IAN REPORT 171 - · PDF fileModeling of the Cougar Creek Debris Flood Retention Structure;...
Transcript of IAN REPORT 171 - · PDF fileModeling of the Cougar Creek Debris Flood Retention Structure;...
University of Natural Resources and LifeSciencesDepartmentofCivilEngineeringandNaturalHazards
InstituteofMountainRiskEngineeringPeterJordanStr.82 Tel.:+43‐1‐47654‐4350A‐1190WIEN Fax:+43‐1‐47654‐4390
IANREPORT171
PhysicalModelingoftheCougarCreekDebrisFloodRetentionStructure
Vienna,February2016
2
Projektleitung: Univ.Prof.Dipl.‐Ing.Dr.HüblJohannes
Mitarbeiter: FalkensteinerMartin
Dipl.‐Ing.Dr.ChiariMichael
IliadisMarie
Reference: HÜBL, J., FALKENSTEINER, M., CHIARI, M., ILIADIS, M. (2016): Physical ModelingoftheCougarCreekDebrisFloodRetentionStructure;IANReport 171, Department of Civil Engineering and Natural Hazards, University of NaturalResourcesandLifeSciences–Vienna(unpublished)
Vienna,February2016
UniversityofNaturalResourcesandLifeSciences
DepartmentofCivilEngineeringandNaturalHazards
InstituteofMountainRiskEngineering
PeterJordanStr.82 Tel.:+43‐1‐47654‐4350
A‐1190WIEN Fax:+43‐1‐47654‐4390
IANReport171:
PhysicalModelingofthe
CougarCreekDebrisFloodRetentionStructure
3
Contents
INTRODUCTION ...................................................................................................................... 6
1 MODEL SETUP ................................................................................................................ 7
1.1 Froude scaling .............................................................................................................. 7
1.2 Construction of the model ............................................................................................. 8
1.2.1 Water supply ........................................................................................................ 8
1.2.2 Central model ...................................................................................................... 9
1.2.3 Stilling basin and erosion area .......................................................................... 16
1.3 Sensors and measurements ....................................................................................... 18
1.3.1 Discharge .......................................................................................................... 18
1.3.2 Water level heights ............................................................................................ 18
1.3.3 Thomson Weir ................................................................................................... 19
1.3.4 Height of throttle opening .................................................................................. 20
1.3.5 Volume of the bedload deposition an remobilization ......................................... 20
1.3.6 Bedload transport capacity in the culvert ........................................................... 21
1.3.7 Density of the bedload deposit .......................................................................... 21
1.3.8 Flow velocities ................................................................................................... 21
1.4 Rakes .......................................................................................................................... 22
1.4.1 Rake#1 .............................................................................................................. 23
1.4.2 Rake#2 .............................................................................................................. 24
1.4.3 Rake#2a ............................................................................................................ 26
1.4.4 Rake#3 .............................................................................................................. 27
1.4.5 Rake#4 .............................................................................................................. 29
2 EXPERIMENTS ............................................................................................................... 31
2.1 Hydraulic experiments ................................................................................................ 31
2.1.1 Types of the hydraulic experiments ................................................................... 31
4
2.1.2 Design of the outlet channel .............................................................................. 33
2.1.3 Effect of throttle design ...................................................................................... 36
2.1.4 Effect of rake designs ........................................................................................ 37
2.1.5 Effect of the inlet design and positioning of the rake ......................................... 39
2.1.6 Length of the overfall ......................................................................................... 40
2.1.7 Discharges at different storage levels ............................................................... 41
2.2 Experiments with woody debris .................................................................................. 42
2.2.1 Test setup .......................................................................................................... 42
2.2.2 Effect of rake designs ........................................................................................ 45
2.3 Experiments with bedload transport ........................................................................... 45
2.3.1 Setup ................................................................................................................. 45
2.3.2 Experiments ....................................................................................................... 47
2.4 Overflow scenario ....................................................................................................... 55
2.4.1 Velocity distribution ............................................................................................ 55
2.4.2 Stilling basin ...................................................................................................... 56
2.5 Investigations on the diversion tunnel ......................................................................... 60
2.5.1 Setup ................................................................................................................. 60
2.5.2 Hydraulic investigation ....................................................................................... 62
2.5.3 Sediment transport investigation ....................................................................... 67
3 CONCLUSIONS AND RECOMMENDATIONS ............................................................... 68
3.1 Hydraulic experiments ................................................................................................ 68
3.2 Experiments with woody debris .................................................................................. 68
3.3 Experiments with bedload transport ........................................................................... 69
3.3.1 Deposition behavior and remobilization of material ........................................... 69
3.3.2 Bedload transport in the outlet channel ............................................................. 69
3.3.3 Bedload deposition/erosion behavior in the ‘stilling basin ................................. 69
3.4 Overflow ...................................................................................................................... 69
5
3.5 Diversion tunnel option ............................................................................................... 70
3.6 Scaling issues in hydraulic modelling ......................................................................... 70
4 REFERENCES ................................................................................................................ 71
5 ATTACHMENTS ............................................................................................................. 71
6
Introduction
CougarCreek ispartof theMountainCreekHazardMitigationProgram.After thedebris‐flood
eventinJune2013,establishinglong‐termmitigationbecameapriorityfortheTownofCanmore
inordertoavoidanothercatastrophicsituation.Indeed,thislastmountainhazardcausedsevere
damagesintheCougarCreekcatchmentandonthealluvialfan.Moreover,apartoftheTrans‐
CanadianHighwayandCanadian‐PacificRailwaywasdestroyed,breakingconnectionsbetween
Banff(WestofCanmore)andCalgary(BGCENGINEERINGLtd.,2014).Theshort‐termmitigation
was initiated early 2014 and completed in May 2014, one year after the devastating event
(CANMORE, 2015a), including excavations of the creek channel, cleaning out debris aggraded
duringthedebris‐floodof2013,constructionofchannelbedprotectionandadebrisnet,etc.
ManyscientificstudieswereconductedonCougarCreek,mainlyaboutgeomorphology,hydro‐
climate and watershed. For long‐term mitigation a debris flood retention structure was
recommended following an option analysis and evaluation phase. ALPINFRA CONSULTING +
ENGINEERINGGMBHandCanadianHydrotechCorp.arethemainconsultantsontheproject.
To support the process of planning, hydraulic experiments on a physical scale model were
performedattheInstituteofMountainRiskEngineeringofUniversityofNaturalResourcesand
LifeSciencesinVienna.
Scopeoftheprojectwas:
hydraulicoptimizationoftheoutletchannelgeometry.
optimizationsofroughnessintheoutletchannel;
investigationsontheeffectofdifferentthrottledesigns;
optimizationofthegravelrakeshape;
investigationsonsedimentdepositionintheculvert;
observationsofthelocationofahydraulicjumpand
investigationsondepositionanderosionofsedimentup‐anddownstreamofthedebris
floodretentionstructure.
7
1 Model Setup
1.1 Froude scaling
Inordertotransferalltheprocessesandconclusionsbetweenthemodelandreality,mechanical
similarity, which comprises geometric, kinematic, and dynamic similarity, has to be fulfilled
(Preissleretal.1989).Inopenchannelflows,theflowingmediumiswater,whichhasaverylow
Newtonianviscosity.Forphenomenawheregravityandinertialforcesaredominantandeffects
ofremainingforcessuchaskinematicviscosityaresmall,Froudescaledmodelsarepreferred.In
ordertokeepunavoidableerrorssmall,thegeometricalscalingfactorshouldbekeptassmallas
possible(i.e.thephysicalmodelshouldbeaslargeaspossible).ThescalefortheCougarCreek
modelwaschosentoequal1:30.
Incontinuummechanics,theFroudenumber(Fr)isadimensionlessnumberdefinedastheratio
oftheflowinertiatotheexternalfield.NamedafterWilliamFroude,theFroudenumberisbased
onthespeed–lengthratioasdefined:
∗
where v0 is a characteristic flow velocity, g is the acceleration due to gravity, and h is a
characteristic length (PREIßLERandBOLLRICH,1985). Equality in Fr in model and full scale
will ensure that gravity forces are correctly scaled.
InTable1thescalingratioalongfordifferentphysicalunitsisgivenbyλ,whichisthescaling
factorforFroudesimilarity.
Table1:ScalingratioalongFroudesimilaritylaw.
description symbol scalefunction(Fr)
length l λ
acceleration b λ0
pressure p λ
speed v λ1/2
discharge q λ5/2
time t λ1/2
8
1.2 Construction of the model
Fortheexperiments in the laboratoryof the InstituteofMountainRiskEngineeringaFroude‐
scaledmodelwithaphysicalscaleof1/30wasbuilt.
Duetoalimitedwidthofthelaboratorya30mwidesectionoftheretentionstructurewiththe
bottomoutletchannelinthecenterwasrepresentedbythemodel.Thelengthoftheupstream
channelbedwaslimitedto115minnaturaldimensions.Fortheupstreamchannelbedanaverage
inclination(3.5%)ofthelast165mupstreamwasused.Thegeometricdesignofthedamwas
plannedaccordingtospecificationsprovidedbyalpinfra.Theinclinationatthefootprintofthe
retentionstructurewas4.37%.Theinclinationoftheupstreamembankmentdamalsofollowed
theinformationfromalpinfra,butneglectingtheaccessroad.Afterall,theinclinationfromthe
lowesttothehighestpointofthedamcrosssectionwasused(38.1%).Toprovideabetterinsight
intotheprocessofthetunneldischarge,thedownstreamsurfaceofthemodelwasnotinstalled
forthefirsttests.Itwasaddedeventuallyforthe‘overflow’(2.1.1.4)testsinthelaststageofthe
modeling.
TheoveralldimensionsoftheCougarCreektestsetupreachedalengthof14mandawidthof3m,
including:
Thewatersupplywithwaterreservoir,Thomsonweirandbypass(3.05mlength).
Thecentralmodelwithriverbedsectionanddamstructure(8.9mlength).
Thesectionforthestillingbasinanderosionarea(1.6mlength).
Thefilterbasin,partlyplacedbelowtheerosionarea(1.24mlength,0.48moverlapping).
Aconveyorbeltwasusedtoaddbedloadmaterial.
1.2.1 Water supply
The configuration of our laboratory includes a 27m3 sub level water basin (see Figure 7). A
circulatingpump (type:Grundfos ‐ CLM150‐271‐18.5A‐F‐A‐BBU)bringsup thewater (up to
50l/s)andfillstheso‐called‘ThomsonBasin’.
SubsequenttotheThomsonBasinisanintermediatebasinwithbypass,whichallowstosuddenly
stopthedischargeinthemodel(Figure1).
9
1.2.2 Central model
Themainmodelwasbasedon10reinforced‘U‐profiles’madeoutof10x10cmsquareshaped
timber.The‘U‐profiles’hadaninnerwidthof120cmandaheightof150cm(seeFigure9).
The profileswere placed in a linewith a distance of 100cm from each other and horizontal
leveled.Averticallyplacedrasterframeworkoutofathree‐layersheeting(company:doka)was
placed on the base structure, following the specified inclinations for the channel bed and the
embankment dam structure (see Figure 2). Sheeting boards (1m wide) were placed on that
framework,providingthebaselayerforthedamstructureandasealingfoil.
Further,1.5mwidethree‐layerboards,fixedverticallytotheleftandrightandtheupstreamhead
endofthemodel,flankedthebottomconstruction.Thesidewallsweresupportedbytheabove‐
mentionedu‐profiles inavertical, and20x8cmH‐beamtimber inahorizontaldirection.The
modelofthedamstructurewasplacedinthischannel,sotheretentionbasinwasformed.The
foundationwasthencoveredwithanimpermeablefoiloutofEPDM‐material.
Figure1:Watersupplyinstallations.
10
Additionalsheetingboardsforfurtherinstallationswereplacedonthesealinglayer.Anadditional
basinwithscumbaffle(breakingthevelocityoftheinflow)wasfixedontheboards,placedonthe
channelbedsection.Thechannelroughnesswasplacedonthoseboardstoo.Theboardsatthe
upstreamslopeoftheembankmentdamsupportedtheinstallationofthethrottle,thedifferent
inletdesignsandrakes.
1.2.2.1 Dam slopes
Theupstreamdamslope showeda rectangular, rake‐coveredbypass channel,with awidthof
33.3cmandadepthof8.33cm, including therakeconstruction. If the lowerrakestructure is
clogged,watercanpassthroughthisbypassandwilldischargethroughintotheoutletchannel
(seeFigure3).Thisensuresacontrolleddischargedownstreamthedam.
For the downstream face of the dam it was needed to install an adequate roughness,
correspondingtoriprapinnaturaldimensions(seeFigure4).Theinclinationof30°followsthe
requirementsofalpinfra.Thedesignofthetransitionreachbetweendamfootandstillingbasin
wasadaptedduringtheproject.
Figure2:Baseframeworkofthemodel(Iliadis,2015).
11
Figure3:Upstreamdamsurface,rakeandinletdesign. Figure4:Downstreamdamstructure.
12
1.2.2.2 Culvert
Theculvert channelwasdesignedasa sealedU‐profile,one sidewallmadeoutof transparent
acrylicplastic.Witha lengthof4.34m it reached fromthe throttle to theendof thedamand
followedtheinclinationofthedambase.Thisbasicstructureenabledtheinstallationofdifferent
culvertdesignsandfacilitatedobservationsthroughthetransparentoutlet(seeFigure10).
1.2.2.3 Inlet design
Arectangularcuttinginthedamstructure(horizontaldistanceof78cmfromtheintersectionof
theupstreamdamsurfaceandthechannelbed;widthof33.3cm)incorporatedtheculvertinlet
andthethrottlestructure.
Upstreamoftheinletahydraulicallyconvenientbottleneckwasshapedtominimizeenergylosses.
Along this narrowing the slope of the side walls was 4V:1H at the stone-pitched bottleneck
(height of 10 cm) and then transitions to the circular shaped outlet channel design. Thisdesign
wasconstructedbyshapinginsulationboardsandaddingriprap(accordingtothephysicalscale
ofthemodel)inthesectionupstreamoftherakestructure(seeFigure5).
1.2.2.4 Throttle
Thethrottlewasdesignedasverticaladjustableslide(27x24x1.2cm)infrontoftheculvertinlet
(seeFigure6).Theoverlappingdesignguaranteedasealedperformance.Ameasuringscalewith
verniersupportedthedetectionofaccurateadjustments.Fortestingdifferentthrottledesignsthe
throttlecouldbechangedeasily.
Figure5:Inletdesignandthrottle.
13
1.2.2.5 Water supply to the basin
Attheupstreamendoftheretentionbasinanadditionalbasinwithascumbafflewasinstalledin
ordertogethomogeneousinflowconditionsoverthewidthofthemodel(seeFigure7andFigure
48).
Figure6:Upstreamdamsurfacewithadjustablethrottle.
14
Figure7:Longitudinalsectionplotmodel(dimensionsincm).
15
Figure8:Planviewphysicalmodel(dimensionsincm).
Figure9:Sectionplotmodel(dimensionsincm).
16
1.2.3 Stilling basin and erosion area
Asimplesealedwoodenframeworkwithalengthof1.6mandawidthof1mformedthissection
asahorizontalbasin.Athree‐layerboardseparatedthebasinintwoparts,sothedimensionsof
the stillingbasin couldbeeasilymodified (seeFigure10).Theheightof the separationboard
followedthespecificationsofalpinfra;theheightoftheboardattheendofthemodelisbasedon
theinclinationoftheculvert.Duringtheperiodoftheoverflowinvestigation,theframeworkwas
adaptedtoassessthissectioninmoredetail.
Figure10:Stillingbasin,erosionarea andculvertstructure.
17
Figure11:Overview:physicalsclaemodelbasedesign.
Figure11showsthewholemodelincludingtheconveyorbeltintheback,thespillwaythestilling
basinanderosionarea.
18
1.3 Sensors and measurements
1.3.1 Discharge
Thepumpingcycleofourlaboratoryincludesaflowmeterbetweenthecirculationpumpandthe
Thomsonbasin.Thisflowmeter(SIEMENSSITRANSFMMAGFLOWMAG5000)informedabout
theactualdischargeinl/s,andwascontrolledbytheThomsonweir(see1.3.3).
1.3.2 Water level heights
Figure 12 shows an ultrasonic sensor ‘UC500‐
30GM‐IUR2‐V15’ (PEPPERL + FUCHS GROUP,
2014).
Six ultrasonic sensors of this type were used
duringthetests.SensorUS_1wasplacedinfront
of the rake, sensor US_5 directly upstream the
throttle. Both were set close to the ground and
whenwaterwasnotretained,fortestswithhigher
waterlevelsthesesensorswereremoved.Sensor
US_2 gave information about the water level at
filledupconditions.US_2wasinstalledontheleft
sidewhenwaterwasflowingandatthelevelofthe
left sidewall of the model (see Figure 13). Two
other sensors (US_3, US_4) were placed in the
tunnel, one at 2m and the other at 3,5m
downstreamthethrottle.
Figure13:Positionsoftheultrasonicsensors(dimensionsincm).
Figure12:UltrasonicsensorPEPPERL&FUCHS.
19
Thesensorsmeasurethedistancebetweenthebaseofthesensorandthewaterlevel(Figure14).
Knowingthedistancebetweenthefixedsensorandthegroundlevelofthemodel,thewaterlevel
canbedetermined.Theultrasonicsensorswereoperatedwith10Hz.Theresponseofultrasonic
sensors is linear with distance and independent upon the reflectivity of water (ROCKWELL
AUTOMATIONInc.,2015).
1.3.3 Thomson Weir
Thesixthsensor(US_Thomson)wasplacedabovetheThomsonbasin(seeFigure7).Theoutlet
of this steel tankhadaV‐shapedprofilewitha specifiedangle.Combinedwith theUS‐sensor,
whichshowedthewaterheight,theaccuratedischargewascalculatedtocontrolthesignalfrom
thepump(seeFigure15).
AccordingtoPREIßLERandBOLLRICH(1985),thisV‐shapehelps,tocalculatethedischarge:
815
∗ μ ∗ 2 ∗ ∗ /
With:μ 0.565 0.0087/√
Theparameters , , andμcorrespondto:
,thedischarge(m3/s)
,thegravitationalacceleration(m/s2)
,theheightofthewaterlevel(m)
μ,thedischargecoefficient
Figure14:Drawingofthemeasuredparameterwithanultrasonicsensor.
20
Figure15:DrawingoftheV‐shapedThomsonbasin(adapt.formPREIßLERandBOLLRICH,1985).
1.3.4 Height of throttle opening
Tomeasuretheopeningofthethrottleattheinletofthetunnel,avernierscalewasinstalled.One
sidewasfixedtothetopofthethrottleandthus,therulerwasmovingatthesametimeasthe
throttle(seeFigure16).Thethrottleopeningisdefinedastheheightbetweenthebottomofthe
outletchannelandthebottomedgeofthethrottle.
Figure16:Vernierscalemeasuringthethrottleopeningheightanddetailofvernierscale.
1.3.5 Volume of the bedload deposition an remobilization
Atwo‐stepprocessgeneratedthedataforbedloaddepositionvolumesintheretentionbasin.
1. In the first step the surface data was generated by using photogrammetry. For this
purpose the Agisoft PhotoScan softwarewas used. Eight targetswere attached to the
modelandreferencedtosetdimensionsinthelab(seeFigure48).Duringabedloadtest
runregularbreaksweredonetotakephotoseriesofthedepositedbedload.Thesoftware
21
automaticallydetects the targets, andgenerates a3D‐model.For thenextprocess the
modelwasexportedasTIFFfile.
2. The‘Surfer13’(GoldenSoftware)programwasusedtocomputethedepositionvolumes
of the3D‐models.Therefore itwaspossible to compare thevolumedataandvisualize
growthorre‐mobilizationofsediment.
1.3.6 Bedload transport capacity in the culvert
Sedimentwastransportedthroughtheculvertatdifferentstagesofthebedloadtests.Togetthe
informationaboutthetransportcapacity,sedimentwastrappedatthedownstreamendofthe
culvert.A0.5mm(DIN4188)sievewastakentofilterthematerialforaperiodof1minuteper
sample.Thesamplesweredriedandweighted,andanaveragevalueontheremoval‐timewas
calculatedtogettheunitkg/s.
1.3.7 Density of the bedload deposit
Fordensitymeasurementsofthesedimentasamplingring(innerdiameter:9.9mm)wasused.
Sedimentwassampledwith thesamplingringat3positions in theretentionbasin:1.2,2and
2.7mupstreamthethrottle(Position‘0’),inthemiddleofthebasin.Thesamplesweremeasured,
driedandweighed.
1.3.8 Flow velocities
Forrecordingthevelocitydistributionatthedownstream
faceofthedamandintheoutletchannelaflowmeterfrom
Schiltknecht(MC20)wasused.Thesmalldiameterofthe
impeller (1cm inner diameter) helped to measure at
smallflowheights(Figure17).Thechangedwatersurface
heightcausedbyentrappedairatthelowersectionofthe
dam, precluded flow velocity measurements based on
ultrasonicsensors.
Figure17:Flowmeter:SchiltknechtMC20.
22
1.4 Rakes
A central question for the physicalmodelingwas to develop a rake structure thatmeets the
followingrequirements.
Therakeshouldnotaffecttheflowconditionsatthethrottleinadisadvantageousway.
Woodydebrisshouldbetrapped,toavoidblockingatthethrottleandtheoutletchannel.
Smallbedloadtransportingeventsshouldpassalmostundisturbedthroughtheculvert
buttherakeshouldfilterthecoarsestfractions.
Thetechnicalpracticabilityonrealisticconditionsshouldbegiven,andthefrontshould
bemodifiableforlateradaptions.
Thus, different rakes were in
discussionandtestedduringthe
experimentstomeetthevarious
issues. The designs of Rake#2
andRake#2awere provided by
alpinfra, Rake#1, Rake#3 and
Rak#4 were developed at the
Institute of Mountain Risk
Engineering.
With the exception of Rake#1
therakebeamsweremadeoutof
especially cropped 10to10mm
aluminumH‐profiles.Otherdetailsandmostoftherequiredintersectionswererealizedby3D‐
printedcomponents(seeFigure18).TheverticalbeamsofRake#1showedaroundcrosssection
withadiameterof10mm,butontheuppersideH‐profilebeamswereplaced.
Figure18:Model:Rake#4.
23
1.4.1 Rake#1
Likeabove‐mentioned,the
verticalbeamsof‘Rake#1’
were made with round
profiles. Also the
upstreamfrontoftherake
showed a half circular
section (see Figure 21)
with a radius of
176.65cm. The distance
betweenthesinglebeams
was 2cm. The upper
beams showed a distance
of1.5cm.Onbothsidesof
the rake additional
(concrete)‐flapssimplified therakestructureandguaranteedbeneficial flowconditionsat the
throttle(seeFigure19).Thehydraulicconvenientverticalbeamsandtheenlargedsurfaceofthe
crosssectionshouldenhancehighdischargeswithoutclogging.
Figure20:Longitudinalsection:Rake#1(dimensionsinmm).
Figure19:3D‐plot:Rake#1.
24
1.4.2 Rake#2
Rake#2wasdesignedasa
simple rake following the
inclination of the dam
structure. The front
section was built of
vertical H‐profile beams,
which end 3.42cm above
the bottom.Thatdistance
correlatedwith thewater
heightof8m³/sdischarge
at this position. The
distance between the
beams was set to 1.5cm
(see Figure 22 to Figure
24).
Figure21:Planview:Rake#1.
Figure22:3D‐plot:Rake#2.
25
Figure23:Longitudinalsection:Rake#2(dimensionsinmm).
Figure24:Planview:Rake#2.
26
1.4.3 Rake#2a
The differences between
rake#2 and rake#2a
(Figure 25 to Figure 27)
were in length and
distance of the rake front
to the ground. Therefore
the rake was pushed
forward to the position
wherethelowerendofthe
rakemetadistancetothe
bottom structure of
1.5cm.
Figure26:Longitudinalsection:Rake#2a(dimensionsinmm).
Figure25:3D‐plot:Rake#2a.
27
1.4.4 Rake#3
Rake type#3 showed two
kinks, the upper one at a
height of 9,7cm over
ground, the lower one at
6cm (see Figure 28 to
Figure 30). The beams on
thefrontsideended1,5cm
above the ground. The
inclination of the flatter
middle section was 14°.
The distance between the
beamswasagainspecified
with1.5cm.Thattypewas
plannedtofilteroutwoodydebris.Thesmallheightofthefrontbeamsforcesthewoodydebris
todepositattheflat‐angledareaaboveandsoavoidclogginginthelowerparts.
Figure27:Planview:Rake#2a.
Figure28:3D‐plot:Rake#3.
28
Figure29:Longitudinalsection:Rake#3(dimensionsinmm).
Figure30:Planview:Rake#3.
29
1.4.5 Rake#4
Rake#4 (Figure 31 to
Figure 33) included two
disks to support the rake
and avoid clogging by
woody debris.
Additionally, the disks
enhance water velocities
at the rake and increase
self‐cleaning effects after
sediment deposition. The
disks were designed as
triangleswitha45°angle,
andathicknessof1.67cm
(0.5mnaturescale).Theupstreamedgeswereconstructedwithroundprofiles;thelengthonthe
basewas11.67cm(3.5mnaturescale).
Figure32:Longitudinalsection:Rake#4(dimensionsinmm).
Figure31:3D‐plot:Rake#4.
30
Figure33:Planview:Rake#4
31
2 Experiments
2.1 Hydraulic experiments
Thehydraulicexperimentsshouldansweraseriesofissuesaroundtheoutletchanneldesign,the
inletstructureandthrottleconstruction,aswellastherakestructure.Fourmaintestsetupsfor
thehydraulicexperimentsweredeterminedtodeliversufficientresults.
Thehydraulicexperimentswereoperatedwithsteadystateconditions.Thatmeans,atestneeded
toshowconstantvaluesoveralongerperiodoftime.Onlywhensteadyconditionsappeared,the
measuredvalueswereusedforevaluation.Fromtheacquiredvalues,ameanvaluewascalculated
whichcanbefoundintheresulttables.
2.1.1 Types of the hydraulic experiments
2.1.1.1 Full basin (FB) test:
Inafirststep,theparticularsetupwasrunwiththeso‐called‘fullbasin’or‘FB’test.
The retention basin was filled up with water to its top (see Figure 34). Then, the particular
dischargewassettothewatersupplypump.Now,thethrottlewasadjustedtotheaskedmaximal
flows,sothatthewaterheightintheretentionbasinstayedconstantoveraspecificperiodoftime.
Figure34:Retentionbasinat'fullbasin'conditions.
32
2.1.1.2 Maximum discharge (MD) test:
In a second step, themaximum free surface flowwithout backwater effect at the determined
throttleheightwastested.
Therefore the throttle
specifications from the ‘FB’ tests
were used and the discharge
graduallyincreasedfrom‘0’tothe
level where it showed the first
backwater effects at the throttle
(see Figure 35). This information
wasrequestedfromtheengineers,
because the retention of water
changes the flow conditions
upstreamthestructureandforthis
reasonsitalsoaffectsthebedload
transportsituation.
2.1.1.3 Normal flow (NF) test:
The‘NF‐tests’focusedondischargesbelowthe‘maximumdischarge’.Waterheightsonspecified
positionsupstreamtherakestructureweremeasured,upstreamthe throttleand in theoutlet
channel.Thatsetupprovidedinformationontheeffectsofdifferentraketypesandfortheannual
flows.
2.1.1.4 Overflow (OF) test:
Forapossibleoverflowevent,a318m³/sscenarioinnaturalscalewasrequested.The318m³/s
scenario(64.5l/sinthemodelscale)wouldleadtoanovertoppingoftheretentionstructure.As
ourmodelwas limited to awidth of 1m andour pump to 50l/s, itwasneeded to adapt the
experiments.According toaproposalofalpinfra,webuilt inanarrowing to75.4cm(22.6m)
widthatthedownstreamfaceofthedam.Operatedwithadischargeof48.7l/s(240m³/s)the
setupmatchesthesameheightoftheoverflowingwateratthedamcrest.The‘OF’‐experiments
investigatedtheflowvelocitiesalongthedownstreamfaceofthedam,theflowconditionsinthe
stillingbasin, thebedloadbehavior in the stillingbasinand theerosionarea. Someadditional
installations(chuteandbaffleblocks)were tested.Apart fromthevelocitymeasurements, the
effectsweredocumentedwithpicturesandvideos.
Figure35:Throttleatmaximumdischargeconditions.
33
2.1.1.5 Classification
ForabetterorientationaTest‐IDsystemtonumberthesingleexperimentswasused.Thecode
containsaseriesofnumbersandlettersdescribingthetestsetup.
2.1.2 Design of the outlet channel
Intheprogressofprojectplanning, thecrosssectionof theoutletchannelwasoneof the first
issuesthephysicalmodellingshoulddealwith.Theideawastoconstructanoutlettunnel,which
canbeusedforthedischargeaswellasfortransportofdepositedbedloadmaterialbytrucks.
Therefore theoutletchannelhad toprovidea tunnelwithappropriatedimensionsof5.5m to
5.5mforthetrucksandanadditionaladischargechannelbelow.
Therefore, a squared U‐profile basic structure with the maximum required dimension was
installed(Figure10).Lateron,thechannelprofilestotestwereinstalled.Athrottlewasfixedat
thechannelinlet,toreducethecrosssectionalareaaccordingtotherequireddischarge.Forthe
tests,thethrottlewasadjustableinitsheightbyathreadedrod,tofindtheadequateadjustment
bytesting(seeFigure6orFigure16).
Pos1: H‐(for‘hydraulics’)testwithonlywater;BL refersto‘Bedload’.
Pos2: E‐theoutletchannelhasarectangularprofile;Rincludesaroundprofile.
Pos3: OO‐fornorake;RaforRake#1;RbforRake#2;RcforRake#3;RdforRake#4;Refor
Rake#2a.
Pos4: 06,08,10,…,50,60or100forthevalueofthedischargetested(m³/s),
Pos5: FBforthesimulationtype‘fullbasin’;MDforthesimulationtype‘maximaldischarge’,
NFfor‘normalflow’tests.
Pos6: 001showsthesequencenumberofthetest.Ifatestwasrepeated,thenumberrose.
Examples:
The filenameHE0050FB_001means: it isahydraulic testwith therectangularprofile intheoutlet
channel,withoutrakeandthetypeofsimulationis‘fullbasin’.Itisalsothefirsttest.
HRRd06NF_002:hydraulictestwiththeroundoutletchannelprofile,rake#4wasinstalled,adischarge
of06m³/srespectively1.22l/swasused.Itwasa‘normalflow’testtypeandthesecondtestwiththis
setup.
34
2.1.2.1 Test with rectangular outlet
channel
Following the specifications of alpinfra, a
rectangular channel crosssection (seeFigure36)
wastestedwith45,50,60and100m³/s.Thegoal
was to find the particular throttle opening to
achieveamaximumdischargeof45m3/sunderfull
storagecondition.(‘fullbasin’:compare2.1.1.1)In
a second step the maximum free surface flow
without a backwater effect for each throttle
adjustment was tested. (‘maximum discharge’:
compare2.1.1.2)
InTable2theFroudeconversionfortherequireddischargesisshown.
Table2:Froude‐scalingthespecifieddischarges.
Q real (m³/s) Q model (l/s)
40 8.11
45 9.13
50 10.14
60 12.17
100 20.29
Afterrunningthe‘fullbasin’and‘maximumdischarge’experimentswiththerectangularoutlet
channel,theresultsgiveninTable3canbeshown.Figure37showsthecorrespondingthrottle
openingheights.
Table3:Resultsofhydraulicexperimentswithrectangularoutletchannel.
Rectangular outlet channel
Model condition Real conditions
Discharge Opening height: Throttle
Maximum discharge
DischargeOpening height: Throttle
Maximum discharge
l/s cm l/s m³/s m m³/s
9,13 3,83 2,80 45,00 1,15 13,80
10,14 4,48 3,30 50,00 1,45 16,27
12,17 5,49 3,90 60,00 1,65 19,23
20,29 6,89 7,00 100,00 2,07 34,51
Figure36:drawingoftheoutletchannelsection(dimensionsincm).
35
Throttleopeningheightfor29mpressureheadat
a) 45m3/s
b) 50m3/s
c) 60m3/s
d) 100m3/s
2.1.2.2 Tests with round design of the outlet channel
The Institute ofMountainRiskEngineering
suggestedaroundchanneldesignforbetter
sedimenttransportonlowerdischarges(see
Figure 38). The Town of Canmore reduced
the maximum discharge to 45m³/s. Thus,
‘full basin’ and ‘maximal discharge’
experiments were run with the specified
maximum discharge only. A roughness
correspondingtoasteelsurfacewaschosen
for these investigations to protect the
originaloutletchannelprofilefromabrasion
by bedload transport. Furthermore, the
smoothsurfacepreventssedimentdeposition.
Forthe‘fullbasin’testsawaterheadof29.85m
(inrealscale)at the loweredgeof thethrottlewasaskedbyalpinfra.Forthiswaterheadthe
experiment determined a throttle opening height of 4.34cm ‐ 1.3m in real dimensions. The
Figure37:Differentthrottleopeningheights(dimensionsincm).
Figure38:Roundchannelcrosssection(dimensionsincm)
36
‘maximum discharge’ test showed a discharge of 2.75l/s, which means 13.6m³/s for real
conditions.
Thefollowingexperimentswereallrunwiththerounddesignoftheoutletchannel.
2.1.3 Effect of throttle design
In anext step, effectsof different throttledesigns shouldbe shown.To this end, two typesof
throttleswere compared, inwhich themain designwas the same, but the lower edge shape
changed(seeFigure39).Thetest‐IDwiththeadditional‘a’inTable4,showstheexperimentswith
the45°angleshapedthrottle.
As it can be seen in Table 4, the throttle
openingheight varied0.5mmand led to a
differenceof3.4mmofthewaterheight in
the retention basin. Considering the
accuracy of the single measurements and
the period of several hours to get stable
conditions the presented deviations are
negligible. It has to be mentioned, that a
hydraulically optimized design would lead
toanoutletwithasmalleropeningheight.In
ordertomaximizethe‘maximumdischarge’
that does not result in backwater effects, a
hydraulic unfavorable design is preferable.
Thisisthereasonwhynootherdesignsliketaintergatesorrollinggatesweretested.
Table4:Effectsof2testedthrottledesigns.
US_2 Pump Throttle
opening height Square area
[mm] [l/s] [cm] [cm²]
HR0045MD_001 2,76 4,34 33,04
HR0045MDa_001 2,75 4,39 33,55
HR0045FB_001 969,29 9,14 4,34 33,04
HR0045FBa_001 965,88 9,14 4,39 33,55
Figure39:Comparedthrottledesigns(dimensionsincm).
37
2.1.4 Effect of rake designs
Themodelrunsshowedthatwithafilledbasinthedifferentraketypeshavenoeffectontheflow.
Thus,wefocusedontestsat‘normalflow’(compare:2.1.1.3)conditionstoobservetheinfluences
ofdifferentrakes.Thedischargewassetinstepsof2m³/sinnature,from6to14m³/s(see
Table5).
Table5:ConversionafterFroude:Naturetomodel.
Theheightoftheflowwasmeasuredat3Positions:
Upstreamoftherakestructure(pos:‐98).Dependingontheparticularrake,thedistance
betweenrakestructureandmeasurementchanges.
10cmupstreamthethrottle(pos:‐10).
Intheoutletchannel,200cmdownstreamthethrottle(pos:200).
This setup specified the hydraulic properties for the 5 tested rake types. Figure 40 shows a
comparisonofallraketypesatdifferentdischarges.
Nature Model
m³/s l/s
6,00 1,22
8,00 1,62
10,00 2,03
12,00 2,43
14,00 2,84
38
Figure40:Heightsoftheflowat3positionsalongthemodel.The‘0’‐Lineshowsthepositionofthethrottle.Position‘‐98’isjustupstreamtherakestructure,position‘200’displaysthedatafromtheUS‐sensorintheoutletchannel.
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
50
52
54
56
‐115 ‐95 ‐75 ‐55 ‐35 ‐15 5 25 45 65 85 105 125 145 165 185 205
Flow
height[mm]
Distancefromthrottle[cm]
Flowheights@differentrakes
Rake#1@06cms Rake#2@06cms Rake#2a@06cms Rake#3@06cms Rake#4@06cms WithoutRake@06cms
Rake#1@08cms Rake#2@08cms Rake#2a@08cms Rake#3@08cms Rake#4@08cms WithoutRake@08cms
Rake#1@10cms Rake#2@10cms Rake#2a@10cms Rake#3@10cms Rake#4@10cms WithoutRake@10cms
Rake#1@12cms Rake#2@12cms Rake#2a@12cms Rake#3@12cms Rake#4@12cms WithoutRake@12cms
Rake#1@14cms Rake#2@14cms Rake#2a@14cms Rake#3@14cms Rake#4@14cms WithoutRake@14cms
39
Thehighestdeviationscanbefoundinthevaluesatposition‘‐98’upstreamtherakes(Table6).
These are caused by the particular construction reducing the discharge section. Rake#2a and
Rake#3showedthebiggestbackwatereffectsatdischargescorresponding to12and14m³/s.
Thesewerealso theones tohavehorizontally installedbeamson the lowest level (cf.1.4).At
position‘‐10’and‘200’,thedeviationsshowvaluesbelow1.7mm,whichiswithintheaccuracyof
ourmeasurements.
Table6:Maximumdeviationofthewaterheightbetweendifferentrakesatparticulardischarges(valuesinmm).
Discharge Position to throttle
‐98,00 ‐10,00 200,00
06 m³/s 1,67 1,51 0,91
08 m³/s 2,55 1,56 0,70
10 m³/s 1,40 0,35 0,90
12 m³/s 2,74 1,64 1,25
14 m³/s 2,83 1,52 1,11
2.1.5 Effect of the inlet design and positioning of the rake
Eveniftherakestructurehasalittleimpactontheflowconditions,theshapeoftheinletandthe
distancebetweenrakeandthrottledo.Thisimpactwasobservedonconditionswithoutretention
ofwateratthethrottle,upto13.6m3/sinrealscale,respectively.
Inoursetup theoutlet channelwasextended30cmupstreamasaparallelchannel,before it
opened up towards the basin. The funnel leading into the parallel channel was hydraulically
optimized(seeFigure8orFigure19toFigure33)toguidethewatertothethrottle.
Thegreatestbackwatereffectswereobservedinthelastpartofthefunnel,justupstreamofthe
startingpointof theparallelchannelprofile.Theparallelprofileresulted inan increased flow
velocity.Ahighervelocitymeanslowerflowdepth(seeFigure41).So,themaximumdischarge
canbeincreasedbyoptimizingtheareaofacceleration,upstreamthethrottle.
Iftherakestructure‐independentfromthedesign‐wasinstalledtooclosetotheareaofflow
acceleration,firstbackwatereffectsatthethrottlecouldbeobservedatsmallerdischarges.
Forthecaseofanemptybasinahydraulicjumpwasobservedupstreamtherake.Dependingon
thedischarge itwasobservedat locationsbetweenabout205cm(at14m3/s)and150cm(at
6m3/s)upstreamthethrottle.Withapartiallysedimentfilledretentionbasintheseeffectswere
notobservableanymoreduetotheincreasedroughnessofthedepositedbedloadmaterial.
40
2.1.6 Length of the overfall
Figure42showsasketchofthenappeatthechanneloutlet.Thedistances(valuesinnaturalscale)
weremeasuredattheintersectionoftheupperandlowernappeandahorizontallineattheheight
ofthedownstreamboundarywallcrestofthestillingbasin.Themeasurementsweredoneon‘full
basin’conditions.ThevelocityshowninFigure42,wascalculatedbythewaterheightintheoutlet
channel (US_4 showed 1.23m water height, diameter of the outlet channel 3,05m) and the
discharge(45m3/s),anditwasmeasuredbyaflowmeteraswell(see1.3.8).
Calculationforthevelocity:
Theparametersv,QandAcorrespondto:
v,velocity(m/s)
Q,discharge(m3/s)
A,flowarea(m2)
ThecalculatedandmeasuredvelocitywasscaledfollowingthescaleratioafterFroude(see1.1).
Figure41:Inletdesignupstreamthethrottle.
41
Figure42:Sketchofthelongitudinalsectionofthenappeat'fullbasin'conditions.
2.1.7 Discharges at different storage levels
Figure43showsthecorrelationbetweenagivendischargeandthewaterlevelintheretention
basin.Theopeningheightatthethrottlewas1.3minnaturalscale.Themeasurementsweremade
3m (10cm in model scale) upstream of the throttle (position of the sensor US_5), so that
backwaterdidnotaffectthemeasurements.Thegivenvaluesrepresentthewatersurfaceheight
atthethrottle,measuredfromtheoutletchannelbottom.Thedatawererecordedatsteadystate
conditions.
Atransitionfromfreeflowtopressureflowoccursat13.6m3/sinnaturalscale.However,this
flowratecanoccuraseitherfreefloworpressureflowunderdifferentcircumstances.
Withrisingstagethewaterheightforarateof13.6m3/sisabout1.3m(naturalscale)underfree
flowconditions.Thefree flowcontinuesuntil the flowrateexceeds13.6m3/sor if the flowis
disturbed by, e.g. a tree reaching the rake. In the latter case backwater effects occur and the
storagelevelreachesaheightof4m(withasteadyflowof13.6m3/s).Onlyiftheflowleveldrops
belowthisrate,thestorageleveldecreases.
Ifthebasinisfilledandtheinflowdecreasesto13.6m3/sthestorageheightremains4muntil
theflowcontinuestodrop.
42
Figure43:Watersurfaceheightsatdifferentdischarges.
2.2 Experiments with woody debris
Teststoobservetheeffectsofthedifferentrakedesignswereperformedinordertoanalyzetheir
abilityofretainingwoodydebris.4typesofrakeswereusedforthistestbatch(Rake#1,Rake#2a,
Rake#3,Rake#4).Rake#2wasexcluded,becauseofitshighpermeability,duetothehighbasal
outletdesign.
2.2.1 Test setup
A discharge of 2.43l/s (12m³/s in natural scale) guaranteed a maximum of woody debris
transport,withoutbackwatereffects.Thethrottleopeningwith4.34cminthemodelremained
equaltothemaximumdischargeconditionsdownstreamthedam.
Roundbeechwoodstickswithalengthof140mmwasusedtosimulatewoodydebris.Thesticks
were split up in three different diameters: 6mm (‘S’ for small), 11mm (‘M’ formedium) and
15mm(‘L’forlarge).Accordingtothelowlevelflowconditionsupstreamoftherakes,thewoody
debriswassupplied110cmupstreamthethrottle(‘0’‐positionseeFigure13)inthemiddleofthe
channel.Foratestscenario4bundlesofstickswereused,including4S,4Mand2L.Forarandom
distributionofthewoodsticksoverthewholewidthofthechannelabundleofstickswasreleased
at40cmheight,stickbystickinaverticalorientation.Thereforeaspecifiedorder(M‐S‐L‐M‐S‐M‐
S‐M‐S‐L)inasequenceofaboutonesecondwasused.Duringonetest,4bundlesinasequenceof
0
5
10
15
20
25
30
35
0 5 10 15 20 25 30 35 40 45 50
height[m
]
discharge[m3/s]
Dischargesatdifferentstoragelevels
freesurfaceflow
flowunderpressure
43
aboutoneminutewerebroughtin.Besidesthenumberandtypeofthestickspassingtheinstalled
rakewasrecorded.Foreachrakethetestwasrepeated5times.
Drybeechwoodhasasimilardensityasgreenspruce.Therefore,thesticksweredriedbetween
thesingletest‐runs.Table7showsthemeannumberofsticksandtherelatedstandarddeviation
thatpassedtherakefortheabove‐describedsetup(averageof5testsperrake).
Table7:Meannumberofwoodpiecesthatpassedtherake.
All woody debris that passed the rake was transported through the outlet channel without
depositionintheoutletchannelorclockingofthethrottle.
2.2.1.1 Rake#1
Onaverage4.8sticksoutof40passedrake#1.Itistheonlyraketype,werewoodofthecategory
Lpassed.AtypicalpatternofhowthewoodisretainedinfrontoftherakeisshowninFigure44.
.
Figure44:Woodydebrisinfrontofrake#1.
Woody Debris S M L Sum SML
Rake#1 Mean 1.2 2.6 1 4.8
Stan. Dev. 2.17 2.30 1.00 4.55
Rake#2a Mean 2 1.4 0 3.4
Stan. Dev. 2.35 1.67 0.00 3.85
Rake#3 Mean 0.8 0.8 0 1.6
Stan. Dev. 0.84 1.10 0.00 1.82
Rake#4 Mean 0.4 0.6 0 1
Stan. Dev. 0.55 0.55 0.00 0.71
44
2.2.1.1 Rake#2a
Onaverage3.4sticksoutof40passedrake#2a.Atypicalpatternofhowthewoodisretainedin
frontoftherakeisshowninFigure45.
Figure45:Woodydebrisinfrontofrake#2a.
2.2.1.2 Rake#3
Onaverage1.6sticksoutof40passedrake#3.Atypicalpatternofhowthewoodisretainedin
frontoftherakeisshowninFigure46.
Figure46:Woodydebrisinfrontofrake#3.
45
2.2.1.3 Rake#4
Onaverageonly1.0stickoutof40passedrake#4.Atypicalpatternofhowthewoodisretained
infrontoftherakeisshowninFigure47.
Figure47:Woodydebrisinfrontofrake#4.
2.2.2 Effect of rake designs
Thedriftwoodexperimentsshowthatalltypesofrakesfiltertheamountofdriftwood,butrake#4
seemstobethemosteffectiveforthemodeledscenario.Ithastobenoted,thatthesetestshave
been performed with an empty basin (no bedload deposition) and at a discharge, where no
backwater effects are present. Rakes#2a, 3 and 4 are evenmore effective,when the basin is
alreadyprefilled,becausethenthereisnomoreclearancebetweenthegroundandtherake.
2.3 Experiments with bedload transport
2.3.1 Setup
Forthebedloadexperiments,thewaterandsedimentsupplyforthemodelwasredesigned.The
channelstartedwithanarrow40cmwideand48cmlongchannel,followedbyawideningwith
an angle of 26° on both sides. This installation ensured a constant sediment transport. The
installedconveyorbeltprovidedthebedloadmaterialjustabovethemodel.Inthiswayconstant
bedloadtransportcouldbeguaranteed(seeFigure48).
46
Thesedimentthatpassedtherakewastransportedeasilythroughtheoutletchannel(seeFigure
49). The round channel profile and the higher velocity in the parallel profile ensure that the
materialisflushedthroughandpreventlogjamsatthethrottle.
Figure48:Retentionbasinwithtargetsforphotogrammetryandsupplyinstallationforthebedloadexperiments.
Figure49:Sedimenttransportafterrakestructure.
47
Forthegrain‐sizedistributionoftheaddedsediment,transectbynumberanalysesprovidedby
theTownofCanmoreatCougarCreekwereevaluatedafterFehr(1987)anddownscaledforthe
physical scale of themodel. The finest parts could not be considered for the physicalmodel,
becauseofthedifferentbehaviorofcohesivematerial.Acomparisonofthedownscaledgrain‐size
distributionoftheCougarCreekandthesedimentmixtureusedfortheexperimentsisshownin
Figure50.Thematerialhasadensityof2.65tons/m³.
Figure50:Comparisonofthedownscaledgrain‐sizedistributionandthesedimentmixtureusedfortheexperiments.
2.3.2 Experiments
Different scenariosweremodeled. First, the basinwas filledwith constant discharge (12m3/s
naturalscale)andbedloadtransport(0.14m³/snaturalscale)untilthebedloadmaterialreached
the rake. Then stereoscopic pictures had generated an elevation model. The discharge was
increasedstepwise, firstwithand thenwithoutbedloadaddition.Aftereachstepanelevation
model was generated and during the tests, sediment was trapped at the outlet of the outlet
channelandevaluatedfor1‐minuteintervals.Figure51toFigure58showthebedloadtransport
experiments.Thewaterdischarge(blueline)andthesedimentinput(purpleline)aswellasthe
sedimentoutput (magentabars) are shown.Thedepositionvolume in thebasinbasedon the
volumetric analysis is shown by hillshades. The related deposition volumes are shown in the
diagrams.
48
2.3.2.1 Experimental run BL4
Thisrunmodeledaprefilledbasin(untilT=50min),followedbytwosmallerfloodswithadditional
bedload.Thesequenceendedwith5floodpeakswithoutsedimentinputtoinvestigatetheself‐
emptyingbehavior(alldischargevaluesaregiveninFigure 52). For this experimental run all
discharge rates could pass the throttle without backwater effects. After about 115 minutes
sedimentpassedthroughtheoutletchannel.Allsedimentthatpassedthethrottlewastransported
throughthedam.Duringthewholeexperimentnomaterialwasdepositedintheoutletchannel.
Figure51showsthebehaviorofthedepositedmaterial.UntilthetimeT=100minthebasinwas
filled,thenerosionwasthedominantprocess.
Figure51:HillshadesofthebedloaddepositionatdifferenttimesforthebedloadtransportexperimentBL4.
49
Figure52:WaterandsedimentdischargeforthebedloadexperimentBL4.
2.3.2.2 Experimental run BL5_6
This runmodeledaprefilledbasin (untilT=60min), thenapeak flowwithadditionalbedload
followedbyahigherfloodevent.Anotherpeakflowwithadditionalbedloadpursuedthehigher
flood.Duringthehigherfloodbackwatereffectsatthethrottlewereobserved.Duringthistimeno
materialwastransportedthroughtheoutletchannel.Whenthedischargewasreducedagainno
morebackwatereffectswerepresent.Atthisstagesediment(T=250min)transportthroughthe
outletchannelstartedagain.Allsedimentthatpassedthethrottlewastransportedthroughthe
dam.Duringthewholeexperimentnomaterialwasdepositedintheoutletchannelanddeposition
wasthedominantprocess(compare:Figure55and Figure56).
AtthetimeT=150minbedloadmaterialaccumulatedinfrontoftherakeandthelevelofsediment
wasrising.Materialwasthendepositedbetweentherakeandthereachabovethethrottle.
50
This ledtoslightlyreduced ‘maximumdischarge’conditionsresulting inbackwaterconditions
(seeFigure53).Duetotheaccelerationatthethrottle,thethrottleitselfwasnevercloggedduring
theexperimentalruns(seeFigure54).
Figure55:HillshadesofthebedloaddepositionatdifferenttimesforthebedloadtransportexperimentBL5_6.
Figure53:Bedloadtransportthroughthethrottlereduces'maximumdischarge'.
Figure54:Throttleaftersuddenlystoppeddischarge.
51
Figure56:WaterandsedimentdischargeforthebedloadexperimentBL5_6.
2.3.2.3 Experimental run BL7
Therunmodeledaprefilledbasin(untilT=60min);thenashortpeakwithadditionalbedload,
followedbyasmallerpeakwithoutsedimentinput.Thiswasrepeatedthreetimes.Duringthe
short,higherpeaks,thebackwatereffectsatthethrottlewereobservedwithnosedimentpassing
the structure. The longer, lower peaks remobilized the depositedmaterial. All sediment that
passedthethrottlewastransportedthroughtheretentionstructure.Duringthewholeexperiment
nomaterialwasdepositedintheoutletchannel.
Figure57showsthebehaviorofthedepositedmaterial.Duringthefillingphase
andthehighdischargephasesdepositionwasthedominantprocess.Duringthephaseswithlower
dischargeerosiontookplaceinthebasin(seeFigure58).
52
Figure57:Hillshadesofthebedloaddepositionatdifferenttimesforthebedloadtransportexperiment BL7.
53
Figure58:WaterandsedimentdischargeforthebedloadexperimentBL7.
2.3.2.4 Effects in the stilling basin
Thebehaviorofwaterandsedimentinthestillingbasinwasdocumentedwithphotographs.
Thereweresomecharacteristicscenariostoobserve:
Discharges between 0 and 2.8l/s (14m³/s) delivered bedloadmaterial to the stilling
basin,whichwas thendeposited.Thehigherdischargesof this rangealso remobilized
materialinthestillingbasin,incaseofprefilledconditions.(compareFigure59andFigure
60)
54
When the discharge exceeded 2.8l/s, no bedload arrived at the stilling basin due to
backwatereffectson theother sideof the structure.The increaseddischargecauseda
remobilizationofmaterial(seeFigure61).
Figure59:DepositedMaterial. Figure60:Depositingandremobilizingmaterial.
Figure61:Remobilizingmaterialwithoutsedimentsupply.
Figure62:Dischargeof2.5l/s(12m³/sinnature). Figure63:Dischargeat'fullbasin'conditions.
InFigure62theflowbehavioratadischargeof12m3/sisshown.Bedloaddepositiontakesplace
in the not prefilled stilling basin. Figure 63 shows the same scenario, but under ‘full basin’
55
condition.Thewateroftheoutletchannelsplashagainstthedownstreamwallofthestillingbasin
andnobedloadtransportcanbeobserved.
2.4 Overflow scenario
For the overflow experiments, the downstream face of the dam structure was installed (see
chapter2.1.1.4).Severaldifferentsetupsweretested,including:
flowdividersattheintersectionoftheembankmentdamandtheoutletstructurefora
ventilationofthechannel;
baffleblocksonthedownstreamboundaryofthestillingbasintodissipateenergy;
chuteandbaffleblocksatthedamfoot,toinitiateahydraulicjumpclosetothedam;
differentheightsofthedownstreamboundarywallofthestillingbasin;
anddifferentdimensionsofthebasin.
2.4.1 Velocity distribution
Inorder togetavelocitydistributionover thedownstreamfaceof thedam(seeFigure64),a
rasterofmeasuringpoints,regularlyspreadover theareawasused.Themeasuringwasdone
using a flowmeter (see Figure 17 and Figure 65). At the lower quarter section of the dam
entrappedairconditionsoverthewholewidthofthedamfacewereobserved.Figure64shows
themeasuredvelocitydistribution.
56
Figure64:Measuredvelocitydistribution. Figure65:Velocitymeasurements@downstreamdamsurface.
2.4.2 Stilling basin
Figure66andFigure67showplotsofthestillingbasin,containingtheinstalledchuteandbaffle
blocks(grey).Whilethedamconstructionendedwiththeoutletofthechannelforpreviousmodel
runs,itwaselongatedfortheinvestigationswithoverflow(lilacinFigure66).Hence,thefootof
thestructurewaslocatedinthestillingbasin.Partsofthechuteandbaffleblockswereintegrated
inthestructure.
Figure66:Longitudinalsectionofthestillingbasin(dimensionsincm).
57
Figure67:Groundplotofstillingbasin,includingchuteandbaffleblocks(dimensionsincm).
Theeffectoftheblockswastheinitiationsofadirecthydraulicjump(seeFigure68),whereasthe
testswithoutblocksresultedinanelongatedhydraulicjump(seeFigure69).
Figure68:Stillingbasinwithoutchuteandbaffleblocks.
58
InFigure70itispossibletoseetheabove‐mentionedsetupat‘fullbasin’conditions.Inthiscase,
thechuteandbaffleblockstructureisnoteffectiveandthemainflowsplashesinthebasinand
againstthedownstreamboundarywall.Figure71showsthemodelon‘overflow’conditions;the
chuteandbaffleblocksareactivatedresultinginadirecthydraulicjump(seeFigure71).
Figure70:Stillingbasinon'fullbasin'conditions. Figure71:Stillingbasinon'overflow'conditions.
Figure69:Stillingbasinwithchuteandbaffleblocks.
59
Experiments, where the stilling basin was prefilled with bedload material showed, that the
sedimentwaswashedoutduringtheprocessoffillingtheretentionbasin(seeFigure72).While
runningthe‘overflow’conditions,mostofthesedimentwasremobilized,andalittleremainedin
avortex.
Behindtheretentionstructuresedimentationpatternswereobservedduringtheemptyingofthe
basinattheendofthe‘overflow’scenario.Theremainingmaterial,whichwasnotflushedoutof
thestillingbasin,wasrelocatedtothesidesoftheretentionbasin(seeFigure73).
Figure72:Startingatestwithprefilledstillingbasin. Figure73:ErosionofSedimentaftera'overflow'test.
60
2.5 Investigations on the diversion tunnel
Asecondoptionforabottomoutletofthedebrisfloodretentionstructurewasinvestigatedwithin
the detailed design phase. This option includes amined diversion tunnel leading through the
bedrockontheleftsideofthestructureincombinationwiththespillwayasdefinedinthebase
design.
Thephysicalscalemodelwasmodifiedtotestthehydraulicsituationinthetunnel,includingsuper
elevation of the flow and impacts for the design of the aeration system. The scope of work
included:
Investigations on the required throttle opening height for the design of the diversion
tunnel.
Determinationofthemaximumfreesurfaceflowforthechangeddesign.
Velocitydistributionalongthelongitudinalsectionofthediversiontunnel.
Determinationofsuperelevationinthetunnel.
Investigationsonthebehaviorofthesedimenttransportinthediversiontunnel.
2.5.1 Setup
Themodelasexplainedabovewasmodifiedforthediversiontunnel.Becausethediversiontunnel
modelwasnotintegratedinthebasemodel,thesetupandmeasuringmethodisdescribedinthis
chapter.
Thegivenspecificationsforthediversiontunnelinnaturalscalewere:
Aninnerdiameterofthediversiontunnelof4.5m.
Aninclinationof2.7%overthelongitudinalprofileofthetunnel.
Anarcradiusofthetunnelof86matthecenterofthediversiontunnel.
Atunnellengthof150m.
Thesamethrottleshapeasforthebasedesignwasusedforthetunneloptionwiththe
loweredge in thehorizontalposition.Theopeningunder the throttle leads to a semi‐
circularcrosssection.
Thestoragelevelstaysthesamewith29.85mwaterheadattheloweredgeofthethrottle.
Amaximumdischargeat‘fullbasin’conditionsof45m3/s.
Forthephysicalscalemodelahorizontalplatformwasbuiltonwhichatransparentflexibletube
wasplacedinthespecifieddimensionsandadjustment(seeFigure74).
61
Fromtheintermediatebasinatubingtransportedthewatertothediversiontunnel(flexibletube)
withthethrottleinstalledinsideattheupstreamend(seeFigure75).Tubesforpressureheights
wereconnectedtoobserveandcontrolthepressureheight.Thediversiontunnelstructurewas
fixedonasupportingprofilewithaninclinationof2.7%ontheplatform.Figure76showsaplan
viewofthetunnelmodel.
Figure76:Planview:diversiontunnelmodel(dimensionsincm).
Figure74:Platformandflexibletubeofthediversiontunnelmodel.
Figure75:Watersupplytothediversiontunnelmodel.
62
2.5.2 Hydraulic investigation
2.5.2.1 Throttle opening height
Forthehydraulicinvestigations,a‘fullbasin’experimentwasperformedtodeterminethespecific
throttleopeningheightforthisdesignforastoragelevelof29.85minnaturalscale(99.5cmin
modelscale).Thetestresultedinathrottleopeningheightof3.7cminthemodel(1.11mnatural
scale).
Figure77:Crosssectionofthediversiontunnelmodelatthethrottle(undefineddimensionsincm).
2.5.2.2 Maximum free surface flow
The opening area at the throttle changed from 33.15cm2 in the previous model to 33.9cm2
(2.98m2to3.05m2naturalscale).Theeffectofthisdeviationinthemodeliswithinthemeasuring
tolerance.Thus,itisassumedthatthemaximumfreesurfaceflowwillbethesameforthebase
designandthediversiontunnel,aslongastheinlethasthesameinclinationandhydraulically
convenientshape.
2.5.2.3 Super elevation
Forthesuperelevationinvestigations,thedischargeinthemodelwassetto9.13l/s(45m3/sin
naturalscale).Thetransparenttubeallowedtotracethewaterheightatthelongitudinalsection
at the innerandouterradiusof thediversiontunnel.Thepictures inFigure78showthe flow
conditionatthespecificdischargesatthepositionofthehighestsuperelevation.Thesocreated
linesweremeasuredandprojectedtothecenterradiusofthetunnel,ascanbeseeninFigure80.
63
Atsteadystateconditionswithadischargeof9.13l/smodelscale(45m3/snaturalscale), the
pointofthehighestsuperelevationwasreachedat88cmdownstreamofthethrottleinthemodel
(26.4mnaturalscale).Laterintheflowthesuperelevationdecreased.At175to214cm(52.5to
64.2m innaturals scale)downstreamof the throttle the super elevationwas about zero, and
increased again to a secondpeak at 262cm (78.6mnatural scale) and a third one at 398cm
(119.5mnaturalscale)downstreamofthethrottle.Thevaluesforthispeaksinnaturalscaleare
showninTable8.
Table8:Valuesforthethreepeaksofthesuperelevationinnaturalscale.
Positiondownstreamofthethrottle[m]
Waterheightattheouterradius[m]
Waterheightattheinnerradius[m]
Superelevation[m]
26.3 3.5 0.4 3.1
78.7 3.2 0.6 2.6
119.5 2.4 0.9 1.6
Figure78:Thepointwiththehighestvalueofsuperelevationsatthestateddischarges(naturalscale).
64
2.5.2.4 Energy heights
Experiments to investigate the energy heights in the diversion tunnelwere run at ‘full basin’
conditions(45m3/sdischargeinnaturalscale)togetinformationabouttheworstcasescenario.
Observations on the hydraulic conditions in the tunnelwas done at 16 locations. Thesewere
locatedatthemainpointsofinterest,likethehighestandlowestpointsofthesuperelevation,the
upstreamendofthetunnel,directlyatthethrottle,upstreamofthethrottleandatthehalfdistance
inbetweenthepointsofthehighestandlowestsuperelevation.Themeasuringpositionsofthe
tunnelmodelareshowninFigure76.
Attheselocationsthewaterheightsweremeasuredbyametalstickmeasuringthedistancefrom
theupperedgeofthetunneltothewatersurfaceunderdifferentangles.Togaintheinformation
aboutthewatersurface,thesedatawereimportedtoAutoCADandprocessedtoseethedifferent
formsofwatersurface.Thepointsof thehighestand lowestwaterelevationareshowninthe
upperdiagramofFigure80.Thecorrespondingflowarea(comparabletoflowconditionswithout
superelevations)wascalculatedtodeterminethedifferentvelocitiesandpressureheights.
AfterBernoullithetotalEnergyheadEcanbecalculatedforeverymeasuredcross‐section:
²2
Wherezistheelevationofthechannel,yistheflowdepthandv²/2gisthevelocityheadwithv
beingthevelocity(seeFigure79).
65
Figure79:Energylineforopenchannelflow(fromCIVE24002008).
With increasing distance from the throttle itwas possible to observe decreasing velocity and
energyheight(seelowerdiagramatFigure80).
Table9showsthecalculatedvelocityforthecertainpositions.AscanbeseeninTable9andFigure
80 (Energy grade line diagram) there are rising values at the positions of the highest super
elevations.Thiseffectcanbeattributedtoentrappedair,whichmayfalsifythemeasurementat
thispositions.
Table9:Velocitydistributionatthelongitudinalsectionofthediversiontunnelinnaturalscale.
Distance from throttle [m] Calculated velocity [m/s]
‐3 2,83
0 24,61
6,049 22,00
16,158 19,31
26,268 19,85
43,931 17,36
61,594 15,57
69,020 14,90
76,446 15,58
89,466 14,25
102,486 14,09
109,727 14,18
116,969 14,43
130,798 12,54
144,628 12,30
66
Figure80:Diagramincludingcrosssections,superelevationandtheenergygradelinesatthelongitudinalprofileofthediversiontunnel(valuesinnaturalscale).
67
2.5.3 Sediment transport investigation
Toexploreapossiblesedimentdeposition in thediversiontunnel,experimentswithsediment
weremade.Thebasedesignexperimentsshowedamaximumsedimenttransportof0.032kg/s
in model scale (see Figure 58), what correspond to 0,06m³/s in natural scale. For the
investigationsonthediversiontunnelmodelthis0.032kg/swereusedfortestswithdischarges
from1.2to9.13l/s(6to45m3/snaturalscale):Thegrainsizedistributionofthesedimentwas
thesameasinthe‘experimentswithbedloadtransport’,theinputpositionwasjustdownstream
ofthethrottle.
The experiments showed that all the sediment was transported through the tunnel and no
sedimentationwithinthetunnelwasregisteredatalltesteddischarges.Figure81andFigure82
showthesedimenttransportattheendofthetunnelatthestateddischarges.
Figure81:Sedimenttransportat6m3/snaturalscale.
Figure82:Sedimenttransportat14m3/snaturalscale.
68
3 Conclusions and Recommendations
3.1 Hydraulic experiments
Withthe ‘fullbasin’experiment,anthrottleopeningheightof4.3cm,respectively1.3minreal
scalewasdeterminedfortheroundchanneldesignwithandiameterof3minrealscale.
For this throttle opening the ‘maximumdischarge’ test showedadischargeof 2.75 l/s,which
means 13.6m³/s for real conditions, that can pass the retention structurewithout backwater
effects.
Thethrottledesign(45°versusstraightedge)didnotinfluencethedischargesignificantly.
None of the tested rake type influenced the discharge through the structure at ‘full basin’
conditions. The ‘maximum discharge’ was not influenced by the rake as long as the distance
betweentherakeandthrottlewassufficient.Iftherakestructure,independentfromthedesign,
wasinstalledtooclosetotheareaofflowacceleration,firstbackwatereffectsatthethrottlecould
beobservedatsmallerdischarges.
Therakeswithhorizontalbeamsatthelowerleveloftherake(Rake#2aandRake#3)increased
thebackwatereffectoftherakeslightlyatthemostupstreammeasuringposition.Belowtherake
structure,therewasnosignificantinfluenceoftherakeontheflowconditions.
Whentheretentionstructurewasfilledwithwater,uptothedamcrest,andthethrottleopening
was1.3m,thevelocityinatthelowerpartoftheoutletchannelwasaround16m/s.Thenappe
showedadistancefrom4.5mto11.4mfromtheendoftheoutletchannel.Thesedistanceswere
measuredontheheightofthedownstreamwallcrest.
3.2 Experiments with woody debris
Thedriftwoodexperimentsshowedthatalltestedtypesofrakesreducetheamountofdriftwood
byatleast90%,butrake#4seemstobemosteffectiveforthemodeledscenario.Ithastobenoted,
that these tests have been performedwith an empty basin (no bedload deposition) and at a
dischargewithnobackwatereffects.Rakes#2a,3and4areevenmoreeffective,whenthebasin
isalreadyprefilled,becausethenthereisnomoreorsmallerclearancebetweenthegroundand
therake.Assoonasbackwatereffectsarepresentit isveryunlikelythatdriftwoodpassesthe
rake,becauseofthereducedflowvelocityinfrontoftherake.
69
3.3 Experiments with bedload transport
3.3.1 Deposition behavior and remobilization of material
Fortheexperimentsstartingwithemptybasinconditionsthebedloadlayerhadtoreachtherake
first,andthenthematerialwaspartlytransportedthroughtherakeandpassesthethrottle(under
naturalconditionssedimentisavailableimmediately).Assoonasbackwatereffectswerepresent
alladdedmaterialwasdepositedinthebasin.Whennormalflowconditionswerereachedagain
(nobackwateratthethrottle)thedepositedmaterialwasremobilizedagain.Withoutadditional
bedload,erosionwasthedominantprocessinthedepositionbasin.
3.3.2 Bedload transport in the outlet channel
Innoneoftheexperimentsdepositionintheoutletchanneltookplace.Allmaterialthatpassed
thethrottlewastransportedthroughthedam.Forthecaseofhighbedloadtransportandstarting
backwaterconditionsmaterialwasdepositedbetweentherakeandthereachabovethethrottle.
Due to the acceleration at the throttle, the throttle itself had never been clogged during the
experimentalruns.
3.3.3 Bedload deposition/erosion behavior in the ‘stilling basin
Experiments,wherethestillingbasinwasprefilledwithbedloadmaterialshowedthatdeposition
takesplaceatdischargesfrom0to13,6m3/s(‘normalflow’conditions).Higherdischargesofthis
rangealsocauseda remobilizationof sediment,when thebasinwascompletely filledupwith
sediment.Dischargeshigherthan13,6m3/s(showingawaterretentionupstreamthedam)ledto
mobilizationofsedimentintheretentionbasin.Whilerunningthe‘overflow’conditions,mostof
the sediment was remobilized, and a little remained in a vortex. During the emptying of the
retentionbasinfollowingthe‘overflow’scenario,theremainingmaterialwasmovedtothesides
oftheretentionbasin.
3.4 Overflow
Theexperimentsshowedthatthetestedchuteandbaffleblocksareveryeffective.Thechuteand
baffle blocks initiated a direct hydraulic jump in the first sector of the stilling basin during
‘overflow’conditions,whereasthetestswithoutblocksresultedinanelongatedhydraulicjump.
Butinthecaseof‘fullbasin’conditions,thechuteandbaffleblockstructurewasnoteffectiveand
themainflowsplashedinthestillingbasinandagainstthedownstreamboundarywall.
70
3.5 Diversion tunnel option
Asecondoption for thebottomoutletwasspecifiedasadiversion tunnel leading through the
bedrock on the side of the structure. The tunnel in natural scale has a diameter of 4.5m, an
inclinationof2.7%,aradiusof86mandalengthof150m.
Forthissetup,athrottleopeningheightof1.11mnaturalscalewasdetected,themaximumfree
surfaceflowwasthesameasinthetestswiththeoutletchannel(13.6m3/snaturalscale).
The super elevation reached amaximum of 3.1m, 26.2m (natural scale) downstream of the
throttle. At this position thewater height in the diversion tunnel at the outer radius is 3.5m
(naturalscale)overthetunnelbottom.Thewaterdidnotreachthetopofthetunnel.
Thenaturalscalevelocityrangewascalculatedwith24.6m3/s(highestvalue)atthethrottleto
12.3m3/s(lowestvalue)at144.6mdownstreamofthethrottle.
Investigationswithbedloadtransportshownodepositionofsedimentinthediversiontunnelfor
thetestedsetup.
3.6 Scaling issues in hydraulic modelling
AccordingtoTaveiraPinto(2012)differencesbetweenthemodelandtheprototypebehaviormay
occurduetoseveralreasons;however:
Scaleeffectsarealwayspresent.
Thebiggerthescalingfactor,thelargerwillbethescaleeffects.
Scaleeffectsdonotaffectallphenomena/parametersunderinvestigationinthesameway
– qualitatively theymay be reproduced differently betweenmodel and prototype, but
quantitativelytheycanbeproperlyscaled(dischargevsairentrainment).
Ingeneralsomeparametersaresmallerinthemodelthaninprototype–relativewave
height,relativedischarge,transportedrelativevolumeofsand,etc.
Froudesimilarityisnormallyconsideredinopen‐channelhydraulics,wherefrictioneffectsare
negligible(deep‐waterwavepropagation)orforhighlyturbulentphenomena,sincetheenergy
dissipationdependsmainlyontheturbulentshearstressterms.Statistically,thesearecorrectly
scaled even though the turbulent fine structures and the average velocity distribution differ
betweenthemodelandprototypeflows.Thegravitationalaccelerationisnotscaledaswellasthe
othernumbers.
Thereforeup‐scaledmodelresultshavetobeinterpretedcarefully.
71
4 References
ALPINFRACONSULTING+ENGINEERINGGMBH(2015).MountainCreekHazardMitigation,
Designofmitigationmeasures,CougarCreek.InterimReport03:FinalOption
Analysis.DatedfromJanuary2015.
BGCENGINEERINGLtd.(2014).CougarCreekdebrisfloodhazardassessment.Finalreport
revisedpreparedfortheTownofCanmore.DatedfromJune2014.
CANMORE(2015a).AboutCanmore,MountainCreekHazardMitigation.In:TheTownof
Canmore[online].Dateofconsulting:18/08/2015.Availableon:
http://www.canmore.ca/
CANMORE(2015b).CougarCreeklong‐termmitigation,Optionanalysissummaryreport.
CougarCreekOptionSelection.DatedfromJanuary2015.
CIVE2400FluidMechanics(2008).Section2:OpenChannelHydraulicsbyDrGoodwillandDr
Sleigh,UniversityofLeeds,SchoolofCivilEngineering.
PEPPERL+FUCHSGROUP,2014.UltrasonicsensorUC500‐30GM‐IUR2‐V15.Instructions.
PREIßLERG.andBOLLRICHG.(1985).TechnischeHydromechanik/1.VerlagfürBauwesen,
Berlin,2ndEdition.Pages299and500to505.
Preissler, G.; Bollrich, G.; Martin, H. (1989): Technische Hydromechanik. Band 2: Spezielle
Probleme. Berlin: Verlag Bauwesen
ROCKWELLAUTOMATIONInc.(2015).UltrasonicAdvantagesandDisadvantages.In:
RockwellAutomationInc.[online].Dateofconsulting: 15/07/2015.Availableon:
http://www.ab.com/
TAVEIRAPINTOF.(2012):ScalingIssuesinHydraulicModelling,Dateofconsulting7/06/2016.
Availableon:http://www.coastalwiki.org/wiki/Scaling_Issues_in_Hydraulic_Modelling
5 Attachments
TestprotocolsandVideosequencesareprovidedinaseparateddocument.