ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

24
ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team

description

TILC09, Tsukuba April 16-21, Split Quadrupole Concept Design Team Miao Yu- Cooling down analysis Mauricio Lopes- Magnetic center shift Yuri Orlov- 3D design and integration Vladimir Kashikhin- Magnet concept The Quadrupole concept was designed in short period of time by:

Transcript of ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

Page 1: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

ILC Main Linac Superconducting Quadrupole

V. Kashikhin for Superconducting Magnet Team

Page 2: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 2

Outline

• Split quadrupole issues • Quadrupole concept• Conductive cooling• Magnetic design• Installation and disassembly• Summary

Page 3: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 3

Split Quadrupole Concept Design Team

• Miao Yu- Cooling down analysis• Mauricio Lopes- Magnetic center shift• Yuri Orlov- 3D design and integration• Vladimir Kashikhin- Magnet concept

The Quadrupole concept was designed in short period of time by:

Page 4: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 4

Splittable Quadrupole Issues

Task from ILC Project Management: Look at the Split Quadrupole conceptual design to provide the quadrupole package installation and replacement outside of a very clean room. Main issues:

• Stable magnetic and mechanical design;• Effective conductive cooling;• Easy installation and disassembly;• Quadrupole+BPM rigid connection;• Magnetic axis stability;• Quench protection.

Page 5: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 5

ILC Quadrupole Specification

Page 6: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 6

Quadrupole Mechanical Concept

It was chosen the quadrupole design with racetrack coils which easy to split in vertical or horizontal direction.

 

Page 7: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 7

Quadrupole Fabrication• Qudrupole laminated yoke consists of two halfes;• Laminations stamped with accuracy 20 microns;•  Long calibrated rods connect two thick side plates and laminations in the solid unit;• Two coils mounted in each half core.•There is an easy assess to provide accurate coil mounting relatively pole and provide the coil frame prestress;• The half units identical and exchangable;• All current leads should be heavily stabilized with extra copper material.

Split plane

Built and Tested Quadrupole Model 1

Page 8: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 8

Quadrupole Wiring SchemeQuadrupole consists of 4 coils.Each coil has 3 sections of NbTi superconductor: one is for quadrupole and two for vertical and horizontal dipoles.There is also heaters in each coil wound from a stainless steel wire.Quadrupole and dipole sections connected in quadrupole and dipole configuration as shown in figure.The connections easy to rearrange for split configuration

Split line

Page 9: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 9

Quadrupole Cooling-Down • The quadrupole will be cooled using conductive

cooling;• Five heat transfer leads will thermally connect quadrupole core and LHe supply line;• The cross-section of leads 50 mm x 10 mm;• Cooling down time for the cryomodule is 30 hours;• During cooling initially the cold He gas goes through supply line and temperature changes from 300 K to 2 K. In such regime the enthalpy of the cold gas between 4.2 K and 300 K is utilized as well;• To cool down 1 kg steel from 300 K to 2 K is needed to evaporate 0.8 liters of LHe;• The quadrupole mass is ~ 280 kg.

Page 10: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 10

Conductive Cooling Animation 

Quadrupole cooled down from 300K to 3.5K in 38 hours.

Page 11: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 11

Magnet Assembly TolerancesCase # Description

0 Standard ML quadrupole. Gradient 54 T/m. No correction coils.

1 Right half of the magnet displaced 40 microns up.

2 1st Quadrant displaced 40 microns up.

3 1st Quadrant displaced 40 microns right and 40 microns up.

4 Coil displaced 100 microns up.

5 Coil displaced 100 microns up and 100 microns right.

N1 40um up

N2 40um up

N3 57um up

N4 100um upN5 140um

1 unit = 1 Gauss= 1um

Magnetic center shift in microns

Page 12: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 12

Quadrupole Blocks  

Half Quadrupole

Quadrupole Assembly

Quadrupole with Cooling Leads

Page 13: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 13

Half Quadrupole with Beam Pipe View

 

Half Quadrupole Yoke

Beam Pipe

Quadrupole-BPM Connection Flange

Quadrupole Supports

Page 14: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 14

Quadrupole with Beam Pipe View 

Page 15: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 15

Quadrupole with BPM 

Page 16: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 16

Cryomodule Cross-Section 

Quadrupole Package

2 Phase He Supply Pipe

Page 17: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 17

Quadrupole with BPM Cross-Section

 

Quadrupole

BPM

Page 18: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 18

Cryomodule Cross-Section 

Page 19: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 19

Quadrupole Side View 

Page 20: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 20

Cryomodule Cross-Section 

Page 21: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 21

Cryomodule Cross-Section 3D View (1)

 

Page 22: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 22

 

Cryomodule Cross-Section 3D View(2)

Page 23: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 23

Quadrupole Final Assembly View 

Quadrupole

Cooling Leads BPMCurrent Leads

Page 24: ILC Main Linac Superconducting Quadrupole V. Kashikhin for Superconducting Magnet Team.

TILC09, Tsukuba April 16-21, 2009 24

Summary • The first look at the splittable quadrupole showed this

approach visibility;• Proposed the quadrupole concept with vertical split;• Quadrupole has a conduction cooling from LHe supply pipe;• Quadrupole mounted around beam pipe outside of the clean room;• BPM has tight connection with quadrupole;• Quadrupole bolted to the strong 300 mm diameter He gas return pipe;• Special attention paid on the magnet assembly and mounting tolerances;• Current leads also conductively cooled;• Magnet cooling down time ~ 38 Hours;• The Quadrupole model with split should be built and tested to verify the design.