Amity School of Engineering & Technology, AUR

Presentation on

house construction

submitted by- Abhinav saha B.Tech CIVIL Vth sem

1

Page 2: house construction

Amity School of Engineering & Technology, AUR

2

Page 3: house construction

Amity School of Engineering & Technology, AUR

3

Page 4: house construction

Amity School of Engineering & Technology, AUR

4

Page 5: house construction

Amity School of Engineering & Technology, AUR

5

Page 6: house construction

Amity School of Engineering & Technology, AUR

• Excavating ground reveals critical knowledge about the soil and therefore dictates the design of foundation. For example, for reclaimed land (i.e. ones that originally hosted lake and were filled with sand), soil tends to be soft and therefore chances of further strengthening the foundation to avoid it from setting-in. In some cases, ground may be full of rocks and therefore can take longer to excavate.

• Trick they use with excavation is to excavate about 6-inch and then thoroughly soak ground with water. This makes excavation extremely easy. For all load bearing areas excavation is done for 4-feet and column area are excavated for 6-feet. This building is small-enough that all excavation is done manually itself.

6

Page 7: house construction

Amity School of Engineering & Technology, AUR

Foundation plan• Foundation masonry - Cement building blocks that are about 38cm tall, 15cm wide

and 15cm deep are the foundation of the building. They are "stuck" together with cement concrete masonry. It is recommended that anti-termite treatment be done twice - once before placing any cement blocks and next after placing all layers of cement blocks.

• Rain water tank-It was decided to go with what seems like a good size rainwater (RWH) tank - 60,000 litres.

• Columns - Four columns need a bit of special work to get set up. They would essentially setup iron columns in those areas and put concrete around them. Once columns come up to the plinth level, they would be connected to the rest of the house via plinth beam .There are 4 columns to bear the load of the first floor balcony and the family room areas. Excavation for columns is about 1500mm. Base of the column is filled with mortar. Then a steel column of about 3000mm is erected. Rings are tied approx 150mm from each other to hold the column together. Finally, they'd pour cement concrete around it to create the actual column structure.

7

Page 8: house construction

Amity School of Engineering & Technology, AUR

• Cement building blocks that are about 38cm tall, 15cm wide and 15cm deep are the foundation of the building. They are "stuck" together with cement concrete masonry.

• anti-termite treatment be done twice - once before placing any cement blocks and next after placing all layers of cement blocks.

• Mixing ratio – 1 part of cement, 4 part of sand, and 8 part of aggregate.

• In my case, ground level at living room side is about 6 to 12 inches higher than that on the guest bedroom side. Hence, they'd do more layers at latter so plinth beam will be at even level.

8

Page 9: house construction

Amity School of Engineering & Technology, AUR

• Four columns need a bit of special work to get set up. They would essentially setup iron columns in those areas and put concrete around them. Once columns come up to the plinth level, they would be connected to the rest of the house via plinth beam.

• Foundation around load bearing walls will be done first followed by columns and finally by RWH tank structure. Once each component is built they will be joined together through plinth beam. Our expectation is plinth beam will be about 2.5 feet above the natural ground level. This so as to keep house safe from flooding as well as provide appropriate elevation.

9

Page 10: house construction

Amity School of Engineering & Technology, AUR

Plinth beam• Plinth beam is the horizontal cement beam across the house periphery laid

on top of foundation.• PURPOSE

1. Prevent leaking of water into foundation

2. Provides support for walls

3. Holds house together.

10

Page 11: house construction

Amity School of Engineering & Technology, AUR

Basic process to construct plinth beam is as follows:

• Mark-up width - Usually width of plinth is half that of the foundation. In this case, foundation is about 45cm wide and so plinth is 23cm aligning with the outer edge of the foundation. Inner 23cm of foundation meshes into the floor level of the house.

• Lay down the steel beam - As the adjacent picture shows beams are the core of the plinth beam. Beams have a loop every 16cm that holds it together.

• Setup reinforcement - Before concrete is poured, reinforcement has to be established to provide rectangular shape to the beam. This takes majority of effort as planks have to be nailed properly in place and once concrete is poured they need to be removed.

• Pour the concrete - Next step is to pour the concrete. As concrete is poured, mason ensures that it is evenly spread and smoothens out any edges. He also needs to ensure the height of the beam is consistent throughout the periphery.

• Remove reinforcement - Concrete turns solid within 24-hour and final step is to remove the planks leaving the beam intact.

11

Page 12: house construction

Amity School of Engineering & Technology, AUR

Planning of exposed brick walls• Niches - Position, height and width of each niche that would be

placed in the wall.

• Electrical layout - If any ducts have to pass through this wall these need to be planned and performed while these walls come up. (Note: From aesthetics perspective, it is advisable to not have any electrical points in the brick wall itself.)

• Brick patterns - To avoid monotonous look, border brick patterns can be added on a wall. Typically, these are added a few rows above the lintel. These have to be decided and upfront planned with mason. Some times, masons may not know how to lay patterns (especially if they tend to be difficult) and it is wise to allow time for these.

12

Page 13: house construction

Amity School of Engineering & Technology, AUR

Type of brick usedWire cut bricks

•Dimension : 230*105*75MM (Length*Width*Thickness) •Compressive Strength : 300 Kg/Cm2, or 12 N/MM2•Water Absorption : 6% of Total Weight•Quantity Bricks : 10000 Bricks/Truck

13

Page 14: house construction

Amity School of Engineering & Technology, AUR

Lintel beam• lintel beam serves the purpose of binding various spaces in the

house together as well as providing foundation to host brick layers extending to roof. Lintel beam is placed typically on top of window and door spaces.

• Put reinforcement in the form of wooden sticks. Then, lay wooden sheets on top of window or door space.

• Do the form work (i.e. lay-down the steel rods that provides the core of the beam).

• Provide shape by reinforcing wooden planks on both sides. Pour the concrete and allow it to dry for a few days.

• Remove the wooden planks on the side as well as wooden sticks

14

Page 15: house construction

Amity School of Engineering & Technology, AUR

15

Page 16: house construction

Amity School of Engineering & Technology, AUR

First Class Brick Work 1:7

•Brick walls constructed with cement sand mortar in the ratio of 1:7 means 1 part of cement and 7 parts of sand. This mortar is low in strength and is recommended for following works.

•Toe walls

•Single storey buildings•Temporary structures•Light weight walls having no load of beams etc.

16

Page 17: house construction

Amity School of Engineering & Technology, AUR

Plastering•The joints of the brick work shall raked out to a depth of 12 mm and the surface of the wall washed and clean and kept wet for the two days before plastering. The material of mortar should be of standard specification.•The thickness of the plastering shall be of 12mm to ensure uniform thickness of plaster; patches of 15 cm shall be applied first at about 2 m apart to act as guide. First mortar shall be dashed and pressed over the surface and then brought to a true smooth and uniform surface by means of float and trowel •Wall plastering shall be started from top and worked down towards floor,. Ceiling plastering shall be completed before starting of wall plaster.•All corner and edge shall be rounded. The plastered surface shall be kept wet for 10days the surface should be protected from rain, sun, frost, etc.•For wall plastering 1:5 cement mortar and for ceiling plastering 1:3 cement mortar with coarse sand is used.

17

Page 18: house construction

Amity School of Engineering & Technology, AUR

25 cm Cement Concrete floor

•The cement concrete shall be of proportion 1:2:4 cement shall be fresh Portland cement of standard specification. The coarse aggregate shall be hard and tough of 3cm gauge, well graded and free from dust, dirt, etc. the sand shall be coarse of 5mm maximum size and down, well graded, clean and free from dust, direct and organic matters.•The floor shall be leveled and divided into panels or bays of maximums size or 1.2mx1.2m and the sides of the panels shall be bounded with teak wood battens 2. cm thick and 5 cm wide or flat iron of same thickness and fixed with weak mortar, or with nails or hooks. Required camber or slope should be given in floor for draining wash water.•Mixing of concrete shall be down by measuring with boxes to have the required proportion as specified. First cement and sand mixed dry and the dry mix of cement and sand mixed with ballast dry, and the mixed by adding water slowly and gradually to the required quantity, and mixed thoroughly to have a uniform plastic mix. •In ground floor the c.c. floor shall be laid on a 7.5cm base of weak cement concrete as per standard specifications.