IBL cooling tube routing proposal
description
Transcript of IBL cooling tube routing proposal
Single outlet tubeSingle inlet tube
Concentric tube
Outlet Manifold
Inlet Manifold Inlet
Capillaries
IBL Cooling pipes layout idea:
[email protected] IBL CO2 cooling routing proposal
• A survey of the routing possibilities in Atlas has been carried out to come up with a more detailed proposal than the one on the previous slide.
• Routing in difficult areas was simulated with 50mm PVC piping. A Mock-up is made which can be measured and modeled into CAD.
• The dimensions of the neighboring hardware were measured to find space for additional hardware and accessibility. Measurements will be used to check the available 3D models.
• Preliminary check of measurements is done with existing 2d drawings from CDD.
• A principle design of the full tube routing is made– Where to put manifolds, valves, etc. – What isolation can be applied (Foam / Vacuum).
3
[email protected] IBL cooling tube routing CAD measurements
BIL muon
LAR cryo pipesExisting support structuresVertical cables
Cooling pipes
Cooling pipes
Cooling pipes
Cooling pipes
Sector 5
LAR
cry
ogen
ic p
lant
Bart’s CAD office
5
Measured cooling tube routing and support environment in the Atlas overall drawing
[email protected] IBL cooling tube routing at inner detector.
• From the ID-end plate a nice path following the dry-air chimney was found to the top of the tile calorimeter.
• In the empty space between inner muon chamber of sector 5 and the tile calorimeter a path was found to accessible area between sector 5, BIL and BML layers. In this space the transition from IBL feed and return tubing to the concentric transfer tube can be made.
• Delicate equipment can be placed in this area as it is easily accessible.– Valves, filters, sensors.– Manifolds?
• Tubes to ID-end plate can be vacuum insulated and can be installed prefabricated.
• Insulation of transition hardware can only be foam insulated. Placement of a condensation catch channel underneath is possible.
7
[email protected] IBL cooling branch
8
IBL Boiling tube:2.0mmID x 1308mm
(Heated length 708mm)
Inlet Capillary(Flexible)
0.8mmID x 5289mm(2609.5+2679.5)
Outlet tube2.0mmID x 2679.5m
Q≈100 Watt / stave
14 staves = 14 parallel branches.
PP1 Connector
IDEP Inlet Manifold
IDEP Outlet Manifold
PP0 Weld Connector
PP0 Weld Connector
Outlet tube3.0mmID x 2609.5m
or2.0mmID x 2609.5m
(TBD)
PP1 Connector
50mm pvc dummy tube with 45’ connectors
Longitudinal routing near lower BIL muon chamber corner.
Passage through almost empty channel
Routing and clamping on top of “chimney”
Entering ID-endplate left of “chimney”
IBL CO2 cooling tube routing at calorimeter end flange
[email protected] IBL Cooling junction at sector 5
C-side view Top view
ID end plate Vacuum insulated cooling tubesFoam insulated cooling tubes
LAR pipesLAR pipes
Cooling components area
Cable channels
BIL muon chambers
platform
Concentric transfer tube
Concentric transfer tube
Con
nect
ion
to A
-sid
e
Con
nect
ion
to C
-sid
e
Connection to C
-side Con
nect
ion
to A
-sid
e
[email protected] End cap region pictures
11PVC mockup @ Aside (Fits also @ Cside)
IDEP interface
Routing on top of chimney Passage of Tile calorimeter cable channel
Entry of Tile calorimeter cable channel
Passage between S5 BIL muon and Tile calorimeter
Clearance above endcap tile calorimeter for installation passage
[email protected] Sector 5 junction pipe pictures
12
Junction routing at S5Passage between S5 BIL muon and Tile calorimeter
Passage between S5 BIL muon and Tile calorimeter C-side
Passage of BIL muon layer
Junction routing around muon alignment beams
Passage of BIL muon layer
Free installation space for junction box
Junction tubes on top of cable channel /below LAR pipe
A-side C-side
[email protected] IBL transfer tube inside Atlas detector
• A straight path from the sector 5 cooling junction to the outside was found following the cryogenic LAR piping towards the cryogenic LAR plant at level 6.
• The straight path allow us to make the concentric transfer tube in the detector to be vacuum insulated.
• Concentric vacuum assembly can be made using 6m tubes. At the LAR cryogenic plant sufficient space is available for inserting 6m long tubes.
• Construction of 6m long tubes (standard trading length) gives weld joint locations in accessible areas. – BIL/BML sector 5 (Junction box)– BML/BOL sector 7 (Area behind small toroid access door) – LAR cryogenic plant at level 6.
• Routing and inserting was simulated using 50mm PVC piping.
13
[email protected] Concentric transfer line in Atlas detector
14
6 m 6 m
BIL/BML sector 5 (Junction box)
BML/BOL sector 7 (Area behind small toroid access door)
LAR cryogenic plant at level 6
Existing mechanical supports
12.9 m
Concentric transfer line
[email protected] Vacuum insulated transfer tube pictures (S5 and S7)
15
Transfer line at S5
Transfer line terminal at S5
Transfer line underneath platform in S5
Transfer line following LAR cryo-pipes from S5 to S7
Transfer line next to LAR cryo-pipes in S7
S7 accessible area for welding
Only obstacle in the way: ladder in S7: 1cm shift required.
Vacuum insulated transfer tube pictures LAR cryogenic plant
16
Transfer line exits BOL layer at S7/8
Transfer line exits BOL layer at S7/8
Transfer line arrives at LAR Cryogenic plant
Inserted transfer line at LAR Cryogenic plant
Insertion of a 6m tube at LAR cryogenic plant (3)
Insertion of a 6m tube at LAR cryogenic plant (2)
Insertion of a 6m tube at LAR cryogenic plant (1)
[email protected] Transfer tube routing to cooling plant
• A nearly horizontal path was found to the cooling plant area in USA15
• Tubes follow LAR vacuum tube towards cavern wall and go along wall to the tube and cable tunnel.
• Tubes can be installed on top of C3F8 cooling channels to USA15
• Vacuum pump can be installed on cavern wall next to LAR vacuum pump
• Insulation will be foam from LAR cryogenic plant towards CO2 cooling plant
17
[email protected] Cavern tube routing
18
Start at LAR cryo plant
Follow LAR vacuum pipes
Follow pipes at cavern wall
Follow C3F8 pipes in tunnel
Follow C3F8 pipes in USA15
Terminate at proposed IBL cooling plant platform
[email protected] IBL cooling plant location
• A nice free space was found on an empty platform at the upper layer of USA15.
• Tube routing towards this space is easy.• Is this space available for the CO2 plant?
19
[email protected] Tube length summary
Length (m)
Upward length (m)
Downward length (m)
Foam transfer feed line 98.4 2.5 3Vacuum transfer feed line 12.9 0 0Inlet junction 2.5 0 0.4Inlet vacuum pipe 6.5 0 2.9Inlet capillary 5.3 0 2.5Total feed line 125.6 2.5 8.8IBL 1.3 0 0Outlet capillary 5.3 2.5 0Outlet vacuum pipe 6.5 2.9 0Outlet junction 3.1 0.4 0Vacuum transfer return line 12.9 0 0Foam transfer return line 98.4 3 2.5Total return line 126.2 8.8 2.5Total length: 251.8 11.3 11.3
20
[email protected] Summary and conclusions
• Proposed tube routing from IBL to cooling plant is feasible and looks relatively easy to apply.
• Vacuum insulation in the detector – Except at junction area, but very accessible for a proper insulation.
Condensation catch channels will be installed as guarantee.• Pre-fabricated vacuum channel from junction to ID-end plate.• Vacuum insulated transfer line possible to manufacture in place.• Junction area is easy to access, this will be the location for most of
the sensitive hardware.• It will be investigated to locate the manifolds as well in the junction
area.– Long capillary tubing!!– Accessible manifolds.– Possibility to disconnect an IBL cooling channel.
• Can CO2 plant be placed at the free platform in USA15?21