High rise building schedule

download High rise building schedule

of 32

Transcript of High rise building schedule

  • 8/12/2019 High rise building schedule

    1/32

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    Rem

    Dur

    % Early

    Start

    Early

    Finish

    Total

    Float

    Budgeted

    Cost

    Completion of Tower 2BSubtotal 380 295 29 25JAN12A 11APR13 -139 95,090,246.00

    Project Milestones

    T2TX.ML.01 Project start date 0 0 100 25JAN12A 0.00

    T2TX.ML.02 Receival of Drawings from LAND 0 0 0 08MAY12 151 0.00T2TX.ML.03 Receival of Material Submittal 0 0 0 15MAY12 145 0.00

    T2TX.ML.04 Elevators final finish 0 0 0 24FEB13 -99 0.00

    T2TX.ML.05 Testing & Commissioning 0 0 0 22NOV12 -19 0.00

    T2TX.ML.06 Project Handing over 0 0 0 11APR13 -139 0.00

    Priliminaries

    T2TX.PR.01 Start of project (Site Handover) 0 0 100 25JAN12A 0.00

    T2TX.PR.02 Mobilization 5 0 100 25JAN12A 28JAN12A 5,150,000.00

    Drawings & ProcurementDrawings

    T2T8.DR.01 Receival of Drawings from LAND 20 5 75 01FEB12A 08MAY12 151 0.00

    Procurement

    Material Submittals

    Architectural

    Marbles & tiles

    T28.MSA.01 Submittal marble and tiles 4 0 100 29JAN12A 02FEB12A 0.00

    T28.MSA.02 Approval marble and tiles 7 0 100 02FEB12A 09FEB12A 0.00

    Wardrobes

    T28.MSA.18 Submittal Wardrobes 4 0 100 15FEB12A 19FEB12A 0.00

    T28.MSA.19 Approval Wardrobes 7 0 100 20FEB12A 27FEB12A 0.00

    Kitchen Cabinet

    T28.MSA.20 Submittal Kitchen Cabinet 4 0 100 15FEB12A 19FEB12A 0.00

    T28.MSA.21 Approval Kitchen Cabinet 7 0 100 20FEB12A 27FEB12A 0.00

    Epoxy Paint

    T28.MSA.03 Submittal Epoxy Paint 4 0 100 02FEB12A 07FEB12A 0.00

    T28.MSA.04 Approval Epoxy Paint 7 0 100 07FEB12A 19FEB12A 0.00

    Aluminium door ,Window,Louver

    T28.MSA.05 Submittal aluminum door, 4 0 100 02FEB12A 06FEB12A 0.00

    T28.MSA.06 Approval aluminum door, window, 7 0 100 06FEB12A 15FEB12A 0.00

    Roofing Tile

    T28.MSA.08 Submittal roofing tiles 4 0 100 11FEB12A 23FEB12A 0.00

    T28.MSA.09 Approval roofing tiles 7 0 100 02FEB12A 09FEB12A 0.00

    2012 2013J FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR A

    Project start date

    Receival of Drawings from LAND

    Receival of Material Submittal Docs from LAND

    Elevators final finish

    Testing & Commissioning

    Project Handing over

    Start of project (Site Handover)

    Mobilization

    Receival of Drawings from LAND

    Submittal marble and tiles

    Approval marble and ti les

    Submittal Wardrobes

    Approval Wardrobes

    Submittal Kit chen Cabinet

    Approval Kitchen Cabinet

    Submittal Epoxy Paint

    Approval Epoxy Paint

    Submittal aluminum door, window, louver

    Approval aluminum door, window, louver

    Submittal roofing tiles

    Approval roofing til es

    Primavera Systems, Inc.

    Start Date 25JAN12

    Finish Date 11APR13

    Data Date 22MAY12Run Date 03JUN12 14:16

    Early Bar

    Progress Bar

    Critical Activity

    T02B

    UNITED DEVELOPMENT CO(UDC)

    Gen Contr:ACCSub-Contr:Trivalley Ligments JV

    Completion of Tower 2B

    All

    Sheet 1 of 32

    Date Revision Checked Approved

  • 8/12/2019 High rise building schedule

    2/32

  • 8/12/2019 High rise building schedule

    3/32

  • 8/12/2019 High rise building schedule

    4/32Sheet 4 of 32

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    Rem

    Dur

    % Early

    Start

    Early

    Finish

    Total

    Float

    Budgeted

    Cost

    Gypsum boards & Other ceiling boards

    T2T8.PO.13 Placing Purchase order 0 0 100 23FEB12A 0.00

    T2T8.PO.14 Procurement 50 0 100 23FEB12A 08MAR12A 0.00

    T2T8.PO.15 Delivary on site 0 0 100 08MAR12A 0.00

    Paints

    T2T8.PO.16 Placing Purchase order 0 0 0 03MAY12 81 0.00

    T2T8.PO.17 Procurement 5 5 0 03MAY12 08MAY12 81 0.00

    T2T8.PO.18 Delivary on site 0 0 0 08MAY12 81 0.00

    Steel & Wood Doors

    T2T8.PO.19 Placing Purchase order 0 0 100 01MAR12A 0.00

    T2T8.PO.20 Procurement 20 12 40 01MAR12A 16MAY12 68 0.00

    T2T8.PO.21 Delivary on site 0 0 0 16MAY12 68 0.00

    Railings

    T2T8.PO.22 Placing Purchase order 0 0 100 08FEB12A 0.00

    T2T8.PO.23 Procurement 50 0 100 08FEB12A 01MAR12A 0.00

    T2T8.PO.24 Delivary on site 0 0 100 01MAR12A 0.00

    Electrical

    Light Fittings

    T28.POE.07 Placing Purchase order 0 0 100 01MAR12A 0.00

    T28.POE.08 Procurement 25 5 80 05MAR12A 21MAY12 86 0.00

    T28.POE.09 Delivary on site 0 0 0 21MAY12 86 0.00

    Wiring accessaries & cables

    T28.POE.10 Placing Purchase order 0 0 100 05MAR12A 0.00

    T28.POE.11 Procurement 30 3 90 05MAR12A 07MAY12 93 0.00

    T28.POE.12 Delivary on site 0 0 0 07MAY12 93 0.00

    MV Panel

    T28.POE.13 Placing Purchase order 0 0 0 03MAY12 78 0.00

    T28.POE.14 Modification works 20 20 0 03MAY12 26MAY12 78 0.00

    T28.POE.15 Delivary on site 0 0 0 26MAY12 78 0.00

    Earthing Systems & Lighting Protection

    T28.POE.19 Placing Purchase order 0 0 100 03MAR12A 0.00

    T28.POE.20 Procurement 30 15 50 03MAR12A 20MAY12 82 0.00

    T28.POE.21 Delivary on site 0 0 0 20MAY12 82 0.00

    MCC, EMDB,EMCC & VFD

    T28.POE.22 Placing Purchase order 0 0 100 08MAR12A 0.00

    T28.POE.23 Procurement 30 15 50 08MAR12A 20MAY12 87 0.00

    T28.POE.24 Delivary on site 0 0 0 20MAY12 87 0.00

    BMS

    T28.POE.25 Placing Purchase order 0 0 0 12MAY12 61 0.00

    T28.POE.26 Procurement 30 30 0 12MAY12 14JUN12 61 0.00

    T28.POE.27 Delivary on site 0 0 0 14JUN12 61 0.00

    CCTV,Central Battery,Lighting control

    T28.POE.31 Placing Purchase order 0 0 0 12MAY12 53 0.00

    T28.POE.32 Procurement 30 30 0 12MAY12 14JUN12 53 0.00

    T28.POE.33 Delivary on site 0 0 0 14JUN12 53 0.00

    2012 2013J FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR A

    Placing Purchase order

    Procurement

    Delivary on sit e

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Modification works

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on sit e

    Placing Purchase order

    Procurement

    Delivary on sit e

    Sheet 4 of 32

  • 8/12/2019 High rise building schedule

    5/32Sheet 5 of 32

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    Rem

    Dur

    % Early

    Start

    Early

    Finish

    Total

    Float

    Budgeted

    Cost

    Audio Visual

    T28.POE.34 Placing Purchase order 0 0 0 12MAY12 53 0.00

    T28.POE.35 Procurement 30 30 0 12MAY12 14JUN12 53 0.00

    T28.POE.36 Delivary on site 0 0 0 14JUN12 53 0.00

    HVAC

    Chilled water pipes

    T28.POH.01 Placing Purchase order 0 0 100 28FEB12A 0.00T28.POH.02 Procurement 50 0 100 28FEB12A 14MAR12A 0.00

    T28.POH.03 Delivary on site 0 0 100 14MAR12A 0.00

    Ducts & Accessaries

    T28.POH.04 Placing Purchase order 0 0 100 01MAR12A 0.00

    T28.POH.05 Procurement 30 9 70 01MAR12A 13MAY12 64 0.00

    T28.POH.06 Delivary on site 0 0 0 13MAY12 64 0.00

    CW Pumps

    T28.POH.07 Placing Purchase order 0 0 0 12MAY12 55 0.00

    T28.POH.08 Procurement 30 30 0 12MAY12 14JUN12 55 0.00

    T28.POH.09 Delivary on site 0 0 0 14JUN12 55 0.00

    HVAC Machinaries

    T28.POH.10 Placing Purchase order 0 0 100 28FEB12A 0.00

    T28.POH.11 Procurement 50 0 100 28FEB12A 12MAR12A 0.00

    T28.POH.12 Delivary on site 0 0 100 12MAR12A 0.00

    Exhaust & Vent fan

    T28.POH.13 Placing Purchase order 0 0 0 12MAY12 61 0.00

    T28.POH.14 Procurement 30 30 0 12MAY12 14JUN12 61 0.00

    T28.POH.15 Delivary on site 0 0 0 14JUN12 61 0.00

    Plumbing & Drainage

    Pipes & Fittings

    T28.POP.01 Placing Purchase order 0 0 100 28FEB12A 0.00

    T28.POP.02 Procurement 50 0 100 28FEB12A 14MAR12A 0.00

    T28.POP.03 Delivary on site 0 0 100 14MAR12A 0.00

    Sanitary Fixt ure

    T28.POP.04 Placing Purchase order 0 0 100 28FEB12A 0.00

    T28.POP.05 Procurement 50 0 100 28FEB12A 14MAR12A 0.00

    T28.POP.06 Delivary on site 0 0 100 14MAR12A 0.00

    Drainage system

    T28.POP.07 Placing Purchase order 0 0 100 28FEB12A 0.00

    T28.POP.08 Procurement 50 0 100 28FEB12A 14MAR12A 0.00

    T28.POP.09 Delivary on site 0 0 100 14MAR12A 0.00

    Fire Fighting

    FF Pipes & Accessaries

    T28.POF.01 Placing Purchase order 0 0 100 28FEB12A 0.00

    T28.POF.02 Procurement 15 4 75 28FEB12A 07MAY12 65 0.00

    T28.POF.03 Delivary on site 0 0 0 07MAY12 65 0.00

    FF Pumps(To be repaired,Action by LAND)

    T28.POF.04 Placing Purchase order 0 0 0 03MAY12 30 0.00

    T28.POF.05 Procurement 50 50 0 03MAY12 30JUN12 30 0.00

    2012 2013J FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR A

    Placing Purchase order

    Procurement

    Delivary on sit e

    Placing Purchase orderProcurement

    Delivary on sit e

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on sit e

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Delivary on sit e

    Placing Purchase order

    Procurement

    Delivary on sit e

    Placing Purchase order

    Procurement

    Delivary on sit e

    Placing Purchase order

    Procurement

    Delivary on sit e

    Placing Purchase order

    Procurement

    Delivary on site

    Placing Purchase order

    Procurement

    Sheet 5 of 32

  • 8/12/2019 High rise building schedule

    6/32

  • 8/12/2019 High rise building schedule

    7/32

  • 8/12/2019 High rise building schedule

    8/32

  • 8/12/2019 High rise building schedule

    9/32

  • 8/12/2019 High rise building schedule

    10/32

  • 8/12/2019 High rise building schedule

    11/32

  • 8/12/2019 High rise building schedule

    12/32

  • 8/12/2019 High rise building schedule

    13/32

  • 8/12/2019 High rise building schedule

    14/32

  • 8/12/2019 High rise building schedule

    15/32

  • 8/12/2019 High rise building schedule

    16/32

  • 8/12/2019 High rise building schedule

    17/32

  • 8/12/2019 High rise building schedule

    18/32

  • 8/12/2019 High rise building schedule

    19/32

  • 8/12/2019 High rise building schedule

    20/32

  • 8/12/2019 High rise building schedule

    21/32

  • 8/12/2019 High rise building schedule

    22/32

  • 8/12/2019 High rise building schedule

    23/32

  • 8/12/2019 High rise building schedule

    24/32

  • 8/12/2019 High rise building schedule

    25/32

  • 8/12/2019 High rise building schedule

    26/32

  • 8/12/2019 High rise building schedule

    27/32

  • 8/12/2019 High rise building schedule

    28/32

  • 8/12/2019 High rise building schedule

    29/32

  • 8/12/2019 High rise building schedule

    30/32

  • 8/12/2019 High rise building schedule

    31/32

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    Rem

    Dur

    % Early

    Start

    Early

    Finish

    Total

    Float

    Budgeted

    Cost

    Testing & Commissioning

    2012 2013J FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR A

  • 8/12/2019 High rise building schedule

    32/32

    Sheet 32 of 32

    g gT2.TEST.01 Test & Commission 10 10 0 12NOV12 22NOV12 -49 10,462.00

    T2.TEST.02 Test & Commission HVAC 10 10 0 12NOV12 22NOV12 -49 10,462.00

    T2.TEST.03 Test & Commission Plumbing & 10 10 0 12NOV12 22NOV12 -49 10,462.00

    T2.TEST.04 Test & Commission low current 10 10 0 12NOV12 22NOV12 -49 10,462.00

    T2.TEST.05 Final test MV panel etc 10 10 0 12NOV12 22NOV12 -49 10,462.00

    T2.TEST.06 Testing elevators 10 10 0 25FEB13 07MAR13 -139 10,462.00

    T2.TEST.07 FInal test & Snags rectification all 30 30 0 09MAR13 11APR13 -139 11,159.47

    Project Handing OverT2T8.HO.01 Project Handing Over 0 0 0 11APR13 -139 0.00

    Test & Commission eLECTRICAL

    Test & Commission HVAC

    Test & Commission Plumbing & drain

    Test & Commission low current

    Final test MV panel etc

    Testing elevators

    FInal test & Snags rectification all trades

    Project Handing Over

    Sheet 32 of 32