Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have...
-
Upload
ashley-sanders -
Category
Documents
-
view
215 -
download
0
Transcript of Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have...
![Page 1: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/1.jpg)
MICROSOFT: PROJECT ALLUVION
![Page 2: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/2.jpg)
PROJECT ALLUVION
![Page 3: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/3.jpg)
Incentives & Infrastructure
Estimated incentives and Infrastructure cost: $87,000,000
We will have a Development Agreement with Microsoft that will also have a minimum assessment agreement requiring a minimum property valuation of $255,000,000 at the end of Phase IV
![Page 4: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/4.jpg)
![Page 5: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/5.jpg)
Project Description
Four phase data center Area: 154 acres Total investment: $1,126,218,000 Total building size: 1,165,364 square
feet Total employment: 84
![Page 6: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/6.jpg)
Potential Infrastructure Improvements
South 8th Street (old Army Post Rd to County Line Rd)
Pine Avenue to new Army Post Road
![Page 7: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/7.jpg)
Potential Infrastructure Improvements Continued
Pine Avenue upgrades (eastern Corporate Limits to South 8th Street)
Maffitt Road/County Line Road connection (South Veterans’ Parkway to County Line Road)
County Line Road connector to MaffittRoad extension
![Page 8: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/8.jpg)
Water & Sewer
Water line distribution/storage upgrades
Sanitary sewer line upgrades
![Page 9: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/9.jpg)
Services
Relocation of MidAmerican power line
Fiber optic conduit/fiber line installation
Public Safety Facility (to be constructed/equipped as part of TIF District at a date to be determined)
![Page 10: Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will.](https://reader036.fdocuments.net/reader036/viewer/2022070410/56649f005503460f94c16648/html5/thumbnails/10.jpg)
Schedule
Review plans (Phase I only) Grading Construction of Phase 1 Open Phase 1 Future Phases