Impacts of Transmission Tariff on Price Arbitrage … › hzareipo › files › hzareipo ›...
Transcript of Impacts of Transmission Tariff on Price Arbitrage … › hzareipo › files › hzareipo ›...
1
Impacts of Transmission Tariff on Price Arbitrage Operation
of Energy Storage System in Alberta Electricity Market
Abiola I. Adebayo1, Payam Zamani-Dehkordi, Hamidreza Zareipour, Andrew M. Knight
Department of Electrical and Computer Engineering, University of Calgary, Alberta, Canada
Abstract
This paper investigates the application of existing tariff structures to understand how they impact the
economic operation of energy storage system (ESS) for arbitrage. The scope of this research covers
impacts on profitability, operating cost, energy-traded volume, and price volatility. Two facilities of
different scales are considered: an ESS unit small enough to have no impact on price, and an ESS unit,
large enough to have a quantifiable impact on pool price. The hourly impact of ESS operations on the
pool price is estimated by modeling the price sensitivity quota curve from actual hourly market data.
Keywords: energy storage system, transmission tariff, electricity market
1 Corresponding Author: Abiola Adebayo;
Email: [email protected]; Phone: +1-587-433-2855; Fax: +1-403-282-6855
2
Notations
Index
k step size for Bid blocks
s step size for Offer blocks
t time in hours
Parameters
𝜆𝑡,𝑠 Hourly price factoring impact offer block s
𝜆𝑡,𝑘 Hourly price factoring impact of bid block k
𝛾𝑠 Storage efficiency
𝛾𝑐 Conversion efficiency
𝐵𝑑𝑘 Bids in blocks of 10MW
Lf Loss factor
Nk total number of Bid steps
Ns total number of Offer steps
𝑂𝑓𝑠 Offers in blocks of 10MW
𝑇𝑅𝐷𝑐 Trading charge by the system operator
𝑉𝑂𝑀𝑐 Variable operation and maintenance cost
Variables
𝐵𝑡,𝑘 Bid variables ranging from 0-9MW
𝐷𝑜𝑑 Depth of discharge𝑂𝑡,𝑠 offer variables ranging from 0-9MW
𝑃𝑐ℎ𝑡 Power from the grid to charge the system
𝑃𝑑𝑐ℎ𝑡 Power discharged to the grid
𝑆0 Initial state of charge
𝑆𝑡 State of charge at any time t
𝑈𝑡,𝑘 Binary variable indicating active bid block and charging status at any time t
𝑋𝑡,𝑠 Binary variable indicating active offer block and discharging status at any time t
3
1.0 INTRODUCTION
Increasing commercial interest in investment in energy storage systems (ESSs) has generated a need to
investigate factors that can affect the profitability of arbitrage operation in relevant electricity markets.
Common to all ESS facilities, operation and maintenance cost, capital cost, price variation, round-trip
efficiency, energy capacity-to-power ratio and self-discharge loss (Bradbury et al., 2014) all impact
operational profitability of ESS. The capital cost is rapidly changing and has been projected to decrease
significantly by 2020 in a report by Viswanathan et al. (2013) from Pacific Northwest National
Laboratory. Unique to each electricity market, the regulatory policy on storage operation also has
significant impact. Several jurisdictions in North America are reviewing existing policies or formulating
new policies to aid the integration of energy storage into the electricity market.
From a policy perspective, the past three years have been very interesting for energy storage. The U.S.
Federal Energy Regulatory Commission (FERC) implemented a series of related orders (755, 784, and
792) applicable to the electric power markets of Pennsylvania, Jersey, Maryland (PJM), Midcontinent
Independent System Operator (MISO), California Independent System Operator (CAISO), New York
Independent System Operator (NYISO), and Independent System Operator for New England (ISO-NE).
FERC order 755 ensures system operators develop pay for performance tariff for ancillary services
(Masiello et al., 2014); order 784 requires system operator to consider speed and accuracy in
formulating requirement for ancillary services, while order 792 places energy storage on same level
with conventional generators by considering it as a power source (Kintner-Meyer, 2014). Kintner-
Meyer (2014) exhaustively discusses the details of the implementation in each of those jurisdictions.
Even though the Independent System Operator in Alberta; Alberta Electric System Operator (AESO) is
still formulating suitable regulatory policy applicable to ESS, in general, the most important policy to
energy storage proponents in Alberta at the time of writing is the transmission tariff policy.
Transmission tariffs are important because merchant energy storage proponents are very interested in
how tariffs will affect their operating profit. ESS are not currently allowed to participate in the ancillary
service market, only synchronous facilities are allowed based on the current operating reserve technical
requirements (Chen, 2013). The approval of the proposed Western Electricity Coordinating Council
(WECC) Contingency Reserves Standard is expected to allow non-synchronous facilities to participate
in the regulating and spinning reserve market in Alberta (AESO, 2015a), and this is expected to be a
good source of revenue for ESS merchants.
The existing tariff structure in Alberta was not formulated with the consideration of bulk energy storage
facilities. There have been back-and-forth arguments as to how best to classify ESS. Some are of the
opinion that it should be treated as a transmission facility because its operation has the benefit of
deferring new investment in transmission asset and that it does not generate energy on its own but
4
merely withholds energy from the system to subsequently releases it back (Bubik, 2014). Klinkenborg
(2014) is of the opinion that their operation is in no way different than that of conventional generators
when discharging and another opinion is that they act as either load or generator (Cheng, 2014). The
fact that their operational modes can be regarded as either load or generation has led to suggestions that
the current tariff structure for demand and supply may be suitable. Several studies have been conducted
to estimate the potential profitability of arbitrage operation in various electricity markets. The existing
literature has covered deregulated electricity markets in Europe, North America, and elsewhere.
The study by Walawalkar et al. ( 2007) investigated the economics of energy storage operation in the
electricity market of New York by using market data from 2001 to 2005. The study shows that operation
of Sodium Sulphur battery and flywheel for arbitrage and regulation operation in the New York City
region has high probability of positive net present value. In the Electricity Reliability Council of Texas
(ERCOT) market, the maximum potential revenue obtainable from operating a hypothetical 8MW,
32MWh battery connected to HB_Houston node is estimated by Byrne and Silva-Monroy (2015), for
both energy arbitrage and regulation. This study emphasized how largely dependent potential revenue
is on market price fluctuation. The study by Fertig and Apt (2011) investigated the economics of pairing
Compressed Air Energy Storage (CAES) with wind farm in Houston using 2008 hourly ERCOT
electricity market price. Results showed that pairing CAES with a wind farm to smooth dispatchable
power from the farm or storing energy from the wind farm for arbitrage opportunity is not economically
viable. Considering performance-based regulation and battery life cycle, He et al. (2015) proposed an
optimal bidding strategy for a battery energy storage system to maximize profit in markets that have
implemented performance-based regulation (PBR) such as PJM. The study shows that incorporating
PBR and battery life cycle modeling could significantly improve overall economics of Battery Energy
Storage System (BESS).
Using five-year historical data, Adebayo et al. (2016) examined the economic viability of arbitrage
operation of battery in Alberta electricity market with a case study of 30MW, 120 MWh Vanadium
Redox Battery (VRB) considered large enough to have impact on the pool price of electricity. Taking
both impact of the battery operation on price and 2020 projected capital cost estimate into consideration,
the study showed that with a 34% reduction of capital cost, the case study considered could become
economically viable. Another study of Canada's second electricity market by Khani and Dadash Zadeh
(2015) assessed the economic viability of arbitrage operation of cryogenic energy storage with 60%
round-trip efficiency in Ontario electricity market, showing that the system cannot return expected
revenue and proposes a price modulation algorithm to competitively offer subsidy to the merchant.
In Europe, two different studies by Kazempour et al. (2009) and Moghaddam and Saeidian explore the
profitability of arbitrage operation of two different battery technologies; Sodium Sulphur (NaS) and
Vanadium Redox Battery (VRB) in the electricity market of Mainland Spain and reached a similar
conclusion. Findings by Kazempour et al. (2009) show that the 10MW, 70MWh NaS operating in
5
energy, regulating, and spinning reserve market cannot generate a return up to the minimum acceptable
return and thus proposed support mechanisms in form of tax benefits and gratuitous loan to potential
merchant. Similarly, Moghaddam and Saeidian (2010) concluded that a VRB of equivalent power rating
and storage capacity is also not economically viable.
Optimal operational strategy for an energy storage system to maximize arbitrage profit in the real-time
electricity market of Denmark is investigated in the study by Hu et al. (2010), with a comparison of two
battery technologies; VRB and Polysulfide-bromine(PSB). Numerical results from this study show that
PSB is a better investment choice as it has shorter payback time than VRB. With a special focus on
Finland in the Nordic electricity market, Zakeri and Syri (2014) examined the economics of various
energy storage technologies, noting that the ESS considered will require additional benefit to become
economically attractive. Ippolito et al. (2015) analyzed the economic viability of operating customer-
side NaS battery in the Italian electricity market and concluded that at the current hourly price, it is
currently not economically viable due to high initial investment cost. The economics of operating
compressed air energy storage in Turkish power market using probabilistic price estimation to obtain
annual profit from 2011 to 2041 is examined in a study by Yucekaya (2013). Based on net present value
and payback period estimates, this study shows that investment in such a project can be economically
viable. Steffen (2012) investigated the economic prospect of operating Pumped hydro storage system
in Germany using estimates of arbitrage profit from year 2002 to 2010. Internal rate-of-return (IRR)
estimates from this study are noted to be below average industry requirement but increase in renewable
energy penetration could expand opportunity.
Policies in different jurisdictions may affect the economics and general operation of EES. In this paper,
we investigate the impact of transmission tariff policy on the economics of arbitrage operation of ESS
in the Alberta electricity market. Using the AESO’s tariff policy documents accessible on the AESO
website, we incorporate all the potential tariff structures applicable to the ESS operation into a Mixed
Integer Linear Programming (MILP) self-scheduling optimization model to obtain operating profit for
ESS large enough to impact the pool price and another one considered to be small scale with negligible
impact on price. The contributions of this paper are to:
• Formulate a price-maker model using actual historical data from hourly supply curve in Alberta
electricity market;
• Incorporate Alberta's transmission tariff into an economic dispatch model for both price taker
and price maker ESSs; and
• Analyze the impact of energy storage operation on price volatility in Alberta electricity market.
The paper is structured as follows. Section two gives an overview of the tariff structure in Alberta
applicable to ESSs. The energy storage operation model is described in section three. Section four gives
details of the case study considered and section five provides the results.
6
2.0 THE TRANSMISSION TARIFF IN ALBERTA
Alberta’s electric system is legislated to be congestion free (AlbertaEnergy, 2012), requiring continuous
investment in transmission facilities to ensure that sufficient capacity will be available for any device
to connect to the grid irrespective of location. The costs incurred to meet this legislative requirement
are significant and are recovered from the participants in the electricity market through transmission
tariffs. In the following sections, the existing tariff rates that may be applicable to ESS are described
(AESO, 2015b).
2.1 Demand Transmission Service (DTS) Rate
This tariff is applicable to all demand and may be applied to a storage facility during charging operation,
given that an ESS draws power from the grid just like any other load. This tariff comprises the
following:
Connection Charge: The breakdown of the connection charge components is presented in Table 1. The
various charges can be divided into their fixed and variable components. The variable component is
comprised of the metered energy component of Bulk and Local system charges. These components vary
based on operation pattern of the ESS, and thus must be included in the self-scheduling optimization
model later described in section three. The most significant portion of the fixed component is the
coincident-metered demand. This charge is applied to the metered demand that occurred during the 15-
minute interval of peak system demand in each month. This portion is also based on the operation
pattern of the ESS but cannot be included in the optimization model because it is an a-posterioric charge.
In this analysis, we assume that the energy storage facilities have their own substation thus we neglect
Point-of-Delivery charge in the formulation.
Operating Reserve Charge: The AESO estimates this as the sum of the product of the metered energy
and 7.98% of the hourly pool price over all hours of the settlement period. This portion has to be
included in the optimization model since the system can adjust its operation to optimize this cost.
Voltage Control Charge: This is estimated by the AESO as the product of metered energy and
$0.03/MWh over the settlement period. Because this also varies based on the ESS operation, it is
included in the optimization model discussed in Section 3.
Other System Support Charge: This tariff is estimated as the product of the highest metered demand in
the settlement period and $20/MW/month.
7
Table 1: DTS tariff –Connection charge breakdown (AESO, 2015b)
Volume in Settlement Period Charge
Bulk System charge
(a) Coincident metered demand $5,033.00/MW/month
(b) Metered energy $1.68/MWh
Local System Charge
(c) Billing capacity $1,243.00/MW/month
(d) Metered energy $0.70/MWh
Point-of-Delivery Charge
(e) Substation fraction $10,926.00/month
(f) First (7.5 × substation fraction) MW of billing
capacity
$7,401.00/MW/month
(g) Next (9.5 × substation fraction) MW of billing
capacity
$2,732.00/MW/month
(h) Next (23 × substation fraction) MW of billing
capacity
$1,655.00/MW/month
(i) All remaining MW of billing capacity $907.00/MW/month
2.2 Supply Transmission Service (STS) Rate
The Supply Transmission Service rate is applicable to system access service at points of supply. The
tariff applies to all system generators, so may be considered to apply to ESS while discharging. It is
calculated as the product of metered energy sold to the grid over the settlement period, pool price and
loss factor which is determined by the System Operator. Loss factors are location dependent, and due
to the complexity involved, an average loss factor is considered. The average loss factor was 3.39%
between the periods of January and December 2014(Yu et al., 2013). The actual loss factor may be
higher or lower than this, depending on the location where the ESS is sited.
3.0 ENERGY STORAGE OPERATION MODEL
In this section, the formulation of a generic ESS model to obtain optimal operating profit from arbitrage
operation in the energy market is presented. This model is used for small-scale ESS (small enough to
have negligible impact on pool price). For large-scale storage, the formulation is adjusted to account
for impact on pool price as a result of the ESS operation.
8
3.1 Formulation for the Price Taker
The equations below describe a generic model for a small-scale ESS. Additional technical constraints
and choice of parameters are used to depict possible unique features of each technology.
The objective function (1) is to maximize the arbitrage operating profit, that is, the difference between
revenue and cost from participation in the energy market, considering fixed and variable operation and
maintenance costs. It ensures the facility would rather remain idle if the summation of revenue obtainable
from selling power is not greater or equal to the cost of buying power to charge the system and other cost
component. Equation (2) is the revenue obtainable from selling discharge power 𝑃𝑑𝑐ℎ𝑡 at price 𝜆𝑡 while
equation (3) is the costs of buying power 𝑃𝑝𝑐ℎ𝑡 at 𝜆𝑡, variable operation & maintenance cost, trading
charge 𝑇𝑅𝑐, variable component of rate DTS 𝐶𝐷𝑇𝑆, operating reserve charge 𝑂𝑅𝑐 , and rate STS which is
the product of load factor 𝐿𝑓, pool price and power discharged. The variable component of rate DTS
𝐶𝐷𝑇𝑆 comprises bulk system charge, regional system charge and voltage control charge.
𝑀𝑎𝑥 ( 𝑅𝑒𝑣𝑒𝑛𝑢𝑒 − 𝐶𝑜𝑠𝑡) (1)
𝑅𝑒𝑣𝑒𝑛𝑢𝑒 = ∑ 𝜆𝑡𝑇𝑡=1 𝑃𝑑𝑐ℎ
𝑡 (2)
𝐶𝑜𝑠𝑡 = ∑ 𝜆𝑡𝑃𝑐ℎ𝑡𝑇
𝑡=1 + (𝑉𝑂𝑀𝑐 + 𝑇𝑅𝑐)(𝑃𝑑𝑐ℎ𝑡 + 𝑃𝑐ℎ
𝑡 ) + 𝐶𝐷𝑇𝑆 . 𝑃𝑐ℎ𝑡 + 𝜆𝑡(𝑃𝑐ℎ
𝑡 . 𝑂𝑅𝑐 + 𝐿𝑓 . 𝑃𝑑𝑐ℎ𝑡 ) (3)
Equation (4) ensures that the system can discharge (xt=1) or charge (ut =1), but not at the same hour. It
can however be in an idle mode when xt= ut=0.
𝑥𝑡 + 𝑢𝑡 ≤ 1 (4)
Equations 5 and 6 ensure the quantity of power sold and purchased are within the rated capacity of the
system while (7) gives the state of charge (SOC), that is, available energy in the system at any time t.
𝑢𝑡𝑃𝑚𝑖𝑛 ≤ 𝑃𝑐ℎ𝑡 ≤ 𝑢𝑡𝑃𝑚𝑎𝑥 (5)
𝑥𝑡𝑃𝑚𝑖𝑛 ≤ 𝑃𝑑𝑐ℎ𝑡 ≤ 𝑥𝑡𝑃𝑚𝑎𝑥 (6)
𝑆𝑡 = 𝛾𝑠𝑆𝑡−1 + 𝛾𝑐𝑃𝑐ℎ𝑡 − 1
𝛾𝑐⁄ 𝑃𝑑𝑐ℎ
𝑡 (7)
Equation (8) limits the SOC at any time between the depth of discharge and the storage capacity while
(9) makes the operation a continuous self-scheduling such that the SOC at the end of day 1 is the SOC
at the beginning of day 2.
(1 − 𝐷𝑜𝑑)𝑆𝑚 ≤ 𝑆𝑡 ≤ 𝑆𝑚 (8)
𝑆1 = 𝑆0 (9)
3.2 Formulation for the Price Maker
To formulate a price-maker arbitrage model, the impact of ESS operation on pool price must be
accounted for. This impact is accounted for by price sensitivity curves to additional net demand for
hourly interval across the five-year study period. The price sensitivity curve applied in the formulation
9
is a simulation of historical hourly supply curves. Real-market data capturing hourly price-quantity offers
for every hour of the five year period (January 2010 to December 2014) considered was downloaded,
stacked in increasing order of price and used to generate supply curve, also known as the merit order
curve. The historical generators’ offer data for Alberta electricity market is publicly accessible after two
months. In a similar way, demand curve for each hour can be generated from the price-quantity bids
submitted. However, while sizeable market participants are allowed to submit bids to buy energy, the
demand is largely inelastic. The demand curve for each hour is generated by determining equivalent
demand from the clearing price and the actual supply curve. This equivalent demand, with the knowledge
of clearing price, is then implored to estimate adjusted price for steps of increase in equivalent demand.
Price sensitivity curve is a stepwise monotonically decreasing or increasing curve that expresses the
impacted market price as a function of decreasing or increasing market equivalent net demand by small
steps, say 10 or 20 MW. To illustrate this, Figure 1 below shows that the actual market price was
$103/MWh for this particular hour. As the equivalent demand is reduced (through discharge operation
of ESS), the would-be market prices decrease.
Figure 1: Sample price sensitivity curves to additional supply
Another price sensitivity curve shown in Figure 2 illustrates the price for an hour when the net equivalent
market demand is increased (as a result of charging of the ESS) by 10 MW increments.
0
20
40
60
80
100
120
0 10 20 30
Pri
ce (
$/M
Wh
)
Additional Generation (MW)
10
Figure 2: Sample curve of price sensitivity to additional demand
Equations (10) - (20) describe the mixed integer linear programming (MILP) model for obtaining optimal
operating profit from arbitrage operation in energy market for a large-scale ESS. Similar to (1), the
objective is to maximize arbitrage operating profit from participation in energy market. Equation (10) is
the summation of the hourly revenue, which is the product of the clearing price 𝜆𝑡(𝑃𝑑𝑐ℎ𝑡 ) and power
discharge 𝑃𝑑𝑐ℎ𝑡 . The clearing price is now a function of power discharged by the facility 𝑃𝑑𝑐ℎ
𝑡 Total cost
of operation is expressed in (11) and accounts for the variable operation and maintenance cost, trading
charge, transmission tariff charges, and the cost of buying power 𝑃𝑐ℎ𝑡 at the price 𝜆𝑡( 𝑃𝑐ℎ
𝑡 ).
𝑅𝑒𝑣𝑒𝑛𝑢𝑒 = ∑ (𝜆𝑡(𝑃𝑑𝑐ℎ𝑡 ) 𝑃𝑑𝑐ℎ
𝑡 )𝑇𝑡=1 (10)
𝐶𝑜𝑠𝑡 = ∑ ( 𝜆𝑡(𝑃𝑐ℎ𝑡 ) 𝑃𝑐ℎ
𝑡 + (𝑉𝑂𝑀𝑐 + 𝑇𝑅𝐷𝑐 )(𝑃𝑐ℎ𝑡 + 𝑃𝑑𝑐ℎ
𝑡 ) + 𝐶𝐷𝑇𝑆 . 𝑃𝑝𝑐ℎ𝑡 + 𝜆𝑡(𝑃𝑝𝑐ℎ
𝑡 . 𝑂𝑅𝑐 +𝑇𝑡=1
𝐿𝑓 . 𝑃𝑑𝑐ℎ𝑡 )) (11)
Equations (12) and (13) give the hourly discharge power sold and charge power purchased respectively.
Figure 3 below shows how the model solves for discharge power; 𝑃𝑑𝑐ℎ𝑡 (a similar approach) is used to
solve for 𝑃𝑐ℎ𝑡 . 𝑂𝑓
𝑠 and 𝐵𝑑𝑘 represent the offer and bid blocks of 10MW each denoted by step size s and k
respectively. 𝑂𝑓𝑠 and 𝐵𝑑
𝑘 range from 0 to the rated power capacity. For example, when s= 1, 𝑂𝑓𝑠 = 0MW,
when s=2, 𝑂𝑓𝑠=10MW, when s=3, 𝑂𝑓
𝑠=20MW and vice versa for𝐵𝑑𝑘.
𝑃𝑑𝑐ℎ𝑡 = ∑ (𝑂𝑡,𝑠 + 𝑂𝑓
𝑠. 𝑋𝑡,𝑠)𝑁𝑠𝑠=1 (12)
𝑃𝑐ℎ𝑡 = ∑ (𝐵𝑡,𝑘 + 𝐵𝑑
𝑘 . 𝑈𝑡,𝑘)𝑁𝑘𝑘=1 (13)
43.544
44.545
45.546
46.547
47.548
48.549
0 10 20 30
Pri
ce (
$/M
Wh
)
Additional Demand (MW)
11
Figure 3: Generic price sensitivity quota curve showing stepwise MW blocks added to the grid
Equations (14) and (15) give the range of possible integers 𝑂𝑡,𝑠 or 𝐵𝑡,𝑘 (1 to 9) that can be added to the
optimal block size for a particular hour. The values for 𝑂𝑡,𝑠 and 𝐵𝑡,𝑘 are integers because the minimum
bid quantity in the energy market is 1MW. For example, if the optimal value for 𝑃𝑑𝑐ℎ𝑡 = 27MW, then
s=3, thus 𝑂𝑓𝑠 =20MW and 𝑂𝑡,𝑠 =7MW. At each hour, the data in the price sensitivity quota curve is
tabulated, giving price 𝜆𝑡,𝑠 as discrete functions of s, which is a value of 3 in this example. A similar
procedure is followed for 𝑃𝑐ℎ𝑡 but the corresponding price this time around will be 𝜆𝑡,𝑘.
0 ≤ 𝑂𝑡,𝑠 ≤ 9. 𝑋𝑡,𝑠 (14)
0 ≤ 𝐵𝑡,𝑘 ≤ 9. 𝑈𝑡,𝑘 (15)
𝑋𝑡,𝑠 and 𝑈𝑡,𝑘 are binary variables associated with on and off status of the facility at time t and also
determines the s or k value of the MW blocks to select to achieve optimal solution. Equations (16) and
(17) ensure that only one of the block sizes is selected every hour while equation (18) ensures that the
system can only be in any of the three possible states (offline, on and off).
∑ 𝑋𝑡,𝑠𝑁𝑠𝑠=1 ≤ 1 (16)
∑ 𝑈𝑡,𝑘𝑁𝑘𝑘=1 ≤ 1 (17)
12
∑ 𝑋𝑡,𝑠𝑁𝑠
𝑠=1 + ∑ 𝑈𝑡,𝑘𝑁𝑘𝑘=1 ≤ 1 (18)
Equations (19) and (20) ensure that the energy storage facility operates within its rated power capability,
(10) is the state of charge (SOC) at any time t considering the power conversion efficiency while (11)
ensures that the system operates within the maximum storage capacity.
0 ≤ 𝑃𝑑𝑐ℎ𝑡 ≤ ∑ 𝑋𝑡,𝑠𝑁𝑠
𝑠=1 . 𝑃𝑟𝑎𝑡𝑒𝑑 (19)
0 ≤ 𝑃𝑐ℎ𝑡 ≤ ∑ 𝑈𝑡,𝑘𝑁𝑘
𝑘=1 . 𝑃𝑟𝑎𝑡𝑒𝑑 (20)
Equations (8) and (9) are also applicable to price-maker formulation, (8) gives the energy level available
at any time t while (9) is to ensure that energy level at the end of day 1 is the energy level at the beginning
of day 2.
4.0 CASE STUDY
To have a typical representation of arbitrary energy storage operation, ESS small enough to have no
impact on pool price and one large enough to impact the pool price of electricity are considered. Based
on the hourly supply curve, it is noted that ESS with ratings less than or equal to 10MW have negligible
impact on price while the ones greater than 10MW have impact on price which is estimated as discussed
in section 3.2. For every hour of the five-year period considered, impact on price is estimated and these
prices are input to the optimization model. Parameters of the ESS are shown in Table 2 below. It is
expected that the result of this model is technology independent. This is because capital cost and life
cycles that could be significantly different for each technology is not required in the analysis to predict
operating profit.
Five-year (2010- 2014) historical Pool price data are input to the mixed integer linear programming
(MILP) model. To estimate the impact of tariff, the model is run with and without the transmission
tariff. After careful consideration of computational burden with respect to the merit, an optimization
window of 168 hours (one week) is considered. Based on another run, we also found that optimizing
operating profit over 24-hour window will always make the system fully discharge irrespective of the
pool price in hour 24; these results depend on the specific time of day that the window is initialized.
13
Table 2: Parameters of the ESS considered
Energy Storage Parameters (Price Taker)
Round trip efficiency 80%
Self-discharge loss 1% per month
Power rating 10MW
Storage capacity 50MWh
Variable O&M cost $7/MWh
Energy Storage Parameters (Price Maker)
Round trip efficiency 75%
Power rating 100MW
Storage capacity 1200MWh
Variable O&M cost $1/MWh
5.0 RESULTS AND ANALYSIS
To show a generic operating profile of the storage facility, the self-schedule operation output from the
arbitrage model is averaged over a 168-hour window (1 week) and plotted in Figure 4. As intuitively
expected, ESS charges in period of low demand and discharges in period of high demand. The figure
shows that the system withdraws electricity from the grid during overnight hours and supplies it back
during hours from mid-morning to late evenings. The ESS operation schedule for the first week of the
260-week period is plotted against the system demand and shown in Figure 5. While the system is idle
for several hours, the ESS generally charges at hours when the system demand is low which usually
coincides with hours with low pool price, and discharges when the system demand is high, which in
most cases is when the pool price is high. Note that energy supply to the grid is considered positive
while energy removal from the grid is considered negative in all illustrations.
14
Figure 4: Five-year 168-hour summary of operation schedule
Figure 5: Power schedule against system demand for week one-100MW price maker
There are some instances when the ESS charges (at fractions of its rated power) in periods of high
demand. To show these instances, a plot of frequency count for various ranges of operation within
fraction of rated capacity with respect to quintiles of system demand is presented in Figure 6. These
instances could be as a result of low price in period of high demand, which could be as a result of wind
facilities operating at their maximum capacity and bidding into the electricity market at $0 and thus
bringing down the pool price of electricity, despite high demand. The chart also shows that ESS
operating on arbitrage basis are idle a significant number of times (over 60% of the period considered).
-100
-50
0
50Po
wer
(M
W)
0
2000
4000
6000
8000
10000
12000
-100
-50
0
50
100
1 6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
10
1
10
6
11
1
11
6
12
1
12
6
13
1
13
6
14
1
14
6
15
1
15
6
16
1
16
6
Dem
and
(MW
)
ESS
Po
wer
(MW
)
Power Demand
15
These idle periods can be carefully explored for additional profit through participation in ancillary
service (spinning and non-spinning) market.
Figure 6: Charge and discharge frequency with respect to quintiles of system demand for a 100MW price
maker
Using results from the optimal operation schedule also, an evaluation of how often the ESS operate at
above 75% of its rated capacity (in charging or discharging mode), is examined, compared with charge
and discharge operating profile over the 260-week period considered. Shown in Figures 7 and 8, it is
noted that the 10MW price taker ESS most constantly operate close to its rated power while the 100MW
price-maker facility usually operate at a fraction of its rated power because it withholds a portion of its
power in order not to dilute the arbitrage opportunity by charging or discharging at rated power. The
chart shows impact of ESS size on operation and confirms that the model works as intended. Even
though the operation pattern looks similar, it can be seen that the 100MW ESS spends smaller time
operating above 75% of its rating as larger energy volume reduces the price, the model limits the energy
volume so as to not dilute arbitrage opportunity as a result of its impact on price.
0
2
4
6
8
10
12
14
16
< =20 20 to 40 40 to 60 60 to 80 > 80
% f
req
uen
cy
Charge: 75%<P<=100%
Charge: 50%<P<=75%
Charge: 25%<P<=50%
Charge: 0%<P<=25%
idle
Discharge: 0%<P<=25%
Discharge: 25%<P<=50%
Discharge: 50%<P<=75%
Discharge 75%<P<=100%
16
Figure 7: Operation frequency at a range of fraction of rated capacity-10MW price taker
Figure 8: Operation frequency at a range of fraction of rated capacity-100MW price maker
0
20
40
60
80
100
120
140
160
180
200
Nu
mb
er o
f W
eeks
Hours Charging Hrs Charge > 75%
Hours Dischrg Hrs Dischrg > 75%
0
20
40
60
80
100
120
140
160
180
200
Nu
mb
er o
f W
eeks
Hours Charging Hrs Charge > 75%Hours Dischrg Hrs Dischrg > 75%
17
The plots in Figures 7 and 8 for scenarios when DTS was considered, and when it was not, look similar.
This is because the plot is aggregated over five-year period. In the next subsections, the impact of
transmission tariffs on ESS operation is investigated in detail.
5.1 Impact on Operation
The following section assesses the impact of the transmission tariff on the operation schedule and
volume of energy traded (summation of power flow over a period). Using self-schedule operation output
from the arbitrage model over the period considered, Figures 9 and 10 below are presented to show the
impact of the variable components of DTS and STS in the operation pattern of the price-maker and the
price-taker ESSs respectively averaged over a five-year period.
Figure 9: Five-year summary of operation pattern for the price taker considering the transmission tariff
-10.0
-5.0
0.0
5.0
Pow
er )
MW
)
No DTSWith DTS
18
Figure 10: Five-year summary of operation pattern for a 100MW price maker considering the
transmission tariff
Figure 1: Five-year summary of operation pattern for a 100MW price taker considering transmission
tariff
The charts show that irrespective of tariff, the ESS generally charges at night but discharges
midafternoon towards the evening and performs arbitrage operation more during weekdays than
weekends. For both price-taker and price-maker scenarios, the power flow is impacted by the variable
component of the tariff. In the price-maker case, the ESS reduces its power flow while charging in order
-100
-50
0
50
Pow
er (
MW
)
No DTSWith DTS
-100
-50
0
50
Pow
er (
MW
)
No DTSWith DTS
19
to minimize all the variable components of the DTS. Also while discharging, it reduces its power flow
but only slightly as the variable component of rate STS is a function of the power flow and pool price.
The higher the flow, the lower the pool price. Rate STS has lower impact on discharge pattern compared
to rate DTS on charging pattern. In the price-taker scenario, the discharge power flow is impacted more
than the price-maker scenario because the pool price remains constant so the only way it has to minimize
rate STS is to reduce discharging power flow. To confirm this, it is important to consider an additional
scenario to isolate all other factors, most importantly, the price-maker assumption and ESS parameters.
To isolate the impact of price-maker assumption, a third scenario that considers the 100MW, 1200MWh
storage facility as a price taker with same parameters presented in Table 2 is included. As shown in
Figures 10 and 11, both the 100MW, 1200MWh price taker and price maker ESS reduce their power
flow while charging to minimize the impact of the variable component of DTS. The reduction in power
flow is more evident in the price taker scenario as with no DTS, it operates at higher power flow since
its operation is assumed and modeled to have no impact on pool price. Irrespective of the level of power
it draws from the system, the pool price remains the same. With DTS factored in, it responds to the
variable component by reducing its power draw from the system.
For a price maker, the ESS is strategically mindful of diluting arbitrage opportunity by reducing its
power draw from the system, as increase in power draw (charging) will lead to increase pool price. And
when DTS is considered, it further reduces power draw to minimize DTS penalty. This explains the
difference in charge level patterns between the two scenarios.
While the ESS supplies power to the system, with no STS, the price maker operates such that it does
not reduce arbitrage opportunity by discharging power at a level that would severely reduce pool price.
When STS is considered, instead of reducing the level further, it increases the power level slightly as
this reduces the pool price and thus STS penalty as it is a function of pool price. For the price taker
however, with no STS the system supplies power at a relatively higher level as it has no impact on pool
price. With rate STS is included, the system reduces its power flow to minimize STS penalty. Hence
the notable difference in discharge power level pattern between the two scenarios.
The total energy-traded volume with tariff compared to the case when tariff is not included is examined.
The percentage monthly reduction in energy-traded volume (input and output) is seen to vary across the
60 months considered; the percentage decrease in energy input and energy output was about equal in
all the 60 months for both price-taker and price-maker scenario, as shown in Figure 12 and 13 below.
Energy-traded volume is the summation of power flow over the period of consideration. The average
decline in energy traded for the price taker was 18% while it was 12% for the price maker. The tariff
has more impact on small-scale than large-scale ESSs.
20
Figure 2: Percentage decrease in energy input volume as a result of the transmission tariff
Figure 3: Percentage decrease in energy output volume as a result of the transmission tariff
5.2 Impact on Operating Cost
Irrespective of the operation pattern of the ESS, it always incurs the fixed component of the transmission
tariff. These costs include billing capacity (which is 1,243/MW every month), system support charge
and point-of-delivery charge if the ESS merchant does not own the substation. A very significant portion
0%
10%
20%
30%
40%
50%
60%
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59
% decrease in Energy Input-Price maker % decrease in Energy Input-Price taker
0%
10%
20%
30%
40%
50%
60%
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59
% decrease in Energy Output-Price maker % decrease in Energy Output-Price taker
21
of this charge is the coincident peak charge. Coincident peak charge is the product of coincident-
metered demand and $5,033 every month. The coincident-metered demand is estimated by analyzing
the result of the self-schedule optimization to check if the ESS is contributing to the load in the 15-
minute interval overall peak of the month. Historical data on coincident peak period is confidential to
the AESO; thus the exact period is not included in this paper. Other fixed components of the tariff are
the billing capacity, which depends on the power rating of the ESS and substation fraction but is
completely waived if the ESS has its own substation. It is assumed in this analysis that ESS merchant
owns the substation; thus substation fraction component is neglected. Throughout the five-year period
considered, the ESS in the two scenarios was seen to charge only once in the coincident peak period
(CPP). In a typical occurrence, even though the system demand is at its peak, the pool price is relatively
low. This usually occurs on a very windy day when production from wind facilities are at their highest.
Most of the wind farms are located in southern Alberta, so this peak production would be common to
majority of the wind farms. As wind generation has a negligible variable cost, they are offered to the
market at 0$/MWh and thus would always get dispatched. This in turn leads to a lower pool price for
that hour.
Overall, this implies that the portion of the rate DTS might not be much of a threat to profitability of an
ESS that avoids charging in that period but can have huge impact if the ESS charges during CPP. Just
like the coincident peak charge, all the other fixed component of the tariff is not directly included in the
optimization model as it is a post-operation charge. An estimate of the percentage increase in operating
cost as a result of the transmission tariff is presented in Figure 14. Operating cost can be seen to increase
up to fivefold in some months with minimal arbitrage operation. This is because fixed cost contributed
majorly to the operating costs in these months. This is common to the price-taker scenario too, but due
to its lower power rating, it incurs much lower increase in operating cost.
Figure 14: Percentage increase in operating cost as a result of the transmission tariff
0%
50%
100%
150%
200%
250%
300%
350%
400%
450%
500%
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59
Price maker Price taker
22
5.3 Impact on Price
With the assumption that other generators do not change their bidding strategy while the ESS MW bids
and offers move around the generated price sensitivity supply curve, an estimate of average pool price
for all the 60 months (five-year period) is estimated. The 100MW ESS brings down the average monthly
pool price by an average of 6% over the five-year period. This implies that when additional ESS is
added into the system, the average hourly price may drop further. Shown in Figure 15, comparing this
to the result when tariff is considered, there is negligible impact on the change in average pool price.
This shows that even though the variable component of the tariff impacts the energy-traded volume,
this impact is not strong enough to significantly change the operation pattern and strategy.
Figure 15: Monthly average pool price, impacted price based on ESS operation with and without tariff
for the 100MW price-maker case
To estimate the impact of ESS operation on energy cost to consumers, the hourly system demand is
multiplied by the hourly pool price (with no ESS, with tariff and with no tariff). Note that the energy
cost estimated here does not capture exact total cost paid by consumers as there are some other costs by
the distribution company not factored in. As shown in Table 3, the overall cost of energy to consumers
over the 5-year period will have reduced by $1.85 billion if a 100MW, 1200MWh storage facility was
participating in the market. This translates to a $308k per annum reduction in the cost of energy to
consumers per every MWh of ESS connected to the grid. Considering the impact of the transmission
tariff on the ESS, savings on energy cost is reduced to $1.79 billion. This 3.2 % decrease in cost is as a
result of the impact of both STS and DTS tariff.
0
20
40
60
80
100
120
140
160
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59
$/M
Wh
Months(Jan 2010- Dec 2014)
No ESS With ESS ESS with tarif
23
Table 3: Impact of the transmission tariff on the cost of energy to consumers over the 5-year period
considered
Scenario Energy Cost ($bn)
No ESS 24.89
With 100MW ESS 23.04
100MW ESS with tariff 23.10
Net Impact of ESS 1.85
Resulting Impact of tariff 1.79
Using volatility indices from the methodologies explored in (Zareipour et al., 2007) and (Alvarado and
Rajaraman, 2000), hourly price fluctuation i.e. changes in price from one hour to the other for each
month is estimated. The result of index of volatility for price prior to adding ESS to the system, if ESS
is added with no transmission tariff and when the transmission tariff is considered are compared and
shown in Figure 16 for monthly prices for the 60 months considered. It is noted that for all the months
considered except May 2011 and June 2012, addition of ESS reduces the price volatility and the
transmission tariff slightly inhibits ESS from bringing down the price volatility. In May 2011, prices
were relatively low and did not vary significantly hence low price volatility. MW bids and offer
movement across supply curve is seen to be significant in this month. This translates to low arbitrage
opportunity and this shows in the net operating profit, which happened to be the lowest in 2011.
Operational profitability is noted to be directly proportional to average pool price and price volatility.
The correlation between the monthly profits and average price and price volatility were 0.67 and 0.94.
respectively. The facility was idle for about 520 out of the 720 hours in the month, and when the
transmission tariff is considered, it was idle for about 540 hours. In June 2012, prices were generally
low, with a zero price for about 30 hours out of the 744 hours. This is why volatility index was highest
in this month. In estimating the logarithmic return in this period, prices of 0.1$/MWh is assumed for all
the hours with zero prices, so as to get a numerical value for the return. Operation of ESS (withdrawal
and injection of power) during the period only increases the variation and thus the volatility.
24
Figure 16: Impact of the 100MW price-maker operation and the transmission tariff on monthly price
volatility
5.4 Impact on Operating Profit
The operating profit is seen to decline significantly with the consideration of the transmission tariff.
This is expected as the operating cost is increased while the volume of energy traded is reduced as a
result of the transmission tariff. The percentage decrease in profit is seen to vary across the 60-month
period considered. Figure 17 below shows the % annual decrease in profit as a result of the transmission
tariff. The impact on annual operating profit is noted to be quite significant and could be as high as 40%
per annum, driven by the increase in operating cost and reduction in energy-traded volume. While this
reduction in profitability is seen as a loss by ESS merchant, a large percentage of this from a neutral
stand point, is simply a value transfer from one party to another; in this case to the AESO. Part of this
is what the AESO use to invest or recoup investment in transmission facilities to ensure the system runs
congestion free as legislated. The other component is a loss from any perspective as this is the reduction
in operating profit because of the decrease in energy-traded volume due to the variable component of
the tariff. For the five-year period considered, of the 21% reduction in total operating income because
of the transmission tariff, 4% reduction in operating profit is due to lost value as a result of reduction in
energy-traded volume.
The impact of the tariff is less significant when the ESS is more active and more significant when the
ESS is less active (2010 and 2014). This is evident in the quantity of energy injected and withdrawn
from the grid in those years. For instance, the 100MW ESS withdrew 72,498MWh and 80,118MWh in
Years 2010 and 2014 (with most significant impact) respectively compared to 104,511MWh and 123,
278MWh in Years 2011 and 2013(least significant impact) respectively.
0
0.2
0.4
0.6
0.8
1
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59
Mo
nth
ly P
rice
Vo
lati
lity
Ind
ex
Months(Jan2010- Dec 2014)
no ESS with ESS ESS with tariff
25
Figure 17: Annual percentage decline in operating profit as a result of the transmission tariff
To examine the profitability of small-scale and large-scale ESSs, IRR was estimated using the 2020
projected capital cost and life cycle by Viswanathan et al. (2013) and five-year average operating profit.
For the price maker, IRR stands at 8.47% with no tariff consideration, but with tariff considered, IRR
reduces to 6.56%. IRR estimates for the price taker show no economic sense at all. With no tariff
considered, IRR is -1.4% and -3.35% when tariff is factored in. As expected, the transmission tariff
significantly affects the rate of return for both price taker and price maker. The IRR estimate shows that
despite not factoring the impact of deep discharge on lifecycle of small-scale ESS (specifically
batteries), they may not be best suited for investment solely for arbitrage operating profit in Alberta
electricity market. This could change when market rules allow participation in the ancillary service
market, through which more value can be captured, especially converting the very high idle period into
market participation.
5.5 Sensitivity
To understand the dependence of the model on certain parameters, we carried out a sensitivity analysis.
The analysis is only carried out only on the 10MW case. Each sensitivity case is run as a new
optimization, to illustrate the impact of various input parameters. Sensitivity data is presented as
percentage change relative to the initial simulation with no rate DTS charges.
As shown in Table 4, the sensitivity analysis indicates that the conversion efficiency has a significant
impact on operating profit, with 10% increase in efficiency resulting in 6% increase in operating profit;
and 10% decrease in efficiency a 5% reduction in operating profit. Increasing either of power rating or
storage capacity also results in a profit increase by 5% variable operation and maintenance (O&M) costs
have little impact on profit, with a 10% change only impacting profit by 1%.
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
2010 2011 2012 2013 2014
Price maker Price taker
26
Application of rate DTS to the system has more significant impact, which in this case is a 20% reduction
in profit. If the rate DTS tariff were to be 10% higher, the operating profit is reduced by 22% relative
to the no rate DTS case. Comparing to the Base Case with rate DTS, a 10% increase in rate DTS
incrementally reduces operating profit by 3%.
Table 4: Summary of sensitivity analysis
6.0 CONCLUSION
The transmission tariff has a very significant impact on the operational profitability of ESS based on
arbitrage, irrespective of facility scale. This impact does not change overall operation pattern of ESS
but affects the energy-traded volume. Also affected is the operating cost, which directly brings down
the operating profit. The fixed component of the tariff charge has the most significant impact on the
economics of ESS. This cost is incurred monthly and does not depend on operation strategy or volume
of energy traded by the merchant. While this can be considered a loss by an ESS merchant, overall it is
Energy Input
(MWh)
Energy Output
(MWh)
Revenue Cost Profit
Base Case no Rate DTS 0 0 0 0 0
Efficiency Increased 10% 5% 16% 6% -8% 6%
Efficiency Decreased 10% -5% -15% -6% 7% -5%
Power Rating Increased 10% 5% 5% 5% -7% 5%
Capacity Increased 10% 5% 5% 5% -2% 5%
OM Cost Increased 10% -5% -5% -1% 2% -1%
Base Case with Rate DTS -15% -16% -3% -55% -20%
Rate DTS Increased by 10% -17% -17% -4% -58% -22%
Additional Impact of Rate DTS Increase
(Above Base Case with Rate DTS)
-2% -2% -1% -2% -3%
27
actually a value transfer; that is, money transferred to the system operator, the AESO in this case, to
maintain Alberta’s congestion free policy by investing in transmission facility. The variable component
of the tariff drives the actual loss, evident in the reduction of energy-traded volume as a result of the
tariff.
operational strategy or volume of energy traded by the merchant. Monthly average pool price and
volatility is seen to reduce as a result of price-maker ESS operation. The decline would become
increasingly relevant as multiple large-scale ESSs are added to the system. There comes a point when
arbitrage opportunity would be highly diluted, leading to minimal difference in hourly pool price and
thus operational profitability.
This analysis quantifies the impact of the transmission tariff on operational profitability based on
arbitrage in Alberta's energy-only market. It does not take into account the ancillary service market as
it remains unclear at the moment whether ESS will be allowed to participate in the ancillary service
market and what sort of policy would be introduced to guide its operation. In future works, there is a
need to compare how policies in various electricity markets in North America and elsewhere impact the
operation of ESS both in energy and ancillary service markets. Our findings emphasize the relevance
of transmission tariff policy in making a business case for ESS in Alberta. ESS merchant was assumed,
in this work, to own the substation. If otherwise, point-of-delivery tariff component of rate DTS would
be applied and this is expected to further increase the operating cost, depending on the rated power of
the ESS. The load factor value used in this work is the average load factor in 2014 published by AESO,
actual load factor value is location dependent. The lower the load factor, the lower the STS rate incurred.
7.0 ACKNOWLEDGEMENT
We extend our sincere gratitude to the management of NRGSTREAM for granting us access to their
software, which provided us the refined price data and hourly supply curve for our models. This work
was supported by Alberta’s Department of Energy.
28
8.0 REFERENCES
Adebayo, A.I., Zareipour, H., Knight, A.M., 2016. Economic Viability of Price Arbitrage Operation
of Vanadium Redox Battey in Alberta ’ S Energy Market. IET Conf. Publ.
AESO, 2015a. Energy Storage Integration-RECOMMENDATION PAPER [WWW Document]. URL
http://www.aeso.ca/downloads/Energy_Storage_Integration_Recommendation_Paper.pdf
(accessed 4.29.16).
AESO, 2015b. ISO Tariff [WWW Document]. URL
http://www.aeso.ca/downloads/AESO_2015_ISO_Tariff_(2016-01-01).pdf (accessed 2.19.16).
AlbertaEnergy, 2012. Alberta’s Electricity Industry [WWW Document]. URL
http://www.energy.alberta.ca/Electricity/pdfs/RMRC_Appendix3_Industry.pdf (accessed
4.30.16).
Alvarado, F.L., Rajaraman, R., 2000. Understanding price volatility in electricity markets. Proc. 33rd
Annu. Hawaii Int. Conf. Syst. Sci. 00, 1–5.
Bradbury, K., Pratson, L., Patino-Echeverri, D., 2014. Economic viability of energy storage systems
based on price arbitrage potential in real-time U.S. electricity markets. Appl. Energy 114, 512–
519.
Bubik, P., 2014. Stakeholder Comment and AESO Replies Matrix Discussion Paper – Energy Storage
Integration [WWW Document].
Byrne, R.H., Silva-Monroy, C.A., 2015. Potential revenue from electrical energy storage in ERCOT:
The impact of location and recent trends. IEEE Power Energy Soc. Gen. Meet. 2015-Septe.
Chen, J., 2013. Energy Storage Initiative Issue Identification [WWW Document]. URL
http://www.aeso.ca/downloads/Formatted_ES_IS_Paper_Final_20130613.pdf (accessed
10.5.16).
Cheng, J., 2014. Stakeholder Comment and AESO Replies Matrix Discussion Paper – Energy Storage
Integration [WWW Document]. URL http://www.aeso.ca/downloads/Discussion_Paper_-
_Energy_Storage_Integration_-_Reply_Matrix_-_IPCAA_comments.pdf (accessed 4.29.16).
Fertig, E., Apt, J., 2011. Economics of compressed air energy storage to integrate wind power: A case
study in ERCOT. Energy Policy 39, 2330–2342.
He, G., Chen, Q., Kang, C., Pinson, P., Xia, Q., 2015. Optimal Bidding Strategy of Battery Storage in
Power Markets Considering Performance-Based Regulation and Battery Cycle Life. IEEE Trans.
Smart Grid 1–9.
Hu, W., Chen, Z., Bak-Jensen, B., 2010. Optimal operation strategy of battery energy storage system
to real-time electricity price in Denmark. IEEE PES Gen. Meet. PES 2010 1–7.
Ippolito, M.G., Favuzza, S., Sanseverino, E.R., Telaretti, E., Zizzo, G., Palermo, U., 2015. Economic
Feasibility of a Customer-side Energy Storage in the Italian Electricity Market 1–6.
29
Kazempour, S.J., Member, S., Moghaddam, M.P., 2009. Economic Viability of NaS Battery Plant in a
Competitive Electricity Market 453–459.
Khani, H., Dadash Zadeh, M.R., 2015. Real-time optimal dispatch and economic viability of
cryogenic energy storage exploiting arbitrage opportunities in an electricity market. IEEE Trans.
Smart Grid 6, 391–401.
Kintner-Meyer, M., 2014. Regulatory policy and markets for energy storage in North America. Proc.
IEEE 102, 1065–1072.
Klinkenborg, H., 2014. Stakeholder Comment and AESO Replies Matrix Discussion Paper – Energy
Storage Integration [WWW Document]. URL
http://www.aeso.ca/downloads/ATCO_Discussion_Paper_-_Energy_Storage_Integration_-
_Reply_Matrix.pdf (accessed 4.29.16).
Masiello, R.D., Roberts, B., Sloan, T., 2014. Business models for deploying and operating energy
storage and risk mitigation aspects. Proc. IEEE 102, 1052–1064.
Moghaddam, I.G., Saeidian, A., 2010. Self Scheduling Program for a VRB Energy Storage in a
Competitive Electricity Market.
Steffen, B., 2012. Prospects for pumped-hydro storage in Germany. Energy Policy 45, 420–429.
Viswanathan, V., Balducci, P., Jin, C., 2013. National Assessment of Energy Storage for Grid
Balancing and Arbitrage Phase II Volume 2: Cost and Performance Characterization. Pnnl 2.
Walawalkar, R., Apt, J., Mancini, R., 2007. Economics of electric energy storage for energy arbitrage
and regulation in New York. Energy Policy 35, 2558–2568.
Yu, H., John, K., Wang Peng, Ritter Fred, 2013. 2014 Loss factor [WWW Document]. URL
http://www.aeso.ca/downloads/2014_Loss_Factor_Posting_Letter.pdf (accessed 1.1.16).
Yucekaya, A., 2013. The operational economics of compressed air energy storage systems under
uncertainty. Renew. Sustain. Energy Rev. 22, 298–305.
Zakeri, B., Syri, S., 2014. Economy of electricity storage in the Nordic electricity market: The case
for Finland. Int. Conf. Eur. Energy Mark. EEM.
Zareipour, H., Bhattacharya, K., Canizares, C.A., 2007. Electricity market price volatility: The case of
Ontario. Energy Policy 35, 4739–4748.