  • 7/27/2019 IMCA RiskGuideline

    1/23

    ABThe International Marine

    Contractors Association

    Identifying and Assessing Risk

    in Construction Contracts

    An IMCA Discussion Document

    www.imca-int.com July 2006

  • 7/27/2019 IMCA RiskGuideline

    2/23

    ABThe International Marine Contractors Association

    (IMCA) is the international trade associationrepresenting offshore, marine and underwater

    engineering companies.

    IMCA promotes improvements in quality, health, safety,environmental and technical standards through the publicationof information notes, codes of practice and by otherappropriate means.

    There are two core activities that relate to all members: Safety, Environment & Legislation Training, Certification & Personnel Competence

    The Association is organised through four distinct divisions,each covering a specific area of members interests: Diving,Marine, Offshore Survey, Remote Systems & ROV.

    There are also four regional sections which facilitate work onissues affecting members in their local geographic area Americas Deepwater, Asia-Pacific, Europe & Africa and MiddleEast & India.

    IMCA Risk Discussion Document

    This document was prepared for IMCA by its ContractsWorkgroup, under the direction of the Overall ManagementCommittee and IMCA Council.

    www.imca-int.com/contracts

    The information contained herein is given for guidance only and endeavours to

    reflect best industry practice. For the avoidance of doubt no legal liability shall

    attach to any guidance and/or recommendation and/or statement herein contained.

  • 7/27/2019 IMCA RiskGuideline

    3/23

    Identifying and Assessing Risk in Construction ContractsAn IMCA Discussion Document

    July 2006

    1 Introduction ........................................................................................................... 12 This Document ...................................................................................................... 3

    2.1 Risk .......................................................................................................................................................................32.2 Contracting ......................................................................................................................................................... 32.3 Profitability .......................................................................................................................................................... 42.4 Risk Management............................................................................................................................................... 42.5 Where Does Control of Risk Lie? ................................................................................................................. 42.6 Risk Identification...............................................................................................................................................52.7 Target Audience for this Document.............................................................................................................. 62.8 Main Risk Areas.................................................................................................................................................. 6

    3 Contractual Risks................................................................................................... 8

    Appendices

    1 Risk Areas ............................................................................................................. 11

    Performance Risks........................................................................................................................................................12Financial Risks................................................................................................................................................................14Political Risks.................................................................................................................................................................15Technical Risks..............................................................................................................................................................16Geographical Risks .......................................................................................................................................................17Operator Risks..............................................................................................................................................................18

    2 IMCA Competition Law Guidelines .................................................................. 19

  • 7/27/2019 IMCA RiskGuideline

    4/23

  • 7/27/2019 IMCA RiskGuideline

    5/23

    1 IntroductionThe handling of risk in construction contracts varies considerably. This depends on the nature and location of

    the work, the operator and contractor involved and the prevailing contracting climate. Each of these variesover time and there are also outside influences such as banks, governments and the insurance market.

    In recent years, operators and contractors have remarked that the balance and handling of risks in some

    contracts was not ideal and this document aims to promote dialogue between all parties to try to improve thissituation.

    IMCA is an international trade association representing offshore, marine and underwater engineering

    companies. IMCA members are upstream contractors in general, but several of them are integratedcontractors completing downstream projects as well, so the intent of this document is to cover oil and gas

    contracting in general.

    IMCA is widely recognised for collecting good practice from several parties and publishing generic guidelines ofrelevance throughout the industry and around the world on many issues relating to performance in theindustry on, for example, safety, the environment and other aspects.

    Amongst IMCAs objectives are to:

    strive for the highest possible standards with a balance of risk and cost; achieve equitable contracting regimes; and promote co-operation across the industry.In publishing this document, IMCA believes it will serve the long-term interests of all participants in the oil andgas industry and promote dialogue between the parties about risk in pursuit of the above objectives. This, inturn, will improve relations, increase efficiency and reduce overall costs.

    The document is not intended to represent an exhaustive analysis of all risks which are covered by contracts in

    the oil and gas industry. It is a short discussion document intended to highlight issues. The subject is huge andthere exists already a vast knowledge base about risk and risk management in the public arena, published byacademics and the industry with input from operators and contractors. In addition, each operator andcontractor probably has its own department responsible for this subject and its own strategy, perhaps in aformalised document and approach. This document is not intended to replace this regime; rather, it isintended to supplement it.

    Each contract, project and client/contractor relationship is unique. This document does not present apreconceived single solution or recommendation for or against contract styles such as EPIC (engineering,

    procurement, installation and construction) or lump sum. It aims at commenting on some of the issues thatmay need to be addressed in various contracting situations.

    This document is about:

    identifying risk; identifying the financial consequences of the risk becoming a reality; helping the contracting parties to achieve their appropriate risk balance; trying to avoid parties accepting risks they dont understand; and dealing with unknown risks.The document can be used by operators and contractors to identify areas where risk may threaten the

    integrity of a contract. Parties to a contract often do not realize that the person who manages the risk under acontract may not necessarily be the person who carries the financial consequences of the risk becoming areality. The risks should be allocated to the party best to assume the risk.

    This document does not contain contractual clauses and does not form a standard contract. It is published asan aide for operators and contractors alongside their in-house risk approaches. A trade association cannot

    make compliance with its publications mandatory and remain within the bounds of competition law. IMCA

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    IMCA Risk Discussion Document 1

  • 7/27/2019 IMCA RiskGuideline

    6/23

    recognises the requirements of competition law and these are reflected in the IMCA Competition Law Policywhich is reproduced in Appendix 2.

    The document has been developed by the IMCA Contracts Workgroup in conjunction with other IMCAmembers who also contributed to the development of the related document IMCA Contracting Principles.IMCA documents often evolve and any reader is welcome to provide suggestions for additions. This documentshould generally be considered to be work in progress. It is intended as a document to help dialogue betweenthe parties to understand, mitigate and manage risk appropriately to the benefit of all the parties. Its aims areto:

    improve dialogue; improve risk apportionment and understanding in contracts and projects; improve efficiency and project delivery; improve operator/contractor relations; save money; avoid litigation; increase opportunities;

    facilitate the development of alternative solutions; and sustain the industry.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    2 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    7/23

    2 This Document2.1 Risk

    Risk is sometimes poorly understood by the main contracting parties and also those outside.

    The effect of this is a danger:

    to operators, in that they embark upon or frame a development uninformed of some of the risksinvolved;

    to contractors, that they adopt risk that they do not understand and lose money, perhapsbecoming bankrupt, thus reducing the global pool of contractors capable of doing work;

    to both parties, that if the risk is poorly understood and allocated, it is likely to be incorrectlyassessed, mitigated, insured and managed, resulting in poor project delivery;

    to those further down the supply chain, that if the two main players cannot deal with risks wellthemselves, sub-contractors are likely to manage this poorly too;

    to those outside (such as banks, national oil companies, etc.), that they will take poorly informeddecisions that make the risk environment worse;

    to all parties, in that a lack of understanding of risk leads to inefficiency where each pays more andmakes less out of the venture.

    2.2 ContractingDuring the contracting process:

    1 an operator wants to achieve a goal;2 the operator does not want to take the risk of doing the work itself. This could be for a variety

    of reasons: it does not have the skill, personnel, equipment, time, desire, etc.;

    3 contractors offer to do the work on the operators behalf. Why? The contractors areestablished to have the skill, personnel, equipment, time, desire etc.;

    4 however, the capability of the bidding contractors varies. They may all be able to complete thework, but some can accept more of the risks than others. This depends on their skill, personnel,equipment, time, desire etc., as well as their risk acceptance profile. These behaviours may beamongst the distinguishing factors between bidders to help decide who is awarded the work, butall parties need to understand the risks which they are accepting and know how the contract isdealing with them. An operators best interests are not necessarily served by contractorscompeting on criteria such as acceptance of excessive risk.

    A large number of contracts are completed under the lump sum/turnkey regime. The reason for thisis that the operator wants to know at the outset what the budget and schedule is and then should berequired to have no management or other role during the project. It relies on a well-defined scope ofwork and a competent contractor. The intent is that the operators define what they want, the

    contractor builds it and hands it over in working condition to the operator who inserts the key, turnsit on and then owns and operates a successful facility. This idyllic model is easily spoiled by variousfrequently seen events:

    1 the scope is not well-defined at the outset;2 the contractor under-performs;3 during the project, the operator interferes with:

    the scope, or the management, etc.;

    4 unforeseen events.It is not possible to have a lump sum without the turnkey element the two are inseparable.

    The contractor cannot estimate the costs and run his own project whilst maintaining budget andschedule control if the operator interferes. The upstream and downstream construction industry has

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    IMCA Risk Discussion Document 3

  • 7/27/2019 IMCA RiskGuideline

    8/23

    not always been as successful at leaving the contractor to deliver lump sum turnkey facilities as, forexample, the ship building industry.

    Contractors are not bankers or underwriters. The risks of funding projects, changes in foreignexchange rates and insuring projects should be understood and taken by the most appropriate party.The operator may be better placed.

    One of the aims of this document is to avoid erosion of the profit margin through incorrect

    understanding and apportionment of risk.

    2.3 ProfitabilityContractors generally aim to make a certain percentage profit margin. The industry has reported thatprofit margins have been low or negative for several contractors on several projects in recent years.Some contractors have accumulated several loss making projects such that their whole annual resulthas been negative and this viability-threatening situation for several contractors has been one of thedrivers for this document. A number of operators have commented on this unsatisfactory state ofaffairs as well.

    Clearly, features in the commercial process such as competitive bidding impact on profit margins, but

    this model has served the industry well. During difficult commercial times, contractors are presentedwith the difficulty of bidding too high and missing the award. If this occurs, their expensive facilities(offices, workforce, fabrication yards and vessels) will be idle. If there is a large incentive to keepthese facilities active (at almost any cost) then bids can be submitted too low with no (or negative)profit margin in desperation to win work. The work is later completed at a loss and the situation canonly get worse for all parties. This situation is unsustainable.

    Nearly all of the risks discussed in this document have the capacity of eroding profit margin andmoving the project from a profit making into a loss-making venture.

    In the hypothetical case of a contractor with a project target profit margin of 5%, it should be notedthat it takes only a small swing in the contract price of 5% to erode 100% of its margin. Further,it should be noted that the contractor only has recourse to the project duration (a few years at most)

    to achieve its return. The producing life of the facility that the contract was put in place to deliverclearly has a longer time for the operator to break even plus the opportunity to charge more highly ifnecessary/appropriate/possible for its products later in the facilitys life. Of course, a 5% swing in thecontract price for the operator is simply 5%, not 100% of his profit.

    2.4 Risk ManagementRisk management is the process by which the likelihood of risk occurring or its impact on a project isreduced. It has five steps:

    1 Identify the potential sources of risk on the project.2 Determine their individual impact and select those with a significant impact for full analysis.3 Assess the overall impact of significant risk.4 Determine how the likelihood or impact of risk can be reduced.5 Develop and implement a plan for controlling the risks and achieving the reductions.

    2.5 Where Does Control of Risk Lie?One way of classifying the risk is by identifying where control of the risk lies. This may change duringthe life of the project.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    4 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    9/23

    There are five classifications of risk according to where control lies:

    1 External: UnpredictableThese are risks beyond the control of the individual or operator and are totallyunpredictable. They arise from external influences such as third parties, acts of god, etc.

    2 External: Predictable but UncertainThese risks are also beyond the control of individuals or companies. They are expected, butto what extent? There is usually data to determine a norm or average, but the actual impactcan be above or below this norm. Bad weather is an example.

    3 Internal: TechnicalThese are risks arising directly from the technology of the project work, of the design,

    construction or operation of the facility.

    4 Internal: Non-TechnicalThese are within the control of individuals or the operator and usually arise from a failure ofa project team to achieve its expected performance. They may result in schedule delays, costover-runs or an interruption to cash flow.

    5 Legal: Civil and CriminalRisks under civil law can arise from contractual arrangements, patent rights etc. Risks undercriminal law can arise under statute, e.g. the UK Health & Safety at Work Act.

    2.6 Risk Identification2.6.1 Timing of Risk Identification

    Risks need to be identified early enough to do something about them. Project risks should be

    considered from the earliest conceptual stage. For example, risks from environmentalloading are key drivers in choice of conceptual design and so are considered on day one.

    This document indicates that risks should be considered throughout the process fromconceptual screening through more detailed front end engineering and design (FEED), the bidprocess, award and project execution. A risk inventory can run through from phase tophase, so nothing is lost between phases when the contracting parties may change. It cancontinue right through into the production phase where it may have an influence onmaintenance, for example.

    The key message is that the earlier the risk is identified the better.

    2.6.2 Who Retains the Risk?After the risks are identified, it is critical to see which parties retain this risk in practice and

    through the contract clauses. Limiting values and circumstances may need to be defined.

    2.6.3 Risk ImportanceA conventional risk analysis can be used to rank the importance of the risks in descending

    order from: High risk + high value, through high risk + low value or low risk + high value, tolow risk + low value.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    IMCA Risk Discussion Document 5

  • 7/27/2019 IMCA RiskGuideline

    10/23

    2.7 Target Audience for this DocumentThe target audience for this document is:

    Operators: Operator during conceptual development, bidding, construction Operator during production Partners

    Contractors: Prime contractors Sub-contractors Vendors

    Others: Finance community Host governments/national oil companies Insurance market/brokers.

    The key targets are the operators and prime contractors during conceptual development, bidding andconstruction. The other stakeholders in the list can influence the risks and their allocation and needto be aware of the issues.

    2.8 Main Risk AreasThe main areas of risk in these contracts are:

    Contractual Performance Financial Political Technical Geographical Operator

    Contractual risks may include:

    Operator group and contractor group property and personnel Project works (including both operator and contractor supplied items) Pollution Third parties Consequential losses Warranty obligations Unlimited liability/damages at large Insurance cover Force majeure and suspension Delay Variation orders Free access to worksite Intellectual property rights Termination by operator for convenience Operators obligation to pay contractor.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    6 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    11/23

    Performance risks may include:

    Scope, nature and duration of work Schedule interactions Size Safety and environmental performance

    Weather Soil and foundations External influences Operator and influences at time of bid.

    Financial risks may include:

    Profitability Value of contract (size) Balance sheet debt Off-balance sheet debt Level of exposure Foreign currency exposure Terms of payment Operator creditworthiness Insurance.

    Political risks may include:

    Interference Disturbance Confidentiality Permits and licences.

    Technical risks may include:

    FEED quality New technology Weather Soil and foundations.

    Geographical risks may include:

    Location of the work

    Operator risks may include:

    Operator areas of influence Insurance Problems which impact the operator and can impact the contractor.

    There will always be overlaps between these areas. The contractual risks are a function of thewording of the contract whereas the other risks evolve from elsewhere but the contract will be usedwhere necessary to deal with them. For this reason the contractual risks are explored in slightly

    greater detail in section 3 below, whereas the other topics are explored in Appendix 1.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    IMCA Risk Discussion Document 7

  • 7/27/2019 IMCA RiskGuideline

    12/23

    3 Contractual RisksC.1 Operator group and contractor group property and personnel

    The contract should define the costs of loss of or damage to the parties respective groups property

    and personnel of whatsoever nature, irrespective of cause (including negligence).

    C.2 Project works (including both operator- and contractor-supplied items)The contract should define the responsibility for loss of or damage to the project works if such loss ordamage is caused by an act or omission on the part of the contractor group whilst the project worksare in the care, custody and control of the contractor group.

    C.3 Pollution

    The contract should define the responsibility for the effects of pollution and contamination ofwhatever kind emanating from the contractor groups spread and onshore facilities, operatorsfacilities, the work and the facilities of others (third parties).

    C.4 Third parties

    The contract should define the legal liability for third parties losses caused by each, including in

    circumstances where a contractor is required to perform work in an area of close proximity to anyexisting facilities.

    C.5 Consequential losses

    The contract should define the indemnities for each partys groups respective indirect orconsequential losses howsoever caused or arising (including negligence) whether or not foreseeableat the date of the contract.

    C.6 Warranty obligations

    Warranty obligations and defective performance liabilities (including post termination for default) andall other implied liabilities should be expressed in the contract in terms of magnitude, time andremedy.

    C.7 Unlimited liability/damages at large

    The contract should define or limit the contractor groups total cumulative liability under the contractand at law, in order to enable him to assess his overall exposure resulting from, for example, liabilityfor delay, damage, rework, re-performance and/or replacement and default (whether or not suchactions are carried out by a third party).

    C.8 Insurance cover

    The full details of the insurance policy terms, conditions, limits and exclusions (and any alterations)should be available to all parties and define the cover available or not for the project.

    C.9 Force majeure and suspension

    In the event that the contractor is prevented from performing the work due to force majeure orsuspension by the operator, the contract should define whether the contractor has the right toremove any vessel from site once a maximum period agreed in the contract has been exceeded.

    C.10 Delay

    The contractors liability for delay and liquidated damages should be defined and should be the

    operators sole financial remedy under both the contract and at law.

    C.11 Variation orders

    The contract should define the contractors obligations to perform the operator instructed variationorders taking account of contractors other existing commitments, any change to the risk profile ofthe workplace and a mutually agreed adjustment to price and schedule where appropriate.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    8 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    13/23

  • 7/27/2019 IMCA RiskGuideline

    14/23

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    10 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    15/23

    Appendix 1

    Risk Areas

    The main areas of risk in these contracts are:

    Contractual (C) (this is discussed in section 3 above)The following areas of risk are discussed in this appendix below:

    Performance (PE) Financial (F) Political (PO) Technical (T) Geographical (G) Operator (O)

    The risks are grouped, numbered and annotated as shown in the brackets above for ease of cross reference.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    IMCA Risk Discussion Document 11

  • 7/27/2019 IMCA RiskGuideline

    16/23

    Performance Risks

    PE.1 Scope, nature and duration of the work

    The scope and nature of work should be defined in the contract. The contractor should havesufficient time and information to assimilate the detail in the bid phase. Particular difficulty occurs with

    contracts where: there is insufficient time or information available to understand the detail; the information is insufficiently developed at bid stage (poor FEED see T.1); the project depends on the contractor developing a new solution during the project for which he

    cannot quantify the resources (groundbreaking projects see T.2);

    the information available is wrong; the bid scope is outside the knowledge of the operator and/or bidder (eg very large turnkey

    projects).

    The operator also has to perform in order for the contractor to perform. This issue is discussedfurther under O.3.

    If there is a danger of any of these risks occurring, the contract should define how the parties will deal

    with the situation.

    PE.2 Schedule interactions

    The parties should understand the schedule and what happens if the schedule changes. The effect ofschedule changes which are operator initiated (change of scope, delivery of information/materials/components/approvals/permits etc, variation orders) and contractor initiated (delay) should be definedin the contract. This includes interaction with long lead time items.

    PE.3 Size

    The probability of a problem described in items PE.1 and 2 in this performance risk register occurringis increased on large projects.

    PE.4 Safety and environmental performance

    The contractor is expected to complete the work with certain operator/own/industry safetyperformance targets. If these targets are not achieved there will probably be other knock-on effectson the project performance. Any targets, other than the contractors own ones, should be defined inthe contract such that there are no surprises.

    PE.5 Weather

    Weather risk needs to be assessed on a case-by-case basis. For example, some vessels are able toaccept a different level of weather risk than others. This may be a competitive edge issue ifcontractors have, for example, larger equipment which can operate in worse weather conditions. Butfor each contractor there will be a limit, beyond which the responsibility for weather risk should beidentified.

    PE.6 Soil and foundations

    The soil and foundations (site conditions) risk is generally borne by the operator. This follows theprinciple that the risk cannot be fully measured by the contractor prior to the commencement ofwork and so unknown costs could be out of proportion to the contractors reward.

    PE.7 External influences

    Many of the risks discussed in this document may be outside the control of the contractor. Such risksmay prevent the contractor performing and include:

    Access (see C.12); Interfaces with operator and interfaces with other contractors;

    Political risks (see PO.1-4); Risks of interference and disturbance (see PO.1 and PO.2).

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    12 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    17/23

    PE.8 Operator and influences at time of bid

    If there is incomplete information at the time of bid, it will impact negatively on the performance ofthe contractor. If the contract is re-bid or negotiated over an extended period before award, boththe operator and contractor may have a lack of continuity in the bid process and amongst personnel.Both can impact negatively on contractor performance.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    IMCA Risk Discussion Document 13

  • 7/27/2019 IMCA RiskGuideline

    18/23

    Financial Risks

    F.1 Profitability

    Contractors generally aim to make a certain percentage profit margin. This is the most criticaloutcome of the contracting process for the contractor. At the end of the contract the contractor

    only has the financial result. By comparison, the operator acquires an asset with a lifetime expectationof positive returns and with some element of control over these returns.

    F.2 Value of contract (size)

    See PE.3.

    F.3 Balance sheet debt

    The terms of payment and any deposits, performance bonds, bank guarantees, and parent co

    guarantees etc should be understood.

    F.4 Off-balance sheet debt

    The terms of payment and any deposits, performance bonds, bank guarantees, and parent co

    guarantees etc should be understood.

    F.5 Level of exposure

    See F.2. This is related to size but also to payment method, cash flow, etc

    F.6 Foreign currency exposure

    Many contracts are in countries which are not the home country of the contractor. In addition,components, supplies and sub-contractors can also come from further countries. These facts cancombine to mean that the contractor could have a currency exchange risk for the project.The operator is often better placed to cope with this risk. This is because:

    the materials etc which are paid for with foreign currencies may have been designated by theoperator;

    the operator is probably operating in the local country of the work (which the contractor maynot be) and so will be set up to deal with its currency;

    the operator (generally being a larger capitalised company) can get better currency terms andperhaps has access to the host government to negotiate terms.

    Swings of a few percent are regular and should be considered in the light of F.1 above.

    F.7 Terms of payment

    The payment terms should reflect the progress of the work and be cash neutral. It is noted that hostgovernments in some overseas projects are obstacles in this area and it is clearly an operator matterto address this with the relevant government. See F.3 and F.4 above.

    F.8 Operator creditworthiness

    Some operators are now smaller companies than the main contractors. Understanding whether theoperator has the financial backing to continue to pay the contractor is important. For some overseasprojects the parent operator may have sufficient creditworthiness but the project may be operated viaa separate subsidiary with smaller credit.

    F.9 Insurance

    See C.8. The financial integrity/security of the underwriters is critical.

    F.10 Materials

    The implications of material cost fluctuation, e.g. fuel or steel prices, should be understood by bothparties.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    14 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    19/23

    Political Risks

    PO.1 Interference

    PO.1.1 Before award Some host governments interfere with the normal business process(operator/contractor relationship) by insisting on certain contract styles. These include EPIC

    contracts, lump sum bids, specific contract and payment terms, local content and locallegislation/standards. This can add considerable uncertainty and risk to bids. Host governments canfrustrate the award process as well, making the cost of bidding higher (due to protractednegotiations), the risk of interference with other projects for the contractor higher, the prospect offrustrated bidding (a bid submitted which costs money to prepare and where eventually no award ismade), and stimulating general negative effects on contractor cash flow. The contractor has littleopportunity to influence these aspects which should be clarified in the bid stage and the operator isgenerally better placed to influence these aspects positively.

    PO.1.2 During contract The same broad points as in PO.1.1 apply. In addition, the host governmentmay delay payment, change laws and taxes, change local standards, and interfere with local content or,be a cause of delay where local content is late or of unacceptable quality. The contractor has littleopportunity to influence these aspects which should be clarified in the bid and the operator is

    generally better placed to influence this positively.

    PO.2 Disturbance

    The contractor needs a secure environment to complete his work on site. Local disturbance cannegatively influence schedule. The operator has the best opportunity to influence local stability andprovide security to the contractors workforce and spread. Similarly, the operator has the bestopportunity to influence the completion of local work and ensure no interruption to the supply ofmaterials, personnel and third party provided items to the contractor. The parties should worktogether with other operators in the region, host governments and security personnel to aim atsecure working. Again, the contractor has little opportunity to influence these aspects which shouldbe clarified in the bid and the operator is generally better placed to influence this positively.

    PO.3 Confidentiality

    There is a risk that confidentiality may be breached which is a political risk. The contractor has littleopportunity to influence this so it should be clarified in the bid and the operator is generally betterplaced to influence this positively.

    PO.4 Permits and licences

    Permits and licences may not be issued in time by the authorities, or may be required by theauthorities at a time when they cannot be procured by the contractor. The operator is usually closerto the authorities and may be better placed to influence the issue of permits and licences.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    IMCA Risk Discussion Document 15

  • 7/27/2019 IMCA RiskGuideline

    20/23

    Technical Risks

    T.1 FEED quality

    The contractor may be asked to bid on the basis that he has studied the FEED (front end engineeringdesign) and accepted it. There may be insufficient time to complete this study in full depth in the bid

    period. FEED may have errors and in a complex bid these may be impossible to find. It is alsoinequitable to ask the bidders (effectively) to be the auditors of the FEED which is, in part, whatoccurs in a bid where the contractor is asked to accept the FEED. The risk of FEED being inaccurateneeds to be understood and the possible effects of this clarified. This process often needs only to bedone once with the successful bidder, not with all bidders.

    T.2 New technology

    In ground-breaking projects the bidder may be asked to carry out designs and activities during theproject that have not been completed before. The bidder may be unable to envisage that a piece oftechnology will be unsuccessful. Both parties should understand this situation and work towardsunderstanding the risks, their implications and the costs of solutions. Then the risks should beapportioned.

    T.3 Weather

    See PE.5.

    T.4 Soil and foundations

    See PE.6.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    16 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    21/23

    Geographical Risks

    G.1 Location of the work

    The geographical location will determine the magnitude of weather, political and operator risks. Mostof these issues are discussed under Political Risks above and include:

    politics; stability and changes to law/tax; local legislation/standards; governing law; security of vessels and personnel; material supply interruption; hindrance to mobilisation of spread; interruption to supplies for spread; hindrance to movement of personnel (crew change); late delivery of the work from or by third parties;

    project logistics; quality of operator supplied materials; permits and licences.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    IMCA Risk Discussion Document 17

  • 7/27/2019 IMCA RiskGuideline

    22/23

    Operator Risks

    O.1 Operator areas of influence

    The paragraphs above discuss operator risks and the operators influence on:

    the bid; award schedule; intellectual property; credit worthiness; interference; supervision; approval regime and timing; timely provision of information; local content; logistics; contracting regime; FEED quality; scope of work clarity; cash flow for project work and variation orders; permits and licences.

    O.2 Insurance

    If the operator decides to self insure all or part of the project there is sometimes no policy wording.Without it, there is a risk that a claim will lead to dispute rather than payment. In the case of a claim,the contractor has recourse only to the operator (who may be claim averse) rather than to aninsurer, who recognises that paying claims is an integral part of his business. This can lead to souringof the contract relationship. If recourse is to the project manager, whose job is to keep the projectwithin budget (and whose bonus may depend on it) the claim handling may be particularly complicated

    and the project manager may not be well versed in claims handling which is a discipline that insurersparticularly retain. An insurance wording should exist and be available for all parties. See also C.8.

    O.3 Problems which impact the operator and can impact the contractor

    Some project problems impact the operator. If these occur, an operator problem should not bepassed on to the contractor. However, such problems often impact the contractors performance,despite being outside his control. Examples are late delivery of third party materials or information,poor quality third party materials, poor quality information, late approval, late delivery or deficienciesin permits and licences, late payment and poor interfaces. Each of these eventualities should beunderstood by the parties.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.

    18 IMCA Risk Discussion Document

  • 7/27/2019 IMCA RiskGuideline

    23/23

    Appendix 2

    IMCA Competition Law Guidelines

    Introduction

    These guidelines are compiled for members in accordance with the Associations constitution. They will becirculated to all members.

    Policy

    The Association, its regional sections and all committees will comply with all applicablecompetition law (competition, antitrust and similar laws) including those of the United States of

    America, the European Union, the United Kingdom and other countries in which the Association

    is active.

    All meetings will start with this as agenda item 1.

    General

    1. The Constitution and section objectives are written to comply with competition law.2. Membership is open to all companies active in the offshore, marine or underwater engineering industries.

    Any action in rejecting a membership application or current member is reviewed for compliance withcompetition law.

    3. The Association has a formal document retention and disposal policy.4. The Association has a formal complaints procedureRules for Meetings

    Members should comply with the following guidelines when meeting:

    1. Agendas of all meetings should be reviewed for compliance with competition law.2. Items not on the agenda will not be allowed if they raise issues which violate competition law.3. All participants have the right to question any topic or discussion that might violate competition law. Any

    participant has the right to state their objection and leave a meeting if they feel that any topic or discussionviolates competition law.

    4. Minutes of all meetings should be accurate and should not be doctored or incomplete.5. Minutes of all meetings should be reviewed for compliance with competition law. Minutes should also

    include statements to show compliance with competition law.6. All meetings should be scheduled and no unscheduled, informal, ad-hoc or side sessions should be held.The following guidelines should be adhered to by all members during any meetings:

    1. Do not discuss current or future prices.2. Do not discuss what is a fair profit level.3. Do not discuss an increase or decrease in price.4. Do not discuss standardising or stabilising prices.5. Do not discuss pricing procedures.6. Do not discuss cash discounts.7. Do not discuss credit terms.8. Do not discuss controlling sales.9. Do not discuss allocating markets.10. Do not complain to a competitor that its prices constitute unfair trade practices.11. Do not discuss refusing to deal with a company because of its pricing or distribution policies.12. Do not attend unscheduled, informal, ad-hoc or side sessions.Conclusion

    Trade associations can be targets for government agencies patrolling and enforcing compliance withcompetition law. By conducting its business openly and avoiding even the appearance that it is engaging inactivity that might seem to have an effect on prices or competition, the Association and members can protectthemselves from charges of violations of competition law.

    The publication of this document by IMCA is intended to assist and promote industry dialogue and efficiency and its adoption is not mandatory.