Implications of the New NESHAP/NSPS (MACT) for the
Oil & Gas Sector
Presented by
Cindy Bishop(B.S.Ch.E.)
1
American Institute of Chemical EngineersDallas ChapterMarch 27, 2012
2
Implications of the New NESHAP/NSPS (MACT) for
the Oil & Gas Sector
I. What Has Changed?
II. Who Is Affected?
III.What Needs to Be Done?
IV.When Does it Happen?
V. What If You Don’t Do it?
3
Clean Air Act Section 111
EPA Must List Categories of Stationary Sources That Cause or Contribute Significantly to Air Pollution
EPA Must Issue Performance Standards for Each Category “Best System of Emission
Reduction” Cost Non-air Impacts Energy Requirements
ORIGIN
4
NSPS (40 CFR Part 60) – New Source Performance Standards• New and Modified Sources• Industry Specific
• Focus on Criteria Pollutants (VOCs, SO2)
• EPA Review Required Every 8 Years
ORIGIN
5
ORIGINNSPS (continued)
1979 – Oil & Gas Production Placed on EPA’s Priority ListJune 24, 1985 - NSPS for leaking components at gas processing plants (KKK)October 1, 1985 – SO2 regulations from natural gas processing (LLL)
6
Clean Air Act Section 112
NESHAP (40 CFR Part 63) – National Emission Standards for Hazardous Air Pollutants• New and Existing Sources• Industry Specific• Major Sources
MACT – Maximum Achievable Control Technology Top 12% No Cost Consideration
EPA Review Required Every 8 Years
ORIGIN
7
ORIGIN
NESHAP (continued)
July 16, 1992 – EPA Published List of Major and Area Source Categories, including Oil & Gas ProductionFebruary 12, 1998 – Natural Gas Transmission and Storage Added to ListJune 17, 1999 – MACT Issued (HH & HHH)January 3, 2007 – Area Sources
8
WHY NOW?
January 14, 2009 suit filed February 4, 2010 – Settlement:• Proposed Standards by July 28, 2011• Final Action by February 28, 2012
9
10
Who Is Affected?
Operations from Well to Refinery or to Customer
•Onshore & Offshore
•Production (well completion and workover)
•Portable Equipment
•Storage
•Transmission
11
• Aug. 23, 2011 Rule Proposed Published
• Oct. 24, 2011 Comment Deadline
• April 3, 2012 Final Rule
• ???
When Does it Happen?
12
What Has Changed?NSPS Revised:• Equipment Leaks (KKK)• SO2 (LLL)
New (OOOO):• Hydraulic Fracturing• Gas-driven Pneumatic Devices, Centrifugal and
Reciprocating Compressors• Storage Vessels
Applies to new facilities that were constructed or modified after August 23, 2011
13
What Has Changed?NESHAP Revised• Oil & Gas Production Facilities (HH)• Gas Transmission and Storage (HHH)
New• Small Glycol Dehydrators• Storage Vessels at Major Sources
Must Notify EPA within 1 year after rule becomes final
14
Oil & Gas Production, Transmission, and Distribution (OOOO)
Applies to all construction, modification or reconstruction after August 23, 2011
Includes fracking or refracking existing wellhead
Compliance date: date of final rule publication.
NSPS
15
Oil & Gas Production, Transmission, and Distribution (OOOO)
Reduced Emission Completion (“REC”)• Route gas during flowback into collection system• Use sandtraps, surge vessels, separators, and
tanks during flowback and cleanout operations• Capture and direct flowback emissions that cannot
be routed to a gathering line to a combustion device (flare)
NSPS
16
Oil & Gas Production, Transmission, and Distribution (OOOO)
Compressor standards• Rotating compressor: dry seal system• Reciprocating compressor: replace rod packing
before 26,000 operating hours
Pneumatic controller: zero emissions of natural gas if at gas processing plant, otherwise no more than 6 scfh (switch to compressed air driven from gas controller)
NSPS
17
Oil & Gas Production, Transmission, and Distribution (OOOO)
Condensate and Crude Oil Storage Tanks
If :• At least one barrel per day condensate
or• At least 20 barrels per day crude oil;
Then, 95% VOC emission reduction
NSPS
18
Sulfur Recovery Units at Onshore Gas Processing Plants
SO2 standards:
• Feed rates of 5 tons per day or greater or • With an acid gas stream H2S concentration of 50% or greater
•SO2 emission reduction of 99.9% (was 99.8%)
NSPS
19
LDAR (Subpart VVa instead of VV)
Applies to onshore gas processing plants
•Lower “leak” threshold•Monitoring connectors
NSPS
20
Startup, Shutdown, Malfunction
•No “Free Pass” During Startup and Shutdown
•Affirmative Defense for Malfunctions
• Sudden• Infrequent• Not reasonably preventable• Not caused by poor maintenance or careless
operation
NSPS
21
Registration/recordkeeping
•Construction, startup, and modification notifications
•Well registration and 30-day notification prior to each well completion
•Annual Compliance Certification
•Third Party verification
•Electronic reporting
•Over 20,000 completions and recompletions annually
NSPS
22
NESHAP
23
24
25
NESHAP Subparts HH & HHH
Addition of Small Glycol Dehydrators•Oil & Gas Production: gas flowrate < 85,000 scmd or
0.90 Mg/yr benzene emissions
• Existing sources: 1.10 x 10-4 g BTEX/scm• New sources: 4.66 x 10-6 g BTEX/scm
•Gas Transmission & Storage: gas flowrate < 283,000 scmd or 0.90 Mg/yr benzene emissions
• Existing sources: 6.42 x 10-5 g BTEX/scm• New sources: 1.10x 10-5 g BTEX/scm
•Types of control: process vent » control device or closed-vent system
26
NESHAP Subparts HH & HHH
Storage Vessels95% reduction of HAPs for all storage vessels
•Process modifications•Flare•Incinerator•Carbon Filter•Condenser
Performance Testing of Control Device
Elimination of Startup, Shutdown & Malfunction Exemption (See NSPS)
27
NESHAP Subparts HH & HHH
Compliance dates:
Existing sources: 3 years after the date of final rule publication
New sources (commenced construction on or after August 23, 2011): immediately upon startup or the date of final rule publication, whichever is later
28
What has industry said?
Rules will slow drilling, cut natural gas production and reduce royalties (API)
Equipment for capturing emissions during completions is unlikely to be as readily available as EPA assumed, and equipment would have to spend more time at each site than estimated.
29
What If You Don’t Do it?
• EPA can make you do it
• Civil Penalties up to $25,000/day/violation
• Criminal Penalties $250,000 per day per violation and up to five years in jail. Corporations are subject to up to $500,000 per day per violation.
• $10,000 bounty
30
EPA Region 6 2011—2013 National Enforcement Initiatives
1. Keeping raw sewage and contaminated stormwater out of our nation’s waters
2. Preventing animal waste from contaminating surface and ground waters
3. Cutting Toxic Air Pollution that Affects Communities’ Health
4. Reducing Widespread Air Pollution from the Largest Sources, especially the Coal-Fired Utility, Cement, Glass, and Acid Sectors
5. Reducing pollution from mineral processing operations
6. ASSURING ENERGY EXTRACTION SECTOR COMPLIANCE WITH ENVIRONMENTAL LAWS
“To address these emerging problems, EPA will develop an initiative to assure that energy extraction activities are complying with federal requirements”
What If You Don’t Do it?
31
Stay on top of the rules –be organized! Look for exemptions Start reviewing operations now – do not wait until
the rules are final. Look for innovative/emerging technology EPA favors those who voluntarily disclose
problems.
Conclusions