i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD...

35
FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD DISTRIBUTION SYSTEM RELIABILITY QADDAFI ABDULLAH BAJERAI A project report submitted in partial fulfillment of the requirement for the award of the Degree of Master of Electrical Engineering Faculty of Electrical and Electronic Engineering Universiti Tun Hussein Onn Malaysia JULY 2014

Transcript of i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD...

Page 1: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

i

FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD DISTRIBUTION

SYSTEM RELIABILITY

QADDAFI ABDULLAH BAJERAI

A project report submitted in partial

fulfillment of the requirement for the award of the

Degree of Master of Electrical Engineering

Faculty of Electrical and Electronic Engineering

Universiti Tun Hussein Onn Malaysia

JULY 2014

Page 2: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

iv

ABSTRACT

Electricity has become a major necessity in the modern world, and the availability

has to reach to not only the city area but to the rural areas of population as well. To

ensure the electrical distribution system is healthy, protection schemes have to be in

place and one such method is the use of fuse blow method. This method is

extensively used by the electric utility’s distribution system in Sabah and has shown

effective protection requirements. However, this comes as a tradeoff to customers

experiencing outages of electric supply. The study was carried out to identify the

impact of fuse blow method and the accompanying results from actual performance

of the overhead distribution system in a selected area, which in this case is the Kota

Belud area. Many factors influence the reliability of the system such as the length of

the distribution feeders, number of customers in each point of the system and

placement of the fuses. The method used was the enumerative analysis to calculate

the reliability impact of the fuse blow method. From the calculations, the result is

then compared with the actual performance of the system in a one year period. The

length of the feeders has the biggest impact to the reliability calculation and this is

reflected by the data of actual performance of the feeders. A delicate balance of

fusing coordination and limiting of feeder length is needed to ensure that the impact

of the fuse blow method to the customer is adequately mitigated.

Page 3: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

v

ABSTRAK

Elektrik telah menjadi keperluan utama di dunia moden dan ianya perlu disalurkan

bukan sahaja kepada kawasan bandar tetapi di penduduk luar bandar juga. Bagi

menjamin kesihatan system pembahagian elektrik, skema perlindungan perlu

diadakan dan salah satu kaedah yang digunapakai ialah kaedah “fuse blow”. Kaedah

ini digunakan secara meluas oleh syarikat utiliti elektrik bagi system pembahgian di

Sabah dan telah menunjukkan keperluan perlindungan yang efektif.

Walaubagaimanapun, ini memberi kesan kepada pengguna elektrik yang akan

mengalami gangguan bekalan elektrik. Kajian ini dijalankan bagi mengenalpasti

impak kaedah “fuse blow” kepada prestasi sebenar bagi sistem pembahagian talian

atas di suatu kawasan yang dipilih, iaitu kawasan Kota Belud. Banyak faktor

mempengaruhi kedayaharapan sistem seperti panjang talian pembekal pembahagian,

jumlah pelanggan bagi setiap talian dan lokasi fius yang dipasang. Kaedah yang

digunakan ialah “enumerative analysis” bagi membuat kiraan impak kedayaharapan

“fuse blow” ini. Daripada pengiraan yang dibuat, hasilnya dibandingkan dengan

prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar kepada

pengiraan kedayaharapan dan ini dikukuhkan dengan data prestasi sebenar talian.

Keseimbangan dari segi koordinasi pemasangan fius dan menghadkan panjang talian

diperlukan bagi memastikan impak kaedah “fuse blow” kepada pelanggan dapat

dikurangkan sewajarnya.

Page 4: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

vi

CONTENTS

TITLE i

DECLARATION ii

ACKNOWLEDGEMENT iii

ABSTRACT iv

CONTENTS vi

LIST OF TABLE viii

LIST OF FIGURES x

CHAPTER 1 INTRODUCTION 1

1.1 Project Background 1

1.2 Problem Statements 2

1.3 Project Objectives 2

1.4 Project Scopes 3

CHAPTER 2 LITERATURE REVIEW 4

2.1 Introduction 4

2.2 Theories 4

2.3 Description of Previous Methods 5

CHAPTER 3 METHODOLOGY 7

3.1 Project Methodology 7

Page 5: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

vii

CHAPTER 4 DATA ANALYSIS AND RESULTS 10

4.1 Data Analysis 10

4.2 Results 48

CHAPTER 5 DISCUSSIONS AND CONCLUSIONS 52

5.1 Discussion 52

5.2 Conclusions 53

REFERENCES 54

Page 6: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

viii

LIST OF TABLES

4.1 Types and number of customers by Feeder 11

4.2 Failure rate of overhead distribution components (R.E. Brown) 12

4.3 Failure rate for Distribution Lines (Statnett) 13

4.4 Parameters used for reliability indices calculation in Army Camp I 15

4.5 No. of customers by area for Feeder Army Camp I 15

4.6 Result for Feeder Army Camp I 16

4.7 Parameters used for reliability indices calculation in Army Camp II 18

4.8 No. of customers by area for Feeder Army Camp II 19

4.9 Result for Feeder Army Camp II 21

4.10 Parameters used for reliability indices calculation in Ambong 22

4.11 No. of customers by area for Feeder Ambong 23

4.12 Result for Feeder Ambong 23

4.13 Parameters used for reliability indices calculation in Sayap 25

4.14 No. of customers by area for Feeder Sayap 26

4.15 Result for Feeder Sayap 27

4.16 Parameters used for reliability indices calculation in Tenghilan 28

4.17 No. of customers by area for Feeder Tenghilan 29

4.18 Result for Feeder Tenghilan 30

4.19 Parameters used for reliability indices calculation in Timbang 32

4.20 No. of customers by area for Feeder Timbang 32

4.21 Result for Feeder Timbang 33

4.22 Parameter used for reliability indices calculation in Melangkap 35

4.23 No. of customers by area for Feeder Melangkap 35

4.24 Result for Feeder Melangkap 37

4.25 Parameters used for reliability indices calculation in Town 38

4.26 No. of customers by area for Feeder Town 39

4.27 Result for Feeder Town 40

Page 7: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

ix

4.28 Parameters used for reliability indices calculation in Sembirai 41

4.29 No. of customers by area for Feeder Sembirai 42

4.30 Result for Feeder Sembirai 43

4.31 Performance Data for Feeder Army Camp I 44

4.32 Performance Data for Feeder Army Camp II 44

4.33 Performance Data for Feeder Ambong 46

4.34 Performance Data for Feeder Sayap 46

4.35 Performance Data for Feeder Tenghilan 47

4.36 Performance Data for Feeder Town 48

4.37 Performance Data for Feeder Melangkap 48

4.38 Performance Data for Feeder Sembirai 49

4.39 Performance Data for Feeder Timbang 50

4.40 Performance Data for Feeder Interlink 50

4.41 Results of the calculated reliability indices 51

4.42 Compiled performance data for 1 year duration 51

4.43 Comparison between Calculated Reliability Indices and 52

Actual Performance

4.44 Causes of outages by category 56

Page 8: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

x

LIST OF FIGURES

2.1 Typical fuse blow scheme operation 5

3.1 Flow chart for calculation of reliability indices 9

4.1 Overview Single Line Diagram for Kota Belud area 10

4.2 Single Line Diagram for Feeder Army Camp I 14

4.3 Reliability sections for Feeder Army Camp I 14

4.4 Single Line Diagram for Feeder Army Camp II 17

4.5 Reliability sections for Feeder Army Camp II 18

4.6 Single Line Diagram for Feeder Ambong 21

4.7 Reliability sections for Feeder Ambong 22

4.8 Single Line Diagram for Feeder Sayap 24

4.9 Reliability sections for Feeder Sayap 24

4.10 Single Line Diagram for Feeder Tenghilan 27

4.11 Reliability sections for Feeder Tenghilan 28

4.12 Single Line Diagram for Feeder Timbang 31

4.13 Reliability section for Feeder Timbang 31

4.14 Single Line Diagram for Feeder Melangkap 34

4.15 Reliability section for Feeder Melangkap 34

4.16 Single Line Diagram for Feeder Town 37

4.17 Reliability section for Feeder Town 38

4.18 Single Line Diagram for Feeder Sembirai 40

4.19 Reliability section for Feeder Sembirai 41

4.20 Graphical Comparison between Calculated Reliability 53

Indices and Actual Performance

4.21 Correlation of Calculated SAIDI and feeder length 54

4.22 Correlation of Actual SAIDI and feeder length 55

4.23 Pie chart of causes for outages at Kota Belud area 57

Page 9: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

1

CHAPTER 1

INTRODUCTION

1.1 Project Background

Electric utility companies around the world use bare overhead conductors as one of

the more economical methods of transmitting and distributing electricity to

customers. To better sectionalise as well as offer some form of protection in the

electricity system, fuse blow method is used as one of the cheaper alternatives.

Alternatively, fuse saving methods provide a means for the power utility

company to provide allowance in the system for faults to clear on its own and avoid

sending precious manpower to the site for fuse replacement. However, the downside

is the increment in momentary interruption to the customers.

In the increasingly high demand of continuous and stable power supply from

the customers even in the rural areas, more stringent and efficient methods are

required to provide the acceptable level of service to the customers.

In Sabah state utility, the fuse blow method is extensively used throughout

the overhead line system for the purpose of sectionalising and protection of the

circuit in the event that a fault occurs in the system. When a temporary fault occurs

which can be caused by vegetation or animals, the protected section would be

isolated by blowing the fuse which in turn would cause the whole section to be

without power.

This project addresses the impact of a fuse blow philosophy on long lines

commonly found in rural electric utilities as well as shorter lines in more urban areas.

It also assesses the differences in the impact of these schemes in terms of both power

quality and reliability issues.

Page 10: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

2

Improvements in the system would be beneficial to increase the satisfaction

of customers in the state.

1.2 Problem Statements

Fuse saving method was used almost universally until the late 1980s, however as

power quality concerns grew, utilities had to switch to fuse blowing mode. The fine

balance required in using the fuse saving method and fuse blow method is critical in

providing a reliable and stable power supply.

Using the fuse blow method, the interruption to the customers is greatly

impacted as there little discrimination between a transient fault and a permanent fault

in the circuit protected by the fuse. This study is to assess the impact of the fuse blow

method to the reliability of the system. Several areas will be selected to be the case

study for this thesis for a broader perspective on the issue.

This project is expected to analyse in detail the impact on the utility system

and look into the improvements that can be made to improve the performance of the

fuse blow philosophy which would in turn provide the utility a better system

performance.

Data collection and data integrity would be an issue in the event that

unreported incidences occurring on site is not reported would have an impact on the

analysis carried out.

Subsequently, the method of analysis may be subject to further scrutiny in the

event that any inconsistencies appear in the study.

However, whatever methods that are proposed will need to take into account

the economic benefits of implementing and executing the proposed method into

practice by the utility as this project study will only look into the technical aspects of

the method.

1.3 Project Objectives

The major objective of this research is to identify the impact of fuse blow scheme to

reliability and power quality in an electric utility.

Its measurable objectives are as follows:

a) To identify the number of incidences of fuse blow in the system under study

Page 11: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

3

b) To determine the causes of incidences

c) To identify the SAIDI figures for a certain duration and the impact due to the

incidences

d) To identify the SAIFI figures for a certain duration and the impact due to the

incidences

1.4 Project Scope

This project is primarily concerned with the impact of the fuse blow philosophy in

the usage of the electric utility. The scopes of this project are:

a) Rural electrical lines

b) Urban area electrical lines

c) Protection system involving fuses

The project is limited by the scope of electrical overhead distribution lines

only and does not include the fully underground cables feeders or transmission lines

used by the electric utility. However, a mixture of overhead and minimal

underground cables in the feeder will be considered in this study.

The area of interest will be concentrated on the rural as well as urban area,

and the differences in impact of the schemes in terms of power quality and reliability

issues.

This project will not look into the economical or feasible implications of

utilising or implementing the proposed methods discussed.

Page 12: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

4

CHAPTER 2

LITERATURE REVIEW

2.1 Introduction

Fuse blow method, fuse saving methods and combinations of both has been used by

electric utilities since there is need for a distribution system was installed to protect

the equipment in the system. This study will focus on the fuse blow method only and

will include the relevant materials to the impact it has to the distribution system.

The reliability of a distribution system would be readily measured by the

performance that is shown in the historical database of the electric utility and based

on this, several studies have been done to measure the factors and parameters needed

to study the distribution system reliability.

Some of the most used methods to study the distribution reliability are the

Markov Chain model, RELRAD model, series system and parallel system.

2.2 Theories

Fuse blow scheme is a method where the tripping of the circuit breaker or a re-closer

is excluded and the fuse is operated for any faults in the system whether it is

permanent or temporary fault.

The typical fuse blow scheme is depicted in Figure 2.1 as follows. When a

fault occurs on a lateral / spur line of the feeder, the fuse will operate to disconnect

the affected section from the rest of the system, thereby effectively containing the

outage to the downstream area of the fuse protection zone.

Page 13: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

5

Figure 2.1: Typical fuse blow scheme operation

A single fuse can clear most line-to-neutral faults, line-to-ground as well as

single phase line-to-line faults. However, when two fuses operate simultaneously it

can clear a 3-phase line-to-line faults.

2.3 Description of Previous Methods

Several previous studies on the impact of fuse blow method and fuse save method

have been explored and detailed out with respect to the power utility and the usage of

the different methods are very much dependant on the location and type of feeders

that is featured in the study. The seasonal changes in a particular geographic location

are not considered in this study.

Researchers have proposed a combined fuse saving and fuse blow method to

be used as a more effective utilization of the fusing methodology for protection by

looking at the fuse operating time curve and operating it in an optimal fashion.

However, due to economical and capability constraints, not all utilities can afford to

implement the fuse blow and fuse saving method effectively. Therefore, in terms of

practicality and feasibility, some utilities will only employ the fuse blow method.

The reliability indices used in this study are the SAIDI and SAIFI where,

System Average Interruption Duration Index or SAIDI is the average outage duration

each customer experiences.

Substation

Main Intake

CB

CB

CB

Fault occur

Page 14: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

6

(2.1)

(2.2)

System Average Interruption Frequency Index or SAIFI is the average

number of interruptions a consumer experiences.

(2.4)

(2.5)

Description of a distribution system illustrates the many features of a

distribution system which makes it unique. In the state of Sabah, the voltage level of

a distribution system ranges from 11kV up to 33kV. The 33kV system serves

considerably longer lines, however the 11kV system may also be serving long lines

with low load density.

Short circuit levels at the substation would depend on the voltage level and

substation size.[1] There are typically two types of faults, low impedance and high

impedance. Faults which can be detected by normal protection devices are usually

low impedance faults.

The time-current characteristic (TCC) of the fuse operation is also a study by

itself and contributes to the setting and different mode of operations in the utility

system protection sequence. Current limiting fuse (CLF) and non-current limiting

fuse are some of the other different types of methods used to coordinate the system’s

protection settings.

Page 15: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

7

CHAPTER 3

METHODOLOGY

3.1 Project Methodology

There are two main approaches that can be utilised which are analytical and

simulation methods. Simulation generally requires large amount of computing time

and analytical models and techniques have been sufficient to provide the results

needed to make objective decision [2]. For this study, the analytical method or

enumerative analysis is used.

The system under study is represented in a mathematical model and the

reliability indices are evaluated using numerical calculations. Using the basis of a

Markov model, a simple formula can be developed to calculate the reliability of the

distribution network [3]. In this method, two criterions are focused on which is the

frequency of failure (λ) and the repair time (r), where the calculation for the

frequency of failure is as follows:

λ = Number of outages of a component in a set duration (3.1)

Total time the component is in operation

The distribution systems in Sabah is basically designed and operated in radial

system with the mesh system usually only utilised in urban and high density areas. A

radial system would consist of a series of components such as circuit breakers, re-

closer, lines, switches, transformers and the customer. The equations needed to

calculate the basic indices are as follows:

Page 16: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

8

Average failure rate of the system:

(3.2)

Average Outage duration or Repair time of the system:

(3.3)

If λ1 λ2 r1 r2 << λ1 r1 or λ2 r1r2

Average Annual Outage time:

Us = fs . rs = λs . rs (3.4)

Where λi is the failure rate at node i, ri is the outage time at node i.

The system network of 11kV feeders in the study is translated into reliability

sections which are sectionalised by the location of the main line fuses and lateral /

spur fuses. Once the reliability sections have been identified, the system is modelled

according to each individual feeder and its accompanying components. For the

purpose of this study, only the overhead line components will be included in the

modelling, such as the main trunk line and the lateral / spur lines components. The

expected values from the statistical distribution of failure rates and repair times for

all components in the system are then generated and the calculation for reliability

indices for each load point of each component is accumulated. Finally with all the

fault contribution is available, the total accumulated indices can be generated.

The flowchart for this study is shown in Figure 3.1 on the following page.

rs = λ1 r1 + λ2 r2 + λ1 λ2 r1 r2 = ∑ λi ri = Us

λ1 + λ2 ∑ λi λs

λs = λ1 + λs = ∑ λi

i = 1

2

Page 17: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

9

Figure 3.1: Flow chart for calculation of reliability indices

With the results of the numerical calculations, actual performance data of the

feeders will be extracted from the LGBNet (SESB’s reliability indices records) to

compare the calculations and annual performance of the feeders in the study.

Start

Select Network

Component

Calculate reliability

indices impact

Analyse impact for

the system

More

components?

Compare reliability indices

with actual performance

Stop

Yes

No

Page 18: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

10

CHAPTER 4

DATA ANALYSIS AND RESULTS

4.1 Data analysis

The duration of the study is from 1st September 2012 up to 31

st August 2013, which

is the state utility’s financial year and is used due to the financial year reporting of

their data which will greatly simplify the comparison process later.

The selected area for this study is the 11kV feeders in Kota Belud area which

is located towards the north of the capital city of Kota Kinabalu. An overview single

line diagram of Kota Belud area is as shown in Figure 4.1 which basically shows

how the interconnection of the feeders radiate from the Main Intake Substation or

PMU (Pencawang Masuk Utama).

Figure 4.1: Overview Single Line Diagram for Kota Belud area

Page 19: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

11

The number of customers can be segregated by types into 3 different

categories, namely Domestic, Commercial and Industrial customers. Domestic users

are the houses and consumption is usually under 1000kwh per month. Commercial

users are the users who are involved in business and have a higher unit rate tariff.

Industrial users are those that involve the bigger scale consumption of electricity. For

the purpose of this study, the total customers per feeder are used. The table 4.1 shows

the types and number of customers according to individual feeders.

Table 4.1: Types and number of customers by Feeder

Feeder Name Feeder

Number

Number of Customers

Domestic Commercial Industrial Total

Army Camp I K08 1,131 39 1 1,171

Army Camp II B04 2,765 79 3 2,847

Ambong K04 921 23 0 944

Sayap B03 1,799 34 1 1,834

Tenghilan K05 2,937 53 2 2,992

Timbang B01 2,036 84 2 2,122

Melangkap B02 3,665 112 6 3,783

Town K07 1,058 1,359 14 2,431

Sembirai K11 4,412 100 1 4,513

Total 20,724 1,883 30 22,637

The fuses used in the scheme are critical to be coordinated accordingly to the

lateral / spur section that it is assigned as the rating of the fuse is deterministic of its

protection capability.

The main lines or the trunk lines of the feeder is normally installed with high

rated fuses such as 100A and above, however in the rural feeders, these fuse ratings

may be reduced accordingly due to the low load in those areas. Subsequently, the

downstream fuses has to be smaller to allow the affected of faulty areas become

isolated in the event that an outage does occur. When the downstream fuse blows, the

upstream fuses should not be affected and continue to supply the customers without

interruption.

The failure rate may be defined as the rate at which a failure occurs per unit

time under specified operating conditions and for electrical equipment this may be

Page 20: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

12

assumed to follow an exponential distribution [4]. As such, the reliability of the

equipment can be shown as:

R(t) = e-λt

(4.1)

From previous studies and survey works done on distribution systems, one

such typical permanent failure rates of the equipment are shown in Table 4.2 [5]. The

equipment in a distribution system has a relatively constant failure rate (λ) [1].

Overhead line failure rates for temporary faults was assumed to be 3 times that for a

permanent fault. [1]

Table 4.2 Failure rate of overhead distribution components (R.E. Brown)

Description Failure Rate, λ (per circuit mile / year)

Low Typical High

Overhead primary trunk 0.020 0.100 0.300

Overhead Lateral Tap 0.020 0.160 0.300

Fuse Cutout 0.004 0.009 0.030

Line Recloser 0.005 0.015 0.030

Shunt Capacitor 0.011 0.020 0.085

Voltage Regulator 0.010 0.029 0.100

Disconnect Switch 0.004 0.014 0.140

From a study, the typical 1.6km (1 mile) will have on average a failure rate of

15.5% assuming that all abnormalities at or downstream of the distribution

transformers are cleared and prevented from going upstream beyond the transformer

fuse cutout [1].

The calculation for the probability of failing is equal to (1 – e-λt

) for

overhead primary trunk and overhead lateral or spur tap, is as shown in the following

page:

Probability of failure = 1 – e-(0.100 + 0.160) x 1

= 22.9% (4.2)

Page 21: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

13

Another study shows a different failure rate, where the values differ

significantly from those shown in Table 4.2. The study by Statnett (2002) average

temporary and sustained failure rates for power system components in Norway, for

the period 1993 through 2002, are presented as shown in Table 4.3 below.

Table 4.3: Failure rate for Distribution Lines (Statnett)

Failure rate for Distribution

Lines (Underground Cable, UG

and Overhead Line, OHL)

per 100km/year per km/ year

Temporary Permanent Temporary Permanent

OHL (33kV - 110 kV) 1.0400 0.5000 0.0104 0.0050

UG (33kV - 110 kV) 0.1500 0.9500 0.0015 0.0095

The history and characteristic of the laterals (spurs) along with the probability

of developing a fault are worth investigating in determining whether to allow the

lateral (spur) fuse to blow or the feeder breaker / recloser to trip and reclose. [1]

The 11kV Single Line Diagrams for each of the feeders in the Kota Belud

distribution systems are analysed to look into the layout and the connections of the

fuses in the scheme. The layout is then translated into the reliability sections to

enable the numerical calculations to be carried out. For this study, the failure rate

from Table 4.3 is used.

The first feeder to be analysed is the Feeder Army Camp I. The single line

diagram is as shown in Figure 4.2 and is then translated into Figure 4.3. From the

single line diagram in Figure 4.2, there are a total of 17 nos. of substation with

transformers that supply the customers in that particular area. This will then be

translated into load points in Figure 4.3.

Page 22: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

14

Figure 4.2: Single Line Diagram for Feeder Army Camp I

There is a total of 17 load points with 2 main fuse sections and 3 lateral fuse

sections for Feeder Army Camp I as shown in Figure 4.3 below.

Figure 4.3: Reliability sections for Feeder Army Camp I

Page 23: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

15

The reliability sections for Feeder Army Camp I is then tabulated into the

numerical calculation sheet with the relevant parameters to get the SAIDI and SAIFI

calculations. The sections with fuses are identified from the single line diagram and

the length of each reliability section is calculated.

The Table 4.4 shows the parameters used in the numerical calculations which

correspond with the failure rate of the components, number of customers per section

and recovery time for Feeder Army Camp I where the designation M1 up to M2

represent the main line fuses and L1 up to L3 represent the lateral or spur fuses

installed in the feeder.

Table 4.4: Parameters used for reliability indices calculation in Army Camp I

Reliability Section Feeder

Army Camp I

Overhead Line Parameters

Length (km) Failure Rate, λ Repair time, r

(hour)

M1 9.975 0.1037 54.0167

M2 1.815 0.0189 54.0167

L1 0.770 0.0080 54.0167

L2 3.960 0.0412 54.0167

L3 1.540 0.0160 54.0167

The number of customers for each load points is also considered as an input

for the indices calculation. Table 4.5 shows the individual number of customers for

each load points which is needed to calculate the reliability indices.

Table 4.5: No. of customers by area for Feeder Army Camp I

Area No. of Customers

Domestic Commercial Industry Total

Menunggui 130 2

132

Kg kota belud 135 1

136

JBA HQ

1

1

Master Sewarage T.Plan

1

1

Water work

1

1

Water pump

2

2

Bobot 139 3

142

Wokok 40 1

41

Siasai kumpang 66

66

Page 24: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

16

Table 4.5 (continued)

Area No. of Customers

Domestic Commercial Industry Total

Army camp range unit 38 9 47

Army camp culvery 21 8 1 30

Lapang sasar 1 1

Tambulion laut 65 3 68

Tambulion ulu 174 174

Siasai jaya 54 2

56

Tempasuk 2 235 2

237

Total 1,131 39 1 1,171

From the identified 17 nos. of load points using numerical calculation, the

result for Feeder Army Camp I is shown in Table 4.6 where the calculated SAIDI is

481.366 minutes and SAIFI of 0.149 for a one year duration.

Table 4.6: Result for Feeder Army Camp I

No. Indices Value Definition

1 SAIDI 8.023 Hours interruption / customer

481.366 Minutes interruption / customer

2 SAIFI 0.149 No. of interruptions / customer

The next feeder to be analysed is Feeder Army Camp II, and the single line

diagram is as shown in Figure 4.4 in the following page. From the single line

diagram, there are 47 nos. of substations with transformers and each of them will

have their own number of customers. There are 7 main sections and 11 numbers of

lateral sections shown in the single line diagram. This will later be translated into the

reliability sections to carry out the analysis.

Page 25: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

17

Figure 4.4: Single Line Diagram for Feeder Army Camp II

Using the available single line diagram of Feeder Army Camp II, the

reliability section is then generated as shown in Figure 4.5 by identifying the main

fuses and lateral / spur fuses in the system. For the reliability section to be

constructed several assumptions were made such as, the underground cable is not

taken into consideration as the study is focusing on overhead lines impact only. The

usage of re-closers on the line is also not taken into consideration as the reclosing

function can be ignored in this particular study of fuse blow scheme.

Page 26: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

18

Figure 4.5: Reliability section for Feeder Army Camp II

The reliability section for Feeder Army Camp II is then tabulated into the

numerical calculation sheet with the relevant parameters to get the SAIDI and SAIFI

calculations. The sections with fuses are identified from the single line diagram and

the length of each reliability section is calculated.

The Table 4.7 shows the parameters used in the numerical calculations which

correspond with the failure rate of the components, number of customers per section

and recovery time for Feeder Army Camp II, where the designation M1 up to M7

represents the main line fuses and L1 up to L11 represents the lateral or spur fuses

installed in the feeder.

Table 4.7: Parameters used for reliability indices calculation in Army Camp II

Reliability Section Feeder Army Camp

II

Overhead Line Parameters

Length (km) Failure Rate, λ Repair time, r

(hour)

M1 19.250 0.2002 54.0167

M2 3.465 0.0360 54.0167

Page 27: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

19

Table 4.7 (continued)

Reliability Section Feeder Army

Camp II

Overhead Line Parameters

Length (km) Failure Rate, λ Repair time, r

(hour)

M3 4.585 0.0477 54.0167

M4 3.135 0.0326 54.0167

M5 1.165 0.0121 54.0167

M6 11.440 0.1190 54.0167

M7 6.765 0.0704 54.0167

L1 0.770 0.0080 54.0167

L2 2.970 0.0309 54.0167

L3 5.170 0.0538 54.0167

L4 3.245 0.0337 54.0167

L5 3.080 0.0320 54.0167

L6 3.410 0.0355 54.0167

L7 0.770 0.0080 54.0167

L8 6.655 0.0692 54.0167

L9 3.575 0.0372 54.0167

L10 5.830 0.0606 54.0167

L11 3.190 0.0332 54.0167

The number of customers for each load points is also considered as an input

for the indices calculation. Table 4.8 shows the individual number of customers for

each load points which is needed to calculate the reliability indices for Feeder Army

Camp II.

Table 4.8: No. of customers by area for Feeder Army Camp II

Area No. of Customers

Domestic Commercial Industry Total

Kompleks botong 32 3

35

Gunasama

9

9

Botong 92 3 2 97

Quarters army camp 30

30

Perumahan army camp 200

200

Bangkahak nayasan 108

108

Bangkahak sum-sum 44 1

45

Kimo- kimo 32

32

Rosok 123 4

127

Kalibungan 53 1

54

Ginapas 49

49

Bangkahak zink 63 1

64

Bangkahak baru 75

75

Page 28: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

20

Table 4.8 (continued)

Area No. of Customers

Domestic Commercial Industry Total

Bambangan 78

78

Bugaron 68

68

Gantuong 99 1

100

Kawang- kawang 76

76

Pump hse 1

1

1

Penampang 44

44

Pandasan 85 3

88

Lebak kupang 54

54

Timbang 173 11

184

Siudon 27

27

Bungaliu 33

33

Bubuk 28

28

Luadi 35

35

Tambilaung 87 2

89

Mantanau 72 4

76

Ulu kukut 71 6

77

T/mengaris 52 9

61

Jabatan haiwan 7

7

Benih padi 3 2 1 6

IPS quarters 42 1

43

IPS mengaris 30

30

Maxis

1

1

Rampayan ulu 166 3

169

IPS baru 15

15

Tim. Baru 24

24

Timb. Kukut 35

35

Sarang 227

227

Kolam 1 13 3

16

Kolam 2 10 2

12

Kolam 3 10

10

Dudar 49 2

51

Dudar ulu 40

40

Maxis

1

1

Taburon 1 65 3

68

Taburon 2 46 2

48

Total 2,765 79 3 2,847

From the identified 47 nos. of load points using numerical calculation, the

result for Feeder Army Camp II is shown in Table 4.9 where the SAIDI is 961.631

minutes for one year duration.

Page 29: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

21

Table 4.9: Result for Feeder Army Camp II

No. Indices Value Definition

1 SAIDI 16.027 Hours interruption / customer

961.631 Minutes interruption / customer

2 SAIFI 0.297 No. of interruptions / customer

The next feeder to be analysed is the Feeder Ambong. The single line

diagram is as shown in Figure 4.6 and is then translated into Figure 4.7 for the

reliability section identification. From the single line diagram, there are 12 nos. of

substations with transformers in them, which will have their own number of

customers.

Figure 4.6: Single Line Diagram for Feeder Ambong

For Figure 4.7, there are a total of 3 main section fuses and only one lateral

section fuse. The substation transformers are translated into the 12 nos. of load

points.

Page 30: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

22

Figure 4.7: Reliability section for Feeder Ambong

The reliability section for Feeder Ambong is then tabulated into the numerical

calculation sheet with the relevant parameters to get the SAIDI and SAIFI

calculations. The sections with fuses are identified from the single line diagram and

the length of each reliability section is calculated.

The Table 4.10 shows the parameters used in the numerical calculations

which correspond with the failure rate of the components, number of customers per

section and recovery time for Feeder Ambong, where the designation M1 up to M3

represent the main line fuses and L1 represent the lateral or spur fuses installed in the

feeder.

Table 4.10: Parameters used for reliability indices calculation in Ambong

Reliability Section Feeder

Ambong

Overhead Line Parameters

Length (km) Failure Rate,

λ

Repair time, r

(hour)

M1 6.105 0.0635 54.0167

M2 12.320 0.1281 54.0167

M3 1.595 0.0166 54.0167

L1 7.425 0.0772 54.0167

The number of customers for each load points is also considered as an input

for the indices calculation. Table 4.11 shows the individual number of customers for

Page 31: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

23

each load points which is needed to calculate the reliability indices for Feeder

Ambong.

Table 4.11: No. of customers by area for Feeder Ambong

Area No. of Customers

Domestic Commercial Industry Total

Paka- paka 58 1

59

Paka- paka 2 71 1

72

Pahu 111

111

sumbilingon 57

57

Pangi 65 1

66

Pituru darat 113

113

Pituru laut 66 12

78

Ambong 128 2

130

Taulus 57

57

Taulus Rumbia 30

30

Baru- baru 108 6

114

Luk nunuk 57

57

Total 921 23 0 944

From the identified 12 nos. of load points using numerical calculation, the

result for Feeder Ambong is shown in Table 4.12 where the SAIDI is 641.287

minutes for one year duration.

Table 4.12: Result for Feeder Ambong

No. Indices Value Definition

1 SAIDI 10.688 Hours interruption / customer

641.287 Minutes interruption / customer

2 SAIFI 0.198 No. of interruptions / customer

The next feeder to be analysed is the Feeder Sayap. The single line diagram is

as shown in Figure 4.8 and is then translated into Figure 4.9 for the reliability section

identification.

Page 32: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

24

Figure 4.8: Single Line Diagram for Feeder Sayap

Figure 4.9: Reliability section for Feeder Sayap

Page 33: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

61

REFERENCES

[1] Craig A. O’Meally, Member, IEEE, Jim Burke, Fellow, IEEE, (2009). “The

Impact of a “Fuse Blow” Scheme on Overhead Distribution System

Reliability and Power Quality”. Rural Electric Power Conference, 2009.

REPC '09. IEEE

[2] Tempa Dorji (2009), “Reliability Assessment of Distribution Systems”. Master

of Science in Electric Power Engineering, Norwegian University of Scence

and Technology

[3] Bind I, Kapittel 11, Utgitt (1993). “Planleggingsbok for Power Grids”, Updated

2009

[4] P.A. Tobias and D.C. Trindade (1995), “Applied Reliability”, CRC Press

[5] R.E. Brown (2002), “Electric Power Distribution Reliability”, Marcel Dekker

Inc.

[6] Thomas Allen Short (2003). “Electric Power Distribution Handbook (Google

eBook)”

[7] Christopher McCarthy, Ray O’Leary, and Doug Staszesky (2008). “A NEW

FUSE-SAVING PHILOSOPHY”. Presented at DistribuTECH 2008,

January 22-24, 2008, Tampa, Florida

[8] Myoung-Hoo Kim, Sung-Hun Lim, and Jae-Chul Kim (2011). “Improvement

of Recloser-Fuse Operations and Coordination in a Power Distribution

System With SFCL”. IEEE TRANSACTIONS ON APPLIED

SUPERCONDUCTIVITY, VOL. 21, NO. 3, JUNE 2011

Page 34: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

62

[9] Toru TANAKA and Mikio YAHASAKI (2004). “Modeling of Fuses for

Melting Time and Fusing Current Analysis”. Telecommunications Energy

Conference, 2004. INTELEC 2004. 26th Annual International

[10] Tio, A.E.D.C. ; Cruz, I.B.N.C. ; Malquisto, B.M. ; del Mundo, R.D. (2012).

“A Binary Programming Model for Reliability Optimization Considering

Fuse-blow and Fuse-save Schemes”. TENCON 2012 - 2012 IEEE Region

10 Conference

[11] Funmilayo, H.B. ; Butler-Purry, K.L. (2009). “An approach to mitigate the

impact of distributed generation on the Overcurrent Protection scheme for

radial feeders”. Power Systems Conference and Exposition, 2009. PSCE

'09. IEEE/PES

[12] Sedaghati, A. ; Darabi, A. (2011). “An approach to determine penetration

level of Distributed Generation considering fuse fatigue issues in

distribution radial feeders”. Advanced Power System Automation and

Protection (APAP), 2011 International Conference

[13] Ferreira, G.D. ; Bretas, A.S. ; Cardoso, G. (2010). “Optimal distribution

protection design considering momentary and sustained reliability

indices”. Modern Electric Power Systems (MEPS), 2010 Proceedings of

the International Symposium

[14] John S. Schaffer (2003). “Current Limiting Fuse Theory and Operation”.

Transmission and Distribution Conference and Exposition, 2003 IEEE

PES

[15] I. Zamora, G. Buigues, A.J. Mazon, P. Eguia (2003). “Coordination and

Selection of Expulsion and Current-Limiting Fuses in Pad Mounted

Transformer Primary Protection”

Page 35: i FUSE BLOW SCHEME AND ITS IMPACT ON OVERHEAD …eprints.uthm.edu.my/6679/1/QADDAFI_ABDULLAH_BAJERAI.pdf · prestasi sebenar setiap talian . Panjang talian mempunyai impak terbesar

63

[16] Fredrik Roos, Sture Lindahl (2003), “Distribution System Component Failure

Rates and Repair Time”

[17] Leonard L. Grigsby (2012), “Electric Power Generation, Transmission and

Distribution”, Third Edition

[18] Ying He (2010), “Study and Analysis of Distribution Equipment Reliability

Data”

[19] A. Baharu,, F.M. Alwan, S.T. Hasson (2013), “A Case Study of Reliability and

Performance of the Electric Power Distribution Station Based on Time

between Failures”