Huzurnagar 220kV line-BOQ.xls

download Huzurnagar 220kV line-BOQ.xls

of 22

Transcript of Huzurnagar 220kV line-BOQ.xls

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    1/22

    Sl. No Description Total Cost Rs.

    SCHEDULE-A1 147382529.98

    SCHEDULE-A2 11349885.70

    Total of A 158732415.68

    SCHEDULE-B1-Electrical 12950224.18

    SCHEDULE-B1-Civil 22891837.65

    SCHEDULE-B1(Elec+Civil) 35842061.83

    SCHEDULE-B2-Electrical 3749534.63

    SCHEDULE-B2-Civil 2037603.47

    SCHEDULE-B2(Elec+Civil) 5787138.10

    Total of B 41629199.93

    Eestimated Contract Value 200361615.61

    2003.62

    ABSTRACT

    Erection of 220KV DC line from Pulichintala Hydro Project to proposed 220/132KV SS

    Huzurnagar and 2 nos 220KV bays at Huzurnagar in Nalgonda district

    Signature of the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    2/22

    Sl. No Description Unit Qty. Unit Rate in Rs. Amount in Rs.

    1 G.I Tower parts including stubs,cleats and stub

    settin tem lates

    MT 704 80291.00 56524864.00

    2 G.I Bolts & Nuts including Spring & Flat Washers MT 18.5 79020.10 1461871.85

    3 Step Bolts MT 2.8 79020.10 221256.28

    4 Supply of Moose ACSR Conductor KM 215 335606.80 72155462.005 Supply of Single Suspension Hardware (AGS type)

    with FAH as per IS conforming to latest issue

    suitable for Moose conductor

    Sets 606 5719.09 3465768.54

    6 Supply of Single Tension Hardware as per IS

    conforming to latest issue suitable for Moose

    conductor.

    Sets 630 4379.71 2759217.30

    7 Supply of Repair sleeves conductor ie., accessories

    as per relevant IS of latest issue suitable for ACSR

    Moose conductor.

    Sets 10 377.53 3775.30

    8 Supply of Stock bridge Vibration dampers ie.,

    conductor accessories as per relevant IS of latest

    issue suitable for ACSR Moose conductor.

    Sets 1542 943.83 1455385.86

    9 Mid Span Compression Joints for Moose Conductor Sets 20 1214.24 24284.80

    10 Supply of 7/3.15mm HTGS Earth wire conforming

    to IS of latest issue.

    KMs 35.855 39267.72 1407944.10

    11 Supply of HTGS single Tension Hardware Nos 105 1065.27 111853.35

    12 Supply of HTGS single suspension Hardware Nos 101 1065.27 107592.27

    13 Mid Span Compression Joints for Earthwire Sets 22 162.74 3580.28

    14 70KN Disc Insulators Nos 7878 297.30 2342129.40

    15 120KN Disc Insulators Nos 8823 585.75 5168072.25

    16 Number Plates Nos 126 171.00 21546.00

    17 Phase Plates Nos 116 353.40 40994.40

    18 Danger Boards Nos 16 171.00 2736.00

    19 P type hangers Nos 100 813.96 81396.00

    20 Bird Gaurds Nos 100 228.00 22800.00147382529.98

    SCHEDULE-A1

    Name of the work: Erection of 220KV DC line from Pulichintala Hydro Project(4X30MW) to Proposed 220KV

    Huzurnagar SS(35.5KM)

    Total

    Signature of the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    3/22

    Page 3

    Sl. No Description Unit Qty. Unit Rate in Rs. Amount in Rs.

    1 Supply of fabricated GI structures from raw steel such as M.S.Angles,

    Plates,channels R.S.Joists M.S rounds etc., including cost of steel,

    fabrication and galvanisation of main and auxiliary structures, booms,

    stubsetting template and foundation bolts 'U' bolts with suitable galvanised

    nuts for foundation bolts, transportation to substation site

    MT 24 72455.00 1738920.00

    2 Supply of hot dip galvanised bolts and nuts of various lengths of 16mm

    dia, 5.6 grade as per IS 1367, required for all structures and booms

    fabricated including transportation to sustation site and conforming to

    Standards specified in the relevant Clauses of the specification and

    Supply of Electro galvanised spring washers of 16mm size with rectangular

    cross section 5 mmx 3.5 mm of type B (with flat ends) conforming to IS

    3063 for use with 16mm dia.G.I.Bolts as per the relevant clause of the

    specification including transportation to the substation site.

    MT 3 79020.10 237060.31

    Supply of following Equipment/material

    3 220KV SF6 Circuit Breakers Nos. 2 2133209.08 4266418.16

    4 220KV Feeder CTs (800-600A /1-1-1-1-1A) Nos. 6 329413.30 1976479.80

    5 220KV Lightening Arrestors Nos. 6 49359.60 296157.60

    6 220KV 800A Isolator without Earth switch Nos. 4 129775.11 519100.44

    7 220KV 800A Isolator With Earth Switch Nos. 2 139111.72 278223.44

    8 ACSR Moose Conductor KM 0.448 335606.80 150351.85

    9(a) 2C x 2.5 Sq.mm Copper Control Cable KM 1 43421.68 43421.68

    (b) 4C x 2.5 Sq.mm Copper Control Cable KM 1 78776.36 78776.36

    (c) 6C x 2.5 Sq.mm Copper Control Cable KM 1 108036.86 108036.86

    (d) 10C x 2.5 Sq.mm Copper Control Cable KM 1.5 190676.69 286015.04

    (e) 12C x 2.5 Sq.mm Copper Control Cable KM 1 234570.18 234570.18

    10 3 1/2X120 Sq.mm Power Cable KM 0.2 322014.99 64403.00

    11 Supply of 7/3.15mm HTGS Earth wire conforming to IS of latest issue. KM 0.30 39267.72 11780.32

    12 220KV Solid Core Insulators Nos. 54.00 19632.79 1060170.66

    TOTAL 11349885.70

    \\vboxsrv\conversion_tmp\scratch_2\[186516528.xls.ms_office.xls]ABSTRACT

    SCHEDULE A2

    NAME OF WORK :-Erection of 2 Nos 220KV Bays at Huzurnagar 220KV SS

    Signature of the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    4/22

    SL.

    No

    .

    DESCRIPTION OF ITEM Qty Unit Unit rate of

    labour in Rs.

    Unit rate of

    material in

    Rs.

    Total of labour

    in Rs.

    1 Earthwork excavation in all types of soils (up to stone

    matrix) which can be excavated with pick axe and crow

    bars and do not require blasting in all conditions such as

    dry, wet and slushy etc. covering initial lead and lift etc

    and backfilling the foundations (after laying foundations)

    with excavated earth and consolidation as per standerdspecification and constructing of platforms around

    foundations utilizing the excavated earth etc. complete as

    directed by Engineer-in-Charge

    14000.00 Cum 165.54 0.00 2317560.00

    2 Extra towrds dewatering charges over and above the

    excavation rate for excavated earth quantity Where

    water table met at 1.50 m or more below G.L

    5030.00 Cum 19.99 0.00 100549.70

    3 Extra towrds dewatering charges over and above the

    excavation rate for excavated earth quantity Where water

    table met between 0.75m and 1.50m below G.L

    4050.00 Cum 71.04 0.00 287712.00

    4 Extra towrds dewatering charges over and above the

    excavation rate for excavated earth quantity where water

    table is met with in 0.75m Below G.L

    2975.00 Cum 137.45 0.00 408913.75

    5 Excavation in Ordinary rock (HDR, soft rock ) (not

    requiring blastingThe rate includes labour charges, cost

    of tools and tackles, disposing of unuseful excavated

    material at all leads and lifts, complete for finished item

    of work as per directions of the Engineer-in-charge

    1800.00 Cum 265.85 0.00 478530.00

    6 Excavation in HDR, Soft rock, F&F requiring blasting

    where ever necessary.The rate includes labour charges,

    cost of blasting materials, tools and tackles, safety

    measures, disposal of unuseful excavted material with

    all leads and lifts, complete for finished item of work as

    per directions of the Engineer-in-charge

    1200.00 Cum 266.32 0.00 319584.00

    7 Hard rock (requiring blasting) The rate includes labour

    charges, cost of blasting materials, tools and tackles,

    safety measures, disposal of unuseful excavted material

    at all leads and lifts, complete for finished item of work

    as per directions of the Engineer-in-charge

    1200.00 Cum 631.99 258.13 758388.00

    8 Sand filling below the foundations as per the standard

    specifications of APDSS in uniform horizontal layers

    including cost and conveyance of all materials, watering

    and ramming, tools & tackles, all labour charges, all

    leads & lifts etc, complete for finished item of work as

    per directions of the Engineer-in-charge.

    320.00 Cum 20.06 481.36 6419.20

    9 Laying of concrete (1:4:8) mix using 40mm HBG Machinecrushed metal conforming to IS 383 for all types of

    foundations including cost & conveyance of all materials,

    dewatering arrangements of the pits before and during

    the process of laying concrete, labour charges, water

    lead, tools and tackles, all leads & lifts etc., complete for

    finished item of work as per directions of the Engineer-in-

    charge. (IS-456)

    320.00 Cum 988.69 2813.97 316380.80

    10 Providing High Yield Strength Deformed (HYSD)/ Thermo

    Mechanically Treated (TMT) steel bars (Fe 415/ Fe 500

    grade as per IS 1786-1979) of TISCO/ SAIL/ VSP make,

    different diameters for RCC works , including labour

    charges for straightening, cutting, bending to required

    sizes and shapes, placing in position with cover blocks of

    approved materials and size and tying and lap-splicingwith binding wire of 18 SWG, forming grills for

    reinforcement work as per approved designs and

    drawings, including cost and conveyance of steel bars,

    including all wastages such as overlaps, couplings,

    chairs, spacer bars including cost and conveyance of

    binding wire, cover blocks and all incidental, operational,

    labour charges such as cutting, bending, placing in

    position, tying including sales and other taxes on all

    materials etc., complete for finished item of work in all

    floors.( APSS No.126)

    15 MT 3460.52 54214.89 51907.80

    Schedule B1-Civil

    Name of work: Erection of 220 KV DC line from Pulichintala Hydro project to proposed 220/132/33 KVSS Huzurnagar

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    5/22

    SL.

    No

    .

    DESCRIPTION OF ITEM Qty Unit Unit rate of

    labour in Rs.

    Unit rate of

    material in

    Rs.

    Total of labour

    in Rs.

    11 RCC M- 20 Nominal mix (Cement 400 kgs ) using 20mm

    size graded machine crushed hard granite metal (coarse

    aggregate) from approved quarry including cost and

    conveyance of all materials like cement, fine aggregate

    (sand) coarse aggregate, water etc., to site and including

    Seigniorage charges, sales & other taxes on all materials

    including all operational, incidental and labour charges

    such as machine mixing, laying concrete, curing andcentering, etc.,complete but excluding cost of steel and

    its fabrication charges for finished item of work.(cement

    400 kg , sand 0.45 cum and metal 0.90 cum)

    230.00 Cum 2966.45 4268.79 682283.50

    12 PCC M- 20 Nominal mix (Cement 330 kgs ) using 20mm

    size graded machine crushed hard granite metal (coarse

    aggregate) from approved quarry including cost and

    conveyance of all materials like cement, fine aggregate

    (sand) coarse aggregate, water etc., to site and including

    Seigniorage charges, sales & other taxes on all materials

    including all operational, incidental and labour charges

    such as machine mixing, laying concrete, curing and

    centering, etc.,complete but excluding cost of steel and

    its fabrication charges for finished item of work.(cement

    330 kg , sand 0.45 cum and metal 0.90 cum)

    2000.00 Cum 1946.19 3951.35 3892380.00

    13 Filling around the foundations if required where ever

    necessary with borrowed earth as per the standard

    specifications of APDSS in uniform horizontal layers

    (0.15) including cost and conveyance of all materials,

    watering and ramming, tools & tackles, all labour

    charges, all leads & lifts etc, complete for finished item of

    work as per the directions of the Engineer-in-charge.

    4200.00 Cum 19.31 141.59 81102.00

    14 Providing shoring and strutting either with country

    wooden planks and scantlings or with steel sheets andprops for excavation of pits for tower foundations

    wherever necessary including cost and conveyance of all

    materials, labour charges, tools & tackles, all leads &

    lifts and etc., complete for finished item of work as per

    directions of the Engineer-in-charge.

    1400.00 Sqm 15.85 67.59 22190.00

    Total 9723900.75

    Service tax 12.36% on total of labour 1201874.13

    Labour Cess @ 1% on total of Labour 97239.01

    TOTAL with Taxes 11023013.89

    TOTAL LABOUR & MATERIAL 22891837.65

    Signature

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    6/22

    Total of

    material in

    Rs.

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    309756.00

    154035.20

    900470.40

    813223.35

    in Nalgonda

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    7/22

    Total of

    material in

    Rs.

    981821.70

    7902700.00

    594678.00

    94626.00

    11751310.65

    NA

    117513.11

    11868823.76

    of the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    8/22

    Page 8

    Sno Description QTY UnitUnit rate of

    Labour

    Unit Rate of

    materialTotal of Labour Total of Material

    1 Check survey 35.50 RKM 4644.00 164862.00

    2

    Setting of stubs with stub-setting

    template : Erection of stubs, stub

    template, fixing of jacks for

    supporting template, alignment and

    leveling for exact location of stubs of

    stub setting template, dismantling of

    template after completion of initial

    curing of C.C., movement of

    template from one location to other

    location including

    transportation.(ABCDTowers)

    126.00 Loc. 12214.57 1539035.82

    3

    Erection of all types of towers and

    extentions upto 12 mts. in full

    towers except JC type towers

    complete with all accessories suchas Number plates, Phase plates,

    Danger boards etc. and including

    the step bolts after full tightening

    and checking tower verticality, and

    anti climbling devices are also to be

    fixed wherever necessary under

    normal conditions. (ABCD Towers)

    693.57 MT 5977.09 4145530.31

    4

    Earthing of towers including cost of

    excavation, back filling, including

    cost of 25 mm dia 2.5 mm thickclass 'C' G.I. pipe of 3 Mtrs length

    with 50 X6 mm G.I flat 4.05 mtrs

    long , Charcoal, Salt etc., and

    measuring tower footing resistance

    126.00 Loc. 4860.74 612453.24

    5

    Counterpoise earthing including

    clamping devices and terminal lugs,

    but excluding cost of steel wire. 120.00 RM 42.19 5062.80

    6

    Hoisting of tension insulators and

    suspension insulators with

    hardware, paving out theconductor,rough sagging, jointing,

    tensioning, clamping,jumpering,

    clipping and fixing of Preformed

    Armour rods and vibration dampers

    etc. complete with 6(six) nos. ACSR

    Moose conductor and measuring

    ground clearences wherever

    necessary(Under nomal Conditions)

    35.50 RKM 100612.07 3571728.58

    7

    Fixing hardware, paving out earth

    wire, jointing, tensioning, stringing,jumpering and clamping of

    7/3.15mm HTG Steelwire .(Under

    nomal Conditions)

    35.50 RKM 7684.68 272806.22

    8

    Half round welding of G.I.bolts and

    nuts of towers in the section

    between ground level & upto bottom

    X-arm level including all bolts

    connecting the bracings at the

    bottom X-arm level and painting the

    welded portion with one coat of zinc

    rich paint

    55989.00 Nos. 19.87 1112501.43

    Schedule B1-Electrical

    Name of the work: Erection of 220KV DC line from Pulichintala Hydro Project(4X30MW) to Proposed 220KV Huzurnagar

    SS(35.5KM)

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    9/22

    Page 9Sno Description QTY Unit

    Unit rate of

    Labour

    Unit Rate of

    materialTotal of Labour Total of Material

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    10/22

    1 Levelling by filling with borrowed gravel by mechanical

    means including pre-watering of soil, excavation of

    soils,conveyance of soils, depositing the soils in filling

    areas , spreading soils, breaking clods, sectioning and

    consolidation with three wheel 8 to 10 MT static Road

    Roller @ OMC to meet requirement as per standard

    specification , including all hire and operational chargesof T&P and seigniorage charges, complete for finished

    item of work as per (Payment will be made based on level

    for finished item of work).

    600.00 Cum 178.31 61.74 106986.00

    2 Earthwork excavation in all types of soils (up to stone

    matrix)which can be excavated with pick axe and crow

    bars and do not require blasting in all conditions such

    as dry, wet and slushy etc. covering initial lead and lift

    etc and backfilling the foundations (after laying

    foundations) with excavated earth complete as per the

    the directions of the Engineer in charge for the finished

    item of work. .

    550.00 Cum 124.49 0.00 68469.50

    3 Excavation in ordinary rock( HDR,soft rock,F&F)

    requiring blasting where ever necessary.The rate

    includes labour charges, cost of blasting materials, tools

    and tackles, safety measures, disposal of unuseful

    excavted material at all leads and lifts, complete for

    finished item of work as per directions of the Engineer-

    in-charge

    50.00 Cum 263.28 0.00 13164.00

    4 Hard rock (requiring blasting) The rate includes labour

    charges, cost of blasting materials, tools and tackles,

    safety measures, disposal of unuseful excavted material

    at all leads and lifts, complete for finished item of work

    as per directions of the Engineer-in-charge

    50.00 Cum 590.51 255.76 29525.50

    5 Providing sand cushion for foundations and basement in

    uniform layers, including cost & conveyance of all

    materials, labour charges, leads, lifts , watering and

    consolidating to required density complete as per the

    directions of the Engineer in charge for the finished item

    of work( APSS No. 309&310)

    100.00 Cum 17.68 467.97 1768.00

    6 Laying of Cement Concrete (1:4:8) mix using 40mm size

    HBG Machine crushed metal for foundations including

    cost and conveyance of all materials at all leads and lifts,

    ramming, consolidating, curing etc,complete. for finished

    item of work as per directions of the Engineer-in-charge.

    25.00 Cum 883.10 2396.59 22077.50

    7 Brick Masonry in CM (1:6) with 2nd class Bricks

    traditional size 23 x 11 x 7 cms of approved quality,

    including cost & conveyance of all materials, labour

    charges, scaffolding leads, lifts and curing complete as

    per the directions of the Engineer in charge for the

    finished item of work .

    5.00 Cum 973.86 2676.98 4869.30

    8 Providing High Yield Strength Deformed (HYSD)/ Thermo

    Mechanically Treated (TMT) (Fe 415/ Fe 500 grade as

    per IS 1786-1979) of TISCO/ SAIL/ VSP make, different

    diameters for RCC works , including labour charges for

    straightening, cutting, bending to required sizes and

    shapes, placing in position with cover blocks of approved

    materials and size and tying and lap-splicing with

    binding wire of 18 SWG, forming grills for reinforcementwork as per approved designs and drawings, including

    cost and conveyance of steel bars, including all wastages

    such as overlaps, couplings, chairs, spacer bars

    including cost and conveyance of binding wire, cover

    blocks and all incidental, operational, labour charges

    such as cutting, bending, placing in position, tying

    including sales and other taxes on all materials etc.,

    complete for finished item of work in all floors.( APSS

    No.126)

    2 MT 7934.4 52228.92 15868.80

    Total of labour in

    Rs.

    Schedule B2-Civil

    Name of work: Erection of 2 No. 220 KV bays at 220 KVSS Huzurnagar for Pulichinthala I & II feeders in Nal

    Sl.

    No

    DESCRIPTION OF ITEM OF WORK Qty Unit Unit

    rate of

    Unit rate

    of

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    11/22

    Total of labour in

    Rs.

    Sl.

    No

    DESCRIPTION OF ITEM OF WORK Qty Unit Unit

    rate of

    Unit rate

    of

    9 RCC M- 20 Nominal mix (Cement 400 kgs ) using

    20mm size graded machine crushed hard granite metal

    (coarse aggregate) (20mm & 12mm (2:1)) from approved

    quarry including cost and conveyance of all materials

    like cement, fine aggregate (screened sand) coarse

    aggregate, water etc., to site and including Seigniorage

    charges, sales & other taxes on all materials including

    all operational, incidental and labour charges such as

    machine mixing, laying concrete, curing and centering,etc.,complete but excluding cost of steel and its

    fabrication charges for finished item of work(Sand 0.45

    cum and Metal 0.90 cum) as directed by the Engineer in

    charge.

    80.00 Cum 2708.43 3902.64 216674.40

    10 PCC M- 20 Nominal mix (Cement 330 kgs ) using 20mm

    size graded machine crushed hard granite metal (coarse

    aggregate) from approved quarry including cost and

    conveyance of all materials like cement, fine aggregate

    (sand) coarse aggregate, water etc., to site and including

    Seigniorage charges, sales & other taxes on all materials

    including all operational, incidental and labour charges

    such as machine mixing, laying concrete, curing and

    centering, etc.,complete but excluding cost of steel and

    its fabrication charges for finished item of work.(cement

    330 kg , sand 0.45 cum and metal 0.90 cum)

    50.00 Cum 1782.46 3618.93 89123.00

    11 Plastering with CM (1:3), 12 mm thick and finishing

    smooth to the required slope and painting two coats of

    Janatha Cem including cost & conveyance of all

    materials, labour charges, leads, lifts and curing

    including cost of Janatha Cem paint two coats, complete

    as per the directions of the Engineer in charge for the

    finished item of work.

    110.00 Sqm 88.75 46.97 9762.50

    12 Construction of cable duct in the switch yard as per

    drawing no.CE/Civil/Trench/Swy 08 including cost &

    conveyance of all materials, labour charges, leads, lifts

    and curing etc, complete as per the directions of the

    Engineer in charge for the finished item of work

    50.00 RM 826.26 1149.90 41313.00

    13 Supply and spreading of crusher dust in the switch

    yard(100mm thick) area including Suitable antiweed

    treatment after completion of final levelling and grading

    including disposal of surplus earth and filling within

    switch yard areaincludind cost of all materials, all leads

    and lifts, labour charges complete as per the directions

    of the Engineer in charge for the finished item of work..

    60.00 Cum 69.54 703.10 4172.40

    14 Supply and laying of 180 GSM LDPE sheet of approved

    make in the switch yard including laying the sheet

    neatly in between layers of crusher dust without folds to

    avoid the vegetation and weed growth, cutting and

    jointing the sheet properly including cost & conveyance

    of all materials, all leads , labour charges for laying

    complete as per the directions of the Engineer in charge

    for the finished item of work..

    600.00 Sqm 0.00 16.01 0.00

    15 Supply and Spreading of 20mm size Hard Broken

    Granite metal in switch yard (100mm thick) including

    providing suitable PCC guage block of size

    100x100x100mm at 2m x2m intervals , cost &conveyance of all materials, labour charges, leads, lifts

    complete as per the directions of the Engineer in charge

    for the finished item of work

    60.00 Cum 62.22 1701.21 3733.20

    16 Filling around the foundations if required where ever

    necessary with borrowed Gravel as per the standard

    specifications of APDSS in uniform horizontal layers

    including cost and conveyance of all materials, watering

    and ramming, tools & tackles, all labour charges, all

    leads & lifts etc, complete for finished item of work as

    per the directions of the Engineer-in-charge.

    100.00 Cum 12.72 241.68 1272.00

    RETAINING WALL

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    12/22

    Total of labour in

    Rs.

    Sl.

    No

    DESCRIPTION OF ITEM OF WORK Qty Unit Unit

    rate of

    Unit rate

    of

    18 Hard rock (requiring blasting) The rate includes labour

    charges, cost of blasting materials, tools and tackles,

    safety measures, disposal of unuseful excavted material

    at all leads and lifts, complete for finished item of work

    as per directions of the Engineer-in-charge

    25.00 Cum 590.51 255.76 14762.75

    19 Excavation in ordinary rock( HDR,soft rock,F&F)

    requiring blasting where ever necessary.The rate

    includes labour charges, cost of blasting materials, toolsand tackles, safety measures, disposal of unuseful

    excavted material at all leads and lifts, complete for

    finished item of work as per directions of the Engineer-

    in-charge

    0.00 Cum 263.28 0.00 0.00

    20 Providing sand cushion for foundations and basement in

    uniform layers, including cost & conveyance of all

    materials, labour charges, leads, lifts , watering and

    consolidating to required density complete as per the

    directions of the Engineer in charge for the finished item

    of work( APSS No. 309&310)

    15.00 Cum 17.68 467.97 265.20

    21 Laying of Cement Concrete (1:4:8) mix using 40mm size

    HBG Machine crushed metal for foundations includingcost and conveyance of all materials at all leads and lifts,

    ramming, consolidating, curing etc,complete. for finished

    item of work as per directions of the Engineer-in-charge.

    8.00 Cum 883.10 2396.59 7064.80

    22 Construction of RR Msaonry in CM (1:6) using hard CR

    Stone , rough granite stone and bond stones (0.16 cum)

    including cost and conveyance of all matreials., labour

    charges, water lead , Curing, all leads and lifts etc.,

    complete for finished item of work as per directions of

    the Engineer-in-charge.

    66.00 Cum 1210.55 1466.82 79896.30

    23 Providing and fixing 110mm dia (4kg/cm2) PVC pipes of

    prince / sudhakar or any ISI brand make for weep holesin RR masonry walls including cost and conveyance of

    all materials complete as per the directions of the

    Engineer in charge for the finished item of work.

    25.00 RM 16.42 167.20 410.50

    24 Plain Cement concrete - Nominal Mix (1:3:6) with 12 to

    20mm HBG metal with necessary form work including

    cost and conveyance of all materials, labour charges,

    water charges, tools and tackles, all leads & lifts etc.,

    complete for finished item of work as per directions of

    the Engineer-in-charge. (IS-456)

    2.00 Cum 1469.59 3026.27 2939.18

    25 Flush Pointing with CM (1:3) to RR Masonry including

    cost and conveyance of all materials, all leads and lifts

    complete as per the directions of the Engineer in charge

    for the finished item of work.

    91.00 Sqm 44.97 10.12 4092.27

    26 White washing two coats with whiting / Suryacem of

    approved quality to give an even shade after thoroughly

    brushing the surface to remove all dirt and remains of

    loose powdered materials including cost of all materials,

    labour charges and incidental such as scaffolding, lift

    charges etc., complete for finished item of work, but

    excluding conveyance charges of materials

    130.00 Sqm 19.97 3.74 2596.10

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    13/22

    Total of labour in

    Rs.

    Sl.

    No

    DESCRIPTION OF ITEM OF WORK Qty Unit Unit

    rate of

    Unit rate

    of

    WATER SUPPLY ARRANGEMENT IN EARTH PITS

    27 Supplying and fixing G.I. pipes Medium Grade as per IS

    1239 of Tata/Zenith make for water supply line to toilets

    including cost and conveyance of pipe, G.I. specials

    such as elbows, Tees concealing same in walls and

    floors by cutting 25/ 20/ 15mm dia to be included

    grooves, packing, finishing after laying pipe in position

    as per the directions of the Engineer in charge for the

    finished item of work.

    a 25mm dia Nominal Bore 50.00 RM 45.14 213.18 2257.00

    b 15mm dia Nominal Bore 70.00 RM 45.14 134.52 3159.80

    28 Providing and fixing in position at all levels of the

    buildings G.M. Gate(GM peet) Valve (Tata/Zenith

    make)as per IS-778 class- 1, Indian make heavy type for

    water services with hand wheel at all elevations for

    following sizes including jointing complete as per the

    directions of the Engineer in charge for the finished item

    of work.

    a 20mm dia Nominal Bore 4.00 No 49.25 430.92 197.00

    29 Supply and fixing of 12.5mm/15mm dia N.P bib tapindian make 300 grams weight Seiko or equivalent make

    including cost & conveyance of all materials, labour

    charges, leads, lifts complete as per the directions of

    the Engineer in charge for the finished item of work .

    7.00 No 31.46 223.44 220.22

    30 Construction of Brick masonry chamber over the cully

    trap or peet valves & fitted with 304.8mm X 228.6mm

    size CI frame & Hinged cover as including cost &

    conveyance of all materials, labour charges complete for

    finished item of work as per the directions of the

    Engineer-in-charge

    4.00 No 112.18 346.56 448.72

    751446.09

    Service tax 12.36% on total of labour 92878.74Labour Cess @ 1% on total of Labour 7514.46

    TOTAL with Taxes 851839.29

    TOTAL LABOUR & MATERIAL 2037603.47

    Sign

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    14/22

    37044.00

    0.00

    0.00

    12788.00

    46797.00

    59914.75

    13384.90

    104457.84

    Total of material in

    Rs.

    onda District.

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    15/22

    Total of material in

    Rs.

    312211.20

    180946.50

    5166.70

    57495.00

    42186.00

    9606.00

    102072.60

    24168.00

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    16/22

    Total of material in

    Rs.

    6394.00

    0.00

    7019.55

    19172.72

    96810.12

    4180.00

    6052.54

    920.92

    486.20

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    17/22

    Total of material in

    Rs.

    10659.00

    9416.40

    1723.68

    1564.08

    1386.24

    1174023.94

    NA

    11740.241185764.18

    ature of the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    18/22

    Page 18

    Sno Description QTY Unit

    Unit rate

    of Labour

    in Rs.

    Unit Rate of

    material in

    Rs.

    Total of Labour

    in Rs.

    1

    Setting of stubs with stub setting templates for SS structures -

    Erection of stubs, stub setting template, fixing of jacks for

    supporting template, alignment and levelling for exact location

    of stubs of stub setting template, dismantling of template after

    completion of initial curing of C.C., movement of template from

    one location to other location.

    a 220KV TA Towers 4 3747.98 14991.92

    b 220KV isolators 6 2811.32 16867.92

    c CPL 18 672.68 12108.24

    2

    Erection of all types of structures fabricated from RS joists,

    M.S.Angles, channels, plates,rods etc.(Super structures and

    Bolts & Nuts)25.5 MT 2903.78 74046.39

    3

    Fixing hardware, stretching the groundwire and stringing of

    overhead earth bus from pinacle to pinacle including supply of

    tension clamps20 each 867.65 17353.00

    a 3 Bolted single tension clamps 40 Nos 798.44 0.00

    4

    Connecting equipment to bus and/or another equipment with

    Single Mooseconductor including measuring,cutting clamping

    and also hoisting of suspension insulator assembly to support

    the conductor wherever necessary44 each 304.18 13383.92

    iTwin moose spacer T clamps 400mm with T-off single Moose

    6 nos 702.30 0.00

    ii T Clamps for single Moose 18 nos 467.81 0.00

    5 Supply and Laying of earth mat including excavation of

    trenches,welding and fixing lugs,connecting to equipment and

    connecting lightning shield to earth mat and earthing of fence

    posts,drilling and connecting earthrods with - 100 x 16mm

    MS Flat

    1000 RM 89.78 635.49 89780.00

    6

    Supply and Laying of earth mat including excavation of

    trenches, welding and fixing lugs,connecting to equipment and

    connecting lightning shield to earth mat and earthing of fence

    posts,drilling and connecting earthrods with 100 x 16mm GI

    Flat

    1000 RM 89.78 863.44 89780.00

    7

    Supply and Laying of earth mat including excavation of

    trenches,welding and fixing lugs,connecting to equipment and

    connecting lightning shield to earth mat and earthing of fence

    posts,drilling and connecting earthrods with - 50 x 8mm MS

    Flat

    1500 RM 70.75 156.35 106125.00

    8

    Supply and Laying of earth mat including excavation of

    trenches,welding and fixing lugs,connecting to equipment and

    connecting lightning shield to earth mat and earthing of fence

    posts,drilling and connecting earthrods with 50 x 8mm GI Flat1500 RM 70.75 212.43 106125.00

    9

    Excavation of earth pit, putting cast iron pipe with flange on

    one end ( as per relevant ISS ), of nominal dia 125 mm and 2.75

    metres long inside the pit including supply and fixing of RCC

    Collars 1mtr dia and 0.6 mtrs long inside the pit, and backfill

    the pit in 25mm size granules of BH coke for full depth of the

    pit with alternate layers of BH Coke and salt of 300mm thick

    around the earth pipe of 150mm on all the sides of the pipe

    including cost and conveyance of BH Coke , salt, C.I.Pipe and

    RCC collars, labour charges for all operational and incidental

    items of work etc., as directed by the engineer in charge. All

    earth pits should be connected to the earth mat.

    10 Nos. 12943.06 129430.60

    10

    Laying of control cables of all sizes (from 2 core, 2.5 sqmm to12

    core,2.5 sqmm both copper and aluminium) in cable trenches

    including cost of suitable metallic glands with rubber lining &

    dressing. This includes running of cables in control room where

    cables are run on cable racks in cable duct.

    5500 RM 9.92 54560.00

    11 Laying of Power Cables above 50Sqmm. 200 18.36 3672.00

    12

    Cable termination to the switch-gear, marshalling boxes/panel

    terminal blocks/control & relay panels, LTAC panel, including

    providing suitable ferrules and lugs as per specification

    (including cost of ferrules and lugs).Note: Rate to be quoted for

    termination of one core of cable at both ends.

    0.00

    a a) 2.5 sq.mm. copper 1000 Nos. 30.82 30820.00

    13

    Supply, installation, testing and commissioning of 80W LED

    lamps along with fixtures for switch yard lighting. 6 each 1161.78 53865.00 6970.68

    Schedule -B2 Electrical

    NAME OF WORK :Erection of 2 Nos 220KV Bays atHuzurnagar 220KV SS

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    19/22

    Page 19

    Sno Description QTY Unit

    Unit rate

    of Labour

    in Rs.

    Unit Rate of

    material in

    Rs.

    Total of Labour

    in Rs.

    14

    Supply and erection of lighting pillar box in switchyard on

    foundation as per drg.no.SET(P) 1/99 cost of all materials &

    cost of pillar box.1 Nos. 1161.24 12000.00 1161.24

    15Erection of the following equipment at site including insurance

    etc., and made fit for commissioning0.00

    a 220KV SF6 Circuit Breakers 2 Nos. 30987.15 61974.29

    b 220KV Feeder CTs (800-600A /1-1-1-1-1A) 6 Nos. 6584.97 39509.80c 220KV CVT 6 Nos. 5878.22 35269.32

    e 220KV Lightening Arrestors 6 Nos. 3440.02 20640.11

    f 220KV 800A Isolator without Earth switch with SCI 4 Nos. 8792.47 35169.88

    g 220KV 800A Isolator With Earth Switch with SCI 2 Nos. 9418.03 18836.07

    16

    Erection of control /relaypanels in the control room duly

    mounting them on channels provided on the cable duct and

    grouting them with foundation bolts.2 Nos. 7334.23 14668.47

    17

    Supply and erection of 220KV CT marshalling boxon the

    structures of equipment including cost of marshalling boxes 2 Nos. 421.56 4511.62 843.12

    18

    Supply and erection of 220KV CVT marshalling boxon the

    structures of equipment including cost of marshalling boxes 2 Nos. 421.56 5730.97 843.12

    19

    Writing of names in the control room for identification of rooms,on panels, equipment, marshalling boxes, with CT ratio etc., &

    on maingates neatly with superior quality paint brushes &

    labour etc., complete on the main gate with superior quality

    synthetic enamel paint with two coats including cost of paint,

    brushes and labour charges etc complete.

    100 Lines 67.00 6700.00

    20

    Supply and fixing of Insulation of Rubber mats of size 2m x 1m

    x 6mm confirming to IS 5424/96 and laying in front of panels

    in the Control Room2 Nos. 0.00 1277.98 0.00

    21

    Supply and fixing of 15 lbs CO2 portable fire extinguishers of

    standard make with ISI certification like Fire flex / Sharathy

    industries complete with first filling Horn and Hose.3 Nos. 0.00 5100.00 0.00

    22

    Supply and fixing of 50 lbs CO2 portable fire extinguishers

    (with Trolley) of standard make with ISI certification like Fire

    flex / Sharathy industries complete with first filling Horn and

    Hose.

    3 Nos. 0.00 13900.00 0.00

    23 Supply & Fixing of GI Flexible earth Bonds 40 Nos. 0.00 146.56 0.00

    24Supply and fixing of Portable Emergency twin tube fittings of

    20Watts capacity make Bajaj/Panasonic4 Nos. 0.00 2500.00 0.00

    Labour - Telecom at 220KV Huzurnagar SS and Pulichintala Hydro Projec 0.00 0.00

    25 Digital PLCC 2 Nos 5474.28 10948.56

    261250A/0.5 mH Wavetraps along with mounting Pedastal and

    insulator stack.4 Nos 4146.18 16584.72

    27 Phase to Phase coupling units 2 Nos 914.28 1828.56

    28 EPAX (8/8), 128 universal ports fullly wired. 1 Nos 2261.76 2261.76

    29 EPB Telephones 10 Nos 0.00 0.00

    30 48V/250AH SMF VRLA Battery set 1 Nos 5734.20 5734.20

    31 48V/50A(1+1) Float cum Boost Charger 1 Nos 2527.38 2527.38

    32 125 Ohms Co-axial Cable 1 Km 13953.60 13953.60

    1055468.87

    130455.95

    10554.69

    1196479.51

    3749534.63TOTAL LABOUR & MATERIAL

    Signature

    TOTAL

    Service tax 12.36% on total of labour

    Labour Cess @ 1% on total of Labour

    TOTAL with Taxes

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    20/22

    Page 20

    Total of

    Material in

    Rs.

    0.00

    0.00

    0.00

    0.00

    0.00

    31937.60

    0.00

    4213.80

    8420.58

    635494.86

    863440.00

    234527.87

    318649.16

    0.00

    0.00

    0.00

    0.00

    0.00

    323190.00

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    21/22

    Page 21Total of

    Material in

    Rs.

    12000.00

    0.00

    0.00

    0.000.00

    0.00

    0.00

    0.00

    0.00

    9023.24

    11461.94

    0.00

    2555.96

    15300.00

    41700.00

    5862.34

    10000.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    2527777.35

    NA

    25277.77

    2553055.12

    f the Bidder

  • 8/14/2019 Huzurnagar 220kV line-BOQ.xls

    22/22

    PRICE BID-SCHEDULE-C

    (These Price Schedules shall be filled up by the Bidder )

    SPECIFICATION NO : e- 54/CE/Construction-I/ APT-e-54 /2013

    NAMES OF THE WORKS :

    A (Material Portion)=A1+A2 B(Labour Portion)= B1+B2

    Sl. No. Item Amount

    1 Total Value of Schedule A+B Rs. 200361616.00

    i. In Figures%ii. In Words

    3

    Unconditional Rebate if any on amount against

    SL.NO.3 above

    i. In Figures%

    ii. In Words

    5

    Amount of discount after loading the percentage

    rate quoted against Sl No.4 above

    6Total value of contract after allowing the

    discount offered(Sl.No.3-Sl No 5)

    Very Important Note to Bidders for evaluation purpose

    Schedule A1&B1:Supply, Erection,Testing and Commissioning of 220KV DC line from Pulichintala Hydro

    Project to proposed 220/132KV SS Huzurnagar

    Schedule A2&B2:Supply, Erection,Testing and Commissioning of Erection of 2 nos 220KV bays at Huzurnagar

    in Nalgonda district

    2

    Percentage Rate quoted below / at par / above the total

    value vide SCHEDULE A + B

    Grand Total value of SCHEDULE A+B after loading the

    percentage rate quoted against Sl No. 2 above

    (i) If the amount arrived is more than tha e-procurement lumpum amount, the

    lumpsum amount shall be taken forward of contract.

    3.. The Quantities of Equipment/material indicated in Schedule-A1 and

    Schedule-A2 and the Quantities indicated in Schedule-B1 and Schedule-B2

    are tentative only. They are likely to vary slightly during execution. The

    Quantities of Equipment will be finalized and confirmed immediately after

    placing purchase order.

    4. Discount offered if any shall be indicated in the schedule 'C' only. Discount

    offered any where else will not be considered.

    Signature of the Bidder with

    seal

    4

    1. In case of discrepancy between the amount calculated by adopting the percentage rate

    quoted for Sl. No. 2 and amount quoted in Sl. No. 3 the percentage rate quoted in words

    in Sl. No. 2, shall govern.

    2.DIFFERENCE IN e-Procurement LUMPSUM AMOUNT AND TOTAL OF THE

    SCHEDULES:

    1. Where there is a discrepancy between the total lumpsum rate quoted in the

    e-procurement platform web page and the total of schedule submitted, the

    total lumpsum rate quoted in the e-procurement platform will govern fordeciding L1

    2.After evaluating the schedules of L1 by taking into consideration the words

    and figures and multiplication and totaling mistakes-

    (i) If the amount arrived is less than tha e-procurement lumpum amount, the

    lesser amount shall be taken forward of contract.