How key events shape stakeholder perceptions of success ... Success... · Although literature...

50
How key events shape stakeholder perceptions of success and failure 17-6-2013 Anke de Poorte MTH-13-01

Transcript of How key events shape stakeholder perceptions of success ... Success... · Although literature...

Page 1: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

How key events shape stakeholder perceptions of success and failure

17-6-2013

Anke de Poorte MTH-13-01

Page 2: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,
Page 3: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

How key events shape stakeholder perceptions of success and failure

Anke de Poorte

Lectoraat New Business & ICT

Instituut voor Communicatie, Media en IT

Kenniscentrum Ondernemerschap

MTH-13-01

17 juni 2013

Page 4: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,
Page 5: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

Abstract

Although literature agrees on the fact that project success is a subjective interpretation of stakeholders, little is known on how stakeholders form their perceptions of success or failure. This paper aims at increased understanding of this process through key events, resulting in the ability to influence the outcomes. Users in HIS-development processes, in this paper healthcare managers and healthcare professionals, were found to construct their perceptions through eight common key events of which four contribute to perceptions of success and four to failure. For developers the key event a good team is especially important, but they ultimately determine the degree of success through evaluation of the quality of their deliverables. An exception was found in the case that all stakeholders perceived as successful, where all stakeholders used the same key events to construct their perception of success. Key events can be used a means to assess the likelihood of a project being perceived as successful. To influence success perceptions and project outcomes, interventions can be designed to facilitate or to prevent the occurrence of key events.

Page 6: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,
Page 7: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

 

 

 

 

How  key  events  shape  stakeholder  perceptions    

of  success  and  failure.    

A  multiple  case  study  in  HIS-­‐development  

 

 

 

 

 

 

 

 

 

Master’s  Thesis  Change  Management  

MSc  Business  Administration    

Anke  de  Poorte  

S2055384  

[email protected]  

06-­‐30962412  

 

 

June  17,  2013  

Word  count:  12213  

 

 

FACULTY  OF  ECONOMICS  AND  BUSINESS  

UNIVERSITY  OF  GRONINGEN    

Page 8: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  2  

 

Abstract  

Although  literature  agrees  on  the  fact  that  project  success  is  a  subjective  interpretation  of  

stakeholders,  little  is  known  on  how  stakeholders  form  their  perceptions  of  success  or  failure.  This  

paper  aims  at  increased  understanding  of  this  process  through  key  events,  resulting  in  the  ability  to  

influence  the  outcomes.    Users  in  HIS-­‐development  processes,  in  this  paper  healthcare  managers  and  

healthcare  professionals,  were  found  to  construct  their  perceptions  through  eight  common  key  

events  of  which  four  contribute  to  perceptions  of  success  and  four  to  failure.  For  developers  the  key  

event  a  good  team  is  especially  important,  but  they  ultimately  determine  the  degree  of  success  

through  evaluation  of  the  quality  of  their  deliverables.  An  exception  was  found  in  the  case  that  all  

stakeholders  perceived  as  successful,  where  all  stakeholders  used  the  same  key  events  to  construct  

their  perception  of  success.  Key  events  can  be  used  a  means  to  asses  the  likelihood  of  a  project  being  

perceived  as  successful.  To  influence  success  perceptions  and  project  outcomes,  interventions  can  be  

designed  to  facilitate  or  to  prevent  the  occurrence  of  key  events.    

 

 

Key  words:  project  success,  project  failure,  stakeholder  perception,  key  events,  healthcare  

information  systems,  IS-­‐development      

Page 9: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  3  

1.  Introduction  

 

Projects  have  become  the  primary  means  for  organizations  to  develop  and  change  (Ika,  2009;  

Pinto,  2010)  and  organizations  initiate  projects  with  the  intention  to  complete  them  successfully.  

Research  on  project  success  revealed  numerous  aspects  that  influence  project  success.  Although  the  

majority  of  this  research  has  tried  to  discover  objective  criteria  (Ika,  2009;  Collins  &  Baccarini,  2004)  

it  is  widely  accepted  that  project  success  is  in  the  eye  of  the  beholder  and  that  stakeholders  

ultimately  decide  whether  a  project  is  successful  (Kaplan  &  Harris-­‐Salamone,  2009;  Ika,  2009;  

Shenhar,  Dvir,  Levy,  &  Maltz,  2001;  Wateridge,  1995).  To  increase  the  number  of  successful  projects,  

it  would  be  helpful  to  understand  how  stakeholders  determine  the  degree  of  success.  This  is  

however  not  a  simple  task  because  perceptions  of  success  evolve  over  time  (Baccarini,  1999;  Ika,  

2009;  Jugdev  &  Müller,  2005;  Lapointe  &  Rivard,  2006).  A  complicating  factor  is  that  stakeholders  

shape  their  perceptions  differently  because  they  perceive  and  judge  success  from  their  own  frame  of  

reference  (Fowler  &  Walsh,  1999;  Shenhar  et  al.,  2001).  Various  authors  support  the  idea  that  

perceptions  of  success  are  constructed  during  projects  (Linberg,  1999;  Teixeira,  Ferreira,  &  Sousa  

Santos,  2012;  Thomas  &  Hernandez,  2008).  At  the  moment,  we  know  very  little  about  this  process  

for  this  area  has  been  neglected  in  research.  As  Ika  (2009)  suggests  “…is  time  to  understand  project  

success  as  it  is  perceived  subjectively  and  as  it  is  constructed  by  stakeholders.”  (Ika,  2009:  p.  5).    

Perception  of  success  is  context  dependent  (Fowler  &  Walsh,  1999)  and  the  value  of  the  

research  would  be  augmented  through  a  context  where  project  success  is  a  rare  commodity.  The  

development  of  healthcare  information  systems  is  such  a  context.  Information  technology  promises  

many  benefits  to  the  healthcare  industry:  It  may  contribute  to  higher  quality  services,  help  to  reduce  

the  increasing  cost  and  it  is  seen  as  a  remedy  for  the  expected  employee  shortage  in  many  countries  

(Eger,  Godkin,  &  Valentine,  2001;  Lau,  Price,  &  Keshavjee,  2011;  Trudel,  Paré,  &  Laflamme,  2012).  But  

IT-­‐projects  are  infamous  for  their  high  failure  rates,  and  this  negatively  influences  the  confidence  of  

the  healthcare  industry  in  IT  (Ammenwerth,  Iller,  &  Mahler,  2006;  Heeks,  2006;  Kaplan  &  Harris-­‐

Salamone,  2009).    

The  development  stage  of  healthcare  information  systems  (HIS)  is  especially  interesting  because  

this  phase  is  critical  for  the  success  of  information  systems  (Hannola  &  Ovaska,  2011)  and  the  ability  

to  positively  influence  this  stage  would  be  an  asset  to  practice.  Previous  literature  on  success  of  such  

projects  is  fragmented.  Many  articles  describe  one  specific  case  and  focus  either  on  the  healthcare  

perspective  or  on  the  perspective  of  information  system  development  (Ammenwerth  et  al.,  2006;  

Eger  et  al.,  2001;  Eley,  Fallon,  Soar,  Buikstra,  &  Hegney,  2008;  Grant,  Campbell,  Gruen,  Ferris,  &  

Blumenthal,  2006;  Lapointe  &  Rivard,  2005;  Linberg,  1999;  Procaccino  &  Verner,  2009;  Saleem,  

Jones,  Van  Tran,  &  Moses,  2006).  I  aim  at  a  comprehensive  view  and  therefore  adopt  a  multiple  case  

Page 10: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  4  

study  approach  where  both  the  healthcare  and  the  information  system  development  perspective  will  

be  explored.    

In  this  paper  I  research  whether  key  events  are  a  useful  mechanism  to  understand  the  process  

by  which  stakeholders  construct  perceptions  of  success  or  failure.  Key  events  are  events  that  

stakeholders  perceive  as  important  and  that  trigger  emotions,  which  in  turn  influence  thoughts,  

feelings  and  actions  and  through  which  stakeholders  construct  perceptions  of  success  and  failure.  

The  concept  of  ‘key  events’  is  supported  in  literature  where  they  are  described  as  a  manner  to  

identify  relevant  transition  moments  in  change  processes  (Munir,  2005;  Stam  &  Stanton,  2010).  Thus,  

I  come  to  research  question  that  will  guide  this  study:  How  do  stakeholders  in  HIS-­‐development  

processes  construct  their  perception  of  success  and  failure  through  key  events?  

This  paper  contributes  to  theory  by  increasing  our  understanding  of  the  process  by  which  

stakeholders  reach  the  conclusion  that  a  project  is  successful.  There  is  little  research  on  the  dynamics  

of  this  process  and  even  less  on  the  influence  of  key  events  on  this  process.    

The  contribution  of  this  study  to  practice  is  that  through  better  understanding  of  the  process  by  

which  perceptions  are  constructed,  interventions  might  be  conceived  that  increase  perceptions  of  

success  or  reduce  perceptions  of  failure.  Both  the  healthcare  and  the  IT-­‐industry  would  benefit  

greatly  when  more  HIS-­‐development  projects  could  be  considered  a  success.  

This  paper  is  set  up  as  follows.  The  next  section  provides  current  theory  on  the  HIS-­‐development  

context  and  on  the  three  underpinning  concepts  of  this  study:  stakeholders,  perception  of  project  

success  and  failure  and  key  events.  The  methodology  section  describes  the  research  approach  and  

introduces  the  cases  that  were  studied.  The  results  section  contains  the  individual  case  results,  which  

is  followed  by  a  cross-­‐case  analysis.  Then,  I  discuss  the  role  of  key  events  in  the  construction  of  

stakeholder  perceptions  and  describe  implications  for  theory  and  practice.  Finally,  I  consider  

limitations  and  directions  for  further  research.    

   

Page 11: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  5  

2.  Theoretical  background  

 

To  understand  how  stakeholders  in  Healthcare  Information  System  (HIS)-­‐development  processes  

construct  their  perception  of  success  and  failure  through  key  events,  I  first  explore  HIS-­‐development  

as  a  context,  and  continue  with  the  concepts  that  need  further  definition:  stakeholders,  perception  of  

success  and  failure  and  key  events.    

 

2.1  HIS-­‐development  

HIS-­‐development  is  a  complex  context  (figure  1).  It  inherits  characteristics  of  several,  very  

different  fields.  HIS  are  information  systems  in  healthcare  and  a  represent  a  specific  field  in    

healthcare  research  and  practice.  Likewise  within  the  field  of  IS,  IS-­‐development  is  specific  area  with  

its  own  research  and  practice.  Where  HIS  meets  IS-­‐development,  one  finds  HIS-­‐development.  In  this  

section  I  explore  the  associated  fields  and  determine  how  they  influence  the  context  of  HIS-­‐

development.    

 

     Figure  1  –  the  context  of  HIS-­‐Development    

 

HIS-­‐development  is  carried  out  in  the  healthcare  industry.  The  healthcare  industry  is  a  unique  

and  complex  domain  because  of  various  interacting  factors:  the  growing  complexity  of  science  and  

technology  in  medical  science,  the  complex  legislation  and  multiple  stakeholders  each  with  various  

goals  and  objectives  (Garde  &  Knaup,  2006;  Sainfort  &  George,  2004).  Healthcare  information  

systems  (HIS)  promise  solutions  for  this  complexity  (Teixeira  et  al.,  2012).  They  create  innovative  

ways  of  working  that  allow  healthcare  practitioners  to  spend  more  time  with  their  patients  by  

working  smarter,  faster,  better  and  more  cost  effectively  (Thakur,  Hsu,  &  Fontenot,  2012).  HIS  are  

also  seen  as  means  to  decrease  medical  errors  and  to  facilitate  learning  (Teixeira  et  al.,  2012).  The  

healthcare  industry  is  very  skilled  at  adopting  stand-­‐alone  technologies  such  as  MRI-­‐scanners,  but  is  

less  adept  at  linking  technology  to  business  processes  (Larsen,  2008).  Unfortunately,  many  HIS-­‐

Informa(on)Systems)

Healthcare)

Healthcare)Informa(on)Systems)

)))IS3Development)

HIS3Development)

Page 12: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  6  

projects  still  fail,  not  because  of  failing  technology,  but  because  of  insufficient  focus  on  human  and  

social  issues  during  the  development  (Teixeira  et  al.,  2012).    

The  IS  in  HIS-­‐development  refers  to  information  systems  (IS).  Hevner,  March,  Park  and  Ram,  

2004:  p.78)  define  IS  as  “…  all  hardware,  software  and  processes  that  support  an  organization  and  

are  composed  of  people,  structures,  technologies,  and  work  systems”.  The  closer  to  the  core  of  a  

business,  the  better  the  fit  must  be  between  the  business  practices  and  the  IS.    McAfee  (2006)  calls  

this  ‘enterprise-­‐IS’  and  the  implementation  of  an  enterprise-­‐IS  results  without  exception  in  major  

changes  in  the  way  organizations  work  (McAfee,  2006).  Because  HIS  are  moving  closer  to  the  core  of  

the  healthcare  processes,  HIS-­‐development  is  increasingly  developing  enterprise-­‐IS  and  as  a  

consequence,  the  implementation  of  HIS  increasingly  generates  major  changes  in  healthcare  

organizations.      

HIS-­‐development  also  contains  IS-­‐development.  IS-­‐development  is  a  complex,  emergent  process  

of  change  with  many  uncertainties  (Markus  &  Robey,  1988;  Orlikowski  &  Lacono,  2001).  During  this  

process,  user  requirements  are  transferred  into  working  solutions  often  through  experimentation  

and  by  trial  and  error  (Hannola  &  Ovaska,  2011;  Leonard,  2004;  Orlikowski  &  Lacono,  2001).    

Summarizing  the  above,  in  HIS-­‐development,  healthcare  information  systems  are  conceived,  

designed  and  built.  The  process  deals  with  three  types  of  complexity.  Firstly,  there  is  environmental  

complexity  because  of  the  highly  complex  environment  of  healthcare  with  conflicting  influences  from  

many  stakeholders.  Secondly,  there  is  organizational  complexity,  because  changing  the  care  

processes  means  changing  the  DNA  of  the  healthcare  organizations.  Lastly,  HIS-­‐development  deals  

with  technological  complexity,  is  innovative  and  of  an  emergent  nature.  To  date,  HIS-­‐development  

seems  to  fail  because  human  and  social  aspects  are  not  sufficiently  taken  into  account  and  the  

approach  is  too  techno-­‐centric  (Heeks,  2006;  Rinkus  et  al.,  2005;  Samaras  &  Horst,  2005;  Zhang,  

2005).    

 

2.2  Stakeholders  in  HIS-­‐development    

Stakeholders  in  HIS-­‐development  inherit  their  characteristics  from  stakeholders  in  healthcare  

and  stakeholders  in  IS-­‐development.  In  this  section  I  explore  the  associated  fields  and  determine  

what  that  means  for  stakeholders  in  HIS-­‐development.  

In  healthcare  four  stakeholder  groups  are  identified:  administrators,  physicians,  nurses  and  

patients  (Lyons  et  al.,  2005;  Lapointe,  Mignerat,  &  Vedel,  2011).  Administrators  are  the  non-­‐medical  

and  financially  responsible  managers  of  healthcare  organizations  (Lapointe  et  al.,  2011).  Physicians  

are  a  highly  independent,  powerful  group  with  focus  on  providing  care,  in  line  with  the  standards  of  

their  occupational  group  (Governance  Institute,  2009;  Lapointe  et  al.,  2011).  Nurses  are  the  medical  

professionals  who  provide  day-­‐to-­‐day  care.  They  are  the  interface  between  physicians  and  patients    

Page 13: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  7  

and  focus  on  patient  care  (Lyons  et  al.,  2005).  The  fourth  stakeholder  group  are  the  patients  who  are  

the  recipients  of  the  care  (Heeks,  2006;  Lapointe  et  al.,  2011;  Lyons  et  al.,  2005).    

In  an  IS-­‐development  context,  stakeholders  are  defined  as  any  individual,  group  or  organization  

that  can  affect  or  be  affected  by  an  information  system  and  who  have  direct  or  indirect  influence  on  

its  requirements  (Ballejos  &  Montagna,  2011).  The  two  most  prevalent  stakeholder  groups  identified  

in  literature  are  users  and  developers  (Agarwal  &  Rathod,  2006;  Ballejos  &  Montagna,  2011;  He  &  

King,  2008;  Hsu,  Liang,  Wu,  Klein,  &  Jiang,  2011;  Lapointe  et  al.,  2011;  Leonard,  2004;  Subramanyam,  

Weisstein,  &  Krishnan,  2010).  Many  authors  describe  the  gap  between  users  and  developers.  They  

seem  to  come  from  different  worlds,  to  speak  different  languages  and  to  have  different  motivations  

and  goals  (Hannola  &  Ovaska,  2011;  Heeks,  2006;  Lapointe  et  al.,  2011).  Users  express  their  needs  in  

their  own  terms  filled  with  tacit  knowledge  and  developers  use  the  vocabulary  of  systems  

development    (Hannola  &  Ovaska,  2011).  For  users,  the  world  of  information  technology  is  often  new  

and  unknown.    They  have  no  idea  of  what  can  be  achieved,  have  limited  technological  literacy  

(Dewan,  Lorenzi,  &  Shaohong,  2004)  and  as  a  result  are  unable  to  articulate  their  requirements  (Pitts  

&  Browne,  2007).    

Close  user  involvement  improves  the  quality  of  the  IS  and  is  especially  important  when  systems  

are  close  to  the  core  of  an  organization  (Ammenwerth  et  al.,  2006;  Harris  &  Weistroffer,  2009;  Jiang,  

Klein,  Wu,  &  Liang,  2009;  Subramanyam  et  al.,  2010).  The  emerging  practice  of  co-­‐creation  makes  

users  partners  in  the  development  process  and  gives  them  a  sense  of  control  over  the  outcome  

(Fernandez  &  Fernandez,  2008;  Harris  &  Weistroffer  (2009);  Prahalad  &  Ramaswamy,  2005;  Teixeira  

et  al.,  2012).  The  scarce  literature  on  HIS-­‐development  concurs  on  user  involvement  and  co-­‐creation  

as  important  ways  to  generate  user  acceptance  (Eger  et  al.,  2001;  Heeks,  2006;  Leonard,  2004;  

Saleem  et  al.,  2006).  The  challenge  in  HIS-­‐development  seems  to  be  merging  the  healthcare-­‐specific,  

functional  expertise  of  users  with  technical  expertise  of  developers  (Cheng  &  Atlee,  2007;  Saleem  et  

al.,  2006).  A  different  solution  comes  from  Heeks  (2006)  who  suggest  an  interpreter,  someone  who  

contributes  to  HIS-­‐development  success  because  he  understands  both  worlds  and  is  able  to  bridge  

the  gap.  

Summarizing  these  explorations,  healthcare  literature  identifies  stakeholders  by  their  role  in  the  

healthcare  organization  and  in  the  care  processes.  Four  stakeholders  are  generally  identified:  

managers,  physicians,  nurses  and  patients.  (H)IS-­‐development  literature  identifies  two  stakeholders:  

users  and  developers  where  users  provide  requirements  and  functional  expertise  and  developers  

provide  the  technical  expertise.  All  healthcare  stakeholders  fit  the  user-­‐profile,  depending  on  the  HIS  

that  is  developed.  Healthcare  managers  bring  expertise  on  general  business  goals  and  finances,  

physicians  and  nurses  bring  functional  expertise  on  clinical  effectiveness  and  knowledge  of  the  care  

processes.  Patients  may  be  users  if  the  HIS  is  part  of  their  treatment.    

Page 14: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  8  

 

2.3  Perception  of  success  and  failure  

In  this  section  I  explore  what  is  known  about  perceptions  of  success  and  failure  in  general  and  

determine  what  is  relevant  for  the  context  of  HIS-­‐development.    

In  project  management  and  IS-­‐literature  there  is  agreement  on  the  fact  that  success  is  difficult  to  

define  and  as  a  consequence  difficult  to  measure  (Jugdev  &  Müller,  2005;  Kaplan  &  Harris-­‐Salamone,  

2009;  Tomas  &  Fernandez,  2008;  Wateridge,  1995).  There  is  little  research  on  this  subject  from  the  

healthcare  perspective.  Two  relevant  studies  on  HIS  success  and  failure  agree  that  defining  HIS  

success  is  complex,  that  there  are  different  definitions  of  success  and  that  better  understanding  of  

different  stakeholder  views  is  needed  (Heeks,  2006;  Kaplan  &  Harris-­‐Salamone,  2009).  Heeks  (2006)  

defines  success  as  a  situation  in  which  most  stakeholder  groups  reach  their  goals  and  do  not  

experience  significant  undesirable  outcomes  and  Kaplan  and  Harris-­‐Salamone  (2009)  define  success  

as  “simply  getting  the  application  or  system  turned  on,  getting  people  to  use  it,  and  getting  at  least  

grudging  acceptance”  (Kaplan  &  Harris-­‐Salamone,  2009:  p.294).    

There  is  also  agreement  that  success  is  a  perception  of  stakeholders  (Agarwal  &  Rathod,  2006;  

Basten,  Joosten,  &  Mellis,  2011;  Ika,  2009;  Jugdev  &  Müller,  2005;  Thomas  &  Fernandez,  2008).  

Stakeholder  perception  of  success  is  most  commonly  operationalized  as  user  satisfaction  (Collins  &  

Baccarini,  2004;  Jugdev  &  Müller,  2005;  Procarino  &  Verner,  2008;  Shenhar  et  al.,  2001).  The  

rationale  is  that  if  users  are  satisfied  with  the  outcome  of  a  project,  they  consider  the  project  a  

success.  In  IS-­‐literature  success  is  also  measured  through  user  satisfaction,  which  is  further  specified  

towards  the  information  system  for  example  as  ease  of  use  (Saleem  et  al.,  2006).  

Failure  is  generally  mentioned  in  one  breath  with  success,  defined  as  ‘not  successful’  and  mainly  

phrased  in  terms  of  the  classic  project  management  criteria  of  time,  cost  and  quality  (Agarwal  &  

Rathod,  2006;  Shenhar  et  al.,  2001;  Wateridge,  1995).  Ojiako,  Johansen  and  Greenwood  (2008)  

conclude  that  failure,  just  as  success,  is  a  matter  of  stakeholder  perception.  

Perception  of  success  or  failure  can  be  influenced.    Time  is  a  factor  known  to  influence  

perception  of  success  (Baccarini,  1999;  Ika,  2009;  Lapointe  &  Rivard,  2006).  Success  is  typically  

measured  at  project  closure,  when  the  outcomes  of  the  project  are  delivered  to  the  sponsor  (Munns  

&  Bjeirmi,  1996),  but  when  the  products  are  used,  user  satisfaction  develops  and  success  evolves  to  

become  the  equivalent  of  how  well  the  project  deliverables  meet  the  users’  needs  (Gray,  1999;  

Jugdev  &  Müller,  2005;  Shenhar  et  al.,  2001).    A  shared  definition  of  success  positively  influences  the  

likelihood  that  a  project  will  be  perceived  as  successful  (Hartman  &  Ashrafi,  2002;  Thomas  &  

Fernandez,  2008;  Wateridge,  1995).  From  IS-­‐literature  is  known  that  user  perception  of  success  is  

influenced  by  the  technological  complexity  of  the  project.  The  more  complex  the  project,  the  more  

users  expect  benefits  compared  to  old  situation  (Shenhar  et  al.,  2001).  Perceived  success  is  also  

Page 15: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  9  

influenced  by  the  time  a  user  has  to  invest  in  a  project.  Less  time  is  better,  most  likely  because  users  

have  to  balance  their  normal  work  and  their  project  work  (Eley  et  al.,  2008;  Subramanyam  et  al.,  

2010).  Participative  development  methods  and  the  use  of  working  prototypes  positively  influence  

user  perception  of  success  because  they  increase  their  sense  of  ownership  and  their  influence  over  

the  outcome  (Eley  et  al.,  2008;  Subramanyam  et  al.,  2010).  For  developers,  perception  of  success  is  

positively  influenced  by  the  innovativeness  of  the  project,  whether  the  functionality  was  delivered  as  

intended  and  if  there  was  a  small,  high  performing  project  team  (Agarwal  &  Rathod,  2006;  Linberg,  

1999;  Procaccino  &  Verner,  2009).  Pereira,  Cerpa,  Verner,  Rivas,  and  Procaccino  (2008)  found  a  

causal  relationship  for  developers  between  teamwork  and  project  success.    

 Concluding  from  literature,  success  is  difficult  to  define  and  measure  and  success  is  a  perception  

of  stakeholders.  Failure  is  defined  as  the  absence  of  success  and  also  a  perception  of  stakeholders.  

Perception  of  success  or  failure  is  time  dependent  and  facilitated  by  a  shared  definition  of  success.  

Different  factors  influence  users  and  developers.  User  perception  of  success  or  failure  is  influenced  

by  technological  complexity,  invested  time,  the  use  of  participative  development  methods  and  

having  access  to  a  working  prototype  (Eley  et  al.,  2008;  Shenhar  et  al.,  2001;  Subramanyam  et  al.,  

2010  ).  Factors  that  influence  developer  perception  are  innovativeness,  delivering  the  product  as  

intended  and  teamwork  (Agarwal  &  Rathod,  2006;  Linberg,  1999;  Pereira  et  al.,  2008;  Procaccino  &  

Verner,  2009).  In  the  field  of  healthcare  no  literature  has  been  found  on  perceptions  of  project  

success  and  failure.  For  HIS-­‐development  the  starting  point  therefore  must  be  what  is  known  from  

project  management  and  IS-­‐development  literature.    

 

2.4  Key  events  

The  final  concept  in  the  research  question  of  this  paper  are  key  events,  which  will  be  defined  in  

this  section.    

To  understand  project  success  as  it  is  perceived  subjectively  one  must  attempt  to  look  through  

the  lens  of  a  stakeholders’  frame  of  reference,  as  if  looking  through  his  eyes.  In  literature  success  

criteria  and  success  factors  are  commonly  used  to  describe  project  success;  success  criteria  are  

standards  or  principles  that  are  used  to  evaluate  the  success  of  a  project  and  success  factors  are  

conditions  or  circumstances  that  facilitate  the  achievement  of  success  (Collins  &  Baccarini,  2004;  Ika,  

2009;  Jugdev  &  Müller,  2005;  Pinto  &  Prescott,  1988;  Shenhar  et  al.,  2001).  Client  consultation,  for  

example,  is  a  success  factor  and  defined  as  “communication,  consultation,  and  action  listening  to  all  

impacted  parties“  (Pinto  &  Prescott,  1988:  p.7).  This  definition,  however,  does  not  consider  the  

stakeholders’  perspective.  It  describes  what  should  be  done  to  achieve  project  success,  but  it  does  

not  explain  how  and  when  a  factor  results  effect  and  who  should  act  the  factor  towards  whom.    

By  identifying  factor  and  process  research  approaches,  Newman  and  Robey  (1992)  provide  a  

Page 16: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  10  

missing  angle  in  the  research  on  project  success.  Research  so  far  has  taken  a  factor  approach  where  

success  criteria  and  factors  describe  predictors  and  inferred  outcomes  but  do  not  explain  how  one  

leads  to  the  other  (Newman  &  Robey,  1992).  Process  approaches  describe  series  of  events  which  

explain  how  and  why  results  occur  (Newman  &  Robey,  1992)  and  allow  to  understand  a  process  as  

stakeholders  experience  it.  Therefore,  I  will  use  a  process  approach  to  search  for  events  that  explain  

how  stakeholders  construct  their  perceptions  of  success  and  allow  for  understanding  their  

perspective.    

Critical  encounters  or  key  events  are  the  focus  of  study  in  a  process  approach  (Newman  &  

Robey,  1992).    Isabella  (1990)  and  Dutton  and  Dukerich  (1991)  used  the  concept  of  key  events  to  

similar  effect  as  they  tried  to  learn  as  much  as  possible  about  stakeholders’  emotions,  thoughts  and  

responses  to  these  key  events.  They  used  these  as  a  means  to  understand  the  unfolding  processes  

that  they  researched  (Dutton  &  Dukerich,  1991;  Isabella,  1990).  Key  events  have  been  defined  as  

events  that  are  important  to  an  individual  (Isabella,  1990;  Schein,  2010),  not  necessarily  large  or  

spectacular  events.  Key  events  are  also  described  as  a  manner  to  identify  relevant  transition  

moments  in  change  processes  (Munir,  2005;  Stam  &  Stanton,  2010).  

To  identify  key  events  I  will  search  for  the  emotions  that  were  triggered  by  these  events.  

Emotions  are  the  fitting  search  criterion  because  emotions  arise  in  response  to  events  that  an  

individual  perceives  as  relevant  and  important  (Beaudry  &  Pinsonneault,  2010,  Stam  &  Stanton,  

2010).  The  emotions  will  help  stakeholders  to  identify  such  events  because  these  events  are  

characterized  by  the  fact  that  an  individual  can  recall  exactly  how  he  felt  when  the  event  occurred  

(Bagozzi  et  al.  1999).    

The  theory  above  supports  the  underlying  assumption  of  this  paper  that  key  events  are  a  useful  

mechanism  to  understand  how  stakeholders  construct  their  perception  of  success  or  failure.    

Integrating  the  statements  above,  I  define  key  events  as  events  that  stakeholders  perceive  as  

important  and  that  trigger  emotions,  which  in  turn  influence  thoughts,  feelings  and  actions,  and  

through  which  stakeholders  construct  perceptions  of  success  and  failure.    

 

   

Page 17: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  11  

3.  Methodology  

 

The  goal  of  this  study  is  to  increase  our  understanding  of  the  way  stakeholders  in  HIS  

development  processes  construct  their  perception  of  success  or  failure  through  key  events.  

 I  chose  to  conduct  an  interpretive  study,  based  on  three  arguments.  Firstly,  positivist  research  

on  stakeholder  perception  of  project  success  has  not  been  able  to  capture  the  complexity  of  this  

subject  (Ika,  2009)  and  interpretive  research  could  complement  our  understanding  by  filling  in  

knowledge  gaps  (Orlikowski  &  Baroudi,  1991).  Secondly,  this  study  aims  at  increased  understanding  

of  human  interaction  and  therefore  fits  within  interpretive  research  (Orlikowski  &  Baroudi,  1991).  

Finally,  I  do  not  believe  that  that  researchers  are  impartial  observers  who  can  evaluate  objectively  

(Paré,  2004),  and  I  share  the  opinion  of  Quek  and  Garcia  (1997)  who  believe  that  a  researcher’s  

interpretations  play  a  key  role  to  bring  quality  arguments  (Quek  &  Garcia,  1997).  I  chose  to  conduct  

an  exploratory  case  study  because,  according  to  various  authors,  exploratory  case  studies  allow  for  

inductive  development  of  theory  by  the  letting  patterns  and  underlying  logic  emerge  (Benbasat,  

Goldstein  &  Mead,  1987;  Darke,  Shanks,  &  Broadbent,  1998;  Paré,  2004).  A  multiple  case  study  was  

chosen  to  gather  more  compelling  evidence  (Dubé  &  Paré,  2003),  to  go  beyond  initial  observations  

(Eisenhardt,  1989),  to  allow  a  cross-­‐case  search  for  patterns  (Eisenhardt,  1989),  and  empirical  testing  

through  pattern-­‐matching  (Yin,  2009).    

The  cases  were  selected  from  applied  research  projects  in  the  professorship  New  Business  and  

ICT  in  the  research  area  Health  and  ICT  at  Hanze  University  of  Applied  Science,  Groningen  in  the  

period  2010-­‐2013.  These  projects  allow  healthcare  organizations  to  explore  the  application  of  new  

technologies  and  innovate  through  student  projects.  The  projects  are  generally  semester  

assignments.    

According  to  Paré  (2004),  a  researcher  looks  in  case  studies  for  a  particularly  good  story  that  

illuminates  the  questions  under  study.  The  HIS-­‐development  research  projects  provide  such  stories,  

because  the  HIS  that  are  developed  are  enterprise-­‐IS  where  technology  is  embedded  in  the  care  

processes.  During  this  stage  users  and  developers  interact  to  ensure  that  the  functional  knowledge  of  

users  becomes  part  of  the  systems  (Cheng  &  Atlee,  2007;  Hannola  &  Ovaska,  2011;  Saleem  et  al.,  

2006).  Differences  between  the  stakeholders  will  inevitably  surface  (Heeks,  2006;  Lapointe  et  al.  

2011)  and  provide  a  context  filled  with  interaction  where  much  can  be  learned.    

The  functional  knowledge  that  users  should  bring  in  HIS-­‐development  processes  could  be  

provided  by  all  healthcare  stakeholder  groups.  For  this  study  I  chose  to  look  at  the  user  perspective  

through  two  stakeholder  groups:  healthcare  managers  and  healthcare  professionals.  Healthcare  

managers  provide  the  perspective  of  business  goals  and  finances.  Healthcare  professionals  are  

Page 18: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  12  

physicians  and  nurses  who  provide  the  care  perspective.  The  third  stakeholder  group  in  this  research  

are  developers;  teachers  and  students  in  computer  science.    

To  find  particularly  fitting  stories,  I  used  criterion  sampling  (Paré,  2004)  based  on  three  criteria:  

1.  the  case  concerns  a  HIS-­‐development  process  of  enterprise-­‐IT,  2.  the  three  stakeholder  groups  

under  research  (healthcare  managers,  healthcare  professionals,  and  developers)  were  involved,  and  

3.  the  case  delivered  a  working  prototype.  The  selection  process  was  performed  by  the  leading  

professor  and  the  researcher.  From  a  first  long-­‐list  of  eight  potentially  suitable  cases  four  cases  were  

selected.  Of  the  four  cases  that  were  not  studied,  in  two  cases  the  HIS  development  process  did  not  

fit  within  this  study  and  in  two  cases  the  required  stakeholder  groups  were  not  available  for  

interviews.    

To  ensure  reliability  and  consistency,  the  main  data  collection  was  done  through  interviews  

using  a  case  study  protocol  (added  as  Appendix  A).  To  ensure  validity,  multiple  sources  of  data  were  

used:  project  documentation,  observations  and  publicly  available  information  on  the  participating  

organizations  (Eisenhardt,  1989;  Paré,  2004;  Yin,  2009).  One  case  was  used  as  the  pilot  case  and  

because  no  adjustments  to  the  interview  script  were  required,  this  case  was  included  in  the  study.  

The  average  length  of  the  interviews  was  approximately  one  hour.  The  interviews  consisted  of  open  

questions,  aimed  at  understanding  the  stakeholders’  perception  of  project  success  and  failure,  his  

identification  of  key  events  and  effects  of  these  events  on  his  actions  and  thoughts  related  to  his  

perception  of  success  or  failure.  A  total  of  16  interviews  was  held,  four  healthcare  managers,  six  

healthcare  professionals  and  six  developers.  Interviewees  reviewed  their  transcript  and  the  case  

description  of  their  case.  During  the  data  processing  stage  some  further  clarification  was  obtained  

through  follow-­‐up  e-­‐mails  and  interviews.  Information  was  collected  between  1  and  18  months  after  

the  projects  were  completed.  All  stakeholders  were  interviewed  individually  to  avoid  group  think  

bias.    

The  interviews  were  recorded  and  transcribed,  except  for  one  where  the  recording  technology  

failed.  Field  notes  were  taken.  Data  analysis  in  qualitative  research  is  the  result  of  an  iterative  

process  of  data  reduction  that  leads  to  data  displays  which  allows  for  data  analysis    and  conclusion-­‐

drawing  and  verification  (Huberman  &  Miles,  1984).  The  data  analysis  in  this  study  was  done  in  a  

five-­‐step  process.  During  the  first  step  stakeholder  responses  were  coded  and  placed  in  an  overview  

per  interviewee  by  interview  question  and  the  individual  overviews  were  aggregated  into  an  

overview  per  case.  In  the  second  step  the  aggregated  overview  was  used  to  create  the  individual  

case  descriptions.  The  information  was  dissected  in  the  three  dimensions  of  Pettigrew  and  Whipp’s  

model  of  strategic  management  of  change  (Pettigrew  &  Whipp,  1991):  content,  context  and  process.  

This  model  was  used  to  create  rich  case  descriptions  (Yin,  2009)  and  was  chosen  because  it  has  been  

used  for  this  purpose  before  (Stetler  et  al,  2007).  During  the  third  step  of  the  data  analysis,  key  

Page 19: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  13  

events  that  according  to  stakeholders  contributed  to  success  or  failure  were  collected  from  the  case  

overviews  and  placed  in  an  overview  which  visualizes  the  events  per  stakeholder  and  per  project  

phase.  The  fourth  step  covered  the  within-­‐case  analysis,  which  resulted  in  a  description  of  the  

process  by  which  each  stakeholder  constructed  his  perception  of  success.  The  final  step  consisted  of  

the  cross-­‐case  analysis.  Pattern-­‐matching  was  used  to  generate  a  cross-­‐case  overview  of  key  events.  

Through  a  search  for  patterns  and  dissimilarities  eight  common  key  events  and  two  approaches  to  

constructing  perceptions  emerged.  These  were  the  basis  for  the  conclusion-­‐drawing  and  verification  

in  the  discussion  section  of  this  paper.    

 

   

Page 20: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  14  

4.  Case  descriptions  and  within-­‐case  analysis    

 

This  section  presents  the  within-­‐case  analyses  of  the  four  cases  that  were  examined.  In  the  the  

general  idea  of  the  project  and  the  involved  stakeholders  are  described.  The  content  describes  the  

envisioned  HIS  and  what  stakeholders  consider  a  success.  Under  process,  the  story  of  the  project  is  

told.  For  each  case  the  within-­‐case  analysis  presents  an  integrated  overview  of  key  events,  a  

description  of  the  perception  construction  process,  and  concludes  with  the  answer  to  the  research  

for  that  particular  case.    

 

 Figure  2  –  Case  overview  

 

4.1  Case  1  -­‐  Exercise  stimulation  

Context    

In  a  protected  home  environment  for  clients  with  visual  and  mental  deficiencies  a  project  was  

started  to  research  whether  clients  could  be  motivated  by  music  to  exercise  at  a  higher  level  of  

intensity,  and  whether  a  relation  between  an  external  motivator  and  exercise  intensity  could  be  

learned.  Many  clients  have  physical  disabilities  as  well  and  are  wheelchair  bound.  Motivating  these  

clients  to  exercise  is  a  challenge,  but  it  is  important  because  exercise  contributes  to  health  and  

wellbeing.  Constant  supervision  is  required  to  reach  the  desired  level  of  exercise.  External  motivation  

might  help  to  reach  results  with  more  clients  at  the  same  time  and  reduce  the  need  for  one-­‐to-­‐one  

supervision.  In  this  case  a  professor-­‐physiotherapist  and  a  motion  therapist  from  the  healthcare  

organization  were  involved.  From  the  applied  research  projects,  a  healthcare  and  a  computer  science  

teacher  and  student  groups  of  various  backgrounds  were  involved.  

 

Content    

The  HIS  would  be  an  exercise  stimulation  system  where  music  and  other  sounds  are  used  as  

motivators.  The  system  must  allow  for  individual  definition  of  the  desired  level  of  exercise  intensity.  

A  stimulant  might  be  a  favorite  song  or  the  voice  of  a  therapist  or  a  loved  person.    Sound  stimulants  

should  be  tailored  to  each  client.  Different  sound  stimulants  must  be  available  to  start  activities,  to  

Case%details Exercise%stimulation Independent%living%support Reliving%memories Mobile%treatment%support

Duration%(months) 15 24 18 6Type%of%care inFpatient outFpatient inFpatient outFpatient

Healthcare%managers 1 1 1 1Physicians/Nurses 2 1 2 1Developers 1 1 2 2

Total&interviews 4 3 5 4

Page 21: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  15  

stimulate  continuation  and  to  increase  the  intensity  of  the  exercise.  A  heart  rate  belt  would  be  used  

to  detect  exercise  activity.  Activity  data  would  be  logged  to  monitor  the  effects  of  exercising  over  

time.    

All  stakeholders  defined  success  as  a  working  HIS  that  would  stimulate  clients  to  reach  higher  

levels  of  exercise  intensity.  For  the  healthcare  manager  success  would  also  be  a  scientifically  proven  

approach  and  more  knowledge  on  motivation  of  their  clients.  For  the  healthcare  professional  an  

important  criterion  was  added  value  in  the  care  for  the  clients;  “The  system  must  not  replace  our  

relation  with  the  client.  It  should  be  an  extension  of  or  an  addition  to  the  relation.”  The  developers  

defined  success  as  a  product  would  exceed  customer  expectations  resulting  in  a  satisfied  customer  

and  considered  reduction  of  the  intensity  of  the  care  a  success  criterion.  

 

Process    

Project  duration  was  15  months  and  consisted  of  three  phases.  During  the  first  phase  a  

prototype  was  build  and  demonstrated  in  a  lab  environment.  During  the  second  phase,  the  

prototype  was  tested  in  the  healthcare  environment  with  clients.  The  prototype  worked  and  the  

intended  effects  were  observed,  but  the  heart  rate  sensor  did  not  provide  the  effects  consistently.  

Based  on  the  test  results  with  clients,  an  implementation  advice  was  delivered  which  proposed  

functional  fine  tuning  and  the  use  of  a  different  sensor,  for  example  a  rotation  counter.  During  the  

third  phase  this  advice  should  have  been  implemented.  This  however,  did  not  happen.  The  project  

ended  with  a  partially  installed  sensor  on  a  home  trainer.    

 

Within-­‐case  analysis  

Stakeholders  in  this  case  identified  12  key  events,  six  contributing  to  success  and  six  contributing  

to  failure.    

 

 

 

Page 22: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  16  

 

 

Figure  3  –  Overview  of  key  events  Case  1  

 

The  healthcare  manager  experienced  key  events  contributing  to  success  during  all  phases  of  the  

project.  The  enthusiasm  of  the  developers  made  him  think  the  idea  was  feasible.    The  excellent  

prototype  augmented  that  feeling  and  increased  his  own  enthusiasm.  When  the  intended  effects  

were  observed,  he  felt  that  implementation  was  close  at  hand.  He  realized  that  the  project  was  more  

complicated  than  he  anticipated  when  the  third  phase  did  not  deliver,  and  communication  from  the  

developers  stopped.  This  led  to  disappointment  and  the  realization  that  implementation  would  

require  more  time.    His  final  perception  is  that  the  project  is  neither  a  success  nor  a  failure  but  that  it  

is  not  finished;  “  When  I  saw  the  prototype  I  was  really  impressed.  The  product  was  nearly  ready.  

And  I  still  hope  to  get  a  working  product.  I  am  not  satisfied,  because  it  is  simply  not  finished  yet.”  

For  the  healthcare  professional  the  project  organization  was  unclear  from  the  onset  of  the  

project.  He  found  the  enthusiasm  of  the  developers  very  important  because  it  made  him  feel  heard.  

He  was  impressed  by  the  prototype.  During  the  second  phase  he  felt  no  longer  part  of  the  project  

because  communication  stopped  and  because  it  was  not  clear  why  it  stopped.  When  no  working  

product  was  delivered,  his  perception  of  the  project  was  failure.    

One  of  the  developers  developed  the  prototype.  He  experienced  excellent  teamwork  as  a  key  

event  contributing  to  success  and  delivered  an  excellent  product,  which  for  him  resulted  in  a  

perception  of  success.    

Identified(by(stakeholder1 Enthusiasm*of*the*developers Healthcare*manager,*Healthcare*professional2 The*willingness*of*the*developers*to*learn*about*care*processes Healthcare*professional3 This*is*a*good*team Developer*14 The*excellent*quality*of*the*working*prototype* Healthcare*manager,*Healthcare*professional5 The*high*quality*of*the*implementation*advice* Healthcare*manager,*Healthcare*professional6 The*finish*is*within*reach Healthcare*manager,*Healthcare*professional

Identified(by(stakeholderA Project*organization*was*unclear Healthcare*manager,*Healthcare*professionalB ‘No*communication’*and*unclear*why*communication*stopped Healthcare*manager,*Healthcare*professionalC More*time*is*needed Healthcare*managerD Disappointment*because*of*unfinished*product Healthcare*managerE The*prototype*does*not*work*as*expected*with*clients Developer*2F Not*being*able*to*deliver*to*developer’s*standards Developer*2

Contributing(to(success

Contributing(to(failure

Stakeholder Phase&1 Phase&2 Phase&3 Phase&1 Phase&2 Phase&3

Healthcare&Manager 1,&4 1,&5 1,&6 6 A,&B A,&B,&C,&D

Healthcare&professional 1,&2,&4 1,&5 1 A A,B A,B

Developer&1 3 6 6 6 6 6

Developer&2 6 6 6 6 E,&F F

Key$events$contributing$to$success Key$events$contributing$to$failure

Page 23: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  17  

The  other  developer  was  involved  during  the  whole  project.  He  delivered  a  working  prototype  

according  to  agreed  specifications,  which  he  considers  a  success.  He  evaluates  the  key  event  that  the  

sensor  did  not  work  as  expected  outside  his  influence  although  it  caused  him  not  to  be  able  to  

deliver  to  his  quality  standards;  “I  am  a  developer  and  I  cannot  doubt  the  knowledge  of  the  expert  in  

his  field,  because  if  I  did,  I  would  have  to  become  an  expert  in  that  field  myself.  I  don’t  want  that  and  

even  if  I  wanted  to,  it  would  be  impossible.“  As  a  consequence  of  these  key  events  he  modified  his  

perception  from  success  to  partial  success.    

Concluding,  the  stakeholders  in  this  case  constructed  their  perceptions  of  partial  success  and  

failure  in  different  ways.  For  the  healthcare  manager,  the  key  events  contributing  to  success  were  so  

powerful  that  he  continues  to  believe  that  the  end-­‐result  is  within  reach.  He  does  not  accept  partial  

success  or  failure  and  therefore  did  not  form  a  final  perception.  The  healthcare  professional  

experienced  key  events  contributing  to  failure  during  the  whole  project.  Although  he  identified  key  

events  that  contributed  to  success,  they  were  not  strong  enough  to  modify  his  perception  of  failure.  

One  developer  only  experienced  key  events  that  contributed  to  success  and  he  perceived  the  project  

as  a  success.  The  other  developer  considered  the  project  a  partial  success,  but  this  perception  was  

not  formed  by  the  interaction  of  key  events.  His  perception  came  from  the  fact  that  he  considers  the  

causes  for  failure  outside  his  influence.    

 

4.2  Case  2  –  Independent  living  support  

Context    

In  this  case  the  healthcare  organization  started  a  project  to  find  out  if  and  how  smart  technology  

could  support  independent  living  of  clients  with  minor  mental  deficiencies.  These  clients  have  

difficulties  in  certain  areas  of  self-­‐organization,  for  example  keeping  a  regular  day-­‐night  pattern.  They  

receive  outpatient  care  mainly  through  home  visits  by  counselors.  The  smart  technology  would  help  

to  reduce  the  amount  of  care  and  the  number  of  people  involved  in  the  care  because  counselors  

would  be  guided  to  provide  the  right  care  at  the  right  time.  The  smart  technology  would  allow  clients  

to  retake  control  of  parts  of  their  lives.  In  this  case  a  team  manager  responsible  for  the  outpatient  

care  and  an  outpatient  counselor  were  involved  from  the  healthcare  organization.  From  the  applied  

research  projects  a  healthcare  teacher,  a  computer  science  teacher  and  different  groups  of  students  

from  various  backgrounds  were  involved.  

 

Content  

The  HIS  would  be  smart  technology,  in  and  around  the  house,  that  would  help  clients  in  three  

known  problem  areas:  maintaining  a  regular  day-­‐night  pattern,  home-­‐work-­‐traffic  and  managing  

energy  cost.  The  system  consisted  of  various  sensors  in  client  homes.  Sensor  output  was  transmitted  

Page 24: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  18  

to  a  central  system  where  SMS-­‐messages  were  generated.  The  system  could  be  tailored  for  each  

client:  which  messages  should  be  send,  when  and  how  often  and  whether  a  counselor  was  informed  

or  not.  A  portable  demo  case  was  developed  during  the  project.    

All  stakeholders  described  success  as  the  smart  technology  having  been  implemented  with  a  

number  of  clients  and  supporting  the  three  identified  problem  areas.  The  healthcare  professional  

and  the  developer  considered  added  value  for  clients  and  counselors  an  additional  measure.  For  the  

developer  success  also  meant  a  satisfied  principal  and  a  learning  experience.  

 

Process    

The  project  was  duration  was  24  months  and  consisted  of  two  phases.  During  the  first  phase,  

preliminary  research  was  performed  on  useful  sensors  and  a  baseline  questionnaire  was  to  be  

developed,  but  neither  product  was  delivered  to  satisfaction.  During  second  phase,  the  project  

approach  was  changed,  so  that  learning  in  the  healthcare  organization  would  be  supported.  A  series  

of  short  development  cycles  were  executed.  At  the  end  of  every  cycle  the  healthcare  professionals  

could  experiment  with  the  system  and  suggest  improvements.  During  one  of  these  cycles  a  portable  

demo  case  was  conceived,  which  became  an  important  tool  in  explanatory  meetings  with  clients  and  

counselors.  This  phase  concluded  with  the  installation  of  the  system  in  the  clients’  homes.  

The  project  faced  innumerable  problems  with  technology.  Although  the  sensors  were  known  to  

work  in  a  different  environment,  time  and  again  they  did  not  function  as  expected.  There  were  many  

technical  and  organizational  issues  with  suppliers.  Fault  tracing  was  complex  and  time  consuming  

because  of  the  number  of  organizations  involved,  because  of  privacy  issues  and  because  the  

geographical  dispersion  of  the  involved  locations.  All  stakeholders  concluded  that  the  complexity  of  

the  HIS  was  underestimated  and  that  the  chosen  pilot  environment  had  increased  the  complexity.  

 

Within-­‐case  analysis    

Stakeholders  identified  12  key  events,  six  contributing  to  success  and  six  contributing  to  failure.    

 

Page 25: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  19  

 

 

Figure  4  –  Overview  of  key  events  Case  2  

 

To  construct  his  perception,  the  healthcare  manager  carefully  revisited  the  key  events  he  

identified  and  considered  their  impact.  The  continuing  issues  with  technology  and  the  fact  that  

suppliers  were  unable  to  adjust  their  ways  of  working  to  the  clients  were  major  sources  of  irritation  

and  frustration.  In  his  perception  these  key  events  ultimately  caused  an  unreliable  HIS  and  he  

perceived  that  as  failure.  He  modified  his  perception  to  partially  successful  through  the  key  events  

that  contributed  to  success.  The  demo  case  and  the  excursion  to  the  supplier  facilitated  and  

stimulated  learning  with  both  clients  and  counselors;  “People  have  become  more  attuned  to  

technology  as  an  aid  to  organize  things.”  He  also  felt  that  his  personal  involvement  showed  

commitment  to  the  original  ideas;  “  I  am  still  convinced  that  it  could  work  and  I  often  thought  about  

another  location  that  would  have  been  a  better  fit.”  

In  the  perception  of  the  healthcare  professional  the  project  was  a  partial  success.  The  process  by  

which  he  came  to  the  conclusion  was  similar  to  that  of  the  healthcare  manager.  The  key  events  

contributing  to  failure  in  his  case  led  to  dispiritedness,  because  every  technological  issue  and  every  

issue  between  suppliers  and  clients  reduced  the  likelihood  of  a  working  HIS.  In  this  process  he  could  

indicate  precisely  when  he  missed  a  person  in  charge;  “  I  would  have  liked  to  have  one  person  who  

was  really  in  charge,  who  understood  all  steps  and  had  time  to  communicate  everything  with  

everybody”.  He  then  considered  the  joyful  learning  experience  which  for  him  was  a  key  event  

Identified(by(stakeholder

1 The$high$quality$demo$case$to$demonstrate$the$ideaHealthcare$manager,$Healthcare$professional,$Developer

2 Excursion$to$supplier$with$clients$ Healthcare$manager3 Active,$positive,$personal$involvement$ Healthcare$manager4 An$exiting$journey$of$discovery$and$learning Healthcare$professional5 A$good$team$ Developer6 Prinicpal$actively$and$closely$involved Developer

Identified(by(stakeholderA Many,$many$issues$with$technology Healthcare$manager,$Healthcare$professionalB Suppliers$do$not$deal$well$with$our$clients Healthcare$manager,$Healthcare$professionalC Not$enough$time$to$make$it$work Healthcare$professionalD Not$one$person$in$charge Healthcare$professional,$DeveloperE No$requirements$specification$by$users DeveloperF Supplier$backing$out Developer

Contributing(to(success

Contributing(to(failure

Stakeholder Phase&1 Phase&2 Phase&1 Phase&2

Healthcare&Manager 1 1,&2,&3 A,&B A,&B

Healthcare&professional 1 1,&4 A,&B,&D A,&B,&C,&D

Developer&1 1 5,&6 1 D,&E,&F

Key$events$contributing$to$failureKey$events$contributing$to$success

Page 26: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  20  

contributing  to  success.  He  considered  the  useful  information  that  was  gathered  and  concluded  that  

in  his  perception  that  the  project  was  partially  successful.  

The  developer  also  perceived  the  project  as  partially  successful,  but  through  different  reasoning.  

His  first  key  event  contributing  to  success  was  the  realization  that  he  had  a  good  team  of  developers.  

This  allowed  for  pleasant,  effective  teamwork  and  the  delivery  of  a  better  product.  For  him  the  

inability  of  the  organization  to  formulate  requirements  was  a  key  event  contributing  to  failure.  This  

could  have  stopped  the  project  before  it  started.  In  response  he  decided  to  start  development  based  

on  common  sense.  He  felt  this  was  a  key  event  contributing  to  success,  because  with  the  first  

prototype  the  healthcare  organization  was  able  to  start  their  contribution  to  the  development  

process.  Like  the  healthcare  professional,  he  also  could  precisely  indicate  when  he  had  missed  

someone  in  charge.  When  the  supplier  backed  out,  he  felt  that  project  success  was  out  of  his  hands.  

Weighing  the  key  events  he  evaluated  the  project  as  partially  successful.  “My  approach  at  least  led  to  

the  delivery  of  some  tangible  results  and  considerably  improved  the  mood  of  the  people  in  

healthcare  organization.”  

Concluding,  stakeholders  in  this  case  constructed  their  perceptions  in  different  ways.  They  all  

started  the  construction  of  their  perception  with  the  observation  that  the  project  did  not  deliver  a  

working  HIS.  The  healthcare  manager  and  the  healthcare  professional  then  remembered  key  events  

contributing  to  failure  and  felt  those  were  the  reason  that  the  project  could  not  deliver.  They  

continued  with  key  events  that  contributed  to  success  and  remembered  joy,  enthusiasm  and  

learning.  They  finished  the  construction  of  their  perception  by  carefully  taking  stock  of  both  types  of  

events  and  the  scales  tipped  to  a  perception  of  partial  success.    The  developer  did  not  construct  his  

perception  of  partial  success  through  the  key  events  he  had  identified.  He  considered  the  positive  

results  of  his  assignment,  then  he  explained  that  the  causes  for  failure  were  outside  his  influence,  

and  concluded  that  the  project  in  his  perception  was  partially  successful.  

 

4.3  Case  3  –  Reliving  memories  

Context    

In  this  cases  a  nursing  home  where  elderly,  demented  people  are  cared  for,  wanted  to  add  

reliving  memories  to  their  care  program.  For  any  type  of  care  it  is  important  to  fit  the  care  program  

to  the  client.  With  demented  people  this  is  difficult  because  clients  have  forgotten  much  about  

themselves  and  caregivers  have  to  turn  to  the  family  for  relevant  information.  The  care  program  

includes  physical  and  social  activities  aimed  at  stimulating  clients  such  as  singing  and  walking.  

Reliving  memories  would  add  an  activity  to  the  existing  palette.  In  this  case  a  team  manager  and  

caregivers  were  involved  from  the  healthcare  organization.  From  the  applied  research  projects  

various  teachers  and  different  groups  of  students  from  various  backgrounds  were  involved.  

Page 27: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  21  

 

Content    

The  HIS  would  be  a  care  intervention  for  elderly,  demented  people  where  they  could  relive  

memories  through  a  virtual  reality  of  images,  sounds,  light  and  fragrance.  Reliving  memories  would  

be  a  pleasurable  experience  contributing  to  the  wellbeing  of  a  client.  It  would  be  a  place  where  

clients  and  their  families  could  relive  the  past.  It  also  would  help  caregivers  to  get  to  know  their  

clients  better  and  use  this  knowledge  in  the  day-­‐to-­‐day  care.  A  lifeline  assessment  was  developed  to  

collect  personal  information.  For  every  client  a  base  line  measurement  was  taken.  A  sensor  belt  and  

camera  were  used  to  monitor  responses  during  the  intervention  and  the  collected  data  were  stored  

to  study  the  effects  of  the  intervention.  

The  healthcare  manager  described  success  as  a  situation  where  the  environment  would  be  

embedded  in  the  day-­‐to-­‐day  care;  “..  an  environment  in  our  building  where  we  or  the  family  could  go  

with  our  clients  and  enjoy  the  experience.”    One  healthcare  professional  described  success  through  

an  example;  the  benefits  he  imagined  for  a  specific  client.  Another  healthcare  professional  described  

success  as  an  environment  that  allows  complete  immersion  in  the  experience  with  proven  results  

and  accumulation  of  knowledge  on  the  intervention;  “An  environment  where  clients  can  have  life-­‐

like  experiences  and  we  would  know  if  the  experience  is  meaningful  for  clients.”  Developers  

described  project  success  as  delivering  a  product  that  satisfies  the  principal,  but  it  would  suffice  to  

reach  the  technical  goals.  Success  for  the  developers  is  also  a  pleasant  working  experience  and  to  

deliver  something  that  they  can  be  proud  of,  as  one  developer  explained;  “  I  like  to  be  able  to  point  

to  a  product  and  say  to  friends  that  I  was  part  of  that  project.”  

   

Process  –  the  story  

The  project  duration  was  approximately  18  months  and  covered  three  phases.  During  the  first  

phase  the  lifeline  assessment  was  developed,  the  virtual  environment  was  installed  and  an  

application  prototype  was  built.  The  intended  effects  were  observed  with  clients.  The  second  phase  

was  characterized  by  organizational  and  technological  setbacks.  The  healthcare  organization  was  

moving  which  occupied  caregivers  and  clients,  leaving  little  time  and  attention  for  the  project.  The  

data  and  technology  of  the  first  phase  were  virtually  non-­‐existent.  The  second  team  was  hard  

pressed  to  deliver  anything  but  managed  to  continue  the  project.  The  healthcare  organization  was  

somewhat  disappointed  in  what  was  delivered  during  this  phase.  Communication  was  unstructured.  

A  few  times,  the  healthcare  organization  organized  extra  personnel  to  accompany  clients  and  the  

project  could  not  deliver.  This  was  not  taken  lightly  because  funds  are  scarce.  Another  issue  were  the  

families  who  had  invested  time  and  energy  and  did  not  receive  what  was  promised.  The  technology  

Page 28: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  22  

turned  out  to  be  more  complex  than  anticipated.  During  the  third  phase  a  robust  system  is  

developed  and  the  first  working  prototypes  have  been  delivered.    

 

Within-­‐case  analysis    

Stakeholders  identified  11  key  events,  five  contributing  to  success  and  six  contributing  to  failure.    

 

 

 Figure  5  –  Overview  of  key  events  Case  3  

 

To  construct  his  perception  of  success,  the  healthcare  manager  first  remembered  the  observed  

effects  with  clients,  which  for  him  was  the  single,  most  important  key  event.  Then  he  considered  the  

four  events  contributing  to  failure  and  he  described  how  these  had  affected  his  expectations.  He  

realized  that  the  project  would  take  longer  and  that  working  with  students  was  more  complex  than  

anticipated;    “There  is  a  lot  of  work  to  be  done  before  it  will  be  embedded  in  care  processes,  the  way  

I  envisioned  it”.    He  then  considered  his  active  personal  involvement,  which  allowed  him  to  spread  

his  belief  in  the  project.  Finally  he  considered  the  whole  project  as  very  interesting  and  something  he  

enjoyed;  “It  simply  is  a  lot  of  fun.”    

One  healthcare  professional  started  with  revisiting  the  events  were  the  student  results  were  not  

as  expected  and  the  effects  thereof  on  care  givers  and  family.  He  also  considered  his  experiences  

Identified(by(stakeholder1 This%is%an%interesting%project%and%a%lot%of%fun Healthcare%manager,%Healthcare%professional%2

2 The%observed%effects%with%clientsHealthcare%manager,%Healthcare%professional%1,%Healthcare%professional%2

3 Active,%positive,%personal%involvement Healthcare%manager,%Healthcare%professional%24 A%good%team% Developer%15 Clear%directions%from%principal Developer%2

Identified(by(stakeholderA Unavailable%results%from%phase%1,%no%transfer%to%phase%2 Healthcare%manager,%Healthcare%professional%2

B Really%complex%technologyHealthcare%manager,%Healthcare%professional%1,%Healthcare%professional%2

C Results%from%students%are%not%always%good Healthcare%manager,%Healthcare%professional%1D Unclear%ownership Healthcare%manager,%Healthcare%professional%1%E It%takes%so%much%longer%than%originally%expected Healthcare%managerF Inconvenient%timing Healthcare%professional%2

Contributing(to(success

Contributing(to(failure

Stakeholder Phase&1 Phase&2 Phase&3 Phase&1 Phase&2 Phase&3

Healthcare&Manager 1,&2,&3 1,&2,&3 1,&3 C,&D A,&B,&C,&D,&E B,&E

Healthcare&professional&1 2 2 < B,&C,&D B,&C,&D B

Healthcare&professional&2 < 1,&2,&3 1 < A,&B,F <

Developer&1 < < 4 < < <

Developer&2 < < 5 < < <

Page 29: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  23  

with  the  complex  technology.  The  unclear  ownership  for  him  had  lead  to  miscommunication  and  

irritation.  He  concluded  the  process  with  the  effects  for  clients.  For  him  these  did  not  carry  enough  

weight  to  modify  his  perception  that  the  project  was  a  failure;  “  It  has  not  delivered  anything,  it  just  

cost  much  time  and  energy.”  

The  other  healthcare  professional  started  the  construction  of  his  perception  at  the  moment  

when  phase  two  realized  that  phase  one  had  left  nothing;  “I  see  us  in  the  room  where  the  products  

should  have  been  and  there  was  nothing.  No  hardware,  no  assessments,  no  shows.  Nothing.  We  

were  stunned.”  He  considered  various  events  where  the  team  struggled  with  the  complex  

technology.  He  then  remembered  a  number  of  events  that  illustrated  inconvenient  timing.    He  

concluded  that  the  project  was  essentially  doomed  to  fail.  Next,  he  revisited  his  active  personal  

involvement  through  a  number  of  carefully  chosen  interventions.  The  effect  was  that  the  project  

team  rediscovered  their  motivation  and  delivered  what  was  feasible  given  the  circumstances.  He  was  

pleased  with  the  results  that  were  achieved  with  the  clients.  He  then  considered  the  project  as  a  

whole  and  described  enthusiasm  and  joy  in  working  in  this  interesting  project.  He  constructed  his  

perception  by  deliberately  weighing  all  his  key  events  and  concluded  that  the  project  was  partially  

successful.  

The  developers  constructed  their  perception  by  reconsidering  the  event  that  led  to  a  good  team  

and  the  event  where  the  principal  set  out  clear  directions.  These  key  events  allow  them  to  work  

effectively  and  pleasurable  and  facilitate  the  delivery  of  agreed  results.    

Concluding,  stakeholders  in  this  case  constructed  their  perceptions  of  success,  partial  success  

and  failure  through  different  key  events.  The  healthcare  manager  and  one  of  the  healthcare  

professionals  both  perceived  partial  success.  For  them  the  content  of  the  project  and  the  observed  

effects  with  clients  were  powerful  key  events  contributing  to  success.  These  outweighed  the  many  

key  events  that  contributed  to  failure.  For  the  other  healthcare  professional,  all  moments  where  the  

project  did  not  deliver  what  was  promised  outweighed  by  far  the  results  for  clients.  He  perceived  the  

project  as  a  failure.  The  developers  only  partially  constructed  their  perception  of  success  through  key  

events,  because  for  them  a  technically  sound  product  ultimately  determines  success.    

 

4.4  Case  4  –  Mobile  treatment  support  

Context    

The  fourth  case  is  part  of  a  research  project  on  the  support  of  treatment  of  eating  disorders  with  

information  technology.  Overweight  is  becoming  a  societal  problem  and  associated  with  a  higher  

medical  risk  profile  and  lower  overall  health.  This  project  focused  on  patients  with  a  combination  of  

mental  illnesses  and  eating  disorders.    The  treatment  consists  of  behavioral  therapy,  which  leads  to  

different  and  better  nourishment  and  more  exercise.  Involved  in  this  case  were  the  researcher  and  a  

Page 30: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  24  

healthcare  organization  in  mental  hygiene.  The  project  was  executed  by  a  multi  disciplinary  group  of  

students  and  a  healthcare  teacher.    

 

Content    

The  aim  of  this  project  was  to  develop  a  tool  to  support  the  cognitive  behavioral  treatment  of  

people  with  eating  disorders.  It  would  be  a  website  or  mobile  application,  that  would  not  replace  the  

contact  between  patient  and  therapist,  but  support  the  treatment  process  when  the  patient  is  not  in  

contact  with  his  therapist  or  coach.  The  tool  would  support  the  process  of  gaining  insight  in  triggers  

that  induce  dysfunctional  eating.  The  tool  should  be  available  whenever  patients  are  engaged  in  their  

treatment.  The  healthcare  manager  and  the  healthcare  professional  described  success  as  a  high  

quality  functional  design.  The  developers  described  project  success  as  having  delivered  a  fine  

product,  a  satisfied  principal  and  a  pleasant  working  experience.  

 

Process    

The  project  duration  was  five  months.  An  application  was  designed  that  guides  patients  through  

the  cognitive  behavioral  therapy  process,  similar  to  a  therapy  session.  The  team  designed  a  food  

diary  that  assists  in  maintaining  descriptive  log.  The  project  delivered  a  high  quality  functional  design  

and  also  delivered  a  partially  working  prototype.  Both  products  were  received  enthusiastically  and  

consecutive  phases  to  develop  the  application  and  test  it  with  patients  are  foreseen.    

 

Within-­‐case  analysis    

Stakeholders  identified  four  key  events  contributing  to  success  and  no  key  events  contributing  to  

failure.    

 

 

 

 

 

 

 

Page 31: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  25  

 

 Figure  6  –  Overview  of  key  events  Case  4  

 

In  this  case  the  stakeholders  constructed  their  perception  of  success  in  a  surprisingly  similar  

manner.  As  soon  as  stakeholders  started  talking  about  the  project,  broad  smiles  and  infectious  

enthusiasm  appeared.  They  described  frequent  interactions  between  the  stakeholders  where  the  

research  was  aimed  towards  clearly  defined  results.  They  experienced  these  as  key  events  

contributing  to  success  because  during  these  interactions  curiosity  and  enthusiasm  was  enhanced  

and  learning  was  facilitated.  They  described  a  reciprocal  process  where  the  stakeholders  jointly  

constructed  a  spiral  upwards  leading  to  perception  of  success.  The  healthcare  manager  explained:  “It  

is  great  to  see  that  a  project  becomes  self  propelling.  That  boosts  my  energy  and  makes  me  want  to  

add  even  more.”  The  developers  also  emphasized  how  working  in  a  good  team  is  experienced  as  a  

key  event,  as  one  developer  put  it;  “  In  a  good  team  energy  is  put  into  moving  one  another  in  the  

right  direction  and  then  I  work  really  hard  to  give  my  best.”    

Concluding,  the  stakeholders  in  this  case  constructed  their  perception  of  success  by  recounting  a  

process  of  frequent  interactions,  where  each  meeting  became  an  accelerator  for  the  project  

outcomes  and  facilitated  the  emergence  of  a  great  team.  All  perceived  the  project  as  successful.    

 

 

 

 

 

   

Identified(by(stakeholder

1 Clear&aim&in&research,&widen&perspectives&and&focus&on&resultsHealthcare&manager,&Healthcare&professional,&Developer&1,&Developer&2

2 Seed&curiosity,&harvest&enthusiasm&and&learning&Healthcare&manager,Healthcare&professional,&Developer&1,&Developer&2

3 Development&of&the&additional&prototype& Healthcare&professional

4 A&good&team,&similar&working&attitude,&one&project&roomHealthcare&professional,&Developer&1,&Developer&2

Contributing(to(success

Key$events$contributing$to$success Key$events$contributing$to$failureStakeholder Phase&1 Phase&1

Healthcare&Manager 1,&2 2

Healthcare&professional 1,&2,&3,&4 2

Developer&1 1,&2,&4 2

Developer&2 1,&2,&4 2

Page 32: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  26  

5  –  Cross-­‐case  analysis  

 

During  the  cross-­‐case  analysis  13  key  events  emerged,  seven  of  which  contribute  to  success  and  

six  to  failure.  The  importance  of  the  events  was  evaluated  based  on  the  number  of  cases  in  which  the  

event  was  identified  and  the  number  of  stakeholders  that  identified  the  event.      

Of  the  key  events  contributing  to  success,  as  shown  in  figure  7,  four  were  identified  in  all  cases:  

enthusiasm,  working  prototype,  willingness  to  learn  and  good  team.  This  can  be  considered  

compelling  evidence  (Dubé  &  Paré,  2003;  Yin,  2009)  that  these  are  common  key  events  contributing  

to  success.  Three  events:  clear  direction,  building  trust  and  high  quality  output,  were  identified  in  just  

two  cases,  indicating  a  less  common  occurrence.  For  two  of  these,  an  opposite  was  identified  as  key  

event  contributing  to  failure:  clear  direction  versus  lack  of  direction  and  high  quality  output  versus  

low  quality  output.    

Of  the  key  events  contributing  to  failure,  as  shown  in  figure  8,  four  were  identified  in  three  

cases:  low  quality  output,  technology  issues,  lack  of  direction  and  time  is  slipping.  These  are  

considered  common  key  events  contributing  to  failure.  Two  events:  insufficient  communication  and  

limited  technological  literacy,  were  identified  in  less  than  three  cases  which  indicates  a  less  common  

occurrence.    

The  cross-­‐case  analysis  further  revealed  that  stakeholders  can  experience  key  events  once  and  

recurring.  Recurring  key  events  are  experienced  in  two  ways.  Some  events  have  a  clear  first  

occurrence  and  then  continue  to  occur.  Stakeholders  indicate  that  the  importance  of  such  a  recurring  

event  does  not  change  over  time,  each  occurrence  is  as  important  as  the  first.  Examples  of  these  

events  are  working  prototype  and  good  team.  Other  events  only  become  a  key  event  if  they  recur.  

Each  occurrence  adds  to  the  importance  and  after  a  number  of  occurrences  they  are  identified  as  key  

event.  Examples  of  these  events  are  enthusiasm,  willingness  to  learn,  technology  issues,  low  quality  

output  and  lack  of  direction.  

 

Page 33: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  27  

 

Figure  7  –  key  events  contributing  to  success  

 

 

Figure  8  –  key  events  contributing  to  failure  

 

Stakeholders  experience  different  key  events  and  they  experience  key  events  in  different  ways.  

Enthusiasm  is  mostly  experienced  by  healthcare  managers  and  healthcare  professionals.  

Stakeholders  explain  that  it  creates  positive  energy  and  that  it  is  contagious.  They  experience  

enthusiasm  as  a  recurring  key  event  and  describe  it  as  the  source  of  the  energy  that  is  needed  to  

change  established  ways  of  working.  A  healthcare  professional  voiced  this  as:  “The  developer  and  I  

were  really  working  alongside  and  I  enjoyed  this  very  much.  This  helped  to  stay  motivated  and  

focused  during  all  the  issues  that  we  faced.”  

Identified(by(stakeholder( Typical(example(how(often) (from&case)Healthcare)manager)(5)times) Enthusiasm*of*the*developers*(Case*1) RecurringHealthcare)professional)(4)times) The*finish*is*within*reach*(Case*1) OnceDeveloper)(2)times) Active,*positive,*personal*involvement*(Case*2,*Case*3) Recurring

It*is*an*interesting*project*and*a*lot*of*fun*(Case*3)* RecurringSeed*curiosity,*harvest*enthusiasm*and*learning*(Case*4)* Recurring)

Healthcare)manager)(3)times) The*excellent*quality*of*the*working*prototype*(Case*1) RecurringHealthcare)professional)(5)times) The*high*quality*demo*case*to*demonstrate*the*idea*(Case*2) RecurringDeveloper)(1)time) The*observed*good*effects*with*clients*(Case*3) Recurring

Development*of*the*additional*prototype*(Case*4) Recurring)Healthcare)manager)(2)times) Willingness*of*the*developers*to*learn*about*the*care*processes*(Case*1) RecurringHealthcare)professional)(3)times) An*exiting*journey*of*discovery*and*learning*(Case*2) RecurringDeveloper)(2)times) It*is*an*interesting*project*and*simply*a*lot*of*fun(Case*3) Recurring

Seed*curiosity,*harvest*enthusiasm*&*learning*(Case*4) RecurringHealthcare)professional)(1)time) A*good*team*(Case*1,*Case*2,*Case*3) RecurringDeveloper)(6)times) A*good*team,*similar*working*attitude,*work*in*one*room*(Case*4) RecurringHealthcare)manager)(1)time) Clear*directions*from*principal*(Case*3) RecurringHealthcare)professional)(1)time) Aim*research,*widen*perspective*and*focus*on*results*(Case*4) RecurringDeveloper)(4)times)Healthcare)manager)(3)times) Excursion*to*supplier*with*clients*(Case*2) OnceHealthcare)professional)(1)times) Active,*positive,*personal*involvement*of*management*(Case*2,*Case*3) RecurringDeveloper)(1)time))Healthcare)manager)(1)time) The*high*quality*of*the*implementation*advice*(Case*1) Once)Healthcare)professional)(1)time)High)quality)output 1,)2

Building)trust 2,)3

Key(events(contributing(to(success

Good)team 1,)2,)3,)4

Willingness)to)learn 1,)2,)3,)4

Clear)direction 3,)4

Found(((((in(case Occurs

Enthusiasm 1,)2,)3,)4

Working)prototype 1,)2,)3,)4

Common)key)events)

Identified(by(stakeholder Typical(Example(how(often) (from&case)Healthcare)manager)(4)times) Disappointment+because+of+unfinished+product+(Case+1)+ Once)Healthcare)professional)(3)times) Not+being+able+to+deliver+to+developer’s+standards+(Case+1) OnceDeveloper)(1)time) Suppliers+do+not+deal+well+with+our+clients+(Case+2) Recurring

Supplier+backing+out+(Case+2)+ OnceThe+results+from+students+are+not+always+good+(Case+3) Recurring

Healthcare)manager)(1)times) The+prototype+does+not+work+as+expected+with+clients+(Case+1)+ RecurringHealthcare)professional)(2)times) Many,+many+issues+with+technology+(Case+2) RecurringDeveloper)(1)time) Really+complex+technology++(Case+3) Recurring

Healthcare)manager)(2)times) The+project+organization+was+unclear+(Case+1) RecurringHealthcare)professional)(3)times) Not+one+person+in+charge+(Case+2) RecurringDeveloper)(1)time) Unclear+ownership+(Case+3)+ Recurring)

Inconvenient+timing+(Case+3) RecurringHealthcare)manager)(2)times) More+time+is+needed+(Case+1) OnceHealthcare)professional)(1)time) Not+enough+time+to+make+it+work+(Case+2) Once

It+takes+so+much+longer+than+originally+expected+(Case+3) Recurring)Healthcare)manager)(2)times) No+communication+and+unclear+why+communication+stopped+(Case+1)+ RecurringHealthcare)professional)(2)times) Unavailable+results+from+phase+1,+no+transfer+to+phase+2+(Case+3)+ Once

Developer)(1)time) No+requirements+specification+by+users+(Case+2) RecurringLimited)technological)literacy)

Lack)of)direction 1,)2,)3

Time)is)slipping 1,)2,)3

Insufficient)communication 1,)3

1

Occurs

Low)quality)output 1,)2,)3

Technology))issues

Key(events(contributing(to(failure

Found(in(case*

1,)2,)3

*)In)Case)4)no)key)events)contributing)to)failure)were)identified.)

Limited)technological)literacy)

Common)key)events)

Page 34: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  28  

A  working  prototype  is  mainly  experienced  by  healthcare  managers  and  healthcare  

professionals.  Stakeholders  evaluate  this  as  a  key  event  because  by  working  with  a  prototype  they  

start  to  see  what  the  HIS  will  mean  for  them  and  how  it  will  add  value.  They  experience  this  as  a  

recurring  event  because  they  continue  to  learn  when  using  a  prototype  and  this  contributes  to  self  

confidence.  One  healthcare  professional  said:  “  A  working  prototype  makes  you  understand  how  it  

works.  When  you  keep  working  with  it  you  master  the  technology  and  then  you  really  start  to  

understand  what  it  means.”  

Willingness  to  learn  is  a  key  event  for  all  stakeholders  and  has  two  aspects.  One  is  the  individual  

willingness  to  learn  and  it  reflects  the  joy  stakeholders  experience  in  learning  new  things.  The  other  

aspect  is  important  for  healthcare  professionals  and  occurs  when  developers  show  that  they  are  

willing  to  invest  time  to  understand  the  care  processes.  Healthcare  professionals  feel  heard  and  

believe  that  their  knowledge  will  become  embedded  in  the  HIS,  as  one  of  them  said;  “  The  

developers  were  so  inspiring  and  enthusiastic.  They  wanted  to  understand  our  practice  and  that  

helped  me  believe  in  the  project.”  Willingness  to  learn  is  described  as  recurring  key  event.    

A  good  team  is  an  important  key  event  for  developers.  All  developers  can  exactly  pinpoint  the  

moment  they  realize  that  they  are  working  in  a  good  team.  Developers  describe  enthusiasm  as  the  

result  of  this  event  and  say  that  it  augments  the  energy  that  they  are  willing  to  put  into  the  project.  

The  effect  is  similar  to  enthusiasm  for  healthcare  managers  and  healthcare  professionals,  but  for  

developers  a  good  team  is  a  precondition  to  enthusiasm.  It  is  a  recurring  event,  because  a  good  team  

keeps  stimulating  developers  during  the  whole  process,  as  one  developer  said;    “I  felt  this  most  when  

we  were  really  discussing  things,  trying  to  figure  things  out.  I  am  content  when  everybody  does  what  

he  is  supposed  to  do,  then  you  can  stimulate  each  other.”    

Low  quality  output  is  the  key  event  where  products  are  not  delivered  as  promised  or  not  with  

the  expected  quality  and  was  mostly  experienced  by  healthcare  managers  and  healthcare  

professionals.  It  results  in  annoyance  and  recurrence  amplifies  the  emotions  of  the  stakeholders  to  

the  point  of  irritation  or  anger.  As  one  healthcare  manager  said:  “  The  technicians  did  not  believe  us,  

they  blamed  our  clients.  That  made  me  so  angry.”  The  opposite  event,  high  quality  output,  was  

experienced  in  one  case  by  the  healthcare  manager  and  healthcare  professional  and  increased  their  

believe  in  project  outcomes.  

Technology  issues  was  described  as  a  key  event,  mostly  by  healthcare  managers  and  healthcare  

professionals,  as  a  healthcare  manager  voiced;  “The  technology  which  time  and  again  did  not  work:  

frustrating!”  Some  issues  occurred  because  the  chosen  technology  was  not  mature  or  reliable  

enough,  other  issues  occurred  because  the  interaction  between  components  of  the  system  were  

more  difficult  than  foreseen.  Some  issues  occurred  because  of  the  interaction  between  the  clients  

and  the  technology.  This,  healthcare  stakeholders  thought,  might  be  explained  by  the  fact  their  

Page 35: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  29  

clients  are  not  the  standard  users  for  which  the  technology  is  developed.  In  three  cases  technology  

issues  resulted  in  a  non-­‐working  HIS.    

Lack  of  direction  was  described  as  a  key  event,  mostly  by  healthcare  managers  and  healthcare  

professionals.  It  was  experienced  when  progress  was  not  according  to  plan  and  when  it  was  not  clear  

who  had  the  ability  to  take  decisions  regarding  progress.  The  effects  are  described  as  feeling  doubt  

and  loss  of  interest.  The  opposite  event,  clear  direction,  was  strongly  experienced  in  the  case  that  all  

stakeholders  perceived  as  successful.  Stakeholders  described  the  effect  as  feeling  purpose  and  being  

able  to  direct  their  energy  towards  a  better  product.  A  developer  phrased  it  as:  “If  you  know  where  

you  go,  you  don’t  have  to  spend  time  to  figuring  that  out.  You  can  put  all  your  energy  in  what  needs  

to  be  done.”    

Time  is  slipping  was  experienced  by  healthcare  managers  and  healthcare  professionals  when  

they  realized  that  the  original  planning  was  no  longer  feasible.  A  healthcare  manager  explained:  “It  

takes  much  longer.  I  had  to  adjust  my  expectations  quite  a  bit  and  it  will  still  take  some  time  before  

the  system  is  ready.”  This  event  is  related  to  technology  issues,  and  occurs  when  the  technology  

cannot  be  made  to  work  reliably  within  the  planned  timeframe.  As  a  result,  expectations  were  

lowered  and  expectation  adjustment  activities  were  initiated  in  the  healthcare  organization.  

Stakeholders  described  feeling  tension  and  disappointment.  

 

The  cross-­‐case  analysis  revealed  that  to  construct  their  perceptions  of  success  or  failure  

stakeholders  mentally  revisit  the  key  events  that  they  identified,  as  if  replaying  a  movie,  and  that  

they  use  two  different  approaches  to  construct  their  perceptions  of  success  or  failure.  In  the  first  

approach,  stakeholders  follow  the  timeline  of  the  project  and  evaluate  key  events  as  they  occurred  in  

time.  This  approach  was  found  with  developers  and  in  the  case  that  all  stakeholders  perceived  as  

successful.  For  the  second  approach,  stakeholders  revisit  key  events  per  type.  They  start  with  the  key  

events  that  lead  to  failure,  and  continue  with  the  key  events  that  lead  to  success  or  vice  versa.  

Stakeholders  then  form  their  conclusion  by  carefully  taking  stock  of  both  experiences.  Healthcare  

managers  and  healthcare  professionals  mostly  used  the  this  approach.    

 

Finally,  the  cross-­‐case  analysis  revealed  that  various  practices  known  to  contribute  to  success  

were  applied  in  the  projects.  For  example,  they  tried  to  intertwine  healthcare-­‐specific,  functional  

expertise  with  technical  expertise  (Cheng  &  Atlee,  2007;  Saleem  et  al.,  2006)  and  they  used  

prototypes  to  make  the  technology  work  in  the  daily  care  processes  (Markus  &  Robey,  1988;  Hannola  

&  Ovaska,  2011).  In  the  case  of  Mobile  Treatment  Support  these  practices  seem  to  have  delivered  

what  theory  predicts.    

Page 36: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  30  

In  the  other  three  cases  a  number  of  known  causes  for  failure  were  observed.  The  technology  

was  judged  ready,  but  turned  out  to  be  an  amalgam  of  fragile  and  fragmentary  components  that  had  

a  tendency  to  break  down  or  fail  unexpectedly  (Orlikoswki  &  Lacono,  2010).  The  interaction  between  

technology  and  clients  resulted  in  unexpected  setbacks  indicating  a  too  techno-­‐centric  approach  and  

insufficient  understanding  of  human  and  social  aspects  involved  (Heeks,  2006;  Rinkus  et  al,  2005;  

Samaras  &  Horst,  2005;  Zhang,  2005).  During  the  projects,  stakeholders  realized  that  major  changes  

in  the  organization  were  required  (McAfee,  2006)  which  were  underestimated  and  took  much  longer  

than  originally  anticipated.  This  leads  to  the  observation  that  on  the  one  hand  known  mistakes  are  

still  made  in  practice  and  on  the  other  hand  that  the  relation  between  success  practices  and  actual  

project  success  remains  a  complex  one.        

Page 37: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  31  

6.  Discussion  

 

This  section  discusses  the  underlying  assumption  of  this  paper  that  key  events  are  a  useful  

mechanism  to  understand  how  individual  stakeholders  shape  their  perceptions  of  success.  It  

discusses  the  common  key  events  in  the  HIS-­‐development  processes  that  were  found  during  the  

within-­‐case  and  cross-­‐case  analysis  and  addresses  the  research  question:  how  do  stakeholders  in  HIS-­‐

development  processes  construct  their  perceptions  of  success  and  failure  through  key  events?  

 

6.1  Understanding  construction  of  perceptions  through  key  events  

Stakeholders  identify  key  events  by  searching  for  the  emotions  that  are  triggered  by  these  

events.  Stakeholders  remember  exactly  how  they  felt  during  a  specific  event  and  how  their  feelings  

influenced  their  thoughts  and  actions.  They  consider  each  of  these  events  relevant  in  relation  to  

success  or  failure  and  attach  more  value  to  events  with  higher  emotional  intensity.  These  findings  

support  what  was  inferred  in  the  theoretical  background  section  of  this  paper  (Bagozzi  et  al.,  1999;  

Isabella,  1990;  Beaudry  &  Pinsonneault,  2010;  Stam  &  Stanton,  2010;  Stein,  2010).    

Stakeholders  associate  emotions  such  as  joy,  enthusiasm,  motivation,  and  being  acknowledged,  

with  success  and  emotions  such  as  irritation,  frustration,  tension,  disappointment,  doubt  and  anger,  

with  failure.  Stakeholders  perceive  that  success  is  facilitated  by  emotions  that  are  associated  with  

success  and  hindered  by  emotions  that  are  associated  with  failure.  This  relation  was  theorized  before  

by  various  authors  (Bagozzi  et  al.,  1992;  Stam  &  Stanton,  2010).    

Stakeholders  construct  their  perception  by  replaying  key  events  before  their  mind’s  eye  and  

they  re-­‐experience  the  emotions  that  the  key  events  triggered.  During  the  interviews  the  emotions  

were  observed  in  facial  expressions,  tone  and  volume  of  voice  and  expressed  in  the  choice  of  words.    

In  the  case  were  the  project  delivered  according  to  plan,  the  mental  reconstruction  of  key  events  was  

very  similar  for  all  stakeholders  as  were  the  emotions  that  they  experienced  with  each  of  these  

events  and  the  resulting  perception.  In  the  cases  where  the  projects  did  not  deliver  according  to  

plan,  each  stakeholder  reconstructed  his  own  mental  picture.  Each  event  triggered  different  

emotions  with  different  stakeholders  and  each  stakeholder  constructed  his  own  perception  of  

success  or  failure  by  taking  stock  of  his  emotions.      

 

6.2  Common  key  events  and  their  role  in  HIS-­‐development  processes  

From  the  cross-­‐case  analysis,  eight  common  key  events  emerged.    Four  common  key  events  

contribute  to  perceptions  of  success:  enthusiasm,  working  prototype,  willingness  to  learn  and  good  

team.  The  first  three  are  mostly  experienced  by  users  in  HIS-­‐development  processes:  healthcare  

managers  and  healthcare  professionals.  The  last  is  experienced  mostly  by  developers.  Four  common  

Page 38: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  32  

key  events  emerged  that  contribute  to  failure  or  hinder  success:    low  quality  output,  technology  

issues,  lack  of  direction  and  time  is  slipping.  Key  events  that  contribute  to  failure  are  mostly  

experienced  by  users  in  HIS-­‐development  and  not  by  developers.  One  developer  voiced  a  possible  

explanation:  “I  made  sure  our  part  was  done  well,  but  there  were  more  interests  and  those  issues  

were  outside  my  influence  .”  

Enthusiasm  was  experienced  by  nearly  all  users  and  the  related  key  event  good  team  was  

experienced  by  nearly  all  developers.  Stakeholders  attach  great  importance  to  inspiring  and  pleasant  

interaction  between  team  members  and  a  shared  team  spirit.    Aronson,  Shenhar,  and  Patanakul  

(2013)  named  this  phenomenon  ‘project  spirit’  which  they  found  to  increase  project  success.    

The  occurrence  of    technology  issues  is  a  first  sign  that  project  success  is  at  risk  because  this  key  

event  only  surfaces  when  stakeholders  have  become  irritated  through  earlier  technology  events.  

When  technology  issues  occur,  stakeholders  are  at  the  verge  of  loosing  faith  in  the  project.  Low  

quality  output  and  lack  of  direction  tend  to  surface  alongside  or  shortly  after  and  are  further  

indicators  of  the  increasing  likelihood  that  the  project  will  be  perceived  as  a  failure.    

Key  events  do  not  have  the  power  to  make  a  project  successful.  Success  in  this  study  was  

defined  by  all  stakeholders  as  a  working  HIS.  But  when  no  working  HIS  is  delivered,  key  events  are  

capable  of  modifying  stakeholders  perception  from  failure  into  partially  successful.      

One  key  event  contributing  to  success  had  a  powerful  influence,  but  was  not  identified  as  such  

by  stakeholders.  In  three  cases  the  healthcare  managers  were  strongly  committed  to  the  idea  of  the  

HIS.  During  the  interviews  they  all  identified  the  exact  moment  that  they  committed  themselves.  This  

key  event,  which  I  named  the  idea  is  my  idea,  results  in  the  conviction  that  the  idea,  eventually,  will  

become  reality.    

 

6.3  How  stakeholders  in  HIS-­‐development  processes  construct  their  perceptions  of  success  or  

failure  during  through  key  events  

Stakeholders  construct  their  perceptions  of  success  or  failure  through  mental  reconstruction  of  

key  events,  they  re-­‐experience  the  associated  emotions  and  carefully  take  stock  of  these  

experiences.  Two  approaches  were  found  for  this  process:  a  timeline  approach  and  a  type-­‐by-­‐type  

approach.  In  the  timeline  approach  stakeholders  reconstruct  and  re-­‐experience  following  the  project  

timeline.  This  approach  was  used  by  developers  and  in  the  successful  case.  In  the  type-­‐by-­‐type-­‐

approach,  stakeholders  start  to  reconstruct  and  re-­‐experience  the  key  events  contributing  to  failure  

and  then  the  key  events  contributing  to  success  or  vice  versa.  This  approach  is  mostly  used  by  the  

users  is  this  study:  healthcare  managers  and  healthcare  professionals.  Developers  add  an  extra  step  

to  construct  their  perception  of  success.  Once  they  have  evaluated  the  key  events,  they  consider  the  

quality  of  their  results  and  then  construct  their  final  perception  of  success  or  failure.  This  allows  

Page 39: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  33  

them  to  construct  a  perception  of  success  in  relation  to  their  own  contribution  when  overall  project  

success  is  not  attainable.    

 

6.4  Implications  for  theory  

This  paper  contributes  to  theory  of  project  management  and  (H)IS-­‐development  two  ways:  It  

increases  our  understanding  of  how  stakeholders  determine  the  degree  of  project  success  and  it  

increases  our  understanding  of  stakeholder  perceptions  in  (H)IS  development  processes.    

This  study  confirms  that  success  is  a  perception  of  stakeholders  (Collins  &  Baccarini,  2004;  

Jugdev  &  Müller,  2005;  Procarino  &  Verner,  2008;  Shenhar  et  al.,  2001)  as  different  stakeholders  

were  found  to  form  different  conclusions  of  the  same  project.  Previously,  failure  has  been  defined  as  

the  absence  of  success  (Agarwal  &  Rathod,  2006;  Shenhar  et  al.,  2001;  Wateridge,  1995),  but  I  found  

that  the  absence  of  success  is  not  necessarily  evaluated  as  failure,  but  rather  as  partial  success  or  

partial  failure.  User  satisfaction  has  been  most  commonly  used  to  measure  stakeholder  perception  of  

success,  usually  at  the  end  of  the  project  (Collins  &  Baccarini,  2004;  Jugdev  &  Müller,  2005;  Procarino  

&  Verner,  2008;  Shenhar  et  al.,  2001).  Through  this  study  we  understand  that  perceptions  of  success  

are  constructed  during    projects  and  that  key  events  influence  this  process.  This  study  furthermore  

showed  that  a  shared  definition  of  success  by  itself  does  not  facilitate  perceptions  of  success  

(Hartman  &  Ashrafi,  2002;  Thomas  &  Fernandez,  2008;  Wateridge,  1995),  but  that  shared  events  

through  which  a  shared  definition  evolves  contribute  to  joint  perceptions  of  success.      

Contribution  to  theory  on  (H)IS  development  was  found  in  our  increased  understanding  of  how  

participative  methods  and  working  prototypes  contribute  to  perceptions  of  success  (Eley  et  al.,  2008;  

Shenhar  et  al.,  2001;  Subramanyam  et  al.,  2010  ).  They  stimulate  the  occurrence  of  enthusiasm  and  

willingness  to  learn,  which  are  both  key  events  contributing  to  success  and  increase  the  users’  

capability  to  articulate  requirements  (Pitts  &  Browne,  2007),  which  is  important  in  achieving  

successful  HIS  (Hannola  &  Ovaska,  2011).      

Towards  developers,  this  study  increases  our  understanding  of  how  success  the  factors  teamwork  

and  delivering  the  product  as  intended  influence  the  way  developers  determine  the  degree  of  

success  (Agarwal  &  Rathod,  2006;  Linberg,  1999;  Pereira  et  al.,  2008;  Procaccino  &  Verner,  2009).  

Teamwork  positively  influences  perceptions  of  success  through  the  key  event  good  team  and  

delivering  a  product  as  intended  was  found  to  be  the  ultimate  success  criterion  for  developers.    

Various  authors  claim  that  success  is  difficult  to  define  (Jugdev  &  Müller,  2005;  Kaplan  &  Harris-­‐

Salamone,  2009;  Tomas  &  Fernandez,  2008;  Wateridge,  1995).  This  I  found  not  to  be  the  case:  It  is  

achieving  success  that  is  difficult.    

Concluding,  this  study  sheds  light  on  the  stakeholder  view  in  HIS-­‐development  as  has  been  

requested  by  Heeks  (2006)  and  Kaplan  and  Harris-­‐Salamone  (2009)  and  it  contributes  to  the  answer  

Page 40: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  34  

of  the  question  that  was  the  starting  point  of  this  paper:  To  understand  project  success  as  it  is  

subjectively  perceived  by  stakeholders  (Ika,  2009).    

 

6.5  Implications  for  practice  

The  first  contribution  of  this  study  to  practice  is  the  demonstration  that  much  of  the  knowledge  

from  theory  on  practices  that  contribute  to  success  is  applied  in  the  cases  under  study.  The  

application  of  these  methods  does,  however,  not  prevent  the  occurrence  of  known  causes  for  failure,  

such  as  underestimating  the  complexity  of  the  technology  (Orlikowski  &  Lacono,  2001)  and  not  

paying  enough  attention  to  human  and  social  aspects  in  HIS-­‐development  (Heeks,  2006;  Rinkus  et  al.,  

2005;  Samaras  &  Horst,  2005;  Teixeira  et  al.,  2012Zhang,  2005).  Where  these  authors  state  that  the  

approaches  to  these  projects  are  too  techno-­‐centric,  I  found  that  there  was  underestimation  of  

complexity  and  readiness  of  technology.  Looking  at  these  projects  as  innovation  processes,  were  the  

technology  is  new  to  the  organization  (Garcia  &  Cantalone,  2002)  may  shed  a  different  light  on  the  

causes  for  failure.  This  type  of  innovation  requires  time  for  adaption  and  learning.  Furthermore  

healthcare  organizations  are  renowned  for  their  emphasis  on  reliability  and  accountability,  are  

perfect  candidates  for  structural  inertia  and  therefore  reluctant  innovators  (Hannan  &  Freeman,  

1984).  Practitioners  should  therefore  design  projects  that  allow  for  learning.  Projects  should  start  

with  the  lowest  conceivable  complexity  and  increase  complexity  in  small  steps.  This  allows  the  

technology  to  ripen,  facilitates  learning  in  the  organization  and  results  in  adaptation  to  the  social  and  

human  processes  in  healthcare.  

The  second  contribution  to  practice  is  that  key  events  can  be  used  as  a  means  to  assess  the  

likelihood  for  project  success  and  to  conceive  interventions  to  increase  the  likelihood.  This  approach  

is  supported  by  Newman  and  Robey  (1992)  and  Stam  and  Stanton  (2010),  who  propose  that  

emotionally  significant  key  events  are  a  means  to  diagnose  problems  and  that  practitioners  can  

design  events  to  move  projects  in  a  different  direction.  Practitioners  should  monitor  for  key  events  

contributing  to  failure  to  surface,  because  they  are  indicators  that  the  project  is  at  risk  of  becoming  a  

failure.  In  case  of  the  appearance  of  technology  issues,  lack  of  direction  and  low  quality  output,  a  

technology  focused  intervention  should  be  considered  to  remove  the  technological  causes  for  these  

key  events.  Practitioners  also  should  look  for  enthusiasm  and  good  team  at  project  startup.  When  

these  fail  to  appear,  team  building  efforts  or  team  reconstruction  should  be  considered.  The  energy  

that  these  events  create  is  a  prerequisite  to  project  success.    

   

6.6  Limitations    

The  most  obvious  limitation  of  this  study  is  the  HIS-­‐development  context  and  as  a  consequence  

the  question  of  generalizability  of  the  findings.  According  to  Lee  and  Baskerville  (2003)  

Page 41: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  35  

generalizability  of  the  resulting  theory  beyond  domain  where  the  study  took  place  can  only  be  

proven  by  empirical  testing  in  that  specific  setting  (Lee  &  Baskerville,  2003).    It  seems  however  likely  

that  results  will  hold  in  IS-­‐development  because  most  of  the  theoretical  background  was  retrieved  

there.  Similarly  the  results  are  likely  to  hold  in  project  management,  because  this  study  builds  on  

earlier  studies  on  success  and  stakeholder  perceptions  that  originate  there.  Generalizability  to  

healthcare  is  difficult  to  predict,  because  there  is  not  enough  literature  available  to  base  a  

reasonable  assumption  upon.    

I  recognize  limitations  of  this  research  in  the  fact  that  some  of  the  projects  were  finished  in  the  

past  so  that  interviewees  had  to  reconstruct  and  may  have  suffered  from  memory  recall  bias.    

The  projects  were  of  relatively  small  scale,  which  is  not  unusual  for  innovation  projects.  As  a  

consequence  it  was  not  always  possible  to  interview  more  individuals  in  the  same  stakeholder  role,  

which  may  have  led  to  overemphasis  of  individual  opinions.    

Finally,  the  study  did  not  include  cases  that  delivered  a  working  HIS.  As  a  consequence,  I  might  

have  missed  common  key  events  that  occur  such  projects.    

 

6.7  Further  research  

For  further  research  I  propose  to  continue  this  research  with  additional  projects  in  the  same  

context  to  examine  projects  along  their  full  lifecycle  and  to  include  projects  that  delivered  a  working  

HIS  to  complete  the  overview  of  common  key  events.  Another  area  for  further  research  is  the  extent  

to  which  perceptions  of  success  may  be  influenced,  for  example  through  the  effect  of  interventions  

that  create  or  prevent  the  occurrence  of  key  events.  Finally,  I  would  like  to  examine  the  effect  of  this  

research  as  an  intervention  in  the  tradition  of  action  research,  because  during  this  research  I  

experienced  that  as  a  possibility.  I  did  not  however  pursue  this,  because  it  was  outside  the  scope  of  

this  paper.  An  interesting  approach  for  action  research  would  be  to  attach  the  role  of  translator  

(Heeks,  2006)  to  the  researcher.    

 

   

   

Page 42: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  36  

7.  Conclusion    

This  paper  set  out  to  answer  the  question  how  stakeholders  construct  their  perception  of  

success  and  failure  during  HIS-­‐development  processes  through  key  events.  This  study  shows  that  key  

events  are  indeed  a  useful  mechanism  to  understand  the  stakeholder  perspective.  Key  events  trigger  

emotions  that  influence  the  way  stakeholders  perceive  these  events.  Stakeholders,  in  this  study  

users  and  developers,  experience  different  key  events  and  construct  perceptions  in  different  ways.  

Users  shape  their  perception  of  success  or  failure  based  on  key  events.  Developers  consider  key  

events,  but  ultimately  construct  their  perception  of  success  based  on  the  quality  of  the  products  that  

they  delivered.    

Key  events  have  the  ability  to  change  stakeholder  perception  of  failure  into  partially  successful.  

The  absence  of  key  events  contributing  to  success  indicates  that  important  prerequisites  for  success  

are  missing.  The  appearance  of  key  events  contributing  to  failure  indicates  that  the  project  is  at  risk  

of  not  delivering  what  is  intended  and  being  perceived  as  a  failure.  The  observation  of  key  events  

that  contribute  to  success  without  any  key  events  contributing  to  failure,  indicate  a  project  that  has  a  

fair  chance  of  being  perceived  successful  and  delivering  what  was  intended.  

                                           Acknowledgements  

Herewith,  I  thank  the  project  members  of  the  cases  involved  in  this  study  for  sharing  their  

experiences,  as  those  are  the  foundation  of  this  study.  I  gratefully  acknowledge  the  constructive  

comments  of  Prof.  Dr.  A.  Boonstra,  Dr.  C.  Reezigt  and  Dr.  H.  Velthuijsen  and  thank  A.  Dol  for  helpful  

suggestions.    

Page 43: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  37  

References    

Agarwal,  N.,  &  Rathod,  U.  (2006).  Defining  success  for  software  projects.  International  Journal  of  

Project  Management,  24,  358–370.  

Ammenwerth,  E.,  Iller,  C.,  &  Mahler,  C.  (2006).  T-­‐adoption  and  the  interaction  of  task,  technology  

and  individuals:  a  fit  framework  and  a  case  study.  BMC  Medical  Informatics  and  Decision  Making,

6  (3).  

Aronson,  Z.  H.,  Shenhar,  A.  J.,  &  Patanakul,  P.  (2013).  Managing  the  intangible  aspects  of  a  project:  

The  affect  of  vision,  artifacts,  and  leader  values  on  project  spirit  and  success  in  technology-­‐driven  

projects.  Project  Management  Journal,  44  (1),  35-­‐58.    

Baccarini,  D.  (1999).  The  logical  framework  method  for  defining  project  success.  Project  

Management  Journal,  30  (4),  25-­‐32.  

Bagozzi,  R.  P.  (1992).  The  self-­‐regulation  of  attitudes,  intentions,  and  behavior.  Social  Psychology  

Quarterly,  55  (2),  178-­‐204.  

Ballejos,  L.,  &  Montagna,  J.  (2011).  Modeling  stakeholders  for  information  systems  design  processes.  

Requirements  Engineering,  16,  281–296.  

Basten,  B.,  Joosten,  D.,  &  Mellis,  W.  (2011).  Managers’  perceptions  of  information  system  project  

success.  Journal  of  Computer  Information  Systems,  52  (2),  12-­‐21.  

Benbasat,  I.,  Goldstein,  D.  K.,  &  Mead,  M.  (1987).  The  case  research  strategy  in  studies  of  information  

systems.  MIS  Quarterly,  11  (3),  369-­‐386.  

Beaudry,  A.,  &  Pinsonneault,  A.  (2010).  The  other  side  of  acceptance:  Studying  the  direct  and  indirect  

effects  of  emotions  on  information  technology  use.  MIS  Quarterly,  34  (4),  689-­‐710.  

Cheng,  B.  H.,  &  Atlee,  J.  M.  (2007).  Research  directions  in  requirements  engineering.  In  2007  Future  

of  Software  Engineering  (pp.  285-­‐303).  IEEE  Computer  Society.  

Collins,  A.,  &  Baccarini,  D.  (2004).  Project  success?  A  survey.  Journal  of  Construction  Research,  5  (2),  

211-­‐231.  

Darke,  P.,  Shanks,  G.,  &  Broadbent,  M.  (1998).  Successfully  completing  case  study  research:  

combining  rigour,  relevance  and  pragmatism.  Information  Systems  Journal,  8  (4),  273-­‐289.  

Dewan,  N.  A.,  Lorenzi,  N.  M.,  &  Shaohong,  Z.  (2004).  Overcoming  resistance  to  new  technology.  

Behavioral  Health  Management,  24  (1),  28-­‐32.  

Dubé,  L.,  &  Paré,  G.  (2003).  Rigor  in  information  systems  positivist  case  research:  Current  practices,  

trends,  and  recommendations.  MIS  Quarterly,  27  (4),  597-­‐635.  

Eger,  M.S.,  Godkin,  R.  L.,  &  Valentine,  S.  R.  (2001).  Physicians’  adoption  of  information  technology:  A  

consumer  behavior  approach.  Health  Marketing  Quarterly,  19  (2),  3-­‐21  

Eisenhardt,  K.  M.  (1989).  Building  theories  from  case  study  research.  Academy  of  Management  

Page 44: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  38  

Review,  14,  532–550.  

Eley,  R.,  Fallon,  T.,  Soar,  J.,  Buikstra.  E.,  &  Hegney,  D.  (2008).  Barriers  to  use  of  information  and  

computer  technology  by  Australia’s  nurses:  a  national  survey.  Journal  of  Clinical  Nursing,  18,  

1151–1158.  

Fernandez,  D.J.,  &  Fernandez,  J.D.  (2008).  Agile  project  management  -­‐  agilism  versus  traditional  

approaches.  Journal  of  Computer  Information  Systems,  49  (2),  10-­‐17.  

Fowler,  A.,  &  Walsh,  M.  (1999).  Conflicting  perceptions  of  success  in  an  information  systems  project.  

International  Journal  of  Project  Management,  17  (1),  1-­‐10.  

Garcia,  R.  &  Cantalone,  R.  (2002).  A  critical  look  at  technological  innovation  typology  and  

innovativeness  terminology:  a  literature  review.  The  Journal  of  Product  Innovation  Management,  

19,  110-­‐132.  

Garde,  S.,  &  Knaup,  P.  (2006).  Requirements  engineering  in  healthcare:  The  example  of  

chemotherapy  planning  in  paediatric  oncology.  Requirements  Engineering,  11,  265–278.  

Governance  Institute.  (2009).    Leadership  in  healthcare  organizations.    A  guide  to  joint  commission  

leadership  standards.  Retrieved  from  www.governanceinstitute.com.    

Grant,  R.  W.,  Campbell,  E.  G.,  Gruen,  R.  L.,  Ferris,  T.  G.,  &  Blumenthal,  D.  (2006).  Prevalence  of  basic  

information  technology  used  by  U.S.  physicians.  Journal  of  General  Internal  Medicine,  21  (11),  

1150-­‐1155.  

Gray,  R.  J.  (1999).  Organisational  climate  and  project  success.  International  Journal  of  Project  

Management,  19,  103-­‐109.  

Hannan,  M.  T.,  &  Freeman,  J.  (1984).  Structural  inertia  and  organizational  change.  American  

Sociological  Review,  49  (2),  149-­‐164.  

Hannola,  L.,  &  Ovaska,  P.  (2011).  Challenging  front-­‐end-­‐of-­‐innovation  in  information  systems.  Journal  

of  Computer  Information  Systems,  52  (1),  66-­‐75.  

Hartman,  F.,  &  Ashrafi,  R.  A.  (2002).  Project  management  in  the  information  systems  and  information  

technologies  industries.  Project  Management  Journal,  33  (3),  5-­‐15.  

Harris,  M.A.,  &  Weistroffer,  H.R.  (2009).  New  look  at  the  relationship  between  user  involvement  in  

systems  development  and  system  success.  Communications  of  the  Association  for  Information  

Systems,  24,  739-­‐756.  

He,  J.,  &  King,  W.  R.(2008).  The  role  of  user  participation  in  information  systems  development:  

implications  from  a  meta-­‐analysis.  Journal  of  Management  Information  Systems,  25  (1),  301–331.  

Heeks,  R.  (2006).  Health  information  systems:  Failure,  success  and  improvisation.  International  

Journal  of  Medical  Informatics,  75  (2),  125-­‐137.  

Hevner,  A.  R.,  March,  S.  T.,  Park,  J.,  &  Ram,  S.  (2004).  Design  science  in  information  system  research.  

MIS  Quarterly,  28  (1),  75-­‐105.  

Page 45: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  39  

Hsu,  J.  S.,  Liang,  T.  P.,  Wu,  S.  J.,  Klein,  G.,  &  Jiang,  J.  J.  (2011). Promoting  the  integration  of  users  and  

developers  to  achieve  a  collective  mind  through  the  screening  of  information  system  projects.  

International  Journal  of  Project  Management,  29,  514–524.  

Huberman,  A.  M.,  &  Miles,  M.  B.  (1984).  Drawing  valid  meaning  from  qualitative  data:  Toward  a  

shared  craft.  Educational  Researcher,  13  (5),  20-­‐30.  

Ika,  L.  A.(2009).  Project  success  as  a  topic  in  project  management  journals.  Project  Management  

Journal,  40  (4),  6–19.  

Jiang,  J.  J.,  Klein,  G.,  Wu,  S.  J.,  &  Liang,  T.  P.  (2009).  The  relation  of  requirements  uncertainty  and  

stakeholder  perception  gaps  to  project  management  performance. Journal  of  Systems  and  

Software,  82,  801–808.  

Jugdev,  K.,  &  Müller,  R.  (2005).  A  retrospective  look  at  our  evolving  understanding  of  project  success.  

Project  Management  Journal,  36  (4),  19-­‐31.  

Kaplan,  B.,  &  Harris-­‐Salamone,  K.  (2009).  Health  IT  success  and  failure:  recommendations  from  

literature  and  an  AMIA  workshop.  Journal  of  the  American  Medical  Informatics  Association,  16  (3),  

291-­‐299.  

Lapointe,  L.,  &  Rivard,  S.  (2005).  A  multilevel  model  of  resistance  to  information  technology  

implementation.  MIS  Quarterly,  29  (3),  461-­‐491.  

Lapointe,  L.,  &  Rivard,  S.  (2006).  Getting  physicians  to  accept  new  information  technology:  insights  

from  case  studies.  Canadian  Medical  Association  Journal,  174  (11),  1573-­‐1578.  

Lapointe,  L.,  Mignerat,  M.,  &  Vedel,  I.  (2011).  The  IT  productivity  paradox  in  health:  A  stakeholder's  

perspective.  International  Journal  of  Medical  Informatics,  80  (2),  102-­‐115.    

Larsen,  M.  (2008).  Technology  in  healthcare,  leveraging  new  innovations.  Healthcare  Executive,  5,        

9-­‐14.  

Lau,  F.,  Price,  M.,  &  Keshavjee,  K.  (2011).  From  benefits  evaluation  to  clinical  adoption:  Making  sense  

of  health  information  system  success  in  Canada.  Healthcare  Quarterly,  14  (1),  39-­‐45.  

Lee,  A.  S.,  &  Baskerville,  R.  L.  (2003).  Generalizing  generalizability  in  information  systems  research.  

Information  Systems  Research,  14  (3),  221-­‐243.  

Leonard,  K.  (2004).  Critical  success  factors  relating  to  healthcare's  adoption  of  new  technology:  A  

guide  to  increasing  the  likelihood  of  successful  implementation.  Electronic  healthcare  2  (4),  72-­‐81.  

Linberg,  K.  (1999).  Software  developer  perceptions  about  software  project  failure:  a  case  study.  The  

Journal  of  Systems  and  Software,  49,  177-­‐192.  

Lyons,  S.,  Tripp-­‐Reimer,  T.,  Sorofman,  B.,  DeWitt,  J.,  BootsMiller,  J.,  Vaughn,  T.,  &  Doebbeling,  B.  

(2005).  Information  technology  for  clinical  guideline  implementation:  Perceptions  of  

multidisciplinary  stakeholders.  Journal  of  the  American  Medical  Informatics  Association,  12  (1),  

64-­‐71.  

Page 46: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  40  

Markus,  M.,  &  Robey,  D.  (1988).  Information  technology  and  organizational  change:  Causal  structure  

in  theory  and  research.  Management  Science,  34  (5),  583  –  598.  

McAfee,  A.  (2006).  Mastering  the  three  worlds  of  Information  Technology.  Harvard  Business  Review,  

84  (11),  141-­‐149.  

Munns,  A.  K.,  &  Bjeirmi,  B.F.  (1996).  The  role  of  project  management  in  achieving  project  success.  

International  Journal  of  Project  Management,  14  (2),  81-­‐87.    

Munir,  K.  A.  (2005).  The  Social  Construction  of  Events:  A  study  of  institutional  change  in  the  

photographic  field.  Organization  Studies,  26  (1),  93-­‐112.  

Ojiako,  U.,  Johansen,  E.,  &  Greenwood,  D.  (2008).  A  qualitative  re-­‐construction  of  project  

measurement  criteria.  Industrial  Management  and  Data  Systems,  108  (3/4),  405-­‐417.  

Orlikowski,  W.  J.,  &  Baroudi,  J.  J.  (1991).  Studying  information  technology  in  organizations:  Research  

approaches  and  assumptions.  Information  Systems  Research,  2  (1),  1-­‐28.  

Orlikowski,  W.J.  &  Iacono,  C.  (2001).  Research  Commentary:  Desperately  seeking  the  “IT”  in  IT  

research  –  A  call  to  theorizing  the  IT  artifact.  Information  Systems  Research,  12  (2),  121-­‐134.  

Paré,  G.  (2004).  Investigating  information  systems  with  positivist  case  study  research.  

Communications  of  the  Association  for  Information  Systems,  13,  233-­‐264.  

Pereira,  J.,  Cerpa,  N.,  Verner,  J.,  Rivas,  M.,  &  Procaccino,  J.  2008.  What  do  software  practitioners  

really  think  about  project  success:  A  cross-­‐cultural  comparison.  Journal  of  Systems  and  Software,  

81  (6),  897-­‐907.  

Pinto,  J.  K.  (2010).  Project  Management.  Achieving  Competitive  Advantage  (2nd  ed.).  Upper  Saddle  

River,  NJ:  Prentice  Hall.  

Pinto,  J.  K.,  &  Prescott,  J.  E.  (1988).  Variations  in  Critical  Success  Factors  Over  the  Stages  in  the  

Project  Life  Cycle.  Journal  of  Management,  14  (1),  5-­‐18.  

Pitts,  M.,  &  Browne,  G.  (2007).  Improving  requirements  elicitation:  An  empirical  investigation  of  

procedural  prompts,  Information  Systems  Journal,  17  (1),  89-­‐110.    

Prahalad,  C.K.,  &  Ramaswamy,  V.  (2000).  Co-­‐Opting  Customer  Competence.  Harvard  Business  

Review,  78  (1),  79-­‐87.  

Procaccino,  J  .,&  Verner,  J.M.  (2009).  Software  developers’  views  of  end-­‐users  and  project  success.  

Communications  of  the  ACM,  52  (5),  113-­‐116  .  

Quek,  F.,  &  Garcia,  L.  (1997).  Qualitative  research  in  information  systems:  Time  to  be  subjective?  

Information  Systems  and  Qualitative  Research,  444.  

Rinkus,  S.,  Walji,  M.,  Johnson-­‐Throop,  K.,  Malin,  J.,  Turley,  J.,  Smith,  J.,  &  Zhang,  J.  2005.  Human-­‐

centered  design  of  a  distributed  knowledge  management  system,  Journal  of  Biomedical  

Informatics,    38,  4–17.    

Page 47: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  41  

Sainfort,  F.,  &  George,  W.  (2004).    Healthcare  delivery  systems  in  the  US.  Engineering  Enterprise,  3,  6-­‐

9.    

Saleem,  N.,  Jones,  D.,  Van  Tran,  H.,  &  Moses,  B.  (2006).  Forming  design  teams  to  develop  healthcare  

information  systems.  Hospital  Topics,  84  (1),  22-­‐30.  

Samaras,  G.,    &  Horst,  R.(2005).  A  systems  engineering  perspective  on  the  human-­‐centered  design  of  

health  information  systems.  Journal  of  Biomedical  Informatics,  38  (1),  61–74.    

Schein,  E.  H.  (2010).  Organizational  culture  and  leadership  (4th  ed.).  San  Francisco:  Jossey-­‐Bass.                                              

Shenhar,  A.,  Dvir,  R.,  Levy,  D.,  &  Maltz,  A.  (2001).  Project  Success:  A  Multidimensional  Strategic  

Concept.  Long  Range  Planning,  34  (6),  699–725.  

Stam,  K.,  &  Stanton,  J.  (2010).  Events,  emotions,  and  technology:  Examining  acceptance  of  workplace  

technology  changes.  Information  Technology  &  People,  23  (1),  23  –  53.  

Stetler,  C.  B.,  Ritchie,  J.,  Rycroft-­‐Malone,  J.,  Schultz,  A.,  &  Charns,  M.  (2007).  Improving  quality  of  care  

through  routine,  successful  implementation  of  evidence-­‐based  practice  at  the  bedside:  An  

organizational  case  study  protocol  using  the  Pettigrew  and  Whipp  model  of  strategic  change.  

Implementation  Science,  2  (3),  1-­‐13.  

Subramanyam,  R.,  Weisstein,  F.,  &  Krishnan,  M.  S.  (2010).  User  participation  in  software  

development  projects.  Communications  of  the  ACM,  53  (3),  137-­‐141.  

Thakur,  R.,  Hsu,  S.,  &  Fontenot,  G.  (2012).  Innovation  in  healthcare:  Issues  and  future  trends.  Journal  

of  Business  Research,  65  (4),  562–569.  

Teixeira,  L.,  Ferreira,  C.,  &  Sousa  Santos,  B.  (2012).  User-­‐centered  requirements  engineering  in  health  

information  systems:  A  study  in  the  hemophilia  field.  Computer  Methods  and  Programs  in  

Biomedicine  106  (3),  160–174.  

Thomas,  G.,  &  Fernandez,  W.  (2008).  Success  in  IT  projects:  A  matter  of  definition?  International  

Journal  of  Project  Management,  26  (7),  733–742.  

Trudel,  M.,  Paré,  G.,  &  Laflamme,  J.  (2012)  Health  information  technology  success  and  the  art  of  

being  mindful:  Preliminary  insights  from  a  comparative  case  study  analysis.  Health  Care  

Management  Review,  37  (1),  31-­‐42.  

Wateridge,  J.  (1995).  IT  Projects:  a  basis  for  success.  International  Journal  of  Project  Management    

13,  (3),  169-­‐172.  

Whipp,  R.,  &  Pettigrew,  A.  (1992).  Managing  Change  for  Competitive  Success:  Bridging  the  Strategic  

and  the  Operational.  Industrial  and  Corporate  Change,  1  (1),  205-­‐235.  

Yin,  R.K.  (2009).  Case  Study  Research,  Design  and  Methods  (4rd  ed.).  Beverly  Hills:  Sage.  

Zhang,  J.  (2005).    Human-­‐centered  computing  in  health  information  systems.  Part  1.  Analysis  and  

design.  Journal  of  Biomedical  Informatics,  38  (1),  1–3.      

Page 48: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

 

  42  

Appendix  A  –  Interview  guideline  

 

Introduction  

a. Introduction  to  the  interview  • Introduce  interviewer,  explain  research  and  confidentiality  and  recording    

b. Introduction  interviewee  • Name,  function  and  work  history  

 Interview    

1. Description  of  the  project  by  interviewee    • Describe  the  project  in  your  own  words  • What  did,  in  your  opinion,  the  project  aim  to  achieve?  • What  can  you  tell  about  the  project  approach?.  • What  was  your  role?    • Why  did  you  participate?    • What  were  your  expectations?    

2. Was  the  project  in  your  perception  a  success?    • If  yes,  what  made  it  a  success?  • If  not,  what  made  not  a  success?    

3. If,  at  the  beginning  of  the  project,  you  would  have  been  asked  to  describe  success,  what  would  have  been  your  answer?    

4. Did  your  idea  of  success  change  during  the  project?    If  yes,  how  and  by  what?  

5. Which  important  event  mostly  influenced  your  perception  of  success?    • When  during  the  project  did  this  event  take  place?    • What  in  your  opinion,  exactly  happened?  

6. How  did  this  event  influence  your  perception  of  success?  • How  did  it  influence  your  thoughts?  • How  did  it  influence  your  actions?  • Why  was  this  according  to  you  an  important  event  in  relation  to  the  success  of  this  project?  

7. What  are,  in  general,  events  during  a  project  that  make  you  consider  a  project  successful?    Closing      A. Do  you  have  additional  remarks?  

 B. Is  there  anything  relevant  for  this  project  or  this  research  that  has  not  yet  been  discussed?    

Page 49: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

1

Page 50: How key events shape stakeholder perceptions of success ... Success... · Although literature agrees on the fact that project success is a subjective interpretation of stakeholders,

2

Contact Kenniscentrum Ondernemerschap Zernikeplein 7 9747 AS Groningen 050 595 2070 [email protected]