    TERMS OF REFERENCE FOR INDEPENDENTENGINEERS FOR PPP PROJECTS

    BY

    PRABIR DATTA,B.Sc,F.I.E(I)CONSULTANT CHARTERED MECHANICAL ENGINEERVISITING FACULTY AND SENIOR CONSULTANT/INDIAN MARITIMEUNIVERSITY,KOLKATA CAMPUS.SENIOR CONSULTANT/JACOBS--CONSULTING ENGINEERING SERVICES (I) PVTLTD,GURGAON.SENIOR CONSULTANT/BMTCI,AHMEDABADLIFE FELLOW/INSTITUTION OF ENGINEERS(I)LIFE MEMBER/CONSULTING ENGINEERS ASSOCIATION OF INDIA,NEW DELHI(FIDICAFFILIATED).SENIOR CONSULTANT/INDIAN PORT ASSOCIATION,NEW DELHITECHNICAL ADVISOR/INTERNATIONAL SEAPORTS(I) PVT LTD.

  • 8/12/2019 Independent Engineer

    2/4

    2

    TERMS OF REFERENCE FOR INDEPENDENT

    ENGINEER

    The Scope of services of the Independent Engineer (IE) would broadly

    cover the Construction stage of the project till commissioning.

    The Indicative Terms of Reference are as follows :

    The IE shall provide the following services during the construction period :

    Regular reporting of physical progress in construction upto

    commissioning in line with the capacity build-up plan and schedule

    for implementation.

    Assessment of variation in orders & contracts and its implication on

    the technical aspects of the projects.

    Reporting and certifying physical performance testing andacceptance provisions.

    Monitoring and certifying compliance with Concession Agreement

    and other regulatory requirements.

    The Independent Engineer is required to certify the structural safety

    and adequacy, commensurate with the design parameters and also

    with further requirements due to use of any specialized equipment

    the licensee proposes to install either at present or in future.The Independent Engineer shall also certify the constructed

    structures for their strength, stability and safety by specialized

    supervision for the construction of the berth & ancillary facilities.

  • 8/12/2019 Independent Engineer

    3/4

    3

    The licensee shall submit programme in the form of Bar Chart for

    completion of the project including designs and drawings to theIndependent Engineer and Licensors. The Bar Chart shall contain

    completion of key miles stone bases on the accepted proposal under

    this Agreement.

    The licensee shall submit designs and drawings to the Independent

    Engineer according to the approval programme shown in the Bar

    Chart.

    The Independent Engineer shall review the designs and drawingssubmitted by the licensee and endorse for approval of the licensor

    according to provisions of Clauses of the License Agreement.

    The licensee shall submit monthly progress report to the

    Independent Engineer and the licensor. The Independent Engineer

    shall hold progress review meeting within a week of the date of

    receipt of monthly progress report. Format for monthly progress

    report shall be approved by the Independent Engineer in

    consultation with the licensor.

    The Independent Engineer shall prepare minutes of meeting of the

    progress review meeting and circulate the same to the licensor and

    the licensee highlighting therein the slippage and suggested

    corrective activities to cover up the same.

    The licensee shall submit revised Bar Chart and or Catch up Plan

    incorporating the suggestion of the Independent Engineer to the

    licensor and the Independent Engineer.

    Licensee shall submit order letters issued to different vendors along

    with respective tender documents to the Independent Engineer.

  • 8/12/2019 Independent Engineer

    4/4

    4

    The Independent Engineer shall examine the order letters and

    corresponding tender documents in the perspective of approved

    design and drawing and time schedule specified in the Bar Chart.

    In the event that the Independent Engineer has found any deviationand/or discrepancy, it shall promptly and without any undue delay

    notify the licensee or its objection, seek clarification or suggest

    changes or modifications or corrections thereto under intimation to

    the licensor. Thereupon, the licensee shall provide necessary

    clarifications to the Independent Engineer after incorporating the

    changes, modifications or corrections suggested by the Independent

    Engineer. If the Independent Engineer does not object to theclarifications submitted to it by the licensee within 14 days of

    submission the Independent Engineer shall be deemed to have

    approved such clarifications and the licensee shall be entitled to

    proceed with the work.

    The consultant is required to indicate no. of days of deployment of

    the IE per month on weekly basis.

    The consultants are to quote retainer fees on monthly basis.

    The engagement will be for a period of approx. 15-18 months for

    Construction Stage, till commissioning.