Hydrostatic Test Procedure Site RevD

download Hydrostatic Test Procedure Site RevD

of 23

Transcript of Hydrostatic Test Procedure Site RevD

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    1/23

    Owner

    Torrent Power Generation Limited

    Consultant

    TCE CONSULTING ENGINEERS LIMITED

    MUMBAI

    D 2007/03/22 S,K.AN Revised to reflect to site preparation.

    C 2007/02/22 S,K.AN Revised as Siemens Comment.

    B 2007/02/15 S,K.AN Revised as Siemens Comment.

    A 2007/01/20 S.K. AN First IssueIndex

    Rev.

    Datum

    Data

    bearb.

    Coord.

    gepruft

    Checked Anderungshinweis / Details of RevisionSub-Contractor

    Sub-Contractor document No.

    IKR-PROC-001Urspaung-Nr./Original No.Ursprung/ Original Urspr-PKZ-Nr.

    Orig.-PC

    Projekt/project

    1100 MW SUGEN CCPPPKZ/PC

    IND696Datum Data Name MaBstaB

    Scale A4 UA/DCCType DH01gezeich.Drawn

    bearb,Coord.

    GepruftChecked

    InfalrskennzeichenContents Code

    HA

    AbtlgDept. E932

    Benennung/Title

    HYDROSTATIC TEST PROCEDUREFOR HRSG (SITE)

    Zahl-Nr.

    Reg.No. 223104

    SIEMENS Dienstst./DetE932 UNID 458077234 Index/Rev.D Version

    IND696-DH01-HA-223104

    Ang-VR./Offer-Var. Var./Opt. Blatt-Nr./Page-No.

    23Erstellt mit / designed with:Intergraph

    Ersatz furSupersedes

    Copyright

    (C)Siemens2001

    x

    Inkor Engineering Pvt. Ltd.This document is the property of INKOR, and is to be used only for thepurpose of the agreement with INKOR pursuant to which it is furnished

    Thereproduction,

    transmissionoruseofthisdocu

    mentoritscontentsis

    notpermittedwithoutexpresswrittenauthority.

    Offenderswillbeliablefordamages.

    Allrights,

    includingrightscreatedby

    patentgrantorregistrationofautilitymodelordesig

    n,arereserved.

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    2/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 2 of 23

    TABLE OF CONTENT

    1. INTRODUCTION

    1.1 Purpose

    1.2 Applicable Code and Reference Data for Hydrostatic Test

    1.3 Responsibility

    2. CONDITIONS FOR HYDROSTATIC TEST

    2.1 Preliminary

    2.2 Hydrostatic Test Pressure and Water Volume.

    2.3 Treated Water Requirement

    3. PRE-TEST PREPARATION

    3.1 Safety Valves

    3.2 Test Gauges

    3.3 Temporary Facility

    3.4 Communication

    3.5 Advance Material Readiness

    4. HYDROSTATIC TEST GENERAL REQUIREMENTS

    4.1 Boiler Metal Temperature

    4.2 Sectional Testing of the HRSG System

    4.3 Double Valve Arrangement

    4.4 Communication

    5. PROCEDURE

    5.1 Inspection before Hydrostatic Test

    5.2 Hydrostatic Test

    6. INSPECTION AND TEST

    7. Post Hydrostatic Test Procedures

    8. APPENDICES AND ATTACHMENT

    8.1 The Pressure curve of Hydrostatic Test for HRSG (Typical)

    8.2 Pressure Test Circuit.

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    3/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 3 of 23

    1. INTRODUCTION

    After installation of all pressure parts, Section I of the ASME Boiler and Pressure Vessel Code

    requires that a boiler shall be subjected to a Hydrostatic Pressure Test. This will be conducted at

    a test pressure of 1.5 times the maximum allowable working pressure as stamped on the boiler

    identification plate.

    This procedure is applicable to the hydrostatic test for the pressure parts of HP, IP, LP, CPH

    section for 1100MW SUGEN CCGT HRSG.

    This description only describes the general procedure for the hydrostatic pressure test of the

    HRSG. The detailed description will be contained in an additional detail engineering document.

    1.1 Purpose

    The primary purpose of this procedure is to provide a good quality of performance of HRSG

    before chemical cleaning and commissioning operation. And also to find a fault in site welding

    parts and to repair it.

    1.2 Applicable Code and Reference Data for Hydrostatic Test

    a) ASME Boiler and Pressure Vessel Code Sect. I

    b) ANSI B31.1 (for external piping)

    c) IBR1950

    1.3 Responsibility

    a) Erector is responsible for confirming and controlling the hydrostatic test job is being carriedout according to the prescribed procedure.

    b) The manager in charge of hydrostatic test for HRSG must follow the procedure as

    requested, review and manage in accordance with the prescribed procedure.

    c) Temporary control office should be placed around the pressurization pump. The

    communication system for pressurization and depressurization shall be carried out by

    means of walkie-talkie.

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    4/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 4 of 23

    2. CONDITIONS FOR HYDROSTATIC TEST

    2.1 Preliminary

    Before starting to fill the boiler make sure all drums and headers are cleared of foreign material.

    Close all drains. Open all vents normally used when filling the HRSG (such as superheater link

    vents, economizer link vents, drum vents).

    2.2 Hydrostatic Test Pressure and Water Volume

    System

    Design

    Pressure

    (barg)

    Hydrostatic

    Test Pressure

    (barg)

    Water

    Volume

    (M3)

    Remarks(Test Circuits Color / P&ID No.)

    HP

    (F.W)257 385.5 3 Dark Blue (IND696-XG02-HAD10-220011)

    HP

    (SH,Eva,Eco)145 218 161 Purple (IND696-XG02-HAD10-220011)

    IP

    (F.W,Eco)110 165 3 Blue (IND696-XG02-HAD50-220051 / 220052)

    IP

    (SH,Eva)38 57 43 Mauve (IND696-XG02-HAD50-220051)

    RH

    (RH,HP Bypass Outlet)

    38 57 50Mauve (IND696-XG02-HAD50-220052 /

    HAD10-220011)LP

    (F.W)50 75 2 Light Blue (IND696-XG02-HAD80-220081)

    LP & LBG 11 16.5 47Orange (IND696-XG02-HAD80-220081 /

    LAA20-412001 / LBG10-421111)

    Deae. To Cond. Sys 50 75 3 Brown (IND696-XG02-LAA20-412001)

    Deaerator 8 12 25 Deep Purple (IND696-XG02-LAA20 / 412001)

    CPH 50 75 34 Light Green (IND696-XG02-LCA30-413032)

    HP Bypass Cooling

    water

    58 87 Nil Gray (IND696-XG02-HAD10-220011)

    Total 371

    2.3 Treated Water Requirement

    1) Superheater and Reheater

    - Type : Demineralized water

    - Temperature : 21 C to 49 C

    - Contents : Ammonia 10ppm solution

    Hydrazine 200ppm solution

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    5/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 5 of 23

    - pH : 10

    NOTE : Demineralized or Condensate quality water is defined as containing no more than

    1 ppm (1 / ) of identifiable solids and essentially a zero concentration (orlowest detective level ) of organic material.

    CAUTION : The use of fill water, treated with solid chemicals, should be avoided.

    Deposits of solid materials in superheaters can be detrimental from heat transfer

    and corrosion standpoints. Superheaters containing stainless steel tubing are

    particularly vulnerable to stress corrosion cracking in the presence of such

    chemicals as caustic and chlorides.

    2) Remainder of HRSG unit:

    Fill with treated condensate or treated demineralized water, or, if not available, with a

    clean source of filtered water with 10 ppm (10 cm3/m3) of ammonia and 200 ppm (200

    cm3/m3) of hydrazine

    The water conditions as stated above can be adjusted by pouring chemicals, Ammonia in the

    temporary storage tank i.e. condensate storage tank.

    The water can be treated with only ammonia. This will however reduce the period of time that

    this water can be left in the system.

    3. PRETEST PREPARATION

    3.1 Safety Valves

    All safety valves will be checked for having the Hydro Plug inserted if applicable. TheCompression screw on the Safety Valve must be turned clockwise until the locknut makes up on

    the Yoke.

    3.2 Test Gauges

    - Only recently calibrated test gauges are to be used.

    - Dial pressure gauges used in the testing shall preferably have dials graduated over their

    entire range of about double the intended maximum test pressure, but in no case shall the

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    6/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 6 of 23

    range be less than 1 times that pressure.

    - There should be at least two (2) pressure gauges installed, one of which is at the highest

    point of the system, the other gauge is to be installed at the Hydro-Pump.

    3.3 Temporary facility

    Description Capacity Qty Remarks

    D.M Pump 1 Water filling for Temp. Tank

    Filling Water Pump 20 kg/cm2g 1 Water filling for System

    Pressurizing pump 450 kg/cm2g 1 Pressurizing

    Temporary Water Tank 10 m3

    1 Pressurizing

    Air Compressor 10 kg/cm2g 1

    Fire Hose 2 ~ 20m 5 Water filling for System

    High Pressure Hose ~ Multitude

    Pressurizing

    Temporary Piping Water filling & Pressurizing

    3.4 Communication

    All communication between the boiler control station and the Hydro-Pump station will be with

    Radios. Back-up radios are to be readily available at each control station.

    - Radio : More than 4 walkie-talkie

    - Location : Control center (filling water pump or pressurization pump area) Top (pressure

    gauge, thermometer and vent area) Inspector

    - Inspector and recorder must be placed in a convenient area to communicate for the

    pressure gauge, inspection of thermometer and control center.

    3.5 Advance Material Readiness

    Scaffolds, lights and repair tools are to be ready at time of Hydro-Test.

    4. HYDROSTATIC TEST GENERAL REQUIREMENT

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    7/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 7 of 23

    4.1 Boiler Metal Temperatures

    The metal temperature of all components to be Hydro-Tested must be at least 21 C (70 F)

    before applying the Hydro Test pressure but shall not exceed 48.8 C(120F)

    4.2 Sectional Testing of the HRSG Systems

    When Hydrostatic Testing is to be done on a section of the system which is not directly linked to

    a lower than test pressure designed system, but segregated by the test boundary isolation, all

    vent valves in the lower pressure designed system must be open to avoid over pressurization of

    the same.

    4.3 Double Valve Arrangements

    - All components tested will be as indicated on the flow chart or P&ID for the specific test.

    - Always open the root valve fully and throttle with the down stream valve when

    depressurizing or draining a system.

    4.4 Communication

    All communication / Co-ordination concerning the Hydro-Test has to be addressed through

    designated personnel.

    5. PROCEDURE

    5.1 Inspection before Hydrostatic Test

    5.1.1 Check for any foreign materials of tools, clothes and other things inside the drum, heater,

    manifolds etc. and then close the manholes and all holes of the pressure.

    5.1.2 The pressure gauge to be used for Hydro-Test should exactly be calibrated. In addition to

    this, the filling piping and pressurization shall be checked.

    5.1.3 It is very important to check whether the instruments and the temporary construction piping

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    8/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 8 of 23

    are free from foreign particulate matters.

    5.1.4 The safety valves gagged. (when the worker install safety valve, he must check whether

    the test plug is inserted or not, and if inserted, a tag with No operating must be attached)

    5.1.5 Before filling , to close the block valves and open the vent valve of each system,

    Authorization of concerned in charge is required to be done in the valve operation list.

    5.1.6 In case of deaerator, Spray valve & tray should be separated to avoid foreign material. But

    if spray valve is installed in deaerator, take a note water filling must not be done through

    spray valve.

    5.2 Hydrostatic test

    5.2.1 Water filling

    In case of non availability of condensate transfer pump, which are to fill the water, filling of

    water shall be done by temporary filling water pump shall be installed in each system as

    paragraph 5.2.1.2.

    5.2.1.1 In advance, in the close condition of the specified valve, it has to be checked then the

    signature on the control list is requested under the open condition of top air vent valve. If

    the above condition is pleased it may be filled for water washing.

    5.2.1.2 It is a fundamental rule to fill the inside of HRSG through specified valves for each

    system(HP, IP, LP, CPH and Deaerator).

    5.2.1.3 If water is seen being filling from bottom valve, each air vent valve shall be closed on

    sequentially till top air vent valve at that time a full filling should be confirmed at top air

    vent valve.

    5.2.2 Pressurization

    5.2.2.1 HP F.W. Section

    a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable working

    pressure(design pressure 257barg).

    b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    9/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 9 of 23

    pressure (385.5 barg) ofHP F.W. section and held for min. 30 minutes. The pressure

    must be under control at all times and shall never exceed by more than 6%(23.1 bar)

    of the desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2~3 kg/cm^2/min. (depressurization rate) till the

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure.

    f) If the result during checking is under the normal condition, the pressure shall be

    reduced by 3~5 kg/cm^2/min. by opening a drain valve.

    5.2.2.2 HP section

    a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable working

    pressure(design pressure 145 barg).

    b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test

    pressure (217.5 barg) ofHP section and held for min. 30 minutes. The pressure must

    be under control at all times and shall never exceed by more than 6%(13.0 bar) of

    the desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2~3 kg/cm^2/min. (depressurization rate) till the

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure.

    f) If the result during checking is under the normal condition, the pressure shall be

    reduced by 3~5 kg/cm2^/min. by opening a drain valve.

    5.2.2.3 IP F.W Section

    a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable working

    pressure(design pressure110 barg).

    b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test

    pressure (165 barg) ofIP F.W. section and held for min. 30 minutes. The pressure

    must be under control at all times and shall never exceed by more than 6%(9.9 bar)

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    10/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 10 of 23

    of the desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2~3 kg/cm^2/min. (depressurization rate) till the

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure

    f) If the result during checking is under the normal condition, the pressure shall be

    reduced by 3~5 kg/cm^2/min. by opening a drain valve.

    5.2.2.4 IP Section

    a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable

    working pressure(design pressure 38 barg).

    b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test

    pressure (57 barg) ofIP section and held for min. 30 minutes. The pressure must be

    under control at all times and shall never exceed by more than 6%(3.4 bar) of the

    desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2~3 kg/cm^2/min. (depressurization rate) till the

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure.

    f) If the result during checking is under the normal condition, the pressure shall be

    reduced by 3~5 kg/cm2^/min. by opening a drain valve.

    5.2.2.5 LP F.W. Section

    a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable

    working pressure(design pressure 50 barg).

    b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test

    pressure (75 barg) ofLP F.W section and held for min. 30 minutes. The pressure

    must be under control at all times and shall never exceed by more than 6%(4.5 bar)

    of the desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2~3 kg/cm^2/min. (depressurization rate) till the

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    11/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 11 of 23

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure.

    f) If the result during checking is found in normal condition, the pressure shall be

    reduced by 3~5 kg/cm^2/min. by opening a drain valve.

    5.2.2.6 LP section

    a) The pressure should be increased by 2~3 kg/cm^2/min. up to Max. allowable

    working pressure(design pressure 11 barg).

    b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test

    pressure (16.5 barg) ofLP section and held for min. 30 minutes. The pressure must

    be under control at all times and shall never exceed by more than 6%(1 bar) of the

    desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2 ~ 3 kg/cm^2/min (depressurization rate) till the

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure.

    f) If the result during checking is found in normal condition, the pressure shall be

    reduced by 3~5 kg/cm^2/min. by opening a drain valve.

    5.2.2.7 CPH section

    a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable

    working pressure (design pressure 50 barg).b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test

    pressure(75 barg) ofCPH section and held for min. 30 minutes. The pressure must

    be under control at all times and shall never exceed by more than 6% (4.5 bar) of the

    desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2 ~ 3 kg/cm^2/min (depressurization rate) till the

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    12/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 12 of 23

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure.

    f) If the result during checking is found in normal condition, the pressure shall be

    reduced by 3~5 kg/cm^2/min. by opening a drain valve.

    5.2.2.8 Deaerator section

    a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable

    working pressure (design pressure 8 barg).

    b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test

    pressure(12 barg) ofDeaerator section and held for min. 30 minutes. The pressure

    must be under control at all times and shall never exceed by more than 6% (0.7 bar)

    of the desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2 ~ 3 kg/cm^2/min (depressurization rate) till the

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure.

    f) If the result during checking is found in normal condition, the pressure shall be

    reduced by 3~5 kg/cm^2/min. by opening a drain valve.

    5.2.2.9 HP Bypass Cooling Water Section

    a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable

    working pressure (design pressure 58 barg).

    b) Observe test section for any obvious leaks.

    c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-testpressure(87 barg) ofHP Bypass cooling water section and held for min. 30 minutes.

    The pressure must be under control at all times and shall never exceed by more

    than 6% (5.5 bar) of the desired Hydrostatic Test Pressure.

    d) The pressure shall be reduced by 2 ~ 3 kg/cm^2/min (depressurization rate) till the

    design pressure by opening drain valve.

    e) A close visual inspection of all boiler pressure parts and connecting piping shall be

    carried out after the pressure was lowered from hydrostatic test pressure to design

    pressure.

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    13/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 13 of 23

    f) If the result during checking is found in normal condition, the pressure shall be

    reduced by 3~5 kg/cm^2/min. by opening a drain valve.

    6. INSPECTION AND TEST

    6.1 All welding points, valves and hangers which were welded on pipe must be inspected

    during the hydrostatic test. During the inspection if there is an abnormal condition the

    inspection should be stopped and a repair work should be done.

    6.2 The test data should be recorded at an interval of 5 minutes but not less than 5 measuring

    data in each case during hold time and during subsequent inspection, and the basis of the

    pressure is the pressure gauge installed at the highest point of the system, and

    temperature should be recorded from the temporary temperature gauge installed near the

    pressure gauge.

    6.3 The inspection must be witnessed as per the inspection points in hydro test inspection

    table.

    NOTE : Hydrostatic test pressure should not be applied to the boiler of the metal

    temperature of the pressure parts is below 70 F ( 21 C ). Since there is generally

    some time delay between the hydrostatic test and the initial boiling out and

    cleaning for the boiler the unit should remain full of water, air should not be allowed

    to enter.

    7. Post Hydrostatic Test Procedures

    7.1 Hydrostatic test water will be left in the system for preservation. Pressure approximately 3to 5 psig (21 to 34 kPa) to be maintained, checked and recorded on a regular basis.

    7.2 Remove all hydrostatic test plugs and gags from the safety valves prior to starting up the

    unit.

    NOTE: Since there is generally some time delay between the hydrostatic test and the initial

    boiling out and acid cleaning of the HRSG, it should remain full of water; air should

    not be allowed to enter.

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    14/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 14 of 23

    8. ATTACHMENT

    8.1 The pressure curve of hydrostatic test for HRSG

    A. HP F.W Section pressure curve (Typical)

    B. HP Section pressure curve (Typical)

    C. LP Section Pressure Curve(Typical)

    D. LP F.W Section Pressure Curve (Typical

    E. CPH Section pressure curve (Typical)

    F. IP & RH Section Pressure Curve (Typical)

    G. IP F.W Section Pressure Curve (Typical)

    H. Deaerator Section Pressure Curve (Typical)

    I. HP Bypass Cooling Water Section Pressure Curve (Typical)

    8.2 Pressure Test Circuit ------- 1 Set

    Red Color Marking(golden joint) means pipe will be blanked before hydrostatic test and

    RT will be done for weld joint after Hydrostatic test.

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    15/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 15 of 23

    Attachment 8.1. The pressure curve of hydrostatic test for HRSG

    A HP F.W. Section Pressure Curve (Typical)

    0 50 100 150 200 250 300

    0

    50

    100

    150

    200

    250

    300

    350

    400

    Pres

    sure

    [barg]

    Time Hours

    Min.30 Minutes

    At 385.5 barg(393.4 / )

    (hydrostatic Test Pressure)

    Inspection Time

    At 257 barg

    (261.1 / )

    (Design Pressure)

    Pressure Up Pressure Down

    Time [min]

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    16/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 16 of 23

    B. HP Section Pressure Curve (Typical)

    Pressure U Pressure Down

    Min. 30 Minutes

    At 218 barg (222.5 / )

    (Hydrostatic Test Pressure)

    Inspection Time

    At 145 barg

    (148.0 / )

    (Design Pressure)

    P

    ressure

    [barg]

    0

    50

    100

    150

    200

    250

    300

    Time [min]

    0 50 100 150 200 250

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    17/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 17 of 23

    C. LP Section Pressure Curve (Typical)

    Pressure U Pressure Down

    0 20 40 60 80 100

    0

    4

    8

    12

    16

    20

    24

    Pressure

    [barg]

    Time [Min]

    Min. 30 Minutes

    At 16.5 barg(16.8 / )

    (Hydrostatic Test Pressure)

    Inspection TimeAt 11 barg

    (12 / )

    (DesignPressure)

    120

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    18/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 18 of 23

    D. LP F.W Section Pressure Curve (Typical)

    Min. 30 Minutes

    At 75 barg(76.5 / )

    (Hydrostatic Test Pressure)

    Inspection TimeAt 50 barg

    (51.0 / )

    (DesignPressure)

    Pressure Pressure Down

    0 20 40 60 80 100

    0

    15

    30

    45

    60

    75

    90

    Time [Min]

    Pressure

    [barg]

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    19/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 19 of 23

    E. CPH Section Pressure Curve (Typical)

    Min. 30 Minutes

    At 75 barg(76.5 / )

    (Hydrostatic Test Pressure)

    Inspection TimeAt 50 barg

    (51.0 / )

    (DesignPressure)

    Pressure Pressure Down

    0 20 40 60 80 100

    0

    15

    30

    45

    60

    75

    90

    Time [Min]

    P

    ressure

    [barg]

    120

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    20/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 20 of 23

    F. IP & RH Section Pressure Curve (Typical)

    Min. 30 Minutes

    At 57 barg(58.1 / )

    (Hydrostatic Test Pressure)

    Inspection TimeAt 38 barg

    (38.8 / )

    (DesignPressure)

    Pressure U Pressure Down

    0 20 40 60 80 100

    0

    10

    20

    30

    40

    50

    60

    Pressure

    [barg]

    Time [Min]

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    21/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 21 of 23

    Time [min]

    G. IP F.W Section Pressure Curve (Typical)

    0 30 60 90 120 150 180

    0

    25

    50

    75

    100

    125

    150

    175

    Pressure

    [barg

    ]

    Min.30 Minutes

    At 165 barg(168.4 / )

    (Hydrostatic Test Pressure)

    Inspection Time

    At 110 barg

    (112.2 / )

    (Design Pressure)

    Pressure Up Pressure Down

    200

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    22/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc.No : IKR-PROC-001Rev.0 Page 22 of 23

    H. Deaerator Section Pressure Curve (Typical)

    Pressure U Pressure Down

    0 15 30 45 60 750

    2

    4

    6

    10

    12

    8

    Pressure

    [barg]

    Time [Min]

    Min. 30 Minutes

    At 12 barg(12.3 / )

    (Hydrostatic Test Pressure)

    Inspection Time

    At 8 barg

    (8.2 / )

    (DesignPressure)

  • 7/29/2019 Hydrostatic Test Procedure Site RevD

    23/23

    1100MW SUGEN CCPP HRSG

    Hydrostatic Test Procedure for HRSG (Site) Doc No : IKR PROC 001

    I. HP Bypass Cooling Water Section Pressure Curve (Typical)

    Min. 30 Minutes

    At 87 barg(88.8 / )

    (Hydrostatic Test Pressure)

    Inspection Time

    At 58 barg

    (59.2 / )

    (DesignPressure)

    Pressure Pressure Down

    0 20 40 60 80 100

    0

    15

    30

    45

    60

    75

    90

    Time [Min]

    Pressure

    [barg]