HVDC P3 Project - · PDF fileHVDC Switchyard Reconfiguration HAY & BEN Bipole Outage 29 Nov-5...
Transcript of HVDC P3 Project - · PDF fileHVDC Switchyard Reconfiguration HAY & BEN Bipole Outage 29 Nov-5...
1
HVDC P3 Project
CIAG Update 2 December 2011
Project Progress –Update
2
•HAY Converter Transformer Assembly
•HAY Thyristor Valve Assembly
•HAY & BEN Smoothing Reactor Installation
•BEN Converter Transformer delivery to site
Andrew Gard
HVDC Switchyard Reconfiguration HAY & BENExisting Configuration
1. P2 HVDC Bus
2. P2 DC Filter
3. P2 Neutral Bus
4. P1 HVDC Bus
5. P1 DC Filter
6. P1 Neutral bus
7. Common Neutral and E/L
Bus
1
2
3
4
56
7
HVDC Switchyard Reconfiguration HAY & BEN
Bipole Outage 29 Nov-5 Dec
Installation of Temporary bypass
cables
Relocation of Electrode line bus
Temporary relocation of capacitor
P1.C1
HVDC Switchyard Reconfiguration HAY & BEN
High level Breakdown of Stages
Bypass cable installations
Relocation of Electrode line bus (4)
Install DC Filter Resistors
Relocate P2 HVDC Bus (1B,8)
Install P3 HVDC Bus (4,3,1A)
Install High Speed Electrode Line Switch
(6)
Install Surge Arrester (6)
Install Station Ground Switch (7)
Install P3 High Speed Switch (2)
Install P2 High Speed Switch (5A,5B)
Final DC yard commissioning
Multiple short duration/weekend
outages Feb –May 2012
Pole 3 CommissioningHVDC Transfer requirements
2012
6
Example
Years
7
-400
-200
0
200
400
600
800
1000
HV
DC
No
rth
Tra
ns
fer
(MW
)
Time - Sept. To Dec.
2002 2005 2008
• Every year is different.
• An “average” year is unlikely.
• We won‟t know what transfers are likely until closer to the time.
Test Schedule
8
-1200
-900
-600
-300
0
300
600
900
1200
No
rth
Tra
nsfe
r (M
W)
Time - Sept. To Dec.
- 126 Tests
- 42 Days (6 Sept-24 Oct)
-Red Bars Are Monopole
- Yellow Bars Are Round Power/Bipole- Tests In Approximate Order Only
- Some Can Be Completed Simultaneously
Average Transfer
Analysis
9
-100
0
100
200
300
400
500
600
700
No
rth
Tra
nsfe
r (M
W)
Time - Sept. To Dec.
-Gray is what an average year would look like.
-Blue is a rolling average showing the trend.
-Green is the average transfer for all data.
-Yellow is the average daily peak and trough.
-The averages comes from the years 2002 to 2010
Test Schedule With Average Transfers• No naturally occurring South
transfer.
• For the series of low north
tests, the HVDC would be
constrained back.
• The medium north flow tests
are likely to fall within
scheduled transfer.
• The high and overload tests
will require a much larger
transfer than scheduled.
• The total net transfer will be
in the vicinity of 70 GWh
North.
• High level of reserve
required for the monopole
high power transfer tests
10
-1200
-900
-600
-300
0
300
600
900
1200
No
rth
Tra
nsfe
r (M
W)
Time - Sept. To Dec.
•The red lines are the highest and lowest transfers
between 2002 and 2010.
•The yellow lines are the average daily peak and
trough.
•The green line is the average transfer for all data.
Assumptions
• Assuming each test takes four hours. In reality the test time will vary.
The overload tests will be as short as half an hour.
• Assumes at least three tests are done per day. Some tests will be
done simultaneously which will save time, however some tests may
need to be repeated.
• The GWh estimate is based on these two assumptions.
11
Test Program Summary
12
Monopole
Round Power
Bipole
Total
Tests
Number
of Days
North Transfer
17 4 21 7
HVDC will need to be constrained back for this series of tests. The majority of tests are at
100MW but will need to operate as low as 35MW for others. The 21 tests are likely to be
run over seven days, taking up to 84 hours. The total transfer will be approximately 6GWh.
South Transfer
5 5 10 4
For this section of tests the HVDC needs to operate in south transfer. Again the tests range
from 35MW to 100MW. The ten tests will likely take three to four days taking up to 40
hours. The total south transfer be approximately 3GWh.
Monopole
Round Power
Bipole
Total
Tests
Number
of Days
North Transfer
10 24 34 11
If next year is an average year, then this sequence of tests are all likely to fall within normal
scheduled transfer. The tests to be conducted will be a number of power levels up to
350MW. The 34 tests will likely be completed over 11 days, taking up to 136 hours and
transferring approximately 43GWh.
South Transfer
2 12 14 5
The HVDC will again need to operate in south transfer. The tests are of the same power
levels as the medium north transfer. It will take approximately 56 hours over five days
transferring 17GWh.
26GWh
Number of TestsImplications
Net
Transfer
North
3GWh
Low Load - 0 to 100MW
Net
Transfer
North
Medium Load - 101 to350MW
ImplicationsNumber of Tests
13
Monopole
Round Power
Bipole
Total
Tests
Number
of Days
North Transfer
8 13 21 7
This section of tests is almost entirely 700MW. If next year is average we expect the daily
peak transfer to be between 400MW and 500MW. So for this section the HVDC will need
to operate in north transfer up to 300MW higher than usually scheduled. The 21 tests are
expected take close to 84 hours over seven days. Transferring about 71GWh north.
South Transfer
5 6 11 4
HVDC will need to operate in south transfer up to 700MW. The 11 tests are likely to take
around 44 hours spread over four days. The south transfer will be close to 30GWh.
Monopole
Round Power
Bipole
Total
Tests
Number
of Days
North Transfer
0 11 11 4
HVDC will need to be transferring power levels up to 1000MW. This is around 600MW
higher than what would be expected to be scheduled. The duration of these tests will not
exceed 30 minutes. The 11 tests will likely be conducted in the space of four days taking six
hours. The total transfer will be roughly 5GWh.
South Transfer
0 4 4 2
Again these four tests require the HVDC to operate in a south transfer at power levels up to
1000MW. All four tests should be able to be completed in a total of two hours over one or
two days. The south transfer for this series of tests is going to be in the vicinity of 2GWh.
Net
Transfer
North
41GWh
Net
Transfer
North
3GWh
Overload >700MW (Half an hour)
High Load - 351 to 700MW
Implications
Implications
Number of Tests
Number of Tests
Test Program Summary
14
•Further analysis against high and low storage
scenarios
•Develop detailed test schedule and confirm
commissioning roundpower options with Siemens
•Assess P3 secondary risk performance with the
System Operator
Test Program Summary
15
Commissioning requires an „industry‟ solution.– HVDC Transfer
– Reserve availability
Utilise the market – Minimum impact/disruption on day to day market operation
– Utilise commercial behaviour
Issues to be considered– Contracting for availability -adding certainty to completion of test programme
– Impact of unfavourable system conditions
Timeline 2012Dec-Jan Confirm test plan, HVDC transfer and reserve requirements
Feb-Apr Industry briefings on commissioning, HVDC transfer and reserve requirements
May-Jun Tender for availability where appropriate
Jul Contracts in place. Market based exercise
Aug Ready for P3 commissioning
HVDC Transfer and Reserve Requirements