How to build a subsidized virtualization service
Dave [email protected]
IET
Virtualization Overview
• Benefits are well known – Savings in • Space• Power• Deployment time, management overhead, ….
• Virtualization as a service deployed June 2009
• June 2010 we had grown to 156 guests
• Subsidy approved for $150,000 June 2010
IET
Develop a Pricing Model
• Identify all associated costs• Housing• Staff• Security• Training• Hardware/licenses
• Project expected utilization
• Determine service headroom• How long does it take to order additional equipment?• What triggers new order?
• Secure startup funds• Unused equipment reserves
IET
UCD Pricing
• Pricing by memory allocation• $28.50/GB/month• 2GB server $690 / year• Dedicated CPU available
• Pricing break-even based on 57% utilization• As we get more servers, surge margin will be smaller
percentage of total memory and expected utilization will go up
• Review costs and charges frequently• Pass on lower hardware costs to customers
IET
Pricing
• 1 hour setup time per server $77.50 / hr• Only charged in unusual circumstances
• Disk space (annual) • SATA $3.15 / GB • FC $6.82 / GB
• 10% of disk space is reserved for snapshots
IET
Architecture
• Dell M1000 blade chassis
• B710 intel blades with 144GB RAM
• EMC CX4-240 with FC and SATA drives• OS drive must be FC
• Vsphere Enterprise
• Target service was higher end, high availability• Entry level or tiered service was discussed and dismissed
IET
Compare to Departmental Server
• Dell Optiplex 2GB $1,300
• Amortize over 3 years: • $433 yearly cost• Department owns the equipment and can run it past its
useful lifecycle.
• Costs don’t make service worthwhile• (Remember 2GB virt server is $690 / year)
IET
What departments overlook
• Equipment lifecycle management
• Deployment time
• High availability
• Backups – recovery time
• Labor, security, housing
• Networking
IET
What departments don’t care about
• Space• Space is free• We already have space• I can keep it under my desk
• Power• Power is free• Power is centrally managed and paid for• Buildings have metering, but are shared with many
departments
IET
TANSTAAFL
• Power cost for a server• 250W• $0.085 / kWHr• 1.5 PUE• Lbs CO2 per KWHr 0.725
• Each server uses 3,300 kWHr costing $280 and emitting 1.0 tonnes of CO2 annually
IET
Those were conservative
• More liberal numbers• 300 W• $0.12 / kWHr• 1.7 PUE• Lbs CO2 per KWHr 0.725
• 4,500 kWHr costing $540 and emitting 1.5 tonnes of CO2 annually
IET
Determine Costs and Savings
• Power Costs• Might take multiple calls to facilities folks to get the right
person
• Determine PUE• Impossible to do without metering, studies, or consultants• Used SDSC study as a reference
IET
CO2 Reductions
• PGE has kWHr to CO2 conversion on web
• Standard conversions are available at http://www.climateregistry.org/resources/docs/protocols/grp/GRP_3.1_January2009.pdf page 95
• UC has a mandated CO2 reduction goal. Virtualization contributes greatly to that goal.
IET
Calculate space savings
• UCD is short on server room space
• 30 to 1 virtualization ratio means 180 servers in 10U – four racks saved
• Real Estate Services can provide market rate
• Each rack uses 30-40 sqft
IET
Subsidy Justification (based on 108 guests)
• Avoided power usage 338,355 kWHr
• Power cost savings $29,000 ($5,752 per host)
• CO2 savings 111 metric tons
• 60-80 sqft space saved (2 racks)
IET
Get Support
• Who pays the utility bill?• Facilities endorsement
• Environmental Stewardship• Energy Savings, CO2 reduction are campus goals• UCD has AVC of environmental stewardship• Helped with language for proposal
• Client Feedback
IET
Server Room Governance
• Server Room long range planning committee
• Server Room Space Evaluation Committee
• Provost mandate to review all server room retrofits
IET
Subsidy
• $150,000 over three years
• Working on implementation details – goal is to keep costs the same for clients over 3 years
• Need to project utilization over next 3 years
• Will either charge percentages to client and subsidy account or just lower costs overall
IET
Subsidy
• Plan is to apply subsidy to overall rate• Problem is that higher memory systems don’t save as
much power
• Yearly evaluation of program
• Need to project yearly growth to apply subsidy evenly and keep rates the same each year
IET
Backups
• SAN snapshots included for free
• Host based backups available via netbackup• License costs high
• Other products considered • Vranger• Veeam
• Other products cheaper, but required two backup interfaces
• Advantage are file-based, LAN free backups
IET
Other Services
• NAS• EMC NS40G• Highly available• Fully integrates with AD• Snapshots integrated with explorer
• Disaster Recovery• Will host images for future use• Alternate site at UCDMC• Foundry Serveriron Load Balancer
IET
Accounting
• Service is 100% cost recovery
• Charge internal and external clients
• Built billing database using mysql, snmp
• Daily snapshot of disk usage and available systems
• Electronic billing of clients
IET
Other Efforts
• Server room build out approval process
• Server room space inventory – 46,000 sqft
• Passing power costs onto departments• Stanford model
• Server buy back program• Six year old 80 node cluster donated to UCD
IET
Lessons learned
• People don’t care about green when they have to foot the bill for it
• Use fast disk for OS• FC gives us ~4 x performance over SATA
• Don’t let people undersize their systems• Cheap clients cause swapping and disk IO
IET
Resources
• SAICF http://saicf.ucdavis.edu
• SRSEC http://srsec.ucdavis.edu
• Virtualization Service http://virtualization.ucdavis.edu
• Resources http://virtualization.ucdavis.edu/documents.cfm
• Dave Zavatson• [email protected] 530-752-7758