INDIA: Accelerating Infrastructure Investment Facility in ...

32
Environmental and Social Due Diligence Report Project Number: 47083-004 December 2019 INDIA: Accelerating Infrastructure Investment Facility in India Tranche 3 Mytrah Vayu (Krishna) Private Limited (Part 9 of 10) Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance Company Limited and the Asian Development Bank.

Transcript of INDIA: Accelerating Infrastructure Investment Facility in ...

Page 1: INDIA: Accelerating Infrastructure Investment Facility in ...

Environmental and Social Due Diligence Report

Project Number: 47083-004 December 2019

INDIA: Accelerating Infrastructure Investment

Facility in India – Tranche 3 Mytrah Vayu (Krishna) Private Limited (Part 9 of 10)

Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance

Company Limited and the Asian Development Bank.

Page 2: INDIA: Accelerating Infrastructure Investment Facility in ...

This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: INDIA: Accelerating Infrastructure Investment Facility in ...

s.no Stakeholder Stakeholder

Category

Objective of

Engagement

Stakeholder

Influence

Methods of Consultation and

Engagement

Frequency of

Consultations and

Engagement

requirements;

and

As per the need.

5. District

Administration

(Tehsildaar, SDO,

Patwari)

Primary

Stakeholder

Regular engagement

Participation in CSR

Activities

High Regular meetings and

participation in CSR events

Regular Meetings;

or

Monthly or as &

when required

6. Land Sellers and Land

Users

Primary

Stakeholder

To seek support if

required

Very Low Attendance in plant

functions/occasions, or seek

their support as and when

required

Meeting and

invitation in

events

7. Local Community Primary

Stakeholder

Managing and

ensuring

participation in CSR

activities.

As part of GRM.

Low Open Meetings,

Interactions with

community at Gram

Panchayat,

Sharing of CSR reports and

other documents, if

required, as part of the

disclosure mechanism and

the GRM; and

Involvement in CSR activities

As and when

required

8. Local Women Primary

Stakeholder

Managing and

ensuring

participation in CSR

activities.

Low Meetings specific to women

o o e ’s g oups

Sharing of CSR reports and

other documents, if

As and when

required

Page 4: INDIA: Accelerating Infrastructure Investment Facility in ...

s.no Stakeholder Stakeholder

Category

Objective of

Engagement

Stakeholder

Influence

Methods of Consultation and

Engagement

Frequency of

Consultations and

Engagement

As part of GRM. required, as part of the

disclosure mechanism and

the GRM; and

Involvement in CSR activities

9. Agricultural

Labourers

Primary

Stakeholder

For necessary

information

Managing and

ensuring

participation in CSR

activities.

As part of GRM.

Very

low/Non

Existent

Open Public Consultations

sharing of reports and other

documents as part of the

disclosure mechanism

(Provisioning of reports in

Hindi/local language, if

required)

Involvement in CSR activities

As and when

required

10. Vulnerable

Community (not

affected by land

acquisition)

Secondary

Stakeholder

Managing and

ensuring

participation in CSR

activities.

As part of GRM.

Medium Discussions, FGD, Open

meetings and consultations

with each category,

meetings as part of the GRM

and

Involvement in CSR activities

FGDs with each

group

Provisioning of

reports in

Hindi/local

language, if

required.

11. Village Institution

(School & PHC)

Secondary

Stakeholder

Managing and

ensuring

participation in CSR

activities

Low Discussions, Consultations

and Open Meeting and

discussions, FGDS; and

Involvement in planning and

implementation of CSR

activities

Depending upon

requirements.

Page 5: INDIA: Accelerating Infrastructure Investment Facility in ...

H.7. Reporting and Documentation Process

Details of all the engagement activities is to be properly recorded in the form of minutes and maintained as a

stakeholder engagement database for the projects that MEIPL undertakes. Such a database would allow for

effective monitoring of the engagement process as well as ensure that the concerns and query of the

stakeholders are resolved in a timely manner. The recording process is to be carried out in a definitive manner

adhering to a framework which apart from illustrating the outcome of the meetings with the stakeholders in a

comprehensive manner provides scope for demonstrating other vital aspects of each meeting such as date,

place/ location of meeting, key participants and so on.

A Stakeholder Engagement Report consolidating the stakeholder engagement processes of multiple projects in

the solar and the wind sectors respectively may be recorded annually that may include a summary of issues

raised by stakeholders, numbers and subjects of grievances, a summary of key actions taken to address concerns,

analysis of trends in KPIs, (if any), and plans for engagement in the next period.

H.8. Information Disclosure Mechanism

One of the most important aspects of any consultation or engagement process is the process of information

disclosure. This process is not only part of certain regulatory requirements but also a requirement of the

investors in the project. The process of information disclosure can be undertaken in two manners, either

voluntary disclosure or disclosure as part of the regulatory requirements.

While regulatory disclosure involves the provisioning of information as required by the authorities and agencies

involved in the project, voluntary disclosure refers to the process of disclosing information to the various

stakeholders in a voluntary manner. The process of disclosure involves the provisioning of information in an

accessible manner (a manner which allows for easy understanding, such as in the local language) to the various

stakeholders in a project. This disclosure not only allows for trust to be build amongst the stakeholders through

the sharing of information but also allow for more constructive participation in the other processes of

consultation and resolution of grievances due to availability of accurate and timely information.

The disclosure of impact assessment reports and relevant plans is to be carried out in a manner which would

make the information available to the community in an accessible and timely manner. Some of the disclosure

related activities proposed for the future are as follows:

This would include making copies of the main reports/executive summary, available in the Panchayat offices

or the community centres and/or other locations readily accessible (through means such as pamphlets or

leaflets) to the entire community in the locally preferred language.

The provisioning of these reports and plans at the Panchayat Office or a small open meeting with the

community to notify the stakeholders of the documents being disclosed and their nature and location as well

as decide a date for receiving feedback from the community.

Another approach could be to engage the community during the various other community development

activities, including livelihood development, farmers meeting etc. These forums could also be used for the

disclosure of the information to the community;

As a part of the disclosure, the stakeholder reports or the key public consultation findings or the grievance

related records can also be made available at project office;

At minimum, such disclosure should be done on an annual basis to the various stakeholders through suitable

manner.

Public consultations can be done as and when the urgency of the situation warrants having such public

consultations.

H.9. Institutional setup for SEP Implementation

To manage its engagements with the project stakeholders and meet the objectives of stakeholder engagement,

MEIPL is required to ensure that this engagement process is given as much importance as the other project

Page 6: INDIA: Accelerating Infrastructure Investment Facility in ...

activities as well as guarantee the availability of certain resources. To ensure compliance of the objectives with

the timeline given above, respective site incharge is overall responsible for the implementation of the same.

H.10. Monitoring and Review

The monitoring of the SEP and the efficacy of its implementation for any project are required to be carried out

as per formats devised or planned as per requirement of the project. The monitoring and reviewing schedule

can either be developed as part of the impact assessment planning and planned in commensuration with the

developed ESMP or developed standalone to meet or suffice the requirements of the project.

Page 7: INDIA: Accelerating Infrastructure Investment Facility in ...

RAJEEV SHARMA

VP - O & M (WIND & SOLAR)

Date: 01.07.2018

BINAYAK BASU

AGM – O&M

A M SODDI – SAAKSHI

ELECTRICALS & ELECTRONICS

SURANJAN SARKAR

AVP&HEAD- QSHE&SYSTEMS

SADANAND PATIL

SR. MANAGER – O&M

(SAVALSANG)

PRAKASH SALUNKHE – AM

OPERATION & MAINTENANCE

SANKARLIGHAM– SR ENGINEER

OPERATION & MAINTENANCE WTG -

GAMESA

KISHORE KUMAR

AM– QSHE & SYSTEMS

HSE

SHIVANAND P K

DM – QSHE & Systems

BOB SMITH

Director, Head – Asset Management &

Future Business

SHARAD MORE

SS INCHARGE -MYTRAH

APPROVED BY

VICE PRESIDENT – O&M

SECUTIY

SANGAPPA – SUPERVISOR

PREPARED BY

SADANAND PATIL

Page 8: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

Emergency Response Plan

Plan review number: 00 Date of release: 27 November 2017

Name Org Unit

Prepared by: Mr.NS Rakhesh HSE Department

Released by: Mr.Sankaralingam Site Incharge

Major changes compared to last revision New Plan

Record hard copies (Number and location).

Site Office , Warehouse, SCADA .

Siemens Gamesa Renewable Power Pvt Ltd,

33/220KV Pooling Substation

Savalsung,

Horti,

Vijayapur District,

Karnataka.

Page 9: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

Contents Emergency Instructions ......................................................................................................................................... 1

1. INTERNAL COMMUNICATION FLOW .......................................................................................................... 3

2. SITE MAPS ................................................................................................................................................... 4

3. BEFORE INCIDENT ……………………………………………………………………………………………………6

4. BUILDING EVACUATION .............................................................................................................................. 7

4 a. Assembly Point Instructions ....................................................................................................................... 8

4 b Assembly Point Registration ......................................................................................................................... 9

5. INJURY / ILLNESS ...................................................................................................................................... 10

6. FIRE INSTRUCTION…………………………………………..……………………………………………………..11

7. ENVIRONMENTAL INCIDENT……………………………………………………………………………………... 12

8. BUILDING DAMAGE. .................................................................................................................................. 13

9. CRIMINAL ACTIVITY. ................................................................................................................................. 14

10. CONTACT LIST ............................................................................................................................................ 15

Page 10: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

1. INTERNAL COMMUNICATION FLOW ER (Emergency response)Tasks to be performed By Employees Observing the Event.

Sit

e/L

oc

ati

on

e

mp

loy

ee

s.

Assess the situation and mitigate the

risks.

Activate the Site/Location ERP

Follow the instructions in the local ERP

and notify duty holder.

Incident at Site or Location Level

EHS incidents must be reported in KRIMA EHS within 24 hrs. (see PRO 16745 KRIMA EHS Software Application.)

What to do: How to report:

ER (Emergency Response) Tasks performed by Site/Location appointed Duty holder.

Sit

e/lo

ca

tio

n

Ma

na

ge

me

nt +45 99 42 5550

Service center Nuurenberg

If the situation develops and

the impact escalates from level 1 to 2 or 3

Assess the situation based on the impact of the incident and follow

instructions in local ERP.

Handle incident at site level.

Low Impact Level 1

Classify Incident impact

Medium Impact Level 2

High Impact Level 3

Report incident in IR@WP

For incidents <16 24 hours > 16 less than 2

hours. (see PRO-37432

Reporting of significant

incidents in IR@WP)

High impact Level 3 Medium impact Level 2 Low impact Level 1 • Fatality • Kidnapping • Extortion • Civil Unrest • Natural Disasters on site • Sabotage • Loss of location/site

• Incidents potentially resulting in significant injury / hospitalization or multiple casualties i.e. distributed to multiple treatment locations

• Simultaneous activation of more than one Emergency Response Plan within one affected Division/ Business Unit or Regional Country.

• Incidents assessed to have a negative interest of local medias.

• Equipment / IT damage with a potential to stop or significantly delay planned operation when such impact cannot be mitigated within 24 hours or involve a cost of > 10.000 - EUR.

• Industry related incident with potential to affect our operations

• Emergency Services have been called to the site

• Accident/Incident incl. Near Miss - Potential risk ≥ 16

• Risk rate all occurrences immediately!

• First aid cases

Site Duty Holder: Before calling Service center Nurenberg (+4599425550) consider answeres for these questions:

"Who is calling?

"Where did the incident happen?

"What has happened?

"How did the incident happen?

"Which actions have been initiated?

"Is the situation under immediate control (Yes /No)?

Surname? Given name? Business unit? Phone number? Org code or department?

Country? Site or location name? Other description (If relevant)? When did the incident happen (Date, Time)?

Type of incident Injury (Yes / No - which type of injury & how many injured)? Equipment damage? Other (Short description)?

Short description of circumstances in headlines and any additional important information?

Local emergency services called ( e.g. 108 )? Other local authorities notified: (e.g. Riddor, OSHA)?

(If the answer is "No" - description of details not in control - immediate assistance needed)”

Page 11: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

2. SITE MAPS

Area Address

Siemens Gamesa Renewable Power Pvt Ltd,

33/220KV Pooling Substation

Savalsung,

Horti,

Vijayapur District,

Karnataka.

Page 12: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

Emergency Escape Plan Building/Office

Location of Antivenom S.No Location Contact person Contact Number

1 SCADA M.Sankaralingam 7349294330

3. BEFORE THE INCIDENT

Emergency instructions These instructions will assist you and your managers to reduce the impact of accidents.

Page 13: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

General safety • Use common sense, no work is so important that it cannot be done in a safe manner!

• Use your personal protective equipment (PPE)

• If in any doubt then ask your safety rep. or your manager

• Follow your work instructions

• Adhere to rules and guidance for storage of flammable items and other hazardous materials.

• Respect hot work permits

• Keep the work place tidy!

• Never block the emergency evacuation routes or exits

• Do not force fire doors to stay open!

• Be careful with open flames/fire

• Switch off lights and electrical equipment which are not in use

• Check where first aid kits, eye flushes, absorbent materials and firefighting equipment are stored as well as their correct use

• Regularly check storages for leaks

• Report irregularities

• Report all accidents, incidents and near misses – without the reports no lessons are learned and your workplace won’t get safer

• ASK!!!

Refresh these instructions with all new members of staff, when they start in a new area, if you are unsure or if there has been an accident!

Walk through the emergency evacuation route(s) – you won’t have time to study these instructions during an accident!

Be sure you know where the assembly point is located!

4. BUILDING EVACUATION

• When an alarm is activated everybody must immediately leave their position and follow the designated evacuation route and emergency exit to the assembly point.

Page 14: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

• Do not take anything with you, o Except for a coat if it is safe to do so, – But only if you have it within reach o Personal medication & keys, laptop and PKI – But only if you have it within reach

• On your way out: o To the extent possible stay together in groups from where you evacuate o Close doors and windows o To the extent possible ensure that no persons are left back in the building. o When you reach the assembly point stay together in groups from where you evacuated o Try to obtain overview of individuals from you group/work area and report to the assembly point leader.

Page 15: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

4 a. Assembly Point Instructions

• First arriving capable individual on the assembly point will take function as Assembly Point Leader until a senior manager arrives and confirms that he/she can take over.

o Assembly Point Leader wears an orange vest

• The Assembly Point Leader is responsible for discipline and actions taken at the assembly point during the evacuation.

• The Assembly Point Leader can appoint helpers (usually taken from the Emergency Response Team) to cordon off, provide first aid etc.

o Helpers wear yellow vests

• Assembly Point Leader ensures that: o Helpers are placed to prevent unauthorized access to the evacuated area o Helpers are placed to prevent unauthorized access to the reception

• Each team will check that all members of their team have been evacuated. o Missing persons must be reported to the assembly point leader, o Assembly Point Leader communicates this to the rescue services (including where the missing person(s)

were last seen)

• If people (e.g. because they could not be moved/were injured) have been left behind o the assembly point leader must be informed of their location and condition

• If the primary assembly point is compromised for any reason the assembly point leader must identify alternative assembly point and foresee relocation of all evacuees.

• The assembly point leader is responsible for: o Communication with Emergency service supporting the incident. o Calling off the evacuation o Nominating individuals as assembly point assistants.

Page 16: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

4 b Assembly Point Registration

Location of accident/incident Assembly Point Leader: Area Time reported clear Person(s) left behind Comments

Individuals not accounted for (missing): 1

5

2 6

3 7

Page 17: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

5.INJURY / ILLNESS

STOP THE ACCIDENT

• Consider hazards / risks / own safety • Stop the machines/processes • Switch off electricity • Consider if you have to move the casualty to a safer location

NOTE! IN SOME CASES YOU NEED TO RAISE THE ALARM BEFORE ADMINISTERING FIRST AID

LIFESAVING FIRST AID • Raise alarm by shouting • Check for signs of life (see/feel/listen) • Check for consciousness/breathing • Call an ambulance if required • Free airways (possibly rescue breathing) • Stop major bleedings • Provide ordinary first aid • Monitor the injured person • Ensure that guide has been sent out to meet the ambulance

ALARM • Call 108 / 102 / 08352-270009 • Inform: Who you are and the phone number you are calling from • Request for ambulance • Savalsung wind farm, Horti, 33/220KV SS, Bijapur (KA- India), • Casualties and persons at risk • The Alarm Central will inform you when the conversation is over! • When the ambulance have been requested the Security Guards shall be called/

informed

NON-EMERGENCY REQUESTS FOR MEDICAL ASSISTANCE

• Continue First Aid • Approch nearst hospital • Seek the Advice from medical practitioner • If required take support from site Manager / safety Officer • Inform: Who you are and the phone number you are calling from and inform that we

are coming with an injured person as well as type of injuries.

INFORM/ALARM • In case of an accident the Site Manager / Safety Officer should be called/ informed

ASSEMBLY POINT • During larger accidents it will be beneficial to evacuate the area to create space for our ERT and the rescue services

GUIDE FOR EMERGENCY SERVICES

• Send guide to receive emergency services at the main gate/point of contact • Bring site plans, floor plans, keys and data sheets

OTHER INFORMATION AND CONSIDERATIONS

• Only company approved spokesperson communicate with the press • Gather information (Notes / photos) for the investigation without disturbing the scene

Page 18: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

6.FIRE INSTRUCTION(

Assess the situation – raise the alarm

FIRE FIGHTING Use the fire extinguishers, fire blankets etc. if safe. The Fire Brigade must be informed even though the fire was put out.

ALARM • Alart manual call point / Siren • Call 108 /101 / 08352-270160 • Inform: Who you are and the phone number you are calling from • There is a fire at: • Savalsung wind farm, Horti, 33/220KV SS, Bijapur (KA- India), • Where the fire is observed • What is on fire • Casualties and persons at risk

The Alarm Central will inform you when the conversation is over!

RESCUE/ EVACUATE • Evacuate immediately when you hear the alarm – never await verification • The ABA Supervisor is responsible for possible verifications (it can be the guard or the

caretaker)

ASSEMBLY POINT • See the site plan

INFORM/ALARM (FOR ALL ALRMS AND FALSE ALARMS)

• In case of an accident the Security Guards / Site Manager should be called/ informed

MAKE AREA SAFE • Close doors and windows • Switch off ventilation and machinery • Switch off fuel supplies etc. • Remove gas bottles • Evacuate/cordon off • Do not re-enter the building without permission from the Assembly Point Leader

GUIDE EMERGENCY

SERVICES

• Send guide to receive emergency services at the main gate/point of contact. • Bring site plans, floor plans, keys and data sheets

OTHER INFORMATION

AND CONSIDERATIONS

• Only the company approved spokesperson communicates with the press • Cordoning off will be done by the fire department. • Take notes / photos to prepare for the investigation of the accident

Page 19: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

7. Environmental incident

Gain overview – Consider if it’s necessary to make an alarm

STOP THE ACCIDENT • Shut off taps and valves. • Shut of electrical power, stop engines etc. • Cover drain gratings / Restrain for spill with ”cat litter” or other suitable material.

CHECK • Inform the Site Manager: • What type of emission? • Look up the safety data sheet and additional information • What is the extent / what is the risk? • Wear suitable PPE (Personal Protection Equipment) • Use absorption material- / collection equipment to limit chemical spill,

ALARM • Call to Site Manager • Inform: Who you are and the phone number you are calling from • Savalsung wind farm, Horti, 33/220KV SS, Bijapur (KA- India), • and location where the accident has happen. • What type of spill, and if the emission is to: air, soil or water. • If there are injured persons, or any persons or animals in danger. • The Alarm Center will inform you when the conversation is over!

RESCUE/ EVACUATE • Push fire button if evacuation of area is necessary. • Evacuate immediately when you hear the alarm – never await verification. • The ABA Supervisor is responsible for possible verifications

ASSEMBLY POINT • See site plan

INFORM/ALARM (FOR ALL

ALRMS AND FALSE ALARMS) • In case of an accident the site Manager shall be called/ informed

MAKE AREA SAFE

(Always consider own

safety!)

• Close doors and windows • Switch off machines • Switch off fuel supplies etc. • Remove gas bottles • Evacuate/cordon off • Do not re-enter the area without permission from the assembly point leader

ROAD MAP • Send guide to receive emergency services at the main gate/point of contact. Bring site plans, floor plans, keys and data sheets.

OTHER INFORMATION

AND CONSIDERATIONS • Only the company approved spokesperson communicates with the press • Do you require extra help for cordoning off? • Make initial registrations (notes / photos) for the investigation of the accident

Page 20: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

8. BUILDING DAMAGE.

Assess the situation – think of own safety before acting!

Structural damage Flooding Power failure. (Always consider own safety!)

• Impact assessment - consider: • Stop/prevent the accident/incident

o Risks / Hazards o Switching off power/machines o Prevent damage to property o During storms – open windows doors in the lee side and cover damage in

the wind side o Evacuation/cordoning off o Impact on the production o Invoking Business Continuity Plan o Sending guide to main gate/point of contact o Need for (extra) security guards

• Call in: o Facilities / building contractors o Contractor with pumps / generators o Emergency services o Alarm System Supervisor

• Check: o Service Level Agreement (SLA) with our service providers o That we are given appropriate priority o If we need to escalate call out o Insurance

INFORM/ALARM (FOR

ALARMS AND FALSE ALARMS) • Facility Service on duty phone and Site Manager / Security Guards shall be called/

informed

GUIDE EMERGENCY SERVICES

• Send guide to receive emergency services at the main gate/point of contact. • Bring site plans - floor plans - keys - data sheet

ITEMS FOR THE SITUATION REPORT

• Injuries to person(s) • Building damage • Impact(s) on the environment • Production • Risks and hazards • Where, when, what, who, how Actions (initiated/planned) • Who has been informed so far?

OTHER INFORMATION AND CONSIDERATIONS

• Only the company approved spokesperson communicates with the press • Do you require extra help for cordoning off, the authority will take care of it. • Make initial registrations for the investigation of the accident

Page 21: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

9. CRIMINAL ACTIVITY.

Assess the situation – think of own safety!

Burglary/Trespassing • Assess the situation and do not get involved/ contact the culprit on less this can be done absolutely safely.

• Observe the situation and call local police • Call Siemens Gamesa Security • Take notes / photos • If safe stay with in observation distance and await arrival of police/ security

Suspicious object • Do not touch or move the object • Evacuate the building / area • Call local police • Call Siemens Gamesa security • Do not reenter the building before access is released by police

MOB THREAT

Page 22: INDIA: Accelerating Infrastructure Investment Facility in ...

Savalsung Windfarm,Bijapur (KA -India)

Emergency Response Plan For internal use only

Version 00, 27 November 2017

Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System

Savalsung Wind Farm , Version 00 Ref PH: Emergency

WP

10. CONTACT LIST

24/7 contact option

Security Guards at site office (24/7)

Security Guards

Other relevant contacts for Savalsung wind farm

Name Department Phone Mobile E-mail (optional)

M.Sankaralingam Site Incharge 7349294330 [email protected]

Manikandan Emergency Spoke

Person 8072254400

MANIKANDAN.VENKADACHALAM@siem

ensgamesa.com

Sadanad P Site Manager -

MYTRAH 9880917070 Sadanand M [email protected]

S.Selvan Emergency Spoke

Person 9901310998 [email protected]

NS Rakhesh SAFETY OFFICER 9972998758 [email protected]

S.SIVAKUMAR REGIONAL HEAD,KA 9880985457 [email protected]

Pani Martin InCharge -M/S

Aarudhra 9894564166 [email protected]

FIRE STATION BIJAPUR 08352-270160

AMBULANCE BIJAPUR 102/108

GOVT.HOSPITAL HORTI 08422-283809

Primary health centrer BIJAPUR 08352-270009

BLOOD BANK BIJAPUR 08352-253604

Page 23: INDIA: Accelerating Infrastructure Investment Facility in ...

Issued Date t2.| 2018

Our RefNo TC506418000001974

Work Order No 9100006843

lssued to:Mltroh V.yu (Xri$r) Priv.te Limited.# 8001, qcity, S.No:109, Nanakramguda, Gachibowli,Hydersbqd- 500 012, India.Site: Mytrsh Vryu (Krisn.) P.ivrte Limited.Survey No:490/3, Horti Post, Talukar lndi. Districr- Vijayapura.Near Inchgiri villag6586 II7, Krrnataka

Your RefDale 26 l0 2018

DateofMonftoriu 05.1I 2018 Sample Description Ambient Air

Date ofRegistration 08 I I 2018 Sample(s) condition Found Ok

Monitoring Location Site Omce Area

Moniloring Conducred by 11SON LABS

Ambient Temperature oC28 (Average) Wind Direction NE

Weather Condition Clear Flow rate ofcases (LPM) 0.20

S.No.[hitr Test

Results

NationslAmbientAir QuslityStandrrds(NAAOS}

Anrtysis Method

Paniculate Matter (PMro) Fgmr 18_2Respirsble Dust Sampler n€ll}od(IS:s182 P23-2006)

2. Paniculate Matter (PM ,r) rc/m' 24.3 <60 CPCB Guidelines for the measurement ofAmbient At PollutaDts Vol. I, May 201I

3. Sulphur Dioxide (SO:) $dmr 6.8 {80 lmproved Wesl and Geake rn€thod(lS: 5182 P ll - 2001)

Oxiles ofNitrogen (NO, rdm' l9.l <80Jacob and Hocbheiser rmdified (Na-

Arsenite) method (IS : 5182 P VI - 2001)

Ozone (Or) pdm' <5.0 <100 lS 5182 Pan-9 1974

oc"4 t.j3Sr. Chemist AuthoriiChecked by

Vrsox LansEnvironmenlal Consultants &Analyrical Services

Recognised by lSo/iEC 17025:2005 (NABL), MoEF & CC,

FSSAI, NABET{CI,lS0 9001 :2015 & oHSAS 18001 :2007.

AMBItrNT AIR OUALITY TEST REPORT

TEST RESULTS

Page I oflNote:-l. The resuhs ofthe monitored data indicate that the ambient air quality ofthe region in general is

conformity with respect to nonns ofNational Ambient Air Quality sta ards

2. Sanpling & Ana[sis were done as per stasdard method prescribed by CPCB

e

VUQEHS/5, 1O/TR

H.No. 16-11'23/37/A, Flat No. 205, 2nd Floor, Opp. R T A. Office, Musarambagh' Malakpel' Hyderabad - 500 036'

Iet : 040-2454432},24541338, lrob : 98491 10019 / 94408 41338, E-mail : lnfo@ visonlabs.com, vison labs@ gmail.com

NOTE : This Reporl is subiecl to th! t'ffis and condltlons mentloned ov'rletl'

< 100

5.

Page 24: INDIA: Accelerating Infrastructure Investment Facility in ...

t2 I1.20r8

Our RefNo TCs064 I 80000039 75

Work Order No 9300006843

Issued to:Myl t V.yo (Krirn.) Priv.r. Limit.d.# 8001, Ocity, S.No:109. Nrmlrrlnsrda ca.hibowlirHyd€rabsd- 500 032, lodia.Sire Mytnh V.yu (KrtD.) Priv.rc Linia.d.Survey No:490/3, Honi Po$, Taluta: lndi. Disrri]!- Vija),lpura,Near Inchgiri village' 586 I 17, Krnutska

Your RefDare 26 l0 20t8

Date ofMoniloring 05 I t.20tE Sample DescriF'on

Date ofRe!istmri,)n 08.1t.2018 Sample(s) condirion Found Ok

CMC

MonitorinS Conducred by VTSON LABS

Ambient Temperature oC 28lAvera8e) Wind D ection

Weather Condition Clear Flow rateofGases (LPM) 0.20

S.No.l'nils T€{I

Results

Nationsl Ambi€ntAirQurlitySrrndrrds

Anxlysis Method

Paniculare Maner (PM ro) pdm' < 100Respirsble Dust Samplcr m€thod

5182 P 2l,Paniculate Marer (PM,r) ll/Irr' 22_3

CPCB Cuidelines for $€ rneasurement ofAmbietu Air Pollutants Vol. 20tI

Sulphur Dioxide (SO, FdmlInproved West and Geale rnethod

5182 P I - 200t

Oxides ofNtrogen (Nq) srmr t8 5Jecob and Hochheis€r rDdified (Na-

Arsenite) method (lS:5182 P VI-2001)

Ozone (Or) Idm] <5.0 < I00 tS 5182 Pan-g 1974

Chcckcd by Sr. Chemist

=-EE=EE-

VrsoN LansEnvironmental Consultants &Analytical Services

Recognised by lSo/lEC 1702512005 (NABL), oEF E CC,

FSSAI, i{ABET{CI,lS0 9001 :2015 t oHSAS 16001 :2007.

AMBIf,]'{T AIR OLALITY TEST REFORT

TEST Rf,SUL'I.s

Page I of I

Note: -l. The resuhs oflh€ rmnitored data indicate that the ambient ah quality ofthe region in geoeral is

conformfty with respect to nonns ofNational Ambient Air Quality sla.dards

2. Sanpling & Anal)sis were done as per stand.rd m.thod pres.ribed by CPCB

ldera

VUOEHS/5, 1O/TR

H.No.1&11-23Y37/A,FlatNo.2O5,2ndFloor,OppFI.T.AOtfice,Musarambagh'Malakpet,Hydorabad-500036'|el I 040-24544320' 24541338, Mob : 98491 10019 / 9.t408 41338' E.mail : lnlo@visonlabs,com, vison.labs@ gmail,com

NoIE : nrl. illgon b tuu.G't to th. t I[s tnd codllont rtrtlotEd ou'rL't'

446

2 <60

'7.1 <80

<80

l

.l

5

Page 25: INDIA: Accelerating Infrastructure Investment Facility in ...

lssued Date t2.l L20t8

Our RefNo TC5064 I 8000003976

Work Order No 9100006843

Issued to:

Mytrih Vryu (Krisnr) Privrt. Limited.# 8001, Gcity, S.No:109, NaElrsntsuds, c&hibowti,Hlderabod- 500 032, Iodia.SitG: Mfr.t Vry[ (Kri!r.) Privrtc Limiad.Survey No:490/1, Honi Pos, Taluka: lndi District- VijaFFrra,Near lochgiri village-S86 I 17, Krrn{ska

Your RefDate 26 I0 2018

Date ofMoniloring 05.t t.20t8 Sanple Descripion

Date of Registralion 08.1t.2018 Sarple{s) condnion Found OlMoniloritu! t-ocaiion Krnour Vilhse

Monitoring Cooducted by VISON I-ABS

Ambient Temperature oC 28 (Average) Wind Direction NE

Weather Condition Clear Flow rate ofGases (LPM) 020

S..\"o.tioirs Test

Resulls

N.tioorl AmbieotAir QorlitySlrodrrds(NAAQS)

Aoa't_si! Method

Paniculare Matrer (PM ro) [9m] 40 I < 100Resphable Dusl Sampler method(lS:5182 P 23 - 2m6)

2 Pantulare Mrner (PM ?J) Igm] .60 CPCB Guidelines 6rthe measurement ofAmbienl Air Pollutaots Vol. I, May 201I

lgml 6.6 <803 Sulphur Dioxide (SO?)Improved West and Geake nEthod(lS:5182 P II - 2001)

.1 Oxides ofNit ogen (Nq) pdm' I5 7 <80 Jacob rnd Hochheiser modilied (Na'Arsenite) merhod (lS:5182 P Vt-2001)

pgm' <50 .. t00 lS 5182 Part-9 1974Ozone (Or)

C!r-+@:N1Anthorized lsr ChemistChecked by

-EE=CE+ Vrsols Lass

Environmental Consultants & Analytical Services

Recognised by lSoilEC 17025:2005 I[ABL), LloEt & CC,

FSSAI, NABET-QCI, lS0 9001 | 2015 t oHSAS 18001 : 2007.

A}IBII]NT AIR OIIAI,ITY TEST REPORT

T[,ST REST I,I S

Page I of I

Note: -L The results ofthe rr)nitored dat! indicde thrt the ambient air quality ofthe region in genersl is

codbnnity with respect to nonns ofNetionel Ambi.fl Air Qurlity stardards

2. Saryliog & Analysis were done as per slandard hethod prescrib€d by CPCB

VUOEHS/5. 1O/TR

H.No.16-11-23/37lA,FlatNo.2O5,2ndFlootOpp'R'T'AOtlice,Musarambagh'Malakpet'Hyderabad-H iOii-ZiSCCiiO, ZqSar sga, [,too, ga+gr roorgts44oe qtseg, e-mail: tnfo@visonrabs,com' vison,labs

NOTE : Thi. A.Port lt tubl'cl to lhi t'Im' ind condltlon' m'ntlontd ov'rl'al

500 036.

@gmail.com

I

5.

Page 26: INDIA: Accelerating Infrastructure Investment Facility in ...

:

=E-

Vrsou LansEnvironmental Consultants & Analytical Services

Recognised by lSo/lEC 17025:2005 (NABL), MoEF & CC,

FSSAI, NABET{CI,1S0 9001 :2015 & oHSAS 18001 :2007.

Toral A Resuhs tlnit\ .lB

AMAIINt NO|Sf, LCV[[,Sl',

Nore. I D{y rin. s rcctmcd b€Nem 6 !.n. rd 9 p D, Nisit nE i rcclasi hcwd I p.m .nd 6 r.D

2 Non. doidng wd. ddc ss pd 3lr ltd 6.{tod prcdibdl by IS 9E76:lr8l(Rallim.d 20nl)& IS4758:1968

VUOEHS/5, 1O/TR

Issued Date t2 I L20t8Our RefNo TC5064 I 8000003977

Work Order No 9 r00006843

Issued to:Mltrrh Vryu (Rrism) Privrtc Limircd.# 8001 . qcity, S. No: I 09, NalutrarBuda. Cachibowti,Hlderabad- 500 032, India.

Sire: Mltrih V.yu (Kritni) P.iv.re Limired.Survey No:490/3, Honi Post, Taluka: lndi Distrac Vijay"pura,Near Inchsiri villase-5861I7. Xrrnarala

Your RefDate 26 l0 20t8

Monitoring conducted by I'ISON L.ABS

Sn. Orr.D.t.:03-11.2018 r

06.1l.20lE

CMC AdHi.rI).r.: 05.I I l0l a ro

06.11.2018

Krrnlr Yilhg.D.l.:05.ll.20lEto

05.11.201t

Inchcgcri Vill.g.Drl.l 05.11.2018 to

ff.ll.r0t6I 06 00 07.m 126 400

07 00 08 00 492 .11 I

08.00 - (B-00 51.2 4lr 2 4:l l0900-1000 5l.l {ll l

5 10.00 I 1.00 54.1( J t.2 4?.1

1t.00 - 12.00 56 It 52.6 5161 t2.m l3 00 555 50 I

8. t3.m l4 00 564 52.1r 53?t4.00 I5.00 J0.2 ,19 3

l0 l5.m 16.00 54.5 516 50tll t6.00 - 17.00 55 I 5t 7

l: 17.00 - 18.00 516 53.7

ll l8.m t9.00 65 I 6{t (, 519 ,lll lt-1 19.00 20.00 58? 537 478 56.8

20.00 21.00 514 49t 455 167l6 2l.m - 22.00 ,1119 4?0 445

22_$ 23.U) 41 \t .t4 5 412 41_1l718. 23.00 24.00 412 42.2 l9:l

420 401 lrt 179l9 24.m 0l 00

20. 01.00 02.00 lli.l:l 02 fi) - 01 00 t70 16 I 15.2 3.12

139 35522_ l5ll36.023. 04 00,05.t10 t75 157 145

19.0 36.624 05 00 06 00

56.? 52.7t-rq drY da(A).17.9 .18.2l,eo \ist( dB(^) .12.0 .t0.0

Limirs ir dB (A) NiEhtTimeLimits in dB (A) Dit'rime<75 <70Industrial Area(A)

<ss<65(B)<45<55(c) Reside ial Area

<50 <40(D) Silence Zone

eor[Checked byPrQared by

Tel

H'No. 16.11.23l37/A, Flat No.2o5, 2nd Floor, opp' R.T.A, oflice' Musarambagh, Malakpet' Hyderabad - 500 036.', ifr-iisiiio, z.cia1s38, Mob:98491 tOdtS / ga4oe +resg, e-mart : [email protected], [email protected]

NOIE I Thlr B.Pon 13 tubl'ct lo th' itrm! tnd condtilont m'ntlomd ov'l"l'

45.E

49J

I

@4r

Page 27: INDIA: Accelerating Infrastructure Investment Facility in ...

=-EE=E-

Vrsox LansEnvironmental Consultants & Analytical Services

Recognised by lSo/lEC 1702512005 (tlABL), MoEF t CC,

FSSAI, NABET.QCI,IS0 9001 :2015 EoHSAS ,l8001

i2007.

AMBI}:NT NOISE OTJALITY MONITORING I,EVIiLS

Total Results. Units: dB

AMBIINT NOISE LIJVUL S TAN DARDS

Nd. I D.v titr t Ed6cd i. p.e , Nig[l i@ is r.d6di i! hrw@ 9 p D .!d 6 i o2 Nois mmilcirs w* do. $ F sund.d ni<r[.d p,wiH by IS 9876:1981(Rammed 2ml) & Is 4753 1968

VUOEHS/s, 1O/TR

Issued Date 12 Il 2018

Our RefNo TC506t I 8000003977-01

work Order 91000061i4r

Issued to:Mytr.h Vr,u (Xrirm) Privrt. Liltitcd.# 80Ol, Gciry, S.No:toS, Nao.karEudq cachibowli,Hlderabsd- 50O 032, Irdia.Siae: Mfrrh V.yu (Krba.) Priv.te Limited.

Taluka: lndi. District- Vijayapura,Karn!trk!

Survey No:490/3, Horti Pon,Near 586t I7

Your RefDate

26.10.20t8

Monitoring conducred byVISON LABS

s.\o YotritorinS TiR M.Lve.r T.dtD.t.: 05.1 l.20lE to 0,6.1 l.20lE

SrvdsrngViLs.D.t.: 05.1t.201t to 06-r r.2or8

06.00 07.fi) l9l 4t) 107,00 08.(xl 42.1 42208 00 -{D 00 44.5 44.5

.l 0900-t000 411 45 II000- 1t.00 48 1r

I1.00 t2.00 4.t.2 41.1'1 l2.m- ll.rx) 411 128

l3.rx) - l4 00

t4.(xl - t5 fi) 410 472lr) 15 00 t6 0t) 4821t 16.00- 17.00 4ll 481t2 17.00 - l,i.m 5U0tl t8.m - 19.00 176ll t9.00 20.fi) 454 50215. 20.00 21.00 4t.2

21.00 22 00 410 44.0

22.1fi 13-OO 41 5

23.Ut 24 U) 189 t9.019 24.00 01.00 165 3rJ.3

20 0l.m- 02. ) l5 I 36.6

ll 02 00 0l 00 162 l4.l01.00 04.00 111 35.4

21. 04.00 -05.u) 15:l t9.021 05.00 - 06.00 llt 2 39.8

Ltq dr\ dB{A) 45.5 :16.6

L€q Nishi dB(A) !7.1 .]6.5

l.inil! in dB (Al Drl Tide l.imib in dB (A) h_ilht Time(A)

{Dl Silmce Zone <50 <40

sr4Authorized StChecked byPrepared by

H.No. 16-11-2r37/A, Flat No. 205, 2nd Floor, Opp. R.TA. Ottice, Musarambagh, Malakpet' Hyderabad - 500 036

Iel:040.24544320,24541338,Mob:9849,|toots/9a4oactsse,[email protected]'vison.|abs@gmail,comNOIE :Thl. Bcport l.subi€cl io tlr' ltm3

'nd conditlom trEnllon'd @'n'd'

L7

3.

t1.lll

@.*

Page 28: INDIA: Accelerating Infrastructure Investment Facility in ...

Issled Date 12 l L2018Our RefNo TC5064 I 8000001978

Work Order No 9100006841

Issued to:Mytrrh Vryu (Kri!nr) Priv.tc Limired.# 8m I . qciy, S No: I 09, Nan tranEuda cachibowtiHtserabod- 500 032, Iodia.Site Mytnh Vryu (Kri![.) Privrte Limired.Survey No:490/3. Honi Pos, Taluka: Indi. Disrricl- Vijalapura,

KarnatataNear Inchgiri villase-586 I 17

Your RefDate 26 t0.20lE

Sample description Drirkinr W.t.r Co[.ct d .i CMCBrildirB Mode ofPackine

Appearance of the Sample Clear Liluid Sarple condition of testinS Found OkSample collection date 06.1 t.20t8 Satrple Quantiry I ltrSarnple Coll€.tior Time 02:30 pm Analysis stanins d.le 08 I I 20t8Sample Registrarion dare 08.1 I 2018 Amlysis Complerion dale 12.1t.2018Sarple colle.led by VISON LABS

s.\o ( hrrr(erislic Tesi Method Unils 'I esl Resulls

I pH st 250C lS:1025 pdn ll 1983 RA-2012 1.47 6.5-8.52 Turbidnv IS:3025 Pan l0 1984 RA-200? NTU -:1.0 5-I0l Conducliviry al 2 5!f' IS:3025 Psn l4 1984 P.A-2013

4 TotalSusDmdcd Solids IS: 1025 Pafl l? 1984 RA-2012 <1.0

Tolal DBsolv.d Solids lS:3025 Pan l6 l9E4 RA-2fi)6 50u-?000

IS:1025 Pan 4 l98l RA-2006 <05

7 ISr3025 pan 08 1984 RA-2002

Odor IS:3025 Dan 05 1983

CHEMI(]AL PARAMETELSToGl Alkllinitv ss CaCOr ISr3025 P.n 2l l986.fA-2003 m,f,{! 20

l0 Chlorid.s as Cl' rS:3025 Pan 32 I98f. RA'20()9 rn!"q- l5 250 - t000

o)sll 66 200 - .100ll Subhares &s SO. : IS:1025 Pan 24 l986,RA-2003

Nirrates as NOr lS: lll2J Psn l4 1988 RA-2001 nPtL o6 40 - r00t2

'rq,q,<o 02ll. Phosphales as POa lS:1025 Panll 1988 RA-2003

m.slL ?o 200 600l4 Total Hardness as CaCOI IS: lO25 Prn 2 I 2iI)9

mp'I- 40 '75 - 2Nt5. Calcium as Ca lS: 3025 Pan40 l99l-RA-2009

t0 Io0lS: 3025 Pln46 1994. RA-2003 mc,l-t6ns4- t2.4t7 Sodium 6s Ns IS: 1025 Pnt45 1993. RA-20{Y)

$F/L 04t8. Poussium as K IS:1025 Pan 45 1993 RA-2009

-0 004 t- t.5lS:1025 Pan 60 2008 m!I/{-l9 Fluorides as F

mp4- .:0 04 0.1- IIS:1025 Part 53 2003, RA-200320<0 001 0.00t - 0.002ms,1-2t Phenolic Compounds AIHA 23d Ediriotr 5330D

,J:,all- .0 001 0 005IS 3025 Pan 27 198622 Cvanide as CNo2ms/L <0.001lS 3025 Part 26 198623 Residual Chlorine as CI

0.01n*tl' <0.001lS 3025 Part 41 199224 Csdmium ss Cd0.05ma/L <0.00tIS 3025 Pan 52 200325 Tolal Chromium 5s Cr005<0.02mgLIS 1025 Pan 47 lD426 Lead as Pb

Vrsox LansEnvironmental Consultants &Analytical Servaces

Recognised by lSo/lEC 17025:2005 (NABL), MoEF & CC,

FSSAI, NABET{CI, lS0 9001 :2015 & oHSAS 18001 :2007.

Tf,ST RESULTSPHYSICAI PARAMETERS

VUOEHS/5. 1O/TB

036H.No.16-11-2337/A,FlalNo.2O5,2ndFloor,Opp.R'T'AO'ffice,Musarambagh'Malakpet'Hyderabad-

fel : (YO-2454432O,24541338, Mob : 98491 10O19/94408 41338, E-mail: lnfo@visonlabs com' vison labs

NoTE : Thl. RlPon b !!bl'cl lo th' t'm3 and condilloN nr'ntiql.d ov'rlolt'@gmail.com

Page 29: INDIA: Accelerating Infrastructure Investment Facility in ...

Sariple descri ion Drinldng Wrtcr Colhct.d .t CMC Buitditrt

Our RefNo TC50&118000001978

'l'est ]\lethod llnns Tesl R€sullss.\o Charr.t€ristic

27 IS:302s Pan 37 1988. RA-2003 n,EL <0 0l 0 0l28. Z;nc

^s Zn lS 3025 Pan 49 1994 lr,P/L <0 00t 5-t5

29 MaDganese as Mn IS: 1025 Pan 24 2006 ru/L <0 001 _10 - t00t0 Copper as Cu IS 1025 Pan 42 1992 m,/t. <0 001 0.05 - t.53t Nickel as Ni IS 1025 Pan 54 2003 mP]L ?0.001 l0-5032 Boron lS 1025 Pan 57 2005 n,y'L <0 001 10033 lS 13428 Anner K <o 00t 020l4 MiDsral Oil APHA 23'i Enhion 20t2 m.9,4, <0.001 0.0135 Aluminium as Al IS 1025 Pan 55 20Ol mdL <0 001 00316. Mercury as Ha lS 1025 Pan 48 1994 rIPIL <0.0002 00031 Pesticides USEPA <0 001 <0 00118. lS:5402 :2012

39 E Coli IS: l5l8J:2016 cFU/tuhL

,,W@*v, e""+sr ChemistChecked by " I

===l

-

VrsoN LassEnvironmental Consultants &Analytical Services

Recognised by ISO/IEC 17025:2005 (tlABL), MoEF & CC,

tSSAl, NABET{CI,lSO 9001 :2015& oHSAS 1800,l :2007.

Png. 2 of 2

VUQEHS/5, 1O/TR

H,No. ,16..11.23l37/A, Flat No.2o5, 2nd Floor, opp' R.T.A' otfic6. Musarambagh, Malakpel, Hyderabad ' 500 036.

Tet : 0l(,-24544320,24541338, Mob : 98491 t Odt g l g+log tt ssa, e-mail : [email protected]' vison.labs@ gmail,com

NoTE : Thl! Rcporl l. .ubi'ct lo th' t"mt tnd condllion! mlnllontd ov'rl4r'

vdl-CrU/mL

Nol dctcctcd

Page 30: INDIA: Accelerating Infrastructure Investment Facility in ...

lssued Date t2.I L2018Our RefNo TC5064 I 8000003979

Work Order No 91000(}6841

Issued to:Myrnh Vryo (Kri!n.) Piiv.t. Limhed.# 8m I . qcity, S.No: I 09, Narukrar8uda CachibolrliHlderahad- 50O 032, India.

Sit : Mltr.h V.yu (Kri.n.) Privrre Limircd,Ho(i Po$, Talukn: lndi. Dbrri(- Vijarapura,

Near

Sufv.y No:49Ol3,

iri viltaSe-5861 17, Krmarska

Your RefDale 20 t0.20lE

Sarqle descriptionDdnkirt W.t.r Colh.t.d .t Eorai

ModeofPacking Pet bolle

Appearance of lhe Sanple Clear Liruid Saryle condition of resting

Sarple colledion date 06. I I 20t8 Sarnple Quantiry lhrSarple Collection Time 240pm Analysis stanins dale 08 r r 20t8Sanple Rcghtrarion dstc 08.11.2018 Anslysis ComDletion dar. 12.I r 2018

colllcred VISON I,ABS

'I-est Mr(hod Ilnili 'I-esi Rrsulls

I DH at 25oC IS:3025 pfi ll l9E3 RA-!012 7.15 6.5 - 8.52 Turbidny IS:1025 Pa( l0 1984 RA-2002 NTU 5-r01. CondudilnY ar 2soc IS: 1025 Pan 14 l9E4 RA-2013 62

4 Toral Suspmdcd Solids IS: 3025 PEt l7 1984 RA-20125 Tolrl D,ssollcd Solids lS:1025 Pan 16 1984 RA-2006 4l

Cotour IS:1025 Part 4 1983ItA-2006 Ha7en <05 5007 lS:1025 pan 06 l9E4 AA-2002

Odor IS:1025 pan 05 l98l( HEIlIICAL PARA}tETERS

Totll Altilinity es C.CO IS:302! Pd 23 l986.RA-2m3 ry./L IE

Chlorid.s rs Cf n,sl-IO rS:3025 Prn 32 1988. RA-2009 1.5 250 . 1000

ll Sulphares as SOr i IS:1025 Pan 2.1 l986,RA-2003 m,+{- 09 200 - 400

l2 Nitrates as NO IS:1025 Pan 14 1988. RA-2003 rnPJl, 0l 40 - I00l3 Phosphales as POa IS:3025 Part I I 1988, RA-2003 r,tqll- <0 002

t4 Tolal Hardncss as CaCOr IS:1025Fan2l2Ul9 nltlL t0 200 600

mc,/L 40 't5 - 2Nt5 Calcium as Ca IS:3025 Pan40 l99l P!q-2009

lSr 1025 Pan 46 1994, RA-2003 nc|,- 2.1 .10 100l6 Magn€sium as Mg

l7 Sodiun as Na IS:1025 Pan 45 1993 RA-2009 rnp,lL 4.0

mr,/L 0.2l8 IS: l02J Pan45 l99l RA-20@

lS:3025 Pan 60 2008 w,a, ro 004 l-1.5t9nsn- <0.04 0.1- l20. lron as lre IS:1025 Pan 53 2001. RA-2003

mq/L ..0 001 0 00t -00022t Phenolic Compounds A?HA 2ld Edition 5330D

ms/L .:0 001 0 0052.2 Cvanide as CN IS 3025 Pan 27 1986

.:0 001 0:lS 1025 Parl 26 1986 mc/L23 Residual Chlorine as Cl-mc/t, <0 001 0 0lCadmium as Cd IS 3025 Palt41 1q]221

005,l:,s,lL <0.00r25 Total Ckomium as Cr IS 1025 Pan 52 2m3

005mp,/L <0.0226 L€ad as Pb IS 3025 Pan 47 19114

-EE

-

Vrsou LansEnvironmGntal Consultants &Analytical Services

Recognised by lSo/lEC 17025:2005 (NABL), [toEF E CC,

ESSAI, NABET{CI,lS0 9001 r2015 &oHSAS 18001 :2007.

TEST RtrSULTSPIIYSICAL PARAMtrTtrRS

VUOEHS/5, 1O/TR

H No. 1 6- 1 23t31/4, Flal No. 205. 2nd Floor B, IA, Office, Musarambagh, Malakpel,

338, Mob 9849 '1 001 9 94408 1 338, E-mail lnfo @ visonlabs.comTel o40-24544320 24541

NOTE

[email protected]

Page 31: INDIA: Accelerating Infrastructure Investment Facility in ...

Sanple dBcription Drintins W.l.r CoIcrt.d .t Ho.ti YiLg. Ph Ar.r

Our RefNo 1 C5064 I 8000001979

( hsrrclerhtic Test MethodS.No tinirs

27 1S.3025 Pan l7 1r88. RA-2001 mgr- <0.0I 00l28 Zin as Zn IS 3025 Pan 49 1994 msr- <0 001 5- 1529 IS: 3025 Pan 24 2006 ms/L <0.00t l0 - too10. IS 3025 Pan 42 1992 lI,91- <0 001 0.05 - t.5rl Nickel as Ni lS 1025 Pan 54 2003 ln-g'l- <000t 1.0-5032 Boron IS 1025 Pan 57 2005 m,y'L <0 001 looll Anionic D€ter,aents IS 13428 Ann€x K m14L <0.00r 020l4 MineralOil APHA 23d Edirrco 20t2 nt44. <0 001 0 0ll5 Aluminium as Al IS 3025 Pan 55 2001 lr,sll- <0 001 001l6 Mercury as HE IS 3025 Pan 48 1994 ,,:.s/L <0.0002 000l7 Pesricides USEPA lgrL <0.001 L0 001l8 IS:5402 :2012 CFU/mLl9 E CoU IS: 15185 :2016 CFU/ l0lhnl

N

6n*il- AP'F ,.hIChmked bv sr Ch€mist

:

-EE=E-

Vrsox LansEnvironmental Consultants & Analytical SeNices

Recognised by lSo/lEC 17025:2005 (tlABL), itoEF t CC,

FSSAI, I{ABET{CI, ISO 9001 :2015 t oHSAS 18001 : 2007.

Page 2 of 2

Ir

VUOEHS/5. 1O/TR

H.No. 16-1 1-23l37lA, Flat No 2O5, 2nd Floor' Opp. R.T A. O,tlice, Musarambagh' Malakpet' Hyderabad - 500 036'

kl : o;4o-2454432l,24541338, Mob : 98491 t OOt S / gaaog +t sgg, e-mait : tnlo@ visontabs.com, vison.labs @ gmail.com

NOTE :rhB FePon i. subist to th' i"mt lnd condltlon' m'ntlon'd @'ri"l'

Page 32: INDIA: Accelerating Infrastructure Investment Facility in ...

Issu€d Dare 12.lr 20l8Our RefNo TC5064 I 8000003980

Work Order No 930000684:l

Issued tr':

Mytrih Vryu (Krittr.) Privrtc Limited.# 80O1, qciy, S.No:109, Nanakarnguda, Gachibowli,Hferabad- s00 032, India.

Sire: Mytr.h Vryu (Kri!n.) Privrt€ Limir€dSurwy No:490/3, Horti Post, Taluka: bdi. Disrricl- Vijalqura,

villagc-586 I 17, f\arnatakaNear

Your R€fDale 26 10.2018

Sarple des.riptionD.inkiog W.ter Colhcted rtVijrypln Cu6! Ho$. Mode of Pscking

Appearance of lhe Sarple Clear Liquid Sampl€ condition of resring Found OkSample coUection dale 06.I1.20I8 Sarple Quantiry lhrSanple Collection Time l:30 pm Analysis slanina dare 08. t I 2018

Samplc Rcgistrdion dste 08 I I 20 t8 Ar8lysis Coflpleliotr dste l2.l1.20t8Sanplc collccled by VISON LABS

s.i\o Chrrrc(€ristic Test Nlelhod linits Test Resulls

I pH ar 25uC ISr3025 pan Il l9rll RA-1012 6.5,8.52. Turbrdily lS:3025 P.n l0 l9ll4 RA-2m2 NTT] <t.0 5- 10l Conductivilv at 2soc IS:3025 Part 14 l9li4 RA-2011 ll5I TolalSuspmded Solid! IS:1025 Pan l7 1984 RA-2012 MPJL

Total Dissolvcd Solids IS:1025 Pan 16 1984 RA-2m6 nell- J00-2000a IS:3025 Pan4 l98l RA-20fi,7 IS:1025 psn olJ l9E4 RA-2002x Odor IS:1025 pon05 1983

CHtrMICAL PARAMEl'ER5Total AlkaliDftv as CaCOI IS:3025 Pon 23 l9tl6. RA-2003 mg,/L 20

l0 Chlo.ides as Cl' IS:3025 Pan32 198,1. RA-2txl9 mCrl- :s 250 - t 000

II Sulphates as SO. 1 ISr 1025 P.n 24 l986.RA-llx)3 mg!,I, 5.5 200 - 400t2 Nirrates as NG IS:302J Pan 34 l9li8. RA-20lrl m.!,1- 03 40 - 100

l.l Phosphates a5 PO{ IS:3025 Pan 3l 1988. RA-2001 mp{: <0 02

t4 Total Hardness as CaCOI IS:1015 Pan 2l 2ul, ms{: :0 200 600

l5 Calcium as Ca IS: 3025 Pd 40 1991. RA-2009 ms/L ,10 '75 ,20016. Magnesium as Mr ISi1025 Pld 46 1994. RA-2Ui3 m,atr 2.4 30 - t00t7 Sodium as Na ISr3025 Prn 45 l!93. RA-2m9 tl,r.E/L I8.4

l8 Potassium as K IS:1025 Pan45 1991. RA-2{x), n.stL 02.

l9 Fluorides as F IS:3025 Pan 60 2008 md- <0.00.t 1 15

20. Iron as [e IS:3025 Pan 53 2(xi3. RA'2m3 ,,:,z/L <0.M 0.:l - I<0 001 000t -00022t Phenolic Compounds APHA 23d Eduion 5ll0D m,q/L

lS]025 Pan 27 l!tr6 n:.14q- <0.001 0 00522. Cyanide as CN

23 Residual Chlorine as Cl' IS 1025 Pan 26 19116 r,r,s/L <0.001 o2rr.qfl- <0.001 0.ol24. Cadmium as Cd IS 1025 Pan4l Itr)2

0.05To.al Chromium as Cr lS 3025 Pan 52 2lnl itpl- <0 00125

005lS 3025 Pad 47 I{r4 mp'I- <0.0226 t ead as Pb

-E=E

Vrsox LansEnvironmental Consultants & Analytical Services

Recognised by lSo/lEC 17025:2005 (NABI-), lroEF & CC,

FSSAI, NASET{CI,lS0 90{l :2015 E oHSAS 18001 r2007

TEST RESTJLTSPHYSICAL PARAMtrTERS

o

VUQEHS/5. 1O/TR

H.No. 16-11'23/37lA, Flat No. 205, 2nd Floor' Opp. R.T.A. Otlice, Musarambagh' Malakpet' Hyderabad -

fel.0)40-24544g20,24541338,Mob:9849110019/9440841338,E-mail:lnfo@visonlabs'comvison'labsNOTE : Ihis F€pon i5 subiei io th' l"mt and condltlon3 m'ntlor'd d'rl€al'

@gmail.com