IN LABOUR APPEAL COURT OF SOUTH AFRICA HELD … · in labour appeal court of south africa held at...
Transcript of IN LABOUR APPEAL COURT OF SOUTH AFRICA HELD … · in labour appeal court of south africa held at...
IN LABOUR APPEAL COURT OF SOUTH AFRICA HELD AT JOHANNESBURG
CASE NO: CA5/2007
In the matter between: SOUTH AFRICAN MUNICIPAL WORKERS 1st APPELLANT UNION (SAMWU) AA EWERTS & 16 OTHERS 2nd to 18th APPELLANTS and KANNALAND MUNICIPALITY RESPONDENT
Judgment
Tlaletsi AJA
Introduction
[1] This is an appeal from a judgment of Nel AJ sitting in the Labour Court
in a trial relating to a dismissal dispute between the appellants and the
respondent. The first appellants contended that the second to
eighteenth appellants (“the individual employees”) who were all
members of the first appellant, a representative trade union
(“SAMWU”), were unfairly dismissed by the respondent on 30
November 2004. The respondent on the other hand, contended that
the dismissal of the individual employees was based on its operational
requirements and was fair.
[2] The dispute concerning the fairness of their dismissal was referred to
the South African Local Bargaining Council-Western Cape (“the
Bargaining Council”). The dispute remained unresolved as at 27
November 2004 and a certificate to that effect was issued by the
2
Bargaining Council on 5 December 2004. The matter was referred to
the Labour Court for adjudication.
[3] It is perhaps apposite to state that the matter was heard by the
Labour Court from 11 to 15 September 2006. Only the respondent
tendered oral evidence.
[4] The Labour Court gave its judgment on 23 January 2007. The Labour
Court found that the dismissal of the individual employees was
substantively fair but procedurally unfair. Although the Labour Court
found the dismissal to be procedurally unfair, it made no order for
compensation and costs.
[5] Aggrieved by that part of the order of the Labour Court relating to the
substantive fairness of the dismissal and failure to make an order for
compensation and costs, the appellants applied for leave to appeal
against “the whole of the judgment” of the Labour Court. Leave was
granted on 28 May 2007.
Factual background
[6] The following facts are either common cause or not in dispute. The
respondent is a municipality established in terms of the Local
Government: Municipal Structures Act 117 of 1998 (“the Structures
Act”). The process of establishing the respondent involved the
amalgamation of several municipalities, namely Ladysmith, Calitzdorp,
Zoar and Van Wyksdorp.
[7] During 2003, representatives of the South African Local Government
Association (“SALGA”) (of which the respondent is a member), the first
appellant as well as its sister trade union, the Independent Municipal
and Allied Trade Union (“IMATU”) entered into a collective agreement
3
termed the Organisational Rights Agreement ("the ORA") under the
auspices of the Bargaining Council. The ORA sought to regulate inter
alia, the organisational rights afforded to the trade unions, the conduct
of collective bargaining and the resolution of disputes at national level.
The agreement was binding on all municipalities affiliated to SALGA.
[8] Clause 7 of the ORA made provision for the establishment of Local
Labour Forums at each workplace. The workplaces in this instance
were the member municipalities. Such fora were compulsory dispute
resolution bodies at the workplaces. Disputes could be referred by
either the trade unions or municipalities to these fora. It is important
to note that the Local Labour Forums were not empowered to deal with
matters that are bargained at national and provincial forums. Their
powers and scope were only limited to matters relating to the work
places and which were not the subject of bargaining at either national
and or provincial level.
[9] During December 2002 SALGA, SAMWU and IMATU entered into a
collective agreement which was commonly known as the Placement
Agreement. Clause 3 of the Placement Agreement required each new
municipality to prepare final organograms of all departments and to
submit it to the Local Labour Forums for consultation prior to their
finalisation by the Councils of the municipalities. Should such
consultation at the Local Labour Forums fail to reach consensus, the
concerned municipality had the right to unilaterally adopt and
implement the aforesaid new organogram.
[10]Following its amalgamation, the respondent produced an organogram
containing the proposed structure for the municipality as envisaged by
the Placement Agreement. This organogram was consulted on in the
Local Labour Forum and agreement was reached. Placements in terms
of the organogram were subsequently effected. The date when the
4
agreement on the organogram and when it was subsequently
implemented are not provided. However, nothing turns on the said
dates safe to note that the respondent had complied with the
Placement Agreement by submitting the final organograms to the
Local Labour Forum for consultation and an agreement was reached.
[11]During March 2004 an organisation known as Zader Municipal Services
was tasked with investigating the parlous financial state of the
respondent. Out of this exercise a report dated 23 March 2004 known
as the “Zader Report” was produced. The report made certain
proposals that included a new organogram for the municipality. The
report stated inter alia that the new organogram had been drawn up in
conjunction with the Municipal Manager and Heads of Departments of
the respondent; that there had not been consultation at the Local
Labour Forum and that the consultation process be completed once the
Local Labour Forum had been reconstituted and its powers defined. It
is important to note that the new organogram had the effect of
rendering at least 28 employees redundant as they would not be
catered for in the budget of the respondent.
[12]During the course of the year 2004 the Member of the Executive
Council (“MEC”) responsible for Local Government and Housing in the
Western Cape Province, acting in terms of Section 106 of the Local
Government: Municipal Systems Act No: 32 of 2000, (“the Systems
Act”) appointed L A Dekker (“Dekker”) and Oppelt to conduct an
investigation into the affairs of the respondent. There were at that
time serious allegations of maladministration at the respondent.
Dekker testified that he is an attorney specialising in Labour Law and
Municipal Law. He had been in the municipal field for about thirty
years and also ten years doing Labour matters. The investigating team
produced a report on its activities dated 16 April 2004. This report
became known as the “Dekker Report”. All relevant stakeholders
5
including the trade unions, councillors, officials and members of the
public participated in the process. Dr Kaap whose entity produced the
Zader Report also made a presentation to the investigating team.
[13]Dekker and Oppelt’s brief were to investigate alleged
maladministration and allegations concerning corrupt activities that
were taking place at the respondent. The investigators were to gather
evidence, make findings and recommendations to the MEC. The
following are some of the findings of the investigation relevant to this
appeal:
13.1 It was found that the recommendation that was made by a
certain municipal finance official who was appointed to assist the
respondent during 2002 about ways to deal with the
respondent’s financial deficit were not as yet implemented by
2004;
13.2 Zader Report had established that the income of the respondent
was below than what was budgeted for, and that there had been
personnel appointed without being budgeted for. The team then
prepared a financial recovery plan that was adopted by the
respondent and approved by the MEC. This plan had also not
been implemented;
13.3 Loans and overdrafts were not being repaid;
13.4 Politicians at the respondent were involved in appointing staff.
Through this unauthorised process they improperly appointed
their family members and relatives;
13.5 Staff appointments were made outside the policy framework of
the respondent. The municipal manager was contrary to policy
framework not involved in the appointment process. The staff
policy framework was only one page and proved inadequate;
13.6 Post levels were not allocated and job descriptions were
incomplete. A glaring example is that of a general labourer at
6
the cemetery at post level 14, who was rewarded by being
elevated eleven notches up to the position of internal auditor by
the Mayor after he testified in the mayor’s defence at a rape
trial. Unsurprisingly, the appointee did not have the necessary
qualifications and experience of internal auditor position;
13.7 There were irregular and ad hoc upgrading of post levels without
changing the content of the post or providing reasons for such
steps;
13.8 Appointments, promotions and upgrading of posts were done by
the Local Labour Forum and submitted to the Executive Mayoral
Committee only for information and without taking the financial
implications into account. The City Treasurer was not even part
of the Local Labour Forum. This conduct together with others
rendered the staff establishment of the respondent to be
unaffordable.
[14] The Dekker Report made a number of recommendations aimed
at improving the situation at the respondent. Those relevant for
this matter included:
that the respondent should create an affordable staff
establishment;
the Local Labour Forum should be reconstituted and its powers
be limited to what was agreed previously at SALGBC;
that a policy framework of the respondent provided for in section
55 and 66 of the Systems Act be revised, improved and
approved by the Council of the respondent;
that any possible dismissal of employees based on operational
requirements that might be considered in terms of Section 189
of the Act be done with the help and advice of the Western Cape
Local Government Association (“WECLOGO”).
The report was handed to the MEC on 16 April 2004.
7
[15] On 21 June 2004 the MEC for Local Government published a set of
directives emanating from the Dekker Report. In addition the MEC
wrote a letter to the Mayor and the Speaker of the respondent’s
Council. In the letters the MEC outlined the findings of the
investigating team and listed directives with time frames that were
to be implemented by the respondent. Some of the directives were
that:
the respondent was to revise and improve its policy framework
in terms of section 55 and 66 of the Systems Act so as to enable
the municipality to perform its statutory functions (by 31 August
2004);
the respondent was to restructure the organogram to make its
staff structure “leaner and more streamlined” cost effective;
the Local Labour Forum was to be revived;
the revised organogram was to be implemented once the Council
had approved it and any possible retrenchments were to be
carried out with the assistance of WECLOGO;
the timeframe set for completion of the process was within three
months.
[16] It is common cause that during April 2004, the first appellant was
advised by the respondent that approximately 28 employees of the
municipality were not catered for in the municipal budget and that,
as a result, the municipality was in financial difficulty.
[17] On 28 April 2004 a Special Council Meeting was convened. Adv.
Etienne Vermaak from SALGA had been appointed to conduct the
consultations for the envisaged retrenchments on behalf of the
respondent. His appointment coincided with the recommendations
of the Dekker Report and the subsequent directive by the MEC that
any possible retrenchments were to be carried out with the
assistance of WECLOGO. Vermaak as well as Mr Besselsen
8
representing ZADER attended the meeting. A letter from SAMWU
requesting some clarification on the 28 employees not catered for in
the budget was presented to the Council. The Council resolved to
note the letter. Both Vermaak and Besselsen addressed the council
on the process relating to the negotiations about the restructuring
that had taken place up to that stage. They also reported to the
Council what else was still to be done. Council resolved to approve
their report and that the unions be provided with a copy of the
report.
[18] It is common cause that on 7 June 2004 Vermaak held a
consultation meeting with the unions. The meeting was postponed
at the instance of the unions to enable them to study the Zader
report.
[19] A second meeting was held on 21 June 2004 between Vermaak and
the unions. The meeting was also postponed so that the union could
be provided with the Section 106 report commissioned by the MEC.
It is also on this day that the MEC made the Dekker report public.
[20] On 29 June 2004 a council meeting was held. At this meeting a new
organogram was tabled. Council noted the organogram.
[21] On 19 July 2004 a meeting was held between Vermaak and
SAMWU. It would appear that SAMWU was handed a Section 106
report. According to Johan De Wet, who was the Manager:
Administration at the respondent, the purpose of the meeting was
to consult on the organogram. De Wet testified that he does not
know whether the minutes of this meeting were available. He
however recalled that SAMWU’s representatives at this meeting
requested certain documents relating pensions as well as the
Integrated Development Plan (“IDP”) of the respondent. De Wet
9
testified further that the agendas, minutes and other documents of
the respondent were confiscated by the South African Police
Services during an investigation conducted by Dekker during the
year 2000 to 2004. De Wet confirmed that the process for the
preparation for the IDP was undertaken by the respondent with the
participation of all stakeholders, including the unions. The IDP
document was ultimately adopted by the respondent on 24 April
2002 after it lay for inspection and comments for a period of 21
days. He mentioned that it was the responsibility of the Municipal
Manager that the IDP was prepared and that it was ultimately
implemented. The Municipal Manager was also responsible for the
preparation of a budget and organogram of the respondent in terms
of the IDP and to appoint staff that would deliver services in terms
of the IDP. De Wet testified further that the meeting of 19 July
2004 was postponed in order to allow the SAMWU and also IMATU
who was not represented at this meeting time to study the Section
106 report. This arrangement was confirmed by a letter from
Vermaak to SAMWU on 21 July 2004.
[22] On 27 July 2004 Vermaak addressed a letter in terms of Section
189(3) of the Act to the unions in which he, inter alia, advised that:
22.1.the respondent’s Council had approved the new organogram in
principle and would take a final decision on receiving a report
from WECLOGO on 30 July 2004;
22.2 the approval of the organogram by Council would lead to
dismissals of some employees;
23.3 a final request for consultation in terms of Section 189 was being
made.
[23] On 30 July 2004 SAMWU replied to Vermaak’s letter. In their reply
they mentioned inter alia that:
23.1 there had up to that stage not been any real consultation;
10
23.2 the organogram had not served before the Local Labour Forum
and that a date should be set for that purpose to finalise the
organogram;
23.3 the section 189 (3) notice was issued prematurely as the
organogram had not been subject to consultation before the
Local Labour Forum.
[24] It is common cause that there was no response to the aforesaid
letter from SAMWU wrote another letter to Vermaak in which they
stated the following:
24.1 the issuing of the notice in terms of Section 189 was
premature as there had not been a consultation on the
new organogram and also that the organogram had not
been approved by Council;
24.2 the consultation before the Local Labour Forum had been
required by the Zader Report and was also compulsory;
24.3 a meeting before the Local Labour Forum be convened;
that the forum be revised as suggested by the MEC and
the Zader Report; that the organogram then be finalised
and the affected employees be placed.
The letter made further submissions regarding the effect of the new
organogram on service delivery and SAMWU’s proposals on the
organogram as well as their “expenditure limiting strategy.”
[25] In the meantime Mr B G Seitisho had in the beginning of August
2004 been appointed Acting Municipal Manager of the respondent.
He was appointed to assist in resolving the administrative as well as
the financial problems at the respondent. According to Seitisho
there were serious problems relating to lack of service delivery,
“logistical arrangements” and the administration was in a chaotic
state. The MEC responsible for local government had provided him
with a two paged letter containing things that he had to perform.
11
Seitisho was at the same time involved at Kokstad and Plattenberg
Bay municipalities in the same capacity. These Municipalities faced
some challenges as well.
[26] It is not disputed that some of the serious problems discovered by
Seitisho were that the respondent was unable to fund its loans from
the Southern African Development Bank and ABSA bank. Funds
from national and provincial governments intended for projects
were wrongly utilized to fund operational expenses; there were no
funds to run the sewer networks, water purification works and road
maintenance; UIF, PAYE, Pension and Medical Aid deductions were
made from employee’s salaries but were not paid over to their
intended beneficiaries. This meant that book entries on these items
were made without the necessary transfer of fund’s being made.
[27] Seitisho testified that upon his arrival at the respondent he was
briefed by Vermaak on what had transpired in the process that far.
He also met the union leaders who were at that point not satisfied
with the consultation process that was supposed to have taken
place. Some of the union’s complaints were that the organogram
had not been consulted on at the Local Labour Forum. On the other
hand, Vermaak advised him that there had been proper and
adequate consultation. However, Vermaak was unable to produce
minutes of consultation meetings he held with the unions to support
his claim. As part of his mandate was to deal with retrenchments,
Seitisho felt duty bound to report to Council of the respondent that
there might not have been enough consultation process and that to
be on the safe side, he needed more time to sort out the
consultation process.
[28] There was once again no response from the respondent to
SAMWU’s letter dated 15 August 2004 referred to above. However,
12
on 16 August 2004 a Special Council Meeting of the respondent was
held. The following was recorded on the minutes:
28.1 the Acting Mayor notes that the two letters from SAMWU had
been replied;
28.2 Mr Seitisho noted that the respondent had possibly not
consulted sufficiently enough with the union;
28.3 Mr Seitisho requested a week to finalise the consultation with
the unions;
28.4 the matter would be finalised during a Special Council Meeting
to be held the following week.
[29] On 30 August 2004 another Special Council Meeting was held. The
minutes reflected that:
29.1 “it was noted that the “relevant policy” was in place;
29.2 the Council would not take a decision;
29.3 ‘Seitisho opined that the decision rested with him’;
29.4 The Council again would not take a decision.”
[30] On 31 August 2004 the individual employees were handed letters of
termination of employment for operational requirements dated 30
August 2004, with the termination date set as 30 September 2004.
[31] It is not disputed that a series of correspondence passed between
the appellant’s attorneys and Vermaak regarding the unlawfulness
or otherwise of the intended dismissals of the employees. The
appellants demanded that the dismissals be withdrawn and in turn
the respondent’s officials were not prepared to do so.
[32] On 29 September 2004 the appellants launched an urgent
application seeking to have the dismissals set aside. The application
was set down for hearing on 30 September 2004.
13
[33] On 29 September 2004 the respondents held a meeting with the
unions in the evening. A settlement agreement was entered into.
The terms thereof were that:
33.1 SAMWU withdrew its urgent application;
33.2 The respondent unconditionally withdrew the notices of
termination of employment;
33.3 The parties undertook to engage in further consultations
outside of the Local Labour Forum;
33.4 The parties undertook to finalise the consultation by 29
October 2004 and attempt to reach consensus;
33.5 If no consensus is reached the respondent would be entitled
to “initiate the provisions of Section 189 of the LRA;”
33.6 The parties agreed to finalise voluntary retrenchments at their
first consultation which would then form the basis for further
consultations.
In consequence, the retrenchment notices were withdrawn on 30
September 2004. The Agreement of settlement was made an order of
court on 30 September 2004.
[34] It is not in dispute that on 30 September 2004 Vermaak sent a
letter to SAMWU requesting it to urgently inform him of five
possible dates on which they would be available for consultations.
SAMWU did not reply to this letter.
[35] On 5 October 2004 Vermaak sent a further letter to SAMWU noting
their failure to reply to his aforesaid letter and again requesting
them to urgently inform him of five possible dates on which they
would be available for consultations. Once again SAMWU failed to
reply to this letter.
14
[36] On 6 October 2004 IMATU which was also requested to supply
dates for consultations, replied and provided possible dates on
which it would be available for consultations.
[37] On 11 October 2004 Vermaak sent a letter to Seitisho expressing
his concerns about the fact that SAMWU had failed to make itself
available for consultations and that he was going to seek an opinion
from an advocate. The said opinion was subsequently obtained on
12 October 2004. A copy of the letter dated 14 October 2004 from
SAMWU is not provided.
[38] On 11 October 2004 IMATU sent a letter to Vermaak expressing
their concerns that no consultations had taken place and further
requesting an urgent meeting to be held on 15 October 2004.
[39] On 15 October 2004 Vermaak sent a letter to SAMWU in which he
referred to the letter from SAMWU dated 14 October 2004. He
further expressed his surprise that SAMWU failed to attend a
meeting in Ladysmith and furthermore, confirming SAMWU’s
undertakes to attend the meeting to be held on 18 October 2004.
[40] On 18 October 2004 a consultation meeting took place between
SAMWU, IMATU, Vermaak, G J Louw and De Wet. Louw, who was a
financial consultant and also part of the ZADER team, attended the
meeting at the invitation of Vermaak. Louw testified that he
addressed the meeting on the problematic cash flow situation at the
respondent, outstanding debt and unpaid short term creditors. He
further informed the meeting that the respondent was in dire
financial problems and was unable to obtain credit and financial
assistance because of its uncredit worthy position. He was only
called into the meeting at the end in order to make a presentation
15
on the respondent’s financial position. At this meeting his input on
the financial situation of the respondent was not disputed.
[41] It is common cause that a consultation meeting with the trade
unions was scheduled for 29 October 2004 at SALGA offices.
Amongst those who attended were Seitisho, Vermaak and
representatives of IMATU. According to Seitisho the meeting started
by confirming the agenda and thereafter they waited for the arrival
of the representatives of SAMWU. They waited for about two and
half hours. They were telephoned several times and they did not
answer their phone. They later managed to speak to one of them.
He mentioned that they were lost. The representatives of IMATU
became impatient and indicated that they were leaving as they had
waited for a long time and that they had no interest in the proposed
meeting. IMATU representatives indicated further that they were
not going to participate in the meeting.
[42] Seitisho testified further that as they were leaving the premises
they met SAMWU’s representatives at the stairs. He asked one of
them, Mr Baartman who was one of his co-employees in
Plattenburg Bay where they had been. He reported that they had
been lost. He told him that he found it strange that they were all
full time shop stewards and also members of SALGA but they got
lost when they knew where the SALGA offices were. Seitisho
mentioned further that there was no discussion about further
meetings with SAMWU representatives. He denied that SAMWU
representatives requested another meeting. They all left without
having discussed about what was to happen thereafter.
[43] On the same day, Seitisho held a meeting with the Mayor and
Vermaak at the latter’s office. The two reported to the Mayor about
the failed meeting and that they were running out of time and
16
further that the respondent did not have the funds to maintain the
staff component as it was. They also expressed the view that the
appellants were deliberately delaying the process and that the
process had become costly to the respondent. It was then decided
that letters terminating services be issued on the same day as the
time frame set for consultation as per the agreed court order had
come to an end. The selection criteria for the employees to be
dismissed were based on the LIFO principle as previously resolved
at the Council meeting.
[44] As pointed out already the appellants did not tender any evidence
at the court a quo. It was contended on behalf of the appellants
that the decision to dismiss the employees for operational
requirements was taken by Seitisho as the Acting Municipal
Manager and was ultra vires. The reasons why the decision was
said to be ultra vires were based on the following argument:
In the first place it was contended that only the respondent’s
Council had the power to retrench employees; secondly, and in the
alternative, Seitisho was only able to exercise the power to retrench
once a policy had been promulgated by the respondent’s Council
under section 55, 66 and 67 of the Systems Act; and thirdly, also in
the alternative to the first submission, it was contended that
Seitisho and or the respondent was only able to exercise his powers
in accordance with the directions made by the MEC in terms of
sections 106 of the Systems Act.
[45] The Labour Court held that the Acting Municipal Manager was
empowered to appoint employees in terms of the Systems Act, and
when necessary could dismiss the employees of the Municipality.
With regard to the first alternative argument that the Acting
Municipal Manager could only dismiss employees once policy had
been promulgated by the respondent’s Council, the Labour Court
17
held that there was a policy in existence at the respondent at the
time. This conclusion was based on the findings by both the Zader
and Dekker reports that appointments had been made outside the
municipal policy and that those appointments were not budgeted
for. Withregard to the second alternative argument relating to the
directives issued by the MEC, the Labour Court found itself not
persuaded by the argument that the directives issued in terms of
section 106 of the Systems Act constituted statutory framework
within which the respondent had to from that point act upon failing
which its actions would be ultra vires.
[46] Withregard to the procedural fairness of the retrenchment process
the Labour Court held that there had not been sufficient
consultation as required by section 189 of the Act. The Labour
Court found that the respondent had not proved that the appellants’
representatives wilfully stayed away from the meeting of 29
October 2004 and that it would have been reasonable for the
respondent to reschedule the meeting to conclude the consultation
process. By doing so, the Labour Court reasoned, the process would
have complied with the procedural fairness requirements. The court
a quo held further that it was satisfied, in the absence of evidence
to the contrary, that the 17 individual appellants had been properly
selected by applying the LIFO criteria for retrenchment.
[47] Withregard to order of compensation, the Labour Court considered
the role played by the respective parties during the period of
consultation and also what caused the last meeting not to take
place and decided not to order compensation for procedural
unfairness. In doing so, it considered as paramount the following
factors: Firstly, that the employees had a benefit of an extra
month’s income due to the settlement agreement to pursue
consultations for a further month; secondly, the fact that the
18
employees received three weeks salary instead of the “obligatory”
one week salary for each year of service; thirdly, the Labour Court
held that the individual employees were appointed under the
circumstances where they ought not to have been appointed
resulting in them receiving a benefit of income. The Labour Court,
however, held that there was no evidence to suggest that the
individual employees themselves acted improperly for them to be
appointed. As regards costs, the Labour Court held that the
procedural fairness only related to failure to hold one further
meeting which was to a large extend unsuccessful due to the
conduct of SAMWU. For this reason the Labour Court ordered that
each party should pay its own costs.
The appeal
[48] Both in this Court and in the heads of argument filed on behalf of
the appellants, they persisted in the same argument that was
presented in the Labour Court. As regards substantive fairness, it
was argued on behalf of the appellants that the Acting Municipal
Manager did not have the power to dismiss the employees and as
an employee of the respondent he could only acquire such powers
through either legislation or a delegation from the Council. The
Labour Court, it was argued, should therefore have found that the
Acting Municipal Manager acted unlawfully and as such the reason
for the dismissal would fall away. In the alternative, it was
submitted that the Acting Municipal Manager could only act in terms
of a policy directive in place entitling him to dismiss the employees,
and as such policy was not in existence he acted in a vacuum. It
was further argued that the Labour Court should have found that
the directives issued by the MEC in terms of section 106 of the
Systems Act created rights for the appellants and as such the
respondent was obliged to follow those directives.
19
[49] Withregard to procedural fairness the attorney for the appellants
submitted that although there is no appeal against the finding of
the Labour Court, it should have been found that the respondent
failed to comply with the directives from the Dekker Report and that
such a finding would have had the effect of a substantial amount of
money as compensation being awarded in favour of the individual
employees for procedural unfairness.
[50] The appellants do not challenge the Labour Court’s findings that the
respondent was in a financial crisis which necessitated the
dismissals of employees. It was also not their case that the
individual employees were not employed under the circumstances
presented by the respondent through the evidence of its witnesses.
It is also not the appellants’ contention that the individual
employees were incorrectly or unfairly identified for dismissal. In
any case no evidence was tendered by the appellants in the Labour
Court that could support any challenge to the above findings.
[51] It must therefore be accepted that if the three grounds upon which
the appellants are contending the substantive fairness of the
dismissal of the individual employees; i.e. the authority of the
Acting Municipal Manager and failure to comply with the MEC’s
directives, are found to be without foundation, then the dismissal of
the individual employees would have been for a fair reason. Put
differently, the appellants’ only challenge to the substantive
fairness of the dismissal is not based on the financial crisis that the
respondent is in and its actions to restructure its operations to free
itself from the crisis, but on the authority to dismiss and the
procedure followed in dismissing the employees.
[52] The relevant provisions of the Systems Act on which the appellants
base their challenge to the Acting Municipal Manager’s authority are
20
sections 55, 56 and 67. The relevant parts thereof are quoted
hereunder in full for a better understanding of the responsibilities of
Municipal Managers and the framework within which they operate:
“55 Municipal managers (1) As head of administration the municipal manager of a municipality is, subject to the policy directions of the municipal council, responsible and accountable for- (a) the formation and development of an economical,
effective, efficient and accountable administration- (i) equipped to carry out the task of
implementing the municipality's integrated development plan in accordance with Chapter 5;
(ii) operating in accordance with the municipality's performance management system in accordance with Chapter 6; and
(iii) responsive to the needs of the local community to participate in the affairs of the municipality;
(b) the management of the municipality's administration in accordance with this Act and other legislation applicable to the municipality;
(c) the implementation of the municipality's integrated development plan, and the monitoring of progress with implementation of the plan;
(d) the management of the provision of services to the local community in a sustainable and equitable manner;
(e) the appointment of staff other than those referred to in section 56 (a), subject to the Employment Equity Act, 1998 (Act 55 of 1998);
(f) the management, effective utilisation and training of staff;
(g) the maintenance of discipline of staff; (h) the promotion of sound labour relations and
compliance by the municipality with applicable labour legislation;
(i) advising the political structures and political office bearers of the municipality;
(j) managing communications between the municipality's administration and its political structures and political office bearers;
(k) carrying out the decisions of the political structures and political office bearers of the municipality;
21
(l) the administration and implementation of the municipality's by-laws and other legislation;
(m) the exercise of any powers and the performance of any duties delegated by the municipal council, or sub-delegated by other delegating authorities of the municipality, to the municipal manager in terms of section 59;
(n) facilitating participation by the local community in the affairs of the municipality;
(o) developing and maintaining a system whereby community satisfaction with municipal services is assessed;
(p) the implementation of national and provincial legislation applicable to the municipality; and
(q) the performance of any other function that may be assigned by the municipal council.
(2) As accounting officer of the municipality the municipal manager is responsible and accountable for-
(a) all income and expenditure of the municipality; (b) all assets and the discharge of all liabilities of the
municipality; and (c) proper and diligent compliance with the Municipal
Finance 66 Staff establishments
(1) A municipal manager, within a policy framework determined by the municipal council and subject to any applicable legislation, must-
(a) approve a staff establishment for the municipality; (b) provide a job description for each post on the staff
establishment; (c) attach to those posts the remuneration and other
conditions of service as may be determined in accordance with any applicable labour legislation; and
(d) establish a process or mechanism to regularly evaluate the staff establishment and, if necessary, review the staff establishment and the remuneration and conditions of service.
(2) Subsection (1) (c) and (d) do not apply to remuneration and conditions of service regulated by employment contracts referred to in section 57.
67 Human resource development (1) A municipality, in accordance with applicable law and subject to any applicable collective agreement, must develop and adopt appropriate systems and procedures to ensure fair, efficient, effective and transparent personnel administration, including-
22
(a) the recruitment, selection and appointment of persons as staff members,
(b) service conditions of staff; (c) the supervision and management of staff
(d) the monitoring, measuring and evaluating of performance of staff
(e) the promotion and demotion of staff; (f) the transfer of staff; (g) grievance procedures; (h) disciplinary procedures;
(i) the investigation of allegations of misconduct and complaints against staff
(j) the dismissal and retrenchment of staff, and (k) any other matter prescribed by regulation in
terms of section 72. [Sub-s. (1) amended by s. 38 of Act 51 of 2002.]
(2) Systems and procedures adopted in terms of subsection (1), to the extent that they deal with matters falling under applicable labour legislation and affecting the rights and interests of staff members, must be consistent with such legislation. (3) Systems and procedures adopted in terms of subsection (1), apply to a person referred to in section 57 except to the extent that they are inconsistent with that person's employment contract.
(4) The municipal manager must- (a) ensure that every staff member and every
relevant representative trade union has easy access to a copy of these staff systems and procedures, including any amendments;
(b) on written request by a staff member, make a copy of or extract from these staff systems and procedures, including any amendments, available to that staff member; and
(c) ensure that the purpose, contents and consequences of these staff systems and procedures are explained to staff members who cannot read.”
[53] Section 106 of the Systems Act in terms whereof the MEC
commissioned the Dekker Report reads thus:
“106 Non-performance and maladministration (1) If an MEC has reason to believe that a municipality in the province cannot or does not fulfil a statutory obligation binding on that municipality or that maladministration, fraud, corruption or any other
23
serious malpractice has occurred or is occurring in a municipality in the province, the MEC must- (a) by written notice to the municipality, request the
municipal council or municipal manager to provide the MEC with information required in the notice; or
(b) if the MEC considers it necessary, designate a person or persons to investigate the matter.
(2) In the absence of applicable provincial legislation, the provisions of sections 2, 3, 4, 5 and 6 of the Commissions Act, 1947 (Act 8 of 1947), and the regulations made in terms of that Act apply, with the necessary changes as the context may require, to an investigation in terms of subsection (1) (b). (3) (a) An MEC issuing a notice in terms of subsection (1) (a) or designating a person to conduct an investigation in terms of subsection (1) (b), must within 14 days submit a written statement to the National Council of Provinces motivating the action. (b) A copy of the statement contemplated in paragraph (a) must simultaneously be forwarded to the Minister and to the Minister of Finance. [Sub-s. (3) substituted by s. 18 (b) of Act 19 of 2008.] (4) (a) The Minister may request the MEC to investigate maladministration, fraud, corruption or any other serious malpractice which, in the opinion of the Minister, has occurred or is occurring in a municipality in the province. (b) The MEC must table a report detailing the outcome of the investigation in the relevant provincial legislature within 90 days from the date on which the Minister requested the investigation and must simultaneously send a copy of such report to the Minister, the Minister of Finance and the National Council of Provinces.”
[54] The argument presented on behalf of the appellants is that
what is clearly absent from Sections 55, 66 and 67 of the
Systems Act is the power of the Municipal Manager to initiate
a retrenchment exercise or to retrench employees in the
absence of a delegation or assignment from the Municipal
Council. The attorney submitted that it does not appear that
the Council at any stage assigned or delegated its power to
24
implement a retrenchment exercise to the Acting Municipal
Manager.
[55] Counsel for the respondent has refereed us to Chapter 5 of
the Structures Act which outlines the functions and powers of
municipalities. She correctly pointed out that Section 831 of
the Structures Act refers to the functions and powers assigned
to municipalities in terms of sections 1562 and 2293 of the
1 (1) A municipality has the functions and powers assigned to it in terms of sections 156 and 229 of the Constitution. (2) The functions and powers referred to in subsection (1) must be divided in the case of a district municipality and the local municipalities within the area of the district municipality, as set out in this Chapter. (3) A district municipality must seek to achieve the integrated, sustainable and equitable social and economic development of its area as a whole by- (a) ensuring integrated development planning for the district as a whole;
(b) promoting bulk infrastructural development and services for the district as a whole;
(c) building the capacity of local municipalities in its area to perform their functions and exercise their powers where such capacity is lacking; and
(d) promoting the equitable distribution of resources between the local municipalities in its area to ensure appropriate levels of municipal services within the area.
2 (1) A municipality has executive authority in respect of, and has the right to administer-
(a) the local government matters listed in Part B of Schedule 4 and Part B of Schedule 5; and
(b) any other matter assigned to it by national or provincial legislation. (2) A municipality may make and administer by-laws for the effective administration of the matters which it has the right to administer. (3) Subject to section 151 (4), a by-law that conflicts with national or provincial legislation is invalid. If there is a conflict between a by-law and national or provincial legislation that is inoperative because of a conflict referred to in section 149, the by-law must be regarded as valid for as long as that legislation is inoperative. (4) The national government and provincial governments must assign to a municipality, by agreement and subject to any conditions, the administration of a matter listed in Part A of Schedule 4 or Part A of Schedule 5 which necessarily relates to local government, if- (a) that matter would most effectively be administered locally; and (b) the municipality has the capacity to administer it. (5) A municipality has the right to exercise any power concerning a matter reasonably necessary for, or incidental to, the effective performance of its functions. 3 (1) Subject to subsections (2), (3) and (4), a municipality may impose-
(a) rates on property and surcharges on fees for services provided by or on behalf of the municipality; and
(b) if authorised by national legislation, other taxes, levies and duties appropriate to local government or to the category of local government into which that municipality falls, but no municipality may impose income tax, value-added tax, general sales tax or customs duty.
(2) The power of a municipality to impose rates on property, surcharges on fees for services provided by or on behalf of the municipality, or other taxes, levies or duties-
25
Constitution of the Republic of South Africa Act 1996 (Act 108
of 1996) while section 83(3)(a) to (d) of the structures Act
lists the specific functions and powers of municipalities, and
that section 4 of the Systems Act outlines the rights and
duties of Municipal Councils. She submitted that none of the
aforesaid provisions empower the Municipal Council to
exercise the power to initiate a retrenchment exercise.
Indeed, the rights and duties of Municipal Councils are general
in nature and constitute a combination of policy and duties in
respect of service delivery to the communities.
[56] In contrast with the general powers and policy functions of
the Municipal Council, the Structures Act and Systems Act
assign a hands on administrative role to the Municipal
Manager. It is evident from the above quoted sections that a
Municipal Manager is empowered to appoint, manage,
effectively utilise and train staff4; maintain discipline; promote
sound labour relations; to account for all income and
expenditure of the municipality5. The Municipal Manager is
also empowered to, within a policy framework approved by
(a) may not be exercised in a way that materially and unreasonably prejudices
national economic policies, economic activities across municipal boundaries, or the national mobility of goods, services, capital or labour; and
(b) may be regulated by national legislation. (3) When two municipalities have the same fiscal powers and functions with regard to the same area, an appropriate division of those powers and functions must be made in terms of national legislation. The division may be made only after taking into account at least the following criteria:
(a) The need to comply with sound principles of taxation. (b) The powers and functions performed by each municipality. (c) The fiscal capacity of each municipality. (d) The effectiveness and efficiency of raising taxes, levies and duties. (e) Equity.
(4) Nothing in this section precludes the sharing of revenue raised in terms of this section between municipalities that have fiscal power and functions in the same area. (5) National legislation envisaged in this section may be enacted only after organised local government and the Financial and Fiscal Commission have been consulted, and any recommendations of the Commission have been considered.
4 Section 55 (1) (b) – (h) 5 Section 55 (2)
26
the Municipal Council and subject to any applicable law,
approves a staff establishment for the municipality and
provide a job description for each post on the staff
establishment6.
[57] It is in my view logical that the power to appoint, discipline,
manage, utilise and train staff should include the power to
initiate a retrenchment exercise. However, even if this
interpretation may be found to be incorrect, the facts of this
case have shown that the Council of the respondent was at all
times kept abreast of the developments and that at the
Special Council Meeting in August 2004 noted that the
decision to retrench lied with the Acting Municipal Manager
and allowed the process to proceed. The Council also gave
Seitisho additional time to engage in negotiations with a view
to cure whatever defects that may have existed in the
consultation process that took place before Seitisho’s
appointment. The argument therefore that the Acting
Municipal Manager’s actions should be found to be ultra vires
is without merit.
[58] The next issue raised is that the retrenchments could only
take place once there was a policy in place and that in this
instance the respondent had no policy in place. It is not
disputed, as the Labour Court also found, that there was a
one page policy that existed at the respondent. According to
Dekker, that policy was developed in compliance with the
provisions of sections 55 and 56 of the Systems Act. The
Acting Municipal Manager and the respondent’s Council acted
in terms of that policy. The revised policy that was not as yet
approved by Council cannot be taken to have negated the 6 Section 66(1)
27
existing policy before its approval. Furthermore, the fact that
the policy in existence may have been inadequate in certain
respects as Dekker testified does not mean that there was no
policy in place. Appellants’ contention therefore in this regard
is also without merit.
[59] The last alternative argument relate to failure to comply with the
directive of the MEC by the respondent. I find no fault in the
Labour Court’s finding that the appellant’s argument in this
regard is not persuasive. There is no provision in Section 106
of the Systems Act as it was then or elsewhere that gave the
MEC’s letter containing directives statutory powers. What the
MEC was authorised to do was to submit a written statement
to the National Council of Provinces (“NCOP”). It remained up
to the respondent whether the recommendations from the
MEC were followed or not. Although some of the directives
from the MEC required that the existing policy be revised,
improved and approved, there is no evidence to suggest that
the retrenchment exercise was conditional upon the MEC’s
directives. The retrenchment exercise had been initiated by
the respondent and was never challenged. It is also important
to note that the MEC had not taken any steps against the
respondent for its failure to comply with his directives.
[60] This matter must be understood in the context that until the
stage that an application was launched to challenge the
retrenchment process, the parties entered into a settlement
agreement in terms whereof they agreed that the dismissal
letters be withdrawn, the parties to engage in further
consultations outside the Local Labour Forum, the consultations
be finalised by 29 October 2004, and that an attempt be made
28
to reach consensus and that if no consensus is reached the
respondent would be entitled to initiate the provisions of section
189 of the LRA. It is apparent from the terms of the settlement
agreement that SAMWU agreed to a retrenchment process, and
agreed to a month’s time frame to finalise the process. All that
was to follow from here on was the consultation meetings to be
held. The matters relating to the policy framework, and the
authority of the Acting Municipal Manager to initiate a
retrenchment were never an issue. In fact SAMWU agreed that
the process should take place outside the Local Labour Forum.
They cannot now be heard to complain that the Local Labour
Forum was not revised, improved and approved as directed by
the MEC, and use that as a bar to the retrenchment process.
SAMWU made an election to continue with a process and their
election was made an order of court.
[61] The submission that the respondent was obliged by the
Placement Agreement to negotiate the new organograms at the
Local Labour Forum is thus without merit. In my view the
Placement Agreement only applied at the initial stage of the
establishment of the Respondent when various municipalities
were amalgamated. The process had long been finalised after
the then new organogram served before the Local Labour Forum,
agreement reached and placement made as agreed.
[62] It is clear from the evidence tendered that the respondent took
the necessary steps to comply with the agreed court order.
Requests were made to SAMWU to provide dates for consultation
meetings. SAMWU did not respond to the requests. A meeting
was held on 18 October 2004 at which the financial position of
the respondent was presented and the voluntary retrenchment
applications were discussed as agreed. Furthermore, another
29
meeting was held on 29 October 2004. This is the meeting that
SAMWU representatives failed to attend. In my view, the
conclusion by Seitisho that SAMWU delegation intentionally
stayed away from the meeting in order to drag the process is not
unreasonable. Seitisho’s evidence that they knew very well
where the venue of the meeting was and they could not have got
lost was not controverted by any evidence. No explanation was
placed on record about circumstances that could have caused
them not to find the venue of the meeting and where they had
been.
[63] The attorney for the appellants contended that it was not open
to the respondent to simply terminate the contracts of the
individual employees when the period set aside for consultations
came to an end. He argued that the settlement agreement
stipulated that the respondent had to “formally initiate a
retrenchment process in terms of section 189”. By this
submission he meant that after the consultation for
retrenchments had been finalised by 29 October 2004 and there
being no consensus, then the respondent was obliged to issue a
formal notice in terns if section 189 of the Act and invite the
parties to participate in the process. Surely, this interpretation
cannot be what was intended. If that was the case, what would
have been the point of having a consultation in the first place. It
would make no sense and also be a waste of time to undergo the
same process twice with the same result. Such interpretation
would also defeat the purpose of the clause in the agreed court
order relating to the voluntary retrenchments and the entire
spirit and purpose of the agreed court order.
[64] In relation to the relief for procedural unfairness, the appellants
contended that they should have been awarded compensation
30
equivalent to twelve month’s remuneration. In support of this
contention, the appellants referred us to the alleged mala fide
conduct of the respondent before the signing of the settlement
agreement and also that they were forced to approach the
Labour Court on urgent basis to prevent a patently unfair
dismissal. Unfortunately no evidence relating to the conduct of
the respondent and the circumstances that led to the bringing of
the urgent application was tendered in the Labour Court. The
Labour Court in arriving at a decision to award no compensation
was exercising a discretion. Its reasons for the decision are in
my view reasonable. Its decision should therefore not be
tempered with.
[65] As regards costs, I am of the view that it would be in accordance
with the requirements of the Law and fairness that each party
should pay its costs as ordered by the Labour Court. The same
would apply in this Court.
In the result the following order is made:
(1) The appeal is dismissed.
(2) Each party is to pay its costs.
_____________
Tlaletsi AJA
I agree.