Huzurnagar 220kV line-BOQ.xls

download Huzurnagar 220kV line-BOQ.xls

of 22

  • date post

    04-Jun-2018
  • Category

    Documents

  • view

    219
  • download

    3

Embed Size (px)

Transcript of Huzurnagar 220kV line-BOQ.xls

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    1/22

    Sl. No Description Total Cost Rs.

    SCHEDULE-A1 147382529.98

    SCHEDULE-A2 11349885.70

    Total of A 158732415.68

    SCHEDULE-B1-Electrical 12950224.18

    SCHEDULE-B1-Civil 22891837.65

    SCHEDULE-B1(Elec+Civil) 35842061.83

    SCHEDULE-B2-Electrical 3749534.63

    SCHEDULE-B2-Civil 2037603.47

    SCHEDULE-B2(Elec+Civil) 5787138.10

    Total of B 41629199.93

    Eestimated Contract Value 200361615.61

    2003.62

    ABSTRACT

    Erection of 220KV DC line from Pulichintala Hydro Project to proposed 220/132KV SS

    Huzurnagar and 2 nos 220KV bays at Huzurnagar in Nalgonda district

    Signature of the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    2/22

    Sl. No Description Unit Qty. Unit Rate in Rs. Amount in Rs.

    1 G.I Tower parts including stubs,cleats and stub

    settin tem lates

    MT 704 80291.00 56524864.00

    2 G.I Bolts & Nuts including Spring & Flat Washers MT 18.5 79020.10 1461871.85

    3 Step Bolts MT 2.8 79020.10 221256.28

    4 Supply of Moose ACSR Conductor KM 215 335606.80 72155462.005 Supply of Single Suspension Hardware (AGS type)

    with FAH as per IS conforming to latest issue

    suitable for Moose conductor

    Sets 606 5719.09 3465768.54

    6 Supply of Single Tension Hardware as per IS

    conforming to latest issue suitable for Moose

    conductor.

    Sets 630 4379.71 2759217.30

    7 Supply of Repair sleeves conductor ie., accessories

    as per relevant IS of latest issue suitable for ACSR

    Moose conductor.

    Sets 10 377.53 3775.30

    8 Supply of Stock bridge Vibration dampers ie.,

    conductor accessories as per relevant IS of latest

    issue suitable for ACSR Moose conductor.

    Sets 1542 943.83 1455385.86

    9 Mid Span Compression Joints for Moose Conductor Sets 20 1214.24 24284.80

    10 Supply of 7/3.15mm HTGS Earth wire conforming

    to IS of latest issue.

    KMs 35.855 39267.72 1407944.10

    11 Supply of HTGS single Tension Hardware Nos 105 1065.27 111853.35

    12 Supply of HTGS single suspension Hardware Nos 101 1065.27 107592.27

    13 Mid Span Compression Joints for Earthwire Sets 22 162.74 3580.28

    14 70KN Disc Insulators Nos 7878 297.30 2342129.40

    15 120KN Disc Insulators Nos 8823 585.75 5168072.25

    16 Number Plates Nos 126 171.00 21546.00

    17 Phase Plates Nos 116 353.40 40994.40

    18 Danger Boards Nos 16 171.00 2736.00

    19 P type hangers Nos 100 813.96 81396.00

    20 Bird Gaurds Nos 100 228.00 22800.00147382529.98

    SCHEDULE-A1

    Name of the work: Erection of 220KV DC line from Pulichintala Hydro Project(4X30MW) to Proposed 220KV

    Huzurnagar SS(35.5KM)

    Total

    Signature of the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    3/22

    Page 3

    Sl. No Description Unit Qty. Unit Rate in Rs. Amount in Rs.

    1 Supply of fabricated GI structures from raw steel such as M.S.Angles,

    Plates,channels R.S.Joists M.S rounds etc., including cost of steel,

    fabrication and galvanisation of main and auxiliary structures, booms,

    stubsetting template and foundation bolts 'U' bolts with suitable galvanised

    nuts for foundation bolts, transportation to substation site

    MT 24 72455.00 1738920.00

    2 Supply of hot dip galvanised bolts and nuts of various lengths of 16mm

    dia, 5.6 grade as per IS 1367, required for all structures and booms

    fabricated including transportation to sustation site and conforming to

    Standards specified in the relevant Clauses of the specification and

    Supply of Electro galvanised spring washers of 16mm size with rectangular

    cross section 5 mmx 3.5 mm of type B (with flat ends) conforming to IS

    3063 for use with 16mm dia.G.I.Bolts as per the relevant clause of the

    specification including transportation to the substation site.

    MT 3 79020.10 237060.31

    Supply of following Equipment/material

    3 220KV SF6 Circuit Breakers Nos. 2 2133209.08 4266418.16

    4 220KV Feeder CTs (800-600A /1-1-1-1-1A) Nos. 6 329413.30 1976479.80

    5 220KV Lightening Arrestors Nos. 6 49359.60 296157.60

    6 220KV 800A Isolator without Earth switch Nos. 4 129775.11 519100.44

    7 220KV 800A Isolator With Earth Switch Nos. 2 139111.72 278223.44

    8 ACSR Moose Conductor KM 0.448 335606.80 150351.85

    9(a) 2C x 2.5 Sq.mm Copper Control Cable KM 1 43421.68 43421.68

    (b) 4C x 2.5 Sq.mm Copper Control Cable KM 1 78776.36 78776.36

    (c) 6C x 2.5 Sq.mm Copper Control Cable KM 1 108036.86 108036.86

    (d) 10C x 2.5 Sq.mm Copper Control Cable KM 1.5 190676.69 286015.04

    (e) 12C x 2.5 Sq.mm Copper Control Cable KM 1 234570.18 234570.18

    10 3 1/2X120 Sq.mm Power Cable KM 0.2 322014.99 64403.00

    11 Supply of 7/3.15mm HTGS Earth wire conforming to IS of latest issue. KM 0.30 39267.72 11780.32

    12 220KV Solid Core Insulators Nos. 54.00 19632.79 1060170.66

    TOTAL 11349885.70

    \\vboxsrv\conversion_tmp\scratch_2\[186516528.xls.ms_office.xls]ABSTRACT

    SCHEDULE A2

    NAME OF WORK :-Erection of 2 Nos 220KV Bays at Huzurnagar 220KV SS

    Signature of the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    4/22

    SL.

    No

    .

    DESCRIPTION OF ITEM Qty Unit Unit rate of

    labour in Rs.

    Unit rate of

    material in

    Rs.

    Total of labour

    in Rs.

    1 Earthwork excavation in all types of soils (up to stone

    matrix) which can be excavated with pick axe and crow

    bars and do not require blasting in all conditions such as

    dry, wet and slushy etc. covering initial lead and lift etc

    and backfilling the foundations (after laying foundations)

    with excavated earth and consolidation as per standerdspecification and constructing of platforms around

    foundations utilizing the excavated earth etc. complete as

    directed by Engineer-in-Charge

    14000.00 Cum 165.54 0.00 2317560.00

    2 Extra towrds dewatering charges over and above the

    excavation rate for excavated earth quantity Where

    water table met at 1.50 m or more below G.L

    5030.00 Cum 19.99 0.00 100549.70

    3 Extra towrds dewatering charges over and above the

    excavation rate for excavated earth quantity Where water

    table met between 0.75m and 1.50m below G.L

    4050.00 Cum 71.04 0.00 287712.00

    4 Extra towrds dewatering charges over and above the

    excavation rate for excavated earth quantity where water

    table is met with in 0.75m Below G.L

    2975.00 Cum 137.45 0.00 408913.75

    5 Excavation in Ordinary rock (HDR, soft rock ) (not

    requiring blastingThe rate includes labour charges, cost

    of tools and tackles, disposing of unuseful excavated

    material at all leads and lifts, complete for finished item

    of work as per directions of the Engineer-in-charge

    1800.00 Cum 265.85 0.00 478530.00

    6 Excavation in HDR, Soft rock, F&F requiring blasting

    where ever necessary.The rate includes labour charges,

    cost of blasting materials, tools and tackles, safety

    measures, disposal of unuseful excavted material with

    all leads and lifts, complete for finished item of work as

    per directions of the Engineer-in-charge

    1200.00 Cum 266.32 0.00 319584.00

    7 Hard rock (requiring blasting) The rate includes labour

    charges, cost of blasting materials, tools and tackles,

    safety measures, disposal of unuseful excavted material

    at all leads and lifts, complete for finished item of work

    as per directions of the Engineer-in-charge

    1200.00 Cum 631.99 258.13 758388.00

    8 Sand filling below the foundations as per the standard

    specifications of APDSS in uniform horizontal layers

    including cost and conveyance of all materials, watering

    and ramming, tools & tackles, all labour charges, all

    leads & lifts etc, complete for finished item of work as

    per directions of the Engineer-in-charge.

    320.00 Cum 20.06 481.36 6419.20

    9 Laying of concrete (1:4:8) mix using 40mm HBG Machinecrushed metal conforming to IS 383 for all types of

    foundations including cost & conveyance of all materials,

    dewatering arrangements of the pits before and during

    the process of laying concrete, labour charges, water

    lead, tools and tackles, all leads & lifts etc., complete for

    finished item of work as per directions of the Engineer-in-

    charge. (IS-456)

    320.00 Cum 988.69 2813.97 316380.80

    10 Providing High Yield Strength Deformed (HYSD)/ Thermo

    Mechanically Treated (TMT) steel bars (Fe 415/ Fe 500

    grade as per IS 1786-1979) of TISCO/ SAIL/ VSP make,

    different diameters for RCC works , including labour

    charges for straightening, cutting, bending to required

    sizes and shapes, placing in position with cover blocks of

    approved materials and size and tying and lap-splicingwith binding wire of 18 SWG, forming grills for

    reinforcement work as per approved designs and

    drawings, including cost and conveyance of steel bars,

    including all wastages such as overlaps, couplings,

    chairs, spacer bars including cost and conveyance of

    binding wire, cover blocks and all incidental, operational,

    labour charges such as cutting, bending, placing in

    position, tying including sales and other taxes on all

    materials etc., complete for finished item of work in all

    floors.( APSS No.126)

    15 MT 3460.52 54214.89 51907.80

    Schedule B1-Civil

    Name of work: Erection of 220 KV DC line from Pulichintala Hydro project to proposed 220/132/33 KVSS Huzurnagar

  • 8/14/2019 Huz