    Variable Rates of Contractors, Materials & Architect

    Contractor Items

    Unit Rate/ Unit

    Option 1 Option 2

    Excavation for foundation CFT 6 7

    Plain cement concrete for foundation CFT 85 85

    Reinforce cement concrete for foundation CFT 120 120Masonary upto plinth beam CFT 110 110

    RCC 1:2:4 Plinth beam CFT 125 125

    Masonary ground floor (above plinth beam) CFT 115 120

    Masonary first floor (above plinth beam) CFT 120 125

    Plaster internal wall SFT 15 17

    External plastor SFT 20 22

    Ceiling plastor SFT 18 20

    RCC 124 Column CFT 125 126

    RCC Lintal CFT 125 126

    RCC slab CFT 125 126

    RCC 124 Stair case CFT 160 165

    Steel reinforcement with placing and fixing KG 63 65

    Roof top screeding 1:2:4 with GI mesh SFT 40 38

    Plumbing (covered area) SFT 8 10

    Pipe fittings (water, sui gas, sewerage pipes) SFT 35 35

    Electric (covered area) (labor cost) SFT 9 11Wire fittings (ordinary, high voltage) SFT 15 17

    Lacqour wood polish SFT 21 20

    Emulsion paint + enamel paint (wall + ceiling) SFT 2 3

    Enamel paint (ceiling) SFT 2 3

    Weathershield paint (exterior) SFT 2 3

    Construction Material

  • 8/14/2019 House Building Cost Data

    2/17

    Unit Rate/ Unit Manufactured by/in Rate/ Unit

    Option 1

    Electricity fittings

    Switch socket Per point 33 Chinese -

    Chandelair set Per set 7500 Chinese -

    Light fittings (wall lights including bulb) Per unit 1250 Chinese -

    Tube lights (complete set) Per unit 330 Philips -

    Electricity main board (with circuit breakers) Per unit 2950 Chinese -

    Ceiling fans Per unit 2375 Parwaz (craze) 3300Exhaust fans Per unit 720 Parwaz (window type) 880

    Bathroom fittings

    Shower set Per set 2200 Super Asia 3200

    Basic amenities set Per set 3900 Forte 3600

    Accessories set (mirror, towel hangers, soap shelf etc) Per set 1800 Master 1200

    Bathtub Per set 1890 Super Asia -

    Bathroom tiles (8 cm. * 12cm.) (for walls) Per mtr. 290 Forte 330

    Bathroom tiles (8 cm. * 12cm.) (for floor) Per mtr. 290 Forte 330

    Paint

    Lacqour wood polish Per gallon 1075 ICI 1075

    Enamel synthetic paint (ceiling) Per gallon 650 ICI 650

    Emulsion paint (wall) Per gallon 1550 ICI 1550

    Weathershield paint (exterior) Per gallon 3400 ICI 3400

    Accessories

    Gas Heater (servant quarter) Per unit 850 Pakistani -

    Gas Heater (auto-ignition) Per unit 5900 Canon -

    Gas Geyser (40 gallons) Per unit 10500 SSG -

    Cooking range (5 burner + oven) Per unit 22100 Care 11000

    Air conditioner (split unit, heat & cool) (1.5 Ton) Per unit 27000 GREE

    Wood work

  • 8/14/2019 House Building Cost Data

    3/17

    Wooden main door (including locks) Per unit 6500 Local Manufactured -

    Wooden washroom doors (including locks) Per unit 1650 Local Manufactured -

    Wooden doors (including locks) Per unit 2220 Local Manufactured -

    Wooden cabinets (bedroom & t.v. lounge) SFT 260 Local Manufactured -

    Wooden cabinets (kitchen) SFT 300 Local Manufactured -

    Aluminium windows wih grills Per sq. mtr 400 Local Manufactured -

    Window panes (glass plain) Per sq. mtr 29 Al-Karam Glass 35

    Main Gate Per sq.ft 350 Local Manufactured -

    Overhead water tank (200 gallon) Per unit 5760 Local Manufactured 4160

    Floor marbles (for terrace and porch) Per sq. ft 80 Local Manufactured -

    Floor tiles (18 inch by 18inch) Per sq. ft 250 Local Manufactured -

    Kitchen counter marbles SFT 350 Local Manufactured -

    Architect fee

    2% of total cost of construction

    Note: The yellow coloured boxes are the options selected by our group, based on price or quality consideration.

  • 8/14/2019 House Building Cost Data

    4/17

  • 8/14/2019 House Building Cost Data

    5/17

    Manufactured by/in

    Option 2

    -

    -

    -

    -

    -

    Parwaz (marvel)Parwaz (sprint)

    Gujranwala

    Super Asia

    Super Asia

    -

    Amco

    Amco

    Berger

    Berger

    Berger

    Berger

    -

    -

    -

    Pakistani

  • 8/14/2019 House Building Cost Data

    6/17

    -

    -

    -

    -

    -

    -

    Khwaja Glass

    -

    Local Manufactured

    -

    -

    -

  • 8/14/2019 House Building Cost Data

    7/17

    Total Selected Costs

    Plot Price (50' x 90')

    Contractor ItemsUnit Rate/ Unit Quantity

    Excavation for foundation CFT 6 15,000

    Plain cement concrete for foundation CFT 85 945

    Reinforce cement concrete for foundation CFT 120 2,800

    Masonary upto plinth beam CFT 110 1,700

    RCC 1:2:4 Plinth beam CFT 125 510

    Masonary ground floor (above plinth beam) CFT 115 4,320Masonary first floor (above plinth beam) CFT 120 3,960

    Plaster internal wall SFT 15 17,100

    External plastor SFT 20 5,040

    Ceiling plastor SFT 18 6,750

    RCC 124 Column CFT 125 1,000

    RCC Lintal CFT 125 216

    RCC slab CFT 125 3,960

    RCC 124 Stair case CFT 160 90

    Steel reinforcement with placing and fixing KG 63 15,000

    Roof top screeding 1:2:4 with GI mesh SFT 40 4,248

    Plumbing (covered area) SFT 8 7,632

    Pipe fittings (water, sui gas, sewerage pipes) SFT 35 7,632

    Electric (covered area) (labor cost) SFT 9 7,632

    Wire fittings (ordinary, high voltage) SFT 15 7,632

    Lacqour wood polish SFT 21 360

    Emulsion paint + enamel paint(wall + ceiling) SFT 2 24,000

    Enamel paint (ceiling) SFT 2 900

    Weathershield paint (exterior) SFT 2 5,040

    Contractor Cost

    Construction MaterialUnit Rate/ Unit Manufactured by/in

  • 8/14/2019 House Building Cost Data

    8/17

    Electricity fittings

    Switch socket Per point 33 Chinese

    Chandelair set Per set 7,500 Chinese

    Light fittings (wall lights including bulb) Per unit 1,250 Chinese

    Tube lights (complete set) Per unit 330 Philips

    Electricity main board (with circuit breakers) Per unit 2,950 Chinese

    Ceiling fans Per unit 2,375 Parwaz (craze)

    Exhaust fans Per unit 720 Parwaz (window type)

    Bathroom fittings

    Shower set Per set 3,200 Gujranwala

    Basic amenities set Per set 3,900 ForteAccessories set (mirror, towel hangers etc.) Per set 1,800 Master

    Bathtub Per set 1,890 Super Asia

    Bathroom tiles for walls (8 cm.*12cm.)(Rs.330/sq.m) Per SFT 31 Amco

    Bathroom tiles for floor (8 cm.*12cm.)(Rs.330/sq.m) Per SFT 31 Amco

    Paint

    Lacqour wood polish Per gallon 1,075 ICI

    Enamel synthetic paint (ceiling) Per gallon 650 ICI

    Emulsion paint (wall) Per gallon 1,550 ICI

    Weathershield paint (exterior) Per gallon 3,400 ICI

    Accessories

    Gas Heater (servant quarter) Per unit 850 Pakistani

    Gas Heater (auto-ignition) Per unit 5,900 Canon

    Gas Geyser (40 gallons) Per unit 10,500 SSGCooking range (5 burner + oven) (first floor) Per unit 11,000 Pakistani

    Cooking range (5 burner + oven) (ground floor) Per unit 22,100 Care

    Air conditioner (split unit, heat & cool) (1.5 Ton) Per unit 27,000 GREE

    Wood work

    Wooden main door (including locks) Per unit 6,500 Local Manufactured

    Wooden washroom doors (including locks) Per unit 1,650 Local Manufactured

    Wooden doors (including locks) Per unit 2,220 Local Manufactured

  • 8/14/2019 House Building Cost Data

    9/17

    Wooden cabinets (bedroom & t.v. lounge) SFT 260 Local Manufactured

    Wooden cabinets (kitchen) SFT 300 Local Manufactured

    Aluminium windows wih grills Per sq. mtr 400 Local Manufactured

    Window panes (glass plain) Per sq. mtr 35 Khwaja Glass

    Main Gate (1 gate) Per sq.ft 350 Local Manufactured

    Overhead water tank (200 gallon) Per unit 5,760 Local Manufactured

    Floor marbles (for terrace and porch) Per sq. ft 80 Local Manufactured

    Floor tiles (18 inch by 18inch) Per sq. ft 250 Local Manufactured

    Kitchen counter marbles SFT 350 Local Manufactured

    Construction Material Cost

    Total Cost (Contractor cost + Material cost + Plot price)

    Architect fee

    2% of total cost of construction

    TOTAL CONSTRUCTION COST

  • 8/14/2019 House Building Cost Data

    10/17

    1,900,000

    Labor Cost Total Amount90,000 90,000

    80,325 144,576

    61,236 336,000

    33,680 187,000

    11,500 63,750

    90,000 496,80085,536 475,200

    46,656 265,500

    18,144 100,800

    21,870 121,500

    22,680 125,000

    4,860 27,000

    89,100 495,000

    2,592 14,400

    163,296 945,000

    30,585 169,920

    59,911 59,911

    - 267,120

    68,688 68,688

    - 114,480

    7,560 7,560

    48,000 48,000

    1,800 1,800

    11,794 11,794

    1,049,813 4,636,799

    Quantity Amount

  • 8/14/2019 House Building Cost Data

    11/17

    171 5,643

    2 15,000

    53 66,250

    30 9,900

    1 2,950

    17 40,375

    10 7,200

    7 22,400

    8 31,2007 12,600

    1 1,890

    1,000 31,000

    350 10,850

    9 38,700

    4 10,400

    6 37,200

    5 68,000

    1 850

    2 11,800

    1 10,5001 11,000

    2 22,100

    6 162,000

    2 13,000

    10 16,500

    19 42,180

  • 8/14/2019 House Building Cost Data

    12/17

  • 8/14/2019 House Building Cost Data

    13/17

    Bid Price

    (Rs.)

    Total Cost 8,891,133

    Profit Margin (10% of total cost) 889,113

    Total bid price (Total cost + Profit Margin) 9,780,246

    Total bid price = Rs. Nine million seven lac eighty thousand two hundred and forty six rupees only

  • 8/14/2019 House Building Cost Data

    14/17

    Costing

    DIRECT MATERIALS

    Plain cement concrete for foundation 64,251

    Reinforce cement concrete for foundation 274,764

    Masonary upto plinth beam 153,320

    RCC 1:2:4 Plinth beam 52,250

    Masonary ground floor (above plinth beam) 406,800

    Masonary first floor (above plinth beam) 389,664

    Plaster internal wall 218,844

    External plastor 82,656Ceiling plastor 99,630

    RCC 124 Column 102,320

    RCC Lintal 22,140

    RCC slab 405,900

    RCC 124 Stair case 11,808

    Steel reinforcement with placing and fixing 781,704

    Roof top screeding 1:2:4 with GI mesh 139,335 3,205,386

    Electricity fittings

    Switch socket 5,643

    Chandelair set 15,000

    Light fittings (wall lights including bulb) 66,250

    Tube lights (complete set) 9,900

    Electricity main board (with circuit breakers) 2,950

    Ceiling fans 40,375

    Exhaust fans 7,200 147,318

    Bathroom fittings

    Shower set 22,400

    Basic amenities set 31,200

    Accessories set (mirror, towel hangers, soap shelf etc) 12,600

    Bathtub 1,890

    Bathroom tiles (8 cm. * 12cm.) (for walls) (Rs.330/sq.m) 31,000

    Bathroom tiles (8 cm. * 12cm.) (for floor) (Rs.330/sq.m) 10,850 109,940

    Accessories

    Gas Heater (servant quarter) 850

  • 8/14/2019 House Building Cost Data

    15/17

    Gas Heater (auto-ignition) 11,800

    Gas Geyser (40 gallons) 10,500

    Cooking range (5 burner + oven) (first floor) 11,000

    Cooking range (5 burner + oven) (ground floor) 22,100

    Air conditioner (split unit, heat & cool) (1.5 Ton) 162,000 218,250

    Wood work

    Wooden main door (including locks) 13,000

    Wooden washroom doors (including locks) 16,500

    Wooden doors (including locks) 42,180

    Wooden cabinets (bedroom & t.v. lounge) 187,200

    Wooden cabinets (kitchen) 90,000 348,880

    Aluminium windows wih grills 228,000

    Window panes (glass plain) 19,950

    Main Gate (1 gate) 23,100

    Overhead water tank (200 gallon) 5,760

    Floor marbles (for terrace and porch) 104,000

    Floor tiles (18 inch by 18inch) 775,000

    Kitchen counter marbles 45,500 1,201,310

    Paint

    Lacqour wood polish 38,700

    Enamel synthetic paint (ceiling) 10,400

    Emulsion paint (wall) 37,200

    Weathershield paint (exterior) 68,000 154,300

    Total Direct Materials 5,385,384

    DIRECT LABOR

    Excavation for foundation 90,000

    Plain cement concrete for foundation 80,325

    Reinforce cement concrete for foundation 61,236

    Masonary upto plinth beam 33,680

    RCC 1:2:4 Plinth beam 11,500

    Masonary ground floor (above plinth beam) 90,000

  • 8/14/2019 House Building Cost Data

    16/17

  • 8/14/2019 House Building Cost Data

    17/17

    INCOME STATEMENT(Rs)

    Sales Revenue 9,780,245

    Less: Cost of House

    Beginning inventory 0Cost of house Manufactured 8891133

    Cost of house Available for sale 8891133

    less:Ending Inventory 0

    Total Cost of House Sold (8,891,133)