Implementation of EnMS at MFT
-
Upload
irfan-abbasi -
Category
Documents
-
view
220 -
download
0
Transcript of Implementation of EnMS at MFT
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 1/51
Page 1 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
IMPLEMENTATION OF ENERGY MANAGEMENT SYSTEM
IN
FAROOQ TEXTILE MILLS -2010
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 2/51
Page 2 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
TABLE OF CONTENTS
S.# Topic Page #
A Title 1
B Table of Contents 2-3
C Executive Summary 4
1 General Information of the Textile Sector 5
2 Global and Local Energy Crisis Impact on Pakistan Textile sector 5
3 General Information of Company 5
4 Scope of Project 6
5 Scope of Report 6
6 Limitation of the Report 7
7 Format of the Report 7
8 Our Audit Approach 7
9 Data Collection Method 8
10 Instruments used for Data Collection 8
11 Units of Measurement 9
12 Unit Cost Calculations 9
13 Industry Benchmark 10
14 Company Energy Consumption Performance 10
15 Manufacturing Process Flow 17
16 Preliminary Energy Audit Observations 18
17 Detailed Energy Audit –Baseline Data (As is Scenario) 21-38
17.1 Energy Producers—Electrical
17.2 Energy Producers—Steam
17.3 Energy Producers—Gas combustion at singeing
17.4 Energy Consumers—Electrical Machines & Motors
17.5 Energy Consumers—Electrical Lighting
17.6 Energy Consumers—Steam @ machines, pipes and steam traps
17.7 Management Practices 39
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 3/51
Page 3 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
TABLE OF CONTENTS
S.# Topic Page #
18. Energy Management Objectives –(To be Scenario) 42-5018.1 Energy Producers—Electrical
18.2 Energy Producers—Steam
18.3 Energy Producers—Gas combustion at singeing
18.4 Energy Consumers—Electrical Machines & Motors
18.5 Energy Consumers—Electrical Lighting
18.6 Energy Consumers—Steam @ machines, pipes and steam traps
18.7 Management Practices
19 Recommended Implementation Strategy 51
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 4/51
Page 4 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Executive Summary
Mohammad Farooq Textile Mills Limited (MFTML) participated in the Renewable Energy & Energy
Efficiency Program of GTZ under the platform of APTMA and in coordination with SMEDA for EnergyManagement System Development and Implementation. Arch Associates was selected by GTZ as
project consultant.
This report describes the Energy Audit Findings conducted as a part of the Energy Management System
Development and Implementation. Committee Draft ISO 50001 of Energy Management System (EnMS)
was used as the benchmark standard for the Energy Audit and system implementation. The Energy
Policy, System Procedures and related forms are compiled as a separate manual.
A holistic approach for energy audit was used with focus on energy balance at the energy producer and
energy consumer entities. Electricity, Steam and Heat in any form are considered as form of energy.
Preliminary and detailed energy audit has identified inefficiencies mainly at the electrical power
generation and consumption stage. Almost in all the energy consumption domains (electricity, steam,
water, gas), the per kg fabric consumption is much higher than the international and national
benchmarks.
Besides cost saving opportunities related to electrical energy generation and consumption (Rs 6
million), significant cost savings can be achieved in the area of steam generation and consumption by
combustion efficiency of boilers (Rs 7 million), utilizing the heat from waste gases of boiler stack, heat
losses in the processing area due to steam leakages (Rs 2.6 lacs), inefficient steam traps, effective
insulation of semi-insulated and bare steam pipes (Rs 52000).
Also increasing the consumption efficiency of water (Rs 4.4 million) and gas in the wet processes and at
singeing machine (Rs 42000) will yield high cost savings.
Except for waste heat recovery from generators, rest of the identified energy conservation
opportunities does not require heavy investment and merely by improving the management systems
related to preventive maintenance and good housekeeping with focus on workers training and creating
sense of process ownership will yield high savings.
By converting from estimation based energy cost management to real time measurement of energy
production and consumption efficiencies and calculating cost impact as a part of Energy Management
Information System will support MFTML management in prompt identification of high cost drivers and
its impact on overall cost of production
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 5/51
Page 5 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
1. General Information about Pakistan Textile Sector
Pakistan Textile and Apparel industry generates about 64 % of total exports and constitutes 46 % of
Manufacturing Industry. It employs 40% of Country’s working population and contributes 11% of thetotal GDP. Pakistani clothing export growth slowed to 8% in 2006, following three years of double digit
increase.
2. Global and Local Energy Crisis Impact on Pakistan Textile Sector
Pakistan’s textile industry has been particularly ravaged by high energy prices and shortages of supply.
National exports for last year fell 25% or US$5.12 billion short of targets, and this year’s forecasts have
been substantially scaled back as well. Despite the current global economic recession, estimates place
the losses due to energy prices at around US$1 billion annually, with failure to meet orders caused by
the effects of energy shortages on production times driving away future business. Given that 64% of the country’s export earnings come from textiles, the crisis is of vital importance to Pakistan’s
economic recovery and future.
3. About Mohammad Farooq Textile Mills Limited
Company Name: Mohammad Farooq Textile Mills Ltd
Industrial Sector: Textile Processing
Range of Products: Woven fabrics, Dyed & Printed bed sheets and curtains
Address: Plot # 6& 7, Sector 21, Korangi Industrial Area. Karachi
Telephone: 92-021-350515498URL: www.mohammadfarooq.com
Contact Person: Mr. M. Younus—General Manager Operations
Energy Manager: Mr. Lucman (Utility Manager)
Site Characteristics
Total Space = 16 acre (65000 m2)
Production Space = 44000 m2
Office Space = 603 m2
Storage Space = 498 m2
Production Capacity: 2.3 million liner meter fabric
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 6/51
Page 6 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Mohammad Farooq Textile Mills Limited is among the oldest and largest textile units of Pakistan
located in Karachi. The company is involved in the manufacturing, dyeing and printing of woven fabrics
mainly related to Home Textiles. Previously the company was the complete vertical unit from spinning
to garments but now due to recession and slump in textile trade, it has reduced its manufacturing
operations to dyeing and printing predominantly while few weaving looms and small garment unit.
Currently its products are mainly exported to USA and few lawns are for sale in the local market.
Since 2001, company is maintaining ISO 9001 Quality Management System Certification and also
follows buyers Code of Conduct for Corporate Social Responsibility
4. Scope of the Project
German Technical Corporation (GTZ) as Project Sponsor with Small Medium Enterprise DevelopmentAuthority (SMEDA) as the coordinating body and All Pakistan Textile Manufacturers Association
(APTMA) as the beneficiary body initiated the Energy Management System Development and
Implementation Project for the selected group of textile companies related to spinning, weaving and
processing sector. The objective of the project is to not only identify the energy cost savings through
energy audits but also to bring on board all the management functions of the company for sustainable
energy conservation practices through documented Energy Management System development and
implementation.
In this regard the upcoming Energy Management Standard of ISO 50001 is selected as the benchmark
model to develop the Energy Management System
For Energy Management System (EnMS) development and implementation at Mohammad Farooq
Textile Mills, the processing area comprising dyeing and printing is selected for EnMS development and
implementation beside electrical power generation and steam production.
The areas of weaving and garment are out of scope for this project.
5. Scope of the Report
This report details the Energy Audit findings and the corresponding Energy Management Objectives for
the processing area comprising dyeing and printing including power generation and steam production.
The Energy Manual and related procedures including instructions are presented as separate document
and are not part of this report.
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 7/51
Page 7 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
6. Limitation of the Report
Since energy audit was performed during the period of Dec 2009—Jan 2010, which is usually low
production phase for the textile sector, therefore at times the data measured at the machines when itwas not running at its optimum capacity. Also no measurement was collected for pad steam as it was
not operational during the audit time frame. Similarly our observations and measurement were
focused on energy generation, consumption and wastages as a process and does not take into account
the balancing between total power generation and production capacities as currently power
generation model is based on the previous manufacturing setup including spinning, weaving,
processing and garments while presently the same power generation model is catering only processing
and partly few looms and garment section.
7. Format of the Report
The report is structured in the form of “As is Scenario” and “To be Scenario” for each component of
energy producer and consumer. Each component is depicted in the form of energy input and output
supported by data tables, graphs and calculations to demonstrate energy wastage and cost saving
potential
8. Our Approach for Audit
We take the holistic view of the total energy model employed at Mohammad Farooq Textile Mills and
categorized it as Energy Producers and Energy Consumers.
Under Energy Producers, gas fired Generators and Boilers (gas fired and thermo) are categorized while
Electrical Panels, Machines, Motors, Pumps, Fans, Building [lighting] etc are categorized as Energy
Consumers consuming energy in the form of electrical power or heat energy.
To identify the energy loss at Energy Producers and Energy Consumers stage, energy balance approach
is used as depicted below.
Energy InputEnergy Conversion
Value Added Energy
Output
Energy Wastage
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 8/51
Page 8 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
This energy process realization is used to identify the Energy Efficiency, Energy Wastages and the Cost
associated with the wastages either at the input stage or output stage.
For cost saving opportunities identification we initially identified the maximum possibleopportunities during the preliminary energy audit and used 80/20 approach in detailed audit for
data collection and cost savings potential. Only those 20% energy savings opportunities haven been
taken as Energy Management Objectives (EMO) which have an impact of 80% cost savings in the
total cost saving pie.
9. Data Collection
Method
The data collection process comprised of data provided by the organization and the measurementexercise carried out by our team during the detailed energy audit scenario.
Where data reported by organization was based on estimation rather than measurement, it was
measured during the detailed energy audit in order to have accuracy in energy efficiency, energy
wastages and cost savings values.
To the extent possible, dependability on estimated values is discouraged for calculations except in
those cases where measurements for the total number of equipments (e.g. motors) was not possible
and sample results are averaged and plotted for the total range of similar equipments (conditionality:
similar make, rating and type of equipment)
Following were the sources of data collection
Data provided by organization in the form of gas bills, production figures, electricity units
generated through self generation, water consumption etc
Data noted from the measuring devices installed at different equipments
Data collected through measurement exercise during the detailed energy audits in
collaboration with Department of Energy & Environment of QUEST--Nawabshah and
Environmental Research Centre of Bahria Univeristy –Karachi.
Data collected through visual observations
10. Instruments Used for Data Collection
Flue gas analyzer
Lux Meter
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 9/51
Page 9 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
PF Meter
Volt Meter
Electric Power Meter Analyzer
Low and High Infrared Temperature Meter
Tong Tester
Flow Meter
11. Units of Measurement
Production = linear meter
Steam = Kg/ year
Electricity = Kwh/year
Gas = m3
12. Unit Cost for Calculations (based on 2009 data)
The unit cost calculation for gas, electricity and steam are based on the fuel consumption cost and does
not take into account the overhead cost involved as in case of energy savings, the direct impact will be
on the fuel cost than on the overhead cost. Also the financial savings demonstrated through energy
conservation will be more accurate and verifiable in the absence of inclusion of overhead cost. The cost
provided by the company and included in the tables coverts the total generation cost i.e. fuel cost plus
the overhead cost.
For Steam
Steam Consumption= 86261760/12499886 = 6.90 kg/ meter
6.90 kg = 8.17 Rs.
Cost of 1 Kg Steam = 8.17/ 6.90 = 1.18 Rs/ kg (provided by MFTML)
For electricity
Number of electricity units generated per month= 357131 Kwh
Cost of 1 m3 Natural gas = 10.44 Rs.(derived from Gas Bill)
Gas consumption for 1 Kwh = 0.346 m3
Cost for generation 1 Kwh = 3.612 Rs. /Kwh (Calculated from gas consumptionand does not include overhead cost)
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 10/51
Page 10 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
13. Industry Benchmark
Water Consumption Norms (per Kg)
World Consumption---50-100 litres/kg of fabricNational Consumption ---Sind –50-80 litres/kg of fabric Punjab---200-300 litres/kg of fabric
Steam Consumption---6-8 kg of steam/ kg of fabric
Electricity Consumption----0.8—1.5 KWh / kg of fabric
Gas Consumption---0.35 m3
of gas/ kg of fabric
14. Company Energy Consumption Performance
To evaluate the company energy consumption performance against the established benchmarks /
norms, data for the year 2009 was collected and analyzed.
Water Consumption
Table 1—Machine wise water consumption data for the year 2008-09
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 11/51
Page 11 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Graph-1- Water Availability data per day from KDA and Well water
Graph-2-Machine wise water consumption trend during the month
Analysis
Average Water Consumption (2008-09) = 88897392 / 12 = 7408116 gallons per month
Average Production (2008-2009) = 1047770 m per month = 209554 kg for 2009 (Assume 200 gm per linear
meter)
Average Water consumption per linear meter of fabric= 133.81 litres/kg of fabric which is much higher
than the benchmark value for Sind and international norm.
High consumption rate is noticeable at bleaching and washing machine. This is supported by water
wastage savings identified at these machines and explained in the Detailed Audit section
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 12/51
Page 12 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Steam Generation
Table-2- Boiler wise steam generation data
Table-3- Machine wise steam consumption data
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 13/51
Page 13 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Graph-Steam consumption at different machines (This data is based on approximation)
Analysis
Average Steam Consumption (2008-09) = 6127680 kgs per month (excluding steam consumed in
stitching 1& 2, HVAC and sizing)
Average Production (2008-2009) = 1047770 m per month = 209554 kg for 2009 (Assume 200 gm per linear
meter)
Average Steam consumption per linear meter of fabric= 29.24 kg of steam /kg of fabric which is much
higher than the benchmark value.
Since steam monthly production is not measured and recorded therefore its consumption pattern
against the monthly production can’t be analyzed.
Electricity Consumption
Table-4 –Electricity Generation Data (Till Oct 2009)
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 14/51
Page 14 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Graph
Analysis
Average KWh Consumption (Jan-Nov 2009) = 7786654 KWh / 11 = 707877 KWh
Average Production (Jan-Nov 2009) = 11525478 / 11 = 1047770 m per month = 209554 kg for 2009
(Assume 200 gm per linear meter)
Average Electricity consumption per kg of fabric= 3.37 KWh kg of electricity /kg of fabric which is much
higher than the benchmark value.
An abnormal trend is observed for the month of May 2009 when production volume increased
considerably compared to April 2009 but the electricity generation in KWh is showing decreasing trend
in May 2009
Gas Consumption
Table
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 15/51
Page 15 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Cumulative Gas Consumption Details Nov 2008—Oct 2009
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 16/51
Page 16 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Graphs
Analysis
Average Gas Consumption (Nov 2008—Oct 2009) = 638255.9167 m3. Gas consumed in production onlyAverage Production (Nov 2008—Oct 2009)= 1240565.25 m = 248113 Kg (Assume 200 gm per linear
meter)
Average Gas consumption per kg of fabric= 2.57 m3
gas /kg of fabric which is much higher than the
benchmark value . Taking into consideration the gas consumed for electric power generation, the per
kg fabric value comes to around 4.53 m3
.
An abnormal trend is observed for the month of May 2009 when production volume increased
considerably compared to April 2009 but the gas consumption is showing decreasing trend in May
2009
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 17/51
Page 17 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
15. Manufacturing Process Flow
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 18/51
Page 18 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
16. Preliminary Audit Observations
Steam Generation and Consumption
1. Steam header valve is leak.
2. Temperature, pressure and other gauges are not calibrated.
3. Most (almost 100%) of steam traps are leakages.
4. Steam leakage at Kuster Pre Treatment
5. Piping insulation at Kuster PT is not proper.
6. Condensate pipe is leak.
7. Insulation not proper at Thermo boiler (Rotary Printing)
8. Two Feed Water tanks are not insulated.
9. Blow down water tank is also not properly insulated.
10. No drainage is made for the water at the Boiler House. 11. Condensate Water is drained.
12. Water Flow meter not installed anywhere in the Boiler House.
13. No any measuring device for the Steam generation, Gas Consumption, Electricity Consumption, Boiler
Feed water tank is installed.
14. Boiler Efficiency is not monitored as there is no measuring instrument installed for efficiency
measurement.
15. No any device for the measurement of NOx, SOx, and other flue gases. Energy Accounting
16. In piping some of the line are oversized and some are undersized (No uniformity of the piping system).
17. Steam Condensate pipes leakages are not fixed.
18. Damaged insulation is not repaired, and where fixed the correct insulation material is not used.19. No pre-heating of combustion air with waste heat (22 0C reduction in flue gas temperature increases
boiler efficiency by 1%).
20. No use of variable speed drives on boiler combustion air fans with variable flows.
21. One oil tank requires insulation.
22. No maintenance record to conform that burners, nozzles, strainers, etc are cleaned
23. No inspection record related to Inspection of oil heaters for proper oil temperature.
24. Close burner air and/or stack dampers when the burner is off to minimize heat loss up the stack.
25. Improve oxygen trim control (e.g. -- limit excess air to less than 10% on clean fuels). (5% reduction in
excess air increases boiler efficiency by 1% or: 1% reduction of residual oxygen in stack gas increases
boiler efficiency by 1 %.)26. Automate/optimize boiler blow down. Recover boiler blow down heat.
27. Use boiler blow down to help warm the back-up boiler.
28. Optimize deaerator venting.
29. No Inspection of door gaskets.
30. No Inspection for scale and sediment on the water side
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 19/51
Page 19 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
31. (A 1 mm thick scale (deposit) on the water side could increase fuel consumption by 5 to 8%).
32. No Inspection for soot, flyash, and slag on the fire side. (A 3 mm thick soot deposition on the heat
transfer surface can cause an increase in fuel consumption to the tune of 2.5%.)
33. Optimize boiler water treatment. Presently continuous blow down indicates water treatment is not
effective.
34. Add an economizer to preheat boiler feed water using exhaust heat.
35. Recycle steam condensate.
36. Study part-load characteristics and cycling costs to determine the most-efficient mode for operating
multiple boilers.
37. Fix steam leaks and condensate leaks (A 3 mm diameter hole on a pipe line carrying 7 kg/cm2 steam
would waste 33 kilo litres of fuel oil per year).
38. Accumulate work orders for repair of steam leaks that can't be fixed during the heating season due to
system shutdown requirements. Tag each such leak with a durable tag with a good description.
39. Ensure process temperatures are correctly controlled.
40. Maintain lowest acceptable process steam pressures.
41. Reduce hot water wastage to drain.
42. Remove or blank off all redundant steam piping.
43. Ensure condensate is returned or re-used in the process (6 0C raise in feed water temperature by
economiser/condensate recovery corresponds to a 1% saving in fuel consumption, in boiler).
44. Check operation of steam traps.
45. Inspect steam traps regularly and repair malfunctioning traps promptly.
46. Consider recovery of vent steam (e.g. -- on large flash tanks).
47. Use waste steam for water heating.
48. Repair damaged insulation (A bare steam pipe of 150 mm diameter and 100 m length, carrying
saturated steam at 8 kg/cm2 would waste 25,000 litres furnace oil in a year.)
49. Insulate all flanges, valves and couplings
50. Insulate open tanks (70% heat losses can be reduced by floating a layer of 45 mm diameter
polypropylene (plastic) balls on the surface of 90 0C hot liquid/condensate).
Electrical Power Generation and Consumption
1. Almost all of the lights are TUBE LIGHTS and ON during the day time where sufficient daylight is
available.
2. Panels in the Boiler House are very old and rust is present on them.
3. No maintenance of the electrical equipment was found.
4. There was dust on the tube lights as there is no proper cleaning system of the tube lights.
5. Power Factor on the generators is very low i.e. 0.75
6. Power Factor at the distribution side is also low
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 20/51
Page 20 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Feeder # 1 :0.74
Feeder # 2 :0.83
Feeder # 3 :0.87
Feeder # 4 :0.85
7. Schedule your operations to maintain a high load factor
8. Correct power factor to at least 0.90 under rated load conditions.
9. Relocate transformers close to main loads. (Two transformers are at distance from the main load)
10. Use energy-efficient motors where economical.
11. Use synchronous motors to improve power factor.
12. Use variable-speed drives for large variable loads.
13. Check belt tension regularly.
14. Clean screens and filters of blowers regularly.
15. Repair seals and packing of pumps to minimize water waste.
16. Balance the system to minimize flows and reduce pump power requirements.
17. Consider painting the walls a lighter color and using less lighting fixtures or lower wattages.
18. Optimize generator loading
19. Use waste heat to generate steam through WHRB.
20. Use jacket and head cooling water for process needs
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 21/51
Page 21 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
17. Detailed Audit--Baseline Data ( As is Scenario)
Energy Producer
17.1. Electrical Power Generation
MFTML has three gas fired generators, out of which two are for normal operations and one used as
standby arrangement. The details of engines are as below
Gas, Air mixture
Generators Electrical Power
Stack Gases @ 520 C as
waste
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 22/51
Page 22 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
The operating parameters when measured on Jan 09,2010 indicated the following readings
The electrical power generated through two generators is routed to two transformers (incoming power) and
four feeders (outgoing power) as per following arrangement
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 23/51
Page 23 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
The distribution of electricity in different areas is as per below table
Total
Electricity
Generated
(kWh)
Consumption (kWh)
Processing Main
Office
Boiler RO Computer Power
House
unknown Etc
213322 412255 455544 21415 5555 2211 2255 12221 111
132132
100% 10% 20% 15% 30% 10% 10% 4% 1%
The low power factor at Generators and feeders indicates energy wastage which can be saved by
technological intervention. The calculations for power factor improvement from existing 0.75 to 0.9
are detailed below along with cost saving potential calculations.
Generator Low Power factor Cost Impact calculation
Running load of generator # 1= 650 kW
Average Power Factor = 0.75
kVA taken at 0.75 = 866.6
kVA taken at 0.90 = 755
=866.6-755
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 24/51
Page 24 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
=111*0.9 (desired power factor) = 100.04
=100.04* 8760(running hours) * 3.61(fuel cost for electricity generation)
Savings on Gas fuel =Rs. 3175009.44/Year
For two generators =2* 3175009
Total Savings on Gas bill =Rs. 6350018 /yr
17.2. Steam Generation through waste gases
Similarly waste gases from the two generators are currently emitted in the atmosphere. The profile of
stack gases of both the generators is tabulated below.
STACK GAS ANALYSIS FROM GENERATOR I
S.No. Parameters Unit Monitoring Results
1 Temperature (Ambient) oC 28.8
2 Temperature (Stack) oC 532.4
3 Carbon Monoxide ppm 171
4 Carbon dioxide % 1.47
5 Nitrogen Oxide ppm 43
6 Nitrogen dioxide ppm 0.6
7 Sulphur Oxide ppm ---8 Hydrogen ppm 71
9 Oxygen % 18.41
STACK GAS ANALYSIS FROM GENERATOR II
S.No. Parameters Unit Monitoring Results
1 Temperature (Ambient) oC 29.6
2 Temperature (Stack) oC 538.6
3 Carbon Monoxide ppm 94
4 Carbon dioxide % 0.72
5 Nitrogen Oxide ppm 17
6 Nitrogen dioxide ppm 0.3
7 Sulphur Oxide ppm ---
8 Hydrogen ppm 55
9 Oxygen % 19.72
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 25/51
Page 25 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
On the basis of oxygen and CO2 contents of the stag flue gases the combustion efficiency is in the range of 75-
80%. This low efficiency is due to the high oxygen content in the flue gas.
Currently the total steam requirement is around 22 TPH which is met through four gas fired boilers.Capturing of high temperature stack gases and directing them in Waste Heat Recovery Boiler (WHRB)
will reduce the steam demand from conventional boilers thereby impacting on gas consumption.
The calculations below demonstrate the potential for steam generation through WHRB and cost
savings.
WASTE HEAT RECOVERY COST CALCULATION
Power = P= 650
Exhaust temp. = 532.4 0C
Pressure= 10.54 kg/cm2
Mass of stack gas = 78.6 Nm3/min=5.07 Kg/kwh
Cp= 0.25 K cal/kg 0C
Feed water Temp.= 70 0C
H= 663.755 k cal/kg
Temp of steam= 272.4 0C
Hrs/year= 8760
Qty of heat available from the flue gas= 650 * 5.07 * 0.25 * (532.4- 272.4)
= 214207.5 K cal/hrs
Qty of Steam generated = 214207.5 / (663.755- 70)
= 360.76 Kg/hrs (for one generator)
= 721.52 kg /hrs (for two generators)
= 721.52 * 8760 * 1.18 (steam cost)
Steam Generation Cost saving = Rs. 7458207.9/ year
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 26/51
Page 26 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
17.3. Burners Inefficiency at Singeing M/c
Burners are not adjusted with respect to the fabric width. Burner flames remains open either fabric width is 66”
or 116”
Usually Singeing machine consumes gas 0.0015 m3 (industry benchmark) for 1 linear meter of fabric but in
MFTML singeing machine consumes 0.005 m3 for 1 linear meter of fabric.
Average production = 11648599 meters for based on last 3 years (2007-2009) production data
= 17472.99 If M/c consumes 0.0015 m3 gas for 1 linear meter fabric
= 58242.99 m3 (machine consumes 0.005 m3 gas for 1 meter fabric)
Difference = 40770 m3
Gas Cost = 10.44 Rs. /m3
Amount Loss = Rs. 425638.8
NOTE: The amount may be increased because all flames are remains open either fabric width is 66” or 116”.
This amount is additional to that which can be saved if flames are adjusted as per the width of the fabric.
17.4. Steam Generation
MFTML has four gas fired boilers generating steam primarily for the processing area while partly it is
utilized in garment section and three thermo boilers in the processing area.
Gas, Air mixture
Water, chemicals
Boilers
Steam
Stack Gases @ 324 C as
waste gas
Blow Down
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 27/51
Page 27 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Boiler#1
Make: Standard Duisburg Kessel
Construction Year 1960 Type Fire TubeChimney Height approx 28-30 ft Fuel Gas Fired
Boiler # 2
Make: Babcock Steam Block
Construction Year 1969 Type Fire Tube
Chimney Height approx 50 ft Fuel Gas Fired
Boiler # 3
Make: GWB Boilers
Construction Year Not Available Type Fire Tube
Chimney Height approx 32 ft Fuel Gas Fired
Boiler # 4
Make: GWB Boilers
Construction Year Not Available Type Fire Tube
Chimney Height approx 25 ft Fuel Gas Fired
Thermal Rating of Oil Heater
# Thermal
Rating
(kcal/hr)
Oil
circulation
(m3/hr)
Oil
Holding
Capacity
(lit)
Temperature
(˚C)
Machines
operated
Gas
consumption
(m3/day)
Electricity
consumption
(kWh)
1 2000 2200 250 Stenter I
(4chamber),Stork
Steamer I.
950 50
2 2200 2200 250 Rotary Printing,
Stork Steamer II,
1250 50
3 1800 2200 250-280 Stenter (6
Chamber)
1300 35
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 28/51
Page 28 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
The stack gases analysis results as follows
STACK GAS ANALYSIS FROM THERMO BOILER I
S.No. Parameters Unit Monitoring Results
1 Temperature (Ambient) oC 31.4
2 Temperature (Stack) oC 226.9
3 Carbon Monoxide ppm ---
4 Carbon dioxide % ---
5 Nitrogen Oxide ppm ---
6 Nitrogen dioxide ppm 0.2
7 Sulphur Oxide ppm ---
8 Hydrogen ppm 55
9 Oxygen % 20.49
STACK GAS ANALYSIS FROM BOILER II
S.No. Parameters Unit Monitoring Results
1 Temperature (Ambient) oC 27.8
2 Temperature (Stack) oC 182.6
3 Carbon Monoxide ppm 167
4 Carbon dioxide % Nil
5 Nitrogen Oxide ppm 1
6 Nitrogen dioxide ppm 0.1
7 Sulphur Oxide ppm ---
8 Hydrogen ppm 60
9 Oxygen % 20.23
On the basis of oxygen and CO2 contents of the stag flue gases the combustion efficiency is in the range of 80-
85%. This low efficiency is due to the high oxygen content in the flue gas.
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 29/51
Page 29 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
STACK GAS ANALYSIS FROM THERMO BOILER II
S.No. Parameters Unit Monitoring Results
1 Temperature (Ambient)o
C 31.02 Temperature (Stack) oC 324.3
3 Carbon Monoxide ppm 5
4 Carbon dioxide % 7.02
5 Nitrogen Oxide ppm 36
6 Nitrogen dioxide ppm 0.1
7 Sulphur Oxide ppm ---
8 Hydrogen ppm 52
9 Oxygen % 8.62
STACK GAS ANALYSIS FROM THERMO BOILER III
S.No. Parameters Unit Monitoring Results
1 Temperature (Ambient) oC 31.3
2 Temperature (Stack) oC 289.1
3 Carbon Monoxide ppm 8
4 Carbon dioxide % 10.21
5 Nitrogen Oxide ppm 52
6 Nitrogen dioxide ppm 0.5
7 Sulphur Oxide ppm ---
8 Hydrogen ppm 29
9 Oxygen % 2.99
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 30/51
Page 30 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
17.5. Energy Consumer
Electrical Power Consumption
Electrical Power in MFTML is used for running the processing machines, motors, pumps, compressors,
lighting, air conditioning, chillers etc. The major consumer of electric load is machines, motors and
pumps. The detail of electrical load requirement for major machines is tabulated below.
MACHINE TYPE NOMINATIVE POWER (kW)
Singe-Desize 20
Benninger Pretreatment 44
Benninger Mercerize 20
Cylinder Dryer 11
Kuster Pretreatment 40
Kuster Washing 50
Benninger Pad Steam 20
Monforts Thermosole I 18
Monforts Thermosole II 30
Jet 12
Jigger I,II 10
Monforts Stenter II 80
Monforts Stenter IV 90
Bruckener Stenter 60
Zimmer Flat Bed Printing 75
Zimmer Rotary Printing 90Kuster Calendar 80
Electrical Power
Machines
Motors
Pumps
Compressors
Mechanical Power
Heat
Vibration
Lighting
Cooling
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 31/51
Page 31 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Motors Data
COMPRESSOR DATA
There are 8 compressors in the mill. Compressor # 4,5 & 6 are not working nowdays.
Description Compressor # 1 Compressor #2 Compressor #3 Compressor #7 Compressor #
Location
Make Atlas copco Atlas copco Atlas copco Atlas copco Atlas copco
Type Rotary screw
type
Rotary screw
type
Rotary screw
type
Rotary screw
type
Rotary screw
type
Rated power
(kW)
160 160 160 90 37
Cooling method Water Water Water Air Air
Free Air Delivery
(m3/min)
386 386 386 98
Set operating
pressure (bar)
6.5 6.5 6.5 6.5 6.2
Receiver tank
volume (m3)
Drain System Manual Manual Manual Manual Manual
Dryer Install & in
working
condition
Install but not
working
Install but not
working
Install but not
working
Install but not
working
Delivery line size 3" 3" 3" 2" 2"
Suction status Normal Normal Normal Not workproperly
Good
Max. Speed (rpm) 1500 1500 1500 2970 3000
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 32/51
Page 32 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
On the basis of measurement exercise, the motors were found to be operated at low efficiency level i.e. 85%
compared to industrial norm of atleast 90% efficiency level.
MOTOR LOW EFFICIENCY COST
hp= 12.7
Actual efficiency= 85 %
Desired Efficiency = 90%
Operating hrs/ year = 6300
Unit price = 3.61 Rs/ kwh
@ 85 % efficiency = 12.7 * 0.745/ 0.85 = 11.43 kw
@ 90 %efficiency = 12.7 * 0.745/ 0.90 = 10.51 kw
Total loss = 11.43 – 10.51 = 0.917 kw
Cost Saving = 0.917 * 6300 (running hours) * 3.61 (electricity generation fuel cost) = Rs. 20855.331/ year
Total motors = 210
Total cost savings for all motors = Rs. 4400405 / yr (approximation used is that all motors were
assumed at 12.7 HP although the Hp ranges from 0.08-60 Hp)
Savings through Effective Lighting
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 33/51
Page 33 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
17.6 Steam / Heat Consumption
Measurement data demonstrated that heat energy contained in steam and hot water is wasted during
steam distribution through condensate, steam leakages, steam traps, hot water drainage etc. Also gas
as fuel is wasted during singeing process when flame is not adjusted as per the fabric width.
Heat (Flame, Steam,
Hot Water)
Fabric
Machines
Pipes
Mechanical Power
Steam Leakage (pipes,
tra s
Loss through conduction
Hot water drain
Condensate
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 34/51
Page 34 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Cost Impact Calculations for Steam Leakages.
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 35/51
Page 35 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 36/51
Page 36 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Cost Impact Calculations for Semi Insulated Steam pipes and bare steam pipes
.
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 37/51
Page 37 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Wastage of Water
Cooling water is drained from different areas of machines. This water can be reused.
Kuster Bleaching
Cost Saving from Drive motors Water of chamber # 3 & 7:
From Chamber # 3
drive motor
18 lit/min 25920 lit/day 25.92 m3/day
From Chamber # 7
drive motor
24 lit/min 34560 lit/day 34.56 m3/day
Total 42 lit/min 60480 lit/day =
13321.6 gallons/day
60.48 m3/day
This water is used at ambient temperature.
Cost of 1 gallon of water = 0.15 Rs.
Drainage water cost = 1998.23 Rs./day = 599471.36 Rs./ year (Assume 300 working days)
Advice
Since purpose this water is to cool the hydraulic motor drives and usually a fast flow rate is maintained ,
therefore this water can be reused either by transferring it to tank or use it in the washing chambers.
Kuster Bleaching
Post washing water will be used in the prewashing chamber; this will save the water cost i.e.
Waster used in the pre washing chamber = 2 l/kg
Average production = 12499886 meters for 2009
= 2499977 kg for 2009 (Assume 200 gm per linear meter)
= 2499977 * 2 = 4999954 litres
Water cost = 0.15 Rs.
Total loss = 4999954 * 0.15 = 749993 Rs./year 2009
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 38/51
Page 38 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
DYEING
From Hydraulic pump
Padder motor
12 lit/min 17280 lit/day 17.28 m3/day
Total 12 lit/min 17280 lit/day =
3806 gallons/day
17.28 m3/day
Cost of 1 gallon of water = 0.15 Rs.
Drainage water cost = 570 Rs./day = 171277 Rs./ year (Assume 300 working days)
SINGEING MACHINE:
Cost saving at Singeing M/c.
Water from Right
burner (Temp of
water @ 50C)
7.6 lit/min 10944 lit/day 10.944 m3/day
Water from Left
burner(Temp of water
@ 50C)
11.8 lit/min 16992 lit/day 16.992 m3/day
Water from Upside
Cooling(Temp of
water @ 30C)
33.5 lit/min 48240 lit/day 48.240 m3/day
Water from Downside
Cooling(Temp of
water @ 30C)
25.4 lit/min 36576 lit/day 36.576 m3/day
Total (Temp of water
@ 40C)
78.3 lit/min 112752 lit/day
=24835 gallons/day
112.752 m3/day
Cost of 1 Gallon of Water= 0.15 Rs.
Drain water cost =3725.28 Rs./day = 1117585 Rs./ year (Assume 300 working days)
This water can be reused at the singeing machine.
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 39/51
Page 39 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
17.7.Management Practices
Maintenance Systems
There is no formal preventive maintenance system in place for all the power producing and consuming
equipments. No preventive maintenance schedules, checklists and records were shown during the
audit.
Machine breakdown data was not provided. The overall equipment condition, steam and water pipes
condition, insulation status, apparent steam and water leakages indicated the lack of maintenance and
availability of resources.
Quality Control
In effective process and product Quality Control is an indirect source of energy wastage. The re-work
records related to stenter 2 & 4 for the year 2009 is tabulated below
Month Stenter 2 Stenter 4
Jan 12060 9005
Feb - 16115
Mar - 16570
Apr 2170 15760
May 3322 11,157
Jun 13836 14225Jul 20790 35805
Aug 350 2140
Sep 1550 1665
Oct 5895 21205
Nov 14090 14225
Dec 15695 16380
Total = 264,010 m
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 40/51
Page 40 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Process Instrumentation
Availability of gauges for monitoring of temperatures, pressures, flow rates etc during the entire
course of electricity and steam generation and distribution and manufacturing processes is very scarce.
Even at critical stages e.g. gas flow rate at boiler is not measured and monitored.
The energy data utilized by the company is derived more from approximation rather than from
measurement.
No formal calibration system is in place. At places measuring devices are not in working conditions.
Measurement and Monitoring of Energy Key Performance Indicators (EnKPI’s)
Currently company has not identified nor monitoring any EnKPI’s in relation with the cost. MFTML
finance department records and reports the cost of electricity generation, steam generation, electricity
consumption, steam consumption on approximation basis and does not compare the consumption
trends with any benchmark values. Inability to identify, measure and monitor EnKPI’s deprives the
organization to focus on increasing the efficiency in energy generation and consumption thereby
reducing cost.
Housekeeping Issues
A very untidy atmosphere is prevalent in the processing area. Management and workers are not
focused to capture the energy efficiency opportunities merely by practicing Good Housekeeping
Practices which requires no dust and dirt in the area, no leakages of steam and spillage of water.
Presently except for floor cleaning no other part of the machine, work place, including tube lights is
cleaned
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 41/51
Page 41 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Total Cost Saving Opportunities
Area Domain Savings in Rupees/year
Power Generation Power Factor Improvement 6350018
Using Waste Heat of Stack gases 7458207
Power Consumption Increasing Motor Efficiency 4400405
Lighting 280479
Gas Combustion Singeing 425638
Steam Consumption Leakages, insulation, hot water
drainage etc
316662
Water Wastage Water for Cooling purpose 1692018
Total Savings
20923427
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 42/51
Page 42 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
18. Energy Management Objectives (To Be Scenario)
Objective # 1
OBJECTIVE NAME To improve the power factor of Generators from 0.75 to 0.90 byinstalling PFI panel
DOMAIN Power Generation CATEGORY Short Term
PURPOSE OF
OBJECTIVE
To balance the power generation and distribution efficiency in case of
fluctuating load demands.
RESULT OF
OBJECTIVE
Gas savings in power generation.
TARGET START DATE April 2010 TARGET COMPLETION DATE June 2010
APPROX INVESTMENT Rs. 1 Million APPROX
SAVINGS
Rs. 6 Million PAYBACK
PERIOD
2 month
DETAILS /STEPS RESPONSIBILITY
Seeking Managing Director approval for investment based on
potential cost savings and low pack back period.
GM Operations
Seeking quotes for PFI panel Utility Manager
Meeting with equipment suppliers and seeking best energy
efficiency arrangement and configuration. Discuss current and
future power generation requirements and arrangements.
Utility Manager
Requesting potential suppliers to arrange demo of anyindustrial unit for application of PFI panel and its impact on
cost savings.
Utility Manager
Selecting supplier Utility Manager
Installation of PFI panel Utility Manager
Monitoring PF improvement at power generation and
consumption stages
Utility Manager / Energ
Manager
Monitor cost impact for two months. Utility Manager / Energ
Manager
Report observations to management. Utility Manager / EnergManager
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 43/51
Page 43 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Objective # 2
OBJECTIVE NAME Steam generation through Waste Heat Recovery Boiler by utilizing
waste gases of generatorsDOMAIN Power & Steam Generation CATEGORY Mid Term
PURPOSE OF
OBJECTIVE
To utilize the high temperature of stack gases from generators for steam
generation
RESULT OF
OBJECTIVE
Reduction in steam demand from conventional boilers thereby reducing gas
consumption for steam generation
TARGET START DATE Jan 2011 TARGET COMPLETION DATE Jun 2011
APPROX INVESTMENT Rs 8 Million APPROX
SAVINGS
Rs. 7.4million
PAYBACK
PERIOD
13months
DETAILS /STEPS RESPONSIBILITY
Seeking Managing Director approval for investment based onpotential cost savings and low pack back period.
GM Operations
Seeking quotes for WHRB Utility Manager
Meeting with equipment suppliers and seeking best energy
efficiency arrangement and configuration. Discuss current and
future power generation requirements and arrangements and
potential of steam generation.
Utility Manager
Identification of land requirements and installation area. Utility Manager
Requesting equipment supplier to submit technical and
financial data related to proposed WHRB including costsavings related to natural gas savings at conventional boilers.
Utility Manager
Evaluate simplex and duplex WHRB models and their cost
impact in terms of investment.
Utility Manager
Requesting potential suppliers to arrange demo of any
industrial unit for application of WHRB and its impact on cost
savings.
Utility Manager
Selecting supplier Utility Manager
Design, Fabrication and Installation of WHRB Supplier
Monitoring steam generation data from WHRB at different
power generation loads
Utility Manager / Energ
Manager
Monitor cost impact for two months. Utility Manager / Energ
Manager
Report observations to management. Utility Manager / Energ
Manager
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 44/51
Page 44 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Objective # 3
OBJECTIVE NAME Improving the electric motors efficiency from 85% to 90%
DOMAIN Power Consumption CATEGORY Short TermPURPOSE OF
OBJECTIVE
To increase motors efficiency
RESULT OF
OBJECTIVE
Direct reduction in electrical load and indirect savings at power generation fue
TARGET START DATE Immediate TARGET COMPLETION DATE Dec 2010
APPROX INVESTMENT Rs. 2 million APPROX
SAVINGS
Rs 4.4 Million PAYBACK
PERIOD
6 month
DETAILS /STEPS RESPONSIBILITY
This objective does not require heavy financial investment compared
to commitment and determination from the Mechanical and Electrical
Maintenance Team to focus on preventive maintenance of each
motors and ensuring that it runs at its optimum efficiency.
If the total preventive maintenance cost on all the machines is
approximated at Rs.2 million per year, the payback period of this
investment is 6 months.
Also in case of continuing preventive maintenance , the cost on
preventive maintenance will decrease appreciably while savings
remains the same
Mechanical and
Electrical Managers
Randomly select motors and measure their actual efficiency andcalculate the energy losses. Energy Manager
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 45/51
Page 45 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Objective # 4
OBJECTIVE NAME Replacing existing tube lights and mercury bulbs with energy savers
DOMAIN Power Consumption CATEGORY Short TermPURPOSE OF
OBJECTIVE
To achieve reduction in electric power demand
RESULT OF
OBJECTIVE
Direct reduction in electrical load and indirect savings at power generation fue
TARGET START DATE April 2010 TARGET COMPLETION DATE June 2010
APPROX INVESTMENT Rs 1.25 Lac APPROX
SAVINGS
Rs 2.3 Lacs PAYBACK
PERIOD
5 month
DETAILS /STEPS RESPONSIBILITY
Determine the lux value currently in each area and compare it
with the required lux value.
Electrical Manager for
measurement
Departmental
Managers for identifying
required lux value
Determine the number of energy savers required to obtained
the required lux value and compare it with number of
tubelights required to obtain the same lux value
Electrical Manager
Based on this comparison, replace the tubelights with energy
savers
Electrical Manager
Monitor cost impact for two months. Energy Manager Report observations to management. Energy Manager
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 46/51
Page 46 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Objective # 5
OBJECTIVE NAME To improve burners efficiency at singeing
DOMAIN Power Consumption CATEGORY Short TermPURPOSE OF
OBJECTIVE
To achieve reduction in gas consumption
RESULT OF
OBJECTIVE
Gas consumption per kg of fabric will decrease.
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT Rs. 1 Lac APPROX
SAVINGS
Rs 4 lacs PAYBACK
PERIOD
3 month
DETAILS /STEPS RESPONSIBILITY
This objective does not require heavy financial investment compared
to commitment and determination from the Mechanical team and
machine operator to focus on preventive maintenance of each burner
and regular cleaning of the machine and ensuring that it runs at its
optimum efficiency.
Mechanical Manager
Objective # 6
OBJECTIVE NAME To eliminate steam leakages at different machines and improveefficiency of steam traps
DOMAIN Steam Consumption CATEGORY Short TermPURPOSE OF
OBJECTIVE
To achieve reduction in steam consumption demand thereby reducing gas
consumption
RESULT OF
OBJECTIVE
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT To be determined APPROX
SAVINGS
Rs 2.6 lacs PAYBACK
PERIOD
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 47/51
Page 47 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Objective # 7
OBJECTIVE NAME To reduce heat losses due to semi insulated and un-insulated pipes
DOMAIN Steam Consumption CATEGORY Short Term
PURPOSE OF
OBJECTIVE
To achieve reduction in steam consumption demand thereby reducing gas
consumption
RESULT OF
OBJECTIVE
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT To be determined APPROX
SAVINGS
Rs 52000 PAYBACK
PERIOD
Objective # 8
OBJECTIVE NAME To reduce water wastageDOMAIN Water CATEGORY Short Term
PURPOSE OF
OBJECTIVE
To achieve reduction in water consumption in processing area
RESULT OF
OBJECTIVE
Improved water consumption will not only reduce the water bills but also
reduce the wastewater which if untreated is an environmental burden.
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT APPROX
SAVINGS
Rs.1.7million
PAYBACK
PERIOD
DETAILS /STEPS RESPONSIBILITY
Determination of areas at each machine where outflow watercan either be reused in the same process/machine or used at
another machine / process.
Dyeing and PrintingManager
Evaluate the current water inflow rate and compare it with the
process requirements. Identify the impact on Quality of
process and final product in case of reduction in inflow rate.
Dyeing and Printing
Manager
Based on above, identify the viable options for each machine Dyeing and Printing
Manager
Determine the additional piping work and storage tanks
required.
Mechanical Manager
In case of piping work and storage tanks, determine the cost
involved at each machine and the amount of water saved and
its cost.
Mechanical Manager
Seek management approval for piping work/storage tanks. Mechanical Manager
Monitor water outflow rate and calculate cost savings. Energy Manager
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 48/51
Page 48 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Objective # 9
OBJECTIVE NAME To develop and implement effective Total Preventive Maintenance
SystemDOMAIN Management Systems CATEGORY Short Term
PURPOSE OF
OBJECTIVE
To improve machine energy consumption efficiency and reduce wastages
RESULT OF
OBJECTIVE
Decreased breakdowns, improved energy consumption
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT To be determined APPROX
SAVINGS
PAYBACK
PERIOD
DETAILS /STEPS RESPONSIBILITY
For each machine identify the electrical and mechanicalparameters which needs to be regularly checked on daily,
weekly and monthly basis. Focus not only machines but
electrical distribution equipments including panels
Mechanical andElectrical Managers
Train machine operators on basic machine cleaning Mechanical and
Electrical Managers
For each breakdown maintenance , maintain the record in
terms of stoppages and cost incurred on breakdown
maintenance.
Mechanical and
Electrical Managers
Implement the preventive maintenance checklist and monitor
the reduction in breakdown stoppages.
Mechanical and
Electrical Managers
Calculate the energy savings due to reduction in stoppages. Energy Manager
Objective # 10
OBJECTIVE NAME To enhance In-process Quality Control based on Quality Plan
DOMAIN Management Systems CATEGORY Short Term
PURPOSE OF
OBJECTIVE
To reduce reworks at processing
RESULT OF
OBJECTIVE
Indirect energy saving by improving per fabric consumption due to higher
productivity.
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT APPROX
SAVINGS
PAYBACK
PERIOD
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 49/51
Page 49 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Objective # 11
OBJECTIVE NAME To develop cost driven based effective Energy ManagementInformation System based on Energy Key Performance Indicators
(EnKPI’s) DOMAIN Management Systems CATEGORY Short Term
PURPOSE OF
OBJECTIVE
To support management in monitoring the cost of energy in relation to overall
cost of production and also sponsoring areas for energy conservation.
RESULT OF
OBJECTIVE
Identification of actual cost impact at each energy production and consumptio
point.
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT APPROX
SAVINGS
PAYBACK
PERIOD
Objective # 12-a
OBJECTIVE NAME To install measuring devices (temperature gauges, flow meters,pressure gauges etc) based on EnKPI’s
DOMAIN Steam Consumption CATEGORY Long term
PURPOSE OF
OBJECTIVE
To support in the implementation of EnMIS and also in monitoring of energy
production and consumption efficiency.
RESULT OF
OBJECTIVE
Cost savings due to identification of areas consuming more energy or
inefficient energy producers
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT APPROX
SAVINGS
PAYBACK
PERIOD
DETAILS /STEPS RESPONSIBILITY
Based on EnKPI’s and EnMIS, identify the points at each
machine / equipments where data related to energy
production and consumption is required either by installing
flow meters, pressure gauges, temperature gauges,
Energy Manager
Select measuring devices installation points based on material
and energy balance approach.
Energy Manager
Determine the accuracy requirement for each measuring
device
Energy Manager
Select measuring devices Energy Manager
Seek quotations Energy Manager
Installation of measuring devices Energy Manager
Feeding data in EnMIS software and generating reporting
containing technical data and financial calculations.
Energy Manager
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 50/51
Page 50 of 51
EnMS Program supported by
GTZ-SMEDA-APTMA
Objective # 12-b
OBJECTIVE NAME To engage Energy & Environmental Department Lab of QUEST for
energy related testing services based on EnKPI’sDOMAIN Steam Consumption CATEGORY Short Term
PURPOSE OF
OBJECTIVE
RESULT OF
OBJECTIVE
TARGET START DATE TARGET COMPLETION DATE
APPROX INVESTMENT APPROX
SAVINGS
PAYBACK
PERIOD
8/3/2019 Implementation of EnMS at MFT
http://slidepdf.com/reader/full/implementation-of-enms-at-mft 51/51
EnMS Program supported by
GTZ-SMEDA-APTMA
Implementation Strategy for Energy Management Objectives
Arch Associates recommends that in order to ensure complete and effective implementation of EMO’s, a
realistic road map based on current financial status of MFTML be developed.
We propose to take on those EMO first which require an investment of upto Rs 1 million and less and after
achieving savings from these actions, channelize savings in those areas which require investment of more than
one million or has high payback period i.e. more than one year.
CONCLUSION:
The objectives set for MFTML after being achieved the industry will be conforming to the International
Industry Bench marks. The bench marks are identified for textile industry in the report as well. It meansMFTML will be amongst the good practicing industries and an example for other textile units operating
in the area.