High Voltage Transmission Construction Supervision

download High Voltage Transmission Construction Supervision

of 45

description

How to QC High Voltage transmission construction

Transcript of High Voltage Transmission Construction Supervision

  • 5/20/2018 High Voltage Transmission Construction Supervision

    1/45

    - Simple - Inspiring - Performing - Phenomenal -8/26/2010Spv KonstSplTriyoso

    Belajar Untuk Berbagi 1

    SUPERVISI KONSTRUKSI SIPILTRANSMISI (SUTT DAN SUTET)

  • 5/20/2018 High Voltage Transmission Construction Supervision

    2/45

    - Simple - Inspiring - Performing - Phenomenal -2

    DAFTAR TAYANGAN

    I. PENDAHULUAN

    II. PONDASI TOWER TRANSMISI

    III. DINDING PENAHAN TANAH (TURAP)

    IV. SUPERVISI GALIAN PONDASI & DEWATERING

    V. SUPERVISI STUB SETTING & PEKERJAAN BETON BERTULANG

    VI. SUPERVISI PENIMBUNAN & PEMADATAN TANAH.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    3/45

    - Simple - Inspiring - Performing - Phenomenal -3

    TUJUAN PEMBELAJARAN

    SETELAH MENGIKUTI PENDIDIKAN INI PARA

    PESERTA MAMPU MELAKSANAKAN

    SUPERVISI (PENGAWASAN) PEKERJAAN

    SIPIL KONSTRUKSI TRANSMISI

  • 5/20/2018 High Voltage Transmission Construction Supervision

    4/45

    - Simple - Inspiring - Performing - Phenomenal -

    4

    I. SUPERVISOR

    DIFINISI UMUM:

    Adalah seseorang/pejabat yang ditunjukoleh pengguna barang dan jasa yang diberi

    kewenangan untuk melakukan

    pengawasan dan pemeriksaan terhadap

    pelaksanaan pekerjaan yang sudah dan

    sedang dilaksanakan oleh pihak penyedia

    barang/jasa.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    5/45

    - Simple - Inspiring - Performing - Phenomenal -5

    TUJUAN SUPERVISI

    Agar supaya pelaksanaan pekerjaan

    berjalan dengan lancar dan baik sesuaidengan yang direncanakan, baik dari

    segi mutu, biaya dan selesai tepat

    waktu serta tertib administrasi.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    6/45

    - Simple - Inspiring - Performing - Phenomenal -8/26/2010Spv Konst SplTriyoso 6

    Pengawas pekerjaan bertugas mengawasi pekerjaan

    konstruksi dari segi kualitas, kuantitas dan lajunya

    mencapai penyelesaian volume dari keseluruhan

    pekerjaan yang dikerjakan serta tertib dalam pelaksanaanadministrasi.

    Termasuk didalamnya adalah mengawasi metode

    pelaksanaan, mengkoordinasikan perubahan-perubahanpekerjaan yang diperlukan, melakukan monitoring, dan

    pelaporan/pengukuran hasil pekerjaan.

    TUGAS SUPERVISOR

    Belajar Untuk Berbagi

  • 5/20/2018 High Voltage Transmission Construction Supervision

    7/45

    - Simple - Inspiring - Performing - Phenomenal -

    7

    YANG DILAKUKAN SUPERVISOR

    1. Memeriksa dan mempelajari dokumen kontrak yang akan

    dijadikan dasar dalam tugas pengawasan.

    2. Mengawasi pemakaian material, peralatan serta metode

    pelaksanaan.

    3. Mengawasi pelaksanaan konstruksi dengan benar dari aspek

    kualitas, kuantitas dan laju pencapaian penyelesaian volume

    pekerjaan (waktu pelaksanaan).

    4. Menginventarisasi perubahan dan penyusunan yang harus

    dilakukan di lapangan sehubungan dengan permasalahan yangtimbul.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    8/45

    - Simple - Inspiring - Performing - Phenomenal -

    5. Mengadakan rapat-rapat lapangan secara berkala, membuat

    laporan pekerjaan, pengawasan berkala mingguan danbulanan dengan masukan hasil rapat lapangan serta laporan-

    laporan pelaksanaan harian, mingguan dan bulanan yang

    dibuat oleh kontraktor.

    6. Menyusun berita acara persetujuan kemajuan pekerjaan dan

    pembayaran angsuran, pemeliharaan pekerjaan, serta serahterima hasil pekerjaan yang pertama dan kedua.

    7. Meneliti gambar-gambar yang sesuai dengan pekerjaan yang

    dilaksanakan di lapangan (as bui l t drawing), sebelum serah

    terima yang pertama.

    8. Membuat laporan hasil pengawasan dan pengendalian dari

    seluruh aktivitas pekerjaan dilapangan.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    9/45

    - Simple - Inspiring - Performing - Phenomenal -

    KOMPETENSI SUPERVISI

    1. Memahami maksud dan tujuan dari pada isi

    Dokumen Kontrak yang akan dijadikan dasar dalam

    tugas pengawasan (supervisi)

    2. Mengetahui Mutu material & Kondisi Peralatan

    yang dipakai

    3. Mengetahui Metode Pelaksanaan konstruksidengan benar.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    10/45

    - Simple - Inspiring - Performing - Phenomenal -

    KOMPETENSI SUPERVISI

    4. Mampu membaca dan meneliti gambar sebelum

    dan sesudah pekerjaan dilaksanakan dilapangan

    5. Mampu menginventarisasi perubahan danpermasalahan yang timbul dilapangan

    6. Mampu membuat Laporan pekerjaan (harian,

    mingguan dan bulanan), maupun Laporan hasilpengawasan seluruh aktivitas pekerjaan

    dilapangan.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    11/45

    - Simple - Inspiring - Performing - Phenomenal -

    LINGKUP PEKERJAAN SUPERVISOR

    1. Mengetahui bisnis proses Perusahaan Listrik Negara (PLN).

    2. Mengerti maksud dan tujuan dari pada isi Dokumen Kontrak yang akan

    dijadikan dasar dalam tugas pengawasan.

    3. Mengontrol Mutu material & Kondisi Peralatan yang akan dipakai

    4. Mengetahui Lingkup Pekerjaan dan Metode Pelaksanaan konstruksi

    dengan benar.

    5. Memastikan gambar kerja yang akan dilaksanakan sebelum pekerjaan

    dilmulai dilapangan .

    6. Menginventarisasi perubahan dan permasalahan yang timbul

    dilapangan.

    7. Membuat Laporan pekerjaan (harian, mingguan dan bulanan), maupun

    Laporan hasil pengawasan seluruh aktivitas pekerjaan dilapangan

    11

  • 5/20/2018 High Voltage Transmission Construction Supervision

    12/45

    - Simple - Inspiring - Performing - Phenomenal -12

    LINGKUP PEKERJAAN PADA TRANSMISI

    1. Mencari jalan masuk ke lokasi Tower sedekat

    mungkin.

    2. Menyiapkan data dari type Tower.

    3. Pengukuran kembali letak, arah dan sudut arah Tower.

    4. Pematangan, Penimbunan dan Pemadatan tanah.

    5. Pembuatan Pondasi Tower (Pemasangan Kaki Tower).

    6. Pemasangan sistem Pembumian.

    7. Erection Tower dan Penarikan Konduktor (stringing)..

    Belajar Untuk erbagi

  • 5/20/2018 High Voltage Transmission Construction Supervision

    13/45

    - Simple - Inspiring - Performing - Phenomenal -

    BODY EXTENTION

    BODY PART

    CROSS ARM

    CROSS ARM PEAK

    KAKI TIANG

    13

  • 5/20/2018 High Voltage Transmission Construction Supervision

    14/45

    - Simple - Inspiring - Performing - Phenomenal -

    Stub tower

    Main Member

    Pondasi rakit beton bertulang

    Muka tanah

    PEMASANGAN KAKI TOWER PADA Pondasi

    14

    CONTOH

  • 5/20/2018 High Voltage Transmission Construction Supervision

    15/45

    - Simple - Inspiring - Performing - Phenomenal -15

    A

    Keterangan: Pondasi TRANSMISI

    TYPE. I (Pondasi Telapak)

    A = Panjang Pad Pondasi.

    B = Lebar Pad Pondasi.

    H = Tebal Pad Pondasi.

    D = Diameter Chimney

    (bisa bulat ; atau bujursangkar ).

    T = Kedalaman Pondasi dari

    permukaan tanah.

    T1 + 1000 mm = Tinggi Chimney

    (panjang leher Pondasi).

  • 5/20/2018 High Voltage Transmission Construction Supervision

    16/45

    - Simple - Inspiring - Performing - Phenomenal -

    STUB SETTING

    1. Tentukan ukuran pondasi pada tanah atau lokasi yang sudah tersedia

    sesuai dengan tipe tower dan body extention tower, misal :+6, +9, +122. Setting galian sesuai rencana dan lakukan penggalian pondasi sesuai

    rencana (panjang x lebar x dalam)

    3. Lakukan setting stub sesuai data (panjang back to back, diagonal dansudut kemiringan tower/slop).

    4. Semua keagiatan tersebut dilakukan diatas lantai kerja pondasi

    5. Setelah diyakini setting stub sudah sesuai rencana, segera dikunci padabagian bawah stub dengan campuran beton

    6. Selanjutnya pekerjaan pondasi dilaksanakan mulai dari pemasanganbesi tulangan sampai dengan pengecoran

    7. Semua kegiatan pengukuran tersebut diatas, dilakukan pengukuran

    dengan theodolit.8. Diingatkan kembali bahwa sesaat sebelum pengecoran dan setelahpengecoran selesai dilakukan recheck terhadap data setting.

    9. Toleransi kesalahan untuk stub setting tower adalah max 5 mm

    16

  • 5/20/2018 High Voltage Transmission Construction Supervision

    17/45

    - Simple - Inspiring - Performing - Phenomenal -

    PEMASANGAN SISTIM PEMBUMIAN UNTUK

    TOWER TRANSMISI1. Mempersiapkan material yang akan dipasang (ground root,

    kawat BC 100, dll)

    2. Pemancangan ground root (arde) zone dalam harus sedekat

    mungkin dengan pondasi tetapi tidak boleh mengenai beton

    pondasi.

    3. Kedalaman pemancangan gound root (arde) dipastikan

    minimum sampai ke muka air tanah terendah.

    4. Pastikan penyambungan ujung arde dengan kawat BC dan

    Stub Tower benar-benar menyatu.

    17

  • 5/20/2018 High Voltage Transmission Construction Supervision

    18/45

    - Simple - Inspiring - Performing - Phenomenal -18

    SISTIM PEMBUMIAN TIANG

    SUTT

    ALTERNATIF. 1

  • 5/20/2018 High Voltage Transmission Construction Supervision

    19/45

    - Simple - Inspiring - Performing - Phenomenal -

    ALTERNATIF. 2

  • 5/20/2018 High Voltage Transmission Construction Supervision

    20/45

    - Simple - Inspiring - Performing - Phenomenal -8/26/2010Spv Konst SplTriyoso 20

    PENATAAN LAHAN

    TAPAK TOWER

    150 KV

    KENDALA NON TEKNIS

    MENCARI JALAN MASUK

    KE LOKASI YG TERDEKAT

    PENDEKATAN DENGAN

    MASYARAKAT DLL

    Belajar Untuk Berbagi

  • 5/20/2018 High Voltage Transmission Construction Supervision

    21/45

    - Simple - Inspiring - Performing - Phenomenal -

    a. Untuk Pekerjaan Transmisi sebelum dimulai pekerjaan pokok

    harus dilakukan pengukuran Ulang.

    b. Semua kegiatan pengukuran harus dilakukan dengan

    theodolit.

    c. Untuk pekerjaan Transmisi Lakukan pengukuran dua kali

    untuk memastikan posisi tower.

    d. Pengukuran yang ke dua dimulai dari titik yang berlawanan.

    e. Hindari kecerobohan-kecerobohan sekecil mungkin.

    f. Bila diperlukan adakan pengecekan yang terpisah.

    21

    ii. PEKERJAAN PENGUKURAN

  • 5/20/2018 High Voltage Transmission Construction Supervision

    22/45

    - Simple - Inspiring - Performing - Phenomenal - 22

    PEKERJAAN PONDASI

    i. PONDASI.

    Adalah bagian terendah dari bangunan yang meneruskan

    beban bangunan ke tanah atau batuan yang ada di

    bawahnya.a) Pondasi Dangkal.

    a.1. Pondasi Telapak.

    a.2. Pondasi Memanjang.

    a.3. Pondasi Rakit.b) Pondasi Dalam.

    b.1. Pondasi Sumuran (Pondasi Peralihan).

    b.2. Pondasi Tiang.

    . Tiang Pancang. (Pneumatic; Tekan HidroliK).. Tiang Bor.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    23/45

    - Simple - Inspiring - Performing - Phenomenal - 23

    PENGETESAN PEKERJAAN PONDASI

    PENGUJIAN PONDASI TIANG.

    Pengujian Pondasi tiang yang sering dilakukan adalah

    pengujian dengan beban desak, walaupun pengujianbeban tarik dan beban lateral juga kadang dilakukan

    Ada 4 macam pengujian yang sering diklakukan

    1. Kalendering.

    2. Beban Langsung (loading Test).

    3. Pile Dynamic Analysis (PDA).

    4. Pile Integrity Test (PIT).

  • 5/20/2018 High Voltage Transmission Construction Supervision

    24/45

    - Simple - Inspiring - Performing - Phenomenal -24

    Pile cap

    Beton biasa 1 m

    A A

    A - ASelubung Sumuran

    L

    D

    L/D>4 selubung beton bertulang

    L/D < 4 selubung beton biasa

    Cor Beton Siklob

    Pondasi SUMURAN

    Untuk pondasi

    cakar ayam A dan

    B jadi satu

    A

    B

  • 5/20/2018 High Voltage Transmission Construction Supervision

    25/45

    - Simple - Inspiring - Performing - Phenomenal -25

    Pile Cap

    TIANG PANCANG BETON

    Tiang Pancang

    2D - 3D 1,5D

    D

    PT PLN (P )

  • 5/20/2018 High Voltage Transmission Construction Supervision

    26/45

    - Simple - Inspiring - Performing - Phenomenal -26

    PENGANGKATAN TIANG PANCANG (TP)

    2/3L

    1/3L

    L L L

    0.207L 0.586L 0.207L

    Belajar Untuk Berbagi

    PT. PLN (Persero)

    JASA MANAJEMEN KONSTRUKSI

  • 5/20/2018 High Voltage Transmission Construction Supervision

    27/45

    - Simple - Inspiring - Performing - Phenomenal -27

    ALAT PEMANCANG

    Tiang Pancang

  • 5/20/2018 High Voltage Transmission Construction Supervision

    28/45

    - Simple - Inspiring - Performing - Phenomenal - 28

    METODE PELAKSANAAN PONDASI PANCANG

    1. PERSIAPAN PEMANCANGAN.

    a) Tentukan alat pancang dan jenis hammer

    b) Rencanakan final set tiang

    c) Rencanakan urutan pemancangan.d) Tentukan letak titik pemancangan.

    2. PROSES PEMANCANGANa) Dilakukan oleh Kontraktor

    b) Sebelum proses pemancangan Pengawas harus tahu secara detailinformasi teknis pekerjaan pemancangan.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    29/45

    - Simple - Inspiring - Performing - Phenomenal -8/26/2010Spv Konst SplTriyoso Belajar Untuk Berbagi 29

    PT. PLN (Persero)JASA MANAJEMEN KONSTRUKSI

  • 5/20/2018 High Voltage Transmission Construction Supervision

    30/45

    - Simple - Inspiring - Performing - Phenomenal -30

    INFORMASI TEKNIS MENGENAI PEMANCANGAN TIANG HARUS DIKETAHUI OLEH

    PENGAWAS

    1. Type dan ukuran pemukul tiang, peralatan lain termasuk bantalan (cushion).

    2. Ukuran tiang, lokasi tiang dalam kelompok tiang dan lokasi kelompoknya.

    3. Urutan pemancangan dalam kelompok.

    4. Data sondir tanah.

    5. Daya dukung rencana setiap tiang pancang.6. Jumlah pukulan per satuan panjang untuk seluruh panjang tiang, dan set

    (penetrasi) untuk 10 pukulan (kalendering tiang).

    7. Elevasi akhir dari dasar dan kepala tiang.

    8. Papan (kayu keras) setebal 2,5cm sebanyak 6 lapis diletakkan diatas

    kepala tiang, untuk pelindung beton.

    9. Pemeriksaan tiang untuk posisi vertikal isasi tiang.

    10.Keterangan lain seperti penangguhan kelangsungan pemancangan,

    kerusakan tiang dll.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    31/45

    - Simple - Inspiring - Performing - Phenomenal - 31

    PILE DIAMETER

    (mm)

    Diesel Hummer, Kobe dan sejenisnya

    K22 / K25

    K32 / K35

    K45 / KB45

    350

    X

    400

    X

    450

    X

    X

    500

    X

    600

    X

    X

    Ring of working

    load

    (Ton)

    40 - 140

    80 - 230

    140 -320

    DAFTAR TYPE DIESEL HUMMER

  • 5/20/2018 High Voltage Transmission Construction Supervision

    32/45

    - Simple - Inspiring - Performing - Phenomenal -32

    3. QUALITY CONTROL HASIL PEMANCANGAN.

    1. Kondisi fisik.

    a. Seluruh permukaan tiang tidak boleh retak atau rusak.

    b. Umur beton sudah memenuhi syarat (28 hari)

    c. Kepala tiang tidak boleh mengalami keretakan selama pemancangan,2. Toleransi.

    a. Vertikalisasi tiang diperiksa secara piriodik selama pemancangan.

    b. Arah Vertikal dibatasi tidak boleh lebih dari 1 : 75.

    c. Arah Horizontal dibatasi tidak boleh lebih dari 75 mm.3. Penetrasi.

    Badan tiang diberi tanda setiap 50 cm untuk mendetaksi penetrasinya.

    4. Final seting.Pemancangan baru boleh diberhentikan bila sudah dicapai final seting sesuai

    perhitungan.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    33/45

    - Simple - Inspiring - Performing - Phenomenal -33

    TIANGFRANKI

  • 5/20/2018 High Voltage Transmission Construction Supervision

    34/45

    - Simple - Inspiring - Performing - Phenomenal -34

    1. Pengeboran dimulai dengan Auger dengan diameter sedikit

    lebih besar (untuk kemudian dipasang Casing).

    2. Pengeboran dilanjutkan dengan auger atau bucket.

    3. Bila dinding lubang bor runtuh, maka dibutuhkan pengisian air

    dalam lubang selama proses pengeboran berlangsung.

    4. Setelah kedalaman lubang yang direncanakan tercapai, proses,

    pembersihan lubang dimulai dengan menggunakan cleaning

    bucket.

    5. Setelah pembersihan lubang selesai dibersihkan kemudianpembesian tulangan pondasi dipasang dan disusul pipa tremie.

    Metode Pelaksanaan Bor pile.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    35/45

    - Simple - Inspiring - Performing - Phenomenal -35

    6. Bila di dalam lubang terdapat volume air yang cukup

    banyak dan deras maka pengecoran dilaksanakan melalui

    pipa tremie

    7. Pipa tremie dipasang sepanjang lubang bor.

    8. Selama pengecoran berlangsung tremie ditarik sedikit-

    demi sedikit dan ujung tremie dijaga tetap terbenamdalan campuran beton.

    9. Pengecoran dilakukan sampai beton berada diatas

    panjang rencana dasar poer 1 meter untuk menjamin

    mutu beton yang baik elevasi dasar poer.10. Bilaman tidak air dalam lubang bor, maka pengecoran

    dilakukan dengan pipa tremie pendek 1 meter dan

    sebagai corong saja.

    Metode Pelaksanaan Bor pile.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    36/45

    - Simple - Inspiring - Performing - Phenomenal -36

  • 5/20/2018 High Voltage Transmission Construction Supervision

    37/45

    - Simple - Inspiring - Performing - Phenomenal -37

    TIANG BETON PRECAST DENGAN SISTIM TEKAN HIDROLIK

    Hal-hal yang perlu diperhatikan oleh Pengawas

    1. Cek batas kedekatan/jarak minimum terhadap bangunan

    yang ada atau peralatan yang ada dengan alat Jecking.

    2. Cek Hasil data sondir dan Boring.3. Tandai semua permukaan tiang dengan cat dengan interval 1

    meter.

    4. Marking tiang pondasi beton dan harus ditandai dengan kayu

    atau besi.

    5. Cek kedudukan vertikal tiang sebelum dijecking apakah

    kedudukan sudah memenuhi syarat (toleransi vertikal adalah

    1 : 80).

  • 5/20/2018 High Voltage Transmission Construction Supervision

    38/45

    - Simple - Inspiring - Performing - Phenomenal -38

    TIANG BETON PRECAST DENGAN SISTIM TEKAN HIDROLIK

    Hal-hal yang perlu diperhatikan oleh Pengawas

    6. Cek kedudukan horizontal tiang pada elevasi permukaan

    tanah, sebelum di jecking apakah kedudukan sudah

    memenuhi syarat (toleransi horizontal terhadap permukaantanah 50 75 mm).

    7. Bila tiang disambung, cek kondisi sambungan, tidak boleh ada

    celah/lubang pada sambungan las.

    8. Semua tiang akan disertai pencatatan jecking dari awal

    sampai akhir (piling record) pada interval jarak 1 meter.

    9. Semua tiang akan dijecking sampai beban maksimum

    (200%XDesign Load). Atau sesuai dengan spesifikasi dalam

    kontrak.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    39/45

    - Simple - Inspiring - Performing - Phenomenal -39

    Tiang Beton Precast

  • 5/20/2018 High Voltage Transmission Construction Supervision

    40/45

    - Simple - Inspiring - Performing - Phenomenal -40

    PENGUJIAN Pondasi PANCANG.

    Kalendering.

    Data-data yang perlu disiapkan adalah:

    1. Data Boring tanah.

    2. Data tahanan kones dari sondir

    3. Kertas Folio dan Pensil (ditempel pd t p).

    Pembebanan Langsung.

    Kelengkapan yang perlu disiapkan.

    1. Beban yang akan dipakai untuk uji beban.

    2. Dongkrak hydrolik.

    3. Alat pengukur beban.

    4. Tiang yang akan diuji.

    5. Perlengkapan pendukung lainnya.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    41/45

    - Simple - Inspiring - Performing - Phenomenal - 41

    ALATSONDIR (CPT)

    1. Standart ASTM D3441-982. Kapasitas alat 2,5 ton.

    3. Tahanan konus 200kg/cm

  • 5/20/2018 High Voltage Transmission Construction Supervision

    42/45

    - Simple - Inspiring - Performing - Phenomenal - 42

    Standard Penetration Test (SPT)

    1. Dilakukan bersamaan dengan pekerjaan boring (tiap

    kedalaman 2 meter.

    2. Alat yang dipakai Split spoon barrel.3. Hammer seberat 140 lbs (63,5 kg) dengan tinggi jatuh

    30 (76,2 cm).

    4. Nilai SPT = jumlah tumbukan untuk penetrasi 2 X 15 cm.

    5. Acuan tanah keras dicapai pada N-SPT > 50.6. Standard ASTM D.1586-84.

  • 5/20/2018 High Voltage Transmission Construction Supervision

    43/45

    - Simple - Inspiring - Performing - Phenomenal - 43

    GRAFIK TAHANAN KONES

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

  • 5/20/2018 High Voltage Transmission Construction Supervision

    44/45

    - Simple - Inspiring - Performing - Phenomenal - 44

    SIMBUL

    BUATAN

    PEMBERIAN NAMA KEDALAMAN (M)

    ENDAPAN HALUS, berwarna kelabu tua, sangat lepas dan lembek, pd

    kedalaman 12,10

    TANAH LEMPUNG, tediri atas campuran lempung, sangat kaku, kelabu

    muda kecoklatan pada kedalaman 2,109,00, dan ada sisipan pecahan

    batu pasir diameter maksimum 50 mm, pada kedalaman 78, warna kelabu

    tua.

    -- 1

    -- 2

    -- 3

    -- 4

    -- 5

    -- 6

    TANAH LEMPUNG BERLANAU, kelabu muda kecoklatan berbutir halus,

    berpasir jarang, kekuatan sangat lemah, lapuk sedang, pada kedalaman 9,00

    16,00.

    Pada kedalaman 13,0015,00, terdapat sisipan batu lempung keras

    berpasir, berwarna kelabu kehitam-hitaman, tak lapuk.

    -- 7

    -- 8

    -- 9

    -- 10

    -- 11

    -- 12-- 13

    TANAH KERAS, tanah liat keras, kerikil padat, tanah liat

    bercampur kerikil dan batu kecil (tanah granuler), berwarna

    abu-abu kehitam-hitaman, tidak lapuk, bergradasi baik.

    Pada kedalaman 16,0019,00

    -- 14

    -- 15

    -- 16

    -- 17

    -- 18-- 19

    CONTOH DATA BORING

  • 5/20/2018 High Voltage Transmission Construction Supervision

    45/45

    UJI BEBAN LANGSUNG DENGAN

    DONGKRAK HIDROLIK