Hospital of the FutureConstruction Update as of Dec. 3, 2010
Hospital of the Future
West side of the building.
Hospital of the Future
View of brick work from Springfield Street.
Hospital of the Future
Green Roof (install spring 2011).
Hospital of the Future
Basement boiler started early Nov. to provide temporary heat during construction.
Hospital of the Future
Basement air handler unit started in early Dec. for temporary heat during construction.
Hospital of the Future
Endovascular procedure rooms support steel duct installation ongoing.
Hospital of the Future
Endovascular procedure room coordination complete, released for fabrication.
Endovascular procedure room coordination (each room = 200 hours of configuration).
Hospital of the Future
2nd Floor: CARE area drywall underway.
Hospital of the Future
3rd Floor: Rough-in complete; drywall underway.
2011
Facility Milestones to Come:
•Finished ceilings begin. •Exterior landscaping begins. •Final painting begins.•Phase 1 construction complete.
2012
NEW PATIENT AREAS OPEN!