Holistic Approach to Capturing and Sustaining Energy Savings · Holistic Approach to Capturing and...

24
©2006 Aspen Technology, Inc. All rights reserved Holistic Approach to Capturing and Sustaining Energy Savings December 7 th , 2006

Transcript of Holistic Approach to Capturing and Sustaining Energy Savings · Holistic Approach to Capturing and...

©2006 Aspen Technology, Inc. All rights reserved

Holistic Approach to Capturing and Sustaining EnergySavings

December 7th, 2006

2©2006 Aspen Technology, Inc. All rights reserved

Outline

•What is energy management?

•Advanced Process Design

•Sustainability

•Holistic approach

•Summary

3©2006 Aspen Technology, Inc. All rights reserved

Energy Flow and Profitability

Supply Profile

Demand Profile

4©2006 Aspen Technology, Inc. All rights reserved

Energy Management Components

Supply SideSupply Side

(Utilities)(Utilities)

DesignDesign

OperationsOperations

Demand SideDemand Side

(Processes)(Processes)

5©2006 Aspen Technology, Inc. All rights reserved

Energy Management –Time Horizons

Supply SideSupply Side

(Utilities)(Utilities)

Demand SideDemand Side

(Processes)(Processes)

Strategic Planning

Tactical Planning

Scheduling

Operating Decisions

Control

Years

Months/Weeks

Days

Hours

Minutes

DesignDesign

OperationsOperations

6©2006 Aspen Technology, Inc. All rights reserved

Utilities system modeling

Total Site Pinch Analysis

Optimize utilities system design

Cogeneration Feasibility

GHG Planning

Energy/yield/purity/throughputtrade-off

Process/Column Pinch Analysis Catalyst Replacements Process re-sequencing &

optimization Establish energy targets

Energy Management Components

Supply SideSupply Side

(Utilities)(Utilities)

Operator Decision SupportSystem

Performance management Dynamic targeting & alerting Heat Exchanger Monitoring Advanced Control Real time Optimization

Fuel, Steam & Poweroptimization

Performance Management Utilities Contract Management Emissions management Reduce flaring & venting

Demand SideDemand Side

(Processes)(Processes)

DesignDesign

OperationsOperations

7©2006 Aspen Technology, Inc. All rights reserved

RawMaterials

DesiredProductsProcess?

The objective of process design is the creation of a process toconvert raw materials into desired products

What is Process Design?

8©2006 Aspen Technology, Inc. All rights reserved

Feed Heat Cool

Reactor

Process design starts with the Reactor

What is Process Design?

9©2006 Aspen Technology, Inc. All rights reserved

FEED RECYCLE

Cool

CoolCoolHeat

Heat

Heat

Heat

ReactorFEED

PRODUCT

BYPRODUCT

The reactor design dictatesthe separation and recycle problem

What is Process Design?

10©2006 Aspen Technology, Inc. All rights reserved

Cool

Cool

Heat

Heat

Heat

Reactor

FEED

FEED

PRODUCT

BYPRODUCT

The reactor and separator system dictate the heating and cooling dutiesof the streams, so the heat exchanger network can be developed

FEED

What is Process Design?

11©2006 Aspen Technology, Inc. All rights reserved

CW

CW

Steam

Steam

Steam

ReactorFEED

FEED

PRODUCT

BYPRODUCT

Those duties which cannot be satisfied by heat integrationdictate the need for .external utilities

Steam Mains

CoolingTower

FEED

What is Process Design?

12©2006 Aspen Technology, Inc. All rights reserved

Reactor

Separation Scheme

Heat ExchangerNetwork

Utility Selection

Base Case

Different possibilitiesfor heat recovery

Type, SequencePressure, Feed ConditioningSide Reboiler / Condenser

Steam, Hot OilFlue gas, Refrigerant

Type, Phase, CatalystPressure, Temperature

Once a base case design has been developed, this can then beimproved by considering Structural and Parametric Changes

Process Improvement

13©2006 Aspen Technology, Inc. All rights reserved

Engineer Modeling

Quantify real impact

Idea # 3 ......Idea # 2Idea # 1,

Traditional Approach to Process Improvement

14©2006 Aspen Technology, Inc. All rights reserved

SynthesisGenerate Ideas

ModelingEvaluate Ideas

Engineer

Quantify real impact

Set targetsIdentify critical designchanges

Key Ideas

AspenTech Advanced Process Design

15©2006 Aspen Technology, Inc. All rights reserved

Modeling

ModelingExistingProcess

ExistingProcess

ImprovedProcess

ImprovedProcess

Reduced Modeling EffortBetter Improvement Option

Impact on ProcessConfiguration

Why use Process Synthesis?

Value•5-30% energy savings with 1-2 years payback (energy and emissions reduction)•5-15% capacity increase with 10-30% less capital (plant debottlenecking)

Value•5-30% energy savings with 1-2 years payback (energy and emissions reduction)•5-15% capacity increase with 10-30% less capital (plant debottlenecking)

16©2006 Aspen Technology, Inc. All rights reserved

Design for Energy EfficiencySamsung General Chemicals, Daesan (Korea)

Site Profile

•Energy costs had risen

dramatically since plant start-up

(oil price $17 $29 $40 )

•By 2000, the annual energy bill for

the complex was over $60MM

•SGC began to study radical

revamp plans to significantly

reduce energy costs

Business Challenges

How AspenTech Helped•Joint project executed by Samsung General Chemicals / Samsung

Engineering / AspenTech.•Several SGC’s ideas were used, together with new ideas generated from

modelling and energy system optimization analysis.•Practical project ideas developed and costed.($9.1MM)•20%+ energy savings achieved. ($12MM/year)

•SGC operates a large aromaticscomplex in Daesan, Republic ofKorea

•Built in 1997•Capacity:

480,000 MTA Paraxylene240,000 MTA Benzene100,000 MTA Toluene

Complex-wide revamping for energy optimization

Aromatic Complex Revamping

17©2006 Aspen Technology, Inc. All rights reserved

Design for Energy EfficiencyZero Capital Opportunities

Site Profile

•Rigorous, predictive Aspen plus model

•Detailed analysis and specific

operational modifications of:

•Ethane-propane feed splitter

•Cold box- Demethaniser

•Ethylene splitter / fractionator

•Rigorous acceptance testing of all

modifications

Deliverables

Results•Changes were easily implemented and tested within a 4 month period.•Energy savings in excess of $500,000 / year with no capital

expenditure.•Many other potential improvements and debottlenecking opportunities

identified for future development.•Unit personnel gained more knowledge, which has helped improve

operation and optimization efforts

•Ethylene Plant•Capacity - 1 billion lb per annum•Ethane/propane feedstock

Aromatic Complex RevampingCrackingFurnaces

GasSweetening Quench

Diln Steam

Compression1-3

NaOH WashDrying

Cold Box

Chilldown

Companders

EthyleneReFridge

DeEthaniser

DePropaniser

Stabiliser

EthyleneSplitter

DeMethaniser

C3's

C5's

C4's

H2

Methane

Ethylene

Ethane r/c

EthaneFeed

PropaneReFridge

Steam System

Comp-4

AcetHydro

PropaneFeed

PyGas

Water

Framework•Pay-for-performance fee basis

•Zero capital expenditure

18©2006 Aspen Technology, Inc. All rights reserved

Design for Energy EfficiencyZero Capital Opportunities (cont.)

Demethanizer Operational Improvements–Cold Box refrigeration loads / profile shifted

•Make better use of higher level refrigeration and lower duty on colder

refrigeration levels

–Methane Circulation maximized

Hydrogen purity

Hydrogen intrusion into demethanizer

Recycles to methane refrigeration compressor (MRC)

Pressure required at PGC and Demethanizer

–Methane in Bottoms Reduced to 50 ppm, Side Reboiler Duty Reduced

& Pre-heater Flow Increased

•Properly balanced tray loading

•Maximized separation efficiency

19©2006 Aspen Technology, Inc. All rights reserved

Sustainability

A year later….

Most of the operational improvements had regressed to their

original state

Why?–Inadequate follow-up by process engineering to train operations

–“But we’ve always run it that way”mentality

–Staff turn-over

–Lack of management attention

–No on-line performance management system

20©2006 Aspen Technology, Inc. All rights reserved

Performance Management System

21©2006 Aspen Technology, Inc. All rights reserved

Energy Investment Plan &

Program Management

Energy Investment Plan &

Program Management

Energy Management AnalysisEnergy Management AnalysisAssess Current State of site energy managementAssess Current State of site energy managementMap improvement needs to AspenTech capabilitiesMap improvement needs to AspenTech capabilitiesPlan the Energy Management ProgramPlan the Energy Management Program

Holistic Approach

Supply SideSupply Side(Utilities)(Utilities)

Demand SideDemand Side(Processes)(Processes)

DesignDesign

OperationsOperations

Energy / yield / purity / throughputtrade-off

Process/Column Pinch Analysis Catalyst Replacements Process re-sequencing & optimization Establish energy targets

Operator Decision Support System Performance management Dynamic targeting & alerting Heat Exchanger Monitoring Advanced Control Real time Optimization

Utilities system modeling Total Site Pinch Analysis Optimize utilities system design Cogeneration Feasibility GHG Planning

Fuel, Steam & Power optimization

Performance Management

Utilities Contract Management

Emissions management

Reduce flaring & venting

22©2006 Aspen Technology, Inc. All rights reserved

Month 1 Month 2 Month 3 Month 4 Months 5 & 6 Months 7 to 9 10 to 12 13 to 18

Typical Sequence of Events

EnergyManagement

Analysis

Program Management

Engineering Design, Construction &CommissioningAdvanced Process

Design

Utilities ManagementUtilities Planning Utilities Operations

Energy

TargetsOperationalImprovements

CapEx Projects

Operational Improvements

Advanced Process Control / Real-time Optimization

Performance Management

Base-lining Targeting Continuous Improvement

23©2006 Aspen Technology, Inc. All rights reserved

SummaryV

alu

e

Time

=

Syn

erg

y+

Su

stai

nab

ility

Consulting report

No Knowledge transfer

Implement Point Solutions

Transfer Know-how & models

Investment Plan

Program management

Performance Management

Deliverables

SYNERGY –Design, Operation, Supply & Demand workingtogether towards the same goal

SUSTAINABILITY –Capture improvements, then “Sustain the Gains”

©2006 Aspen Technology, Inc. All rights reserved

Holistic Approach to Capturing and Sustaining EnergySavings

QuestionsDecember 7th, 2006