Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing...

44
INCREASING EFFICIENCY IN THE HOUSTON FIRE DEPARTMENT PERMITTING SECTION USING LEAN SIX SIGMA

Transcript of Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing...

Page 1: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

INCREASING EFFICIENCY IN THE HOUSTON FIRE DEPARTMENT PERMITTING SECTION

USING LEAN SIX SIGMA

Page 2: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

BACKGROUND

Houston Fire Department Permitting Office

• Provides fire alarm and fire prevention permitting for

the City of Houston

• Includes 7 Customer Service Representatives (CSRs)

and 2 supervisors

• Primary duties include opening and processing mail,

processing walk-in customers, answering phones,

sending invoices and other general office duties

Page 3: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

METHODOLOGY

Define Measure Analyze Improve Control • Problem /

Mission

Statement

• Define Project

Scope

• Observe

• Invoice

Printing

• Mail

Processing

• Permit Issuing

• Create Process

Map

• Time studies

• Sendback mail

analysis

• Mail Batch

analysis

• ILMS issue

breakdown

• Just Do It

(phone system)

• Develop future

state

• Reassignment of

Job Duties

• Standard Work

Implementation

• Monitor new

Sendback log

• Monitor Standard

Work

• Monitor Mail Batch

processing

Page 4: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

DEFINE

Page 5: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

DEFINE: PROBLEM AND MISSION STATEMENT

Problem Statement: Due to recent compliance efforts, the Houston Fire Department Permit Office is aware that mail in permits will increase by at least 15 percent in the next 3-4 months.

With a diminished staff and a lack of standard work, the increased workload cannot be handled appropriately, leading to possible customer complaints, backlog issues and downstream confusion among fire inspectors.

Mission Statement: To reduce the inefficiency of mail processing to process a workload increase of 15 percent with the existing staff over the next 3-4 months (ending June 2013).

To reduce the average time to print invoices from 4-8 hours to under 1 hour, resulting in time savings of 75-87% by March 2013.

Scope: The Project Scope includes identifying opportunities for efficiencies in fire prevention and alarm permits mail processing and invoicing. This includes addressing standard work, reassignment of duties, invoicing, sendbacks and the phone system.

Page 6: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

Supplier Input Process Output Customer

Facility Owner

Permitting

Supervisor

Fire Inspector

Mailed

Permit

Request

Annual

Renewal

CSRs

Supervisors

Computers

Databases

1. CSR sends invoice to

customer

2. Customer receives

invoice

3. Customer renews

permit via mail

4. Supervisor receives

and distributes mail

5. CSR inputs permit

into ILMS or Smart

CM

6. CSR prints permit

7. CSR mails permit

8. Customer receives

permit

Invoice

Permit

Receipt

Facility

Owner

Fire inspector

6

DEFINE: SIPOC

Page 7: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

MEASURE AND ANALYZE

Page 8: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

8

MEASURE: CURRENT STATE PROCESS MAP FIRE PREVENTION PERMITS MAIL PROCESSING

HFD Fire Prevention Mail Process

CS

R 2

FIR

E P

RE

VE

NT

ION

CS

RS

up

erv

iso

r

Yes

No

Yes

Mail contain

all of the

req’d info?

Enter date

received into

spreadsheet

Choose pile and

add up $ amount

on outside of

envelope

Write $ amount

on outside of

envelope

Put each

envelope in 1 of

6 piles

Double check

totals

Time Stamp mail

contents

Write NC or NP

on the envelope

Take checks

and sales orders

to the cashiers

Enter

assignments into

Mail Batch

spreadsheet

STARTOpen All

Envelopes

Hand out

assignments

Pick up

documentation

from cashiers

Give checks and

sales orders to

Vickie

Go to the 205

screen

Print slip (from

10 key

calculator)

Is Mail a

SendBack?

Open project

number in ILMS

Mail original

documents and

cover sheet to

customer

Create Sales

OrderYes

All Checks

Processed?

No

Open and examine

mail to determine if all

information was

provided by customer

N

Complete send

back cover

sheet

Make copies of

all materials

being returned

Provide copies

to CSR

responsible for

completing the

Send Back log

SOMETIMES

All

Sendbacks/

Mail

completed?

No

ENDYes

Enter Check and

Application

details in the

Send Back log

Shred copies

Give

applications to

another CSR for

scanning

Make comments

in the 103

screen

SOMETIMES

Go to Mailbox

and retrieve mail

NP – No Paperwork

NC – No check

Other Dept.

1. Fire Prevention

2. Fire Alarm Permit

3. Standbys (Supervisor keeps)

4. False Fire Alarm Fees

5. HazMat fees (Supervisor keeps)

6. MiscDone for tracking and

reconciliation.

Number of Checks

Monetary amount

assigned to each CSR for

reconciliation purposes

Just a cursory review of

mail. Not a thorough

review.

All info

available to

process

permit?

Y

Checks

Only?

Project #

on Check?

Y

Statement/

Invoice # on

Check?

Go to 225

screen in ILMS

Use the

Statement/

Invoice # to

locate the

Project Number

N

Y

Situs Address

on Check

Use Address to

locate project

number, if

possible

Project

Number

located?

Y

N

Y

N

Y

Missing

Affidavit?

Call the

customer

Can

customer

correct

issue?

Wait for

Customer to

correct issue

N

SOMETIMES Y

N

Prepare end of

day processing

sheet

Give to CSR to

distribute to

CSR that

created each

batch

Identify which

CSR made the

batch 10KEY slip used to identify the CSR

that created the batch originally, if

that is not available log into ILMS to

find out who created the batch (just

need to check the first receipt in the

batch)

Assign batches

to the relevant

CSR

Open the project

in ILMS

Go to 103

screen and

make a note that

permit/receipt

was mailed

All Permits

Printed?Print Permits

Mail Permits and

Receipts

Batch

complete?

N

Y

N Y END

Y

Fire

Prevention?FIRE ALARM

A

B

B

C

C

SOMETIMES

N

Incorrect

Check

Amount?

SOMETIMES

SOMETIMES

(cashiers process

checks, print permits

and receipt, and send

Vickie an email) 24 hr

turnaround

Page 9: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

9

MEASURE: CURRENT STATE PROCESS MAP FIRE PREVENTION PERMITS MAIL PROCESSING

HIGHLIGHTED AREAS

Yes

No

Mail contain

all of the

req’d info?

Choose pile and

add up $ amount

on outside of

envelope

Write $ amount

on outside of

envelope

Put each

envelope in 1 of

6 piles

Time Stamp mail

contents

Write NC or NP

on the envelope

Enter

assignments into

Mail Batch

spreadsheet

STARTOpen All

Envelopes

Hand out

assignments

Print slip (from

10 key

calculator)

Go to Mailbox

and retrieve mail

NP – No Paperwork

NC – No check

Other Dept.

1. Fire Prevention

2. Fire Alarm Permit

3. Standbys (Supervisor keeps)

4. False Fire Alarm Fees

5. HazMat fees (Supervisor keeps)

6. MiscDone for tracking and

reconciliation.

Number of Checks

Monetary amount

assigned to each CSR for

reconciliation purposes

Just a cursory review of

mail. Not a thorough

review.

FIRE ALARMA

• Mail is assigned in batches to CSRs by the supervisor on a daily basis

• Mail is opened, batched, tallied by both monetary amount and number of pieces, and given to the CSR • This process takes anywhere from 2-3 hours each morning, resulting

in 14-21 hours of CSR downtime • Mail batch sizes differ from CSR to CSR

2-3 hours each morning

Page 10: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

10

MEASURE: CURRENT STATE PROCESS MAP FIRE PREVENTION PERMITS MAIL PROCESSING

HIGHLIGHTED AREAS

Yes

Go to the 205

screen

Is Mail a

SendBack?

Open project

number in ILMS

Open and examine

mail to determine if all

information was

provided by customer

N

Complete send

back cover

sheet

Make copies of

all materials

being returned

SOMETIMES

Make comments

in the 103

screen

All info

available to

process

permit?

Y

Checks

Only?

Project #

on Check?

Y

Statement/

Invoice # on

Check?

Go to 225

screen in ILMS

Use the

Statement/

Invoice # to

locate the

Project Number

N

Y

Situs Address

on Check

Use Address to

locate project

number, if

possible

Project

Number

located?

Y

N

Y

N

Y

Missing

Affidavit?

Call the

customer

Can

customer

correct

issue?

Wait for

Customer to

correct issue

N

SOMETIMES Y

N

C

SOMETIMES

N

Incorrect

Check

Amount?

SOMETIMES

SOMETIMES

• There is no standard method to process sendbacks 7 CSRs processing 7

different ways

No real definition for a “sendback”

CSRs hold sendbacks waiting for customer to follow up

• The documentation of the sendbacks is not standard or consistent At least 2 different

people documenting

2 different worksheets inconsistently maintained

1-2 minutes per piece

5 m

inu

tes

– 9

da

ys

pe

r p

iec

e

Page 11: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

11

MEASURE: CURRENT STATE PROCESS MAP FIRE ALARM PERMITS MAIL PROCESSING

HFD Fire Alarm Mail Process

CS

R 2

FIR

E A

LA

RM

CS

RS

up

erv

iso

r

Yes

No

N

No

Y Y

N

N

Y

N

SOMETIMES Y

N

Checks Only?

Wait for Customer

to correct issue

Open and examine

mail to determine if

all information was

provided by

customer

Mail original

documents and

cover sheet to

customer

Process RenewalAll Checks

Processed?

Permit Number

on Check?

Scan copies

Lookup Permit

Number in

SmartCM

Missing

Affidavit?

Give checks and

sales orders to

Vickie

Prepare end of

day processing

sheet

Enter date

received into

spreadsheet

Provide originals

to CSR

responsible for

completing the

Send Back log

All Sendbacks/

Mail

completed?

Complete send

back cover sheet

Is Mail a

SendBack?

Double check

totals

All info

available to

process

renewal?

Call the customer

Send applications

to another CSR for

scanning

Take checks to

bank

END

Can customer

correct issue?

Print permit

Enter Check and

Application details

in the Send Back

log

A

B

B

If renewal notice had to be

reprinted, make a comment

of this in Smart CM

YesNCitations

outstanding?

Place permit in

Citation hold folder

Y

YesMail Permits

SOMETIMES

N

Incorrect Alarm

Address

Permit expiration is

measured based on when

Vickie picks up the mail

instead the postmark date on

the envelope

SOMETIMES

N

Incorrect

Application?

SOMETIMES

New Permit: Customer does

not provide the correct count

of actuating devices

Call customer and inform

them that permit is being

held due to outstanding

citations

Enter comments in

Smart CM that

there are pending

citations

Unclear what follow up is done to close these out

Unclear what happens when the customer settles

these accounts, what happens to the previously printed

permits if another CSR processes the citation payment

When the CSR process the citation payment do they

check to see if the permit was mailed and do they mail

the permit?

END

Page 12: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

12

MEASURE: CURRENT STATE PROCESS MAP FIRE ALARM PERMITS MAIL PROCESSING

HIGHLIGHTED AREAS

• There is no standard method to process sendbacks 7 CSRs processing 7

different ways

No real definition for a “sendback”

CSRs hold sendbacks waiting for customer to follow up

• The documentation of the sendbacks is not standard or consistent At least 2 different

people documenting

2 different worksheets inconsistently maintained

Yes

N

N

N

Y

N

SOMETIMES

Checks Only?

Open and examine

mail to determine if

all information was

provided by

customer

Permit Number

on Check?

Missing

Affidavit?

Complete send

back cover sheet

Is Mail a

SendBack?

All info

available to

process

renewal?

Call the customer

B

N

Incorrect Alarm

Address

Permit expiration is

measured based on when

Vickie picks up the mail

instead the postmark date on

the envelope

SOMETIMES

N

Incorrect

Application?

SOMETIMES

New Permit: Customer does

not provide the correct count

of actuating devices

5 m

inu

tes

– 9

da

ys

pe

r p

iec

e

1-2 minutes per piece

Page 13: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

13

MEASURE: CSR WORKLOAD CAPACITY

• CSRs are responsible for processing the daily incoming

mail, sendbacks, handling walk-in customers, processing

outgoing mail and answering incoming phone calls

• Based on how work is being processed by the CSRs

some of them appear to be at capacity

• Note: CP, MV, EB, and WT handle additional

responsibilities not represented in the utilization numbers

CSRAvailable Daily

Minutes (A)

Current Daily

Mail Batch Size

Sendback Daily

Mailing Batch Size

Walk-In Daily

Batch Size

Permit Mailing

Daily Batch Size

Current CSR

Productive

Time (mins/day)

(B)

CSR Utilization

(=B/A)

CP 405 5 7 5 221 55%

DF 405 12 5 2 12 391 97%

ED 405 13 4 13 335 83%

EB 405 7 2 7 7 269 66%

MV 405 4 6 4 176 44%

RW 405 12 7 12 328 81%

WT 405 5 6 5 206 51%

58

Page 14: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

14

MEASURE: SENDBACKS PIECES OF MAIL UNABLE TO BE PROCESSED BECAUSE OF INCOMPLETE

OR INACCURATE INFORMATION

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0

50

100

150

200

250

No

. o

f S

en

db

acks

Fire Prevention Send BacksJuly - Dec 2012

Fire Prevention Checks Cum Sendback %

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0

10

20

30

40

50

60

70

80

90

Expired Permit Incorrect Funds Missing Paperwork

No Affidavit Incomplete Application

Valid Permit Out of City Limits

No

. o

f S

en

db

acks

Fire Alarm Send BacksJuly - Dec 2012

Fire Alarm Checks Cum Sendback %

Page 15: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

15

MEASURE: CURRENT STATE PROCESS MAP INVOICING

• The invoicing process is quite onerous

• Time studies showed it takes 4 to 8+ hours to process

monthly invoices

• Print monthly invoices (1,200-2,000 pages)

• Separate 2 pages (only use 1 page)

• Re-print address, reminder and block over barcode on front

• Re-print affidavit on back

Print 2 Page

InvoiceSeparate 2 Pages

Throw Page 1

Away Mail Invoices

Print the Address

Bar, Reminder and

Black Box on Page

2

Print Affidavit on

Back of Page 2

Page 16: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

16

ANALYZE: ROOT CAUSE ANALYSIS

Overall

Inefficient Mail

Process

Phone Employees

System Process

Lack of standard work

Lack of training

Lack of feedback loop

Absenteeism Incorrect auto-information Lack of answering

Excess work Unclear priorities

Lack of division of

labor

Lack of consistency

No reporting capability

Lack of specific

configuration

Incorrect Invoices

Limited capacity to

control data entry

Incomplete information

Lack of oversight

Page 17: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

17

ANALYZE: CURRENT STATE PROCESS MAP FIRE PERMITS MAIL PROCESSING

• Supervisor takes over 2 hours to distribute mail due to a lengthy control process • Mail is assigned in batches to CSRs by the supervisor on a daily basis • Mail is opened, batched, tallied by both monetary amount and

number of pieces, and given to the CSR • This process takes anywhere from 2-3 hours each morning, resulting in 14-21

hours of combined downtime for the CSRs waiting on the mail

• Mail batch sizes differed from CSR to CSR

• CSRs were not always processing mail by the end of the day

Because of the lack of consistent reporting on mail batches, measuring standard mail batches and processing time was originally impossible

• Obvious sendbacks are distributed into the “normal” mail process

• Each CSR chooses how to process sendbacks as they received them

• Each CSR mails their own finished permits whenever they chose to do so

Page 18: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

18

ANALYZE: TIME STUDY MAIL PROCESSING

• Time studies showed no variation in permit process

time for simple fire prevention permits or fire alarm

permits

• When information was complete and accurate, processing

time was under 2 minutes per piece of mail

• However, when information was incomplete, CSRs

had a variety of ways to handle each piece, thus

causing significant variation and inconsistencies in

mail processing

Page 19: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

19

ANALYZE: SENDBACKS

• Process time varied from 5 minutes to 9 days

• There is no standard method to process sendbacks

7 CSRs processing 7 different ways

No real definition for a “sendback”

CSRs sit on sendbacks waiting for customer to follow up

• The documentation of the sendbacks is not standard or

consistent

At least 2 different people documenting

2 different worksheets inconsistently maintained

• Available records showed at least 10% of daily mail volume

was being sent back

The actual number of sendbacks may be larger since the

handling of sendbacks is not consistent

Page 20: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

20

ANALYZE: CSR DUTIES

DF CP EB MV RW ED WT

Compile FA Sendbacks Fire Alarm Renewal Notices Compile FP Sendbacks Reconciliation FP Renewal Notices (monthly)FP Scans Standbys

False Fire Alarm Notices Vickie's Backup Standbys Inspector Faxes

Monica Backup HazMat

FA Scans

Process Sendbacks Process Sendbacks Process Sendbacks Process Sendbacks Process Sendbacks Process Sendbacks Process Sendbacks

Process Mail Payments Process Mail Payments Process Mail Payments Process Mail Payments Process Mail Payments Process Mail Payments Process Mail Payments

Walk ins Walk ins Walk ins Walk ins Walk ins Walk ins Walk ins

Phone Phone Phone Phone Phone Phone Phone

Mail Permits/Receipts Mail Permits/Receipts Mail Permits/Receipts Mail Permits/Receipts Mail Permits/Receipts Mail Permits/Receipts Mail Permits/Receipts

• 2 different CSRs were compiling sendback information, leading to differences in how the data was collected

• 2 different CSRs were responsible for a weekly scanning of documentation, leading to time away from their desks to complete other tasks

• All CSRs were processing sendbacks, leading to differences in how sendbacks were handled and length of time it took to process them

• All CSRs were responsible for an end of day permit mailing, leading to time away from their desks to complete other tasks

• Some CSRs were not using the mail machine to process the outgoing permit mail

Page 21: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

21

• Root cause analysis outlined several issues with ILMS and the invoice design

• It was determined that the invoice was an important area to fix as it was not meeting the needs of the group, took an exorbitant time to process and was confusing customers • 2 page invoice

• Incorrect Address

• Unnecessary and confusing barcode

• Lack of affidavit on actual invoice

• Unclear permit fee

• Confusing ‘Responsible Party’ language

ANALYZE: INVOICING

Page 22: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

EXAMPLE: INVOICING

Page 23: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

IMPROVE

Page 24: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

24

IMPROVE: FUTURE STATE PROCESS MAP HIGH LEVEL ALL MAIL PROCESSING

MAIL PERMIT PROCESS – HIGH LEVEL FUTURE STATE PROCESS MAP

SU

PE

RV

ISO

RC

AS

HIE

RC

SR

2C

SR

(S

EN

DB

AC

K)

CS

R 1

N

MAIL PERMITS

AND RECEIPT TO

CUSTOMER

CASHIER

PROCESSES

LOG

SENDBACKS

DEFECT

CORRECTED?

SEPARATE MAIL

INVESTIGATE

DEFECTIVE

SUBMISSIONS

FP: SEND NEW

AND RENEWAL

INFO TO

CASHIER

RECEIVE MAIL

PROCESS NEW

AND RENEWAL

PERMITS IF ALL

REQ’D INFO

PROVIDE

PROCESS

SENDBACK

MAIL SENDBACK

TO CUSTOMER

GOOD TO

PROCESS?

Y

N

PROCESS NEW

AND RENEWAL

PERMITS IF ALL

REQ’D INFO

PROVIDE

Y

FA: GIVE CHECKS

AND PROCESSING

SHEETS TO

SUPERVISOR

FP: SEND NEW

AND RENEWAL

INFO TO

CASHIER

FA: GIVE CHECKS

AND PROCESSING

SHEETS TO

SUPERVISOR

Page 25: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

25

IMPROVE: FUTURE STATE PROCESS MAP FIRE PREVENTION PERMITS MAIL PROCESSING

HFD Mailed In Fire Prevention Permit Process – Future State

CS

R 3

(O

UT

GO

ING

MA

IL)

CA

SH

IER

ING

CS

R 2

(S

EN

D B

AC

KS

/RE

JE

CT

S)

CS

R 1

(W

OR

KA

BL

E)

Su

pe

rvis

or

NO

NO

YES

LOG

SENDBACKS

DEFECT

CORRECTED?

SEND CHECKS

AND SALES

ORDERS TO

CASHIERING

PROCESS

SENDBACK

RECEIVE MAIL

INVESTIGATE

DEFECTIVE

SUBMISSIONS

MAIL SENDBACK

TO CUSTOMER

GIVE CHECKS

AND SALES

ORDERS TO

SUPERVISOR

PICKUP TIME WILL BE IN

THE AFTERNOON

INSTEAD OF THE

MORNING.

Y

OPEN AND

CHECK MAIL

FOR

COMPLETENESS

YESGOOD TO

PROCESS?

1. NO COMMENTS ON THE 103 SCREEN

2. ONE CSR DOES THE MAIL

THESE CSRs ONLY

PROCESS GOOD

MATERIAL

MUST FOLLOW SPECIFIC

SENDBACK RULES

USE THE MAIL MERGE

AND A STANDARD LETTER

TEMPLATE

CLIP & TIME

STAMP MAIL

CONTENTS

OPEN

ENVELOPESCAN MAIL BE

PROCESSED?

PLACE IN SEND

BACK BIN

RECORD THE

NUMBER OF SEND

BACKS IN BATCH

ASSIGNMENT

SPREADSHEET

GIVE SEND

BACKS TO CSR

NOTE THE

NUMBER OF

CHECKS AND

PERMITS/

INVOICES

PLACE MAIL IN

EACH CSR’S BIN

RECORD THE NUMBER OF

CHECKS AND PERMITS/

INVOICES IN THE BATCH

ASSIGNMENT SPREADSHEET

FOR EACH CSR

YES

NO

OPEN PROJECT

NUMBER IN ILMS

GO TO THE 205

SCREEN

CREATE SALES

ORDER

CASHIER

PROCESSES

ALL CHECKS

PROCESSED?

UPDATE BATCH

ASSIGNMENT

SPREADSHEET

YES

NO

YESRESEARCH?

NO

CREATE SALES

ORDER

RECORD

COMMENTS IN

ILMS AS

NECESSARY

GIVE CHECKS

AND SALES

ORDERS TO

SUPERVISOR

DO NOT WAIT LONGER

THAN END OF DAY FOR

CUSTOMER RESPONSE

END

PICK UP MAIL

FROM

CASHIERING

PERMIT &

RECEIPT

PRINTED?

SHOULD

PERMIT HAVE

PRINTED?

PRINT PERMIT

MAIL DOCUMENT

(S)YES

NO

NO

YES

END

Page 26: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

26

IMPROVE: FUTURE STATE PROCESS MAP FIRE PREVENTION PERMITS MAIL PROCESSING

IMPROVED AREAS

RECEIVE MAIL

PICKUP TIME WILL BE IN

THE AFTERNOON

INSTEAD OF THE

MORNING.

CLIP & TIME

STAMP MAIL

CONTENTS

OPEN

ENVELOPESCAN MAIL BE

PROCESSED?

PLACE IN SEND

BACK BIN

RECORD THE

NUMBER OF SEND

BACKS IN BATCH

ASSIGNMENT

SPREADSHEET

GIVE SEND

BACKS TO CSR

NOTE THE

NUMBER OF

CHECKS AND

PERMITS/

INVOICES

PLACE MAIL IN

EACH CSR’S BIN

RECORD THE NUMBER OF

CHECKS AND PERMITS/

INVOICES IN THE BATCH

ASSIGNMENT SPREADSHEET

FOR EACH CSR

YES

NO

• Eliminated unnecessary work in the mail sort and assignment process

• Eliminated the distribution of obvious sendbacks to all CSRs

• Reduced time to sort and assign mail by 75% to 30-45 minutes

Page 27: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

27

IMPROVE: FUTURE STATE PROCESS MAP FIRE ALARM PERMITS MAIL PROCESSING

HFD Mailed In Fire Alarm Permit Process – Future State

CS

R 3

CS

R 2

(S

EN

D B

AC

KS

/RE

JE

CT

S)

CS

R 1

(W

OR

KA

BL

E)

Su

pe

rvis

or

NO

NO

YES

Y

YES

THESE CSRs ONLY

PROCESS GOOD

MATERIAL

MUST FOLLOW SPECIFIC

SENDBACK RULES

USE THE MAIL MERGE

AND A STANDARD LETTER

TEMPLATE

YES

NO

YES

NO

DO NOT WAIT LONGER

THAN END OF DAY FOR

CUSTOMER RESPONSE

GOOD TO

PROCESS?

CREATE NEW

ADDRESS IN

SMART CM

PROCESS

SENDBACK

TAKE CHECKS

TO THE BANK

PRINT PERMIT

DEFECT

CORRECTED?

OPEN AND

CHECK MAIL

FOR

COMPLETENESS

INVESTIGATE

DEFECTIVE

SUBMISSIONS

RESEARCH?

ALL CHECKS

PROCESSED?

RECORD

COMMENTS IN

SMART CM AS

NECESSARY

LOG

SENDBACKS

PREPARE END

OF DAY

PROCESSING

SHEET

COMPLETE

RECONCILIATION

SHEETS

UPDATE BATCH

ASSIGNMENT

SPREADSHEET

PREPARE END

OF DAY

PROCESSING

SHEET

GIVE SEND

BACKS TO CSR

TO PROCESS

MAIL SENDBACK

TO CUSTOMEREND

PLACE MAIL IN

EACH CSR’S BIN

NEW PERMIT?YES

LOOKUP PERMIT

NUMBER IN

SMART CM

PROCESS

RENEWAL

FALSE ALARM

FEE

PENDING?

IF FALSE ALARM FEE IS OUTSTANDING, PRINT FALSE

ALARM BILL AND RETURN CHECK TO BUSINESS

REQUESTING FULL PAYMENT (FALSE ALARM FEE AND

RENEWAL)

NEED A FORM LETTER THAT INFORMS THE BUSINESS

OWNER THAT THE PERMIT WILL NOT BE RENEWED

UNTIL THE FALSE ALARM FEE IS PAID. THE CUSTOMER

WILL BE RESPONSIBLE FOR ALL FALSE ALARMS

INCURRED UNTIL THE PERMIT RENEWAL HAS BEEN

GRANTED.

NO

NO

YES

MAIL PERMIT(S)

PROCESS

PERMIT

SAME STANDARD

PROCESS AS IF

ORIGINALLY IDENTIFIED

AS GOOD

MAIL PERMIT(S)

GIVE CHECKS AND

PROCESSING SHEET

TO CSR FOR

RECONCILITATION

GIVE CHECKS AND

PROCESSING

SHEET TO CSR FOR

RECONCILIATION

GIVE CHECKS

AND

RECONCILATION

SHEET TO

SUPERVISOR

Page 28: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

28

IMPROVE: FUTURE STATE PROCESS MAP FIRE ALARM PERMITS MAIL PROCESSING

IMPROVED AREAS

NO

YES

MUST FOLLOW SPECIFIC

SENDBACK RULES

USE THE MAIL MERGE

AND A STANDARD LETTER

TEMPLATE

YES

NO

DO NOT WAIT LONGER

THAN END OF DAY FOR

CUSTOMER RESPONSE

PROCESS

SENDBACK

DEFECT

CORRECTED?

INVESTIGATE

DEFECTIVE

SUBMISSIONS

RESEARCH?

RECORD

COMMENTS IN

SMART CM AS

NECESSARY

LOG

SENDBACKS

PREPARE END

OF DAY

PROCESSING

SHEET

MAIL SENDBACK

TO CUSTOMEREND

IF FALSE ALARM FEE IS OUTSTANDING, PRINT FALSE

ALARM BILL AND RETURN CHECK TO BUSINESS

REQUESTING FULL PAYMENT (FALSE ALARM FEE AND

RENEWAL)

NEED A FORM LETTER THAT INFORMS THE BUSINESS

OWNER THAT THE PERMIT WILL NOT BE RENEWED

UNTIL THE FALSE ALARM FEE IS PAID. THE CUSTOMER

WILL BE RESPONSIBLE FOR ALL FALSE ALARMS

INCURRED UNTIL THE PERMIT RENEWAL HAS BEEN

GRANTED.

PROCESS

PERMITMAIL PERMIT(S)

GIVE CHECKS AND

PROCESSING SHEET

TO CSR FOR

RECONCILITATION

• Created a new definition of a sendback

• Implemented a new direction of what to do when

CSRs encounter a sendback

Page 29: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

29

IMPROVE: SENDBACK RULES

• New definition of a sendback

• New direction of what to do when CSRs encounter a sendback

• New protocols to take obvious sendbacks out of the mail immediately

• Updated and combined sendback log • Created standard reasons

for sendbacks in a drop down menu

• Created new letter with mail merge

Automatic Send Back – no research required:

• Address Change

• Already Paid/Valid Permit

• Business Name Change

• Expired Fire Alarm Permit

• Incorrect Funds

• No form of Payment

• No Longer Need

• No Signature on Check

• Occupancy Issues

• Outside City Limits

• Reinspection Fee Pending

Interoffice Transfer:

• Different Department

Further Investigation – Phone call or ILMS research (24hr. hold max unless directed by Supervisor):

• Customer Owes for Back Years (check with Vickie or Diane)

• Hard Hold

• Missing Paperwork (Check Only)

• Project/Statement/Invoice Number on Check (ILMS research)

• Situs Address on Check (Phone Call)

• Missing Paperwork (Incomplete or Confusing Application)

• New Permit, no Affidavit

• Renewal Permit, Responsible Party Changed

Page 30: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

30

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0

50

100

150

200

250

No

. o

f S

en

db

acks

Fire Prevention Send BacksJuly - Dec 2012

Fire Prevention Checks Cum Sendback %

0%

20%

40%

60%

80%

100%

120%

0

20

40

60

80

100

120

140

160

180

No

. of

Sen

db

acks

Fire Prevention SendbacksFeb - June (MTD) 2013

Total

Cum Sendback %

IMPROVE: FIRE PREVENTION SENDBACKS

Page 31: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

31

IMPROVE: FIRE ALARM SENDBACKS

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0

10

20

30

40

50

60

70

80

90

Expired Permit Incorrect Funds Missing Paperwork

No Affidavit Incomplete Application

Valid Permit Out of City Limits

No

. o

f S

en

db

acks

Fire Alarm Send BacksJuly - Dec 2012

Fire Alarm Checks Cum Sendback %

0%

20%

40%

60%

80%

100%

120%

0

20

40

60

80

100

120

140N

o.

of

Se

nd

ba

cks

Fire Alarm SendbacksFeb - June (MTD) 2013

Total

Cum Sendback %

Page 32: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

32

IMPROVE: STANDARD WORK

Created standard of work

• CSRs • Reprioritized CSR duties and workload

• CSRs processing mail do not process sendbacks

• Assigned weekly sendback processing to one CSR

• Standardized the sendback worksheet (sendback log)

• Implemented sendback rules

• Assigned permit mailing to one CSRs (using mail machine)

• Supervisors • Updated mail batch spreadsheet

• Eliminated unnecessary work in the mail sort and assignment process

• Reduced time to sort and assign mail by 75% to 30-45 minutes

Page 33: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

33

IMPROVE: REASSIGNMENT OF DUTIES

• Realigned priorities and assignments to ensure

standard work

• 1 CSR does all scanning

• 2 CSRs trade off collecting and sending all mail

• 2 CSRs trade off documenting and processing of sendbacks

DF CP EB MV RW ED WT

Mail Permits/Receipts Fire Alarm Renewal Notices Vickie's Backup Reconciliation FP Renewal Notices All Scans (FP and FA) Standbys

False Fire Alarm Notices Monica Backup Standbys NLN to Leticia Inspector Faxes

Mail Permits/Receipts

Process/Document SendbacksProcess/Document Sendbacks

Process Mail Payments Process Mail Payments Process Mail Payments Process Mail Payments Process Mail Payments Process Mail Payments Process Mail Payments

Walk ins Walk ins Walk ins Walk ins Walk ins Walk ins Walk ins

Phone Phone Phone Phone Phone Phone Phone

Page 34: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

34

IMPROVE: CSR WORKLOAD UTILIZATION

• Key changes to the CSR duties and standard work

surrounding sendbacks allows the CSRs to handle the

increased mail volume that has more than doubled.

• CSRs could potentially handle around 3 times as much

mail with current number of employees

CSRAvailable Daily

Minutes (A)

Previous Daily

Mail Batch Size

New Daily Mail

Batch Size% Change

Previous CSR

Productive Time

(mins/day) (B)

New CSR

Productive Time

(mins/day) (C)

Previous CSR

Utilization

(=B/A)

New CSR

Utilization

(=C/A)

CP 405 5 9 69% 221 260 55% 64%

DF 405 12 17 41% 391 225 97% 55%

ED 405 13 21 63% 335 149 83% 37%

EB 405 7 15 122% 269 273 66% 68%

MV 405 4 14 239% 176 146 44% 36%

RW 405 12 21 73% 328 154 81% 38%

WT 405 5 15 183% 206 155 51% 38%

58 111

Page 35: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

35

IMPROVE: INVOICE

• Changes to invoice

• Reduced invoice to 1 page

• Removed barcode

• Added affidavit

• Updated address and phone number

• Clarified permit type and cost

• Clearly identified the ‘Responsible Party’

• CSR now processes invoices in 45 – 60 minutes (approx 86% reduction in processing time)

CITYOFHOUSTONPermit Office· FireSection

Visit us: 1002WashingtonAvenue, Houston,Texas 77002Phone: (832)394-8811

Mail to: Cityof HoustonFireDepartment POBox3625Houston,TX77253

Bill for Fire Prevention Permit

FAILURE TO PAY THIS BILL BEFORE THE EXPIRATION DATE MAY RESULT IN A CITATION.

MCDERMONTT, INC - AUDITORIUM

ABBOTT, FLORENCE757 N ELDRIDGE PKWY

HOUSTON , TX 77040

Statement 0450582Printed: 31-0CT-2012Project No: 12072397

License No: 001496

Permit Address: 757 N ELDRIDGE PKY #FL 14 77079

Permit Type: P2 (Public Assembly)

L ) RENEW THIS PERMIT Enclose Payment in the amount of: $260.00

This permit fee already includes the administrative fee.Please make checks payable to: City of HoustonOur fees are not refundable.

LJ THIS PERMIT IS NO LONGER REQUIRED (Please explain on back)

If any information on this form is incorrect, please make corrections below. This renewal form must be signed by the

responsible person, ABBOTT, FLORENCE, and mailed with your payment.

Company Name: _ _

Mailing Address: _

Mailing City: _ State:_ Zip: _ _

Phone:- ------------ Federal Tax ID:-------- - - - - - - - -Permit Address: ---------------------------ResponsibIe Person Printed Name*": _ _

Responsible Person Signature** : - - - - - - - - - - - - - - - - - - - - - -

**If there is a new responsible person, please complete the affidavit below.**

COUNTY OF HARRIS

888

Deed Restrictions

and Law Compliance

Affidavit

THE STATE OF TEXAS

Before me the undersigned a who being first duly sworn by me

Deposed and said: Type or legibly print name of affiant

I understand and agree that it is my responsibility to comply with all deed restrictions and city, state and federal laws, regulations, or ordinances concerning any

activity authorized by the pennit(s) requested in the application(s) to which this affidavit appertains and concerning any land or place where such activities may be

conducted.

I also understand and agree that the City of Houston , by issuing the permit(s) for which I am applying, does not excuse or approve of any violations of deed

restrictions, or of city, state or federal laws, regulations or ordinance and that any pennit will be void in the event that it is issued in violation thereof .

I fully understand that if any pennit for which I am applying is issued, the City of Houston or any other appropriated entity may institute legal proceedings againstme if I violate any deed restriction. or any city, state or federal law, regulations or ordinance.

To the extent that this affidavit is made on behalf of a Corporation or for the benefit of a corporation or for the benefit of any person(s) other than myself, I certify

that I have advised them of the content of this affidavit and that I am duly authorized to execute the same as the act and deed of the applicant or persons.

NOTARY SEAL

Signature of Affiant Date

Tocertify which. witness my hand and seal of office this _ _ Day of

Notary Public in and for the State of TexasRev 03/13106

Page 36: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

36

IMPROVE: JUST DO IT PHONE SYSTEM UPDATE

• Changes to phone system

• Changed information to include answers to calls most often received

• Updated departmental information

• Updated phone and fax numbers

Page 37: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

37

IMPROVE: OVERALL FIRE ALARM PERMIT INCREASE

0

200

400

600

800

1,000

1,200

July August September October November

New

Renewals

Total

0

200

400

600

800

1,000

1,200

December January February March April

New

Renewals

Total

New Renewals Total

December 463 470 933

January 433 573 1,006

February 444 404 848

March 744 439 1,183

April 453 496 949

2,537 2,382 4,919

New Renewals Total

July 224 457 681

August 194 522 716

September 174 404 578

October 171 603 774

November 174 379 553

937 2,365 3,302

After mailing over 15,500 pieces of mail starting mid-November, new

and renewal fire alarm permit volume increased by 49%, 17% of which

we can directly attribute to the mailing.

Page 38: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

38

IMPROVE: MAIL BATCH SAME DAY PROCESSING

We began tracking same day processing of the mail on February 12, 2013.

• For the first 10 weeks of tracking, (February 12, 2013 – April 30, 2013) 9%

of the mail was NOT processed same day.

• For the following 8 weeks of tracking (May 1, 2013 – June 26, 2013) 5% of

the mail was NOT processed same day

0

1000

2000

3000

4000

5000

6000

7000

8000

Total Checks Processed Next Day Processed

2/12/2013 - 4/30/2013

5/1/2013-6/26/2013

Page 39: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

CONTROL

Page 40: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

40

CONTROL: IMPROVEMENTS DOCUMENTATION AND ERROR PROOFING

• Mail batch log • Simplified log to record daily incoming mail assignments

• Only recording data that is needed

• Sendback log • Standard worksheet

• Standard reason codes in drop down that can be easily tracked

• Standard mail merge

• Pivot table to track monthly sendbacks (ref: slide 30)

Page 41: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

41

CONTROL: IMPROVEMENTS STANDARD WORK POLICIES AND

PROCEDURES

• Processing

• Ability to use Mail Batch spreadsheet to ensure mail is being processed in a timely fashion

• Division of labor ensures that only certain people are

responsible for specific duties

• Sendback log ensures consistency in how sendbacks are

processed and monitored

Page 42: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

42

CONTROL: TRAINING

• All CSRs trained on standard work

• Specific CSRs trained on mail batch and sendback

spreadsheets

• All back-ups trained according to their new roles

• Training documented for future hires

Page 43: Increasing Efficiency in the Houston Fire Department ... - Increasing Efficiency in the...increasing efficiency in the houston fire department permitting section using lean six sigma

43

CONTROL: AUDIT, MONITOR & ALARM

• Audit

• Sendback spreadsheet

• Mail batch spreadsheet

• Monitor

• Supervisor monitors daily activity via mail batch spreadsheet

• Supervisor monitors pareto charts of sendbacks

• Alarm

• Daily activity “diff” column via mail batch spreadsheet