INDIA: Accelerating Infrastructure Investment Facility in ...
Transcript of INDIA: Accelerating Infrastructure Investment Facility in ...
Environmental and Social Due Diligence Report
Project Number: 47083-004 December 2019
INDIA: Accelerating Infrastructure Investment
Facility in India – Tranche 3 Mytrah Vayu (Krishna) Private Limited (Part 9 of 10)
Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance
Company Limited and the Asian Development Bank.
This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
s.no Stakeholder Stakeholder
Category
Objective of
Engagement
Stakeholder
Influence
Methods of Consultation and
Engagement
Frequency of
Consultations and
Engagement
requirements;
and
As per the need.
5. District
Administration
(Tehsildaar, SDO,
Patwari)
Primary
Stakeholder
Regular engagement
Participation in CSR
Activities
High Regular meetings and
participation in CSR events
Regular Meetings;
or
Monthly or as &
when required
6. Land Sellers and Land
Users
Primary
Stakeholder
To seek support if
required
Very Low Attendance in plant
functions/occasions, or seek
their support as and when
required
Meeting and
invitation in
events
7. Local Community Primary
Stakeholder
Managing and
ensuring
participation in CSR
activities.
As part of GRM.
Low Open Meetings,
Interactions with
community at Gram
Panchayat,
Sharing of CSR reports and
other documents, if
required, as part of the
disclosure mechanism and
the GRM; and
Involvement in CSR activities
As and when
required
8. Local Women Primary
Stakeholder
Managing and
ensuring
participation in CSR
activities.
Low Meetings specific to women
o o e ’s g oups
Sharing of CSR reports and
other documents, if
As and when
required
s.no Stakeholder Stakeholder
Category
Objective of
Engagement
Stakeholder
Influence
Methods of Consultation and
Engagement
Frequency of
Consultations and
Engagement
As part of GRM. required, as part of the
disclosure mechanism and
the GRM; and
Involvement in CSR activities
9. Agricultural
Labourers
Primary
Stakeholder
For necessary
information
Managing and
ensuring
participation in CSR
activities.
As part of GRM.
Very
low/Non
Existent
Open Public Consultations
sharing of reports and other
documents as part of the
disclosure mechanism
(Provisioning of reports in
Hindi/local language, if
required)
Involvement in CSR activities
As and when
required
10. Vulnerable
Community (not
affected by land
acquisition)
Secondary
Stakeholder
Managing and
ensuring
participation in CSR
activities.
As part of GRM.
Medium Discussions, FGD, Open
meetings and consultations
with each category,
meetings as part of the GRM
and
Involvement in CSR activities
FGDs with each
group
Provisioning of
reports in
Hindi/local
language, if
required.
11. Village Institution
(School & PHC)
Secondary
Stakeholder
Managing and
ensuring
participation in CSR
activities
Low Discussions, Consultations
and Open Meeting and
discussions, FGDS; and
Involvement in planning and
implementation of CSR
activities
Depending upon
requirements.
H.7. Reporting and Documentation Process
Details of all the engagement activities is to be properly recorded in the form of minutes and maintained as a
stakeholder engagement database for the projects that MEIPL undertakes. Such a database would allow for
effective monitoring of the engagement process as well as ensure that the concerns and query of the
stakeholders are resolved in a timely manner. The recording process is to be carried out in a definitive manner
adhering to a framework which apart from illustrating the outcome of the meetings with the stakeholders in a
comprehensive manner provides scope for demonstrating other vital aspects of each meeting such as date,
place/ location of meeting, key participants and so on.
A Stakeholder Engagement Report consolidating the stakeholder engagement processes of multiple projects in
the solar and the wind sectors respectively may be recorded annually that may include a summary of issues
raised by stakeholders, numbers and subjects of grievances, a summary of key actions taken to address concerns,
analysis of trends in KPIs, (if any), and plans for engagement in the next period.
H.8. Information Disclosure Mechanism
One of the most important aspects of any consultation or engagement process is the process of information
disclosure. This process is not only part of certain regulatory requirements but also a requirement of the
investors in the project. The process of information disclosure can be undertaken in two manners, either
voluntary disclosure or disclosure as part of the regulatory requirements.
While regulatory disclosure involves the provisioning of information as required by the authorities and agencies
involved in the project, voluntary disclosure refers to the process of disclosing information to the various
stakeholders in a voluntary manner. The process of disclosure involves the provisioning of information in an
accessible manner (a manner which allows for easy understanding, such as in the local language) to the various
stakeholders in a project. This disclosure not only allows for trust to be build amongst the stakeholders through
the sharing of information but also allow for more constructive participation in the other processes of
consultation and resolution of grievances due to availability of accurate and timely information.
The disclosure of impact assessment reports and relevant plans is to be carried out in a manner which would
make the information available to the community in an accessible and timely manner. Some of the disclosure
related activities proposed for the future are as follows:
This would include making copies of the main reports/executive summary, available in the Panchayat offices
or the community centres and/or other locations readily accessible (through means such as pamphlets or
leaflets) to the entire community in the locally preferred language.
The provisioning of these reports and plans at the Panchayat Office or a small open meeting with the
community to notify the stakeholders of the documents being disclosed and their nature and location as well
as decide a date for receiving feedback from the community.
Another approach could be to engage the community during the various other community development
activities, including livelihood development, farmers meeting etc. These forums could also be used for the
disclosure of the information to the community;
As a part of the disclosure, the stakeholder reports or the key public consultation findings or the grievance
related records can also be made available at project office;
At minimum, such disclosure should be done on an annual basis to the various stakeholders through suitable
manner.
Public consultations can be done as and when the urgency of the situation warrants having such public
consultations.
H.9. Institutional setup for SEP Implementation
To manage its engagements with the project stakeholders and meet the objectives of stakeholder engagement,
MEIPL is required to ensure that this engagement process is given as much importance as the other project
activities as well as guarantee the availability of certain resources. To ensure compliance of the objectives with
the timeline given above, respective site incharge is overall responsible for the implementation of the same.
H.10. Monitoring and Review
The monitoring of the SEP and the efficacy of its implementation for any project are required to be carried out
as per formats devised or planned as per requirement of the project. The monitoring and reviewing schedule
can either be developed as part of the impact assessment planning and planned in commensuration with the
developed ESMP or developed standalone to meet or suffice the requirements of the project.
RAJEEV SHARMA
VP - O & M (WIND & SOLAR)
Date: 01.07.2018
BINAYAK BASU
AGM – O&M
A M SODDI – SAAKSHI
ELECTRICALS & ELECTRONICS
SURANJAN SARKAR
AVP&HEAD- QSHE&SYSTEMS
SADANAND PATIL
SR. MANAGER – O&M
(SAVALSANG)
PRAKASH SALUNKHE – AM
OPERATION & MAINTENANCE
SANKARLIGHAM– SR ENGINEER
OPERATION & MAINTENANCE WTG -
GAMESA
KISHORE KUMAR
AM– QSHE & SYSTEMS
HSE
SHIVANAND P K
DM – QSHE & Systems
BOB SMITH
Director, Head – Asset Management &
Future Business
SHARAD MORE
SS INCHARGE -MYTRAH
APPROVED BY
VICE PRESIDENT – O&M
SECUTIY
SANGAPPA – SUPERVISOR
PREPARED BY
SADANAND PATIL
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
Emergency Response Plan
Plan review number: 00 Date of release: 27 November 2017
Name Org Unit
Prepared by: Mr.NS Rakhesh HSE Department
Released by: Mr.Sankaralingam Site Incharge
Major changes compared to last revision New Plan
Record hard copies (Number and location).
Site Office , Warehouse, SCADA .
Siemens Gamesa Renewable Power Pvt Ltd,
33/220KV Pooling Substation
Savalsung,
Horti,
Vijayapur District,
Karnataka.
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
Contents Emergency Instructions ......................................................................................................................................... 1
1. INTERNAL COMMUNICATION FLOW .......................................................................................................... 3
2. SITE MAPS ................................................................................................................................................... 4
3. BEFORE INCIDENT ……………………………………………………………………………………………………6
4. BUILDING EVACUATION .............................................................................................................................. 7
4 a. Assembly Point Instructions ....................................................................................................................... 8
4 b Assembly Point Registration ......................................................................................................................... 9
5. INJURY / ILLNESS ...................................................................................................................................... 10
6. FIRE INSTRUCTION…………………………………………..……………………………………………………..11
7. ENVIRONMENTAL INCIDENT……………………………………………………………………………………... 12
8. BUILDING DAMAGE. .................................................................................................................................. 13
9. CRIMINAL ACTIVITY. ................................................................................................................................. 14
10. CONTACT LIST ............................................................................................................................................ 15
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
1. INTERNAL COMMUNICATION FLOW ER (Emergency response)Tasks to be performed By Employees Observing the Event.
Sit
e/L
oc
ati
on
e
mp
loy
ee
s.
Assess the situation and mitigate the
risks.
Activate the Site/Location ERP
Follow the instructions in the local ERP
and notify duty holder.
Incident at Site or Location Level
EHS incidents must be reported in KRIMA EHS within 24 hrs. (see PRO 16745 KRIMA EHS Software Application.)
What to do: How to report:
ER (Emergency Response) Tasks performed by Site/Location appointed Duty holder.
Sit
e/lo
ca
tio
n
Ma
na
ge
me
nt +45 99 42 5550
Service center Nuurenberg
If the situation develops and
the impact escalates from level 1 to 2 or 3
Assess the situation based on the impact of the incident and follow
instructions in local ERP.
Handle incident at site level.
Low Impact Level 1
Classify Incident impact
Medium Impact Level 2
High Impact Level 3
Report incident in IR@WP
For incidents <16 24 hours > 16 less than 2
hours. (see PRO-37432
Reporting of significant
incidents in IR@WP)
High impact Level 3 Medium impact Level 2 Low impact Level 1 • Fatality • Kidnapping • Extortion • Civil Unrest • Natural Disasters on site • Sabotage • Loss of location/site
• Incidents potentially resulting in significant injury / hospitalization or multiple casualties i.e. distributed to multiple treatment locations
• Simultaneous activation of more than one Emergency Response Plan within one affected Division/ Business Unit or Regional Country.
• Incidents assessed to have a negative interest of local medias.
• Equipment / IT damage with a potential to stop or significantly delay planned operation when such impact cannot be mitigated within 24 hours or involve a cost of > 10.000 - EUR.
• Industry related incident with potential to affect our operations
• Emergency Services have been called to the site
• Accident/Incident incl. Near Miss - Potential risk ≥ 16
• Risk rate all occurrences immediately!
• First aid cases
Site Duty Holder: Before calling Service center Nurenberg (+4599425550) consider answeres for these questions:
"Who is calling?
"Where did the incident happen?
"What has happened?
"How did the incident happen?
"Which actions have been initiated?
"Is the situation under immediate control (Yes /No)?
Surname? Given name? Business unit? Phone number? Org code or department?
Country? Site or location name? Other description (If relevant)? When did the incident happen (Date, Time)?
Type of incident Injury (Yes / No - which type of injury & how many injured)? Equipment damage? Other (Short description)?
Short description of circumstances in headlines and any additional important information?
Local emergency services called ( e.g. 108 )? Other local authorities notified: (e.g. Riddor, OSHA)?
(If the answer is "No" - description of details not in control - immediate assistance needed)”
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
2. SITE MAPS
Area Address
Siemens Gamesa Renewable Power Pvt Ltd,
33/220KV Pooling Substation
Savalsung,
Horti,
Vijayapur District,
Karnataka.
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
Emergency Escape Plan Building/Office
Location of Antivenom S.No Location Contact person Contact Number
1 SCADA M.Sankaralingam 7349294330
3. BEFORE THE INCIDENT
Emergency instructions These instructions will assist you and your managers to reduce the impact of accidents.
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
General safety • Use common sense, no work is so important that it cannot be done in a safe manner!
• Use your personal protective equipment (PPE)
• If in any doubt then ask your safety rep. or your manager
• Follow your work instructions
• Adhere to rules and guidance for storage of flammable items and other hazardous materials.
• Respect hot work permits
• Keep the work place tidy!
• Never block the emergency evacuation routes or exits
• Do not force fire doors to stay open!
• Be careful with open flames/fire
• Switch off lights and electrical equipment which are not in use
• Check where first aid kits, eye flushes, absorbent materials and firefighting equipment are stored as well as their correct use
• Regularly check storages for leaks
• Report irregularities
• Report all accidents, incidents and near misses – without the reports no lessons are learned and your workplace won’t get safer
• ASK!!!
Refresh these instructions with all new members of staff, when they start in a new area, if you are unsure or if there has been an accident!
Walk through the emergency evacuation route(s) – you won’t have time to study these instructions during an accident!
Be sure you know where the assembly point is located!
4. BUILDING EVACUATION
• When an alarm is activated everybody must immediately leave their position and follow the designated evacuation route and emergency exit to the assembly point.
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
• Do not take anything with you, o Except for a coat if it is safe to do so, – But only if you have it within reach o Personal medication & keys, laptop and PKI – But only if you have it within reach
• On your way out: o To the extent possible stay together in groups from where you evacuate o Close doors and windows o To the extent possible ensure that no persons are left back in the building. o When you reach the assembly point stay together in groups from where you evacuated o Try to obtain overview of individuals from you group/work area and report to the assembly point leader.
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
4 a. Assembly Point Instructions
• First arriving capable individual on the assembly point will take function as Assembly Point Leader until a senior manager arrives and confirms that he/she can take over.
o Assembly Point Leader wears an orange vest
• The Assembly Point Leader is responsible for discipline and actions taken at the assembly point during the evacuation.
• The Assembly Point Leader can appoint helpers (usually taken from the Emergency Response Team) to cordon off, provide first aid etc.
o Helpers wear yellow vests
• Assembly Point Leader ensures that: o Helpers are placed to prevent unauthorized access to the evacuated area o Helpers are placed to prevent unauthorized access to the reception
• Each team will check that all members of their team have been evacuated. o Missing persons must be reported to the assembly point leader, o Assembly Point Leader communicates this to the rescue services (including where the missing person(s)
were last seen)
• If people (e.g. because they could not be moved/were injured) have been left behind o the assembly point leader must be informed of their location and condition
• If the primary assembly point is compromised for any reason the assembly point leader must identify alternative assembly point and foresee relocation of all evacuees.
• The assembly point leader is responsible for: o Communication with Emergency service supporting the incident. o Calling off the evacuation o Nominating individuals as assembly point assistants.
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
4 b Assembly Point Registration
Location of accident/incident Assembly Point Leader: Area Time reported clear Person(s) left behind Comments
Individuals not accounted for (missing): 1
5
2 6
3 7
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
5.INJURY / ILLNESS
STOP THE ACCIDENT
• Consider hazards / risks / own safety • Stop the machines/processes • Switch off electricity • Consider if you have to move the casualty to a safer location
NOTE! IN SOME CASES YOU NEED TO RAISE THE ALARM BEFORE ADMINISTERING FIRST AID
LIFESAVING FIRST AID • Raise alarm by shouting • Check for signs of life (see/feel/listen) • Check for consciousness/breathing • Call an ambulance if required • Free airways (possibly rescue breathing) • Stop major bleedings • Provide ordinary first aid • Monitor the injured person • Ensure that guide has been sent out to meet the ambulance
ALARM • Call 108 / 102 / 08352-270009 • Inform: Who you are and the phone number you are calling from • Request for ambulance • Savalsung wind farm, Horti, 33/220KV SS, Bijapur (KA- India), • Casualties and persons at risk • The Alarm Central will inform you when the conversation is over! • When the ambulance have been requested the Security Guards shall be called/
informed
NON-EMERGENCY REQUESTS FOR MEDICAL ASSISTANCE
• Continue First Aid • Approch nearst hospital • Seek the Advice from medical practitioner • If required take support from site Manager / safety Officer • Inform: Who you are and the phone number you are calling from and inform that we
are coming with an injured person as well as type of injuries.
INFORM/ALARM • In case of an accident the Site Manager / Safety Officer should be called/ informed
ASSEMBLY POINT • During larger accidents it will be beneficial to evacuate the area to create space for our ERT and the rescue services
GUIDE FOR EMERGENCY SERVICES
• Send guide to receive emergency services at the main gate/point of contact • Bring site plans, floor plans, keys and data sheets
OTHER INFORMATION AND CONSIDERATIONS
• Only company approved spokesperson communicate with the press • Gather information (Notes / photos) for the investigation without disturbing the scene
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
6.FIRE INSTRUCTION(
Assess the situation – raise the alarm
FIRE FIGHTING Use the fire extinguishers, fire blankets etc. if safe. The Fire Brigade must be informed even though the fire was put out.
ALARM • Alart manual call point / Siren • Call 108 /101 / 08352-270160 • Inform: Who you are and the phone number you are calling from • There is a fire at: • Savalsung wind farm, Horti, 33/220KV SS, Bijapur (KA- India), • Where the fire is observed • What is on fire • Casualties and persons at risk
The Alarm Central will inform you when the conversation is over!
RESCUE/ EVACUATE • Evacuate immediately when you hear the alarm – never await verification • The ABA Supervisor is responsible for possible verifications (it can be the guard or the
caretaker)
ASSEMBLY POINT • See the site plan
INFORM/ALARM (FOR ALL ALRMS AND FALSE ALARMS)
• In case of an accident the Security Guards / Site Manager should be called/ informed
MAKE AREA SAFE • Close doors and windows • Switch off ventilation and machinery • Switch off fuel supplies etc. • Remove gas bottles • Evacuate/cordon off • Do not re-enter the building without permission from the Assembly Point Leader
GUIDE EMERGENCY
SERVICES
• Send guide to receive emergency services at the main gate/point of contact. • Bring site plans, floor plans, keys and data sheets
OTHER INFORMATION
AND CONSIDERATIONS
• Only the company approved spokesperson communicates with the press • Cordoning off will be done by the fire department. • Take notes / photos to prepare for the investigation of the accident
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
7. Environmental incident
Gain overview – Consider if it’s necessary to make an alarm
STOP THE ACCIDENT • Shut off taps and valves. • Shut of electrical power, stop engines etc. • Cover drain gratings / Restrain for spill with ”cat litter” or other suitable material.
CHECK • Inform the Site Manager: • What type of emission? • Look up the safety data sheet and additional information • What is the extent / what is the risk? • Wear suitable PPE (Personal Protection Equipment) • Use absorption material- / collection equipment to limit chemical spill,
ALARM • Call to Site Manager • Inform: Who you are and the phone number you are calling from • Savalsung wind farm, Horti, 33/220KV SS, Bijapur (KA- India), • and location where the accident has happen. • What type of spill, and if the emission is to: air, soil or water. • If there are injured persons, or any persons or animals in danger. • The Alarm Center will inform you when the conversation is over!
RESCUE/ EVACUATE • Push fire button if evacuation of area is necessary. • Evacuate immediately when you hear the alarm – never await verification. • The ABA Supervisor is responsible for possible verifications
ASSEMBLY POINT • See site plan
INFORM/ALARM (FOR ALL
ALRMS AND FALSE ALARMS) • In case of an accident the site Manager shall be called/ informed
MAKE AREA SAFE
(Always consider own
safety!)
• Close doors and windows • Switch off machines • Switch off fuel supplies etc. • Remove gas bottles • Evacuate/cordon off • Do not re-enter the area without permission from the assembly point leader
ROAD MAP • Send guide to receive emergency services at the main gate/point of contact. Bring site plans, floor plans, keys and data sheets.
OTHER INFORMATION
AND CONSIDERATIONS • Only the company approved spokesperson communicates with the press • Do you require extra help for cordoning off? • Make initial registrations (notes / photos) for the investigation of the accident
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
8. BUILDING DAMAGE.
Assess the situation – think of own safety before acting!
Structural damage Flooding Power failure. (Always consider own safety!)
• Impact assessment - consider: • Stop/prevent the accident/incident
o Risks / Hazards o Switching off power/machines o Prevent damage to property o During storms – open windows doors in the lee side and cover damage in
the wind side o Evacuation/cordoning off o Impact on the production o Invoking Business Continuity Plan o Sending guide to main gate/point of contact o Need for (extra) security guards
• Call in: o Facilities / building contractors o Contractor with pumps / generators o Emergency services o Alarm System Supervisor
• Check: o Service Level Agreement (SLA) with our service providers o That we are given appropriate priority o If we need to escalate call out o Insurance
INFORM/ALARM (FOR
ALARMS AND FALSE ALARMS) • Facility Service on duty phone and Site Manager / Security Guards shall be called/
informed
GUIDE EMERGENCY SERVICES
• Send guide to receive emergency services at the main gate/point of contact. • Bring site plans - floor plans - keys - data sheet
ITEMS FOR THE SITUATION REPORT
• Injuries to person(s) • Building damage • Impact(s) on the environment • Production • Risks and hazards • Where, when, what, who, how Actions (initiated/planned) • Who has been informed so far?
OTHER INFORMATION AND CONSIDERATIONS
• Only the company approved spokesperson communicates with the press • Do you require extra help for cordoning off, the authority will take care of it. • Make initial registrations for the investigation of the accident
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
9. CRIMINAL ACTIVITY.
Assess the situation – think of own safety!
Burglary/Trespassing • Assess the situation and do not get involved/ contact the culprit on less this can be done absolutely safely.
• Observe the situation and call local police • Call Siemens Gamesa Security • Take notes / photos • If safe stay with in observation distance and await arrival of police/ security
Suspicious object • Do not touch or move the object • Evacuate the building / area • Call local police • Call Siemens Gamesa security • Do not reenter the building before access is released by police
MOB THREAT
Savalsung Windfarm,Bijapur (KA -India)
Emergency Response Plan For internal use only
Version 00, 27 November 2017
Unrestricted © Siemens Gamesa, 2008 All Rights Reserved QEHS Management System
Savalsung Wind Farm , Version 00 Ref PH: Emergency
WP
10. CONTACT LIST
24/7 contact option
Security Guards at site office (24/7)
Security Guards
Other relevant contacts for Savalsung wind farm
Name Department Phone Mobile E-mail (optional)
M.Sankaralingam Site Incharge 7349294330 [email protected]
Manikandan Emergency Spoke
Person 8072254400
MANIKANDAN.VENKADACHALAM@siem
ensgamesa.com
Sadanad P Site Manager -
MYTRAH 9880917070 Sadanand M [email protected]
S.Selvan Emergency Spoke
Person 9901310998 [email protected]
NS Rakhesh SAFETY OFFICER 9972998758 [email protected]
S.SIVAKUMAR REGIONAL HEAD,KA 9880985457 [email protected]
Pani Martin InCharge -M/S
Aarudhra 9894564166 [email protected]
FIRE STATION BIJAPUR 08352-270160
AMBULANCE BIJAPUR 102/108
GOVT.HOSPITAL HORTI 08422-283809
Primary health centrer BIJAPUR 08352-270009
BLOOD BANK BIJAPUR 08352-253604
Issued Date t2.| 2018
Our RefNo TC506418000001974
Work Order No 9100006843
lssued to:Mltroh V.yu (Xri$r) Priv.te Limited.# 8001, qcity, S.No:109, Nanakramguda, Gachibowli,Hydersbqd- 500 012, India.Site: Mytrsh Vryu (Krisn.) P.ivrte Limited.Survey No:490/3, Horti Post, Talukar lndi. Districr- Vijayapura.Near Inchgiri villag6586 II7, Krrnataka
Your RefDale 26 l0 2018
DateofMonftoriu 05.1I 2018 Sample Description Ambient Air
Date ofRegistration 08 I I 2018 Sample(s) condition Found Ok
Monitoring Location Site Omce Area
Moniloring Conducred by 11SON LABS
Ambient Temperature oC28 (Average) Wind Direction NE
Weather Condition Clear Flow rate ofcases (LPM) 0.20
S.No.[hitr Test
Results
NationslAmbientAir QuslityStandrrds(NAAOS}
Anrtysis Method
Paniculate Matter (PMro) Fgmr 18_2Respirsble Dust Sampler n€ll}od(IS:s182 P23-2006)
2. Paniculate Matter (PM ,r) rc/m' 24.3 <60 CPCB Guidelines for the measurement ofAmbient At PollutaDts Vol. I, May 201I
3. Sulphur Dioxide (SO:) $dmr 6.8 {80 lmproved Wesl and Geake rn€thod(lS: 5182 P ll - 2001)
Oxiles ofNitrogen (NO, rdm' l9.l <80Jacob and Hocbheiser rmdified (Na-
Arsenite) method (IS : 5182 P VI - 2001)
Ozone (Or) pdm' <5.0 <100 lS 5182 Pan-9 1974
oc"4 t.j3Sr. Chemist AuthoriiChecked by
Vrsox LansEnvironmenlal Consultants &Analyrical Services
Recognised by lSo/iEC 17025:2005 (NABL), MoEF & CC,
FSSAI, NABET{CI,lS0 9001 :2015 & oHSAS 18001 :2007.
AMBItrNT AIR OUALITY TEST REPORT
TEST RESULTS
Page I oflNote:-l. The resuhs ofthe monitored data indicate that the ambient air quality ofthe region in general is
conformity with respect to nonns ofNational Ambient Air Quality sta ards
2. Sanpling & Ana[sis were done as per stasdard method prescribed by CPCB
e
VUQEHS/5, 1O/TR
H.No. 16-11'23/37/A, Flat No. 205, 2nd Floor, Opp. R T A. Office, Musarambagh' Malakpel' Hyderabad - 500 036'
Iet : 040-2454432},24541338, lrob : 98491 10019 / 94408 41338, E-mail : lnfo@ visonlabs.com, vison labs@ gmail.com
NOTE : This Reporl is subiecl to th! t'ffis and condltlons mentloned ov'rletl'
< 100
5.
t2 I1.20r8
Our RefNo TCs064 I 80000039 75
Work Order No 9300006843
Issued to:Myl t V.yo (Krirn.) Priv.r. Limit.d.# 8001, Ocity, S.No:109. Nrmlrrlnsrda ca.hibowlirHyd€rabsd- 500 032, lodia.Sire Mytnh V.yu (KrtD.) Priv.rc Linia.d.Survey No:490/3, Honi Po$, Taluta: lndi. Disrri]!- Vija),lpura,Near Inchgiri village' 586 I 17, Krnutska
Your RefDare 26 l0 20t8
Date ofMoniloring 05 I t.20tE Sample DescriF'on
Date ofRe!istmri,)n 08.1t.2018 Sample(s) condirion Found Ok
CMC
MonitorinS Conducred by VTSON LABS
Ambient Temperature oC 28lAvera8e) Wind D ection
Weather Condition Clear Flow rateofGases (LPM) 0.20
S.No.l'nils T€{I
Results
Nationsl Ambi€ntAirQurlitySrrndrrds
Anxlysis Method
Paniculare Maner (PM ro) pdm' < 100Respirsble Dust Samplcr m€thod
5182 P 2l,Paniculate Marer (PM,r) ll/Irr' 22_3
CPCB Cuidelines for $€ rneasurement ofAmbietu Air Pollutants Vol. 20tI
Sulphur Dioxide (SO, FdmlInproved West and Geale rnethod
5182 P I - 200t
Oxides ofNtrogen (Nq) srmr t8 5Jecob and Hochheis€r rDdified (Na-
Arsenite) method (lS:5182 P VI-2001)
Ozone (Or) Idm] <5.0 < I00 tS 5182 Pan-g 1974
Chcckcd by Sr. Chemist
=-EE=EE-
VrsoN LansEnvironmental Consultants &Analytical Services
Recognised by lSo/lEC 1702512005 (NABL), oEF E CC,
FSSAI, i{ABET{CI,lS0 9001 :2015 t oHSAS 16001 :2007.
AMBIf,]'{T AIR OLALITY TEST REFORT
TEST Rf,SUL'I.s
Page I of I
Note: -l. The resuhs oflh€ rmnitored data indicate that the ambient ah quality ofthe region in geoeral is
conformfty with respect to nonns ofNational Ambient Air Quality sla.dards
2. Sanpling & Anal)sis were done as per stand.rd m.thod pres.ribed by CPCB
ldera
VUOEHS/5, 1O/TR
H.No.1&11-23Y37/A,FlatNo.2O5,2ndFloor,OppFI.T.AOtfice,Musarambagh'Malakpet,Hydorabad-500036'|el I 040-24544320' 24541338, Mob : 98491 10019 / 9.t408 41338' E.mail : lnlo@visonlabs,com, vison.labs@ gmail,com
NoIE : nrl. illgon b tuu.G't to th. t I[s tnd codllont rtrtlotEd ou'rL't'
446
2 <60
'7.1 <80
<80
l
.l
5
lssued Date t2.l L20t8
Our RefNo TC5064 I 8000003976
Work Order No 9100006843
Issued to:
Mytrih Vryu (Krisnr) Privrt. Limited.# 8001, Gcity, S.No:109, NaElrsntsuds, c&hibowti,Hlderabod- 500 032, Iodia.SitG: Mfr.t Vry[ (Kri!r.) Privrtc Limiad.Survey No:490/1, Honi Pos, Taluka: lndi District- VijaFFrra,Near lochgiri village-S86 I 17, Krrn{ska
Your RefDate 26 I0 2018
Date ofMoniloring 05.t t.20t8 Sanple Descripion
Date of Registralion 08.1t.2018 Sarple{s) condnion Found OlMoniloritu! t-ocaiion Krnour Vilhse
Monitoring Cooducted by VISON I-ABS
Ambient Temperature oC 28 (Average) Wind Direction NE
Weather Condition Clear Flow rate ofGases (LPM) 020
S..\"o.tioirs Test
Resulls
N.tioorl AmbieotAir QorlitySlrodrrds(NAAQS)
Aoa't_si! Method
Paniculare Matrer (PM ro) [9m] 40 I < 100Resphable Dusl Sampler method(lS:5182 P 23 - 2m6)
2 Pantulare Mrner (PM ?J) Igm] .60 CPCB Guidelines 6rthe measurement ofAmbienl Air Pollutaots Vol. I, May 201I
lgml 6.6 <803 Sulphur Dioxide (SO?)Improved West and Geake nEthod(lS:5182 P II - 2001)
.1 Oxides ofNit ogen (Nq) pdm' I5 7 <80 Jacob rnd Hochheiser modilied (Na'Arsenite) merhod (lS:5182 P Vt-2001)
pgm' <50 .. t00 lS 5182 Part-9 1974Ozone (Or)
C!r-+@:N1Anthorized lsr ChemistChecked by
-EE=CE+ Vrsols Lass
Environmental Consultants & Analytical Services
Recognised by lSoilEC 17025:2005 I[ABL), LloEt & CC,
FSSAI, NABET-QCI, lS0 9001 | 2015 t oHSAS 18001 : 2007.
A}IBII]NT AIR OIIAI,ITY TEST REPORT
T[,ST REST I,I S
Page I of I
Note: -L The results ofthe rr)nitored dat! indicde thrt the ambient air quality ofthe region in genersl is
codbnnity with respect to nonns ofNetionel Ambi.fl Air Qurlity stardards
2. Saryliog & Analysis were done as per slandard hethod prescrib€d by CPCB
VUOEHS/5. 1O/TR
H.No.16-11-23/37lA,FlatNo.2O5,2ndFlootOpp'R'T'AOtlice,Musarambagh'Malakpet'Hyderabad-H iOii-ZiSCCiiO, ZqSar sga, [,too, ga+gr roorgts44oe qtseg, e-mail: tnfo@visonrabs,com' vison,labs
NOTE : Thi. A.Port lt tubl'cl to lhi t'Im' ind condltlon' m'ntlontd ov'rl'al
500 036.
@gmail.com
I
5.
:
=E-
Vrsou LansEnvironmental Consultants & Analytical Services
Recognised by lSo/lEC 17025:2005 (NABL), MoEF & CC,
FSSAI, NABET{CI,1S0 9001 :2015 & oHSAS 18001 :2007.
Toral A Resuhs tlnit\ .lB
AMAIINt NO|Sf, LCV[[,Sl',
Nore. I D{y rin. s rcctmcd b€Nem 6 !.n. rd 9 p D, Nisit nE i rcclasi hcwd I p.m .nd 6 r.D
2 Non. doidng wd. ddc ss pd 3lr ltd 6.{tod prcdibdl by IS 9E76:lr8l(Rallim.d 20nl)& IS4758:1968
VUOEHS/5, 1O/TR
Issued Date t2 I L20t8Our RefNo TC5064 I 8000003977
Work Order No 9 r00006843
Issued to:Mltrrh Vryu (Rrism) Privrtc Limircd.# 8001 . qcity, S. No: I 09, NalutrarBuda. Cachibowti,Hlderabad- 500 032, India.
Sire: Mltrih V.yu (Kritni) P.iv.re Limired.Survey No:490/3, Honi Post, Taluka: lndi Distrac Vijay"pura,Near Inchsiri villase-5861I7. Xrrnarala
Your RefDate 26 l0 20t8
Monitoring conducted by I'ISON L.ABS
Sn. Orr.D.t.:03-11.2018 r
06.1l.20lE
CMC AdHi.rI).r.: 05.I I l0l a ro
06.11.2018
Krrnlr Yilhg.D.l.:05.ll.20lEto
05.11.201t
Inchcgcri Vill.g.Drl.l 05.11.2018 to
ff.ll.r0t6I 06 00 07.m 126 400
07 00 08 00 492 .11 I
08.00 - (B-00 51.2 4lr 2 4:l l0900-1000 5l.l {ll l
5 10.00 I 1.00 54.1( J t.2 4?.1
1t.00 - 12.00 56 It 52.6 5161 t2.m l3 00 555 50 I
8. t3.m l4 00 564 52.1r 53?t4.00 I5.00 J0.2 ,19 3
l0 l5.m 16.00 54.5 516 50tll t6.00 - 17.00 55 I 5t 7
l: 17.00 - 18.00 516 53.7
ll l8.m t9.00 65 I 6{t (, 519 ,lll lt-1 19.00 20.00 58? 537 478 56.8
20.00 21.00 514 49t 455 167l6 2l.m - 22.00 ,1119 4?0 445
22_$ 23.U) 41 \t .t4 5 412 41_1l718. 23.00 24.00 412 42.2 l9:l
420 401 lrt 179l9 24.m 0l 00
20. 01.00 02.00 lli.l:l 02 fi) - 01 00 t70 16 I 15.2 3.12
139 35522_ l5ll36.023. 04 00,05.t10 t75 157 145
19.0 36.624 05 00 06 00
56.? 52.7t-rq drY da(A).17.9 .18.2l,eo \ist( dB(^) .12.0 .t0.0
Limirs ir dB (A) NiEhtTimeLimits in dB (A) Dit'rime<75 <70Industrial Area(A)
<ss<65(B)<45<55(c) Reside ial Area
<50 <40(D) Silence Zone
eor[Checked byPrQared by
Tel
H'No. 16.11.23l37/A, Flat No.2o5, 2nd Floor, opp' R.T.A, oflice' Musarambagh, Malakpet' Hyderabad - 500 036.', ifr-iisiiio, z.cia1s38, Mob:98491 tOdtS / ga4oe +resg, e-mart : [email protected], [email protected]
NOIE I Thlr B.Pon 13 tubl'ct lo th' itrm! tnd condtilont m'ntlomd ov'l"l'
45.E
49J
I
@4r
=-EE=E-
Vrsox LansEnvironmental Consultants & Analytical Services
Recognised by lSo/lEC 1702512005 (tlABL), MoEF t CC,
FSSAI, NABET.QCI,IS0 9001 :2015 EoHSAS ,l8001
i2007.
AMBI}:NT NOISE OTJALITY MONITORING I,EVIiLS
Total Results. Units: dB
AMBIINT NOISE LIJVUL S TAN DARDS
Nd. I D.v titr t Ed6cd i. p.e , Nig[l i@ is r.d6di i! hrw@ 9 p D .!d 6 i o2 Nois mmilcirs w* do. $ F sund.d ni<r[.d p,wiH by IS 9876:1981(Rammed 2ml) & Is 4753 1968
VUOEHS/s, 1O/TR
Issued Date 12 Il 2018
Our RefNo TC506t I 8000003977-01
work Order 91000061i4r
Issued to:Mytr.h Vr,u (Xrirm) Privrt. Liltitcd.# 80Ol, Gciry, S.No:toS, Nao.karEudq cachibowli,Hlderabsd- 50O 032, Irdia.Siae: Mfrrh V.yu (Krba.) Priv.te Limited.
Taluka: lndi. District- Vijayapura,Karn!trk!
Survey No:490/3, Horti Pon,Near 586t I7
Your RefDate
26.10.20t8
Monitoring conducred byVISON LABS
s.\o YotritorinS TiR M.Lve.r T.dtD.t.: 05.1 l.20lE to 0,6.1 l.20lE
SrvdsrngViLs.D.t.: 05.1t.201t to 06-r r.2or8
06.00 07.fi) l9l 4t) 107,00 08.(xl 42.1 42208 00 -{D 00 44.5 44.5
.l 0900-t000 411 45 II000- 1t.00 48 1r
I1.00 t2.00 4.t.2 41.1'1 l2.m- ll.rx) 411 128
l3.rx) - l4 00
t4.(xl - t5 fi) 410 472lr) 15 00 t6 0t) 4821t 16.00- 17.00 4ll 481t2 17.00 - l,i.m 5U0tl t8.m - 19.00 176ll t9.00 20.fi) 454 50215. 20.00 21.00 4t.2
21.00 22 00 410 44.0
22.1fi 13-OO 41 5
23.Ut 24 U) 189 t9.019 24.00 01.00 165 3rJ.3
20 0l.m- 02. ) l5 I 36.6
ll 02 00 0l 00 162 l4.l01.00 04.00 111 35.4
21. 04.00 -05.u) 15:l t9.021 05.00 - 06.00 llt 2 39.8
Ltq dr\ dB{A) 45.5 :16.6
L€q Nishi dB(A) !7.1 .]6.5
l.inil! in dB (Al Drl Tide l.imib in dB (A) h_ilht Time(A)
{Dl Silmce Zone <50 <40
sr4Authorized StChecked byPrepared by
H.No. 16-11-2r37/A, Flat No. 205, 2nd Floor, Opp. R.TA. Ottice, Musarambagh, Malakpet' Hyderabad - 500 036
Iel:040.24544320,24541338,Mob:9849,|toots/9a4oactsse,[email protected]'vison.|abs@gmail,comNOIE :Thl. Bcport l.subi€cl io tlr' ltm3
'nd conditlom trEnllon'd @'n'd'
L7
3.
t1.lll
@.*
Issled Date 12 l L2018Our RefNo TC5064 I 8000001978
Work Order No 9100006841
Issued to:Mytrrh Vryu (Kri!nr) Priv.tc Limired.# 8m I . qciy, S No: I 09, Nan tranEuda cachibowtiHtserabod- 500 032, Iodia.Site Mytnh Vryu (Kri![.) Privrte Limired.Survey No:490/3. Honi Pos, Taluka: Indi. Disrricl- Vijalapura,
KarnatataNear Inchgiri villase-586 I 17
Your RefDate 26 t0.20lE
Sample description Drirkinr W.t.r Co[.ct d .i CMCBrildirB Mode ofPackine
Appearance of the Sample Clear Liluid Sarple condition of testinS Found OkSample collection date 06.1 t.20t8 Satrple Quantiry I ltrSarnple Coll€.tior Time 02:30 pm Analysis stanins d.le 08 I I 20t8Sample Registrarion dare 08.1 I 2018 Amlysis Complerion dale 12.1t.2018Sarple colle.led by VISON LABS
s.\o ( hrrr(erislic Tesi Method Unils 'I esl Resulls
I pH st 250C lS:1025 pdn ll 1983 RA-2012 1.47 6.5-8.52 Turbidnv IS:3025 Pan l0 1984 RA-200? NTU -:1.0 5-I0l Conducliviry al 2 5!f' IS:3025 Psn l4 1984 P.A-2013
4 TotalSusDmdcd Solids IS: 1025 Pafl l? 1984 RA-2012 <1.0
Tolal DBsolv.d Solids lS:3025 Pan l6 l9E4 RA-2fi)6 50u-?000
IS:1025 Pan 4 l98l RA-2006 <05
7 ISr3025 pan 08 1984 RA-2002
Odor IS:3025 Dan 05 1983
CHEMI(]AL PARAMETELSToGl Alkllinitv ss CaCOr ISr3025 P.n 2l l986.fA-2003 m,f,{! 20
l0 Chlorid.s as Cl' rS:3025 Pan 32 I98f. RA'20()9 rn!"q- l5 250 - t000
o)sll 66 200 - .100ll Subhares &s SO. : IS:1025 Pan 24 l986,RA-2003
Nirrates as NOr lS: lll2J Psn l4 1988 RA-2001 nPtL o6 40 - r00t2
'rq,q,<o 02ll. Phosphales as POa lS:1025 Panll 1988 RA-2003
m.slL ?o 200 600l4 Total Hardness as CaCOI IS: lO25 Prn 2 I 2iI)9
mp'I- 40 '75 - 2Nt5. Calcium as Ca lS: 3025 Pan40 l99l-RA-2009
t0 Io0lS: 3025 Pln46 1994. RA-2003 mc,l-t6ns4- t2.4t7 Sodium 6s Ns IS: 1025 Pnt45 1993. RA-20{Y)
$F/L 04t8. Poussium as K IS:1025 Pan 45 1993 RA-2009
-0 004 t- t.5lS:1025 Pan 60 2008 m!I/{-l9 Fluorides as F
mp4- .:0 04 0.1- IIS:1025 Part 53 2003, RA-200320<0 001 0.00t - 0.002ms,1-2t Phenolic Compounds AIHA 23d Ediriotr 5330D
,J:,all- .0 001 0 005IS 3025 Pan 27 198622 Cvanide as CNo2ms/L <0.001lS 3025 Part 26 198623 Residual Chlorine as CI
0.01n*tl' <0.001lS 3025 Part 41 199224 Csdmium ss Cd0.05ma/L <0.00tIS 3025 Pan 52 200325 Tolal Chromium 5s Cr005<0.02mgLIS 1025 Pan 47 lD426 Lead as Pb
Vrsox LansEnvironmental Consultants &Analytical Servaces
Recognised by lSo/lEC 17025:2005 (NABL), MoEF & CC,
FSSAI, NABET{CI, lS0 9001 :2015 & oHSAS 18001 :2007.
Tf,ST RESULTSPHYSICAI PARAMETERS
VUOEHS/5. 1O/TB
036H.No.16-11-2337/A,FlalNo.2O5,2ndFloor,Opp.R'T'AO'ffice,Musarambagh'Malakpet'Hyderabad-
fel : (YO-2454432O,24541338, Mob : 98491 10O19/94408 41338, E-mail: lnfo@visonlabs com' vison labs
NoTE : Thl. RlPon b !!bl'cl lo th' t'm3 and condilloN nr'ntiql.d ov'rlolt'@gmail.com
Sariple descri ion Drinldng Wrtcr Colhct.d .t CMC Buitditrt
Our RefNo TC50&118000001978
'l'est ]\lethod llnns Tesl R€sullss.\o Charr.t€ristic
27 IS:302s Pan 37 1988. RA-2003 n,EL <0 0l 0 0l28. Z;nc
^s Zn lS 3025 Pan 49 1994 lr,P/L <0 00t 5-t5
29 MaDganese as Mn IS: 1025 Pan 24 2006 ru/L <0 001 _10 - t00t0 Copper as Cu IS 1025 Pan 42 1992 m,/t. <0 001 0.05 - t.53t Nickel as Ni IS 1025 Pan 54 2003 mP]L ?0.001 l0-5032 Boron lS 1025 Pan 57 2005 n,y'L <0 001 10033 lS 13428 Anner K <o 00t 020l4 MiDsral Oil APHA 23'i Enhion 20t2 m.9,4, <0.001 0.0135 Aluminium as Al IS 1025 Pan 55 20Ol mdL <0 001 00316. Mercury as Ha lS 1025 Pan 48 1994 rIPIL <0.0002 00031 Pesticides USEPA <0 001 <0 00118. lS:5402 :2012
39 E Coli IS: l5l8J:2016 cFU/tuhL
,,W@*v, e""+sr ChemistChecked by " I
===l
-
VrsoN LassEnvironmental Consultants &Analytical Services
Recognised by ISO/IEC 17025:2005 (tlABL), MoEF & CC,
tSSAl, NABET{CI,lSO 9001 :2015& oHSAS 1800,l :2007.
Png. 2 of 2
VUQEHS/5, 1O/TR
H,No. ,16..11.23l37/A, Flat No.2o5, 2nd Floor, opp' R.T.A' otfic6. Musarambagh, Malakpel, Hyderabad ' 500 036.
Tet : 0l(,-24544320,24541338, Mob : 98491 t Odt g l g+log tt ssa, e-mail : [email protected]' vison.labs@ gmail,com
NoTE : Thl! Rcporl l. .ubi'ct lo th' t"mt tnd condllion! mlnllontd ov'rl4r'
vdl-CrU/mL
Nol dctcctcd
lssued Date t2.I L2018Our RefNo TC5064 I 8000003979
Work Order No 91000(}6841
Issued to:Myrnh Vryo (Kri!n.) Piiv.t. Limhed.# 8m I . qcity, S.No: I 09, Narukrar8uda CachibolrliHlderahad- 50O 032, India.
Sit : Mltr.h V.yu (Kri.n.) Privrre Limircd,Ho(i Po$, Talukn: lndi. Dbrri(- Vijarapura,
Near
Sufv.y No:49Ol3,
iri viltaSe-5861 17, Krmarska
Your RefDale 20 t0.20lE
Sarqle descriptionDdnkirt W.t.r Colh.t.d .t Eorai
ModeofPacking Pet bolle
Appearance of lhe Sanple Clear Liruid Saryle condition of resting
Sarple colledion date 06. I I 20t8 Sarnple Quantiry lhrSarple Collection Time 240pm Analysis stanins dale 08 r r 20t8Sanple Rcghtrarion dstc 08.11.2018 Anslysis ComDletion dar. 12.I r 2018
colllcred VISON I,ABS
'I-est Mr(hod Ilnili 'I-esi Rrsulls
I DH at 25oC IS:3025 pfi ll l9E3 RA-!012 7.15 6.5 - 8.52 Turbidny IS:1025 Pa( l0 1984 RA-2002 NTU 5-r01. CondudilnY ar 2soc IS: 1025 Pan 14 l9E4 RA-2013 62
4 Toral Suspmdcd Solids IS: 3025 PEt l7 1984 RA-20125 Tolrl D,ssollcd Solids lS:1025 Pan 16 1984 RA-2006 4l
Cotour IS:1025 Part 4 1983ItA-2006 Ha7en <05 5007 lS:1025 pan 06 l9E4 AA-2002
Odor IS:1025 pan 05 l98l( HEIlIICAL PARA}tETERS
Totll Altilinity es C.CO IS:302! Pd 23 l986.RA-2m3 ry./L IE
Chlorid.s rs Cf n,sl-IO rS:3025 Prn 32 1988. RA-2009 1.5 250 . 1000
ll Sulphares as SOr i IS:1025 Pan 2.1 l986,RA-2003 m,+{- 09 200 - 400
l2 Nitrates as NO IS:1025 Pan 14 1988. RA-2003 rnPJl, 0l 40 - I00l3 Phosphales as POa IS:3025 Part I I 1988, RA-2003 r,tqll- <0 002
t4 Tolal Hardncss as CaCOr IS:1025Fan2l2Ul9 nltlL t0 200 600
mc,/L 40 't5 - 2Nt5 Calcium as Ca IS:3025 Pan40 l99l P!q-2009
lSr 1025 Pan 46 1994, RA-2003 nc|,- 2.1 .10 100l6 Magn€sium as Mg
l7 Sodiun as Na IS:1025 Pan 45 1993 RA-2009 rnp,lL 4.0
mr,/L 0.2l8 IS: l02J Pan45 l99l RA-20@
lS:3025 Pan 60 2008 w,a, ro 004 l-1.5t9nsn- <0.04 0.1- l20. lron as lre IS:1025 Pan 53 2001. RA-2003
mq/L ..0 001 0 00t -00022t Phenolic Compounds A?HA 2ld Edition 5330D
ms/L .:0 001 0 0052.2 Cvanide as CN IS 3025 Pan 27 1986
.:0 001 0:lS 1025 Parl 26 1986 mc/L23 Residual Chlorine as Cl-mc/t, <0 001 0 0lCadmium as Cd IS 3025 Palt41 1q]221
005,l:,s,lL <0.00r25 Total Ckomium as Cr IS 1025 Pan 52 2m3
005mp,/L <0.0226 L€ad as Pb IS 3025 Pan 47 19114
-EE
-
Vrsou LansEnvironmGntal Consultants &Analytical Services
Recognised by lSo/lEC 17025:2005 (NABL), [toEF E CC,
ESSAI, NABET{CI,lS0 9001 r2015 &oHSAS 18001 :2007.
TEST RtrSULTSPIIYSICAL PARAMtrTtrRS
VUOEHS/5, 1O/TR
H No. 1 6- 1 23t31/4, Flal No. 205. 2nd Floor B, IA, Office, Musarambagh, Malakpel,
338, Mob 9849 '1 001 9 94408 1 338, E-mail lnfo @ visonlabs.comTel o40-24544320 24541
NOTE
Sanple dBcription Drintins W.l.r CoIcrt.d .t Ho.ti YiLg. Ph Ar.r
Our RefNo 1 C5064 I 8000001979
( hsrrclerhtic Test MethodS.No tinirs
27 1S.3025 Pan l7 1r88. RA-2001 mgr- <0.0I 00l28 Zin as Zn IS 3025 Pan 49 1994 msr- <0 001 5- 1529 IS: 3025 Pan 24 2006 ms/L <0.00t l0 - too10. IS 3025 Pan 42 1992 lI,91- <0 001 0.05 - t.5rl Nickel as Ni lS 1025 Pan 54 2003 ln-g'l- <000t 1.0-5032 Boron IS 1025 Pan 57 2005 m,y'L <0 001 looll Anionic D€ter,aents IS 13428 Ann€x K m14L <0.00r 020l4 MineralOil APHA 23d Edirrco 20t2 nt44. <0 001 0 0ll5 Aluminium as Al IS 3025 Pan 55 2001 lr,sll- <0 001 001l6 Mercury as HE IS 3025 Pan 48 1994 ,,:.s/L <0.0002 000l7 Pesricides USEPA lgrL <0.001 L0 001l8 IS:5402 :2012 CFU/mLl9 E CoU IS: 15185 :2016 CFU/ l0lhnl
N
6n*il- AP'F ,.hIChmked bv sr Ch€mist
:
-EE=E-
Vrsox LansEnvironmental Consultants & Analytical SeNices
Recognised by lSo/lEC 17025:2005 (tlABL), itoEF t CC,
FSSAI, I{ABET{CI, ISO 9001 :2015 t oHSAS 18001 : 2007.
Page 2 of 2
Ir
VUOEHS/5. 1O/TR
H.No. 16-1 1-23l37lA, Flat No 2O5, 2nd Floor' Opp. R.T A. O,tlice, Musarambagh' Malakpet' Hyderabad - 500 036'
kl : o;4o-2454432l,24541338, Mob : 98491 t OOt S / gaaog +t sgg, e-mait : tnlo@ visontabs.com, vison.labs @ gmail.com
NOTE :rhB FePon i. subist to th' i"mt lnd condltlon' m'ntlon'd @'ri"l'
Issu€d Dare 12.lr 20l8Our RefNo TC5064 I 8000003980
Work Order No 930000684:l
Issued tr':
Mytrih Vryu (Krittr.) Privrtc Limited.# 80O1, qciy, S.No:109, Nanakarnguda, Gachibowli,Hferabad- s00 032, India.
Sire: Mytr.h Vryu (Kri!n.) Privrt€ Limir€dSurwy No:490/3, Horti Post, Taluka: bdi. Disrricl- Vijalqura,
villagc-586 I 17, f\arnatakaNear
Your R€fDale 26 10.2018
Sarple des.riptionD.inkiog W.ter Colhcted rtVijrypln Cu6! Ho$. Mode of Pscking
Appearance of lhe Sarple Clear Liquid Sampl€ condition of resring Found OkSample coUection dale 06.I1.20I8 Sarple Quantiry lhrSanple Collection Time l:30 pm Analysis slanina dare 08. t I 2018
Samplc Rcgistrdion dste 08 I I 20 t8 Ar8lysis Coflpleliotr dste l2.l1.20t8Sanplc collccled by VISON LABS
s.i\o Chrrrc(€ristic Test Nlelhod linits Test Resulls
I pH ar 25uC ISr3025 pan Il l9rll RA-1012 6.5,8.52. Turbrdily lS:3025 P.n l0 l9ll4 RA-2m2 NTT] <t.0 5- 10l Conductivilv at 2soc IS:3025 Part 14 l9li4 RA-2011 ll5I TolalSuspmded Solid! IS:1025 Pan l7 1984 RA-2012 MPJL
Total Dissolvcd Solids IS:1025 Pan 16 1984 RA-2m6 nell- J00-2000a IS:3025 Pan4 l98l RA-20fi,7 IS:1025 psn olJ l9E4 RA-2002x Odor IS:1025 pon05 1983
CHtrMICAL PARAMEl'ER5Total AlkaliDftv as CaCOI IS:3025 Pon 23 l9tl6. RA-2003 mg,/L 20
l0 Chlo.ides as Cl' IS:3025 Pan32 198,1. RA-2txl9 mCrl- :s 250 - t 000
II Sulphates as SO. 1 ISr 1025 P.n 24 l986.RA-llx)3 mg!,I, 5.5 200 - 400t2 Nirrates as NG IS:302J Pan 34 l9li8. RA-20lrl m.!,1- 03 40 - 100
l.l Phosphates a5 PO{ IS:3025 Pan 3l 1988. RA-2001 mp{: <0 02
t4 Total Hardness as CaCOI IS:1015 Pan 2l 2ul, ms{: :0 200 600
l5 Calcium as Ca IS: 3025 Pd 40 1991. RA-2009 ms/L ,10 '75 ,20016. Magnesium as Mr ISi1025 Pld 46 1994. RA-2Ui3 m,atr 2.4 30 - t00t7 Sodium as Na ISr3025 Prn 45 l!93. RA-2m9 tl,r.E/L I8.4
l8 Potassium as K IS:1025 Pan45 1991. RA-2{x), n.stL 02.
l9 Fluorides as F IS:3025 Pan 60 2008 md- <0.00.t 1 15
20. Iron as [e IS:3025 Pan 53 2(xi3. RA'2m3 ,,:,z/L <0.M 0.:l - I<0 001 000t -00022t Phenolic Compounds APHA 23d Eduion 5ll0D m,q/L
lS]025 Pan 27 l!tr6 n:.14q- <0.001 0 00522. Cyanide as CN
23 Residual Chlorine as Cl' IS 1025 Pan 26 19116 r,r,s/L <0.001 o2rr.qfl- <0.001 0.ol24. Cadmium as Cd IS 1025 Pan4l Itr)2
0.05To.al Chromium as Cr lS 3025 Pan 52 2lnl itpl- <0 00125
005lS 3025 Pad 47 I{r4 mp'I- <0.0226 t ead as Pb
-E=E
Vrsox LansEnvironmental Consultants & Analytical Services
Recognised by lSo/lEC 17025:2005 (NABI-), lroEF & CC,
FSSAI, NASET{CI,lS0 90{l :2015 E oHSAS 18001 r2007
TEST RESTJLTSPHYSICAL PARAMtrTERS
o
VUQEHS/5. 1O/TR
H.No. 16-11'23/37lA, Flat No. 205, 2nd Floor' Opp. R.T.A. Otlice, Musarambagh' Malakpet' Hyderabad -
fel.0)40-24544g20,24541338,Mob:9849110019/9440841338,E-mail:lnfo@visonlabs'comvison'labsNOTE : Ihis F€pon i5 subiei io th' l"mt and condltlon3 m'ntlor'd d'rl€al'
@gmail.com