Hummock Pond Road Bike Path Implementation Update January 25, 2012

5
Hummock Pond Road Bike Path Hummock Pond Road Bike Path Implementation Update Implementation Update January 25, 2012 January 25, 2012

description

Hummock Pond Road Bike Path Implementation Update January 25, 2012. HPRBP –Implementation Summary. Bike path will run from end of Milk Street extension to Cisco Beach Funding from the Town of Nantucket and private donations Estimated completion date: May 2013 - PowerPoint PPT Presentation

Transcript of Hummock Pond Road Bike Path Implementation Update January 25, 2012

Hummock Pond Road Bike Path Hummock Pond Road Bike Path

Implementation UpdateImplementation Update

January 25, 2012January 25, 2012

• Bike path will run from end of Milk Street extension to Cisco Beach• Funding from the Town of Nantucket and private donations• Estimated completion date: May 2013• Implements path six years earlier than Transportation Improvement

Program funding

HPRBP –Implementation Summary

January 2012: - ConCom hearings (January 4th and 18th)- Receipt of abutter right of way comments- County public hearing for taking all easements- Utilities notified / initial design plans distributed

December 2011: - Staking of path centerline and property bounds for Stroll Weekend- Finalize Appraisals, ROW plans, and property owner notices- Conservation Commission review initiated

November 2011: - Development and review of initial design with VHB- Notice to abutters of strategy and property staking- ROW plan complete / initiate

October 2011: - BOS / County approval of implementation strategy- Finalize amendment to design contract with VHB- Wetland review with ConCom staff

HPRBP Implementation Schedule – Tasks Completed

May 2013: - Construction complete

October 2012: - Pre-Construction meetings- Construction Starts

September 2012: - Construction bid opening

July 2012: - Finalize design plans- Construction bid

May 2012: - Initiate final design of bike path

April 2012: - Construction funding ($3.2 million) approved at ATM / ballot- Taking filed at Registry if the funding is approved- Right of way damage award notifications

March 2012: - ROW secured via County taking (recorded after ATM / ballot vote in mid-April)

February 2012: - ConCom hearing – seek approval of Order of Conditions- County hearing of taking challenges

HPRBP Implementation Schedule – Tasks to be completed

Issues: WetlandApprox. 3,600 sqft of total wetland impacts at various locations

Wetland near Millbrook Road intersection