MANZANILLO, COLIMA. MEXICO I M P A L A W A R E H O U S I N G BULK CONCENTRATE STORAGE FACILITY

description

Presentacion del complejo industrial Impala Warehousing

Transcript of Impala Warehousing

Page 1: Impala Warehousing

MANZANILLO, COLIMA. MEXICO

I M P A L A

W A R E H O U S I N G

BULK CONCENTRATE STORAGE FACILITY

Page 2: Impala Warehousing

Impala Warehousing

37 acre Development, including:

• Corporate Offices Building

• High Tech Laboratory & Sampling Dock

• 50,000 m² enclosed storage

• 100,000 m² open area storage

• Shops & Warehouse for Operation’s fleet

maintenance

• 6 Scale Weighting Stations linked to the data

network

• Fuel Station with 40,000 Lt Diesel capacity

Page 3: Impala Warehousing

• 8 meter high perimeter wall

• Fiber Optic Telecommunications

• High Tech Global CCTV Closed Circuit Television System

• Hydrant based Fire Fighting System

• 1,500 KVA Power Substation with Emergency Power generation at full charge

• 500 KVA Laboratory Power Substation with Emergency Power generation at full charge

• Complex wide Storm drainage Treatment Plant

• Precast High flow Storm Trenches system that performs pre-decantation, reinforced grids to support loaded eighteen wheelers transit

• 5 Wash Bays with high pressure washing system for incoming and outgoing trucks

Impala Warehousing

Page 4: Impala Warehousing

30,000 m² structure for Copper storage

Foundation

550 tonns of reinforcement steel

7,750 m³ of concrete in 15 meter deep piles @ 1.20 m

average diameter

10 inch concrete slab reinforced with high strenght

thermofused 3/8" steel rebar, executed in 50 days

Structure

2,250 tonns of A-50 structural steel

5,000 m² roofed storage area delivered to the client

every 4 weeks, without affecting the operational

functionality

Complete storage facility delivered in 6 months

Transport, Sandblast, Painting and installation of up to

200 tonns of A-50 structural steel on a typical week

KR-18 Sheet metal roofing, 180° joint, fully waterproof

system

Page 5: Impala Warehousing

10,000 m² structure for Zinc storage

Foundation

34 tonns of reinforcement steel

250 m³ of concrete in 15 meter deep piles @ 1.0

meter average diameter

10 inch concrete slab reinforced with high strenght

thermofused 3/8" steel rebar, executed in 20 days

Structure

880 tonns of A-50 structural steel

Complete storage facility delivered in 3 months

KR-18 Sheet metal roofing, 180° joint, fully

waterproof system

Page 6: Impala Warehousing

2,500 m² enclosed storage facility

for precious metals

Foundation

10 tonns of reinforcement steel

120 m³ of premixed concrete

10 inch concrete reinforced with high strenght

thermofused 3/8" steel rebar, executed in 3 days

Structure

450 tonns of A-50 structural steel

Complete storage facility delivered in 3 months

KR-18 Sheet metal roofing, 180° joint, fully waterproof

system

Page 7: Impala Warehousing

5,000 m² Isolated Lead storage facility

Foundation

40 tonns of reinforcement steel

300 m³ of premixed concrete

Precast concrete wall system conforms interior

material holding bays

10 inch concrete reinforced with high strenght

thermofused 3/8" steel rebar

Structure

1,000 tonns of A-50 structural steel

Completely isolated storage design facility, All Lead is

contained within, isolated from the rest of the complex

This facility is still under construction

KR-18 Sheet metal roofing, 180° joint, fully waterproof

system

Page 8: Impala Warehousing

Fuel Station

40,000 lt Diesel capacity

2 Wheel loader simultaneous fueling capacity

Facility constructed under PEMEX’s

standards

Electronically controlled Fuel supply, linked to

the main data infrastructure

Burst proof Enclosure

Page 9: Impala Warehousing

Each piece has 1 meter wide and 11

meters high

Each one is constructed with 5.5 m³

of premixed concrete and 350 kg of

reinforcement steel

110 m² of perimeter wall installation

in just 12 hours

620 pieces conform Impala

Warehousing’s perimeter

Precast division, Perimeter Walls

Page 10: Impala Warehousing

Precast Division, Architectural Wall

2 meter high architectural wall

20 m² installed per day

300 pieces installed at Impala Warehousing

2,100 m² of concrete parking lot slab, enclosed with

precast architectural walls, installed in only 21 days

Page 11: Impala Warehousing

Precast Division, Tankreto

Independant precast cistern system

12,000 liter storage capacity, with the ability to adjoin pieces

for increased storage capacity if required

5.5 m³ of premixed concrete with 150 kg of reinforcement

steel

1’128,000 liter capacity installed at Impala Warehousing

Page 12: Impala Warehousing

Precast Division, Storm Trenches

2.36 m. wide by 3 m. long precast pieces

Up to 42 Linear meters Installed each day

High speed flow capacity

Galvanized Reinforced heavy load Grids

Easy cleaning

Page 13: Impala Warehousing

Precast Division, Custom design

“J” shaped storm trenches that allow pre-

decantation process by retaining suspended

solids in the storm system

Column Protectors to maximize the storage space

and avoid accidental bumps to the structure

Movable Precast Walls to divide storage areas

with ease

Precast Custom solutions include Post anchors,

SuperPost footings. Manholes and registers,

Shade areas and service shacks and booths help

shorten the construction timeframe

Page 14: Impala Warehousing

General Power Substation

1,500 KVA installed capacity

2@750 KVA transformers, each backed up with a 750

KVA emergency diesel generator, joined together in a

redundant system that allows maintenance services

without electrical interruptions that may affect

operations

The building has 120 m³ of premixed concrete with 6

tonns of reinforcement steel, built in 30 days

All the equipment was installed in only 6 days

Page 15: Impala Warehousing

1,670 m³ premixed concrete

140 tonns of reinforcement steel

450 m² of Landscaping areas

5 executive meeting rooms

80 person Canteen / Dining room

CCTV & Data Sitte for the Complex

Completed in 4 Months

700 m² Corporate Offices

Page 16: Impala Warehousing

800 m² Maintenance facility

Parts warehouse Mezzanine with 1 ton/ m² capacity

Fully equipped shops and maintenance areas,

including compressed air system and oil change

ramps

450 m³ premixed concrete

40 tonns of reinforcement steel

KR-18 Sheet metal roofing, 180° joint, fully

waterproof system

Maintenance Shops & Parts Warehouse

Page 17: Impala Warehousing

Lockers, Showers &

Restrooms

80 m³ premixed concrete

14 tonns of reinforcement steel

Laundry Area

Shower & Dressing rooms

Locker room

24 hr service facility

To be Completed in 3 Months

Page 18: Impala Warehousing

Sampling Dock & Laboratory

800 m² High tech facility

Sampling dock with 6 truck simultaneous capacity

Fully equipped sampling pre-testing stage, Air extraction and dust recolection process

Fully equipped Lab, also with Air extraction and dust recolection process

250 m³ premixed concrete

20 tonns of reinforcement steel

Sampling dock has KR-18 Sheet metal roofing, 180° joint, fully waterproof system

Page 19: Impala Warehousing

Re-Weighting Station &

Panoramic Supervisor

Office

Full Operation views

Strategically placed

45 m³ premixed concrete

8 tonns of reinforcement steel

Page 20: Impala Warehousing

Support Areas

4 access/egress exchangeable lanes each with a Weighting Scale and a hidrojet Washbay tunnel to expedite Operations, fully integrated to the Fiber Optic Data network and Particle removal treatment plants to completely clean the water emission

Particle removal treatment plants to completely clean the water emission

Wastewater treatmant plants

Fire Fighting pressurized system

Presurized Irrigation system

Page 21: Impala Warehousing

OTHER ACTIVE PROJECTS

01 year Maintenance Contract

Cleanup, sandblasting and

rustproofing of upper impeller shield

and upper turbine shield.

Sandblasting and rustproofing of

spillway floodgates

Santa Rosa Dam Power Plant , CFE

Page 22: Impala Warehousing

01 year Maintenance Contract

Fabrication, galvanized rustproofing

and installation of main intake’s

metallic 65 ton grating

Agua Prieta Dam Power Plant , CFE

Page 23: Impala Warehousing

01 year Maintenance Contract

Puente Grande Dam Power Plant , CFE