IEEE Power and Energy Society - MVAR control, integration ...MVAR control, integration of wind...
Transcript of IEEE Power and Energy Society - MVAR control, integration ...MVAR control, integration of wind...
MVAR control, integration of wind generation to grid,
plausible solutions for supporting quality power and reliable grid in
free markets Diran Obadina
Principal, Systems Development ERCOT
July 29, 2015 Paper Number 15PESGM2585
1
Current Records – July 15, 2015
2
Peak Demand Record: 68,305 megawatts (MW)
68,305 MW, August 3, 2011
Weekend Record
65,159 MW, Sunday, August 28, 2011
Winter Peak Record: 57,265 MW
57,265 MW, February 10, 2011
Wind Generation Records (instantaneous)
11,154 MW, February 19, 2015, 10:52 p.m.
- Non-Coastal Wind Output = 9,872 MW
- Coastal Wind Output = 1,282 MW
- Supplying 34.2% of the load
- Active Wind Capacity = 13,370 MW
• 40.58% Wind Penetration, March 29, 2015, 2:12 a.m.
- Total Wind Output = 10,308 MW
- Total Load = 25,400 MW
June 2015 Demand
- 61,732 MW, June 10
June 2014 Demand
- 59,786 MW, June 30
Wind Generation – June 30, 2015
3
816 977 1,173 1,3851,854
2,875
4,785
8,0058,916
9,400 9,60410,407
11,065
12,47013,424 13,424 13,424
2,941
5,5935,593
3,5904,390
116
816 977 1,1731,385
1,854
2,875
4,785
8,005
8,9169,400
9,60410,407
11,065
12,470
16,365
22,607
23,407
0,000 MW
5,000 MW
10,000 MW
15,000 MW
20,000 MW
25,000 MW
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Cumulative MW Installed IA Signed-Financial Security Posted IA Signed-No Financial Security
The data presented here is based upon the latest registration data provided to ERCOT by the resource owners and can change wi thout notice. Any capacity changes will be reflected in current and subsequent years' totals.
Scheduling delays will also be reflected in the planned projects as that information is received. This chart reflects planned units in the calendar year of submission rather than installations by peak of year shown.
Financial security posted for funding interconnection facilities does not include CREZ security deposits, which are refunded to the Interconnecting Entity when an IA is signed.
ERCOT Wind Installations by Year (as of end of June 2015)
Cumulative Installed and Planned Solar Capacity
4
193 193 193
7,563
10,153
15 42 82 121 191 288
7,756
10,346
0
2,000
4,000
6,000
8,000
10,000
12,000
2010 2011 2012 2013 2014 2015 2016 2017
Cumulative MW Under StudyCumulative MW Installed
Megawatts
95
COMPETITIVE RENEWABLE ENERGY ZONES
5
Challenges of Voltage control
6
• Large wind power farms with little or no local loads
served and/or large synchronous machines in the
zone affecting system stability
• Long, highly compensated 345KV transmission lines
to load centers in the north and east;
– Critical voltage at voltage collapse point is relatively high which
could put the system at risk even when the voltages are within
normal ranges
• Multiple wind resource and transmission owners
– Consideration of fairness in a competitive environment.
Wind Power vs 345 KV Voltage
7
Proposed Framework
8
Reactive Resource Scheduling
Contingency List
Load Forecast
SCADA EMS
Wind Forecast
Outage Schedules
Transmission Operators
Real time Reactive Dispatch
Current Operating
Plan
Reactive Resource Scheduler
9
• Schedules switchable reactive devices over multiple hours into the future
• Objective is to minimize number of switching needed over the scheduling horizon in order to maintain voltage
• Maintain adequate reactive reserve in defined reactive areas
• Executes in the day-ahead following RUC and then hourly to refine the day-ahead schedules
Scheduling Horizon; Scheduling Interval; Load Curve
10
time Scheduling horizon (T)
Fore
caste
d L
oad
-C
urv
e
…
…
Reactive Resource Scheduling Objective
11
Reactive Resource Scheduling
12
• Scheduling Horizon: 12-24 hours
• Scheduling Interval: 30-60 mins
• Works with the RT Reactive Dispatch
• Maintains adequate reserve with the voltage
control area
Reactive Resource Scheduler - Controls
13
• Shunt Capacitors
• Shunt reactors
• Line switching
• Unit commitment
• Invokes Reactive Dispatch
Real Time Reactive Dispatch
• Executes in the Real Time Sequence
• Objective – Manage the voltage across the ERCOT grid – Secure base case voltage ranges throughout system
– Maintain post contingency voltages
– Restore post-event secure voltage profile
– Minimum shift/minimum number of controls objective function
14
Real Time Reactive Dispatch - Controls • Generator AVR Target Voltage
• Synchronous Condenser AVR Target Voltage
• SVC Target Voltage
• On-line Transformer Taps
– Tap position
– Target voltage
• Invokes the Reactive Resource Scheduling (RRS) in case of infeasibility
15
Thank You!
16