HF FE schedule

5
HF FE schedule Ulrich Heintz Brown University 7/22/2014 Ulrich Heintz - HF FE schedule 1

description

HF FE schedule. Ulrich Heintz Brown University. QIE10 production. June 2014: submitted engineering run includes QIE10 and QIE11 chips September 2014 : expect delivery of chips One wafer will be packaged for preproduction boards December 2014: bench testing complete - PowerPoint PPT Presentation

Transcript of HF FE schedule

Page 1: HF FE schedule

Ulrich Heintz - HF FE schedule 1

HF FE scheduleUlrich Heintz

Brown University

7/22/2014

Page 2: HF FE schedule

Ulrich Heintz - HF FE schedule 2

QIE10 production• June 2014: submitted engineering run

• includes QIE10 and QIE11 chips

• September 2014: expect delivery of chips• One wafer will be packaged for preproduction boards

• December 2014: bench testing complete• February 2015: packaged chips delivered• April 2015: robot chip testing complete• production QIE10 ASICs available for shipment

7/22/2014

Page 3: HF FE schedule

Ulrich Heintz - HF FE schedule 3

prototype phase• backplane & crates

• done – start production of backplanes following today’s review

• QIE cards• July 2014: revised QIE card design complete• September 2014: preproduction QIE cards (US)• November 2014: preproduction QIE cards from Turkey/Brazil

• ngCCM • September 2014: IGLOO2 mezzanine design complete • October 2014: preproduction ngCCM

• calib module• September 2014: prototype of pulser and light distribution system

• December 2014 – electronics system review of HF FE

7/22/2014

Page 4: HF FE schedule

Ulrich Heintz - HF FE schedule 4

production phase• January 2015 – start of production • frontend crates & backplanes (Brazil)

• April 2015 – could be earlier (backplane design ready/crates are off the shelf)

• QIE cards (Brazil & Turkey)• need packaged and tested QIE10 chips (April 2015??)• July 2015 – QIE cards at CERN• acceptance testing at CERN bat. 904

• calibration system (Brazil)• April 2014 – light mixer shipped to Brazil (US)• July 2015 – calib modules at CERN

• ngCCM (US)• August 2015 – ngCCMs at CERN

7/22/2014

Page 5: HF FE schedule

Ulrich Heintz - HF FE schedule 5

burn-in and installation phase• August 2015 assemble crates in bat. 904• Aug – Dec 2015 burn-in• December 2015 start installation• February 2016 installation complete• March 2016 commissioning complete

7/22/2014