Historical Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
Peter Wong, ISO New EnglandPower Supply Planning Committee MeetingJune 4, 2007
Agenda Item 1.1.2
PSPC Meeting 229
June 4, 2007
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 2
Historical data presented at the April 19, 2007 PSPC meeting
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 3
Historical HQ Phase II Total Transfer Capability and Energy Flows
ISO investigated historical Phase II Total Transfer Capability and energy flows during the January 2003 through August 2006 period.
Results show that when loads are at 24,000 MW or above:– The Total Transfer Capability was equal to or greater than 1,400 MW
approximately 85% of the time.
– There is some uncertainty with the historical Total Transfer Capability data because the default TTC is set at 2,000 MW and it is not adjusted by the operator if the expected energy flow on the HQ Phase II is low. For example, if the TTC shows a 2,000 MW value and the scheduled energy flow is 200 MW, then the operator does not check the actual limits and as a result, the TTC is not updated to reflect the actual limit.
– These data are consistent with actual flow data, as energy imports from the HQ Phase II tie were seldom higher than 1,400 MW, especially at high loads.
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 4
Historical HQ Phase II Energy TTCJanuary 2003 through August 2006 HQ Phase II Total Transfer Capability
TTC vs. Demand
-
500
1,000
1,500
2,000
2,500
24,000 24,500 25,000 25,500 26,000 26,500 27,000 27,500 28,000 28,500
Hourly Demand (MW)
TT
C (
MW
)
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 5
Historical HQ Phase II Energy TTCJanuary 2003 through August 2006 HQ Phase II Total Transfer Capability
TTC (MW) Count % of TTC % Cumulativ
e
750 3 1.6 1.6
1000 9 4.7 6.3
1100 4 2.1 8.3
1200 6 3.1 11.5
1300 6 3.1 14.6
1400 45 23.4 38.0
1900 33 17.2 55.2
2000 86 44.8 100.0
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 6
Historical HQ Phase II Energy Flows
January 2003 through August 2006 Energy Flow vs. NE Hourly Load
-
100
200
300
400
500
600
700
800
900
1,000
1,100
1,200
1,300
1,400
1,500
1,600
1,700
1,800
1,900
20,000 21,000 22,000 23,000 24,000 25,000 26,000 27,000 28,000 29,000
Hourly Load (MW)
Imp
ort
s (
MW
)
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 7
Graphs presented at the May 17, 2007 PSPC meeting
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 8
Hydro-Quebec Phase II TTC and FlowAll Hours
All Hours TTC and Imports
(2,000)
(1,800)
(1,600)
(1,400)
(1,200)
(1,000)
(800)
(600)
(400)
(200)
-
- 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200
TTC In
Imp
ort
s F
low
ed
Summer On-PeakOn-Peak
Winter On-PeakAll Hours
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 9
Hydro-Quebec Phase II TTC and FlowSummer On-Peak Hours
Summer On-Peak Hours TTC and Imports
(2,000)
(1,800)
(1,600)
(1,400)
(1,200)
(1,000)
(800)
(600)
(400)
(200)
-
- 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2,200
TTC In
Imp
ort
s F
low
ed
Summer On-PeakOn-Peak
Winter On-PeakAll Hours
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 10
Additional Graphs and data as you have requested at the May 17, 2007 PSPC meeting
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 11
HQ Phase II Flow and Transfer Capability LimitDuring the 2005-2006 Top Ten Summer Peak Load Days
Hours 10 - 21
0
200
400
600
800
1,000
1,200
1,400
1,600
1,800
18,000 20,000 22,000 24,000 26,000 28,000
MW of Load
MW
of
Imp
ort
/ L
imit
Flow Transfer Capability Limit
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 12
HQ Phase II Flow and Transfer Capability LimitDuring the 2004-2006 Top Ten Summer Peak Load Days
at Hour of Daily Peak
0
200
400
600
800
1,000
1,200
1,400
1,600
1,800
20,000 21,000 22,000 23,000 24,000 25,000 26,000 27,000 28,000 29,000
MW of Load
MW
of
Imp
ort
/ L
imit
Flow Transfer Capability Limit
Limit Data Not Available in 2004
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 13
Hydro-Quebec Phase II Flow and Transfer Capability Limit2005-2006 Top Ten Summer Daily Peak Load Days at Hour of Peak
Date Peak HourPeak Load
(MW)Import (MW)
Transfer Capability
Limit (MW)
6/13/2005 17 25,231 1,254 1,4007/19/2005 15 26,736 1,196 1,4007/20/2005 17 24,983 1,241 1,4007/22/2005 16 24,912 1,242 1,4007/26/2005 17 25,555 1,245 1,4007/27/2005 15 26,885 1,308 1,4008/3/2005 16 24,716 1,339 1,4008/5/2005 15 25,983 1,292 1,400
8/10/2005 16 24,738 1,260 1,4008/11/2005 16 25,282 1,270 1,4006/19/2006 14 24,070 1,360 1,4007/14/2006 17 23,939 1,486 1,5947/17/2006 17 26,721 1,370 1,4007/18/2006 15 27,329 1,378 1,4007/26/2006 17 24,322 1,368 1,4507/27/2006 16 25,318 1,188 1,4007/28/2006 15 25,349 1,362 1,4008/1/2006 17 27,467 1,369 1,4008/2/2006 15 28,130 1,367 1,4008/3/2006 14 27,118 1,362 1,400
Hydro-Quebec Phase II Flow and Transfer Capability Limit Data
© 2007 ISO New England Inc. 14
Questions &
Comments ?