, it is concluded that the concessionaire has
undertaken adequate environmental safeguard measures. The conclusions for the sub-project are
given below:
The sub-project has been planned as per the National and State Government
requirement and not in anticipation to ADB operation.
The project site is not located in an ecologically sensitive area.
The sub-project is being developed in the existing ROW and some additional land
is being acquired for administrative block, flyovers etc. which is agriculture land.
The project does not involve diversion of forest land. However, approximately
1354 trees were coming in ROW which have been shifted to proposed ROW. The
concessionaire will be doing avenue and median plantation on the entire stretch.
The sub-project has the required national and local level permits and approvals for
project implementation.
Concessionaire has confirmed continuous compliance with the terms and conditions
stipulated while according statutory clearances /approvals /consents. Concessionaire
was implementing environment management measures at site and a structured EMP
has been proposed for the sub project. The EMP implementation will be monitored by
IIFCL.
The institutional arrangement available for the implementation of environment, health
& safety appears to be adequate.
The concessionaire is maintaining adequate safety at the site. The EMPs will
minimize any significant negative impact on environment.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 26
During site visit and discussion with the project developer, the implementation of
management measures was found to be adequate.
After approval from the ADB the ESDDR will be uploaded on website for public
disclosure.
52. Based on the site visit and due diligence findings, it can be deduced that the sub-project has no
significant environmental safeguard issues. The sub-project, therefore, does not appear to
involve any kind of reputational risk to ADB funding on environmental safeguards.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 27
DUE DILIGENCE ON SOCIAL SAFEGUARDS
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 28
24. PURPOSE OF THE SOCIAL SAFEGUARDS DUE DILIGENCE
53. The Social Safeguards Due Diligence Report (SSDDR) has been carried out by India
Infrastructure Finance Company Limited (IIFCL) in consultation with the Concessionaire, Dewas
Bypass Tollway Pvt. Ltd. (DBTPL) to assess the Social safeguards compliances of the project
with the applicable National Policies. The report has been prepared as per the
documents/information received from the concessionaire and subsequent to the site visit on 15th
October 2019. The information given in the SSDDR is agreed and confirmed by the
Concessionaire.
25. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST
54. The sub project does not involve any prohibited activity as per the Prohibited Investment
Activities List (PIAL) of ADB.
26. OBJECTIVE OF SOCIAL SAFEGUARDS DUE DILIGENCE
55. Social Safeguards due diligence study is carried out to assess the social safeguards monitoring
compliance status of the project as per the applicable National policies/procedures as observed
during the site visit as well as the information received. The main objective of this Social
Safeguard Due Diligence Report (SSDDR) is:
To assess the likely social impacts and its minimization/mitigation majors adopted
for the project with respect to land acquisition, compensation , Indigenous people
affected, involuntary resettlement and common properties resources affected, if any,
in terms of displacement, loss of incomes, and community links:
To ascertain, in case of any adverse impact, if appropriate mitigation measures have
been taken during the project planning, designing and frameworks established for
carrying out safeguard measures during the construction stage to minimize and
mitigate such if any adverse impacts.
27. APPROACH AND METHODOLOGY
56. The Social safeguard due diligence study for Dewas Bypass Tollways Pvt Ltd (DBTPL) has been
carried out after reviewing the documents made available by the subproject developer. On site
visit to the project location by the Environment and Social Safeguards Specialist and Social
Consultant, discussion with the project developer and various permits and approvals relating to
the project to understand the salient features of the project and social concerns. The following
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 29
documents/Reports/Licenses/permits and notifications were referred in order to prepare the
Social Safeguard Due Diligence Report:
Project Information Memorandum (PIM);
Right of Way (RoW) handover letter
Concession Agreement
Lender’s Independent Engineer (LIE) Reports Independent Engineer Report
Labour License & insurance
28. SOCIAL IMPACT OF THE PROJECT
27.1 Land Acquisition in the Project
57. Land acquisition is not in the scope of the project developer and it is under the purview of
the Concessioning Authority, Madhya Pradesh Road Development Corporation (MPRDC).
Land acquisition for the project DBTPL for 4/6-laning of Dewas Bypass from Km. 0+000
(Ujjain-Dews Junction) to Km. 19+800 (Total Length 19.800) in the state of Madhya
Pradesh on Build, Operate and Transfer (BOT) basis has been completed by MPRDC.
During the discussion and subsequent to the mail received from the project developer it was
informed that the land acquisition including the present right of way was acquired by the
authority MPRDC in the year 2009.
58. As per provision of the Concession Agreement, 100% the Right of Way (RoW)
encumbrance free for 4/6 laning of Dewas Bypass to the extent of 60m has been handed over
to the Concessionaire by MPRDC. At the time of two laning of the project, the land was
acquired in the year 2009 and handed over in one phase to the project developer after
awarding the work in 2017. The RoW hand over letter is attached as Annexure XIX.
59. During the discussion it was told that the total land including the present right of way was
acquired at the time of two laning of project and the additional right of way for
accommodating the future widening of the existing road for 4/6 laning was kept on median.
As per the information provided by the project developer the purpose wise land for 4/6
laning of Dewas Bypass is given in Table 5:
Table 5: Status of Land available at DBTPL
Sl. No. Purpose Land in Hectare (Ha.)
1. Widening of the existing road for 4/6 laning 118.8
2. Realignment Nil
3. Toll Plaza & Truck lay bye 1.20
Total 120
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 30
60. Land acquisition process was initiated prior to IIFCL’s involvement and not in anticipation of
ADB financing.
27.2 Impact on Structure
61. The sub-project stretch falls in Dewas district in the state of Madhya Pradesh. The entire section
of project road is passing through plain terrain. As informed by the concessionaire and noted
during the site visit, that no structure is getting affected due to the project.
27.3 Rehabilitation and Resettlement impact in the sub-project
62. During the site visit it was informed that there was no involuntary resettlement because of land
acquisition for the project. Further during the site visit it was observed that there was no
rehabilitation and resettlement in the project.
27.4 Impact on Indigenous people
63. As information provided by the concessionaire the project does not disturb indigenous people in
the project and does not have adverse impact or create any threat to the survival of any
indigenous community along the alignment, hence no indigenous people affected in this sub-
project.
29. GREIVANCE REDRESSAL MECHANISM FOR THE SUB-PROJECT
64. The Grievance Redressal Register is maintained at project site to ensure that any affected person’s grievances are adequately addressed and to facilitate timely project implementation. During the
site visit it was observed that the project authority has formed their own institutional
arrangements to deal with complaints on site resolve of the issues concerns.
30. EMPLOYMENT GENERATION
65. As informed by the concessionaire, the project land acquisition was completed during 2 to 4-
laning of project in the year 2009, so the project does not impact the livelihood of the local
people. It has been confirmed by the concessionaire that employment opportunities are being
provided to the local people for various unskilled and semi-skilled activities like security guards
and office assistants, drivers.
66. During the discussions it was informed that the employment opportunity is being given to more
than 70 local people belongs to the nearby areas during the project construction period. Further it
was also informed that during the operation of toll plaza as much as possible local people will be
given employment opportunity at toll plaza location.
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 31
31. THE COMMUNITY ENGAGEMENT ACTIVITIES
67. As information provided by the concessionaire, to reach the local people, DBTPL has under taken
few of community development activates to reach the local people during the construction stage
of the project. The subproject developer celebrated its road safety week, blood donation camp,
free medical check-up camp, health and hygiene awareness camps has also been under taken
under community development initiatives as per the demands made by the local community /
nearby village/Panchayats.
32. LABOUR LICENSE OBTAINED BY THE SUBPROJECT DEVELOPER
68. The Labour license has been granted to the subproject developer Dewas Bypass Tollway Pvt.
Ltd. (DBTPL) under Section 12 (1) of the Contract Labour (Regulation and Abolition), Act,
1970. The Labour Commissioner, Government of Madhya Pradesh, Dewas has issued the
license for construction of Dewas Bypass. As per the labour licenses the subproject developer
can employ as contract labour in the establishment shall not, on any day, exceed 300 Nos. The
labour license is attached as Annexure VI.
33. DISCLOSURE
69. After approval from the ADB, the report will be uploaded for public disclosure in ADB and
IIFCL’s website.
34. SITE VISIT OBSERVATION
70. A site visit was undertaken by IIFCL’s Environment and Social Safeguard Specialists and Social
Safeguards Consultant on15th October, 2019. The site visit was undertaken to review the
implementation of the project’s environmental and social safeguards parameters at the project
site. . The sub-project at the time of site visit was in the stage of construction, and more than 83%
of construction activity was completed and the Concessionaire is hopeful to achieve the COD in
the month of December 2019.
71. During the site visit and discussions with subproject developer it was observed/noted that :
The sub-project has been prepared by Madhya Pradesh Road Development Corporation
Ltd. (MPRDC) as per its own funding requirement and not anticipation to ADB
operation;
Land acquisition process was initiated and completed prior to IIFCL’s involvement and not in anticipation of ADB financing.;
Environment and Social Due Diligence Report Dewas Bypass Tollway Private Limited
ESDDR NO. IIFCL/ESMU/ADB/2019/115/V2 32
Land acquisition to the extent of 60m Right of Way (RoW) for 6-laning of this project
was completed during 2 laning of project in the year 2009.
There is no Rehabilitation and Resettlement in the project.
The subproject do not have any indigenous people in the project;
Construction workers are provided with ready access to on- or off-site health care check-
up facilities and are being provided with first aid facilities for minor injuries;
As informed during the site visit it was confirmed that no fatal accident happened in the
project till date.
Emergency contact numbers have been displayed at the prominent places in project site.
During the site visit it was observed that, workers and staffs at the site were seen wearing
personal protective equipment such as helmets, jackets, boots, gloves etc.
As informed by the project developer, after discussions with the local people, the
affected cultural properties are being relocated by the concessionaire;
Local labours are being engaged in the construction activities for skilled as well as
unskilled activities;
It seems that the sub-project does not appear to involve reputational risk to Asian
Development Bank funding on social safeguards and recommended for funding under
the proposed project.
Concessionaire has undertaken community development activities based on the demands
raised by the local people.
72. Based on the site visits observations and desk review, it appears that the sub-project have no
negative significant social safeguard issue.
Collector Court — District Dewas (M.P.)
Letter no./1529/Reader/2017 Dewas, Dated 22-
■-■ ugust-2017
Case no. 09/v-69/2016-2017
:: Permission Letter::
Divisional Manger, Madhya Pradesh Road Development Corporation Limited
through its letter no. 2406/M.P.R.D.C./Dewas Bypass/ R.O.D./R.O.B. 2017 Ujjain,
dated 03-08-2017, stating that under B.O.T. scheme on Dewas Bypass — 4 lane/ 6
lane trees obstructing the road is to be implanted, at present about 1300 tress are
marked to be implanted from 5 to 10 years. Out of which for 495 trees implantation
work is under progress and for 805 trees implantation work is to be done. So
permission for implantation of these marked 1300 trees should be given.
Hence under Madhya Pradesh Land Revenue Code 1959, under section 240 as
stated above permission for implantation of 1300 trees is given with the condition
that during implantation Madhya Pradesh Road Development Corporation Ujjain will
be totally responsible for life of trees (keep the trees alive).
As stated above during implantation Madhya Pradesh Road Development
Corporation Ujjain will be totally responsible to pay the claim amount for any kind of
life/animal loss.
Sd/-
Collector
Distrcit — Dewas (M.P.)
Pg. no./1530/Reader/2017 Dewas, dated 22-August-2017
cc to :-
Divisional manager, Madhya Pradesh Road Development Corporation Limited,
Ujjain for information and compliance.
((c11't-1,ittM 22-31 4 Ikcf-2017
cl:bIZ1DOraT 3u.AcT c i 3n7 Tct -11z1G11ef I 7 r77, 745
Aill=111711111MWSRPW... •
152.9 (091cti, /t---R72017
, (1T.g.)
•
22731.77U-2017
)77 O /31-62/ 201
3rd u[
ei d-alrulfra citEr,TIF210,2T 6Sch ftctUT D-UTF 3u6-1 RI I:R. cipd-110 240 6 /W.A. t.ft.N/acuzi (sIle-1 1-11e-1/3117.311.D../31T7.3nt. 2 0 1 7 .3uula1 RGiict) 03-8-20 1 7 T 3FM-a W. ris[a. War ole-fi ac 112-1 c-(ie-1 1-1R-1-4-1/6 c)0-1 ca IrEm q491-
5 t 1 o a®f c1ct) ri-&:fraciuT 1 3 0 0 q4i1. 4 RI Ge. iRt)c-1 %-aTT 1e-11 ,Dzidl 495 ce-4 1 a qui MT 5 Van. Q'a 21"31 . 805 40 Th-T4 %TIT uila11 1 1-6ircbc1 1 3000 .411 01) Welt LIul
M). v11 1
3f.ff: TM. ca21. 1I eILIRcI Zi.r(7,-dT 1959, aTTZT 240, c1 6c-1 .3c1z-115Z11Z 1 300 rt16-04c1 11ce-11a 1-1 0 1(wi7.1k.11217;1.) E 3fITA 7Trat
11&-.112 1-1u1 17) $i NRicdcii wto Nfta. zum- 7-1----of dcd Trrzr - ei ci-armita 7i121T1t21. ei $75 Ucl-iIZiftuTai 3,1 GI MT I I
3ad Cel I ) 1-Tur eit-C11c'VV) t71a Utig e..1 ITT 1--d:r TTNT T.Ed.7 ct).,Z) E 7.1--Rkuf 3mz ,i1r 3 ccH arc zr- a-rr-JiTar A*-IM,UTEZT;a2T rc1c1-)1 fturef 34 al 4 z c)111
! 536 //2o17
gra-P6-ft !;it Erm. , Trviii.-st
Consent Order Regional office
M.P. Pollt.ition Control Board
Devoe::
Tole 07272251170
CTE-Fresh
VALID UP TO: CTE
CONSENT NO: **"
GREEN-SMALL
PCB ID: 111548
NO: /MPPCB/DEW
M/s. I,—( Ind ,e) Infrastructure Ltd,
Survey No. 384/2/2,403/2/2,405/2/2,384/4/4,405/3,384/2/3 & 403/2/1, Shankarghad,
De., Dist : Dewas,
Subject: Grant of Consent to Establish under section 25 Of the Water (Prevention & Control of Pollution) Act,1974 under section 21 of the Air (Prevention & Control of Pollution) Act,1981
Rol-. Your Consent to Establish Application Receipt N.. 321949 Dt. 18/05/2017.
Without prejudice tO the powers of this Board under section 25 of the Water (Prevention & Control of Pollution) Aet,1974 under section 21 of the Air (Prevention & Control of Pollution) Act,1981 and without reducing your responsibilities under the said
in any way, this is to inform you that this Board grants Consent to Establish for setting up of an industrial plant/activities at
• nkarghad, Dewas, Phone No. 7702200185
SUBJECT TO THE FOLLOWING CONDITIONS
Location: 384/2/2,403/2/2,405/2/2,384/4/4,405/3,384/2/3 & 403/2/1, Shankarghad, Dewas, Contact N.. 7702200185
b. The capital investment in lakhs: Rs. 90
c. Product & Production Capacity:
Product
CTE Qty/y
RMC Plant
238200Mater cube/year
(Two lakh thirty eight thousand two hundred meter Cube per year)
The consent (For operation) as required shall be granted to your industry after fulfillment of all the Conditions mentioned
above. For this purpose you shall have to make an application to this Board in the prescribed proforma at least two months before
the expected date of commissioning of your Industry. TOO applicant shall not operate the unit without obtaining consent for
operation from the Board and shall not bring In to use any out let for the discharge of effluent and gaseous emission.
Enclosures:-
* C
•
onditions under Water Act
* C
•
onditions under Air Act
* G
•
eneral conditions
e seelthaftom LIDALR ANNEX , NEAR BIMA NAGAR , VIJAY NAGAR , INDORE - 452010 , MADHYA PRADESH SS g MILIT Regional Officer
e-Signed On 31/05/2017 16:39:15 (Organic Authentication on AADHAR from UIDAI Server)
PvitaNy Sign with Aulhatar TPAV # U2DM7D1J6D
Consent No:CTE-45626,Validity:17/05/2018, Outward No: 10202,31/05/2017, TPAV # U2DM7D1J6D
cPSIgnaci (Physical Slenatare NOT P.,,„.: 1 /5 NI ,
Consent Order
To'.: 07272251170
CONDITIONS PERTAINING TO WATER (PREVENTION & CONTROL OF POLLUTION) ACT 1974 :-
1. The daily quantity of trade effluent at out fall of the unit shall not exceed 0.000 KUday, and the daily quantity of sewage
at out fall of the unit shall not exceed 1.000 KL/day
2. Trade Effluent Treatment: -
The applicant shelh provide comprehensive effluent treatment system as per the proposal submitted to the Board and
maintain the same properly to achieve following standards -
0H Betweer, 5.5 — 9.0 TDS NOt exceed 2100 r../.
Suspended Souris Not exceed 100 mail. 1000 mu/l .
BOD 3 Deye 270C Not exceed 30
COD Not exceed 250
10
For other parameters general standards of discharge as notified under EP Act 1986 shall be applicable.
3. Sewage Treatment The applicant Shall provide comprehensive sewage treatment system as per the proposal submitted
the Board and maintain the same properly to achieve following standards -
,—
1.1M11.11111111111 )! WC : 68.000 VVWG : 1.000 1 Domestic Purpose 2. 000 1.000
Waite: Source .1
Borew.,,
Borewo,
2 Mnrg Process 66.000 0.000
4. The effluent shall be treated up to prescribed Standards and reuse In the process, for cooling and for green belt
devolvement/gardening within premises. Hence zero discharge condition shall be practiced. In no case treated effluent shall
be discharged outside of industry/unit premises.
5. Water meter preferably electromagnetic/ultrasonic type with digital flow recording facilities shall be installed separately
for category wise consumption of water as per Water (Prevention and Control of Pollution) Cass Act 1977 For Industrial
cooling/boiler feed, mine spray, process & domestic purposes and data shall be submitted online through XGN monthly
Cr patrak/staternents. The industry/unit shall also monitor the treated wastewater flow and report the same online through
monthly patrak/statements.
6. Any change in production capacity, process, raw material used etc. and for any enhancement of the above prior
permission of the Board shall be obtained. All authorized discharges shall be consistent with terms and conditions of this
consent. Facility expansions, production increases or process modifications which result new or increased discharges of
pollutants must be reported by submission of a fresh consent application for prior permission of the Board
7. All treatment/control facilities/systems installed or used by the applicant shall be regularly maintained In good working
order and operate effectively/efficiently to achieve compliance of the terms and conditions or this consent
8. The Consent does not authorize or approve the Construction of any physical structures or facilities or the undertaking of
any work in any water CourSe or within its high flood level (HFL) area
9. The specific effluent limitations and pollution control systems applicable to the discharge permitted herein are set forth as
above conditions.
10. Compilation of Monitoring '
i. Samples and measurements taken to meet the monitoring requirements specified above shall be representative of the
volume and nature of monitored discharge.
ii. Following promulgation of guidelines establishing test procedures for the analysis of pollutants, all sampling and
analytical methods used to meet the monitoring requirements specified above shall conform to such guidelines unless
otherwise specified sampling and analytical methods shall conform to the latest edition of the Indian Standard specifications
and where it is not specified the guidelines as per standard methods for the examination or Water and Waste latest edition of
Consent No:CTE-45626,Validity:17/05/2018, Outward No: 10202,31/05/2017, TPAV # U2DM7D1J6D
a -Sigrieb (Physical Signature NOT reguires) Page: 2 /5 111 I
0H Between 5.5 — 9.0
Suspended SOl,ds Not exceed 100
BOD 3 D., 27° C N. exceed 100 moll.
COD Not exceed 250 rng/i
Oe end grease Not exceed 10 rag/.
•
Consent Order Regional office
Dewey
Tc,le : 07272251170
,.../#'4•000"%esior -esso"ftssiegoft...... -.6110keisolfiis.r
the American Public Health Association, New York U.S.A. shall be used.
The applicant shall take samples and measurement to meet the monthly requirements specified above and report online
through XGN the same to the Board.
11. Recording of Monitoring -
I. The applicant shall make and maintain online records of all information resulting From monitoring activities by this
Consent.
ii. The applicant shall record for each measurement of samples taken pursuant to the requirements of this Consent as
followS:
(I) The date, exact place and time of sampling
(II) The dates on which analysis were performed
(iii)Who performed the analysis?
(iv)The analytical techniques or methods used and
(v)The result of all required analysis
If the applicant monitors any Pollutant more frequently as is by this Consent he shell include the results of such
monitoring in the calculation and reporting or values required in the discharge monitoring reports which may be prescribed
by the Board. Such increased frequency shall be Indicated on the Discharge Monitoring Report Form.
iv. The applicant shall retain for a minimum of 3 years all records of monitoring activities including all records of
Calibration and maintenance of instrumentation and original strip chart regarding continuous monitoring instrumentation.
The period of retention shall be extended during the course of any unresolved litigation regarding the discharge of
pollutants by the applicant or when requested by Central or State Board or the court.
12. Reporting of Monitoring Results: -
Monitoring Information required by this Consent shall be summarized and reported by submitting a Discharge Monitoring
report on line to the Board.
13. Limitation of discharge of oil Hazardous Substance in harmful quantities: -
The applicant shall not discharge oil or other hazardous substances in quantities defined as harmful in relevant regulations
into natural water course. Nothing In this Consent shall be deemed to preclude the institution of any legal action nor relive
the applicant From any responsibilities, liabilities, or penalties to which the applicant is or may be subject to clauses.
14. Limitation of visible floating solids and foam:
During the period beginning date of issuance the applicant shall not discharge floating solids or visible Foam.
15. Disposal of Collected Sol id -
All hazardous waste/sludge shall be disposed of as per the Authorization issued under Hazd & other waste Ru les 2016.
And/other Solids Sludges, dirt, slit or other pollutant separated from or resulting from treatment shall be disposed of in such
a manner as to prevent any pollutant from such materials from entering any such water Any live Fish, Shall fish or other
animal collected or trapped as a result of intake water screening or treatment may be returned to eaters body habitat.
16. Provision for Electric Power Failure -
The applicant shall assure to the consent issuing authority that tho applicant has installed or provided for an alternative
electric power source sufficient to operate all facilities utilized by the applicant to maintain compliance with the terms and
conditions of the Consent.
17. Prohibition of By pass system -
The diversion or by -pass of any discharge from facilities utilized by the applicant to maintain compliance with the terms
and conditions of this Consent in prohibited except
i. where unavoidable to prevent loss of life or severe property damage, or
ii. Where excessive storm drainage or run off would damage any facilities necessary for compliance with the terms and
conditions of this Consent. The applicant shall immediately notify the Consent issuing authorities in writing of each such
diversion or by -pass in accordance with the procedure specified above for reporting non -compliance.
18. Industry/Institute/mine management shall submit the information online through XGN in reference to compliance of
consent conditions.
Consent No: CTE-45626,Va I idity : 17/05/2018, Outward No: 10202,31/05/2017, TPAV # U2DM7 D1J6 D
„ -Signed (Physical Signature NOT requires) Page: 3 / 5 111 I
Consent Order RCIf_110 fl a I office
M.P. Pollution /
Regional
ootrol BoOrc.1
Dewar
T010 07272251170
CONDITIONS PERTAINING TO AIR (PREVENTION & CONTROL OF POLLUTION) ACT 1981 :-
1. The applicant Brig" l provide comprehensive air pollution control System consisting of control equipments as per the proposal
submitted to the Board with reference to generation of emission and Same shall be operated & maintained continuously so as to
achieve the level or pollutants to the following Standards: -
2 . Ambient air quality at the boundary of the industry/unit premises shall be monitored and reported to the Board regularly
on quarterly basis: The Ambient air quality norms are prescribed in M0EF gazette notification no. GSR/826(E). dated: 16/11/09. Some of the parameters are as follows:
a. Particulate Matter (less than 10 micron) - 100 pg/m3 (PM10 pg/m3 24 hrs. basis)
b. Particulate Matter (less than 2.5 micron) - 60 p0/0,3 (PM2.5 pg/r03 24 hrs. basis)
c. Sulphur Dioxide [S02] (24 hrs. Basis) - 80 ps/0,3
0. Nitrogen Oxides [Na<] (24 hrs. Basis) - 80 Ng/m3
e. Carbon Monoxide [CO] (8 hrs. Basis) 2000 pg/m3
3. The industry shall take adequate measures For control of noise level generated from industrial activities within the
premises less than 75 dB(A) during day time and 70 dB(A) during night time.
4. The Industry/unit shall make the necessary arrangements for control of the fugitive emission from any source of
erniSSion/section/activities.
5. All other fugitive emission sources such as leakages, seepages, Spillages etc shall be ensured to be plugged or sealed or
made airtight to avoid the public nuisance.
6. The industry/ unit shall ensure all necessary arrangements For control of odour nuisance from the industrial activities or
process within premises
7. All the internal roads shall be made pucca to control the fugitive emissions of particulate matter generated due to
transportation and internal movements. Good housekeeping practices shall be adopted to avoid leakages, seepages, spillages
etc..
Additional Air condition:-
1.Inclustr y shall take effective steps for extensive tree plantation within or around the Industry/unit premises for general
Improvement of environmental conditions.
2.Unit shall install appropriate air pollution control equipments at all points of emission at the earliest of the plant and shall
Ensure that these are always kept In running and in good working order all time.
3.The approach road should be properly developed and should be sprayed with water
Consent No:CTE-45626,Validity:17/05/2018, Outward No: 10202,31/05/2017, TPAV # U2DM7D1J6D
4 / 5 III I II
Consent Order ReglonAl orrice
M.P. Pollution Control Board
Dowas
Tele : 07272251170
■••■•■•04AMMIN.INOVIII
•■••••—•Norall"-•%.,e ■4111110111.werar....
"414.1gir-
GENERAL CONDITIONS:
2. The applicant shall allow the Starr or Madhya Pradesh Pollution Control Board and/or their authorized representative.
upon the representation of credentials:
a. To inspect raw material stock : manufacturing processes, reactors, premises etc to perform the functions or the
Board.
b. To enter upon the applicant's premises where an effluent source is located or in which any records are required to
be Kept under the terms and conditions of this Consent.
c. To have access at reasonable times to any records required to be kept under the terms and Conditions of thiS
Consent.
d. To inspect at reasonable times any monitoring equipment or monitoring method required in this Consent: or,
e. To sample at reasonable times any discharge or pollutants.
3. This consent/authorisation is transferable, in case of change of ownership/management and addresses of new
Owner/partner/Directors/proprietor should Immediately apply For the same.
4. The issuance of this Consent does not convey any property ri ghts in either real or personal property or any exclusive
(-or privileges, nor does it authorise any invasion of personal rights, nor any infringement of Central, State or local laws or
'egulatiOn5.
5 . Industry shall install separate electric metering arrangement for running of pollution control devices and this arrangement
shall be made in such Fashion that any non Functioning of pollution Control devices Shall immediately Stop electric Supply to
the production and shall remain tripped till such time unless the pollution control device/devices are made functional. The
record of electricity consumption For running of pollution control equipment shall be maintained and submitted to the Board
every month
6. This consent is granted in respect of Water pollution control Act 1974 or Air Pollution Control act, 1981 or Authorization
under the provisions of Hazardous and other Waste (Management & Transboundary movement) Rules 2016 onl y and does
not relate to any other Department/Agencies. License required from other Department/Agencies have to be obtained by the
unit separately and have to comply separately as per there Act / Rules.
7. Balance consent/authorisation fee, If any shall be recoverable by the Board even at a later date.
8. The applicant shall submit such information, forms and fees as required by the board not letter than 180 day prior to the
date of expiration of this consent/authorisation
9. Knowingly making any false statement for obtaining consent or compliance of consent conditions shall result In the
imposition of criminal penalties as provided under the section 42(g) of the Water Act or section 38 (g) of the Air Act
10. After notice and opportunity for the hearing , this consent may be modified, suspended or revoked by the Board in whole
3r In part during Its term for cause including, but not limited to, the Following
(a) Violation of any terms and conditions or this Consent.
(b) Obtaining this Consent by misrepresentation of failure to disclose fully all relevant Facts.
(c) A change in any Condition that requires temporary or permanent reduction or elimination of the authorized discharge.
11. On violation of any of the above -mentioned conditions the consent granted will automatically be taken as canceled and
necessary action will be initiated against the industry.
srtimfroaklili dl.R ANNEX , NEAR BIMA NAGAR , VUAY NAGAR , INDORE - 452010 , MADHYA PRADESH i S
WSW ( PRegionarbfficet) e-Signed On 31/05/2017 16:39:15
(Organic Authentication on AADHAR from UIDAI Server) Dlitaivr.i Sign w4h AChiktaf TPAV # U2DM7D1J6D
Consent No:CTE-45626,Validity:17/05/2018, Outward No: 10202,31/05/2017, TPAV # U2DM7D1J6D
Signed (Physical Signature NOT 5 / 5 ill I ■
O
Consent Order Regional office
NI.P. Pollution Control Board
Dewas
Tele : 07272-251170
GREEN-SMALL
CCA-Renewal Validity (A/W) 31/5/2020
CONSENT NO: ***
PCB ID: 1115481
)" &ik-ttn)5/2 )19
Consent No:AW-65109
To, The Occupier,
M/s. Ijm(India) Infrastructure Ltd,
Survey No.384/2/2,403/2/2,405/2/2,384/4/4,405/3,384/2/3 & 403/2/1, Shankarghad, Tehsil & District Dewas (M.P.)
Subject: Renewal of Consent under section 25 of the Water (Prevention & Control of Pollution) Act,I 974 under section 21 of the Air (Prevention & Control of Pollution) Act,1981
Ref: Your renewal of Consent Application Receipt No. 823746 Dt. 27/04/2019
With reference to your above application for renewal of consent has been considered under the aforesaid Acts and existing rules therein. The M. P. Pollution Control Board has agreed to renewed consent up to 31/5/2020, subject to the fulfillment of the terms & conditions, enclosed with this letter and.
SUBJECT TO THE FOLLOWING CONDITIONS :-
a. Location: Survey No.384/2/2,403/2/2,405/2/2,384/4/4,405/3,384/2/3 & 403/2/1, Shankarghad, Tehsil & District Dewas.
b. The capital investment in lakhs: Rs. 90
c. Product & Production Capacity:
S.No. Products Qty/y
1. RMC Plant 238200Meter cube/year (Two lakh thirty eight thousand two hundred meter cube per year)
Note:- For any change in above industry Mall obtain _fresh consent from the hoard .
The Validity of the consent is up to 31/05/2020 and has to be renewed before expiry of consent validity. Online application
through XGN with annual license fees inthisregard shall be submitted to this office 6 months before expiry of the consent/Authorization. Board reserves the right to amend/cancel / revoke the above condition in part or whole as and when required.
Enclosures:-
* Conditions under Water Act * Conditions under Air Act
* General conditions
e cue LEW
90 MTN'
D.O.Pro, for. we V* ...Law..
e-Signed On 09/05/2019 17:28:28 (Organic Authentication on AADHAR from UIDAI Server) TPAV # 947786ENF4
ALOK KUMAR JAIN
Regional Officer
This Certificate generated from xgnmp.nic. in are valid and does not require physical signatures. the certificate can be validated online from xgn.mp.nic.in using "TPAV" Number. Page: I 5