IEER Vitali

download IEER Vitali

of 19

Transcript of IEER Vitali

  • 7/31/2019 IEER Vitali

    1/19

    Page 1 of19

    Executive Summary

    1. Brief Project Description

    This Proposed Vitali Spring Source Development Project is an alternative solution to the local water

    supply problem of Barangay Vitali, Zamboanga City. The previous project which involved the construction

    of the Tamion Production Well has not been commissioned up to the present due mainly to the water

    quality yielded from the said production well. Thus, the same cannot be supplied to the constituents of

    this barangay as this has not complied with the standards for drinking water.

    The Planning & Design Division, Engineering Department of the Zamboanga City Water District

    considered utilizing surface water to address this problem in water supply in the barangay. Thus, the

    conceptualization of utilizing the Kamalik Spring at Sitio Kamalik some 5 kilometers from the Tamion

    Production Well.

    This project is composed of the construction of a 90 m 3 capacity ground tank, pipelaying of 3,194

    linear meters of 110 mm (O.D.) x 6 meters Polyvinyl Chloride (PVC) Pipeline, Class 150 and 1,630

    linear meters 100 mm (I.D.) Galvanized Iron (G.I.) Pipeline (Schedule 40) and the construction of one

    (1) unit 9m2

    (4.8 m3

    capacity) concrete collector chamber at the source.

    This proposed water system has a total budget cost of ten million five hundred fifty-six thousand two

    hundred ninety-five pesos and 10/100 (Php 10,556,295.10).

    It is expected that during the construction phase of this project there will be an increase in the

    generation of suspended particles, particularly dust, as excavation works will be performed for the

    pipelaying activities. The construction phase would create short-term visual impacts from the appearance

    of the construction operations and their impact on the surrounding landscape which are temporary in

    nature. The same effect would be seen on the construction phase of the source collector chamber and

    the ground tank. But the magnitude of this effect varies in magnitude such that there will be moderate

    significance in the construction of the source collector chamber while the pipelaying activities and the

    construction of the ground tank has negligible significance accounting to its strategic location and the

    ambient environment. At most, the impacts that will be caused to the natural environment of the spring

    source will be the displacement of the natural rocks on the stream accountable to the construction of

    source collector chamber. The flow will be redirected such that the maximum flow will be gathered

    towards the collector chamber. No logging activities will be made and the most minimal disturbance to the

    natural flora and fauna in the spring environment will be caused due to the construction works. In fact,

    reforestation activities will be conducted to improve the yield and quality of the water as soon as the

    project has been completed and the water system commissioned and has commenced operation.

    2. Brief Summary of Projects IEE Process

    The possible environmental impacts that may be caused by this project has been identified by

    comparison with related projects that have been previously done and observing the environmental

    impacts that it has caused. At the same time, relevant literature has been consulted particularly on similar

    undertakings which have been assessed by experts. Series of site inspections have also been conducted

    in the project site to include the identification of land ownership over the proposed site for the construction

  • 7/31/2019 IEER Vitali

    2/19

    Page 2 of19

    of the concrete ground tank and the identification of title of the claimants of the land in the vicinity of the

    spring source that will be utilized for this project.

    In the process, the stakeholders in the community were consistently consulted regarding this project.

    The major concern of the current users of the water body is whether they would still be able to utilize the

    same after it has been developed. The logging issues in the community was also raised particularly to the

    barangay chairman, Jose Alavar, which he accepted graciously and committed to put an end to this inview this development.

    3. Summary of Baseline Characterization

    The project site, considering the land formation at Barangay Vitali, is located at higher elevations

    with the general terrain to be slightly mountainous. Soil classification is generally clayish. For most parts

    of the study area, there are vast open spaces which have evidently been reduced as such due to past

    logging activities in the area.

    There are water bodies, particularly springs,in isolated areas of the barangay which have not

    been explored. Yet according to locales, there are quite a number which are presently used for daily

    activities and which have not been explored by this office.

    The air quality in the area is still at its purest state. No point sources were found in the area such

    as smoke stacks from industrial establishments. At most only smoke from backyard burning, use of

    firewood for cooking and from the few motorcycles that transport goods and persons to the area, are the

    sources of air pollutants in the area.

    The locales within the project site and study area are mostly engaged in agricultural activities

    usually merely for consumption. Logging activities were also evident in the area. Others are engaged in

    latex harvesting in a rubber plantation located adjacent to the study area and approximately 700 meters

    from the project site for the source collector chamber.

    4) Summary of Impact Assessment and Environmental Management Plan

    The hauling activities and earthworks during site preparation, particularly during the excavation

    works for the pipelaying activities, will temporarily decrease the air quality in the area due to dust and

    vehicle emissions. It will increase the pollutant concentrations in the ambient air quality during this time. It

    will also cause minor and temporary changes in the landform and will cause temporary disturbances in

    the community which will continue until the completion of the pipelaying activities.

    The construction of the 90 square meter collector chamber will also cause temporary

    disturbances in the aquatic biota that may thrive in the water body. Water quality may also decrease

    during construction phase due to the introduction of debris in the water as a result of the construction of

    the collection chamber. Run-off from disturbed areas and road surface during earth preparations may

    contaminated catch basins and affect the water quality.

    There are no significant settlements in the project study area. However, relocation of inhabitants

    in the upstream of the source had been requested from the barangay officials in order to ensure the water

    quality of the source which will be a source for drinking water for the barangay. Job opportunities will

    increase as 50% of the manpower requirements for this project will be taken from barangay Vitali. During

    the operation and maintenance phase of the project, locales will be preferred to operate and secure the

    facilities. Forest guards will be employed to secure the area from illegal loggers since forest management

    will be turned-over or co-managed by the Watershed Section of the proponent.

  • 7/31/2019 IEER Vitali

    3/19

    Page 3 of19

    5. Summary of Environmental Monitoring Plan

    The Environmental Monitoring Plan for this project included monitoring activities commencing

    from the planning stage of this project and shall continue during operation and maintenance thereof.

    First hand data were gathered during the initial inspection determining the terrain of the project

    site, soil characteristics, conducting interview with settlers and local officials, taking water sample forlaboratory analysis, conducted volumetric measurements of the water source, took pictures of the project

    sites and taking other relevant data that would be necessary for project preparation and designing

    environmental management plan.

    Data gathered were assessed for project feasibility and assessment of possible environmental

    impacts should implementation ensue. These were compared against literature on similar projects

    implemented to further assess and identify expected environmental impacts and to develop measures to

    mitigate the same.

    Baseline data gathered during project preparation stage will compared if there has been

    significant changes that occurred in the different phases of project implementation. Mitigation measures

    will be applied in the different phases of the project implementation where there are expected adverseenvironmental impacts particularly in the increase of dust and other air pollutants dispersed into the

    ambient atmosphere as a result of the earth works in preparation for pipelaying. Mitigation measures will

    be applied in order that pollution of the water bodies may be avoided.

  • 7/31/2019 IEER Vitali

    4/19

    Page 4 of19

    DRAFT MAIN IEER

    1. BASIC PROJECT INFORMATION

    1.1 Project Name : Proposed Vitali Spring Source Development Project1.2 Location/Address : Sitio Kamalik, Barangay Vitali, Zamboanga City, Region IX

    1.3 Nature of Project : Water System (Construction of Collection Chamber, Pipelaying

    and Construction of Concrete Ground Tank)

    1.4 Threshold Limits

    Applied for : Water Pipelines

  • 7/31/2019 IEER Vitali

    5/19

    Page 5 of19

    Figure 1. Organizational Structure of the Zamboanga City Water District

    The Zamboanga City Water Districts mission is to provide adequate and sustainable supply of potable

    water, sewerage and related services in accordance with International Standards to all customers within

    its service area with the end in view of improving their quality of life anchored on our firm adherence to

    the belief that Agua es Vida(Water is Life). With this end in view, it will continuously strive to make these

    services available to the general majority, if not the whole, of the population of Zamboanga City.

  • 7/31/2019 IEER Vitali

    6/19

    Page 6 of19

    The Zamboanga City Water District also believes in the need commits to actively collaborate with

    all its stakeholders in the protection and preservation of the Pasonanca Watershed and other watersheds .

    1.8 IEE Report Preparer : Anne Aubrey R. De Guzman-Bugtong

    1.9 Address : Planning & Design Division, Engineering Department

    ZCWD Field Office, Old ReservoirScout Limbaga St., Pasonanca

    Zamboanga City,Tel. No. 955-4235

  • 7/31/2019 IEER Vitali

    7/19

    Page 7 of19

    2.0 DESCRIPTION OF THE PROJECTS IEE PROCESS

    2.1. IEE Team

    For this project, the IEE Team was composed of the preparer, personnel from the Planning &

    Design Division, Construction Division and the Environment and Watershed Protection Division.

    Personnel from the Planning and Design Division were principally involved in the Project

    Conceptualization, preparation of the pre-feasibility and feasibility studies and the preparation of the

    detailed engineering plans and design. At these preparatory stages, initial environmental screening and

    assessments have been made before the preparation of the detailed engineering plans and design for the

    project wherein the same was considered and the results incorporated. Site selection, environmental

    screening and the initial assessment and scoping were performed by the preparer together with the

    Planning and Design Division and the Environmental and Watershed Protection Division.

    Detailed assessment, identification of mitigation needs and the preparation of the detailed design

    of the mitigation measures were prepared by the Environmental Engineer/preparer with aid from the

    Planning & Design Division as to the expected activities during the implementation and construction

    phase of the project.

    The Construction Division shall be responsible in the implementation of the mitigation measures

    that have been designed by the Environmental Engineer/preparer. Monitoring, validation and

    Evaluation/Audit of Environmental Compliance and Over-all Performance shall be made by the

    Environmental Engineer/preparer.

    2.2 IEE Study Schedule

    Generally the conduct of the Initial Environmental Examination was made during the

    conceptualization stage and the preparation of the detailed engineering and design of the project. On July

    6, 2011, source verification was conducted by the Planning & Design Division with representation from

    the Watershed Protection Section. This first site inspection was conducted on a rainy season but this

    particular day was sunny to cloudy. This was conducted after information from the Barangay Chairperson

    of Vitali that there are several spring sources that may be developed into a water system that could

    supply water to the barangay. At this time, prospective site was identified, data were gathered and initial

    environmental screening, assessment and scoping was done.

    During the conduct of the topographic survey, which was done two (2) weeks following the initial

    inspection, the different elevations have been identified, and the location for the concrete ground tank

    was chosen. Additional data have been gathered, such as land use of the chosen site, its ownership and

    land classification. These were later on verified with the DENR-CENRO East.

    A second inspection was conducted particularly to identify the site for the construction of the ground

    tank and to verify the discharge flow of the source. Photographs were taken of the different areas that will

    be affected and utilized by this project. This was conducted on September 29, 2011.

    On October 13, 2011 barangay referral was conducted together with the affected settlers in the area

    particularly those having claims over the surface water and using the same for domestic use. It was

    agreed during the said meeting that they are amenable to this introduction of improvement provided that

    they would still be able to use this source for their domestic needs. They were assured by ZCWD that

    they would still be able to utilize the downstream or the overflow of this source.

  • 7/31/2019 IEER Vitali

    8/19

    Page 8 of19

    Figure 2. Road Network Map of the Proposed Source Development at Kamalik, Vitali, Zamboanga City

    Study area for the

    surface watersource

    Study area for

    the ground tank

  • 7/31/2019 IEER Vitali

    9/19

    Page 9 of19

    2.3. IEE Study Area

    The study area for this proposed project includes the 100 meter radius from the surface water

    source. It also includes the unexplored upstream of the source which shall be included in the protection

    and forest management during the operation and maintenance phase of the project. This also includes

    the ambient environment of the surface water that will be the source for this water system. It is particularly

    located at N 7 24' 24.6" E 122 15' 34.7" at an elevation of 160.51 meters above sea level (MASL).

    The whole expanse of the 4.824 kilometres where pipelines will be laid was also part of the study

    area. Especially so that it will be along these areas where decrease in the air quality will be anticipated

    owing to the earth preparation activities that will be conducted which will generate dusts.

    The project site for the concrete ground tank has also been part of the study area and is located

    607.5 meters from the source collection chamber at an elevation of 108.82 MASL.

    Referring to figure 2 which shows the road network map of the proposed project, the study areas

    for the surface water source and the concrete ground tank were highlighted by the green circles. The

    whole expanse of the pipelines where pipelaying works will be done is also part of the study area of this

    project.

    2.1 IEE Methodology

    The initial environmental examination for this project was conducted by determining the different

    pollution generating activities in the project and comparing it against previous projects undertaken and the

    environmental impacts it posed, owing to time constraints and the lack of information, and the nature of

    the project to be undertaken.

    Generally, data gathered were first hand taking the same from the site. Water sample was taken

    and subjected to laboratory analysis to determine water quality. Second hand data were taken from

    appropriate offices having possession of them particularly as to the land use and classification of the

    proposed project area.

    After baseline data from the project site/study area have been gathered, the same was util ized to

    predict the possible impact of the project to the ambient environment. Assessment of the possible

    environmental impacts in the project site was based on previous projects undertaken by ZCWD with

    similar component activities. Possible environmental impacts were determined in relation to the pre-

    construction, construction/development, operation and maintenance stages of the project. As determined

    therein, these components were compared to the proposed project, its location, the baseline

    characteristics of the project site and the degree of the environmental impact that these activities may

    produce.

    Review of related literature was also used to aid in the assessment of the possible impacts that

    the works involved in this proposed project may cause to the ambient environment of the project

    site/study area.

  • 7/31/2019 IEER Vitali

    10/19

    Page 10 of19

    3. PROJECT DESCRIPTION

    3.1. Project Location, Area, ECA category

    Barangay Vitali is situated some 73 kilometers east of the City Hall of Zamboanga. It has an

    approximate land area of 5,409 hectares and a total population of 10,500. It is bounded by barangays

    Mangusu and Tictapul. Sitio Kamalik is situated at approximately 4 kilometers from the TamionProduction Well.

    It is considered, for the purpose of environmental impact assessment, as an environmentally

    critical area as it belongs under Category No. 10 (water bodies categorized by one or any combination of

    the following conditions: tapped for domestic purposes; within the controlled and/or protected areas

    declared by appropriate authorities; which supports wildlife and fishery activities). In this case, the surface

    water utilized is being tapped for domestic purposes by settlers within the vicinity of the area. This source

    is located at geographical coordinates N 7 24' 24.6" E 122 15' 34.7".

    3.2. Project Rationale

    Water is a basic human need that must be addressed with urgency. The people from this

    barangay have been clamouring for a sustainable potable water supply for several years now. Before, a

    barangay water works system has been operating in the barangay to supply water. But this has been

    unsustainable and the local folks could not manage and maintain the same. When this issue was raised

    to the local government for rehabilitation and improvement, the mayor required that the same be turned

    over to the Zamboanga City Water District to ensure its management and maintenance. As an answer to

    this clamour, ZCWD, together with the City Government and

    This project, the Proposed Source Development at Kamalik, Vitali, was conceptualized as an

    alternative to the previous Vitali Water System which included pipelaying works along the main road of

    barangay Vitali and the construction of the Tamion Production Well. This project was constructed as a

    thrust of the City Mayor, Celso L. Lobregat, to provide water supply systems to waterless barangays in

    the city. Thus, the realization of this project in 2008. However, it has never been operational because ofthe change in the water quality discharged by the Tamion Production Well. For this reason, ZCWD is

    studying the possibility of applying treatment procedures that would address the water quality problem of

    this production well.

    In the meantime, the water supply requirements of this barangay must be addressed with urgency

    as water is a basic requirement for life sustenance. Thus, surface water sources have been explored in

    the area as there are existing surface water bodies in the area which are presently being tapped by

    nearby settlers for domestic use. The question only remained is whether the same is capable of supplying

    the needs of majority, if not all, of the barangays constituents. Hydraulic analysis was conducted and it

    was determined that the source would be capable of supplying potable water for the present demand.

    However, should this increase, other sources have already been identified to augment the supply.

    This project, Proposed Source Development at Kamalik, Vitali, Zamboanga City, involves 2 civil

    works (construction of 90 m3

    concrete ground tank and the construction of 4.8 m3

    capacity source

    collection box) and a 4.824 kilometer pipelaying works (3,194 linear meters 110 mm x 6.00 m PVC

    pipelines. Class 150, 1,630 linear meters 6.02 mm thick x 100 mm (I.D.) G.I. Pipeline (Schedule 40.)).

    This specified length of pipelines will be interconnected with the existing Vitali Water System Pipeline at

    Tamion Road in Vitali.

  • 7/31/2019 IEER Vitali

    11/19

    Page 11 of19

    The source that will be utilized for this proposed water system is the Kamalik Spring which has a

    flow of 4.08 liters per second (64.68 gallons per minute) and is situated some 5 kilometers from the

    existing Tamion Production Well, 321 true North of the entrance to Tamion from the national highway,

    and 329 true North of the Tamion Production Well. Thence, it shall be connected to the 1,630 linear

    meters of 100 mm G.I. Pipeline and the 608 linear meters of 110 mm PVC Pipeline and water will be

    stored on a 90 cubic meter ground tank located 1771 metres from the source at an elevation of 125

    meters above sea level (3 meters). Chlorination of the water will be made at the ground tank before

    distribution. The ground tank will be interconnected to the existing Vitali Water System Pipeline by the

    2586 linear meters 100 mm PVC pipe.

    This proposed water system has a total budget cost of ten million five hundred fifty-six thousand two

    hundred ninety-five pesos and 10/100 (Php 10,556,295.10). The manpower requirement has a total of 62

    personnel, which includes 54 laborers, 2 pipefitters, 2 carpenters, 1 welder, 2 steelman, and 2 mason,

    excluding the Project Engineer. It is expected to be completed in 135 days. It shall commence as soon as

    all permits have been acquired, including the issuance of the Environmental Compliance Certificate

    (ECC), and upon acquisition of the land where the proposed ground tank shall be constructed shall have

    been completed.

    3.3. Project Development Plan, Process/Technology and Project Components

    Figure 2 above shows the development plan for this project. Three major activities will form part

    of this project. The project shall begin at the water source which is located 4.8 kilometers from the

    existing Tamion Production Well. A 4.8 cubic meter concrete spring collector chamber will be constructed

    at the water source that will serve as a reservoir for this water system. This spring collector chamber will

    be connected to the 100 mm Galvanized Iron (G.I.) Pipe where the pipelaying activities of this project

    will begin. The pipelaying activities is composed of 1,630 linear meters of 6.02 mm thick x 100 mm

    (I.D.) G.I. pipeline and interconnected with the 110 mm x 6.00 m PVC pipe 608 linear meters in length.

    Then it will be connected with the 90 cubic meter concrete ground tank. From the ground tank it will be

    connected with the PVC pipe at 2,586 linear meters length to the existing Vitali Water System at the

    Tamion Production Well.

    Pipelaying

    Mobilization and hauling of materials will take 30 days and will require the use of 2 units boom

    truck to transport the materials to the project site. The pipelaying activity will require the use of backhoe

    for the excavation works, welding machine and bar cutter. Concrete pipe support will be placed at every 3

    meters interval for the G.I. pipes and before interconnection to the PVC pipe. Along the pipeline network,

    the following appurtenances will be installed: 5 units of 75 mm residential type fire hydrant and

    barricades at 500 linear meters interval; 4 units of blow-off assembly at lowest elevations along the

    pipeline(this requires the use welding machine); and 8 units of air-release assembly and barricade at

    highest elevations along the pipeline. At culverts and creek crossing of the G.I. pipes, welding machines

    will be used. Upon completion of the pipelaying works, the area where pipelines have been laid will be

    backfilled but not tampered in order that necessary repairs and amendments may still be made after

    conducting the hydrostatic test. Hydro testing will be performed where the pipes will be subjected to

    hydrostatic pressure of up to 150 psi for one (1) hour. This is done to expose defective materials that

    have missed prior detection, ensure that any remaining defects are insignificant enough to allow

    operation at design pressures, expose possible leaks and serve as a final validation of the integrity of the

    constructed system. This activity requires the use of a water tanker and a hydrotesting

    machine. Disinfection of the pipelines will be conducted to ensure that these are free from contaminants

    and bacteria that could affect the potability of the water being distributed. This is done by flushing 114

  • 7/31/2019 IEER Vitali

    12/19

    Page 12 of19

    cubic meters of potable water mixed with 3 kilograms of calcium hypochlorite into the pipelines.

    Thereafter, final backfilling and compaction of the earth where the pipes have been laid will be conducted

    using a tamper hammer machine.

    Construction of 90 cubic meter Concrete Ground Tank

    Excavation equivalent to 51 cubic meters in preparation for the construction of the concreteground tank will require the use of a backhoe that will be used for the excavation works and a 1 horse

    power water pump that will be used to pump out water from the excavated earth. A 100 mm full bore

    electromagnetic flowmeter flange type, with two (2) mating flanges and with wall mounted type signal

    converter complete with accessories will be installed in this concrete ground tank before the PVC pipe

    distribution line. The construction of this concrete ground tank will utilize 4 units of concrete bagger mixer

    and 2 units of concrete vibrator. 1 unit welding machine and 1 unit angular grinder will be used for welding

    the steel ladder and manhole cover of the ground tank. The same welding machine will also be used for

    the installation of valves and appurtenances and the interconnection works. After concrete curing of 28

    days, the newly constructed ground tank will be disinfected and subject to leakage test. Disinfection will

    be done by flushing 105 cubic meters of potable water with dissolved 8 kilograms calcium hypochlorite.

    Detecting leaks in the newly constructed tank will be by volumetric testing which is detected based on the

    measured change in volume of the water stored in the tank within 24 hours.

    Construction of 4.8 cubic meter Concrete Spring Collector Chamber

    The construction and interconnection of the spring concrete collector chamber will use 1 unit of

    welding machine, 1 unit concrete bagger mixer and 1 unit of concrete vibrator. After a curing period of 28

    days, disinfection of the spring concrete collector chamber will be done by introducing 35 cubic meters of

    potable water mixed with 1 kilogram calcium hypochlorite.

    3.4. Description of Project Phases (Activities/Environmental Aspects, Associated Wastes and

    Built-in Pollution Control Measures)

    3.4.1. Pre-construction/ Pre-operational phase

    The different activities involved during the pre-construction phase of this proposed project

    include project conceptualization, pre-feasibility and feasibility studies and the preparation of the

    detailed engineering plans and design.

    Consultations with the barangay officials and the residents have been conducted. It was

    during these meetings that possible sources have been identified. These sources have been

    verified and evaluated. Water samples have been taken for laboratory analysis at different dates

    of inspection.

    Survey has also been conducted from the water source to the road network where the

    pipelines will pass including the proposed project site for the constructed concrete ground tank. In

    these rural areas it is a common misconception that whenever topographic surveying activities

    are conducted in the area, their properties will be taken from them allegedly taking advantage of

    their illiteracy and poverty. However, during these surveying activities the residents have been

    forewarned by the local officials in the barangay that the surveying team of the Zamboanga City

    Water District will be conducting topographic survey and that they have been ensured that their

    properties will not be prejudiced along the way.

  • 7/31/2019 IEER Vitali

    13/19

    Page 13 of19

    Following the identification of the most ideal site for the construction of the concrete

    ground tank, the site development plan and sketch plan of this site is endorsed to the Lot

    Acquisition Committee for appropriate action. The Administration and General Services

    Department of this office shall then be responsible in processing the application for Water Rights

    with the National Water Resources Board and the application for land use with the CENRO-East.

    Assessment of improvements introduced by the residents in the area will be made after an

    evaluation by the CENRO-East office as to the land classification of this area and after a

    determination of their rights therein.

    The possible pollutants introduced into the environment during these pre-construction

    activities include emissions from the vehicles used by the team. The regular emission testing of

    these vehicles however assures that the emissions from the vehicles are within the standards set

    by the Clean Air Act.

    Also, solid wastes may be generated during these activities because of the food packs

    and plastic water bottle that were brought by the team. This was mitigated by requiring each

    member of the team to keep their trash with them until return to the office for proper disposal.

    3.4.2. Construction/Development phase

    Construction and Development Phase commences with the mobilization and the hauling

    of materials from ZCWD motorpool to the project site at Vitali. This activity is expected to affect

    ambient air quality due to entrained dust from materials delivery trucks travelling on unpaved road

    and the loading and unloading operations of aggregates and soil. Earth preparation activities

    would also affect air quality as a result of increase in entrained dust in the atmosphere as well as

    exhausts from the Diesel construction equipments used for site preparation, grading and

    excavation. Wind erosion of areas disturbed during construction activities would also affect air

    quality as well as emissions from transportations used by workers to commute to construction

    site. In order to mitigate adverse effects, settling of dust will occur over time and by water flushing

    of unpaved road for a particular interval of time to reduce entrained dusts in the atmosphere and

    to remove build up of loose materials to control dust emissions. All trucks hauling soil, sand and

    other loose materials will be covered or require them to maintain at least two feet of freeboard.

    Traffic speeds will be maintained at 40kph on unpaved surfaces.

    Pipelaying works including operation of heavy equipments and other construction

    equipments including hydrotesting and disinfection works of pipes and source box and ground

    tank, installation of valves and fittings and the interconnection works, as well as the installation of

    five (5) units of 75 mm fire hydrants and barricade and the installation of four (4) units of blow-

    off assembly also have its environmental impacts in the project site. These activities will entail

    generation of solid wastes of at least 5% of the total bulk of materials used for the entire project

    including but not limited to used bags of cement, empty paint cans, wood cuttings used for

    scaffolding of concrete, excess fill materials from grading and excavation activities, scrap woods

    and metals, and small concrete spills. It is also expected to generate a negligible volume of litter

    to include food containers, beverage cans, paper bags, plastic wrappers, and smoking materials,

    including materials generated by the public. Adverse effects will be mitigated by prevention on

    site through segregation of wastes according to recyclables, re-usable and non re-

    usable/recyclable. These wastes will be gathered at a temporary facility on site. Non-recyclable/re

    usable will be disposed of appropriately after a classification is made whether they are

    toxic/hazardous or non-toxic/harzardous.

  • 7/31/2019 IEER Vitali

    14/19

    Page 14 of19

    The use of construction equipments during this phase is expected to affect air quality due

    to their engine exhausts. Emissions from motor vehicles also contribute to these adverse effects

    to the air quality. Entrained dusts from earth preparation works, vehicles travelling on unpaved

    roads and the exhausts of these vehicles also contribute to air pollution. Exhaust from the diesel

    construction equipment used for site preparation, grading, excavation, and construction site of

    source collection box and concrete ground tank as well as the exhaust from diesel-powered

    electric generators, air compressors, water pumps may affect the ambient air quality at the project

    site.

    Sprinkling of water will be done at every identified interval to reduce entrained dusts in

    the atmosphere. Operational measures will also be maintained such as limiting engine idling time

    and shutting down the equipment when not in use in order to mitigate its adverse effects to the air

    quality. Regular preventive measures will also be made to prevent emission increases due to

    engine use. It will also be ensured that low-emitting Diesel engines must meet the standards set

    by the Philippine Clean Air Act (PCAA).

    During the construction phase of the project, noise levels are also expected to increase

    due to the use of heavy equipments such as backhoe, dump truck, welding machine, bar cutter,

    hydrotesting machine and tamper hammer. Considering that the project area is mostly composed

    vast open spaces which in itself is a natural noise barrier, including the vegetation which

    surrounds the spring source where a collection box will be constructed, its adverse effects to the

    community in the area is mitigated thereby. Operators of these heavy equipments are advised to

    use earplugs to mitigate the level of sound they receive to save their hearing.

    Since this project involves the use of an existing water body, it is expected that during the

    construction of the source collection box and its interconnection with the 100 mm G.I. pipe will

    decrease its water quality accountable to the temporary disturbances due to the construction

    activities or the introduction of wastewater from disinfection works which may increase turbidity

    levels and temporary alter the chemical characteristics of the water body concerned. Regular

    monitoring of the water body will be conducted throughout the construction duration either by

    taking water samples and bringing the same to the laboratory for analysis or by conducting onsite

    physical/chemical testing of the concerned water body. Baseline data has been gathered prior to

    the construction thereat. Cement preparation will be made several meters away from the creek to

    avoid contamination of the water body and to allow natural treatment of the creek before

    resumption of domestic use.

    3.4.3. Operational phase

    During the operation of the Vitali Water System, which will supply water to some 3,205

    population of Vitali. Regular maintenance activities at the source box will affect the water quality

    of the creek on which it is constructed. By allowing the creek to flow freely thus flushing down

    sediments and biosolids that formed in the collection box will naturally treat the water body which

    allows domestic use of its downstream.

    3.4.4. Abandonment phase

    Overtime, the natural wear and tear of the pipelines will take its toll thereby requiring the

    district to replace the old ones. These old pipelines will be taken back to the ZCWD motorpool for

    appropriate disposal or brought to recycling firms with respect to G.I. pipes and sanitary disposal

    with respect to the PVC pipes.

  • 7/31/2019 IEER Vitali

    15/19

    Page 15 of19

    3.5. Manpower Requirements

    This project has a total of 64 personnel which includes (1) project engineer, (1) driver, (54)

    labourers, (2) pipefitters, (2) carpenters, (1) welder, (2) steelman, and (1) mason. 50% of these manpower

    requirements will be taken from the local area, except for the skilled labor required for this project.

    3.6. Project Cost

    This project has a total project cost ofTEN MILLION FIVE HUNDRED FIFTY-SIX THOUSAND

    TWO HUNDRED NINETY-FIVE and 10/100 (Php 10,556,295.10).

    3.7. Project Duration and Schedule

    This project shall commence immediately upon its approval and is expected to be completed

    within one hundred thirty-five (135) working days.

    ITEM WORK ITEM/DESCRIPTION Target Duration From To

    I PIPELINES

    A MOBILIZATION/HAULING & STAKING WORKS

    1 Mobilization 5 days 03/01/12 03/05/12

    2 Hauling of Materials 30 days 03/01/12 03/30/12

    3 Final Staking/ Lay-outing/ Line & Grade 30 days 03/06/12 04/04/12

    B Pipelaying Works

    1 Pipelaying

    20

    pipes/day 64 days 03/06/12 05/08/12

    2 Valves/Fittings & Inter-connection Works 2 days 04/05/12 04/06/12

    3 Culvert & Creek Crossing 8 days 03/30/12 04/06/12

    4 Installation of Five (5) units - 75mm Fire 1 unit/day 5 days 04/07/12 04/11/12

    Hydrants & Barricade

    5 Installation of Four (4) units Blow-off Assembly 2 units/day 8 days 04/12/12 04/19/12

    6 Installation of Eight (8) units Air-Release 5 days 05/06/12 05/10/12

    Assembly & Barricade

    7 Disinfection/ Hydrotesting of Pipelines 6 days 04/07/12 04/12/12

    8 Final Backfilling & Compaction

    18

    cu.m./day 64 days 03/06/12 05/08/12

  • 7/31/2019 IEER Vitali

    16/19

    Page 16 of19

    4. BASELINE ENVIRONMENTAL CONDITIONS, IMPACT ASSESSMENT AND MITIGATION

    4.1. The Land (Land use, Pedology, Geology, Geomorphology, Terrestrial biology)

    The general soil classification at the project site is classified by the Bureau of Soils as Antipolo.

    This soil type covers 3484.22 hectares of Barangay Vitali.

    The soil characteristic surrounding the source was mostly compacted clay loam. But the river bed

    is sandy with large rocks and surrounded with trees mostly composed of rubber, mango, lawaan,

    bamboos and other varieties of flora. This extends to the head source of the spring which is sparsely

    vegetated by various trees, including fruit bearing ones, shrubs and grasses. Only light structures may be

    found within the vicinity to include houses made of native materials which are considerably distant from

    one to the next, the nearest of which structure to the source is a house located approximately 700 meters

    to the spring source, and a chapel. An elementary school is found approximately 4 kilometers from the

    spring source. The Tamion Production Well of ZCWD is located approximately 5 kilometers from the

    source.

    In a joint inspection by the Planning and Design Division, with representation from the

    Construction Division of this agency, together the Land Evaluation Party of the City Environment andNatural Resources Office-East of the Department of Environment and Natural Resources, the proposed

    water source and the whole 3 hectare expanse area to which a Special Land Use was applied for, was

    classified as a Timberland. Subsequently, an inventory of forest resources will be conducted in this area.

    The land cover for most hectares, including the proposed project site for pipelaying works and the

    most parts of the project site are grasslands/savannahs and open areas mixed with shrubs, with isolated

    portions used for local agriculture. The entire barangay of Vitali has a total land area of 4,013.18 hectares

    grasslands with mixed shrubs including the area where the proposed concrete ground tank will be

    constructed.

    The terrain in the study area (around the project site for the source collector chamber and the

    project site for the concrete ground tank) is generally mountainous with an estimated slope of 65% fromthe project site of the proposed ground tank, while the slope from the source is estimated at 79% slope.

    The Slope Map for Barangay Vitali as prepared by the City Planning and Development Office (CPDO) has

    classified the 2,245.75 hectares of the said barangay to have a slope at 50% and above, including the

    areas for the proposed project sites.

    5,069.37 hectares of the barangay was identified to be prone to severe erosion according the

    Erosion Map of the barangay sa prepared by CPDO. However, the area where the proposed ground tank

    will be constructed is within the 2,083.02 hectares that have been classified as susceptible to moderate

    erosion.

    An application for Special Land Use has already been submitted by the proponent for the use of

    this area for this proposed project. Only upon the issuance of the aforementioned permit shall this projectensue.

    4.2. The Water (Discuss only relevant modules or modules likely to be affected by project impacts

    Hydrology, Oceanography, Water Quality, Freshwater Biology, Marine Biology

    The water body that will be utilized for the development of this water system is a spring in Sitio

    Kamaliksituated within a piece of land classified as Timberland. It has yield of 4.08 liters per second or

    64.68 gallons per minute and is the source of water for the nearby inhabitants in the area, approximately

  • 7/31/2019 IEER Vitali

    17/19

    Page 17 of19

    for 7 households. The water in this spring is of drinking water quality after it has been subjected to

    physical and chemical laboratory analysis. (water quality result) A bamboo-made flume was used by

    nearby residents to convey water where locals would bring their plastic containers to gather water needed

    for daily consumption. It is used for their daily household particularly for drinking. Nearby streams and

    creeks were used for bathing, washing and gardening.

    Another ground resurgence classified as a 6th magnitude spring which is utilized by residents asource of drinking water was also found some 740 meters from proposed site where a small impounding

    facility will be constructed. However, this was not considered for development because of its insufficient

    yield which was at 5.27 gallons per minute only. The physical and chemical characteristics of the water

    sample taken from this latter spring has passed the national standards for drinking water quality.

    An application for Water Rights over this water source has been applied for by the proponent in

    relation to this proposed project with the National Water Resources Board.

    4.3. The Air - ((Discuss only relevant modules or modules likely to be affected by project impacts -

    Meteorology, Air Quality, Noise

    Despite the deficiency of sufficient forest cover, the ambient air quality is excellent in the areaconsidering the absence of point and non-point air pollutant sources in the area owing to its strategic

    location and the absence of traffic congestion and industrial facilities.

    Noise levels range from 20-50 decibels which could be attributed only to ordinary man-made and

    animal-made sounds.

    4.4. The People

    Residents living nearby the source and within the vicinity of the study area are generally engaged

    in agricultural activities for consumption. There were more or less 40 families residing within the study

    area. But there were less than 10 families within the immediate (within 10-15 meter radius) vicinity of the

    source. Mostly are engaged in latex harvesting in the surrounding rubber plantation in the area.

    The locales within the vicinity of the proposed project site, particularly those which have been

    found residing within what was identified by CENRO-East as timberland, claim to be in occupation of the

    land but without possession of any tenurial instruments which may have been issued by the State. The

    following are the heads of households residing within the 3-hectare timberland land area which the

    proponent have applied for Special Land Use:

    1. Pedro Legazpi

    2. Edwin Legazpi

    3. Joel Fernando

    4. Leonardo Carpio

    5. Gilbert Fernando

    Land ownership of the project site where the proposed ground tank will be considered is covered

    by TCT No. T-58, 051 in the name of Cecinio Danlag married to Caridad Esperat for an area of 41,315

    square meters. For the purpose of this project, the proponent will be negotiating for the acquisition of 200

    square meters out of this area for the construction of the concrete ground tank.

  • 7/31/2019 IEER Vitali

    18/19

    Page 18 of19

    5. ENVIRONMENTAL MANAGEMENT PLAN

    5.1. Impacts Management Plan

    Impacts mitigation strategies are mostly incorporated in the different activities involved in this

    project. At the pre-construction stage, which is mostly composed of data gathering activities, impacts

    prevention are made. During the site/source verification, activities were limited at the water bodies inorder to mitigate impacts to water quality. Solid wastes generated during said activities were gathered for

    disposal at the garbage bins at the office. At this stage, proper coordination with the barangay council had

    already been made in order not to surprise locals and generate unnecessary anxiety of displacement

    from their respective properties. Information dissemination were made by local authorities in order to

    appease them of the succeeding activities. This was done before the topographic survey of the project

    site. Proper acquisition proceedings have been conducted by the Lot Acquisition Committee of this office

    with respect to properties that need to be acquired in relation to this project. Constant visits to the project

    site required transportation. In this case, regular preventive maintenance were made on vehicles used to

    prevent emission increases due to engine. Low sulphur and low aromatic fuel meeting the standards set

    for motor vehicles by the Philippine Clean Air Act (PCAA) were used, as well as low-emitting Diesel

    engines which meets the standards of PCAA.

    An expected decrease in ambient air quality will be brought about by the mobilization and hauling

    of materials during the construction phase of this project. Water flushing will be made of unpaved road at

    every predetermined interval depending upon the degree of fugitive dust caused by material delivery

    trucks to reduce entrained dusts in the atmosphere and to remove build up of loose materials. All trucks

    hauling soil, sand and other loose materials will covered or at least required them to maintain at least two

    (2) feet of freeboard. Also, traffic speeds will be limited at 40 kph at unpaved roads. Final

    staking/layouting/line and grade activities are also expected to affect ambient air quality. Entrained dusts

    are expected to be generated during site preparation and grading/excavation at the construction site. The

    same effects will be generated during onsite travel on unpaved surfaces. Thus, water flushing will be

    made in order to avoid build up of entrained dusts. Exhaust from the Diesel-fuelled construction

    equipments used for site preparation, grading, and excavation. In order that its adverse effects to air

    quality, operational measures such as, limiting of engine idling time and shutting down equipment when

    not in use, will be made. Regular preventive maintenance will also be made to prevent emission

    increases due to engine problems. Water application or chemical dust suppressants will be applied or

    sprayed to control dust emissions from unpaved surface and unpaved parking areas. The same effects

    will be generated by the pipelaying works including the operation of heavy equipments and other

    construction equipments, including hydrotesting and disinfection works, installation of valves/fittings and

    interconnection works; installation of five (5) units of 75 mm fire hydrants and barricade; installation of

    four (4) unit blow-off assembly are also expected to cause decrease in the ambient air quality at the

    project site, particularly, the use of construction equipments, motor vehicles, and brake and tire wear.

    Thus, the same mitigation measures which are applicable will be practiced for these activities at the

    construction phase of this project.

    In general, the solid waste generated during the implementation of this project will be managed

    through site prevention, segregation of waste according to its classification as to recyclables, re-usables

    and non re-usables/recyclables. These will be gathered at a temporary facility where only those classified

    as non-reusables/recyclables will be disposed of after further classification as to toxic/hazardous or non-

    toxic/non-hazardous, in which case appropriate disposal will be made.

    It is expected that during the construction phase of this project noise levels in the project site will

    increase due to use of heavy construction equipments. However, the strategic locations of the project site

  • 7/31/2019 IEER Vitali

    19/19

    Page 19 of19

    versus the location of nearby communities are significant enough to act as noise barriers. Machine

    operators will also be advised to use ear plugs to avoid damage to their hearing.

    Nearby creeks and other water bodies in the area will suffer a temporary decrease in water

    quality due to disturbances that may be caused by the construction activities particularly during the

    construction of source box and pipe supports and creek crossings. Regular monitoring of these water

    bodies will be made by taking water samples to the laboratory for analysis to ensure its quality. Cementpreparation will be made some distance from the creek, approximately 10-20 meters away, to avoid

    contamination of water bodies from cement leachate.

    5.2. Environmental Monitoring Plan

    Generally, the environmental monitoring plan for this project will involve mitigation and control

    measures in order to avert and assuage the adverse effects to the environment at the project site that

    may be caused by this undertaking.

    Because of financial limitations and the nature and degree of the impacts to the environment of

    this water system project, sampling and measurement plans are limited to the conventional methods such

    as random sampling for solid wastes and use of calibrated waste receptacle for measuring the volume ofsolid waste generated; volumetric method of measuring the flow of wastewater used for hydrotesting and

    disinfection works.

    5.3. Institutional Plan for EMP Implementation

    At present, ZCWD is still in the process of developing its institutional plan for EMP

    Implementation. As soon as this will be completed, it will be incorporated in the preparation of EMP for

    future projects and adapted in its future undertakings.