Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

7
@ IJTSRD | Available Online @ www ISSN No: 245 Inte R Im Very High Fixt Makarand Prabhakar Lehekar Deogiri Institute of Engineering & Technology, Aurangabad, India D INTRODUCTION Nowadays the automotive industry is f problems because of changing globa terms of high quality expectation, red production and increased productiv companies are in the motive to solve th through the application of modern tec project attempts to provide an effectiv these problems through lean m techniques. The key objective of this eliminate the wastes and cost of prod increase the quality and productivity th lead time and increased value added a project deals with collection of the time processes and the bottleneck operatio identified and a current state of value str developed. The suggestions were made and implementing various improvement also to develop the future state value st further improvements to achieve the obj project. Objective & Necessity of the Project In today’s scenario suppliers have a over improving quality and delivery a cost, which leads to improved system pr order to remain competitive, waste fr stream must be identified and elimina system with maximum efficiencies. A Production is to order and large different products are produced, each small volume. w.ijtsrd.com | Volume – 1 | Issue – 6 | Sep - Oct 56 - 6470 | www.ijtsrd.com | Volum ernational Journal of Trend in Sc Research and Development (IJT International Open Access Journ mprovement (Kaizen) ture Set up Time on VMC Mac Prof. Mangesh Urne Deogiri Institute of Engineering & Technology, Aurangabad, India Prof. M Associate of engi Au facing various al scenario in duced cost of vity. All the hese problems chniques. This ve solution for manufacturing s project is to duction and to hrough shorter activities. This taken for each ons have been ream map was by identifying ts in processes, tream map for jectives of this great concern and decreasing roductivity? In rom the value ated so to run e numbers of h in relatively The problems of Pre-assemb delayed deliveries, long queues, and high work in process inve Improper utilization. Various Muda’s like o Defects o Over production o Waiting o Not utilizing hum Transport Inventory Motion Extra processing These problems increase ove The need for customized prod lead times together with the competitiveness requires th produced in small batch si requirement. The processing in small batch The adjustment in the flow different processes as per t In addition it requires processes to reduce proces production), efficient planned maintena increased availability) and Reduction in non-value ad setup times, (ii) movemen the work processes and (ii t 2017 Page: 591 me - 1 | Issue 6 cientific TSRD) nal chine Mrs. Suvarna Pingle Professor, PES college ineering, Nagsenvan, urangabad, India bly productions are entories, man potential erall cost of production. ducts/parts with reduced e requirement of global hat products/parts be izes as per customer's sizes necessitates: w of production through their processing speeds. close monitoring of ss variability (defect free ance of all machines (for d dded activities such as (i) nt of material in between ii) additional processing

description

Nowadays the automotive industry is facing various problems because of changing global scenario in terms of high quality expectation, reduced cost of production and increased productivity. All the companies are in the motive to solve these problems through the application of modern techniques. This project attempts to provide an effective solution for these problems through lean manufacturing techniques. The key objective of this project is to eliminate the wastes and cost of production and to increase the quality and productivity through shorter lead time and increased value added activities. This project deals with collection of the time taken for each processes and the bottleneck operations have been identified and a current state of value stream map was developed. The suggestions were made by identifying and implementing various improvements in processes, also to develop the future state value stream map for further improvements to achieve the objectives of this project. Makarand Prabhakar Lehekar | Prof. Mangesh Urne | Prof. Mrs. Suvarna Pingle "Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-1 | Issue-6 , October 2017, URL: https://www.ijtsrd.com/papers/ijtsrd4615.pdf Paper URL: http://www.ijtsrd.com/engineering/other/4615/improvement-kaizen-very-high-fixture-set-up-time-on-vmc-machine/makarand-prabhakar-lehekar

Transcript of Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

Page 1: Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

@ IJTSRD | Available Online @ www.ijtsrd.com

ISSN No: 2456

InternationalResearch

Improvement (Kaizen)Very High Fixture Set

Makarand Prabhakar Lehekar Deogiri Institute of Engineering &

Technology, Aurangabad, India

Deogiri Institute of Engineering &

INTRODUCTION Nowadays the automotive industry is facing various problems because of changing global scenario in terms of high quality expectation, reduced cost of production and increased productivity. All the companies are in the motive to solve these problems through the application of modern techniques. This project attempts to provide an effective solution for these problems through lean manufacturing techniques. The key objective of this project is to eliminate the wastes and cost of production and to increase the quality and productivity through shorter lead time and increased value added activities. This project deals with collection of the time taken for each processes and the bottleneck operations have been identified and a current state of value stream map was developed. The suggestions were made by identifying and implementing various improvements in processes, also to develop the future state value stream map for further improvements to achieve the objectives ofproject. Objective & Necessity of the Project

In today’s scenario suppliers have a great concern over improving quality and delivery and decreasing cost, which leads to improved system productivity? In order to remain competitive, waste from the value stream must be identified and eliminated so to runsystem with maximum efficiencies.

A Production is to order and large numbers of different products are produced, each in relatively small volume.

@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 1 | Issue – 6 | Sep - Oct 2017

ISSN No: 2456 - 6470 | www.ijtsrd.com | Volume

International Journal of Trend in Scientific Research and Development (IJTSRD)

International Open Access Journal

Improvement (Kaizen) Very High Fixture Set up Time on VMC Machine

Prof. Mangesh Urne Deogiri Institute of Engineering &

Technology, Aurangabad, India

Prof. Mrs. Suvarna PingleAssociate Professor, PES college

of engineering, Nagsenvan, Aurangabad

Nowadays the automotive industry is facing various problems because of changing global scenario in terms of high quality expectation, reduced cost of production and increased productivity. All the

are in the motive to solve these problems through the application of modern techniques. This project attempts to provide an effective solution for these problems through lean manufacturing techniques. The key objective of this project is to

astes and cost of production and to increase the quality and productivity through shorter lead time and increased value added activities. This project deals with collection of the time taken for each processes and the bottleneck operations have been

fied and a current state of value stream map was developed. The suggestions were made by identifying and implementing various improvements in processes, also to develop the future state value stream map for further improvements to achieve the objectives of this

In today’s scenario suppliers have a great concern over improving quality and delivery and decreasing cost, which leads to improved system productivity? In order to remain competitive, waste from the value stream must be identified and eliminated so to run

A Production is to order and large numbers of different products are produced, each in relatively

The problems of Pre-assembly productions are delayed deliveries, long queues, and high work in process inventories, Improper utilization. Various Muda’s like

o Defects o Over production o Waiting o Not utilizing human potential

Transport Inventory Motion Extra processing

These problems increase overall cost of production. The need for customized products/parts with reduced lead times together with the requirement of global competitiveness requires that products/parts be produced in small batch sizes as per customer's requirement. The processing in small batch sizes necessitates: The adjustment in the flow of production through

different processes as per their processing speeds. In addition it requires close monitoring of

processes to reduce process variability (defect fproduction),

efficient planned maintenance of all machines (for increased availability) and

Reduction in non-value added activities such as (i) setup times, (ii) movement of material in between the work processes and (iii) additional processing

Oct 2017 Page: 591

www.ijtsrd.com | Volume - 1 | Issue – 6

Scientific (IJTSRD)

International Open Access Journal

n VMC Machine

Prof. Mrs. Suvarna Pingle Associate Professor, PES college

of engineering, Nagsenvan, Aurangabad, India

assembly productions are

ss inventories,

Not utilizing human potential

These problems increase overall cost of production. The need for customized products/parts with reduced lead times together with the requirement of global competitiveness requires that products/parts be produced in small batch sizes as per customer's

The processing in small batch sizes necessitates: he adjustment in the flow of production through

different processes as per their processing speeds. In addition it requires close monitoring of processes to reduce process variability (defect free

efficient planned maintenance of all machines (for increased availability) and

value added activities such as (i) setup times, (ii) movement of material in between the work processes and (iii) additional processing

Page 2: Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456

@ IJTSRD | Available Online @ www.ijtsrd.com

of material. The efficient utilization of machines while producing in small batches reduced WIP inventories, reduced times and reduction in lead times leads to competitive manufacturing. It is need for machine shop manufacturing system to adopt lean environment.improve productivity by identifying waste and then removing that by implementing lean principle in this industry THEME OF THE PROJECT The theme of the project is to productivity of the pre-assembly production like machine shop by identifying various wastes and then removing all those wastes by application of Kaizen & lean principles” Preface of this problem: The devices which are produced in

instrumentation companies are highly customized & tailor made so there are high no of set up changes on all the machines in machine shop. There are on an average 5 to 6 set ups in a day (1 shift) which lead to huge time expediture on set up

Data Collection before Kaizen:

After this data collection it is very clear that actual machining time was 769 hrs whereas total time spent for set up was 311 hrs / month. This means 29% of total time was spent on set up only which is NVA.

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456

@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 1 | Issue – 6 | Sep - Oct 2017

The efficient utilization of machines while producing in small batches reduced WIP inventories, reduced times and reduction in lead times leads to competitive manufacturing. It is need for machine shop

environment. To improve productivity by identifying waste and then removing that by implementing lean principle in this

“To improve assembly production like

by identifying various wastes and then removing all those wastes by application of Kaizen &

The devices which are produced in instrumentation companies are highly customized

tailor made so there are high no of set up changes on all the machines in machine shop. There are on an average 5 to 6 set ups in a day (1 shift) which lead to huge time expediture on set up

time which is a Non value adding activity & thus MUDA.

Due to introduction of new Guided Wave Radar,

various options introduced in existing products line & increased local value addition, the machining content of the total production process has drastically increased.

Also due to various different parts machining, number of fixtures has increased on VMC machine

This has increased enormous pressure on machine shop. It lead to increased set up time on VMC machine as each fixture change is a major set up.

Since we wanted to improve this process we have decided to study the process in depth. So we caluculated total time spent in VA’s & NVA’s i.e. Machining time & set up time. Also the scrap cost encured due to more no. of set ups & also the various delays due to this huge amount of set up time expediture. This data helped us to analyse the situation before & after kaizen implementation.

Data Collection before Kaizen:

After this data collection it is very clear that actual whereas total time spent

for set up was 311 hrs / month. This means 29% of total time was spent on set up only which is NVA.

Also total Scrap cost incurred till 12/2015 85450. The scrap was generated mostly while doing set ups. So more no of set scraps generation.

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470

Oct 2017 Page: 592

time which is a Non value adding activity & thus

ntroduction of new Guided Wave Radar, various options introduced in existing products line & increased local value addition, the machining content of the total production process

Also due to various different parts machining, number of fixtures has increased on VMC

This has increased enormous pressure on machine shop. It lead to increased set up time on VMC machine as each fixture change is a major set up.

Since we wanted to improve this process we have dy the process in depth. So we

caluculated total time spent in VA’s & NVA’s i.e. Machining time & set up time. Also the scrap cost encured due to more no. of set ups & also the various delays due to this huge amount of set up time

ped us to analyse the situation before & after kaizen implementation.

Also total Scrap cost incurred till 12/2015 was Rs. 85450. The scrap was generated mostly while doing set ups. So more no of set ups means more no of

Page 3: Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456

@ IJTSRD | Available Online @ www.ijtsrd.com

Many time due to more time required for set up & machining the flow from machining to assembly line was disrupted & so missing deliveries to customer.This has resulted in Customer dissatisfaction on delays contributing 3% delays due to material not received from VMC. Pareto Analysis of various set times

With Pareto analysis of various NVA’s time on VMC, it is very clear that Fhighest time. So Kaizen Theme is Fixture Set up time reduction. We plotted above problem in Ishikawa diagram to find out various causes & their effects. This is to find out if those are related to man, machine, material, process, management & environment.

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456

@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 1 | Issue – 6 | Sep - Oct 2017

Many time due to more time required for set up & machining the flow from machining to assembly line was disrupted & so missing deliveries to customer. This has resulted in Customer dissatisfaction on

ibuting 3% delays due to material not

Since our aim was to reduce set up time, we further broken down the total set up time into all the small activities of the set up process. And then Pereto chart prepared to study the most time consuthe set up process.

Pareto Analysis of various set times

With Pareto analysis of various NVA’s time on VMC, it is very clear that Fixture setting was contributing Fixture Set up time reduction.

We plotted above problem in Ishikawa diagram to find out various causes & their effects. This is to find out if those are related to man, machine, material, process, management & environment.

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470

Oct 2017 Page: 593

Since our aim was to reduce set up time, we further broken down the total set up time into all the small activities of the set up process. And then Pereto chart prepared to study the most time consuming activity in

ixture setting was contributing

We plotted above problem in Ishikawa diagram to find out various causes & their effects. This is to find out if

Page 4: Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470

@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 1 | Issue – 6 | Sep - Oct 2017 Page: 594

Identification of causes & effects by Fish bone diagram:

Finding out the root cause by Why

analysis: For Process & Equipment Problem: Fixture set up time more Why? When new fixture is loaded on machine, the position of all the sides of the fixture needs to be taught to machine. Why? Every time fixture won’t be placed on the exactly same place. Why? No provision for placing it on exactly the same position. YES, we will make such provision

Brainstorming For Solution:

• Root cause: No provision for placing fixture

on exactly the same position every time.

Can we make Automatic robotic arrangement for fixture trueing?

Possible but it is very expensive & also still it will take time & set up wouldn’t be reduced so much.

Can we provide some reference dowel pins so

that fixture can be placed exactly the same position?

Yes, we can solve this problem by making dowel holes & pins on SMED fixture so that all the fixtures can be placed on the same position every time

Page 5: Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456

@ IJTSRD | Available Online @ www.ijtsrd.com

Design of the Fixture Plate:

Developing Solution: We have prepared the design of the fixture plate. The clamping slots & dowel holes with bushes are made Similar dowel holes are made on all the fixtures we have. The position of the fixture is fixed For each fixture, only once set up has to be done. After 1st set up, only fix the fixture on the defined dowel holes with the Dowel pins. Then Cycle start. No need to true the fixture at all. This is a single minute change of fixture After Kaizen Analysis of various set times:

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456

@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 1 | Issue – 6 | Sep - Oct 2017

the Fixture Plate:

We have prepared the design of the fixture plate. The clamping slots & dowel holes with bushes are made Similar dowel holes are made on all the fixtures we have.

For each fixture, only once set up has to be done. set up, only fix the fixture on the defined dowel holes with the Dowel pins.

Then Cycle start. No need to true the fixture at all. ange of fixture

After Kaizen Analysis of various set times:

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470

Oct 2017 Page: 595

Page 6: Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456

@ IJTSRD | Available Online @ www.ijtsrd.com

After Kaizen implementation analysis it isfrom 35 mins to 3 mins. This means single minute change of fixture. Data analysis (During trial implementation):

After implementation of SMED fixture plate, production is running smoothly with excellent quality & with almost no set up time for fixtures. Our delivery performance has improved to avg. 98% until last month in current year. Follow Up & Review

1) For regular inspection format prepared which is to be used after each new set up.2) Monthly inspection of dowel pins & dowel bush carried out to ensure dowel pin & bushes are worn out

or not. 3) Standard operating procedures have been modified, incorporating the solution

SOP for Operation

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456

@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 1 | Issue – 6 | Sep - Oct 2017

After Kaizen implementation analysis it is clearly seen that there is drastic reduction in from 35 mins to 3 mins. This means single minute change of fixture.

analysis (During trial implementation):

After implementation of SMED fixture plate, production is running smoothly with excellent quality & with almost no set up time for fixtures. Our delivery performance has improved to avg. 98% until last month in

For regular inspection format prepared which is to be used after each new set up.Monthly inspection of dowel pins & dowel bush carried out to ensure dowel pin & bushes are worn out

Standard operating procedures have been modified, incorporating the solution

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470

Oct 2017 Page: 596

in fixture set up time i.e.

After implementation of SMED fixture plate, production is running smoothly with excellent quality & with almost no set up time for fixtures. Our delivery performance has improved to avg. 98% until last month in

For regular inspection format prepared which is to be used after each new set up. Monthly inspection of dowel pins & dowel bush carried out to ensure dowel pin & bushes are worn out

Standard operating procedures have been modified, incorporating the solution

Page 7: Improvement (Kaizen): Very High Fixture Set up Time on VMC Machine

International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470

@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 1 | Issue – 6 | Sep - Oct 2017 Page: 597

Following are some Tangible & Intangible benefits of this Kaizen Tangible Benefits: Productivity & so Delivery performance

improved. Customer is getting devices in time so he is

placing more & more orders Almost Zero rejection Investment:-

Fixture Cost: Rs.50000/- Avg. cost of rejections / Month = Rs. 15000/-

ROI:- 40000 /15000 = 3 months

Excellent Intangible Benefits: No Operator Fatigue Presentation skill improved. Team work improved. Motivation for more & more Kaizens in the

shop floor