Outline
• Business context
• Practical challenges
• Implementation & deployment experience
• Benefits observed
• A few lessons learned
www.incose.org/symp20202
Public Release Approval # IS-2020-1472
What Does “MBSE” Mean to You?
www.incose.org/symp20203
Spreadsheet Model
Requestor initiates request for purchase
Requestor validates requirement with
Functional Manager (FM)
FM forwards request to DO Lead
DO Lead creates PRAL Request in ECE. Logistics is
notified.
Logistics develops quotes and posts
approved quote for review.
FM reviews- approves quote
If rejected the process repeats at
the point of rejection
IA reviews- approves quote meets security
guidelines
If rejected the process repeats at
the point of rejection
DO Lead verifies quote and
funding
If rejected the process repeats at
the point of rejection
Is purchase under
$2,500.00?
Does the DO Lead wish to purchase via Credit Card?
Initiate Credit Card Purchase if requested
Logistics creates PRAL(s) on ECE. DO
Lead is notified
DO Lead adds cut from Spend Plan
showing remaining budgets. Logistics is
notified.
Logistics packages and moves to CCE
DO Lead verifies- approves PRAL.
QAP notified
QAP verifies-approves PRAL.
PM notified
PM verifies- approves PRAL. ACOR notified
If rejected the process repeats at
the point of rejection
ACOR reviews and signs PRAL. DO Lead, Program Manager,
and Logistics is notified
Is the purchase for training?
Once Alt COR approves training
DO Lead will inform the Functional Manager and
requestor.
Requestor will complete the
General Dynamics form HRFORM505A
with Program Manager’s
information as “Supervisor”
Program Manager will sign and forward
the form HRFORM505A to the
Program Director.
Program Director will sign and forward
the form HRFORM505A to
Corporate.
Corporate will process and file
Logistics creates Purchase Request. DO Lead is notified.
DO Lead reviews and approved PR.
Program Manager is notified.
Program Manager reviews and approves PR. Corporate is
notified.
Corporate creates PO. Logistics and vendor are sent copies of the PO
Vendor receives PO and ships item(s)
Logistics receives items. Corporate is
notified.
Corporate requests invoice from vendor
Vendor provides invoice to corporate
Corporate enters information into
Acquisition Purchases (AP)
GDIT invoices the government for
purchases
Government approves invoice
Service Desk (SD)Remedy
Service Catalogue (SC)(External Facing)
Security
Service Knowledge Management System (SKMS)
Configuration Management System (CMS)
Return to Requester
InvalidRequest
Request from: Service Desk, RFC, Web-Online Service Catalog, Phone Call, Email,
for HW/SW/Svcs./Install, Move, Add, Change (IMAC)
Initiate project mgt and associated
processes (including change mgt, design/BOM creation, and
procurement)
Is project funded and approved?
Access Management Policies
Information Security
Management
Access Management
N
Is request commoditized? (i.e., pre-built delivery model w/
established workflow & cost)
Y
End
RequestFulfilled
Request Fulfillment
(Commodity IT Svcs., HW and SW items on APL)
Exostar
Customers and End-UsersStart
Active Directory
- SharePoint Based w/RDBMS- Integration on Submit (for SD) and/or Login through FW to P/L System for authenticated Users-Integration on Submit through FW to SD for non-authenticated users- Tabbed Service Interface- Remedy and P/L Schema map for SD and P/L Systems- Service Buttons for both USBX and non-USBX users (Login for Authenticated Users)(Forward of data to SD for non-Authenticated Users
Authenticated Users
Non-Authenticated Users
Firewall
Populate request form
Input credentials forAD authentication
Populate request form for SD Support OR Authenticate into P/L
System
Requestor completes order in Exostar/
workflow initiated
Populated TT from P/L
System
Workflow generates/
populates Remedy TT
Submit to SD
SD works with requestor via Chat or Phone to complete and submit into P/L System
SD receives request from
Remedy
Visio Diagrams
CAD Models Wiring Diagrams
High-end Computers
“OV-1”
Public Release Approval # IS-2020-1472
“Model-Based Systems Engineering” is…
• INCOSE: “the formalized application of modeling to support system
requirements, design, analysis, verification and validation activities
beginning in the conceptual design phase and continuing throughout
development and later life cycle phases.”
• SysML.org: “a Systems Engineering process paradigm that emphasizes
the application of rigorous architecture modeling principles and best
practices to Systems Engineering activities throughout the System
Development Life Cycle (SDLC).
www.incose.org/symp20204
Public Release Approval # IS-2020-1472
BAE Systems: Digital Engineering (DE) Enterprise Vision
www.incose.org/symp20205
“Connecting Desktop to the Factory Floor and to Force Readiness”
@ Corporate Systems Engineering Working Group (SEWG)
Public Release Approval # IS-2020-1472
Business Drivers: Heard from Customers and Industry…
• Digital Engineering Strategy (DoD):
– Use of models
– Enduring Authoritative Source of Truth
– Technological innovation
– Infrastructure and environments
– Culture and workforce
• “Going Digital:” Better Engineered Systems
– Bringing the right side of the System V to the left
– Clearer requirements, earlier V&V, reduced defects
– Systematic reuse
• Collapsing Cycle Time
– Increased speed of capabilities… in a Model Based
Digital Environment
– “Sense of Urgency:” to accelerate agile delivery
www.incose.org/symp20206
(Source: OUSD)
(Source: NAVAIR SET)
(Source: NAVAIR SET)
Public Release Approval # IS-2020-1472
Practical Challenges in Adopting MBSE/MBE
www.incose.org/symp20207
Experienced Workforce:
• Franchise programs
• Mission understanding
• System / product knowledge
• Customer intimacy
MBSE Challenges:
• Legacy SE skills and processes
• Lack of practical knowledge in MBSE
• Culture… adverse to change
• “This has always been how we do things”
• “We have deadlines to make”
• “Your tool doesn’t work!”
“MBSE… what does it do for you?...”
Organizational dichotomy…
Public Release Approval # IS-2020-1472
Multi-year, Multipronged Investment Strategy
www.incose.org/symp20208
Technology & Infrastructure
Process & Methods
People & CultureBuilt on an Architectural Vision
Public Release Approval # IS-2020-1472
ADAMSTM Reference Architecture: Implementing an MBSE/MBE
Environment Across the Complete System Lifecycle
• Digital backbone for integrated
business process
– Federated tool suite
– Interconnected data & model
traceability
– Paperless, multi-function
Collaboration
• Digital thread as a value
stream
– “Owning the technical
baseline” and change
management
– “Authoritative source of truth”
www.incose.org/symp20209
Concept ◊ Design ◊ Build ◊ Integration ◊ V&V ◊ Sustainment
Dynamic Dashboard
Engineering Design Tools
Project Management
Modeling & Simulation
Tests
Requirements
Architecture
PLM Environment ERP Environment
Inventory Management
VR/AR
Manufacturing Execution
DMSMS Management
Public Release Approval # IS-2020-1472
Technology & Infrastructure: Integrated Data Environment
(IDE) Implementation
• Collaborative modeling environment
– Multi-site, collaborative teams
– Project-based (vice location-based) &
create/modify access from any site
• Services hosted in corporate cloud /
datacenter
– Servers & databases
– Central admin/support and license
management
www.incose.org/symp202010
(Unclassified Environment)
(Classified)(Classified)
Team 1 / Site 1 Team 2 / Site 2
Team 3 / Site 3 Team 4 / Site 4
TeamWork Server DOORS 9.6 Sever 3DX Host
Team 6 / Site 6 Team 7 / Site 7DDG, LCS, SDIO / SoMD
Site 1 Classified Lab
Data Center/License Servers
TeamWork Server DOORS 9.6 Sever
3DX Host
Team 2 Classified Lab
Data Center/License Servers
TeamWork Server DOORS 9.6 Sever
3DX Host
Corporate Datacenter(Cloud)
DOORS
ENOVIA / DEXPERIENCE
Public Release Approval # IS-2020-1472
Technology & Infrastructure: Integrated PLM-ERP
Implementation
• ENOVIA Implementation:
– Product/object-oriented, configuration-controlled design
lifecycle process
– Parts, eBOM, drawings, test plans, documents, and other
engineering artifacts
– Design reuse, change impact analysis, trade studies,
collaborations
• Integrated CAD-PLM:
– Single, unified user environment
– Solidworks, CATIA, AutoCAD, Inventor
– Native parametric modeling, sub-assembly level,
configuration-controlled design collaborations
• Integrated PLM-ERP:
– ENOVIA-CostPoint data connector
– Automated, controlled release of eBOM to mBOM
– Integrated CR/CO/CA–PR/PO workflows
www.incose.org/symp202011
Public Release Approval # IS-2020-1472
Integrated Business Process: Cross-Functional Process
Embedded in Environment
• Integrated, consistent
business process / workflows
– PLM: CR/CO/CA,
engineering design,
component engineering
– ERP: PR/PO, material
planning, logistics
– Automated, controlled
release of eBOM to
mBOM
– CCB, design/peer reviews,
Release Approval
www.incose.org/symp202012
Da
ta
Co
nn
ec
tor
Da
ta
Co
nn
ec
tor
• eBOM to mBOM
• eParts to mParts
• Models to Parts
Public Release Approval # IS-2020-1472
Methodology: Developing Methods through Pilot Use Cases
www.incose.org/symp202013
Syndeia
DOORS MagicDraw
MagicDrawWindchillCreo
Integrated System/SoS Architecture:
• Cross-domain digital thread
• Reqt Functional Logical (HWCI)
Physical (eBOM) 3D Models
• Requirement verification, architecture
design trades
Model-based System Test &
Evaluation (ST&E) strategy:
• Two-stage, model-based
requirement IV&V approach
• Early verification through model
execution & integration of late-cycle
system test events
• System functional testing
automation
Model-Based Engineering (MBE) with
3DExperience Platform:
• Integrated MBE environment
• “RFLP” Traceability
• Requirement Logical & Functional
BOM/Parts/Multi-CAD
• Integrated Project Management
Public Release Approval # IS-2020-1472
Methodology: Developing Methods through Pilot Use Cases
(cont.)
www.incose.org/symp202014
Model-based Cyber Risk Assessment:
• Architecture-driven cybersecurity threat
& system vulnerability assessment
• DoDAF/UAF and SysML models
• RMF automation, mitigation actions,
report generation, POA&M
Model-based Design Reviews &
Standard IDE Template:
• Standard project templates with
instructions
• “Drag & drop” review baseline views
• Comments and model redlining
• Corporate LCM process
Range Operators
Cyber Warriors /
Trainees
SOC / Cyber Defense
Cyber Defenders /
Trainees
MicrosoftATA
UBA (AI/ML)
Unauthorized Change
Indicators of Compromise
Honeypot/Deception
SIEM
Credential Theft
Vulnerability Scanning
Vulnerable Hosts
Attackers
Model-based Cyber Range Operations:
• Virtual cyber range in Cloud
• Model-based range architecture
• Training, exercises, system testing
• Range build-up, tear-down, and
verification directly from system models
Public Release Approval # IS-2020-1472
People: MBSE Catalyst Program
www.incose.org/symp202015
Learn Skills…
Develop Pilots…
Show Demos
Architecture
Design
Test &
Evaluation
Structured Training Program ~ Selective Engineering “HiPots”
Public Release Approval # IS-2020-1472
People: MBSE Catalyst Program Curriculum
Stage 1: Self-Learning & Prep
• I&SU MBSE Pathway
• Level 1: Engineer Track
• Level 2: Modeler Track
• Pilot project planning
Stage 2: Classroom Training & Labs
• System Modeling & Design
• Language: SysML
• Tools: MagicDraw, PLM
• Methods: System architecture, OOSEM
Stage 3: Projects
• Pilot projects
• Customer-facing pilot use cases
• Deliverables: demos
Stage 4: Demos
• Internal & external stakeholder (customer) demos
• Technical feedback & recommendations
Deploy & ExpandCandidate
Selection
Public Release Approval # IS-2020-1472
People & Culture: Implementation and Deployment
• Leadership Workshops: Senior Managers
– “MBSE 101” training
– Challenges & opportunities
– Implementation roadmaps & tech info sessions
• Training & Certification: SMEs
– Training pathways
– Certification incentives
– Tools: train-the-trainers
– First-line support
• Communities of Practice: Practitioners
– Coordinate, collaborate, interchange and sharing
– Best practice stories, demos
– Internal & external speakers
– Training and modeling assets
www.incose.org/symp202017
Program Teams
Business Areas / Sectors
Functional SMEs
MBSE PLM VR/AR Cyber
Public Release Approval # IS-2020-1472
Key Benefits: Digital Transformation to Empower Our Teams
Better Supporting Customer Missions
www.incose.org/symp202018
Early Solutions Enabling Business Winning
Cycle Time Reduction• Rapid engineering change
responses
• Systematic design reuse
• Early architecture decisions
• Fleet Readiness (dependable,
state-of-the-art, “Up” systems)
2
Knowledge Transfer• Expedited knowledge transfer enabled by systematic
knowledge management
• From “grey beard” to
codification of corporate
knowledge
• Institutionalization of IP, trade secret & product know-how
Empowered Teams
• Engineering workforce empoweredby advanced engineering tools
• Changed work style from transactional to transformational
• Inspired Millennial generation by state-of-the-art technology and capabilities
Inspired Work – Performance Excellence – Enabled Customer Missions
Cost Reduction / Take-out • Architecture trades enabling system understanding
much earlier in life cycle
• Reduced defect rates & cost of poor quality avoidance
• Reduction of transactional costs
• Lean engineering, productivity & effectiveness
SpecificationDefects
Reduced 68%
MBE: Left-Shifting Engineering• Earlier Design Decision Reduces Lifecycle Costs
• Earlier Defect Detection & Reduced Rework
Improved Capabilities to Customers• Robust Technical Baseline and change management
• Agile, rapid engineering change responses
• Early architecture decisions, reduced risks, and collapsed cycle time
• Deeper insights and improved acquisition decisions
External/customer collaborations
Public Release Approval # IS-2020-1472
A Few Lessons from Early Experience…
• An overarching architectural vision is important
– Communications of vision and roadmap
– Prioritization of development, guideline for investment
• People is key… the right people
– Requires believers / leaders / champions at all levels
• Management buy-in is critical…
– But they are hard to convince: ROI?
• Culture… is the hardest problem to tackle
– No “silver bullets”
• Be resilient… stick with the vision, work your way through problems and reinvent on the way
– Incremental implementation: crawl-walk-run
– Small pilots lead to small successes
www.incose.org/symp202019
Public Release Approval # IS-2020-1472
It’s an Ongoing Journey…
• Digital Engineering transformation is an enterprise-level, multipronged endeavor
– Technology and infrastructure
– Processes & methods
– People & culture
• The journey continues…
www.incose.org/symp202020
www.incose.org/symp2020 Public Release Approval # IS-2020-1472
Thank You
Gan Wang, Ph.D.
INCOSE Fellow, ESEP
BAE Systems Engineering Fellow
Chief Engineer, Integrated Defense Solutions