Ulrich Heintz - HF FE schedule 1
HF FE scheduleUlrich Heintz
Brown University
7/22/2014
Ulrich Heintz - HF FE schedule 2
QIE10 production• June 2014: submitted engineering run
• includes QIE10 and QIE11 chips
• September 2014: expect delivery of chips• One wafer will be packaged for preproduction boards
• December 2014: bench testing complete• February 2015: packaged chips delivered• April 2015: robot chip testing complete• production QIE10 ASICs available for shipment
7/22/2014
Ulrich Heintz - HF FE schedule 3
prototype phase• backplane & crates
• done – start production of backplanes following today’s review
• QIE cards• July 2014: revised QIE card design complete• September 2014: preproduction QIE cards (US)• November 2014: preproduction QIE cards from Turkey/Brazil
• ngCCM • September 2014: IGLOO2 mezzanine design complete • October 2014: preproduction ngCCM
• calib module• September 2014: prototype of pulser and light distribution system
• December 2014 – electronics system review of HF FE
7/22/2014
Ulrich Heintz - HF FE schedule 4
production phase• January 2015 – start of production • frontend crates & backplanes (Brazil)
• April 2015 – could be earlier (backplane design ready/crates are off the shelf)
• QIE cards (Brazil & Turkey)• need packaged and tested QIE10 chips (April 2015??)• July 2015 – QIE cards at CERN• acceptance testing at CERN bat. 904
• calibration system (Brazil)• April 2014 – light mixer shipped to Brazil (US)• July 2015 – calib modules at CERN
• ngCCM (US)• August 2015 – ngCCMs at CERN
7/22/2014
Ulrich Heintz - HF FE schedule 5
burn-in and installation phase• August 2015 assemble crates in bat. 904• Aug – Dec 2015 burn-in• December 2015 start installation• February 2016 installation complete• March 2016 commissioning complete