HV Substation Interface Activities: Safety/Operational Requirements
Produced By: C Doyle
Contents
• Activity 1: Installation• Activity 2A: Cable termination HV & LV• Activity 2B: Unlicensed Commissioning• Activity 3: Back Energisation• Activity 4: Commissioning• Activity 5: Post COD
HV INTERFACE ACTIVITY 1: INSTALLATION
HV Substation Interface Activities
HV Interface: Activity 1
Installation• Civil works (cable ducts)• Cable Support Install• Scaffolding• HV Cable Pull• LV Cable Pull• Earthing (assume PS Earth is Tested/Complete)• Install APDF Remote I/O Panel• NG Unlicensed Relays Installation in M1/M2
HV Interface Activity 1: Installation Safety/Procedural Boundaries
X190
X196
X194
X193
F19A
Cable bushing
Sub FenceSUBSTATION POWERSTATION
SAFETY:• NG Safety Rules Apply• NG Performs CPS• SAP (P.Monaghan, Brian
Sleigh)• Implementation Safety
Coordinator (P. Monaghan? TBC)
• Following Review of RAMS, LWC may be issued
• Point of isolation issued for work on LV systems/ System Connection Rules
SAFETY:• APDF work is undertaken
under APDF Local Safety Instructions/Safety Rules
• Rules submitted to NG For Review
• RAMS submitted to NG 3 weeks prior to work taking place for review by NG
Operational:• APDF work under a point
of isolation for any LV work utilising their own Safety Instructions
APDF Working Party Requires:NG Persons NG Competent Persons (key Holder also)Approved scaffolders for NG Safety Rules
Operational:• NG Local Instructions • NG Performs CPO
Notes:• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise.
• Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme.
• Note: If earths are not terminated insulated working must be carried out under NSI 5,6 &24, RAMS should be based on this (preferably not done until earths are connected for safety)
Circuit equipment on Power station side
Surge Arrestors
Cable Protected Both Ends
Module M1/M2
Cable Pulled Not Terminated
CCT 1 & CCT 2 C&P Module
Esbi Civil Contractor RequiredNG Persons NG Competent Persons (key Holder also)
NG Working Party Requires:• To work under APDF Permit• Trained as person and work under APDF competent
person
Actions• APDF to confirm what qualifications/inductions NG Working Party Requires to
install Protection Relays in M1/M2 and process for submitting RAMS• APDF to confirm list of personnel undergoing Person/Competent Person
training from AP and DF and that a key holder will also be provided• APDF to confirm the qualifications of their contractors who will access the
substation for cable pulling HV/LV/I&C, cable support install and terminations• APDF RAMs to be submitted to NG a minimum of 3 weeks prior to proposed
work, this is to be coordinated through the TP106/153 meetings on site. ESBI remind APDF of site RAMS review period by OE prior to submission to NG.
• A safety inaugural meeting will be required to take place 6 weeks prior to any works commencing, APDF to advise when this should be scheduled
• APDF to review programme submitted under APDF/CPL/1187 and advise on current programme as changes should be coordinated through the TP meetings with NG
HV INTERFACE ACTIVITY 2A: CABLE TERMINATION HV & LV
HV Substation Interface Activities
HV Interface: Activity 2A
Cable Termination: HV & LV• Install GIS Sealing End (ABB Interface)• HV Cable Testing• Install HV Cable Termination• Earth Terminations (cable)• Scaffolding• LV Cable Testing and Terminations
HV Interface Activity 2A: HV & LV Cable Terminations
X190
X196
X194
X193
F19A
Cable bushing
Sub FenceSUBSTATION POWERSTATION
SAFETY:• NG Safety Rules Apply• NG Performs CPS• SAP (P.Monaghan, Brian
Sleigh)• Implementation Safety
Coordinator (P. Monaghan? TBC)
• Following Review of RAMS, LWC may be issued
• Point of isolation issued for work on LV systems/ System Connection Rules
SAFETY:• APDF work is undertaken
under APDF Local Safety Instructions/Safety Rules
• Rules submitted to NG For Review
• Trafo Compound locked and under NG Safety Rules
Operational:• APDF work under a point
of isolation for any LV work utilising their own Safety Instructions
APDF Working Party Requires:NG Persons NG Competent Persons (key Holder also)Approved scaffolders for NG Safety Rules
Operational:• NG Local Instructions
Apply for Isolations• HVSCC Required to bring
cable and sealing ends in remote compound (Trafo) under NG CPO
• NG Performs CPO
Notes:• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise.
• Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme.
• Note: If earths are not terminated insulated working must be carried out under NSI rules, RAMS should be based on this (preferably not done until earths are connected for safety)
Circuit equipment on Power station side
Module M1/M2CCT 1 & CCT 2 C&P Module
No System Connection 3.5m Safety Distance
HV INTERFACE ACTIVITY 2B: UNLICENSED COMMISSIONING PHASE 1
HV Substation Interface Activities
HV Interface: Activity 2B
Unlicensed Commissioning: (LV Cable terminations Complete, Prior to HV Cable)• Commissioning of signals between PP & SS
(Phase 1)
HV Interface Activity 2B: Unlicensed Relay Commissioning Phase 1
X190
X196
X194
X193
F19A
Cable bushing
Sub FenceSUBSTATION POWERSTATION
SAFETY:• NG Safety Rules Apply• NG Performs CPS• SAP (P.Monaghan, Brian
Sleigh)• Implementation Safety
Coordinator (P. Monaghan? TBC)
• Following Review of RAMS, LWC may be issued
SAFETY:• NG work in M1/M2
under APDF rules• Further coordination
required in working group meetings
Operational:• Discuss with APDF. How
will this interface be managed (Phase 1)
NG Working Party Requires:• To work under APDF Permit• Trained as person and work under APDF competent
person
Operational:• NG Local Instructions
Apply for Isolations• NG Performs CPO• SRS requires discussion
at TP153 (LV equipment)
Notes:• SRS requires discussion at TP153 (LV equipment)• Programme of work to be managed through TP106 and
specific working groups. APDF must submit detailed activity programme.
• NG will work under APDF rules in Module M1/M2Circuit equipment on Power station side
Module M1/M2CCT 1 & CCT 2 C&P Module
No System Connection 3.5m Safety Distance
Actions
• NG Unlicensed to confirm power requirements for relays and APDF to ensure these are available for programmed dates
• NG unlicensed to provide commissioning plan for Phase 1 & Phase 2 commissioning
HV INTERFACE ACTIVITY 3A: BACK ENERGISATION CABLE SOAK
HV Substation Interface Activities
HV Interface: Activity 3
Back Energisation: Cable Soak
• Switch in cable for 24hr soak test• HVSCC issued and Revert Back to busbar
disconnects for further back energisation under NG CPS and APDF CPO
HV Interface Activity 3: Back Energisation Cable Soak
X190
X196
X194
X193
F19A
Cable bushing
Sub FenceSUBSTATION POWERSTATION
SAFETY:• NG Safety Rules Apply• NG Performs CPS• SAP (P.Monaghan, Brian
Sleigh)• Implementation Safety
Coordinator (P. Monaghan? TBC)
• Following Review of RAMS a RISSP may be issued
SAFETY:• APDF work is undertaken
under APDF Local Safety Instructions/Safety Rules
• Rules submitted to NG For Review
• Trafo Compound locked and under NG Safety Rules
Operational:• National Grid are CPO
APDF Working Party Requires:NG Persons NG Competent Persons (key Holder also)
Operational:• NG Local Instructions
Apply for Isolations• HVSCC Required to bring
cable and sealing ends in remote compound (Trafo) under NG CPO
• NG Performs CPO
Notes:• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise.
• Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme.
• Immediately after cable soak the control boundary moves to HV disconnects under a HVSCC, NG relinquish CPO role and O&M undertake this role under their local instructions which have been approved by NG
• NG retain the CPS role under contract to Asset Management
• Partial Discharge monitoring/testing to be discussed at TP106
Circuit equipment on Power station side
Module M1/M2CCT 1 & CCT 2 C&P Module
No System Connection 3.5m Safety Distance
HV INTERFACE ACTIVITY 3: BACK ENERGISATION
HV Substation Interface Activities
HV Interface: Activity 3
Back Energisation: GSUT Energisation, LV GCB, 6.6kV (as per back energisation procedure)
• Energise GSUT, IPB’s, HV Side of GCB, UT up to 6.6kV Incoming Breakers
HV Interface Activity 3B: Back Energisation: GSUT Energisation, LV GCB, 6.6kV (as per back energisation procedure)
X190
X196
X194
X193
F19A
Cable bushing
Sub FenceSUBSTATION (O&M Operational CPO)
POWERSTATION
SAFETY:• NG Safety Rules Apply• NG Performs CPS• SAP (P.Monaghan, Brian
Sleigh)• Implementation Safety
Coordinator (P. Monaghan? TBC)
• Following Review of RAMS a RISSP may be issued (type of safety document to be discussed)
SAFETY:• APDF work is undertaken
under APDF Local Safety Instructions/Safety Rules
• RISSP Issued and taken by O&M CPO, RISSP integrated into APDF safety rules
Operational:• O&M are now CPO
under their operational procedures/local instructions
APDF Working Party in Substation Requires:NG Persons NG Competent Persons (key Holder also)APDF liaise with O&M CPO/Requesting Safety officer
Operational:• HVSCC agreed with SRS
defined as O&M CPO• Contact persons agreed
in SRS and through compliance process between O&M CPO and NG Control Centre
Notes:• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise.
• Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme.
• NG retain the CPS role under contract to Asset Management
• O&M are CPO
Circuit equipment on Power station side
Module M1/M2CCT 1 & CCT 2 C&P Module
O&M Personnel:NG Persons (to access substation)Competent PersonsAuthorised PersonsRequesting Safety Officer (can be the CPO) but must be trained to level to receive a RISSP
Control/Safety/Maintenance Ownership Boundaries
X190X196
X194
X193
CCGT Equipment
Sub Fence
NG Safety Rules /Maintenance
NG Ownership
NG Operational
APDF Safety rules
O&M Ownership
O&M Operational
HV Safety/Operational Interface Protocol
Warwick
Substation
Power Station
NG
O&M
APDF
HV Control Person/ CPO
CPOCPS
Implementing Safety
Coordinator/ SAP
APDF HV Interface manager
TP106/TP153/Working Group meetings
Planned Operational Switching/ Outages
Client Review
Planned Outages
Planned Operational Switching
Emergency Switching
Planned Switching Communications
Switching Request/ RISSP Issue
Emergency Switching
Planned Switching
Actions
• O&M Safety Rules/HV Switching/RISSP Process (including third party involvement) to be finalised and submitted to NG for review ASAP
• O&M to confirm timelines for training of Authorised Personnel for HV Control Persons
• Switching should be remote i.e. DCS• APDF to include a HV Switching Interface protocol in
safety rules to include RISSP process• CPL/O&M to confirm that HV Busbar Disconnects are to
be switched by NG and not at DCS.
HV INTERFACE ACTIVITY 4: COMMISSIONING
HV Substation Interface Activities
HV Interface: Activity 4Commissioning
• Commissioning as Per APDF Programme• Phase 2 Commissioning of Unlicensed Protection Relays (load)• Full Control & Protection Commissioning• Plant functional tests• Grid Compliance Tests• Performance Test• Reliability Run• Handover
HV Interface Activity 4: Commissioning
X190
X196
X194
X193
F19A
Cable bushing
Sub FenceSUBSTATION (O&M Operational CPO)
POWERSTATION
SAFETY:• NG Safety Rules Apply• NG Performs CPS• SAP (P.Monaghan, Brian
Sleigh)• Implementation Safety
Coordinator (P. Monaghan? TBC)
• Following Review of RAMS a RISSP may be issued (type of safety document to be discussed)
SAFETY:• APDF work is undertaken
under APDF Local Safety Instructions/Safety Rules
• RISSP Issued and taken by O&M CPO, RISSP integrated into APDF safety rules
Operational:• O&M are now CPO
under their operational procedures/local instructions
APDF Working Party in Substation Requires:NG Persons NG Competent Persons (key Holder also)APDF liaise with O&M CPO/Requesting Safety officer
Operational:• HVSCC agreed with SRS
defined as O&M CPO• Contact persons agreed
in SRS and through compliance process between O&M CPO and NG Control Centre
Notes:• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise.
• Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme.
• NG retain the CPS role under contract to Asset Management
• O&M are CPO• O&M are working in APDF working parties for power
station commissioning and are trained under APDF Safety Rules
Circuit equipment on Power station side
Module M1/M2CCT 1 & CCT 2 C&P Module
O&M Personnel:NG Persons (to access substation)Competent PersonsAuthorised PersonsRequesting Safety Officer (can be the CPO) but must be trained to level to receive a RISSP
HV Interface: Activity 5
Post COD• Normal Operation
Control/Safety/Maintenance Ownership Boundaries
X190X196
X194
X193
CCGT Equipment
Sub Fence
NG Safety Rules /Maintenance
NG Ownership
NG Operational
O&M Ownership
O&M Operational
O&M Safety Rules /Maintenance
HV Safety/Operational Interface Protocol
Warwick
Substation
Power Station
NG
O&M
HV Control Person/ CPO
CPOCPS
Implementing Safety
Coordinator/ SAP
Planned Outages
Planned Operational Switching
Emergency Switching
Planned Switching Communications/TOGA
Switching Request/ RISSP Issue