HIGHWAY PROGRAM FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW)

Transcript of HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR...

Page 1: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

HIGHWAY PROGRAM

FY 2015-2016

DISTRICT 02

(PRELIMINARY - FOR REVIEW)

Page 2: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.
Page 3: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

INTRODUCTION

1. R.S. 48:229, 230 states that each year “the Department shall provide the Legislature a program of construction to be commenced in the ensuing fiscal year, which shall be based upon anticipated revenues to be appropriated by the Legislature…” The Department shall also provide the Legislature a list of projects “which are in various stages of planning and preparation”.

2. In compliance with this statute, the attached Highway Program identifies the

projects that are scheduled for construction letting in FY 2015-16. These are denoted as being in Stage 4. Projects being developed in the other stages are also included in the document.

3. There are many projects remaining to be let prior to the end of the current

fiscal year, FY 2014-15. For informational purposes, these projects are also listed in this document. In the event any of these projects cannot be let as planned, they will become part of the FY 2015-16 construction program, and will be let as soon as practicable in that fiscal year.

4. The one year construction program and the list of other projects in various

stages are combined into this document which is called the Highway Priority Program or Highway Program. These projects are also submitted to the Federal Highway Administration along with the Transit Program. The two programs together are referred to as the State Transportation Improvement Program (STIP). The Public Hearings held each year in each Highway District fulfill both the State and Federal requirements for public involvement regarding these programs.

5. At this point in time, future funding levels are uncertain. DOTD has based this

preliminary Highway Program on previous allocations of funding. If funding above the expected amount is made available, funding may be used on projects listed in Stages 0, 1, 2, or 3.

6. In the event all of the projects listed for letting in FY 2015-16 cannot be let to

construction due to funding issues or unforeseen problems encountered in the pre-construction process, the affected project(s) will be let as soon as practicable in the following year and other projects listed in Stages 0, 1, 2, or 3 may be advanced into FY 2015-16.

7. Construction estimates are for informational purposes only and are subject to

change.

Page 4: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.
Page 5: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

PRESERVATION NON-INTERSTATE (PAVEMENT) 46.0

NON-INTERSTATE (PAVEMENT) (non-federal aid) 19.4

ROAD PREVENTIVE MAINTENANCE 7.5INTERSTATE (PAVEMENT) 74.0BRIDGE (ON SYSTEM) 133.1BRIDGE (OFF SYSTEM) 13.0

SUB-TOTAL 293.0

ITS (regular & earmarks) 11.0

OPERATIONS TRAFFIC CONTROL DEVICES 14.8ROADWAY FLOODING 3.7WEIGH STATIONS 1.9TRANSPORTATION SYSTEMS MANAGEMENT 7.4INTERSTATE LIGHTING 2.8REST AREAS 11.1ACCESS MANAGEMENT 8.1FERRIES/MAJOR REPAIRS 3.5MOVABLE BRIDGE PM 1.9

SUB-TOTAL 66.2

SAFETY HWY. PROGRAM 49.4

RR CROSSING UPGRADES & SEPARATIONS 16.0

SUB-TOTAL 65.4

CAPACITY REGULAR PROGRAM 0.0

CORRIDOR UPGRADE 46.0SUB-TOTAL 46.0

INTERMODAL CONNECTOR 7.5

TRANSPORTATION ALTERNATIVES PROJECTS 12.0

MISC.

URBAN SYSTEMS, CONGESTION MITIGATION & AIR QUALITY, LOCAL ROAD SAFETY PROGRAM, SAFE ROUTES TO SCHOOLS, URBAN TRANSIT, DEMAND MANAGEMENT 85.0FED EARMARKS (DEMO,...) 42.2

OTHER (BONDS, TOLLS, LOCAL ) 9.3

ROAD TRANSFER 23.1

SUB-TOTAL 179.1

GRAND TOTAL 649.7

Subject to funding availability.

TENTATIVE FY 15-16 BUDGET PARTITION

(COSTS IN MILLION DOLLARS)CONSTRUCTION

PROPOSEDCATEGORY SUB-CATEGORY

Page 6: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

FUNDING TYPES FEDERAL NHPP (NATIONAL HIGHWAY PERFORMANCE PROGRAM FUNDING) STP (SURFACE TRANSPORTATION PROGRAM) STP>200K (URBAN AREAS – NEW ORLEANS, BATON ROUGE, SHREVEPORT,

LAYAFETTE) STP<200K (URBAN AREAS – ALEXANDRIA, HOUMA, LAKE CHARLES, MONROE,

SLIDELL, MANDEVILLE-COVINGTON) STPFLEX (FLEXIBLE) STP<5K (RURAL AREAS) FBROFF (OFF SYSTEM BRIDGE MAP 21) TAP (TRANSPORTATION ALTERNATIVES PROGRAM) TAP>200K (URBAN AREAS – NEW ORLEANS, BATON ROUGE, SHREVEPORT,

LAYAFETTE) TAP<200K (URBAN AREAS – ALEXANDRIA, HOUMA, LAKE CHARLES, MONROE,

SLIDELL, MANDEVILLE-COVINGTON) TAPFLEX (FLEXIBLE) TAP<5K (RURAL AREAS) HSIP, SR2S, HRRR, SATRANS (SAFETY FUNDS, SAFE ROUTES TO SCHOOLS, HIGH RISK RURAL ROADS, SAFETY TRANSFER) RAIL HE. RAIL PD (ELIMINATIONS OF HAZARDS AT RAILWAY-HIGHWAY CROSSINGS) CM (CONGESTION MITIGATION – BATON ROUGE AND LAKE CHARLES) DEMO (FEDERAL DEMONSTRATION AND HIGH PRIORITY PROJECTS – DEFINED BY U.S. CONGRESS) ER (FEDERAL EMERGENCY RELIEF PROGRAM FUNDING) FEMA (FEDERAL EMERGENCY MANAGEMENT AGENCY FUNDS) STATE / LOCAL NFA (STATE TRANSPORTATION FUNDS FOR NON-FEDERAL AID ROUTES) NFABOND (STATE BONDS FOR NON-FEDERAL AID ROUTES) STCASH (STATE TRANSPORTATON TRUST FUNDS FOR STATE FUNDED CONSTRUCTION) TIME (TRANSPORTATION INFRASTRUCTURE MODEL FOR ECONOMIC DEVELOPMENT) STBONDS (GENERAL OBLIGATION BONDS) STGEN (STATE GENERAL FUNDS CASH) TOLLS LOCAL (FUNDS PROVIDED BY LOCAL GOVERNMENT) OTHER (OTHER SOURCE NOT LISTED) NFI (NO FUNDING IDENTIFIED)

Page 7: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - JEFFERSON

Project: H.006519 - SPEED CURVE ADVISORY

Type Impv: DYNAMIC MESSAGE SIGN&FLASHER INST.

Project Manager: HOLM, RICK

Remarks: 737-26-0009;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 SATRANS 286 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.008046 - LA 3152 : CLEARVIEW OPERATIONAL IMPRV.

Type Impv: INTERSECTION IMPROVEMENTS, INCLUDING ADDITIONAL TURN LANES

Project Manager: FOSTER, AMANDA

Remarks: USE TTF AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 3152 826-03 STP>200K 1,462 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009028 - AIRLINE PARK BLVD: W METAIRIE AV-0.4 M N

Type Impv: PANEL REPLACEMENT AND DRAINAGE

Project Manager: DEVILLE, JACQUES

Remarks: USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 STP>200K 2,430 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009406 - LA 48 @ EVANS DR.

Type Impv: DRAINAGE STRUCTURE REPLACEMENTS AND ADDITIONS

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 48 006-30 NHPP 451 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

4-SCHEDULED IN CURRENT FY 14-15

Project: H.010673 - US90Z:HARVEY CANAL TUNNEL REHABILITATION

Type Impv: CLEANING, MECHANICAL, ELECTRICAL AND STRUCTURAL REHABILIT

Project Manager: REVIERE, RYAN

Remarks: SEE NOTES FOR FUNDING INFO

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 90-Z 283-09 NHPP 12,700 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED IN CURRENT FY 14-15

Project: H.010990 - I-10: CLEARVIEW PKWY - CAUSEWAY BLVD.

Type Impv: JOINT REPAIR AND OVERLAY

Project Manager: THOMAS, BEN

Remarks: AC

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON I-10 450-15 NHPP 3,921 PRESERVATION

INTERSTATE

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011182 - ITS DYNAMIC MESSAGE SIGNS (KENNER)

Type Impv: INSTALL 5 DYNAMIC MESSAGE SIGNS.

Project Manager: BANKSTON, TANYA

Remarks: ENTITY WILL PROVIDE MATCH FOR LOYOLA AND POWER

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 49 283-30 STPFLEX 517 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED IN CURRENT FY 14-15

JEFFERSON 000-26 STPFLEX 256 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

JEFFERSON 000-26 STPFLEX 255 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

Project: H.011201 - KENNER SRTS PROJECT - CHATEAU ELEM

Type Impv: EDUCATION AND ENCOURAGEMENT

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 0 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011311 - US 90: WESTWOOD DR - ELEVATED WB EXPY

Type Impv: WIDEN RDWY FOR NEW TURN LANE; CONVERT EX. TL INTO THRU LA

Project Manager: ROONEY, BRITTANY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 90-Z 283-09 STGEN 1,000 PRESERVATION

NON-INTERSTATE

4-SCHEDULED IN CURRENT FY 14-15

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 1 of 226

Page 8: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - JEFFERSON

Project: H.011658 - US 90 BUS SIGNING UPGRADE-WEST BANK

Type Impv: SIGNING UPGRADES

Project Manager: COURTIER, KAY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 90-Z 283-09 NHPP 2,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

4-SCHEDULED IN CURRENT FY 14-15

Project: H.001439 - LA 1 BRIDGES NEAR GRAND ISLE

Type Impv: NEW BRIDGE

Project Manager: BUCCI, MARK

Remarks: 064-01-0047;STRU.IN POOR COND. JT W/064-02-0030

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 1 064-01 STPFLEX 800 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED FOR LETTING FY 15-16

LAFOURCHE LA 1 064-02 NHPP 2,900 PRESERVATION

BRIDGE (ON SYSTEM)

Project: H.002262 - DRAIN CANAL BRIDGE ON LA 45

Type Impv: BRIDGE REPLACEMENT

Project Manager: MUSA, ELNUR

Remarks: 249-90-0037;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 45 249-90 STPFLEX 1,592 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED FOR LETTING FY 15-16

Project: H.006441 - LA 23 (ENGINEERS RD. - LAPALCO)

Type Impv:

Project Manager: DEVILLE, JACQUES

Remarks: 736-38-0002;TRAFFIC STUDY FOR BELLE CHASE HWY.

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 23 062-01 STP>200K 3,345 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

PLAQUEMINES LA 23 062-02 STP>200K 2,900 URBAN SYSTEMS

Project: H.006524 - CITY OF GRETNA SAFE ROUTES TO SCHOOL - M

Type Impv: SIDEWALKS, CROSSWALKS, SIGNS, ETC.

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 SR2S 247 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.006525 - CITY OF GRETNA SAFE ROUTES TO SCHOOLS -

Type Impv: SIDEWALKS, CROSSWALKS, AND SIGNING

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 SR2S 188 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

JEFFERSON 000-26 SATRANS 30 SAFETY

SAFE ROUTES TO SCHOOLS

Project: H.007208 - HARVEY BLVD EXT(PETERS RD-MANHATTAN

Type Impv: NEW ROADWAY EXTENSION

Project Manager: DEVILLE, JACQUES

Remarks: 742-26-0073;SEE NOTES.

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 3017 826-11 STP>200K 876 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

JEFFERSON 000-26 STP>200K 9,597 URBAN SYSTEMS

Project: H.007214 - EAST AMES BOULEVARD IMPROVEMENTS

Type Impv: WIDEN FROM 2 TO 3 LANES

Project Manager: DEVILLE, JACQUES

Remarks: 742-26-0080;OREGON DR.-BLANCHE DR.

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 STP>200K 7,400 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 2 of 226

Page 9: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - JEFFERSON

Project: H.010402 - I-10: WILLIAMS BLVD - VETERANS BLVD

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: THOMAS, BEN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON I-10 450-15 NHPP 4,000 PRESERVATION

INTERSTATE

4-SCHEDULED FOR LETTING FY 15-16

Project: H.010973 - VETERANS BLVD LIGHTING(AIRPORT-LOYOLA)

Type Impv: ROADWAY LIGHTING

Project Manager: DEVILLE, JACQUES

Remarks: CITY OF KENNER

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 STP>200K 660 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010985 - US 90: IMP @ US 90B & NEAR LA 18

Type Impv: EXTEND ACCELERATION LANE AT THE INTERSECTION OF US 90B

Project Manager: GARY, VERTIE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 90 005-10 NHPP 550 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011158 - LA 3139: RAMP-A OVER LA 3152 REPAIR

Type Impv: REPLACE TWO PRESTRESSED CONCRETE GIRDERS AND ASSOCIATE

Project Manager: DELATTE, BRIAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 3139 430-01 STPFLEX 375 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED FOR LETTING FY 15-16

JEFFERSON LA 3139 430-01 REIMB 375 PRESERVATION

BRIDGE (ON SYSTEM)

Project: H.011339 - W ESPLANADE @ HOMESTEAD TRAFFIC SIGNAL

Type Impv: INSTALL TRAFFIC SIGNALS

Project Manager: DEVILLE, JACQUES

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 STP>200K 250 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011482 - US 90 HUEY P. LONG BRIDGE CLEAN & PAINT

Type Impv: CLEANING & PAINTING BRIDGE STEEL NOT PART OF THE WIDENING.

Project Manager: TULLIER, DANNY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 90 006-01 NHPP 20,000 PRESERVATION

BRIDGE PREVENTIVE MAINTENANCE

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011499 - DMS LADDER SYSTEM PHASE 5

Type Impv: THIS PROJECT INCLUDES INSTALLING LADDERS ON EXISTING DMSS.

Project Manager: BANKSTON, TANYA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON I-10 450-15 NHPP 550 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED FOR LETTING FY 15-16

ORLEANS I-10 450-90 NHPP 150 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

ORLEANS I-610 450-34 NHPP 150 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

ORLEANS US 90-Z 283-08 NHPP 150 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 3 of 226

Page 10: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - JEFFERSON

Project: H.001413 - LA 18(4TH ST.EXT.-BURMASTER(GRETNA)

Type Impv: CONSTRUCT 2 LANES

Project Manager: DEVILLE, JACQUES

Remarks: 063-02-0048;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 18 063-02 STP>200K 4,850 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

JEFFERSON LA 18 063-02 STGEN 0 OTHER / MISCELLANEOUS

JEFFERSON LA 18 063-02 TOLLS 0 CCC TOLL PROJECTS

JEFFERSON LA 18 063-02 STPFLEX 1,250 OTHER / MISCELLANEOUS

Project: H.002260 - GOOSE BAYOU BRIDGE

Type Impv: BRIDGE REPLACEMENT

Project Manager: TSAI, LOONG SHEN

Remarks: 249-90-0035;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 45 249-90 STPFLEX 3,836 PRESERVATION

BRIDGE (ON SYSTEM)

3-DESIGN/DEVELOPMENT

Project: H.002263 - JEAN LAFITTE: DOWNTOWN SIDEWALK, PHASE 1

Type Impv:

Project Manager: MEEK, STEPHEN

Remarks: 249-90-0040

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 45 249-90 TAPFLEX 188 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.003074 - I 10: WILLIAMS BLVD - VETERANS BLVD

Type Impv: MAJOR WIDENING - ADD TRAVEL LANES

Project Manager: YANG, LI

Remarks: 450-15-0124

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON I-10 450-15 NFI 70,000 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.007175 - LAPALCO (VICTORY - WESTWOOD)

Type Impv: WIDEN TO 4 LANES

Project Manager: DEVILLE, JACQUES

Remarks: 742-26-0033;FUND WITH DEMO FUNDS.PH.PUR.R/W

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 DEMO 3,600 DEMO / HIGH PRIORITY 3-DESIGN/DEVELOPMENT

JEFFERSON 000-26 STP>200K 8,578 URBAN SYSTEMS

Project: H.007181 - L&A ROAD IMPROVEMENTS

Type Impv: NEW ROADWAY AND ALIGNMENT

Project Manager: DEVILLE, JACQUES

Remarks: USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 STP>200K 4,500 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.007223 - HARVEY BLVD (MANHATTAN - WALL)

Type Impv: WIDEN TO 4 LANE URBAD SECT W MEDIAN

Project Manager: DEVILLE, JACQUES

Remarks: 742-26-0090; USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 STP>200K 7,100 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.008065 - HICKORY/DOCK ROUNDABOUT

Type Impv: ROUNDABOUT INSTALLATION

Project Manager: HARROUCH, JOSHUA

Remarks: 826-44-0032;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 3154 826-44 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

3-DESIGN/DEVELOPMENT

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 4 of 226

Page 11: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - JEFFERSON

Project: H.009087 - I-10: LOYOLA DR. TO WILLIAMS BLVD.

Type Impv: MAJOR WIDENING - ADD TRAVEL LANES

Project Manager: YANG, LI

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON I-10 450-15 NFI 10,000 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.009570 - US 61:TRANSCONTINENTAL DR - DAVID DR

Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 61 007-02 NHPP 1,469 PRESERVATION

NON-INTERSTATE

3-DESIGN/DEVELOPMENT

Project: H.009753 - JEAN LAFITTE: DOWNTOWN SIDEWALK, PHASE 2

Type Impv: SIDEWALK W/LIGHTING, LANDSCAPE & RELATED WORK

Project Manager: MEEK, STEPHEN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 TAP>200K 336 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009804 - KENNER: S WILLIAMS BLVD STREETSCAPING

Type Impv: SIDEWALKS W/ LIGHTING, STREETSCPAING & RELATED WORK

Project Manager: RIGGS, LAURA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 TAP>200K 446 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.010626 - SAUVE ROAD / SONIAT CANAL BRIDGE

Type Impv: BRIDGE REPLACEMENT

Project Manager: PENTEK, GARY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 FBROFF 1,033 PRESERVATION

BRIDGE (OFF SYSTEM)

3-DESIGN/DEVELOPMENT

Project: H.011007 - CHATEAU BLVD RESURFACING

Type Impv: RE-SURFACING

Project Manager: DEVILLE, JACQUES

Remarks: CITY OF KENNER

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 STP>200K 1,470 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011309 - MACARTHUR INTERCHANGE COMPLETION PH. II

Type Impv: RELOCATE THE EXIT RAMP AND CONSTRUCT AN ENTRANCE RAMP

Project Manager: YANG, LI

Remarks: USE CCCD TOLL CREDITS AS MATCH FOR 1.6 MIL. PRELIMINARY

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 90-Z 283-09 NFI 40,000 CAPACITY 3-DESIGN/DEVELOPMENT

Project: H.011457 - WILLIAMS/US61 INTERSECTION IMPROVEMENTS

Type Impv: INTERSECTION ENHANCEMENTS

Project Manager: DEVILLE, JACQUES

Remarks: CITY OF KENNER

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 61 007-02 STP<200K 487 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

JEFFERSON 000-26 STP<200K 487 URBAN SYSTEMS

JEFFERSON LA 49 283-30 STP<200K 487 URBAN SYSTEMS

Project: H.011463 - KENNER TRAFFIC SIGNALS UPGRADE

Type Impv: RESTRIPING AND UPGRADING EXISTING SIGNALS

Project Manager: DEVILLE, JACQUES

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 STP>200K 395 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 5 of 226

Page 12: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - JEFFERSON

Project: H.011534 - WEST LOYOLA & METAIRIE HEIGHTS BRIDGES

Type Impv: BRIDGE REPLACEMENT

Project Manager: PENTEK, GARY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 FBROFF 462 PRESERVATION

BRIDGE (OFF SYSTEM)

3-DESIGN/DEVELOPMENT

JEFFERSON 000-26 FBROFF 447 PRESERVATION

BRIDGE (OFF SYSTEM)

Project: H.011547 - LA 541 & LA 560-2: JESSIE ST. - LA 18

Type Impv: ADD DRAINAGE STRUCTURES

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 560-2 826-49 STPFLEX 800 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

3-DESIGN/DEVELOPMENT

JEFFERSON LA 541 826-13 STPFLEX 200 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

Project: H.011556 - LA 541: E JCT LA 18 - W JCT LA 18

Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 541 826-05 STPFLEX 550 PRESERVATION

NON-INTERSTATE NFA

3-DESIGN/DEVELOPMENT

Project: H.011611 - I-10: CAUSEWAY BLVD. - ORLEANS P/L

Type Impv: COLD PLANE AND OVERLAY

Project Manager: FOSTER, AMANDA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON I-10 450-15 NHPP 2,250 PRESERVATION

INTERSTATE

3-DESIGN/DEVELOPMENT

Project: H.002955 - EARHART EXPRESSWAY

Type Impv: ACCESS IMPROVEMENTS

Project Manager: DEVILLE, JACQUES

Remarks: 430-01-0016

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 3139 430-01 STP>200K 5,000 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.002956 - EARHART AT DAKIN

Type Impv: RAMP CONNECTOR (EB EARHART - DAKIN)

Project Manager: DEVILLE, JACQUES

Remarks: 430-01-0020; USE TTF AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 3139 430-01 STP>200K 2,375 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.004359 - HICKORY (LA 48 - MOUNES)

Type Impv: RELOCATION AND 4-LANING

Project Manager: YANG, LI

Remarks: 826-44-0027;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 3154 826-44 STBONDS 7,296 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

JEFFERSON LA 3154 826-44 OTHER 2,673 OTHER / MISCELLANEOUS

Project: H.004367 - LA3139:EARHART EXPRESSWAY EXT TO US 61

Type Impv: ENVIRONMENTAL. LINE & GRADE STUDY

Project Manager: YANG, LI

Remarks: 700-26-0242;HP NO.1600 (SEE ALSO 736-92-0003)

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 NFI 125,000 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 6 of 226

Page 13: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - JEFFERSON

Project: H.002258 - LA 45 (FLOOD GATE - LA 560-4)

Type Impv: COLD PLANE AND OVERLAY

Project Manager: RAY, JARED

Remarks: 249-01-0056;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 45 249-01 STPFLEX 1,551 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.002264 - BAYOU BARATARIA BRIDGE@JEAN LAFITTE

Type Impv: BRIDGE REPL.(KERNER'S)

Project Manager: YANG, LI

Remarks: 249-90-0041;TEA-21 KERNER'S FERRY BRIDGE

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 45 249-90 DEMO 4,146 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

JEFFERSON LA 45 249-90 FBR-ON/OFF 60,000 PRESERVATION

BRIDGE (ON SYSTEM)

Project: H.002861 - CAUSEWAY BLVD - EARHART EXPRESSWAY INTER

Type Impv: NEW INTERCHANGE

Project Manager: YANG, LI

Remarks: 430-01-0013;JEFF. PH CONSULTANT WORKING (E)

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 3139 430-01 NFI 60,000 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.006442 - AIRPORT - CBD COMMUTER RAIL STUDY

Type Impv: STUDY

Project Manager: GAUTREAU, COLLEEN

Remarks: 736-92-0003;HP 1600 (SEE ALSO 700-26-0242)

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.006513 - US 61 CORRIDOR PRESERVATION

Type Impv: ABANDONED RR R/W ACQ. (HP NO 1600)

Project Manager: GAUTREAU, COLLEEN

Remarks: 737-26-0001;HP=$0.5M. >2OOK=$0.3M IN FY 2001

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 DEMO 6,750 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.009571 - US 61:DAVID DR - WILLIAMS BLVD

Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PA

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 61 007-02 NHPP 1,998 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.009794 - GRETNA BICYCLE ACCESS IMPROVEMENTS

Type Impv: SIGNING, PAVEMENT MARKINGS, M/U PATH & RELATED WORK

Project Manager: RIGGS, LAURA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON 000-26 TAP>200K 170 ENHANCEMENTS 1-PLANNING/ENVIRONMENTAL

JEFFERSON US 90-Z 283-09 TAP>200K 75 ENHANCEMENTS

JEFFERSON LA 466 063-02 TAP>200K 50 ENHANCEMENTS

JEFFERSON LA 466 063-02 TAP>200K 25 ENHANCEMENTS

Project: H.010017 - US 90Z: WESTBANK EXPRESSWAY REHAB

Type Impv: MAJOR BRIDGE REHABILITATION

Project Manager: THOMAS, HOLLY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 90-Z 283-09 NHPP 12,000 PRESERVATION

BRIDGE (ON SYSTEM)

1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 7 of 226

Page 14: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - JEFFERSON

Project: H.010418 - LA 611-1 & LA 611-3:COLD PLANE & OVERLAY

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON LA 611-1 826-14 STPFLEX 200 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

JEFFERSON LA 611-1 826-16 STPFLEX 500 PRESERVATION

NON-INTERSTATE

JEFFERSON LA 611-1 826-16 STPFLEX 100 PRESERVATION

NON-INTERSTATE

JEFFERSON LA 611-1 826-17 STPFLEX 325 PRESERVATION

NON-INTERSTATE

Project: H.011514 - INTERSECT IMPROV ALONG US 61 & LA 3154

Type Impv: INTERSECTION IMPROVEMENT STUDY

Project Manager: HOYT, RYAN

Remarks: FEASIBILITY STUDY

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 61 007-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

JEFFERSON LA 3154 826-44 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.011647 - US61, LA611 & LA3152 CORRIDOR IMPROVE

Type Impv: CORRIDOR IMPROVEMENT STUDY

Project Manager: HOYT, RYAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON US 61 007-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

JEFFERSON LA 3152 826-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

JEFFERSON LA 611-9 826-04 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.011670 - I-10 / LOYOLA INTERCHANGE IMPROVEMENT

Type Impv: FEASIBILITY STUDY, IMR AND ENVIRONMENTAL ASSESSMENT

Project Manager: YANG, LI

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

JEFFERSON I-10 450-15 0 INTERMODAL CONNECTOR 1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 8 of 226

Page 15: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - LAFOURCHE

Project: H.001491 - LA 20 WIDENING: LA 308 - ST PATRICK ST

Type Impv: COLD PLANE AND OVERLAY

Project Manager: PAINE, PEGGY JO

Remarks: 065-06-0046;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 20 065-06 STBONDS 2,190 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

LAFOURCHE LA 20 065-06 HSIPPEN 4,878 SAFETY

- HSIPPEN 182 ROAD TRANSFER

Project: H.008145 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2C

Type Impv: ROUTE LA 1 RELOCATION

Project Manager: NICKEL, TIM

Remarks: 829-32-0010;NEW BRIDGE.NEW ALIGNMENT; AC-ING WITH STBON

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 829-32 STBONDS 31,416 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

LAFOURCHE LA 1 829-32 LOCAL 5,184 OTHER / MISCELLANEOUS

Project: H.009479 - WEST LAROSE VERTICAL LIFT BRIDGE REHAB

Type Impv: BRIDGE REHABILITATION

Project Manager: HINGLE, STEWART

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 064-05 STPFLEX 25,941 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED IN CURRENT FY 14-15

Project: H.010169 - KRAEMER LIFT BRIDGE MECHANICAL REPAIRS

Type Impv: MECHANICAL REPAIR

Project Manager: LAMBERT, JARRETT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 307 829-15 STPFLEX 650 OPER EFFICIENCY/MOTORIST ASSISTANCE

MOVABLE BRIDGE REHABILITATION

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011214 - RWD SIGNING (ST. PATRICK ST.)

Type Impv: PURCHASE AND INSTALL REGULATORY AND WARNING SIGNS.

Project Manager: HOLM, RICK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE 000-29 SATRANS 5 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011297 - LA 3107: LA 309 - LA 20

Type Impv: COLD PLANE, OVERLAY, STRIPING, CLEARING & GRUBBING

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 3107 829-22 STPFLEX 900 ROAD TRANSFER 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011332 - RWD SIGNING (GHEEN'S SHORTCUT RD)

Type Impv: PURCHASE AND INSTALL REGULATORY AND WARNING SIGNS.

Project Manager: HOLM, RICK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE 000-29 SATRANS 6 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011335 - NORTH CANAL PEDESTRIAN PATH, PHASE 1

Type Impv: THE CONSTRUCTION OF 2,850' OF PED-BIKE TRAIL

Project Manager: RIGGS, LAURA

Remarks: CRT IS THE PROJECT MANAGER

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE 000-29 RTP 112 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

LAFOURCHE 000-29 LOCAL 5 RECREATIONAL TRAILS PROGRAM

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 9 of 226

Page 16: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - LAFOURCHE

Project: H.011347 - TRAFFIC & REVENUE TOLLING ANALYSIS LA 1

Type Impv: ANALYSIS AND PRESENTATION OF FINDINGS

Project Manager: GLASCOCK, STEPHEN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 829-32 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011396 - LA 653: EAGLE ISLAND RD - LA 182

Type Impv: ASHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING

Project Manager: JOHNSON, ENNIS

Remarks: LETTER BID IN THE DISTRICT 11/20/2014

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 653 829-12 NFABOND 475 PRESERVATION

NON-INTERSTATE NFA

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011464 - LA 3090: LA 1 - FOURCHON CITY

Type Impv: ROADWAY REHABILITATION

Project Manager: FOSTER, AMANDA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 3090 064-30 STPFLEX 2,600 INTERMODAL CONNECTOR 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011466 - LA 307: TREE & STUMP REMOVAL

Type Impv: TREE AND STUMP REMOVAL

Project Manager: GALATAS, JOEL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 307 829-15 SATRANS 117 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011467 - LA 20: TREE & STUMP REMOVAL

Type Impv: TREE AND STUMP REMOVAL

Project Manager: GALATAS, JOEL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 20 065-06 SATRANS 25 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011481 - LA 1 TOLL PLAZA BUILDING

Type Impv: NEW TOLL PLAZA BUILDING

Project Manager: BANKSTON, TANYA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE 000-29 STCASH 300 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.002780 - LA 308 CURVE IMPROVEMENT

Type Impv: STRAIGHTEN CURVE IN ROADWAY

Project Manager: PICARD, TOBY

Remarks: 407-04-0043;407-04-0044

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 308 407-04 HSIP 2,073 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010109 - RACELAND SRTS PROJECT

Type Impv: SIDEWALK IMPROVMENTS, CROSSWALK, SPEED DETECTION DEVICES

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE 000-29 SR2S 202 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

LAFOURCHE 000-29 SATRANS 26 SAFETY

SAFE ROUTES TO SCHOOLS

Project: H.011239 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2E

Type Impv: CONSTRUCT LEEVILLE MAIN LINE INTERSECTION

Project Manager: NICKEL, TIM

Remarks: AC-ING WITH STBONDS

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 829-32 STBONDS 8,584 OTHER / MISCELLANEOUS 4-SCHEDULED FOR LETTING FY 15-16

LAFOURCHE LA 1 829-32 LOCAL 1,416 OTHER / MISCELLANEOUS

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 10 of 226

Page 17: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - LAFOURCHE

Project: H.011493 - LA 1: ITS EQUIPMENT UPGRADE

Type Impv: UPGRADING AND PROVIDING NEW ITS EQUIPMENT

Project Manager: BANKSTON, TANYA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 829-32 NHPP 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011559 - LA 308: 0.53 MI W DUET DRIVE - LOCKPORT

Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 308 407-90 NFA 950 PRESERVATION

NON-INTERSTATE NFA

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011665 - LA 308:BELLVIEW BRIDGE TO RITA BRIDGE

Type Impv: LA 308 REALIGNMENT.

Project Manager: MOORE, DARRELL

Remarks: 407-90 LOGMILE 13.115 TO 13.52 NFA MATCH (DETAIL 1)

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 308 407-90 HSIP 832 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

LAFOURCHE LA 308 407-90 HSIP 242 SAFETY

Project: H.002794 - VALENTINE CANAL BR. NEAR RACELAND

Type Impv: BRIDGE REPLACEMENT

Project Manager: ISEMANN, ROBERT

Remarks: 407-90-0018; USE NFA AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 308 407-90 FBROFF 1,421 PRESERVATION

BRIDGE (ON SYSTEM)

3-DESIGN/DEVELOPMENT

Project: H.008118 - BAYOU DUMAR & DRAIN CANAL BRIDGE

Type Impv: BRIDGE REPLACEMENT

Project Manager: BUCCI, MARK

Remarks: 829-12-0021;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 653 829-12 FBROFF 670 PRESERVATION

BRIDGE (ON SYSTEM)

3-DESIGN/DEVELOPMENT

Project: H.009320 - ACADIAN ROAD ROUNDABOUT

Type Impv: 5 LEGGED ROUNDABOUT

Project Manager: HANKS, ANNA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 20 065-05 HSIP 1,570 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.009658 - US 90: LA 182 - LA 1

Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE US 90 424-08 NHPP 3,938 PRESERVATION

NON-INTERSTATE

3-DESIGN/DEVELOPMENT

Project: H.009742 - ACADIA RD: AUDUBON-CARDINAL PED PATHS

Type Impv: SIDEWALK WITH LIGHTING

Project Manager: MEEK, STEPHEN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE 000-29 TAP<200K 204 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.010324 - LA 1: GOLDEN MEADOW - LEEVILLE

Type Impv: RAISING ROADWAY GRADE TO CONSISENT ELEVATION BY ADDING

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 064-90 NHPP 900 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

3-DESIGN/DEVELOPMENT

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 11 of 226

Page 18: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - LAFOURCHE

Project: H.010403 - LA 182/LA1: US 90 - ST. MARY ST

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 182 005-06 STPFLEX 2,750 PRESERVATION

NON-INTERSTATE

3-DESIGN/DEVELOPMENT

Project: H.011444 - LA 308: TURN LANES AT TIGER DRIVE BRIDGE

Type Impv: ADD TURN LANES FORM LA 308 TO TIGER DRIVE BRIDGE (LA 3266)

Project Manager: GARY, VERTIE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 308 407-05 STPFLEX 300 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

3-DESIGN/DEVELOPMENT

Project: H.011516 - US 90 @ LA 182

Type Impv: RAISING ROADWAY ELEVATION

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE US 90 005-07 NHPP 250 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

3-DESIGN/DEVELOPMENT

Project: H.011517 - LA 654: LA 308 - GREENS S. CUT RD.

Type Impv: RAISING ROADWAY ELEVATION BY ADDING ASPHALT

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 654 829-10 NFA 350 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

3-DESIGN/DEVELOPMENT

Project: H.011552 - LA 307: LA 20 - LA 182

Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 307 829-15 STPFLEX 1,750 PRESERVATION

NON-INTERSTATE NFA

3-DESIGN/DEVELOPMENT

Project: H.007234 - ACADIAN RD-WEST (CANAL TO LA 3185)

Type Impv: 4-LANE

Project Manager: HANKS, ANNA

Remarks: 742-29-0001;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE 000-29 STP<200K 9,359 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.010469 - EMERG CONT F/REPAIR TO ELMER'S ISLAND RD

Type Impv: FURNISH, PLACE, AND COMPACT AGGREGATE SURFACE COURSE MA

Project Manager: GISCLAIR, GARY

Remarks: LETTER BID 9/17/2012

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE 000-29 STCASH 300 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

Project: H.009662 - LA 308: GOLDEN MEADOW BR - GALLIANO BR

Type Impv: ASPHALTIC CONCRETE OVERLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 308 407-01 STPFLEX 2,115 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.009664 - LA 20: TERREBONNE P/L - JACKSON ST.

Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PA

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 20 065-05 STPFLEX 1,116 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 12 of 226

Page 19: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - LAFOURCHE

Project: H.010006 - LA 182 & LA 58: MOVABLE BRIDGE REHAB

Type Impv: MOVABLE BRIDGE REHABILITATION

Project Manager: BRAUNER, KURT

Remarks: BOTH CONTROL SECTIONS IN HOUMA MPO AREA.

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 182 005-07 STPFLEX 5,089 PRESERVATION

BRIDGE (ON SYSTEM)

1-PLANNING/ENVIRONMENTAL

TERREBONNE LA 58 247-30 STPFLEX 4,253 PRESERVATION

BRIDGE (ON SYSTEM)

Project: H.010152 - LA 1: CONSTRUCTION CANAL DREDGING

Type Impv: DREDGE CANAL AND MITIGATION FOR LA 1 ELEVATED CONSTRUCTIO

Project Manager: NICKEL, TIM

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 064-90 NHPP 2,000 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.010404 - US 90: 2.5 MI E LA 182 - ST CHARLES P/L

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE US 90 005-07 NHPP 4,000 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010408 - LA 1: VALENTINE BR - LA 655

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 064-05 STPFLEX 2,300 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010409 - LA 1: LA 655 - CHAMPAGNE-HARRELSON BR

Type Impv: COLD PLANE AND SUPERPAVE ASPHALTIC CONCRETE OVERLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 064-06 STPFLEX 1,500 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010688 - LA 3235 FEASIBILITY STUDY

Type Impv: ACCESS MANAGEMENT

Project Manager: RENARD, APRIL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 3235 829-26 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011207 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2A

Type Impv: CONSTRUCT RELOCATED LA 1 ON ELEVATED STRUCTURE

Project Manager: NICKEL, TIM

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 829-32 NFI 43,400 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.011208 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2B

Type Impv: ELEVATED RELOCATED LA 1 -LEEVILLE TO GOLDEN MEADOW LEVEE

Project Manager: NICKEL, TIM

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 829-32 NFI 230,000 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.011209 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2D

Type Impv: NEW TOLL FACILITY FOR LA 1 SOUTHBOUND AND APPROACH.

Project Manager: NICKEL, TIM

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

LAFOURCHE LA 1 829-32 NFI 10,000 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 13 of 226

Page 20: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.003182 - IHNC AND ALGIERS CUTOFF BRIDGE REHAB

Type Impv: FINGER JOINTS,ROCKER BEARINGS & DECK OVERLAY

Project Manager: KEMP, KELLY

Remarks: 450-90-0246;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 7,578 PRESERVATION

BRIDGE PREVENTIVE MAINTENANCE

4-SCHEDULED IN CURRENT FY 14-15

ORLEANS LA 407 836-08 NHPP 754 PRESERVATION

BRIDGE PREVENTIVE MAINTENANCE

Project: H.004730 - US 61/90(TULANE) CLAIBORNE - CARROLLTON

Type Impv: SAFETY AND TRAFFIC OPERATIONAL IMPROVEMENTS

Project Manager: FOSTER, AMANDA

Remarks: 700-36-0187;STAGE 0 AND STAGE 1 MATCH BY RPC

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 61 007-01 HSIP 1,614 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS US 61 007-01 NHPP 1,074 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

ORLEANS US 90 006-03 HSIP 1,045 SAFETY

ORLEANS US 90 006-03 NHPP 733 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

ORLEANS US 90 006-03 STP>200K 304 URBAN SYSTEMS

Project: H.006196 - WISNER BLVD BRIDGE REPLACEMENT

Type Impv: BRIDGE REPLACEMENT

Project Manager: PENTEK, GARY

Remarks: 713-36-0108;ENHANCEMENTS PROVIDING $ 2,000,000

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 FBROFF 10,000 PRESERVATION

BRIDGE (OFF SYSTEM)

4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 TAP>200K 2,000 ENHANCEMENTS

Project: H.006567 - PEDESTRIAN CROSSWALK ENHANCEMENTS

Type Impv: SIGNS & PVMT.MARKINGS INSTALLATION

Project Manager: HOLM, RICK

Remarks: 737-36-0016;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SATRANS 276 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.007265 - ST CHARLES AVE (LA AVE-CALLIOPE ST)

Type Impv: OVERLAY

Project Manager: DEVILLE, JACQUES

Remarks: 742-36-0126; USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 3,666 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.007273 - MAGAZINE ST (BROADWAY - CALHOUN)

Type Impv: REHABILITATION

Project Manager: DEVILLE, JACQUES

Remarks: 742-36-0137; USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 3,500 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.007274 - MAGAZINE ST (CALHOUN TO NASHVILLE)

Type Impv: REHABILITATION

Project Manager: DEVILLE, JACQUES

Remarks: 742-36-0139; USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 3,000 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.007275 - ST CHARLES AVENUE (NASHVILLE TO LA AVE)

Type Impv: OVERLAY

Project Manager: DEVILLE, JACQUES

Remarks: 742-36-0140; USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 1,700 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 14 of 226

Page 21: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.007277 - LAKE FOREST BOULEVARD

Type Impv: MINOR WIDENING

Project Manager: DEVILLE, JACQUES

Remarks: 742-36-0142;ADD ENGINEERING TO FY 10

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 370 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009069 - TRI-CENTENNIAL PL PARKING, CITY PARK NO

Type Impv: PARKING LOT

Project Manager: RIGGS, LAURA

Remarks: SEE NOTES FOR FUNDING INFORMATION

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 TCSP 2,107 DEMO / HIGH PRIORITY 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 LOCAL 190 DEMO / HIGH PRIORITY

Project: H.009354 - BROAD STREET CORRIDOR BIKEWAY

Type Impv: CONSTRUCTION OF BIKE LANES, A MULTI-USE PATH AND CROSSING

Project Manager: RIGGS, LAURA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 RTP 89 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 LOCAL 11 RECREATIONAL TRAILS PROGRAM

Project: H.009838 - SAFE ROUTES TO ARISE ACADEMY

Type Impv: NON-INFRASTRUCTURE SRTS PROJECT ONLY

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 50 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.009949 - ESPERANZA SAFE ROUTES TO SCHOOL

Type Impv: NON-INFRASTRUCTURE SRTS PROJECT

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 18 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.010113 - EINSTEIN CHARTER SCHOOL SRTS NON-INFRAST

Type Impv: BIKE/PED SAFETY TRAINING, PURCHASES, ENCOURAGEMENT ACTIVI

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 100 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.010576 - JEFFERSON DAVIS TRAILS

Type Impv: CONSTRUCTION OF A PED-BIKE TRAIL SYSTEM.

Project Manager: RIGGS, LAURA

Remarks: NATIONAL RECREATIONAL TRAILS PROJECT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 RTP 112 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 LOCAL 14 RECREATIONAL TRAILS PROGRAM

Project: H.010719 - US 90 RAMP IMPROVEMENTS

Type Impv: IMPROVE EB ONRAMP TO US 90Z FROM CLAIBORNE AVE.

Project Manager: NICKEL, TIM

Remarks: USE CCCD TOLL CREDITS AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90-Z 283-08 STP>200K 1,500 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS US 90-Z 283-08 NHPP 1,575 OTHER / MISCELLANEOUS

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 15 of 226

Page 22: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.010872 - EARHART CORRIDOR BIKEWAY LINKAGE

Type Impv: CONSTRUCTION OF 2.3 MILES OF BIKE LANE.

Project Manager: RIGGS, LAURA

Remarks: NATIONAL RECREATIONAL TRAILS PROJECT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 RTP 146 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 LOCAL 30 RECREATIONAL TRAILS PROGRAM

Project: H.011078 - NO RTMC BUILDING SECURITY

Type Impv: BUILDING SECURITY SYSTEM FOR THE NO RTMC

Project Manager: SMITH, ERIK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STPFLEX 94 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 STCASH 26 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

Project: H.011139 - NEW ORLEANS SRTS PROJECT - YLC (NI)

Type Impv: BICYCLE RACKS AND TRAINING.

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 0 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011140 - NEW ORLEANS SRTS PROJECT - KIDSWALK (NI)

Type Impv: EDUCATION AND ENCOURAGEMENT

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 0 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011146 - CITY PARK BICYCLE TRAIL

Type Impv: CONST. & IMPROVE. TO BICYCLE INFRAS. TO 1300 ACRES CITY PARK

Project Manager: RIGGS, LAURA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 RTP 116 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 LOCAL 10 RECREATIONAL TRAILS PROGRAM

Project: H.011150 - I-10 WB OVER CHEF MENTEUR BL BR REPAIR

Type Impv: REPLACE TWO STEEL GIRDER AND ASSOCIATED DECK.

Project Manager: D'ANDREA, ARTUR

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 541 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED IN CURRENT FY 14-15

ORLEANS I-10 450-90 REIMB 893 PRESERVATION

BRIDGE (ON SYSTEM)

Project: H.011167 - I-10: HOWARD AVENUE SERVICE ROAD

Type Impv: ROADWAY RESTORATION AND REHAB

Project Manager: FOSTER, AMANDA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 850 PRESERVATION

INTERSTATE

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011172 - US 90-Z: PAVEMENT MARKING REPLACEMENT I

Type Impv: PAVEMENT MARKING REPLACEMENT

Project Manager: COLVIN, JODY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90-Z 283-08 NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

4-SCHEDULED IN CURRENT FY 14-15

JEFFERSON US 90-Z 283-09 NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 16 of 226

Page 23: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.011199 - NEW ORLEANS SRTS PROJ. - EINSTEIN II NI

Type Impv: EDUCATION AND ENCOURAGEMENT

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 50 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011200 - NEW ORLEANS SRTS PROJ. - AUDUBON N.I.

Type Impv: EDUCATION AND ENCOURAGEMENT

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 74 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011238 - I-910/US 90-Z: GENERAL DE GAULLE RAMPS

Type Impv: ASPHALT OVERLAY AND APPROACH SLAB LEVELING OF RAMPS

Project Manager: THOMAS, BEN

Remarks: CCCD TOLL CREDITS AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90-Z 283-08 NHPP 798 PRESERVATION

INTERSTATE

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011246 - PATHS TO PROGRESS (GROUP 38)

Type Impv: ASPHALT OVERLAY

Project Manager: BURST, JEFFERY

Remarks: USE STATEBONDS AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 1,938 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 STP>200K 1,964 URBAN SYSTEMS

Project: H.011271 - I-10 PAVEMENT MARKING REPLACEMENT II

Type Impv: REMOVE AND REPLACE EXISTING PAVEMENT MARKINGS

Project Manager: COLVIN, JODY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

4-SCHEDULED IN CURRENT FY 14-15

JEFFERSON I-10 450-15 NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.011672 - I-610: PONTCHARTRAIN OVERPASS REPAIRS

Type Impv: BRIDGE DECK REPAIR AND PATCHING

Project Manager: GUIDRY, JOHN

Remarks: SECRETARY'S EMERGENCY FUNDS, LETTER DATED 9/12/2014

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-610 450-34 STGEN 95 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.007259 - FLEUR DE LIS (30TH ST - OLD HAMMOND HWY)

Type Impv: RECONSTRUCTION

Project Manager: DEVILLE, JACQUES

Remarks: 742-36-0118;(HARRISON - OLD HAMMOND HWY)

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 6,100 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007271 - CANAL BLVD (R.E. LEE - AMETHYST)

Type Impv: RECONSTRUCT EXISTING 4 LANE DIVIDED

Project Manager: DEVILLE, JACQUES

Remarks: 742-36-0135; USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 3,000 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 17 of 226

Page 24: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.009308 - NEW ORLEANS DPW - EP HARNEY SCHOOL PROJ.

Type Impv: BICYCLE & PEDESTRAIN CROSSING IMPROVEMENTS

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 175 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

ORLEANS US 90 006-03 SATRANS 20 SAFETY

SAFE ROUTES TO SCHOOLS

ORLEANS US 90 006-03 SR2S 25 SAFETY

SAFE ROUTES TO SCHOOLS

ORLEANS US 90 006-03 SATRANS 5 SAFETY

SAFE ROUTES TO SCHOOLS

Project: H.009572 - LA 39:JUDGE SEEBER BR-ST BERNARD P/L

Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS LA 39 046-31 NHPP 1,406 PRESERVATION

NON-INTERSTATE

4-SCHEDULED FOR LETTING FY 15-16

Project: H.010086 - E.P. HARNEY SCHOOL SRTS NON-INFRASTRUCT

Type Impv: SRTS NON-INFRASTRUCTURE

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 0 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.010111 - AUDUBON CHARTER SCHOOL SRTS INFRASTRUCT

Type Impv: SIDEWALK IMPROVMENTS, TRAFFIC CALMING, STRIPING AND MARKIN

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 174 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

ORLEANS 000-36 SATRANS 28 SAFETY

SAFE ROUTES TO SCHOOLS

Project: H.010112 - AUDUBON CHARTER SCHOOL SRTS NON-INFRAST

Type Impv: BIKE AND PED SAFETY TRAINING,PURCHASES, ENFORCEMENT ACTIV

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 125 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.010114 - EINSTEIN CHARTER SCHOOL INFRASTRUCTURE

Type Impv: SIDEWALK IMPROVEMENTS, TRAFIC CALMING, MARKINGS AND STRIP

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 190 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

ORLEANS 000-36 SATRANS 30 SAFETY

SAFE ROUTES TO SCHOOLS

Project: H.010331 - US 90: FLOODWALL - CHEF PASS BRIDGE

Type Impv: RAISING ROADWAY GRADE TO CONSISENT ELEVATION BY ADDING

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90 006-90 STPFLEX 600 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

4-SCHEDULED FOR LETTING FY 15-16

Project: H.010636 - US 90 OVER MISS RVR (GNO2)-CLEAN & PAINT

Type Impv: BRIDGE REPAIRS, CLEANING & PAINTING

Project Manager: REVIERE, RYAN

Remarks: CCCD TOLL CREDITS AS MATCH PHASE 6

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90-Z 283-08 NHPP 9,000 PRESERVATION

BRIDGE PREVENTIVE MAINTENANCE

4-SCHEDULED FOR LETTING FY 15-16

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 18 of 226

Page 25: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.011198 - NEW ORLEANS SRTS PROJ. - EINSTEIN II

Type Impv: SIDEWALKS, STRIPING AND SIGNING

Project Manager: GROS, SCOTT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 SR2S 200 SAFETY

SAFE ROUTES TO SCHOOLS

4-SCHEDULED FOR LETTING FY 15-16

ORLEANS 000-36 SATRANS 25 SAFETY

SAFE ROUTES TO SCHOOLS

Project: H.011503 - I-10 TWIN SPAN ITS

Type Impv: THIS PROJECT INVOLVES INSTALLING A DMS AND CAMERAS.

Project Manager: BANKSTON, TANYA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-17 NHPP 450 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011609 - I-10: US 11 DECELERATION LANE EXTENSION

Type Impv: EXTENDING THE EXISTING DECELERATION EXIT LANE TO US 11 FROM

Project Manager: FOSTER, AMANDA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 300 PRESERVATION

INTERSTATE

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011622 - I-910: RAMPS NEAR SUPERDOME/CLAIBORNE

Type Impv: PCC REHABILITATION; RESURFACING ASPHALTIC CONCRETE

Project Manager: FOSTER, AMANDA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90-Z 283-08 NHPP 500 PRESERVATION

INTERSTATE

4-SCHEDULED FOR LETTING FY 15-16

Project: H.000304 - I 10 - US 61 OVERPASS

Type Impv: BRIDGE REHABILITATION

Project Manager: D'ANDREA, ARTUR

Remarks: 007-01-0022;STAGE 0 PROJECT FEASIBILITY STUDY

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 61 007-01 NHPP 4,000 PRESERVATION

BRIDGE (ON SYSTEM)

3-DESIGN/DEVELOPMENT

Project: H.007250 - ALMONASTER BRIDGE AND APPR.

Type Impv: BRIDGE REPLACEMENT

Project Manager: YANG, LI

Remarks: 742-36-0104;OTHER FUNDS - PORT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STPFLEX 20,000 INTERMODAL CONNECTOR 3-DESIGN/DEVELOPMENT

ORLEANS 000-36 STPFLEX 20,000 PRESERVATION

BRIDGE (ON SYSTEM)

ORLEANS 000-36 OTHER 22,000 OTHER / MISCELLANEOUS

Project: H.009764 - NO CITY PARK: MARCONI MULTI-USE PATH

Type Impv: MULTI-USE PATH, LANDSCAPING & RELATED WORK

Project Manager: RIGGS, LAURA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 TAP>200K 727 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009938 - MAGNOLIA CONVERTED PED BRIDGE REHAB

Type Impv: REHAB OF EXISTING PED BRIDGE (CONVERTED VEHICLE) & REL. WOR

Project Manager: RIGGS, LAURA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 TAP>200K 889 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 19 of 226

Page 26: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.010016 - US 11: LAKE PONTCHARTRAIN BRIDGE REHAB

Type Impv: MAJOR BRIDGE REHABILITATION

Project Manager: BRAUNER, KURT

Remarks: PRIORITY BRIDGE PROJECT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 11 018-02 STPFLEX 25,000 PRESERVATION

BRIDGE (ON SYSTEM)

3-DESIGN/DEVELOPMENT

Project: H.011108 - NS SEVERAL RR XINGS (NEW ORLEANS)

Type Impv: RAIL/HIGHWAY CROSSING WARNING IMPROVEMENTS

Project Manager: SHREWSBERRY,BILL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 RAIL PD 1,000 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.011219 - I-10: NO CBD1 I610-CARROLLTON

Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT & UPGRADE IN NO C

Project Manager: COURTIER, KAY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 4,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

3-DESIGN/DEVELOPMENT

Project: H.011220 - I-10: NO CBD2 CARROLLTON - POYDRAS

Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT & UPGRADE IN NO C

Project Manager: COURTIER, KAY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 8,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

3-DESIGN/DEVELOPMENT

Project: H.011447 - US 90: INTERSECTION IMP AT MLK BLVD

Type Impv: INTERSECTION IMPROVEMENTS ON US 90 AT MLK BLVD

Project Manager: GARY, VERTIE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90 006-03 NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

3-DESIGN/DEVELOPMENT

Project: H.004721 - TCHOUPITOULAS SIGNAGE AND STRIPING PLAN

Type Impv: STUDY

Project Manager: NGUYEN, WAYNE

Remarks: 700-36-0176;$48K H.P.DEMO. $12K MATCH BY RPC

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 DEMO 200 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

Project: H.007272 - HOWARD AVENUE EXTENSION

Type Impv: NEW 2-LANE ROADWAY

Project Manager: NICKEL, TIM

Remarks: 742-36-0136;CITY OWNS R/W

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 DEMO 3,226 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

Project: H.000263 - CHEF MENTEUR PASS BRIDGE & APPROACH

Type Impv: BRIDGE REPLACEMENT

Project Manager: RABALAIS, NICK

Remarks: 006-05-0067;STAGE 1 PROJECT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90 006-05 STPFLEX 85,000 PRESERVATION

BRIDGE (ON SYSTEM)

1-PLANNING/ENVIRONMENTAL

Project: H.004738 - I-610 - TWIN SPANS AND I-10 @ RR

Type Impv: STATE FUNDS FOR STUDY

Project Manager: NGUYEN, WAYNE

Remarks: 700-36-0198;(STAGE 0.PHASE1)

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 20 of 226

Page 27: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.005720 - FLORIDA AVENUE EXPRESSWAY

Type Impv: FLORIDA AVENUE EXPRESSWAY FEASIBILITY STUDY - RESCOPE

Project Manager: PORTER BETTS, CONNIE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 0 TIME 1-PLANNING/ENVIRONMENTAL

Project: H.009499 - LEAKE AVENUE IMPROVEMENTS

Type Impv: PLANNING STUDY

Project Manager: BROUSSARD, DAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.009661 - LA 406: DONNER CANAL BR - STANTON RD

Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PA

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS LA 406 409-02 STPFLEX 823 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.009663 - LA 47: I-10 - BULLARD RD.

Type Impv: PCC REHAB AND ASPHALTIC CONCRETE OVERLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS LA 47 148-03 STPFLEX 4,500 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.009939 - ST CHARLES AVE: STREETSCAPING IMP., PH 1

Type Impv: STREETSCAPING, DECORATIVE LIGHTING, & RELATED WORK

Project Manager: RIGGS, LAURA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 TAP>200K 1,053 ENHANCEMENTS 1-PLANNING/ENVIRONMENTAL

Project: H.010018 - I-10: NO EAST DRAIN CANAL BRIDGE REPLACE

Type Impv: BRIDGE REPLACEMENT

Project Manager: YAP, KIAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 11,758 PRESERVATION

BRIDGE (ON SYSTEM)

1-PLANNING/ENVIRONMENTAL

Project: H.010405 - US 90: CAMELOT DR - FLOOD GATE

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90 006-90 STPFLEX 1,400 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010414 - LA 1253: DOWMAN RD - I-10 FRONTAGE RD

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS LA 1253 419-02 STPFLEX 250 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010634 - CCCD-US90BUS SIGN UPGRADE-EAST/WEST BANK

Type Impv: UPGRADING SIGNS ENTIRE LIMITS. UPGRADING STRUCTURES AS NEE

Project Manager: COURTIER, KAY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90-Z 283-08 NHPP 3,500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

JEFFERSON US 90-Z 283-09 NHPP 3,500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 21 of 226

Page 28: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.011221 - I-10: NO CBD3 POYDRAS - LOUISA

Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT & UPGRADE IN NO C

Project Manager: COURTIER, KAY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 8,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

Project: H.011222 - I-10: NO CBD4 LOUISA - I-510

Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT & UPGRADE IN NO C

Project Manager: COURTIER, KAY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS I-10 450-90 NHPP 5,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

Project: H.011460 - I-10: LA47 & 3021 INTERSEC IMPROV

Type Impv: INTERSECTION IMPROVEMENT STUDY

Project Manager: HOYT, RYAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS LA 47 148-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.011642 - LA39, LA46 & LA3021 CORRIDOR IMPROVEMENT

Type Impv: TRAFFIC COUNTS

Project Manager: HOYT, RYAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS LA 39 046-31 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

ORLEANS LA 46 046-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ORLEANS LA 3021 419-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.011644 - US90: NASHVILLE - S PETERS IMPROVEMENTS

Type Impv: CORRIDOR IMPROVEMENTS

Project Manager: HOYT, RYAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90 006-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

ACCESS MANAGEMENT

1-PLANNING/ENVIRONMENTAL

ORLEANS US 90-Z 283-08 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

ACCESS MANAGEMENT

Project: H.011646 - US 90 - US 61 - LA 611-9 CORRIDOR IMPROV

Type Impv: INTERSECTION IMPROVEMENT STUDY

Project Manager: HOYT, RYAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90 006-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

ORLEANS US 61 007-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ORLEANS LA 611-9 836-05 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 22 of 226

Page 29: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ORLEANS

Project: H.011648 - LA39, 46 & 47 CORRIDOR IMPROVE

Type Impv:

Project Manager: HOYT, RYAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS LA 39 046-31 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

ST BERNARD LA 39 046-32 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ORLEANS LA 46 046-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ST BERNARD LA 46 046-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ST BERNARD LA 47 148-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.011649 - I-610, US 90 & LA3021 CORRIDOR IMPROVE

Type Impv: CORRIDOR IMPROVEMENT STUDY

Project Manager: HOYT, RYAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS US 90 006-90 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

ORLEANS I-610 450-34 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ORLEANS LA 3021 419-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.011651 - I-10: LOYOLA DR-BONNABEL CORRIDOR IMPROV

Type Impv: CORRIDOR IMPROVEMENT STUDY

Project Manager: HOYT, RYAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

JEFFERSON LA 3152 826-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

JEFFERSON I-10 450-15 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.009920 - REMOVE TOLL BOOTHS/RECONFIG TRAVEL LANES

Type Impv: REMOVE TOLL BOOTHS/RECONFIGURATION OF TRAVEL LANES/SIGN

Project Manager: REVIERE, RYAN

Remarks: USE FEDERAL CCC TOLL CREDITS AS MATCH TO STP>200K

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STP>200K 3,000 URBAN SYSTEMS 0-FEASIBILITY/SCOPING

Project: H.009918 - REPLACE 2 CCCD FERRIES

Type Impv: REPLACE UP TO 2 CCCD FERRIES

Project Manager: REED, KEVIN

Remarks: USE TOLLS AS MATCH TO STPFLEX AT 80/20 SPLIT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STPFLEX 16,000 CCC TOLL PROJECTS STAGES 4, 3, 2, 1, 0

Project: H.009919 - REHABILITATION OF CCCD FERRY TERMINALS

Type Impv: REHABILITATION OF CCCD FERRY TERMINALS

Project Manager: REED, KEVIN

Remarks: USE TOLLS AS MATCH TO STPFLEX AT 80/20 SPLIT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ORLEANS 000-36 STPFLEX 3,000 CCC TOLL PROJECTS STAGES 4, 3, 2, 1, 0

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 23 of 226

Page 30: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - PLAQUEMINES

Project: H.010508 - LA 3137: LA 39 - FERRY LANDING ROAD

Type Impv: ULTRATHIN OVERLAY

Project Manager: JOHNSON, ENNIS

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

PLAQUEMINES LA 3137 838-05 NFABOND 639 PRESERVATION

NON-INTERSTATE NFA

4-SCHEDULED IN CURRENT FY 14-15

Project: H.001399 - HAPPY JACK - N.PORT SULPHUR

Type Impv: WIDEN TO 4 LANES

Project Manager: UMEOZULU, JOE

Remarks: 062-04-0029;$1M GS9$ FOR STUDY

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

PLAQUEMINES LA 23 062-04 NFI 30,000 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.004791 - REPL.BRIDGE AND TUNNEL BELLE CHASSE

Type Impv: STATE FUNDS FOR STUDY

Project Manager: TSAI, LOONG SHEN

Remarks: 700-38-0108;FEASIBILITY STUDY STAGE 0

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

PLAQUEMINES 000-38 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.010590 - EMERG ELEC REP&DEBR REM OSTRICA LK&CANAL

Type Impv: EMERGENCY ELECTRICAL REPAIR AND DEBRIS REMOVAL

Project Manager: MILLER, DAVID

Remarks: SECRETARY EMERGENCY LETTER 9/5/2012

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

PLAQUEMINES 000-38 STGEN 400 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.010912 - MISSIPPIPPI RIVER TRAIL-PLAQUEMINES PAR

Type Impv: STAGE 0 FEASIBILITY STUDY

Project Manager: NGUYEN, WAYNE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

PLAQUEMINES 000-38 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 24 of 226

Page 31: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ST BERNARD

Project: H.002562 - BAYOU LALOUTRE BRIDGE REHABILITATION

Type Impv: STRUCTURAL/ELECTRICAL REPAIRS, CLEANING & PAINTING

Project Manager: KEMP, KELLY

Remarks: 284-02-0032;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD LA 46 284-02 FBROFF 3,500 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED IN CURRENT FY 14-15

ST BERNARD LA 46 284-02 ER 800 OTHER / MISCELLANEOUS

Project: H.007331 - PACKENHAM DR (LA46 - LA39)

Type Impv: RECONSTRUCT

Project Manager: DEVILLE, JACQUES

Remarks: 742-44-0006;WAS 742-07-0079

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD 000-44 STP>200K 4,107 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009834 - ST BERNARD PARISH STREET REHAB PROGRAM

Type Impv: OVERLAYS/PANEL REPAIR/PANEL REPLACEMENT

Project Manager: DEVILLE, JACQUES

Remarks: USE LOCAL AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD 000-44 STP>200K 4,668 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010586 - ST BERNARD P MISSISSIPPI RIVER TRAIL PH3

Type Impv: CONSTRUCTION OF A PED-BIKE TRAIL.

Project Manager: RIGGS, LAURA

Remarks: NATIONAL RECREATIONAL TRAILS PROJECT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD 000-44 RTP 112 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ST BERNARD 000-44 LOCAL 425 RECREATIONAL TRAILS PROGRAM

Project: H.011103 - NS SEVERAL RR XINGS (PLAQUEM. & ST.BERN)

Type Impv: UPGRADE RAILROAD WARNING SIGNALS.

Project Manager: SHREWSBERRY,BILL

Remarks: RR PAYS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD LA 39 046-03 RAIL PD 18 RAILROADS 4-SCHEDULED IN CURRENT FY 14-15

PLAQUEMINES LA 39 046-04 RAIL PD 55 RAILROADS

ST BERNARD LA 39 046-03 LOCAL 18 RAILROADS

Project: H.010407 - LA 46: PARIS - 0.025 MI N WEBSTER ST

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD LA 46 046-03 STPFLEX 1,500 PRESERVATION

NON-INTERSTATE

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011118 - ST. BERNARD PARISH MRT TRAILHEADS

Type Impv: CONST. OF 1600' OF LEVEE ACCESS RAMPS ALONG MS RIVER TRAIL

Project Manager: RIGGS, LAURA

Remarks: CRT IS THE PROJECT MANAGER

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD 000-44 RTP 116 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED FOR LETTING FY 15-16

ST BERNARD 000-44 LOCAL 44 RECREATIONAL TRAILS PROGRAM

Project: H.011555 - LA 46:FLORRISANT HWY - GULF OUTLET CANAL

Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD LA 46 284-02 STPFLEX 300 PRESERVATION

NON-INTERSTATE NFA

3-DESIGN/DEVELOPMENT

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 25 of 226

Page 32: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ST BERNARD

Project: H.011557 - LA 300: LA 1245 - END LA 300 (DELACROIX)

Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD LA 300 284-30 STPFLEX 2,000 PRESERVATION

NON-INTERSTATE NFA

3-DESIGN/DEVELOPMENT

Project: H.002567 - REGGIO CANAL BRIDGE

Type Impv: BRIDGE REPLACEMENT

Project Manager: OLIVIER, NICHOLAS

Remarks: 284-30-0023;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD LA 300 284-30 FBROFF 1,834 PRESERVATION

BRIDGE (ON SYSTEM)

1-PLANNING/ENVIRONMENTAL

Project: H.009573 - LA 39:LAKE BORGNE CANAL BR - LA 46

Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD LA 39 046-32 STPFLEX 2,614 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010406 - LA 46: ORLEANS P/L - PARIS RD

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: DEVILLE, JACQUES

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST BERNARD LA 46 046-03 NHPP 3,000 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 26 of 226

Page 33: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ST CHARLES

Project: H.009176 - LULING INTERSECTION SAFETY IMPROVEMENTS

Type Impv: PURCHASE AND INSTALL SIGNS AND SOLAR BEACONS

Project Manager: HOLM, RICK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES 000-45 SATRANS 10 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.009326 - I-10/610 BRIDGE REPAIRS & PAINTING

Type Impv: BRIDGE DECK PATHCING

Project Manager: TULLIER, DANNY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES I-10 450-14 FBR-ON/OFF 3,600 PRESERVATION

BRIDGE PREVENTIVE MAINTENANCE

4-SCHEDULED IN CURRENT FY 14-15

ST JOHN I-10 450-13 FBR-ON/OFF 510 PRESERVATION

BRIDGE PREVENTIVE MAINTENANCE

ORLEANS I-610 450-34 FBR-ON/OFF 2,100 PRESERVATION

BRIDGE PREVENTIVE MAINTENANCE

Project: H.009359 - BONNET CARRE'S SPILLWAY ATV RIDING AREA

Type Impv: RESTORATION AND CONSTRUCTION OF A MOTORIZED TRAIL SYSTEM

Project Manager: RIGGS, LAURA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES 000-45 RTP 199 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009453 - VARIOUS ROADS:SIGNING (ST. CHARLES)

Type Impv: SIGNAGE

Project Manager: HOLM, RICK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES 000-45 SATRANS 5 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.010780 - US 90: LA 306 - EARLY ST

Type Impv: COLD PLANE, OVERLAY, STRIPING, CURB

Project Manager: CHENEVERT, MARK

Remarks: PROJECT CONST. MUST BE COMPL & BILLS PAID BY DECEMBER 2

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES US 90 005-08 STGEN 2,173 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010843 - ORMOND BLVD PAVEMENT REHAB

Type Impv: COLD PLANE, ASPHALT PATCHING, OVERLAY EXISTING ASPHALT, N

Project Manager: DEVILLE, JACQUES

Remarks: ST. CHARLES PARISH TO PROVIDE MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES 000-45 STP>200K 4,284 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011010 - LA 628: ST. CHARLES PL - AIRLINE OVERLAY

Type Impv: THIN LIFT OVRLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 628 845-02 STPFLEX 498 PRESERVATION

ROAD PREVENTIVE MAINTENANCE

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011312 - US 90: MEDIAN CROSSOVER IMPROVEMENTS

Type Impv: ADD LEFT TURN LANES AT MEDIAN CROSSOVERS AND CLOSING OT

Project Manager: ROONEY, BRITTANY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES US 90 005-08 STGEN 1,080 PRESERVATION

NON-INTERSTATE

4-SCHEDULED IN CURRENT FY 14-15

ST CHARLES US 90 005-09 STGEN 84 PRESERVATION

NON-INTERSTATE

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 27 of 226

Page 34: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ST CHARLES

Project: H.011429 - LA 3141: LA 3127 - LA 18

Type Impv: MILLING, ASHALT OVERLAY, PATCHING, STRIPING

Project Manager: JOHNSON, ENNIS

Remarks: LETTER BID IN THE DISTRICT 11/20/2014

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 3141 845-19 NFABOND 300 PRESERVATION

NON-INTERSTATE NFA

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011677 - I-10 W ON BONNET CARRE MM 216

Type Impv: EMERGENCY BRIDGE RAIL REPLACEMENT

Project Manager: JOHNSON, ENNIS

Remarks: SECRETARY'S EMERGENCY LETTER DATED 9/24/2014

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES I-10 450-14 STGEN 100 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010498 - I-310: LULING BR DECK OVERLAY & REPAIR

Type Impv: REMOVE AND REPLACE BRIDGE DECK OVERLAY & STRUCTURAL REP

Project Manager: GUIDRY, CHRIS

Remarks: PRIORITY BRIDGE PROJECT

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES I-310 450-37 NHPP 10,000 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED FOR LETTING FY 15-16

ST CHARLES I-310 450-37 NHPP 10,000 PRESERVATION

INTERSTATE

Project: H.011022 - US 61 @ EVANGELINE RD.

Type Impv: RAISING ROADWAY GRADE

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES US 61 007-03 STPFLEX 250 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011230 - LA 48: INTERSECTION IMP @ RIVER OAKS DR

Type Impv: INTERSECTION IMPROVEMENTS AT RIVER OAKS DRIVE

Project Manager: BRASSET, DAVID

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 48 282-02 STP>200K 950 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011305 - US 61: LEFT TURN LANE AT LOG MILE 6.0

Type Impv: ADD LEFT TURN LANE

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES US 61 007-03 STPFLEX 350 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011442 - LA 3127: RIGHT TL @ ASPHALT PLANT RD

Type Impv: ADD RIGHT TURN LANE AND ACCELERATION LANE

Project Manager: GARY, VERTIE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 3127 428-03 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011472 - I-10 BONNET CARRE EMERGENCY CROSSINGS

Type Impv: EMERGENCY CROSSING UPGRADES

Project Manager: BANKSTON, TANYA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES I-10 450-14 NHPP 70 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011630 - LA 626: LA 48 TO US 61

Type Impv: ULTRA THIN OVERLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 626 282-31 STPFLEX 210 PRESERVATION

ROAD PREVENTIVE MAINTENANCE

4-SCHEDULED FOR LETTING FY 15-16

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 28 of 226

Page 35: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ST CHARLES

Project: H.011631 - LA 3060: US 90 TO LA 18

Type Impv: ULTRA THIN OVERLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 3060 845-18 STPFLEX 95 PRESERVATION

ROAD PREVENTIVE MAINTENANCE

4-SCHEDULED FOR LETTING FY 15-16

Project: H.009763 - ST CHARLES EBANK LEVEE MU PATH, PHASE 6

Type Impv: MULTI-USE PATH & RELATED WORK

Project Manager: MEEK, STEPHEN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES 000-45 TAP>200K 1,025 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011548 - LA 48: LOWERLINE ST. - PROSPECT AVE.

Type Impv: ADDING DRAINAGE STRUCTURES

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 48 282-02 STPFLEX 250 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

3-DESIGN/DEVELOPMENT

Project: H.011553 - LA 632: LA 306 - LA 631

Type Impv: ASPHALT OVERLAY, PATCHING, STRIPING

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 632 845-09 STPFLEX 500 PRESERVATION

NON-INTERSTATE NFA

3-DESIGN/DEVELOPMENT

Project: H.000320 - JEFFERSON PARISH LN. - LA 50

Type Impv: ULTRATHIN HMAC WEARING COURSE

Project Manager: RAY, JARED

Remarks: 007-03-0060;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES US 61 007-03 NHPP 1,688 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.004876 - LA 52: LA 18 - N OAK COURT

Type Impv: SAFETY AND TSM IMPROVEMENTS

Project Manager: DEVILLE, JACQUES

Remarks: DTSGE O COMPLETED UNDER DESIGN PHASE

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES 000-45 STP>200K 1,850 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

ST CHARLES 000-45 OTHER 1,850 URBAN SYSTEMS

Project: H.010413 - LA 48: ORMOND PLANTATION - WESCO ST

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 48 282-02 STPFLEX 1,750 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010416 - LA 3127: ST. JOHN P/L - 3700' W I-310

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 3127 428-03 STPFLEX 5,500 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010417 - LA 306: LA 18 - LA 632

Type Impv: COLD PLANE, GEOGRID & 4" OVERLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES LA 306 845-07 STPFLEX 3,600 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 29 of 226

Page 36: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - ST CHARLES

Project: H.010753 - US 90/I-310 INTERCHANGE

Type Impv: RECONSTRUCTION OF INTERCHANGE OR NEW FLYOVER RAMP

Project Manager: LANDRY, COREY

Remarks: MATCH FOR ENVIRONMENTAL FROM DOTD SURPLUS

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

ST CHARLES I-310 450-38 NFI 0 CAPACITY 1-PLANNING/ENVIRONMENTAL

ST CHARLES US 90 005-08 NFI 0 CAPACITY

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 30 of 226

Page 37: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - TERREBONNE

Project: H.009462 - VARIOUS ROADS:SIGNING (TERREBONNE)

Type Impv: SIGNAGE

Project Manager: HOLM, RICK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE 000-55 SATRANS 32 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.009569 - LA 182: MAIN ST - LA 316

Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 182 005-05 STPFLEX 2,025 PRESERVATION

NON-INTERSTATE

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011397 - LA 3011: LA 57 - MAYFIELD RD

Type Impv: SUPERPAVE ASPHALTIC CONCRETE OVERLAY

Project Manager: JOHNSON, ENNIS

Remarks: LETTER BID IN THE DISTRICT 10/23/2014

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 3011 855-13 NFABOND 400 PRESERVATION

NON-INTERSTATE NFA

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011465 - LA 665: TREE & STUMP REMOVAL

Type Impv: TREE AND STUMP REMOVAL

Project Manager: GALATAS, JOEL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 665 855-09 SATRANS 117 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011666 - TERREBONNE PARISH SIGNING (HOUMA)

Type Impv: PURCHASE AND INSTALL REGULATORY AND WARNING SIGNS.

Project Manager: HOLM, RICK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE 000-55 SATRANS 20 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.007351 - COUNTRY DRIVE WIDENING PHASE A

Type Impv: WIDENING

Project Manager: HANKS, ANNA

Remarks: 742-55-0102;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE 000-55 STP<200K 4,000 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010398 - LA 57:LA 3011-LA 56

Type Impv: SUPERPAVE ASPHALTIC CONCRETE OVERLAY

Project Manager: CHENEVERT, MARK

Remarks: AC WITH NFA AND USE NFA AS MATCH

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 57 246-01 STPFLEX 1,299 PRESERVATION

NON-INTERSTATE NFA

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011441 - LA 3185: RIGHT TURN LANE AT LA 20

Type Impv: ADD RIGHT TURN LANE ON LA 3185 AT LA 20

Project Manager: GARY, VERTIE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 3185 855-17 STPFLEX 100 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011443 - LA 56: RIGHT TURN LANE AT LA 24

Type Impv: ADD RIGHT TURN LANE ON LA 56 AT LA 24

Project Manager: GARY, VERTIE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 56 247-03 STPFLEX 150 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

4-SCHEDULED FOR LETTING FY 15-16

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 31 of 226

Page 38: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - TERREBONNE

Project: H.011560 - LA 55:1.65 MI S MADISON CANAL - EXXON RD

Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING

Project Manager: CHENEVERT, MARK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 55 248-02 NFA 1,600 PRESERVATION

NON-INTERSTATE NFA

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011637 - US 90: 1.5 MI E LA 20 - 0.3 MI W LA 309

Type Impv: ULTRA THIN OVERLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE US 90 424-07 NHPP 800 PRESERVATION

ROAD PREVENTIVE MAINTENANCE

4-SCHEDULED FOR LETTING FY 15-16

Project: H.001498 - LA 24 & LA 316: COMPANY CANAL BRIDGE

Type Impv: BRIDGE REPLACEMENT

Project Manager: PAINE, PEGGY JO

Remarks: 065-91-0017;STAGE 0 FEASIBILITY STUDY

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 24 065-91 STPFLEX 16,700 PRESERVATION

BRIDGE (ON SYSTEM)

3-DESIGN/DEVELOPMENT

Project: H.005043 - LA311: LA 664 (ST CHARLES ST)-SAVANNE RD

Type Impv: WIDEN TO 4 LANES

Project Manager: BROWN, JEFF

Remarks: 700-55-0122

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 311 413-01 NFI 38,000 CAPACITY 3-DESIGN/DEVELOPMENT

Project: H.009660 - LA 311/312: US 90 - LA 24

Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PA

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 311 413-30 STPFLEX 844 PRESERVATION

NON-INTERSTATE

3-DESIGN/DEVELOPMENT

Project: H.009766 - WPARK AVE: ROYCE ST-MARIETTA PL SIDEWALK

Type Impv: SIDEWALKS, SUBSURFACE DRAINAGE & RELATED WORK

Project Manager: MEEK, STEPHEN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 24 065-04 TAP<200K 959 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.010890 - LA 182: ROUNDABOUT AT HOLLYWOOD RD

Type Impv: ADD ROUNDABOUT

Project Manager: HARROUCH, JOSHUA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 182 005-05 STPFLEX 600 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

3-DESIGN/DEVELOPMENT

Project: H.010997 - LA 3185: IMP @ MAIN PROJECT RD

Type Impv: INTERSECTION IMPROVEMENTS

Project Manager: HARROUCH, JOSHUA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 3185 855-17 STPFLEX 150 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

3-DESIGN/DEVELOPMENT

Project: H.011159 - CAROLL STREET AND BUQUET STREET BRIDGES

Type Impv: BRIDGE REPLACEMENT - NO ADDED CAPACITY

Project Manager: PENTEK, GARY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE 000-55 FBROFF 939 PRESERVATION

BRIDGE (OFF SYSTEM)

3-DESIGN/DEVELOPMENT

TERREBONNE 000-55 FBROFF 585 PRESERVATION

BRIDGE (OFF SYSTEM)

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 32 of 226

Page 39: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - TERREBONNE

Project: H.011187 - DISTRICT 02H: SIGNAL TIMING

Type Impv: SIGNAL TIMING

Project Manager: HARROUCH, JOSHUA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 24 065-04 STPFLEX 2 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

3-DESIGN/DEVELOPMENT

TERREBONNE LA 3040 065-30 STPFLEX 1 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

TERREBONNE LA 24 065-91 STPFLEX 1 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

LAFOURCHE LA 1 064-06 STPFLEX 2 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: H.011533 - N. BAYOU BLACK DRIVE / HANSON CANAL

Type Impv: BRIDGE REPLACEMENT

Project Manager: PENTEK, GARY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE 000-55 FBROFF 524 PRESERVATION

BRIDGE (OFF SYSTEM)

3-DESIGN/DEVELOPMENT

Project: H.002238 - ROBINSON CANAL BRIDGE

Type Impv: BRIDGE REPLACEMENT

Project Manager: CAVALIER, STEPHANIE

Remarks: 247-01-0009;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 56 247-01 FBROFF 1,200 PRESERVATION

BRIDGE (ON SYSTEM)

1-PLANNING/ENVIRONMENTAL

Project: H.002244 - BOUDREAUX CANAL BRIDGE

Type Impv: BRIDGE REPLACEMENT

Project Manager: KEMP, KELLY

Remarks: 247-02-0030;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 56 247-02 STPFLEX 30,000 PRESERVATION

BRIDGE (ON SYSTEM)

1-PLANNING/ENVIRONMENTAL

Project: H.005039 - LA 3040 (REPLACE TUNNEL)

Type Impv: STATE FUND FOR STUDY

Project Manager: NGUYEN, WAYNE

Remarks: 700-55-0118;FEASIBILITY STUDY STAGE 0

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE 000-55 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.008411 - BAYOU TERREBONNE BR (LA 660)

Type Impv: BRIDGE REPLACEMENT

Project Manager: PICARD, TOBY

Remarks: 855-07-0010;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 660 855-07 STPFLEX 507 PRESERVATION

BRIDGE (ON SYSTEM)

1-PLANNING/ENVIRONMENTAL

Project: H.009568 - LA 660:US 90 - LA 316

Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PA

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 660 855-07 STPFLEX 1,125 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.009659 - US 90: 1.5 MI E LA 20 - 0.3 MI W LA 309

Type Impv: 3/4" THIN OVERLAY

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE US 90 424-07 NHPP 800 PRESERVATION

ROAD PREVENTIVE MAINTENANCE

1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 33 of 226

Page 40: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - TERREBONNE

Project: H.010328 - LA 659: HOWARD BRIDGE-DAIGLEVILLE BRIDGE

Type Impv: CB-06 TOP MODIFICATIONS, CROSS DRAIN REMOVAL AND REPLACEM

Project Manager: GOLZ, SARAH

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 659 855-04 STPFLEX 200 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

1-PLANNING/ENVIRONMENTAL

Project: H.010410 - LA 24: LA 20 - LA 664 (SB)

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 24 065-04 NHPP 4,000 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010411 - LA 24: LA 55 - PROSPECT STREET BRIDGE

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 24 065-91 STPFLEX 4,500 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.010412 - LA 57: THOMPSON RD - CEDAR GROVE RD

Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE

Project Manager: RAY, JARED

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE LA 57 246-01 STPFLEX 1,750 PRESERVATION

NON-INTERSTATE

1-PLANNING/ENVIRONMENTAL

Project: H.011005 - HOUMA MPO TRAVEL DEMAND MANAGEMENT 2013

Type Impv: PROMOTE COMMUTER CARPOOLING AND VANPOOLING/FLEX TIME

Project Manager: JOHNS, MATT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

TERREBONNE 000-55 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 34 of 226

Page 41: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - DISTRICTWIDE 02

Project: H.011233 - DISTRICT 02 LOW COST SAFETY IMPROVEMENTS

Type Impv: ENHANCED SIGNING AND STRIPING

Project Manager: RENARD, APRIL

Remarks: AC. CONVERT TO HSIPPEN IN FFY 2015.

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 HSIPPEN 1,069 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011407 - DISTRICT 02H CONTROLLER UPGRADE

Type Impv: UPGRADE OF EXISTING SIGNAL CONTROLLERS.

Project Manager: LEBLANC, GARY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 STPFLEX 181 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011625 - PUBLIC EDUC, OUTREACH, PLANNING (NO RPC)

Type Impv: CLEANER TRANSPORTATION FOR THE MARITIME AND ENERGY INDUS

Project Manager: REVIERE, RYAN

Remarks: USE LOCAL AS MATCH; ALL WORK WILL BE IN PHASE 5

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 0 CONGESTION MITIGATION 4-SCHEDULED FOR LETTING FY 15-16

Project: H.009054 - DIST. 02 PAVEMENT MARKING REPLACEMENT II

Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MAKERS

Project Manager: COLVIN, JODY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

3-DESIGN/DEVELOPMENT

Project: H.009186 - DIST. 02 PAVEMENT MARKING REPLACE III:

Type Impv: PLASTIC PAVEMENT STRIPING AND RAVISED PAVEMENT MARKERS

Project Manager: COLVIN, JODY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

3-DESIGN/DEVELOPMENT

Project: H.011406 - DISTRICT 02BC CONTROLLER UPGRADE

Type Impv: UPGRADE OF EXISTING SIGNAL CONTROLLERS.

Project Manager: LEBLANC, GARY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 STPFLEX 331 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

3-DESIGN/DEVELOPMENT

Project: H.011535 - NEW ORLEANS TRAVEL TIME (BLUETOOTH)

Type Impv: BLUETOOTH EQUIPMENT IN DISTRICT 02

Project Manager: BANKSTON, TANYA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

3-DESIGN/DEVELOPMENT

Project: H.005158 - FUTURE I-49 SOUTH (RACELAND TO WESTBANK

Type Impv: UPRGRADING US 90 FOR FUTURE I-49 SOUTH

Project Manager: MUSA, ELNUR

Remarks: 700-92-0011; EIS

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.005164 - SMART GROWTH STRATEGIES LAND USE

Type Impv: LAND USE STUDY

Project Manager: NGUYEN, WAYNE

Remarks: 700-92-0017;STAGE O UNDER WAY

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 35 of 226

Page 42: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 02 BRIDGE CITY - DISTRICTWIDE 02

Project: H.005167 - LONG-RANGE TRANSPORTATION STRATEGY

Type Impv: GROWTH MANAGEMENT STUDY

Project Manager: NGUYEN, WAYNE

Remarks: 700-92-0020;PRE STAGE 0

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.005168 - NEW ORLEANS RAIL GATEWAY EIS

Type Impv: EIS

Project Manager: GOODELL, DEAN

Remarks: STATE & RR EACH PUTTING UP 10% OF MATCH FOR DEMO

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.009731 - L/CNG FUEL FLEETS DISTRICT 02

Type Impv: FLEET CONVERSION TO CNG

Project Manager: AMBEAU, JAUBERT

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: H.010170 - SMART GROWTH PLANNING

Type Impv: TRANSPORTATION PLANNING - LAND USE EDUCATION

Project Manager: NGUYEN, WAYNE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

DISTRICTWIDE 02 000-92 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 36 of 226

Page 43: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 99 STATEWIDE - STATEWIDE

Project: H.010690 - M/V LEVY:DRY-DOCK -5 YEAR EXAM & REPOWER

Type Impv: DRY-DOCK FOR USCG 5 YEAR EXAM & REPOWER

Project Manager: REED, KEVIN

Remarks: 2012 FHWA FBD AWARD TRANSFERRED TO FTA

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 1,350 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.010691 - MV STUMPF: DRY-DOCK: 5 YR EXAM & REPOWER

Type Impv: DRY-DOCK FOR USCG 5 YEAR EXAM & REPOWER

Project Manager: REED, KEVIN

Remarks: FUNDS TRANSFERRED FROM FHWA TO FTA

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 1,250 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.010903 - LRSP TECH ASSISTANCE CRASH DATA ENGR

Type Impv: LRSP TECH ASSISTANCE CRASH DATA ENGR

Project Manager: CHAPMAN, JIM

Remarks: USE SATRANS FUNDS

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 SAFETY

LOCAL ROADS SAFETY

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011006 - STATEWIDE TUNNEL INSPECTION

Type Impv: STATEWIDE INSPECTION OF TUNNELS, PLAN DEVELOPMENT

Project Manager: BROWN, HAYLYE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 PRESERVATION

BRIDGE (ON SYSTEM)

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011318 - M/V CAMERON II: 5 YEAR DRYDOCK (2015)

Type Impv: DRY-DOCK FOR USCG 5 YEAR EXAM

Project Manager: REED, KEVIN

Remarks: EQUIPMENT NUMBER: 10006958

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 750 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED IN CURRENT FY 14-15

STATEWIDE 000-99 STCASH 49 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

Project: H.011331 - OVERHEAD SIGN TRUSS INVENTORY/INSPECTION

Type Impv: INVENTORY/INSPECTION OF OVERHEAD SIGN TRUSSES

Project Manager: BROWN, HAYLYE

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011333 - M/V ST.FRANCISVILLE: 5 YEAR DRYDOCK 2014

Type Impv: DRY-DOCK FOR USCG 5 YEAR EXAM

Project Manager: REED, KEVIN

Remarks: EQUIPMENT NUMBER: 10006959

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 723 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED IN CURRENT FY 14-15

STATEWIDE 000-99 STCASH 49 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

Project: H.011521 - ITS ATMS SYSTEM REPORTING & SUPPORT SVC

Type Impv: ITS ATMS REPORTING AND SYSTEM SUPPORT

Project Manager: FERRIER, CARRYN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011566 - TRAFFIC SIGNAL CONTROL SOFTWARE

Type Impv: REPLACE STREETWISE SOFTWARE WITH ATMS.NOW

Project Manager: FERRIER, CARRYN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 STPFLEX 750 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED IN CURRENT FY 14-15

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 215 of 226

Page 44: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 99 STATEWIDE - STATEWIDE

Project: H.011567 - ITS VIDEO SYSTEM SUPPORT

Type Impv: SUPPORT FOR ITS VIDEO SYSTEMS AND VIDEO WALL EQUIP

Project Manager: FERRIER, CARRYN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011568 - LADOTD TOLL OPERATIONS BUSINESS PLAN

Type Impv: DEVELOP A BUSINESS PLAN FOR LADOTD TOLL OPERATIONS

Project Manager: FERRIER, CARRYN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED IN CURRENT FY 14-15

Project: H.011629 - ALTERNATIVE DELIVERY SUPPORT SERVICES

Type Impv: EVERY DAY COUNTS INITIATIVE

Project Manager: BURST, JEFFERY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

STATEWIDE 000-99 0 OTHER / MISCELLANEOUS

Project: H.009884 - NOGC (STATEWIDE)

Type Impv: RELOCATING LED CROSSBUCK ASSEMBLIES

Project Manager: SHREWSBERRY,BILL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 RAIL HE 250 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010689 - CCC FERRY VESSEL: TERM/LAND TECH UPGRADE

Type Impv: TECHNOLOGY IMPROVEMENTS TO FERRY VESSELS AND TERMINAL L

Project Manager: REED, KEVIN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 200 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.010694 - INSTALL AND MODIFY BARGES AND FERRIES

Type Impv: MODIFICATION, INSTALLATION LANDING BARGE,CONVERSION TO FE

Project Manager: REED, KEVIN

Remarks: FB DISCR FLEXED TO FTA THEREFORE NOT AUTH THROUGH FHW

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 420 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED FOR LETTING FY 15-16

STATEWIDE 000-99 OTHER 330 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

Project: H.011247 - UPDATES TO GIS HISTORIC SITES DATABASE

Type Impv: UPDATE THE STATE GIS DATABASE FOR HISTORIC SITES

Project Manager: ARDOIN, NOEL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OTHER / MISCELLANEOUS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011325 - IC SEVERAL RR XINGS (STATEWIDE)

Type Impv: INSTALL CBAS AT IC'S PASSIVE PUBLIC CROSSINGS.

Project Manager: SHREWSBERRY,BILL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 RAIL PD 250 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011473 - BARGE 305-068: DRY-DOCK FOR REPAIRS

Type Impv: DRY-DOCK FERRY LANDING BARGE FOR MAINTENANCE AND REPAIR

Project Manager: REED, KEVIN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 200 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED FOR LETTING FY 15-16

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 216 of 226

Page 45: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 99 STATEWIDE - STATEWIDE

Project: H.011474 - BARGE 305-069: DRY-DOCK FOR REPAIRS

Type Impv: DRY-DOCK FERRY LANDING BARGE FOR MAINTENANCE AND REPAIR

Project Manager: REED, KEVIN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 200 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011475 - M/V NEW ROADS: 5 YEAR DRYDOCK (2016)

Type Impv: DRY-DOCK FERRY FOR 5 YEAR USCG EXAMS, MAINTENANCE & REPA

Project Manager: REED, KEVIN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 FB DISCR 1,125 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011478 - BARGE 305-008: DRYDOCK FOR REPAIRS

Type Impv: DRYDOCK WORK BARGE 305-008 FOR REPAIRS

Project Manager: REED, KEVIN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 STCASH 250 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011479 - M/V GRIFFITH: DRYDOCK FOR REPAIRS

Type Impv: DRYDOCK TUGBOAT M/V GRIFFITH FOR REPAIRS

Project Manager: REED, KEVIN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 STCASH 150 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011480 - M/V GRAND: DRYDOCK FOR REPAIRS

Type Impv: DRYDOCK M/V GRAND FOR REPAIRS.

Project Manager: REED, KEVIN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 STCASH 150 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011489 - STATEWIDE: SYSTEMIC CURVE PROJECT

Type Impv: SIGNING, PAVEMENT MARKINGS, RUMBLE STRIPS, RPMS, AND HFSTS

Project Manager: RENARD, APRIL

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 HSIPPEN 3,000 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011538 - ROADWAY SAFETY AND INCIDENT PATROL (RSIP

Type Impv: MOTORIST ASSISTANCE

Project Manager: KIMBENG, LUCY

Remarks: WILL BE FOR SFY 2016, 2017, 2018, 2019

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 NHPP 3,600 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

4-SCHEDULED FOR LETTING FY 15-16

Project: H.011537 - STATEWIDE ITS MAINTENANCE

Type Impv: THIS IS A 3 YEAR MAINTENANCE CONTRACT FOR ITS EQUIPMENT.

Project Manager: SMITH, ERIK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 STPFLEX 3,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

3-DESIGN/DEVELOPMENT

Project: H.007026 - ITS MAINTENANCE - STATEWIDE

Type Impv: ROUTINE & EMERGENCY REPAIR TO ITS STATEWIDE SYSTEM

Project Manager: SMITH, ERIK

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 STPFLEX 1,847 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

2-WAITING FOR FUNDING

STATEWIDE 000-99 STPFLEX 1,617 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

STATEWIDE 000-99 STPFLEX 1,617 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 217 of 226

Page 46: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 99 STATEWIDE - STATEWIDE

Project: H.010052 - BR - NO INTERCITY RAIL

Type Impv: FEASIBILITY STUDY

Project Manager: BROUSSARD, DAN

Remarks: NEW ORLEANS MPO TO PROVIDE MATCH TO BTR STP>200K

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.010053 - BR - NO INTERCITY RAIL

Type Impv: FEASIBILITY STUDY

Project Manager: BROUSSARD, DAN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.005734 - LA 447 CORRIDOR STUDY

Type Impv: TRAFFIC ANALYSIS

Project Manager: COLVIN, JODY

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

Project: H.006881 - WEIGH STATION SEWER TREATMENT EQU.

Type Impv: NEW SEWER TREATMENT EQU. STATEWIDE

Project Manager: MCCOY, JANET

Remarks: 737-99-0823;

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 NHPP 350 OPER EFFICIENCY/MOTORIST ASSISTANCE

WEIGH STATIONS

1-PLANNING/ENVIRONMENTAL

Project: H.010037 - NEW FERRY BOAT / CAMERON FERRY CROSSING

Type Impv: CONSTRUCT NEW FERRY BOAT

Project Manager: REED, KEVIN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 NFI 12,500 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

1-PLANNING/ENVIRONMENTAL

Project: H.011177 - INTERCHANGE TRAFFIC COUNTS: PHASE 2

Type Impv: ANALYZE INTERCHANGES TO IMPROVE TRAFFIC FLOW &SAFETY @

Project Manager: HARROUCH, JOSHUA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

Project: H.011180 - INTERCHANGE TRAFFIC COUNTS: PHASE 1

Type Impv: ANALYZE INTERCHANGES TO IMPROVE TRAFFIC FLOW &SAFETY @

Project Manager: HARROUCH, JOSHUA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

Project: H.011181 - INTERCHANGE TRAFFIC COUNTS: PHASE 3

Type Impv: ANALYZE INTERCHANGES TO IMPROVE TRAFFIC FLOW &SAFETY @

Project Manager: HARROUCH, JOSHUA

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

1-PLANNING/ENVIRONMENTAL

Project: H.011334 - 511 ATIS SYSTEM

Type Impv: DEVELOP CONOPS, FUNC. REQUIREMENTS AND RFP

Project Manager: FERRIER, CARRYN

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

1-PLANNING/ENVIRONMENTAL

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 218 of 226

Page 47: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 00 L-PROJECTS - L-PROJECTS

Project: L.000001 - INTERMODAL CONNECTORS PROGRAM

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 3,100 INTERMODAL CONNECTOR STAGES 4, 3, 2, 1, 0

- NHPP 6,200 INTERMODAL CONNECTOR

Project: L.000002 - INTERSTATE PAVEMENT PREVENTIVE MAINT

Type Impv: SURFACE IMP, PM, REPAIR FOR PAVEMENT/EMBANKMENT

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 1,000 PRESERVATION

INTERSTATE

STAGES 4, 3, 2, 1, 0

Project: L.000003 - PREVENTIVE MAINTENANCE NON-INTERSTATE

Type Impv: PREVENTIVE MAINTENANCE/REHABILITATION

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 2,000 PRESERVATION

NON-INTERSTATE

STAGES 4, 3, 2, 1, 0

Project: L.000004 - PREVENTIVE MAINT NON-INTERSTATE (NFA)

Type Impv: PREVENTIVE MAINTENANCE/REHABILITATION

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NFA 2,500 PRESERVATION

NON-INTERSTATE NFA

STAGES 4, 3, 2, 1, 0

Project: L.000005 - ROAD PREVENTIVE MAINTENANCE

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 4,400 PRESERVATION

ROAD PREVENTIVE MAINTENANCE

STAGES 4, 3, 2, 1, 0

- STCASH 6,000 PRESERVATION

ROAD PREVENTIVE MAINTENANCE

Project: L.000006 - MOTORIST ASSISTANCE PATROL

Type Impv: MAP

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 1,200 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

STAGES 4, 3, 2, 1, 0

- STCASH 1 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

Project: L.000007 - TRANSPORTATION SYSTEMS MANAGEMENT

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 250 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

STAGES 4, 3, 2, 1, 0

- STCASH 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRANSPORTATION SYSTEMS MANAGEMENT

Project: L.000008 - URBAN SYSTEM PROJECTS

Type Impv: SELECTED BY MPO'S

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STP>200K 1,000 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

- STP<200K 1,000 URBAN SYSTEMS

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 220 of 226

Page 48: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 00 L-PROJECTS - L-PROJECTS

Project: L.000009 - MISC BOND PROJECTS

Type Impv: AS APPROVED BY LEGISLATURE

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STBONDS 1,000 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000010 - URGENT BRIDGE REPAIR/REPLACEMENT

Type Impv: REIMBURSABLE AND NON-REIMBURSABLE

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- REIMB 5,000 PRESERVATION

BRIDGE (ON SYSTEM)

STAGES 4, 3, 2, 1, 0

- NHPP 1,000 PRESERVATION

BRIDGE (ON SYSTEM)

- STPFLEX 1,000 PRESERVATION

BRIDGE (ON SYSTEM)

- STCASH 1,000 PRESERVATION

BRIDGE (ON SYSTEM)

Project: L.000011 - BRIDGE PREVENTIVE MAINTENANCE

Type Impv: MAINTENANCE

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 1,500 PRESERVATION

BRIDGE (ON SYSTEM)

STAGES 4, 3, 2, 1, 0

- STPFLEX 1,500 PRESERVATION

BRIDGE (ON SYSTEM)

- STCASH 1 PRESERVATION

BRIDGE (ON SYSTEM)

Project: L.000012 - BRIDGE PAINTING PROGRAM

Type Impv: MISC SITES

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 1,000 PRESERVATION

BRIDGE (ON SYSTEM)

STAGES 4, 3, 2, 1, 0

- STCASH 1 PRESERVATION

BRIDGE (ON SYSTEM)

Project: L.000013 - MOVABLE BRIDGE PREVENTIVE MAINTENANCE

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STCASH 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

MOVABLE BRIDGE REHABILITATION

STAGES 4, 3, 2, 1, 0

Project: L.000014 - MISC ECONOMIC DEVELOPMENT INITIATIVES

Type Impv: IN CONJUNCTION WITH DED

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STCASH 500 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

- STBONDS 500 OTHER / MISCELLANEOUS

Project: L.000015 - MISC FERRY PROJECTS

Type Impv: REHABILITATION/REPAIR

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- OTHER 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

STAGES 4, 3, 2, 1, 0

- STCASH 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

FERRY PROJECTS

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 221 of 226

Page 49: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 00 L-PROJECTS - L-PROJECTS

Project: L.000016 - FEDERAL SAFETY PROGRAMS

Type Impv: MISC PROJECTS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- HSIP 300 SAFETY STAGES 4, 3, 2, 1, 0

- STPFLEX 200 SAFETY

- STCASH 100 SAFETY

Project: L.000017 - MISC ITS SYSTEMS

Type Impv: ENGINEERING, CONSTRUCTION, MAINTENANCE, OPERATIONS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

STAGES 4, 3, 2, 1, 0

- DEMO 300 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

- CM 400 OPER EFFICIENCY/MOTORIST ASSISTANCE

ITS

Project: L.000018 - INTERSTATE LIGHTING PROGRAM

Type Impv: IN ACCORDANCE WITH MAINTENANCE AGREEMENTS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

INTERSTATE LIGHTING

STAGES 4, 3, 2, 1, 0

- STCASH 100 OPER EFFICIENCY/MOTORIST ASSISTANCE

INTERSTATE LIGHTING

Project: L.000019 - STATE PARK ROADS

Type Impv: OVERLAY/REHABILITATION

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STBONDS 100 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000020 - MISC DRAINAGE PROJECTS

Type Impv: TO ALLEVIATE FLOODING

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

STAGES 4, 3, 2, 1, 0

- STCASH 250 OPER EFFICIENCY/MOTORIST ASSISTANCE

ROADWAY FLOODING

Project: L.000021 - MISC FEDERAL PROJECTS/PROGRAMS

Type Impv: FEDERAL LANDS HIGHWAYS, ETC.

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- FLH 500 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000022 - RAILROAD CROSSING IMPROVEMENTS

Type Impv: FEDERAL RAILROAD CROSSING IMPROVEMENTS PROGRAM

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- RAIL HE 3,000 RAILROADS STAGES 4, 3, 2, 1, 0

- RAIL PD 3,000 RAILROADS

- STPFLEX 2,000 RAILROADS

- STCASH 200 RAILROADS

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 222 of 226

Page 50: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 00 L-PROJECTS - L-PROJECTS

Project: L.000025 - TOLL FUNDED PROJECTS

Type Impv: ORLEANS AND JEFFERSON PARISHES

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- TOLLS 1,000 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000026 - WETLAND MITIGATION BANK

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STCASH 1,000 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

- TIME 1,000 OTHER / MISCELLANEOUS

Project: L.000027 - EMERGENCY RELIEF PROVIDED BY CONGRESS

Type Impv: EMERGENCY RELIEF

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- ER 100 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000028 - MAINTENANCE MATERIALS

Type Impv: HOT MIX, PIPE, BRIDGE MATERIAL, ETC

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STCASH 5,000 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000029 - FEDERAL ENHANCEMENT PROGRAM

Type Impv: MISC PROJECTS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- TAPFLEX 1,000 ENHANCEMENTS STAGES 4, 3, 2, 1, 0

Project: L.000030 - CRASH ATTENUATOR REPAIRS

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 200 SAFETY STAGES 4, 3, 2, 1, 0

- STCASH 100 SAFETY

Project: L.000031 - DEMO/HI-PRI/OTHER FEDERAL PROGRAMS

Type Impv: AS DEFINED BY FEDERAL GOVERNMENT

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- DEMO 10,000 DEMO / HIGH PRIORITY STAGES 4, 3, 2, 1, 0

Project: L.000032 - REST AREA REHABILITATION

Type Impv: FACILITY REHABILITATION

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

REST AREAS

STAGES 4, 3, 2, 1, 0

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 223 of 226

Page 51: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 00 L-PROJECTS - L-PROJECTS

Project: L.000033 - MISC SIGNS, STRIPING, SIGNALS

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

STAGES 4, 3, 2, 1, 0

- STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

Project: L.000034 - INSTALL RAISED PAVEMENT MARKERS

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STCASH 2,000 OPER EFFICIENCY/MOTORIST ASSISTANCE

TRAFFIC CONTROL DEVICES

STAGES 4, 3, 2, 1, 0

Project: L.000035 - MISC FEDERAL OFF-SYSTEM BRIDGES

Type Impv: BRIDGE REPLACEMENTS/INSPECTIONS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- FBROFF 1,000 PRESERVATION

BRIDGE (OFF SYSTEM)

STAGES 4, 3, 2, 1, 0

- STCASH 200 PRESERVATION

BRIDGE (OFF SYSTEM)

Project: L.000036 - WEIGH STATION REHABILITATION/UPGRADE

Type Impv: MISC SITES STATEWIDE

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 1,900 OPER EFFICIENCY/MOTORIST ASSISTANCE

WEIGH STATIONS

STAGES 4, 3, 2, 1, 0

Project: L.000037 - HIGHWAY SAFETY IMPROVEMENTS

Type Impv: RUMBLE STRIPS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 2,000 SAFETY STAGES 4, 3, 2, 1, 0

Project: L.000039 - ACCELERATED LOADING FACILITY

Type Impv: CONSTRUCT TEST SECTIONS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 50 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000040 - FEDERAL BRIDGE INSPECTION PROGRAMS

Type Impv: INSPECTIONS, RATINGS, LOAD FACTORS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 3,000 PRESERVATION

BRIDGE (ON SYSTEM)

STAGES 4, 3, 2, 1, 0

- STCASH 600 PRESERVATION

BRIDGE (ON SYSTEM)

Project: L.000041 - CONGESTION MITIGATION PROJECTS

Type Impv: NON-ATTAINMENT AREAS

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- CM 1,000 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 224 of 226

Page 52: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 00 L-PROJECTS - L-PROJECTS

Project: L.000042 - MISC CONGESTION MITIGATION PROJ - LKC

Type Impv: IN LAKE CHARLES AS APPROVED BY FHWA

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- CM 500 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

Project: L.000043 - MISC CONGESTION MITIGATION PROJ - BTR

Type Impv: IN BATON ROUGE AS APPROVED BY FHWA

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- CM 1,000 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

Project: L.000068 - ACCESS MANAGEMENT PROJECTS

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STPFLEX 2,500 OPER EFFICIENCY/MOTORIST ASSISTANCE

ACCESS MANAGEMENT

STAGES 4, 3, 2, 1, 0

- STPFLEX 2,500 OPER EFFICIENCY/MOTORIST ASSISTANCE

ACCESS MANAGEMENT

- STPFLEX 8,300 OPER EFFICIENCY/MOTORIST ASSISTANCE

ACCESS MANAGEMENT

- STPFLEX 8,100 OPER EFFICIENCY/MOTORIST ASSISTANCE

ACCESS MANAGEMENT

Project: L.000069 - ROAD TRANSFER PROGRAM

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- STCASH 1,000 ROAD TRANSFER STAGES 4, 3, 2, 1, 0

- STPFLEX 1,000 ROAD TRANSFER

Project: L.000093 - STATEWIDE CONGESTION MITIGATION

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- CM 5,500 CONGESTION MITIGATION STAGES 4, 3, 2, 1, 0

Project: L.000094 - URBAN TRANSIT(INCL TRANSFER TO AGENCIES)

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- CM 100 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

- STP<200K 100 URBAN SYSTEMS

- STPFLEX 100 URBAN SYSTEMS

Project: L.000024 - SOFT SIDE SAFETY

Type Impv: HANDLED THROUGH OPERATIONS BUDGET

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- HSIP 1,000 SAFETY STAGES 2, 1, 0

- STCASH 500 SAFETY

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 225 of 226

Page 53: HIGHWAY PROGRAM FY 2015-2016 · 2016. 1. 13. · FY 2015-2016 DISTRICT 02 (PRELIMINARY - FOR REVIEW) INTRODUCTION ... projects that are scheduled for construction letting in FY 2015-16.

DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16DISTRICT 00 L-PROJECTS - L-PROJECTS

Project: L.000038 - PLANNING, TRAINING AND RESEARCH

Type Impv: HANDLED THROUGH OPERATING BUDGET

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- SPR MAND 7,000 OTHER / MISCELLANEOUS STAGES 2, 1, 0

- SPR OPT 7,000 OTHER / MISCELLANEOUS

Project: L.000023 - SCOPING AND ENVIRONMENTAL STUDIES

Type Impv:

Project Manager:

Remarks:

StageCategory/SubCategoryCon Est x$1000FundCtrl SecRouteParish

- NHPP 400 OTHER / MISCELLANEOUS STAGES 1, 0

- STPFLEX 300 OTHER / MISCELLANEOUS

- STCASH 300 OTHER / MISCELLANEOUS

Report Date: 9/25/2014 6:19:17AMVersion No: 1.14.1Page 226 of 226