HOI HOP 110KV SUBSTATION - World Bankdocuments.worldbank.org/curated/en/... · HOI HOP. 110kV...

44
HOI HOP 110kV Substation _______________________________________________________________________________ Environmental Management Plan 1 NPC NORTH POWER CORPORATION Electric Network Project Management Board ------------------------------- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT : HOI HOP 110KV SUBSTATION PREPARED BY ELECTRICITY NO II JOINT STOCK COMPANY Hanoi, 19 April, 2012 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of HOI HOP 110KV SUBSTATION - World Bankdocuments.worldbank.org/curated/en/... · HOI HOP. 110kV...

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 1

NPC

NORTH POWER CORPORATION

Electric Network Project Management Board

-------------------------------

ENVIRONMENTAL MANAGEMENT PLAN

(EMP)

SUBPROJECT:

HOI HOP 110KV SUBSTATION

PREPARED BY

ELECTRICITY NO II JOINT STOCK COMPANY

Hanoi, 19 April, 2012

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb406484
Typewritten Text
E3035 v14

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 2

NPC

ABBREVIATIONS

CPC Commune People’s Committee

DEP Distribution Efficient Project

ECOP Environmental Code of Practice

EIA Environmental Impact Assessment

EMF Electromagnetic Field

EMP Environmental Management Plan

EVN Electricity of Vietnam

GOV Government of Vietnam

HH Household

HV High voltage

LV Low Voltage

MOIT Ministry of Industry and Trade

MONRE Ministry of Natural Resources and Environment

MV Medium Voltage

NGO Northern Grid Company

NPC Northern Power Corporation

OHL Overhead Line

PAH Project Affected Household

PCBs Polychlorinated Biphenyls

PMU Network Project Management Unit (under the NPC)

PPC Provincial People’s Committee

ROW Right of Way

WB World Bank

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 3

NPC

TABLE OF CONTENTS

I. Introduction ..................................................................................................................... 3

II. Policy, regulation and institutional frameworks ........................................................ 3

2.1. Governmental regulations ............................................................................................. 3

2.2. WB’s safety policy .......................................................................................................... 4

III. Description and Scope of work ................................................................................... 4

3.1. Target and Scope of work ............................................................................................. 4

3.2 Description ...................................................................................................................... 4

3.3. Scope of work: .............................................................................................................. 6

3.4. Main work volume: ....................................................................................................... 8

3.5 Major activities before and during construction .......................................................... 10

3.6. Progress .......................................................................................................................... 12

IV. Summary of natural and environmental conditions of the project site ................... 12

V. Potential impacts ............................................................................................................ 18

VI. Environmental management plan .............................................................................. 18

6.1. Mitigation measures .................................................................................................... 18

6.1.1 Design and land acquisition period ............................................................................. 18

6.1.2 Mitigation measures in the construction period ........................................................... 18

A. Environmental regulations ....................................................................................... 18

B. Mitigation measures for specific impacts of sub-project: ........................................... 24

6.2 Environmental monitoring plan and reporting system ................................................ 25

6.2.1 Environmental monitoring plan ............................................................................... 25

VII. Implementation of EMP and capacity development ................................................ 28

7.1. Implementation responsibility of the Environment Monitoring Scheme (EMS) ........ 28

7.2. Capacity Development Plan .......................................................................................... 28

Table 7.3. Projected schedule and content of trainings on Environment Monitoring ...... 29

Table 7.4. Estimated expenses for subsequent training courses ........................................ 29

Table 7.5. Reporting procedure ........................................................................................... 30

Table 7.6 . Estimated expense for implementing EMS (VND) .......................................... 30

VIII. Information reference and publication .................................................................... 31

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 4

NPC

I. Introduction

Vinh Yen City is the political-cultural center and the key economic region of Vinh Phuc

Province. Analysis of current power supply and electric network, and demand for subloading

of Vinh Yen City in particular and Vinh Phuc Province in general, along with neighbouring

regions indicate that the project “Hoi Hop 110kV substation” is necessary. Investment in this

project will solve the following issues: i) Fulfill analyzed and predicted sub-loading demand;

ii) Fulfill present and future power demand of sub-load; iii) Improve power quality and; iv)

Improve credibility and convenience in operation management.

Aware of the needs for this work, Vinh Phuc Province submitted its request to World Bank

(WB) for financing of this minor project. “Hoi Hop 110kV substation” is among the many

minor projects in Phase I of EVN’s Distribution of Electricity Project (DEP) financed by WB.

This minor project will be implemented in Hoi Hop, Vinh Yen City, Vinh Phuc Province.

Hoi Hop minor project consists of the following activities: i) Constructing110kV sub-station

with 02 MBA, including the installation of 01 transformer of 110/35/22kV-63MVA; ii)

Constructing distribution controller, guardhouse and pump house and; iii) Furnishing SCADA

system to connect with control and regulation centers. These activities may cause negative

impacts to the environment and local community before, during, and after construction and

operation.

To ensure identifying and mitigating potential negative impacts during implementation and

complying with WB’s Environmental Assessment policies - (OP/BP 4.01), Hoi Hop minor

project’s Environmental Management Plan (EMP) was prepared in compliance with

instructions in DEP’s Environmental Management Framework (EMF). The plan, including:

description, policy frameworks, regulations and technical environment standard to be applied,

potential negative impacts and proposed mitigation measures will be implemented in pre-

construction, construction and operation phases. EMP will include Environmental Code of

Practices (ECOP) integrated in tendering and contract documents and environmental

supervision.

The Government of Vietnam stipulates the preparation of Environmental Impact Assessment

for this subproject. The EIA of the subproject has been prepared and approved by Vinh Phuc

Provincial People Committee.

II. Policy, regulation and institutional frameworks

2.1. Government Regulations:

The following laws and regulations are applied for subproject:

- Environment Protection Law 52/2005/QH11 passed by the National Assembly dated

on 29/11/2005 regulating responsibilities of individuals and organizations regarding

environmental protection.

- Law on Forest Development and Protection No. 29/2004/QH11,

- Law on Cultural Heritage No. 28/2001/QH10,

- The Law on Water resources no. 08/1998/QH10 dated 20 May 1998.

- Government Decree N0 80/2006/ND-CP dated August 9

th, 2006 by Vietnamese

Government on detail regulations and guidance on the implementation of some

Articles of the Environment Law.

- Decree no. 29/2011/NÐ-CP dated 18 April 2011 regarding regulations on strategic

environmental assessment, environmental impacts assessment and environmental

protection commitments.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 5

NPC

- Circular no. 26/2011/TT-BTNMT dated 18 July 2011 detailing some articles of

Decree no. 29/2011/ND-CP dated 18 April 2011 regarding regulations on strategic

environmental assessment, environmental impacts assessment and environmental

protection commitments.

- Decree 106/2005/ND-CP dated 17th

August 2005 on detailed regulations and guidance

on implementation of some Articles of the Law on Electricity related to safe protection

of high voltage networks.

- Decree 81/2009/ND-CP dated 12th

October 2009 on revision and addition of some

Articles of Decree 106/2005/ND-CP dated 17th

August 2005 on detailed regulations

and guidance on implementation of some Articles of the Law on Electricity related to

safe protection of high voltage networks.

- Circular no. 12/2011/TT-BTNMT dated 14 April 2011 regarding the management of

hazardous wastes.

- National Technical Regulations: QCVN01:2009/BYT - National technical regulations

on quality of drinking water; QCVN02:2009/BYT - National technical regulations on

quality of domestic water; QCVN08:2008/BTNMT - National technical regulations on

quality of surface water; QCVN09:2008/BTNMT - National technical regulations on

quality of groundwater; QCVN05:2009/BTNMT - Air quality – Standards for ambient

air quality; QCVN06:2009/BTNMT - Air quality – Maximum allowable concentration

of hazardous substances in the ambient air.

- EVN Guidance no. 2623/CV-EVN – KHCN&MT, dated 28 May 2007 regarding the

management and pollution prevention and exposure to PCBs.

2.2. World Bank Safeguard Policy

Environmental screening in accordance with the criteria described in the Environmental

Management Framework of DEP sub-project was conducted and the results showed that the

sub-project must apply the WB policies on Environmental Assessment (OP 4:01),

Involuntary Resettlement Policy (OP 4.12) and information disclosure policies of

the WB. The implementation of Social Safeguard Policies (OP 4.12) will be discussed in a

separate report.

III. Description and Scope of work

3.1. Target and Scope of work

“Hoi Hop 110kV Substation” minor project will serve the following purposes:

a) Constantly supplying and ensuring power quality in sub-loads of Southern Vinh Yen

urban area, Vinh Yen City.

b) Supplying power for sub-loads under construction in socio-economical cluster of Ho

Thinh - Tam Duong County, guild cluster and hostel quarter in Dong Van Commune,

Yen Lac County.

c) Supplying power for plants in Hoi Hop Industrial Zone.

d) Reducing performance loss, improving power quality and safety coefficient for

regional power network.

e) Redistributing power line to avoid overload in current supplies.

3.2 Description

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 6

NPC

The minor project is implemented on an overall area of 4.127.5 m2 in Hoi Hop District,

Northeast of Vinh Yen City, Vinh Phuc Province. The location of 110kV substation is as

follows:

- North: neighboured by infrastructure area planned for Hoi Hop Industrial Zone

- South: margined by national route 2 by-pass, Vinh Yen City

- East: neighboured by infrastructure area planned for Hoi Hop Industrial Zone

- West: margined by planned road 24m in width.

Implementation area for the project is illustrated as follows (Image…):

3.3. Scope of work:

- The 110kV substation is implemented on a rectangle of 62m x 58m, with The operator

/ distributor room located in the southeast and the gate directly connecting access road

to the substation.

- The 110kV distributor ground located in the south.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 7

NPC

- The distributor ground is surfaced with a 7-cm layer of M100 concrete, then overlaid

with a layer of pebble gravel with Dmax = 4cm or a 10-cm layer of track ballast

dimension of 4x6.

Occupied area: 4,127.5m2

Fenced area: 3,790m2

Access road area: 337.5m2

Excavated dirt volume: 760 m3

Backfilled dirt volume: 7,496 m3

Access road backfilled dirt volume: 395 m3

Gate and fence

- The gate consists of a frame and gate leaves synthesized steel. The main gate is 4m in,

and secondary gate is 1 m in width, both painted to prevent rust.

- A brick fence of 25m in length is built on pebble dirt-barrier, with ferro-concrete

pillars in each 2.5m interval. The fence is 2m in height.

Internal routes

- Internal routes are 4m in width, and 5m in radius curvature.

- The route surface is ≥ 5 cm lower than station base. Lengthwise incline i= 0.01; cross

incline i = 0.01.

Access road

- Access road is from national route 2 by-pass, 38m in length, 4.5m in width.

Lengthwise incline i= 0.01; cross incline i = 0.01; radius curvature of 6m.

- Subbase structure:

Subbase rock, 150 in thickness.

Piled pebble 4x6, 2x4 rolled at 250 in thickness.

Transformer foundation

- Foundation designed for transformers 110/35/22kV - 63MVA, total mass of 100 tons,

including 20 tons oil. The transformer is placed directly on bearer.

- Foundation composed of M200ferro-concrete, attached to carrying rail. Foundation

depth -0.6m, dimensions 5.0 x 3.0m.

- Oil collecting pit dimensions 10.0 x 8.0m, depth from 0.2m to 0.35m. Cladding wall

made of M50 brick. Pit bottom composed of M150 concrete, 100 in thickness, inkling

to outlet tube side. Stone of 4x6 dimensions are piled on the pit bottom, to make 0.25

m in thickness. Breakdown oil (if any) shall be collected to oil pit and follow outlet

tube to breakdown oil pit at the corner of the station.

Pillar

- Concrete centrifugal pillar with height H = 20m and 14m to barricade line.

Bearing pole, column foundations

- Pole foundation: M200 ferro-concrete socket foundation; padded with M100 concrete,

100 in thickness.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 8

NPC

- Column foundation: one-piece bed plate M200 ferro-concrete, padded with M100

concrete, 100 in thickness. Troughing and bearing for connecting shaft systems

- Troughing wall and base crossing under road is made of M200 ferro-concrete, 200 in

thickness. Troughing is covered with interlaced M200 ferro-concrete plates, 60 in

thickness for troughing inside distribution station, 150 in thickness for troughing

crossing under road.

Distribution Controlling Chamber

Distribution Controlling Chamber is located at the corner of the station. Designed in 1

storey, the dimensions are (30.2 x 9.5)m, height 4.2m:

The chamber is built in reinforced concrete frame, wall built in M75 solid brick and

M50 cement.

Foundation: designed in ferro-concrete, foundation throat built in M75 brick and M50

cement, braced at altitude 0.00, backed by ballast sand.

Roof: U100 main bar system to support gypsum roof of 600x1200 and 9mm in

thickness.

Roof in monolithic joisted floor M200 ferro-concrete structure including systems of

main beam and two-span beam of 4.20m and 9.50m, continuous beam system running

along the structure’s length, ferro-conrete plates of 80 in thickness buried at 4 corners.

Guardhouse

Guardhouse is located at the gate, dimensions 4.0x4.0m, with foundation, brick wall,

deck roof of M200 ferro-concrete made at-the-spot, resisting temperature by Ausnam shingle.

Bathroom

Bathroom is located near fire extinction basin, dimensions (4.0x2.5) m, with foundation,

brick wall, deck roof of M300 ferroconcrete made at-the-spot.

Water Supply System

Water used for utility and fire extinction is taken from water treatment ward supplied by

borehole inside the station.

Water Drainage System

There is a system of manhole and concrete conduit suitable with inclination and layout

of to serve the drainage requirements of the station. Rainwater is collected to sideroad

manholes, irrigated along concrete conduit dy=300 and dy=500 to dranaing channels and to

drainage system of the station.

Breakdown oil tank

Breakdown oil tank, 32m3 in volume, can collect all the oil of a 63MVA transformer.

Wall and base are made of M200 ferro-concrete, 150 in thickness.

SCADA system

To perform the unmanned function in the future, SCADA system at Hoi Hop 110kV

Substation is facilitated with suitable communication gateway that ensures availability to connect

with control center at Vinh Phuc. Privileged protocols are IEC60870 and IEC61850.

Besides, the control system of Hoi Hop 110kV Substation is also facilitated with gateway to

connect with control center at Vinh Phuc and Northern Regulating Center A1 under communication

procedure of IEC 60870 for current option. At the station’s computer control center, data will be

ready as per protocol IEC 60870 to transmit to control center at Vinh Phuc and A1 to serve the

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 9

NPC

SCADA function. Meanwhile, alternate options between SCADA and Substation will be performed

by software (including overall alteration of control model for the station, lock alteration of control

model for each shaft).

3.4. Main work volume:

Major items and volume

Construction items

- Construct 110kV gate pole foundation and lighting pole

- Process and erect 110kV pillars and beams

- Construct foundation for 110/35/22kV transformers.

- Construct bearing foundation for 110kV switch equipment.

- Process and erect pole foundation for 110kV switch equipment.

- Construct outdoor troughing.

- Construct distribution controlling chamber, guardhouse, pump house.

- Construct fire extinguishing system for 110/35/22kV transformers.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 10

NPC

Construction volume

No Item Unit Amount Note

A Grading – All layout

1 Grading sand m3 8,300

2 TC barricading wall (2.3m÷2.8m in height) m 140

3 Barricading wall 2m in height m 140

4 Gate 4m + 1.5m Set 1

B Outdoor pillar, pole foundation, beam

1 Substation foundation Unit 1

2 Concrete centrifugal pillar T20C Pillar 2

Pole foundation MC-2 Unit 1

3 Concrete centrifugal pillar T20C Pillar 2

Centrifugal pole foundation MC-7 Unit 2

Arrestor Unit 2

4 Concrete centrifugal pillarT14C Pillar 2

Centrifugal pole foundation MC-7 Unit 2

5 Steel beam 9m XT9 Set 2

Beam cradle G11-14-1 và G11-20-1 Set 2 + 2

6 Lighting foudation + pillar Set 8

7 Bearing foundation 110kV Unit 4

8 Bearing foundation for 110kV disconnector Unit 18

9

110kV current transformer bearing pillar TD-27 Pillar 6

110kV current transformer pillar foundation Unit 6

10

110kV shunt transformer bearing pillar TD-27 Pillar 6

110kV shunt transformer pillar foundation Unit 6

9

Lightning-proof bearing pillar of 110kV TD-27 valve Pillar 3

Pillar foundation of lightning proof 110kV valve Unit 3

10 Lightning-proof bearing pillar of 72kV valve +

disconnector Set 1

Pillar foundation of lightning proof 72kV valve +

disconnector Unit 1

11 35/0.4kV auxiliary transformer bearing pillar Pillar 1

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 11

NPC

No Item Unit Amount Note

Pillar foundation of auxiliary transformers Unit 1

12 22/0.4kV auxiliary transformer bearing pillar Pillar 1

Pillar foundation of auxiliary transformers Unit 1

13 Switching equipment bearing Unit 2

14 Outdoor troughing system System 1

15 Outdoor interlaced troughing plate system System 1

16 Distribution chamber Chamber 1

17 Guardhouse Chamber 1

18 Fire extinguishing house Chamber 1

19 Breakdown oil tank Tank 1

20 Fire extinction basin Tank 1

21 Internal route system m3 208.2

22 External route system m3 142.5

23 Water & oil supply & drainage system System 1

24 M100 concrete m3 1,759

25 M200 concrete m3 52,451.2

3.5 Major activities before and during construction

The preparation work shall be carried out suitable for the construction progress,

weather characteristics and infrastructure of the construction area.

Utilization of vacancy areas within the limit of the station to arrange equipment

and material storages.

Camps shall be close to the construction site for facilitating the construction, life

activities and personnel mobilization.

Based on quantity of the construction and erection work, quantity of materials and

equipment, construction progress and etc., it is expected that the scale of

temporary works and storage/yard will be as follows:

Temporary storage/yard

Indoor storage

Building structures made from bamboo, Neohouzeaua, wood, wallboard roof.

Storage area: 50.0m2

In which:

Used to store cement: 35m2, goods storage standard: 1.6 ton/m

2.

Used to store construction tools 15m2.

Outdoor storage, camp

Total area: 100m2

In which.

Used to store steel: 30m2

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 12

NPC

Used to store formwork wood: 20m2

Used to fabricate steel: 50m2

Casting yard

Yard floor structure made from broken brick concrete M50 with the thickness of

100, dense compaction, cement mortar finishing M50 of 2cm in thickness.

Area: 50m2

Construction materials stock yard

Structure: levelling, compaction

Area: Use the available graded plan in the station.

Office room – medical room on site

Area 45m2

In which:

Used for site management and control room and meeting-room: 20m2

Used for healthcare: 15m2

Reception, security office: 10m2

Housing type with bamboo column and truss structure covered with fibro-cement

roof.

Temporary camp:

Structure: bamboo, neohouzeaua, leaves.

Living & accommodation area: 120m2

a. Construction component:

Earthwork

Excavate soild for the transformer foundation, pole foundation,column foundation,

house foundation, cable trough and etc. under the manual method.

Backfill with soil, compact the foundation soil under the manual method.

Concrete work

Concrete mortar shall be mixed by 250L-mobile mixer. Concrete shall be

manually placed. Concrete compaction is made by specialized roller combined

with manual way.

Precast concrete shall be focally placed at the concrete yard of construction unit.

Steel in concrete shall be shop-fabricated.

Installation of building structure

Equipment supporting shall be combined and manually erected by mannual way.

Masonry, plastering work

Mix masonry mortar, plaster by mobile machine with a capacity of 100 liters

Build and plaster manually

Transport materials manually.

b. Equipment installation component

Installation of 110kV transformer

The transformer, when transporting to the construction site, shall be brought in the

base. The correction and arrangement of declination by hydralic jack, winch,

pulley puli.

Install accessories of the transformer: high, medium, low-voltage input bushing,

cooling flanges, explosion vent, connection box and etc. by crane and manual

way.

Filter oil by special purpose machine

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 13

NPC

Complete grounding work and manually paint.

Installation of outdoor equipment

Before installing the equipment, it will be required to check, clean up and

transport to the right location. The installation of equipment supplies shall be

carried out in a manual way.

Install socket, accessories, stretch the earth wire, fillet weld manually.

Installation of indoor equipment

Transport the equipment to the house by using manual method combined with

pulley puli, jack.

Erect into the location and connect by manual method with pulley block.

Sources of materials and equipment and transportation

Sources of materials and equipment

Electric equipment and materials shall be imported completely as per order form

and imported to Hai Phong port and then transport to the station by special

purpose automobiles and trucks.

The 110kV transformer will be fabricated at home.

Column steel, galvanized beam shall be fabricated at home except for column

portion which is installed synchro with the equipment.

Electric material, construction materials shall be exploited at local market.

Transportation work

The construction materials will be transported to the construction site by land by

trucks.

3.6. Progress:

Planned progress is as follows:

- Develop investment plan: Feb 2012

- Develop technical design: Mar 2012

- Select erection contractors and material suppliers: May 2012

- Commence construction: Sep 2012.

- Finalize: Feb 2013

IV. Summary of natural and environmental conditions of the project site

Natural and environmental conditions

Preliminary description of natural and environmental conditions of the project site (e.g.

county of the project site) provincial project, scope of project. Provide important information

about environment, focus on terrain, status of land use, surface water environment,

underground water, air quality (short summary of information from EIS or project

commitment to implement established environmental protection)

Meteorology - Climate. Data provided by Vinh Yen Hydro-Meteorological Station (from

2007 to 2010), indicated that Vinh Phuc Province and project site is under tropical monsoon

climate, with typical hot and humid weather, and divided into two obvious seasons: rain and

dry season. The rain seaon ranges from April to September, and dry season from October to

March of the next year.

Terrain. Vinh Yen City has a typical midland terrain, with altitude of 10-50m over sea level.

Area of highest altitude is mountainous area northeast of Khai Quang District and lowest is

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 14

NPC

Dam Vac. Overall, the terrain tend to incline in northeast – southwest direction and is clearly

divided into 3 areas:

- Low mountain: gathered in north of Dinh Trung and east of Khai Quang counties, with

absolute altitude ranging from 50-260 m; this region has many high noncontinuous hills and

low mountains composed of mica schist, arkose and rhyolite.

- Low hill and antique silt steps: altitude of 10-50 m, lightly inclined and corrugated in south –

southwest direction, alternately inserted with small steps and slots; it includes the whole

central city and ends at hill areas of Mau Lam, Mau Thong hamlets of Khai Quang district.

- Delta and swamp: developed on neo silt deposit in the south, including residential quarters

and farmland of Khai Quang district and Thanh Tru commune; the terrain is lightly

corrugated, with altitude of 7.0-8.0 m, alternately inserted with pond, lake, rammer with good

free air.

Hydrologic conditions. The city has many lakes of different sizes, distributed evenly and are

important in regulating and reserving water. Vinh Yen City is within the basin of Ca Lo and

Pho Day rivers, but river concentration is low. Slow drainage caused overall waterclogged in

low areas. In dry season, water level drops dramatically, causing difficulties water usage for

utility and production.

Air environment. Observation and sampling resuls indicated that, in comparison with QCVN

05:2009/BTNMT regarding air quality of surrounding areas, all observed air is within limit of

standardized environment quality.

Surface water. Observation results indicated bound concentration of metals is lower than

standardized level allowed by QCVN 08:2008/BTNMT regarding surface water quality.

Analysis results of surface water environment quality indicated that surface water status in

project site could still receive treated exhaust. COD, BOD5 and NH4+ parameters indicated

signs of pollution, which is believed to be reserved from agricultural production activities.

Underground water. Survey results of underground water samples in project site indicated

that most concentrations of analyzed samples were lower than standardized levels allowed by

QCVN 09: 2008/BTNMT regarding underground water quality.

Soil. Observation and sampling at project site indicated that concentration of substances was

within allowed standards for industrial land standards. Soil environment status of project site

indicated that all criteria for heavy metals were within allowed limit of QCVN 03:

2008/BTNMT

Cultural and historical sites. At project site there was no famous cultural or historical relic

that was rated or complied with village custom.

V. Environmental impact assessment

Screening Question Yes No Remarks

1. Project's sitting:

Is the Project site adjacent to or within

any of the following environmental

sensitive areas?

No impact

Cultural heritage site X

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 15

NPC

Protected areas such as National

Parks, Nature Reserves,

Bioconservation areas, bird

yards, mangrove forest etc.

X

Wetlands X

Forests X

Estuaries X

Buffer zone of Protected areas X

Rivers and reservoirs

X

Canals and irrigation system X The existing ground elevation of station

location is 7.77- 8m and it will be

heightened to the elevation of 9.2

equivalent to NH2 bypass road elevation.

Such elevation heightening will result in a

difference of more than 1m which likely

causes flooding around the transformer

station area.

The terrain at the station is relatively flat

so surface water sources are mainly rain

water and irrigation water of interior field.

The proposed construction site of the

station does not encounter any river,

chanel, lake and pond so this does not

affect the water source.

.

Agricultural land X

2. Potential environmental impacts

Will the Project cause:

Encroachment on historical/cultural

areas

X

Encroachment on critical ecosystem

(e.g. sensitive or protected area,

national park, nature reserve etc....)

X

Disfiguration of landscape and increase

waste generation

Removal of vegetation cover or cut

down of trees resulted from clearance at

the sub-station and along ROW?

X The transformeer station is located on the

field land, mainly rice and crop fields.

There is a little impact during the

clearance for grading the station. No

perennials are available in the project area.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 16

NPC

Change of surface water quality or

water flows

X - At the Hoi Hop 110kV transformer

station, a 37m-long temporary road will be

provided across a small canal used to

irrigate interior fields. The chanel can be

filled and prevented its stream flow if

proper construction measure is not taken.

Increase water turbidity due to

run- off and erosion

X - Site leveling and construction of the

station, the station access road can result

in washing away soil, stone and gravel

into the surface water system in the

region;

- Impact on polluting the surface water at

the project area which is assessed

insignificantly can be mitigated.

Waste water from camping sites

is directly discharged to the

surface water resources or not?

X Temporary camping area shall be provided

with good drainage and rubbish collection

system, auxiliary works such as

bathhouse, sanitation toilet for workers’

use.

Construction waste is directly

discharged to the surface water

or not?

X Site levelling & grading and construction

activities can result in washing away soil,

stone and gravel into the surface water

system in the region.

Increase the dust level? X Dust is generated from soil excavation and

station site plan leveling work, especially

in dry season. Affected persons will be the

inhabitants living and working around the

project area.

- Dust is generated by means of transport

of materials and plants during the

construction of the Project. Affected

persons will be roadusers on the route of

construction material transportation at the

locality and on the NH2 bypass and

provincial road transporting materials and

plants.

- The Project will be constructed far from

residential and urban areas so air (dust)

pollution does not affect much the people

living in the Project area;

- The nearest residential area is 600m

away from the Project location so this

impact can be assessed at an average level

and can be mitigated.

Increase noise and/or vibration? X Due to equipment, material transportation,

means of transport of the Project, site plan

grading, pole erection and generator.

Permanent land acquisition X Permanently acquired land area: 3,790 m2

of agricultural land for the station area

which will be permanently acquired.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 17

NPC

Temporary land acquisition Temporary acquired land area: 337.5 m2

of agricultural land (for the part of

temporary road) with the acquired time

about 1 to 2 months.

During the construction of the transformer

station, the households who are in the

planning area but are not acquired their

land by the Project will still cultivate their

crops normally and crop productivity and

quality will not be affected.

Resetlement of households? If yes, how

many households?

X

Would the resettlement site is

environmentally and/or culturally

sensitive

X

Is there any risk of disease

dissemination from construction

workers to the local peoples (and vice

versa)?

X - Maximum proposed construction work

shall be in 2 months in which the station

construction only lasts about 1 month and

the remaining time is mainly for the

installation of equipment.

- Many local workers will be employed so

there are only 10 - 10 workers staying in

the temporary camping area;

- At the station area, auxiliary works such

as bathhouse, sanitation rest room will be

constructed.

- Wastes generating from the camp area

will mainly be solid domestic wastes and

can make inhygienic to the enivronment.

However, rubbish is mainly packings,

remaining food and etc. with a little

amount. Therefore, disease distribution

will be aslo limited.

Is there any potential for conflict

between construction workers and local

peoples (and vice versa)?

X - Contradiction can occur by the following

reasons of: difference in income, culture

and behavior. However, most of the

workers come from this region so there is

no big difference in culture and way of

living.

Are explosive and hazardous chemicals

used within the Project?

X The Project does not use chemicals and

explosives;

In the past, there was any accident

incurred due to landmines or explosive

materials remaining from the war?

X The Project area is the area which has

been inspected, cleared from postwar

bombs and mines and is used for

agricultural production.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 18

NPC

Will Project's construction cause

disturbance to the transportation in the

Project's site?

X Insignificant impact

- Transporation of materials and plants

will affect the normal traffic in the reion in

a short term;

- The transporation of materials from

Hanoi to the construction site in general is

limited so this does not overload the

transport system on the NH2 bypass and

relevant provincial road.

- An intersection between NH2 and access

to the construction site during the

construction will be high-risk locations in

terms of traffic safety because of

separation and integration from means of

transport in construction with main traffic

volume, especially vehicles of transporting

bulky equipment.

Project's construction will cause any

damage to the existing local roads,

bidges or other rural infrastructures?

X

Will soil excavation during Project's

construction cause soil erosion?

X

Will Project need to open new access

roads?

X According to planning map, Hoi Hop

110kV transformer station construction

location has been approved by Vinh Phuc

People’ Committee. A temporary road

connecting to NH2 shall be provided in

the north of the transformer station for the

construction. When industrial zone is

completed and put into operation, such

temporary road will be removed to follow

frontage road in the industrial zone. The

temporary road is of 38m in length and

4.5m in width. Pavement elevation is

suitable for the existing NH2 bypass.

Longitudinal gradient shall be i= 0.01;

road cross-section shall be i = 0.01; curve

radius is 6m. Its embankment structure:

subbase, thiclness of 150, placed riprap,

stone 4x6, natural subgrade.

Will Project cause fragmentation of

habitat of flora and fauna?

X

Will Project cause impact on air

quality?

X - Impact on the environment caused by

exhaust of means of transport during the

transportation of materials which shall be

covered against scattering will be

insignificant.

Will Project cause accident risks for

workers and community during

construction phase?

X - Reason: this can happen to workers or

people surrounding the Project area if

safety measures are not paid attention.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 19

NPC

Will Project generate hazardous wastes

including PCBs from the replacement of

transformers?

X - No oil having PCBs and toxic chemicals

will be used for the Project;

- The operation of the station will use

some chemicals available in such

equipment as battery, insulating oil, grease

oil and etc. These substances shall be

registered and managed in accordance

with regulaitons on management of

harmful waste in Vietnam in Circular

12/2011/TT-BTNMT dated 14/4/2011.

This work has been implemented in many

years at other stations of Electricity of

Vietnam and will be applied for the

Station Improvement Project.

Will Project cause risk to safety and

human health (electric and magnetic

fields, electric shock etc.)?

X - The electric line and transformer station

shall be designed in accordance with

specifications of the Standard ensuring

that EMF level (Electromagnetic Field) <

5 kV/m. The sub-project after completed

and put into operation will provide active

support to the local socio-economic

development and development of

handicraft and services industries;

Improve the quality of living for the local

people because power is supplied

sufficiently and stably.

VI. ENVIRONMENTAL MANAGEMENT PLAN

6.1. Mitigation measures

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 20

NPC

Social - environmental issues Mitigating measures Responsibilities

A. In the stage of pre-

construction

1. Affect on economic and social

living of people by temporary

and permanent land

acquirement.

- Survey the sub-project area carefully, consult the local people in order to uses

minimum land area and not resettlement.

- Compensate satisfactorily in compliance with regulations in the sub-project

Resettlement Plan

- Contractors

- PMU

2. Effect on flora by ROW

clearance.

- Inform affected households to get harvest of rice and crops before site clearance and

land using.

- Carry out construction after the harvest.

- Don’t cut the trees beside regulated scale.

- PMU +

Contractors

B. In stage of construction

1. Dust generation - Contractor is responsible for complying Vietnam regulations related to air environment

quality.

- Contractor ensures that dust arising will be mitigated and causes no inconvenience to

local people. Contractor also controls dust to remain a safety working environment

(such as use water sprayer, cover materials during transporting).

- Constructing materials need covering during transporting to avoid scatter.

- Places for material pouring and storing should be covered to prevent dust due to wind.

It’s necessary to consider the main wind direction and sensitive places such as schools

and residential areas before preparing places for material pouring and storing.

- Workers must use dust-mask in area with much dust.

- Contractor

- CSC

2. Air pollution - All means of transportation must comply with Vietnam regulations on controlling the

allowed exhaust limitation.

- Means of transportation in Vietnam must be usually checked and have “Certificate of

quality, technical safety and environmental protection” under Decision

- Contractor

- CSC

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 21

NPC

Social - environmental issues Mitigating measures Responsibilities

No.35/2005/QD-BGTVT;

- Don’t burn waste or constructing materials (for instance: asphalt, …) in the

construction site.

- Concrete-mixer should be far from people’s houses.

3. Noise and vibration - Contractor is responsible for complying with Vietnam regulations related to noise and

vibration.

- All means of transportation must have “Certificate of quality, technical safety and

environmental protection” under Decision No.35/2005/QD-BGTVT”; to prevent

excessive noise arising from unmaintained machines, if necessary, it’s required to carry

out measures to mitigate noise at suitable level including mufflers, dampers or set noisy

machines in noise protection areas.

- Avoid or mitigate traffic pass residential area as well as avoid material process in

residential area (such as cement mixing)

- Contractor

- CSC

4. Waste water pollution - Contractor is responsible for complying with Vietnam regulations related to waste

water emission into environment.

- Contractor

- CSC

5. Water drainage and

stagnation controlling

- Contractor must follow the detail design of water drainage system in construction plan

to prevent local stagnation or erosion of slide soil or areas easy to be erosive from the

rain water.

- Ensure the water drainage system always cleared.

- Remain status of areas not affected by constructing activities.

- Soil digging, pouring and leveling should be remained suitably to constructing standard

details, including sewerage installation, using plant to cover.

- Install stagnation controlling works at necessary areas to avoid flow containing mud

and soil affect on around water quality.

- If necessary, it’s required to dry constructing area (such as pole foundation, …). Water

- Contractor

- CSC

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 22

NPC

Social - environmental issues Mitigating measures Responsibilities

containing mud and sand when willing must be processed by measures of stagnation

controlling before emitted to river.

- Use diversion technique during construction to limit sediment disorder of water flow.

6. Manage material storage and

mine

- Priorly determine material storage in the approved detail technological design.

- Use constructing materials from local suppliers having license of constructing material

business and exploitation.

- Restore material storage area closed to natural condition.

- Contractor

- CSC

7. Garbage and harmful waste - Before constructing, contractor need prepare waste controlling procedure and process

(store, supply wastebasket, plan for cleaning up construction site and removing the

wastebasket,...) and comply with the process during construction.

- Before constructing, it’s required to have all necessary licenses related to waste

management of the sub-project.

- Measures will be taken to reduce littering behavior and negligence in handling all

waste. Contractor will supply wastebasket, container and means of garbage collecting

at necessary places.

- Garbage can be temporarily stored at appointed place approved by Construction

supervision Consultant (CSC) and related local authorities before being collected and

processed by local environmental sanitation unit. If the sub- project area does not have

the unit, harmless living solid waste can be burried.

- Wastebaskets or containers will be covered to prevent leaking out, impact of weather

and scavengers. Do not burn waste.

- Recycled materials such as boards for drainage works, steel, scaffold, wrapping, will be

collected and separated at the site from other emission sources to recycle, use for

leveling or sell.

- If not removed from the site, solid waste and constructing waste will be processed at a

given area approved by CSC and put into garbage management plan. In any cases,

- Contractor

- CSC

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 23

NPC

Social - environmental issues Mitigating measures Responsibilities

contractor has to process all of constructing materials inside the construction site.

- Used oil will be taken out of the site to the approved oil recycling company.

- Used oil, lubricant, cleaning material … from machine maintenance will be collected to

a tight suitable container and contracted with harmful waste processing and collecting

unit.

8. Effect on flora. - Contractor will prepare plan of site clearance and environmental flora restoration

according to current regulations for CSC approval. Contractor seriously complies with

the plan.

- Do not use chemical substances for clearance.

- Do not cut any trees unless it’s allowed clearly in clearance plan.

- If necessary, build temporary barrier to effectively protect trees need protecting before

starting any activities in the region.

- Contractor

- CSC

9. Traffic management - Before constructing, consult local authorities, public and traffic police.

- Impact on flow of means of transport should be put into construction plan before

approval. The roads, especially for heavy vehicles, need to consider to sensitive areas

such as schools, hospitals and markets.

- Install lighting system at night, if necessary, to ensure traffic safety.

- Set signals around construction site to facilitate traffic circulation, provide guidances to

different components of the work and provide safety instruction and warning.

- Use methods of traffic safety controlling including road/river/canal signals and flats for

dangerous warning.

- Do not transport materials in peak hours.

- Corridor for pedestrian and motor vehicles inside and outside of the construction site

need to be isolated with the site and can be approached easily, safely and suitably.

Install suitable signals at necessary places.

- Contractor

- CSC

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 24

NPC

Social - environmental issues Mitigating measures Responsibilities

10. Interrupt activities and

services

- Planned or unplanned interruption to services of water, air, electric and internet:

Contractor has to carry out consultation properly and prepare plan for unexpected

situations with local authorities about consequence of a detail broken or interrupted

service.

- Coordinate with related service suppliers (such as suppliers of water,

telecommunications, …) to set suitable construction schedules.

- Provide information to affected households on working schedule as well as planned

interruption (at least 5 days before starting activities).

- Avoid interrupt water supplying for agricultural area.

- Ensure to supply replaced water for affected people in case of the interruption lasts

longer than 1 day.

- Any damages for cable of current service systems will be informed to local authorities

and repair as soon as possible.

- Contractor

- CSC

11. Restore affected regions - Storage, scaffold and any temporary areas during constructing time of the project items

will be restored about landscape, drainage and flora.

- Start plant covering as soon as possible. Use plant suitable to native plant to grow and

restore natural topography.

- Do not use plant which is exotic or forbidden by functional agencies.

- Places where soil is digged and side of constructing spoil ground need to grow grass to

prevent erosion and landslide.

- All of affected regions will be made landscape and performed quickly necessary repair

works including making green space, roads and other affected regions.

- Restore all stretches of road damaged by the sub-project activities.

- Contractor

- CSC

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 25

NPC

Social - environmental issues Mitigating measures Responsibilities

12. Labour safety and public

safety

- Contractor must comply with all Vietnam regulations about labour safety.

- Prepare and implement action plan to cope with risks and urgent situations.

- Prepare urgent relief services at site.

- Train the workers about occupational safety regulations.

- Provide anti-noise labour tools for workers who use noisy machines.

- Set fence, barrier, and dangerous warning/restricted-zone warning around the

construction site to point out potential danger for people.

- Contractor will provide safety measures such as setting fence, barrier, warning signals

at dangerous positions such as constructing transformer foundation to avoid traffic

accident as well as other risks for people.

- Only permit trained workers to install, maintain and repair electrical devices.

- Turn off and earth exactly the distribution line having electricity before carrying out the

above work, or near the electric line.

- Comply with labour safety process when working above and working with electric

devices.

- Contractor

- CSC

13. Communications to local

public

- Remain contact with related local authorities and people; contractor will coordinate

with local authorities (leaders of ward/commune, village chief) to come to agreement in

plan of constructing activities at areas near sensitive areas or sensitive time (for

example religious festivals).

- Contact with public so that concerning parties can get information on activities in the

area, the sub-project status and sub-project implementation results.

- Follow public interests and required information such as the sub-project schedule

- Respond questions via telephone and text timely and correctly.

- Inform local people the construction plan, working schedule, service interruption,

- Contractor

- CSC

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 26

NPC

Social - environmental issues Mitigating measures Responsibilities

detour lines, temporary bus lines and destruction in suitable time.

- Provide technical document and drawing to public, especially draft construction area

and EMP in the construction site.

- Make notice boards at all construction site to give information on site manager,

environmental staff, health and safety staff, telephone number and information on other

contents so that affected people can express their interest and recommendations.

14. Chance Finds Procedures During construction, if contractor finds historical, cultural and religious monuments

including cemetery or individual graves, contractor will:

- Stop construction activities in revealed area;

- Localize and protect the area to avoid any damages or losses of movable objects. In

case of revealing movable antiques or sensitive monuments, assign a protector until

local authorities or Department of Culture and Information receive;

- Report to CSC, CSC is responsible for reporting in turn to local or state authorities who

are responsible for Vietnam cultural property (within 24 hours or sooner);

- Related local authorities or state agencies are responsible for protecting and isolating

the area before deciding the next principle.

- Decision of processing the findings is responsibility of authorities, may be including

arrangement change (such as when finding an important cultural monument or

archaeology that is unmovable), preservation, isolatation, restoration and rescue;

- If cultural region and/or monument with high value and its preservation is

recommended by specialists and requested by cultural monument management

agencies, NPMU need to change the design if necessary to meet the requirement and

peserve the region;

- Decisions related to management of the findings will be informed via texts by related

authorities;

- Constructing works can continue only when being licensed by local authorities who are

- Contractor

- CSC

- PMU

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 27

NPC

Social - environmental issues Mitigating measures Responsibilities

responsible for the safety of heritage.

C. In the stage of operation

1. Health and safety for

operators and local people

- Design to meet the international standards to protect human health (less than 3kV/m for

electric field and 05 microtesla for magnetic field at the edge if ROW).

CPC

2. Effect on birds - Install device of bird driving on the line or transmission tower. CPC

3. Risks of fire and explosion - Check periodically fire fighting tools.

- Held training about fire fighting works for operators.

- Build incident oil container at the substation.

CPC

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 28

NPC

B. Mitigation measures for specific impacts of sub-project:

Period Impact/Influence Mitigation measure

Construction Affect the traffic

at the connection

point between

temporary road

for the

construction and

NH2,

Plan construction activities for a period of the least

traffic volume. At the connection point, signs shall be

clearly marked.

Limit the time of obstructing traffic, arrange workers

for traffic guidance once a vehicle stops on the road to

load and unload materials and equipment.

Affect flooded

drainage by

heightening the

station foundation

bed.

Design and construct proper drainage systems inside

and around the transformer station to ensure that the

rain water does not cause flood for the surrounding

area.

Affect irrigational

canal in the interior

field when

constructing the

transformer station

and temporary road

for the

construction.

Use the waste stone/soil to fill and level the station

foundation. Protect loose material piles by covering

and making drainage paths surrounding such material

piles in order that the loose materials can not block the

flow of the drainage ditch. When constructing the

temporary road over small drainage ditch, it will be

required to level the plan, remove organic layer about

25- 30cm then place lean concrete and construct

revetment with rip-rap. Place concrete culvert pipe D =

500. Then, grade sand for road embankment and

prevent from blocking the canal flow.

6.2 Environmental monitoring plan and reporting system

6.2.1 Environmental monitoring plan

Impact Parameters

to be

monitored

Place of

monitoring

Equipment

method used

to monitor

Time/frequency

of monitoring

Cost Monitoring

responsibility

Construction period

I. Clearing

vegetation

cover or cut

trees

- Clearing

technique

- Solutions/

behavior to

trees after

cutting

-

Transformer

station

location

- At the place

of gathering

trees after

clearing or

cutting

- Observe - Every day,

from

commencement

to completion of

clearing work.

- Contractor

- Construction

supervision

consultant

II. Surface

water

quality,

Sediment

and erosion

- No carry

out

excavating

soil when it is

raining

- Not clear

plants

thoroughly

- Within the

precinct of

the station

- Surface

water source

near the

construction

area

- Observe - While and after

it rains heavily

- Contractor

- Construction

supervision

consultant

III. Dust, air - Dust level - At the soil - Observe - When it is - Contractor

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 29

NPC

Impact Parameters

to be

monitored

Place of

monitoring

Equipment

method used

to monitor

Time/frequency

of monitoring

Cost Monitoring

responsibility

pollution at the place

of loose

material piles

such as soil,

sand and etc.

- Loose

material

coverage

when

transporting

storage area

after

excavating

and at the

loose

material

storage

blowing hard - Construction

supervision

consultant

V. Noise - Noise level

- Response

from people

to the noise

by

construction

activities

- Areas near

the densely

residential

areas

- Hearing,

consulting

with local

people

- While

implementing

activities which

generate big

noise; When

receiving

complaints from

the people

- Contractor

- Construction

supervision

consultant

VI.

Construct

across small

water ditch

-

Construction

activities

- Small ditch

area 40m

away from

the station

- Observe - While

implementing

activities of

temporary road

construction

across the ditch

- Employer.

- Construction

supervision

consultant

VII.

Sanitation at

the

construction

place,

including

sanitation of

workers’

camps

- Rubbish,

waste water

at the

construction

area and

workers’

camp

- Workers’

camp must be

provided with

clean water

and detritus

pit, mobile

latrine or

other

sanitation rest

room ?

- At the

camp,

surrounding

the station

- Observe - Every week,

when carrying

out acceptance

- Contractor

- Construction

supervision

consultant

VIII. Safety

of workers

and people

- Accident - Works,

locality

- Consultation,

site diary of

contractor

- Contractor

- Construction

supervision

consultant

IX. Traffic at

the

connection

point

- Traffic

situation

Connection

point from

NH2 to the

station

Observe,. - While

implementing

activities

- Employer

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 30

NPC

Impact Parameters

to be

monitored

Place of

monitoring

Equipment

method used

to monitor

Time/frequency

of monitoring

Cost Monitoring

responsibility

between

temporary

road with

NH2

Operation period

X. Water

source

surrounding

the station

Flooding

situation

Area

surrounding

the station

- observe,

hearing from

public

consultation at

the locality

- Every week,

when carrying

out acceptance

- Employer

VII. EMP Implementation Arrangement and Capacity Building

a) During the process of detailed designing and bidding document preparation

During the process of detailed designing and bidding document preparation, the PMB shall be

responsible for including the EMS or certain suitable content of the EMS such as the

preventive measures or implementation responsibility of the contractor as an addendum

attached with the bidding document and contract with the contractor. Engineers responsible

for the detailed design shall refer to the findings in EIS and EMS in ensure that all

environmental issues have been taken into account in the final design.

When preparing the bidding document and contract, it is necessary that the

bidders/contractors receive sufficient information about their responbility and obligations in

implementing measures to minimise possible impact on the environment and ensuring their

compliance.

b) During the construction phase

The PMB shall hand over the work of supervising on a daily basis the implementation of

safety measures of contractors to the Construction Supervision Consultant and/or the site

engineer. According to the terms of reference for the Construction Supervision Consultant

included in corresponding Appendix, Construction Supervision Consultant and/or Site

Engineering shall be responsible for the following tasks:

- Confirming that the idemification to related parties who are influenced by the Project

and bomb and mine disposal have been completed before the commencement of the

construction phase.

- Closely monitoring the implementation of preventive measures during the construction

phase.

- Confirming the compliance of the contractor with the EMS, inspecting for any damage

caused by the contractor, and if necessary, making record and requesting the contractor

to indemnify/restore the original status of the construction site as stipulated in the

contract. Implementation of the contractor towards environmental safety shall be

included in the progress report of the mini-project.

Roles and responsibilities of related parties in the implementation of EMS is indicated in the

below table:

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 31

NPC

Role Responsibilities Organization

Project Owner - Ultimately responsible for overall project management,

including environmental management.

NPC

Environmental

Officer - Specific responsibility and point of contact for

environmental issues.

PMU

Project

Implementation

and management

Agency

- Responsible for coordination and management of

overall project implementation, including guiding and supervising implementation of the EMP.

- Planning and implementation of environmental

management activities during construction

- Coordinating with other parties in relation to environmental management activities.

- Carrying out internal monitoring and supervising

- Supervising and providing budget for monitoring activities.

- Reporting on environmental information to concerned

parties

PMU

Project Operator - Responsible for operation of the project including

operation stage environmental management and monitoring activities.

NPC

Consultant - Responsible for preparation of EMP documentation.

Contruction

Supervision

consultant

- Responsible for supervision of civil works contractors

during construction, including implementation of

environmental management activities under the EMP

Supervisors

of

PMU

Construction

Contractor

Responsible for construction works and following

contractor specifications outlined in the EMP. This includes:

- Take actions to mitigate all potential negative impacts in

line with the objective described in the EMP.

- Actively communicate with local residents and take actions

to prevent disturbance during construction.

- Ensure that at least a staff is assigned to monitor EMP

compliance during the preconstruction and construction

periods.

- Ensure all the construction activities having sufficient

documents from the related organization.

- Ensure that all staff and workers understand the procedure

and their tasks in the environmental management program.

- Report to the PMU on any difficulties and their solutions

- Report to local authority and PMU if environmental

accidents occur and coordinate with agencies and keys

stakeholders to resolve these issues

Contractor

chosen by

PMU

7.2. Capacity Development Plan

Upcoming training plan includes:

Training programme of EVN: Internal training courses on environment

monitoring at the site and methods of reporting on environmental issues of the

Project as a part of the biannual and annual Report. The programme also includes

trainings on how to surmount unwanted influence on the environment, which turns

out different from the forecast of the EMS Report.

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 32

NPC

Training programme of Northern Power Corporation: Training programme of

NPC for employees of local power companies and local residents involves:

Training on labour safety: Periodical training on the safety and maintenance of electrical

grid;

Training on methods of monitoring and reporting on EMS implementation for related

parties in provinces and districts involved in the Project. These trainings will also provide

guidance on collaboration with the community in terms of environment monitoring.

Training on Monitoring of Environment and Hazadous Waste Management

Table 7.3. Projected schedule and content of trainings on Environment Monitoring

No. Description Frequency

Taken charge of by EVN

1 - Environment monitoring at the construction site,

periodical reporting on environment to NPC and WB,

other work relating to environment monitoring for the

Project.

- Every two years.

Taken charge of by NPC

2 - Training on the safety and maintenance of the

transmission line and stations

- Annually

3 - Training on environment and dangerous wastes

monitoring for the transmission line and stations

(collaborating with EVN)

- Annually

4 - Methods of monitoring and reporting on EMS

implementation within the scope of work of the

Distribution Efficiency Project (DEP).

- Annually

Table 7.4. Estimated expenses for subsequent training courses

No. Training Expense (Vietnam Dong)

CONSTRUCTION PHASE

1 Annual training of

EVN for all of its

divisions

Included in the operational expense of the Group’s Divisions.

NPC shall bear the travelling and accommodation expenses of

its participants.

3 participants from the PMB of NPC.

3 persons x 2 days x VND3,000,000/per capita =

VND18,000,000

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 33

NPC

2 Workshop to share

experience in EIS

preparation EMS

implementation

Included in the operational expense of the Group’s Divisions

2 persons x 2 days x VND5,000,000/per capita =

VND20,000,000

3 Training on EMS

implementation

2 participants from High Voltage Power Network Company

2 persons x 2 days x VND5,000,000/ per capita =

VND20,000,000

Total expense for the

construction phase

VND58,000,000

OPERATION PHASE

4 AMB’s training on

labour safety

(normally conducted

by the local high

voltage branch)

Included in the operational expense of High Voltage Power

Network Company

6 persons x 1 day x VND1,000,000/ per capita x 20

years of the Project cycle= VND120,000,000

Total expense for

the Project cycle

VND178,000,000

7.5. Reporting procedure

Responsibility and frequency of reporting the implementation of EMS is indicated in the

below table.

No. Reported by Reported to Reporting frequency

01 Contractor to the investor Project

Management

Board (PMB)

Once before commencing the

construction and on a monthly basis

afterwards

02 Construction superviser (cum

environment monitor)

PMB Monthly

04 Community monitor (if any) (nếu có) PMB At the time of complaint

05 PMB EVN Quarterly

06 EVN WB Biannual

Table 7.6 . Estimated expense for implementing EMP (VND)

No. Item Construction Operation (with a 20-year-cycle)

1 Preventive

measures

This amount is included in

the contract signed with

contruction contractors

This amount is included in the

operational expense of High

Voltage Power Network Company

2 Observation

expense incurred

This amount is included in

the operational expense of

This amount is included in the

operational expense of the authority

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 34

NPC

for technical

supervision of

PMB

the PMB assigned to implement the Project

3 Expense for

capacity

development

58,000,000 120,000,000

SUB-TOTAL 58,000,000 120,000,000

This amount is included in the

operational expense of the authority

assigned to implement AMB’s

Project

TOTAL VND178,000,000

* Expenses for preventive measures during the contruction and environment monitoring

conducted by Construction Supervision Consultant are included in the corresponding

contruction/supervision contracts.

VIII. Information reference and publication

In the preparation stage for the project (2010-2011), the following activities have

been realized:

Activity 1: Enquiring and discussing with the local authority about the place of the

transformer station.

Activity 2: Location surveying and investigation, making Environmental Impact

Assessment and plan for environment control.

Activity 3 : Organizing community consultation.

The meeting with the local people was held at Ho Hop Ward, Vinh Phuc Province. The

Investor and the Consulting Company held the meeting to get their opinion of for the

Environment Management Plan Project. The Investor and the Consulting Company Project

explained to the people on the following main issues:

- Presentation of the project: the site for the construction of the Transformer Station and

the need to build the above-mentioned projects;

- Possible impacts on the environment caused by the project;

- Measures to diminish the impacts.

The mass representatives invited to attend the consultative meeting consisted of: 16

households representing the affected households, representatives of the local authority, of

mass organizations and local electric power office, of three households whose land will not be

taken back but they are cultivating crops on the land around the area of the station.

Problems concerning environmental impacts worried by the consulting households comprise:

- The Hoi Hop 110kV Transformer Station has to build a temporary road about 40

meters long passing through a small canal for the irrigation of the rice fields. What measures

to be taken so as not to fill and block the flow of this canal?

- Is the building of the Transformer Station likely to cause pollution to the surface water

of this canal due to the flushing of earth, stone and raw materials into this source of water?

- The raising of the foundation of the station to a height of 9,2 meters is different with

the present level for about 1 meter, will its cause flood to the surrounding areas?

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 35

NPC

- The building of the temporary road linking with Highway 2 for the construction of the

station creates functions that will be high-risk sites for traffic safety. Has the Investor any plan

or measure to avoid the risks?

- During the period of construction of the station, will the households in the planning

area whose land is not taken back by the project be able to cultivate their crops normally?

- Will the project create toxic wastes?

- The compensation money will be paid according to current regulations. However, in

this area, there are constant transfers, and buying and selling of land, it is requested that the

compensation money be changed depending on the time when the compensation is made.

The Investor has the following feedbacks:

- Reasonable construction measures would be taken when the temporary road is build

such as leveling the ground and dredging the vegetal layer for about 25-30 cm deep, then

pouring lining concretes and building embankments along both sides of the canal with rocks.

Laying concrete conducts of D= 500 for normal flow of water. After that, leveling it with sand

to make the foundation of a side way so as not to block the flow of the canal.

The raising of the foundation of the station to a height of 9.2 meters, different with the present

level of about 1 meter, with not cause flood to the surrounding areas because a design plan

has been made for building a proper system of sewerage inside and around the transformer

station.

- Planning construction activities for the time when there is the least traffic flow. Clear

noticing boards will be posted at junctions.

- Having plans and measures to avoid accidents and risks at the sites of junctions with

Highway 2 such as limiting the time of traffic hindrance, posting workers for traffic guidance

whenever there is a vehicle stopping temporary on the road for loading and unloading

materials and equipment.

- During the period of construction of the transformer station, the households in the

planning area whose land is not taken back by the project could continue to cultivate their

crops normally; the productivity as well as the quality of their crops would not be affected.

- The project does not create any toxic wastes.

- The compensation money proposed at the meeting is provisionally calculated

according to current regulations and could be changed at the actual time of project

compensation.

- The building of the Transformer Station shall have certain influences on the locality.

The Investor and the construction contractor shall have measures to positively reduce the

influences caused by the project.

Activity 4: Reviewing and adjusting the Plan for Environment Control in line with the

opinions contributed.

Activity 5: Disclosure of the EMP.

The PMU will disclose the EMP at the Peopele’s Committee of Hoi Hop Ward, Vinh Yen

City, Vinh Phuc Province before the appraisal of the DEP project.

The EMP copies in Vietnamese and English will also be sent to the Vietnam Development

Information Center at 63 Ly Thai To street, Hanoi City for information disclosure.

The EMP copies in English will also be disclosed at the InfoShop of the World Bank in

Washington DC.

Activity 6: Community Reference in the process of establishing the Project

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 36

NPC

In the Project establishing Stage, independent environmental consulting specialists shall be

hired to supervise the realization of EMP and collaborate with the Investor to organize the

reference of opinions of the administration, non-governmental organizations and the

households affected by the realization of the EMP of the Project. The collected opinions (if

any) shall be conveyed to the Invector. After that, the Invector would collaborate with other

invectors in order to realize satisfactorily the EMP or update this Plan for Environment

Control (if necessary).

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 37

NPC

APPENDIX 1

Map of the site, diagram and images of the actual state of the site where the project is to be

realized

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 38

NPC

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 39

NPC

APPENDIX 2

Summary of consultative information of the community on the environment

HOI HOP 110kV Substation

_______________________________________________________________________________

Environmental Management Plan 40

NPC

No. Small project Place where the

consultation

took place

Time and

date

Number of

participants, among

them how many are

women

List of representatives of

local authority and

households taken part

Summary of problems and concerns discussed/

proposed

Hoi Hop

110kV

Transformer

Station

Hoi Hop Ward

People’s

Committee

8 a.m

11/10/2011

26 persons, among

them 7 women

Mr. Nguyen Tuan Hai

Vice-Chairman

Mr. Phung Quang Duc

Cadastral official

Mr. Phung Van Chien

Vietnamese Fatherland

Front

Mrs. Nguyen Thi Loan

Head of Women’s

Association

19 households (among

them 16 are affected; 3 are

in the planning area)

- Temporary road passing through the

irrigation canal. Measures to be taken to avoid the

blockage and prevention of the flow of the

irrigation canal.

- Dangers causing pollution to the source of

surface water.

- The raising of the station foundation causes

floods to surrounding areas.

- The junction between Highway 2 and the

sideway causes high risks for traffic safety.

- Is the cultivation of crops affected?

- Dangers of creating toxic wastes.

- Compensation money (price)

Plan “TBA 110kV Hoi Hop”

________________________________________________________________ Environnment Management Plan 41

NPC

APPENDIX 3

TOR FOR CONSTRUCTION SUPERVISION CONSULTANT

Overview

The Construction Supervision Consultant will be the provider of engineering services

(“Services”) to ensure the effective implementation of the Sub-project EMP.

Scope of Services:

General services as provided by the Construction Supervision Consultant are checking and

inspecting construction activities to ensure that the mitigation measures set forth in the Sub-

project EMP shall be accurately taken and adverse impacts on the environment shall be

mitigated.

On behalf of PMU, the Construction Supervision Consultant shall fulfill the following tasks:

- Execute site inspection on a regular basis;

- Consider the implementation situation of environmental protection measures stated in the

EMP and Contract Documents;

- Consider efficiency of environmental mitigation measures and environmental

implementation of the Project;

- If necessary, take account of acceptability in terms of environmental aspect of

construction method (for temporary and permanent works), relevant design plannings and

submittals. When necessary, the Construction Supervision Consultant shall look for and

recommend the least impact plan on the environment in consultation with the designer, the

Contractor and PMU;

- Appraise the survey results about any nonconformity to the environmental quality and

efficiency of remedial measures; and

- Provide audit results to the Contractor’s site superintendent in accordance with

nonconformity procedure set forth in the EMP;

- Instruct the Contractor to execute the remedial actions within the prescribed schedule and

carry out additional supervision if necessary, in accordance with requirements and

sequence of the Contract in case there are any nonconformities and complaints;

- Instruct the Contractor to implement actions to mitigate impacts and comply with the

EMP procedures as requested in case the nonconformity/inconsistency is identified;

- Instruct the Contractor to stop the actions which cause adverse impacts and/or the

Contractor’s failure to implement requirements of the EMP / carry out remedial actions.

- For the contracts, it will be required to set forth EMP on site (SEMP), the

Construction Supervision Consultant shall consider the last time and make a

recommendation via all the environmental plans at site which are likely to affect the

environment. This task includes but not limits to: dredging areas, borrowed pits and

dumping site areas, camping area of workers. The Construction Supervision Consultant

shall consider and approve SEMP as submitted by the Contractor. If finding that these

plans do not comply with the EMP, EIA or RAP, the Construction Supervision Consultant

shall co-ordinate with PMU and the Contractor to propose a reasonable solution.

- Settlement of complaints: The complaints about environmental violation such as noise,

dust, traffic safety and etc. from the local people will be received by the Contractor’s site

staff. The site superintendent or his deputy of the Contractor and the Construction

Plan “TBA 110kV Hoi Hop”

________________________________________________________________ Environnment Management Plan 42

NPC

Supervision Consultant shall have to settle and achieve the solution for such complaints.

The Construction Supervision Consultant shall be provided with a copy of such

complaints and certify that these complaints are settled by the Contractor in a proper

manner, which is similar to the related matter as identified in the site inspection.

- Certification of monthly payment: The Construction Supervision Consultant shall

certify monthly payments for the related activities on the environment performed by the

Contractor.

- Report: The Construction Supervision Consultant shall prepare the following

written reports:

o Report on nonconformities every two weeks

o Report on monthly summaries including issues and main findings from review

and construction activities

o To the end of the Project, the Construction Supervision Consultant shall

prepare a final report which summarizes main findings in its work, a number of

violations, solution and etc. as well as provide consultations and guidance’s on

the implementation form of such tasks in future.

Plan “TBA 110kV Hoi Hop”

________________________________________________________________ Environnment Management Plan 43

NPC

APPENDIX 4

Appendix………Illustration form for the inspection report of the realization of the Plan

for Environment Control

(Applied to the monthly report of Construction Inspection Consulting to be sent to the Board

of Management of the Project)

Name of the Project:

Place of the Project: Province:

District:

Commune/District town:

Construction Inspection Consulting: pull name

Date of report:

No Parameter Assessment of the

reflections of the

inspection end the

community

Remark/

Petitions

During the time of executing

1 Muddy surface water and land erosion

2 Noisy level around the site and surrounding

population areas

3 Dust

4 Solid waste and the clearance of the site after

execution

5 Control of sanitary and safety conditions for the

workers

6 Traffic disorder

7 Damages to the roads

8 Application of safety measures

9 Control of building materials

10 Control of unused earth and stones

11 Other environmental problems

Operation stage

12 Maintenance of the passage way

Appendix 5

Illustration form for the inspection report of the realization of the Plan for Environment

Control (Applied to the reports of the contractor)

Name of the Project:

Place of the Project:

Name of execution unit:

Initial report or monthly report of the Project:

Plan “TBA 110kV Hoi Hop”

________________________________________________________________ Environnment Management Plan 44

NPC

Date of report:

No Impacts Reduction measures

realized

Remark

Construction stage

1 Water surface pollution

2 Noises and vibrations

3 Land erosion

4 Air pollution

5 Impacts on agricultural production due to the

temporary requisition of Farmland

6 Traffic disorder

7 Damages to the existing roads

8 Solid waste from earth digging

9 Control of unused earth

10 Impacts on the environment caused by

environmental workers

11 Contradictions between the workers of the

construction works and the local people

12 Health and safety

Name of report maker:

Position:

Address:

Telephone: