FRONT
NH-129-1(30); C.N. 32275I-129, SOUTH SIOUX CITY
PROJECT INFORMATION SHEETAs of October 2019
LOCATIONThe proposed project would resurface approximately 3.23 miles of Interstate 129 (I-129) in South Sioux City in Dakota County. The project would start approximately 0.55 miles west of the grade separation of I-129 under southbound U.S. Highway 75 (US-75)/U.S. Highway 77 (US-77) at mile marker US-20 (MM) 428.37 and extend east to the bridge over the Missouri River at MM 3.05. Construction may begin and/or end approximately 500 feet ahead of or beyond the actual project limits to accommodate transitioning the pavement.
PURPOSE AND NEEDThe purpose of the proposed project is to preserve the I-129 transportation asset, improve the reliability of the transportation system, and perpetuate the mobility of the traveling public. The need for the project is based on the condition of the existing pavement and bridge structures.
SCOPE OF WORKProposed improvements on this project would include milling and resurfacing with asphalt the existing I-129 roadway and shoulders and the US-75/US-77 & Dakota Ave Interchange ramps and shoulders. Bridge structures S129 00008, S129 00107, S129 00123 and S129 00150 on I-129 would undergo repairs. Bridge structures over I-129 at US-75/US-77, S129 00038 & S129 0039 and at C Ave, S129 00201 would also undergo repairs. Additional work would include guardrail improvements and replacing sign trusses over the roadways.
Light Light Italic
Regular Italic
BoldBold Italic
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ROBOTO CONDENSED | Accent copy
Secondary Brand Typefaces
Thin
Light
Regular
Bold
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ROBOTO SLAB | Accent copy
Regular Italic
BoldBold Italic
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ARIAL | Internal use
TRAFFIC VOLUMES
Year 2020 2030
Vehicles Per Day (ADT)
27,140 29,640
% Heavy Trucks 13% 13%
I-129 MM 0.00 - MM 3.08
CONSTRUCTION SCHEDULEConstruction could begin as early as spring 2020 and be completed in approximately 2 years.
ESTIMATED COSTThe estimated cost of the proposed project is approximately $11.6 million. Funding for the project would derive from state and federal funding sources.
ACCOMMODATION OF TRAFFICThe proposed resurfacing and bridge repair work on I-129 and US-75/US-77 would be constructed under traffic with lane closures controlled with approved temporary traffic control; however, local traffic utilizing the ramp accesses along I-129 within the project area would require detours. Designated detours for these ramp accesses would be provided; one would utilize US-75/US-77, N-35, and N-110/G Avenue, the other would utilize US-77, W 28th Street, and Dakota Avenue. The bridge repairs and ramp closures at this location would be separated into three groups, and work on each bridge group would not occur at the same time as another bridge group. These detours could be in place for up to two years. The proposed project would also require detouring C Avenue for repair work on the bridge over I-129. A designated detour would be provided utilizing E 39th Street, Dakota Avenue/IBP Avenue, and E 48th Street. See the maps on the inside of the handout for more details.
Additionally, the project would require short duration night-time detours of I-129 and US-75/US-77 traffic during removal and installation of overhead signs and structures. The detours would be required for eastbound and westbound I-129 and northbound and southbound US-75/US-77. Only one direction of traffic would be detoured per night. Eastbound I-129 and northbound US-75/US-77 would have a designated detour utilizing I-129, N-110, N-35, and US-75/US-77. Southbound US-77 traffic would have a designated detour utilizing W 29th St, Old Hwy 20 and I-129. Westbound I-129 traffic from Iowa would have a designated detour utilizing I-29 and US-77. Westbound I-129 traffic originating in Nebraska would have a designated detour utilizing Dakota Avenue, W 29th St and US-77.
RIGHT-OF-WAYThe proposed project would not require the acquisition of additional property rights. Access to adjacentproperties would be maintained during construction but may be limited at times based on traffic phasingrequirements.
POTENTIAL IMPACTSNo wetland impacts are anticipated. Crystal Cove Park and the Dakota City Trail are located near or within the project area. No impacts to these facilities are anticipated.
PROJECT CONTACTS
Send Comments to:NDOT Public InvolvementSarah Soula1500 Highway 2P.O. Box 94759Lincoln, NE [email protected]
For more information:NDOT District 3 EngineerKevin Domogalla408 S 13th StreetNorfolk, NE [email protected]
Light Light Italic
Regular Italic
BoldBold Italic
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ROBOTO CONDENSED | Accent copy
Secondary Brand Typefaces
Thin
Light
Regular
Bold
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ROBOTO SLAB | Accent copy
Regular Italic
BoldBold Italic
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ABCDEFGHIJKLMNOPQRSTUVWXYZabcdefghijklmnopqrstuvwxyz1234567890
ARIAL | Internal use
Visit http://dot.nebraska.gov/projects/future-projects and click on the “I-129, South Sioux City” link
Bridge Structure S129 00038UTILIZE ORANGE DETOUR
129
Southbound US-77 to eastbound I-129 on ramp & westbound I-129 to
southbound US-77 on ramp
Bridge Structure S129 00123LUTILIZE PURPLE DETOUR
Bridge Structure S129 00039UTILIZE ORANGE DETOUR
Bridge Structure S129 00008RUTILIZE ORANGE DETOUR
DETOUR ROUTES
I-129, SOUTH SIOUX CITY
PROJECT MAP
MM 428.37HWY US-20BEGIN PROJECT
S129 00008LS129 00008R
S129 00038S129 00039
S129 00107L S129 00107R S129 00123L
S129 00123R
S129 00150LS129 00150R
S129 00201
LEGENDPROJECT LOCATION
BRIDGE LOCATION
129
29
76
MM 3.05INTERSTATE I-129END PROJECT
Bridge Structure S129 00008LUTILIZE ORANGE DETOUR
Bridge Structure S129 00201UTILIZE LIGHT PURPLE DETOUR
Bridge Structure S129 00150RUTILIZE PURPLE DETOUR
Bridge Structure S129 00123RUTILIZE PURPLE DETOUR
129
129
129 129
129
129
129
C AV
E.
IBP/
DAKO
TA A
VE.
DAKO
TA A
VE.
IBP
AVE.
129129
G A
VE.
W 29TH ST.
DAKO
TA A
VE.
IBP
AVE.
C AV
E.
E 39TH ST.
E 48TH ST.
Specifics on the bridges and detours can be found on the back page of this handout. Bridges in black font would not need to be detoured. To the right are details on which bridges require detours.
Southbound US-77 to westbound I-129 on ramp
Eastbound I-129 to southbound US-77 on ramp
Northbound US-77 to westbound I-129 on ramp & eastbound I-129 to
northbound US-77 on ramp
Eastbound I-129 exit ramp to IBP Ave
Southbound Dakota Ave to westbound I-129 on ramp
Southbound Dakota/IBP Ave. to eastbound I-129 on ramp
C Ave. bridge over I-129
N
N
N
N
N
N
NN
N N
Images below show the ramp closures associated with bridge repairs.
Bridge Structure S129 00150RUTILIZE PURPLE DETOUR
Bridge Structure S129 00201UTILIZE LIGHT PURPLE DETOUR
35
110