  • Competent Persons Report

    Hellyer Tailings Retreatment Project, Tasmania

    CSA Global Report N R301.2017 20 November 2017

    www.csaglobal.com

  • I

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Report prepared for

    Client Name NQ Minerals Plc

    Project Name/Job Code NQMCPR01

    Contact Name Mike Barden

    Contact Title Chief Development Officer

    Office Address Finsgate, 5-7 Cranwood St, London, UK

    Report issued by

    CSA Global Office

    CSA Global Pty Ltd

    Level 2, 201 Leichhardt Street

    Spring Hill QLD 4000

    AUSTRALIA

    PO Box 1077

    Spring Hill QLD 4004

    AUSTRALIA

    T +61 7 3106 1200

    F +61 7 3106 1201

    E [email protected]

    Division Corporate

    Report information

    File name R301.2017 NQMCPR01 CPR - NQ Minerals Hellyer Tailings Retreatment Project FINAL_v2

    Last edited 31-Dec-17 5:35:00 AM

    Report Status Final

    Author and Reviewer Signatures

    Coordinating Author

    David Williams

    BSc (Hons), MAusIMM Signature:

    Coordinating Author

    Peter Cranfield

    BSc (Hons) ARSM, MIMMM, C.Eng

    Signature:

    Peer Reviewer Galen White

    BSc (Hons), FAusIMM, FGS Signature:

    CSA Global Authorisation

    Galen White

    BSc (Hons), FAusIMM, FGS Signature:

    Copyright 2017

  • II

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Disclaimers

    Purpose of this document

    This Report was prepared exclusively for NQ Minerals Plc (the Client) by CSA Global Pty Ltd (CSA Global). The quality of information, conclusions, and estimates contained in this Report are consistent with the level of the work carried out by CSA Global to date on the assignment, in accordance with the assignment specification agreed between CSA Global and the Client.

    Notice to third parties

    CSA Global has prepared this Report having regard to the particular needs and interests of our client, and in accordance with their instructions. This Report is not designed for any other persons particular needs or interests. Third party needs and interests may be distinctly different to the NQ Minerals Plcs needs and interests, and the Report may not be sufficient nor fit or appropriate for the purpose of the third party.

    CSA Global expressly disclaims any representation or warranty to third parties regarding this Report or the conclusions or opinions set out in this Report (including without limitation any representation or warranty regarding the standard of care used in preparing this Report, or that any forward-looking statements, forecasts, opinions or projections contained in the Report will be achieved, will prove to be correct or are based on reasonable assumptions). If a third party chooses to use or rely on all or part of this Report, then any loss or damage the third party may suffer in so doing is at the third partys sole and exclusive risk.

    CSA Global has created this Report using data and information provided by or on behalf of the Client [and the NQ Minerals Plc agents and contractors]. Unless specifically stated otherwise, CSA Global has not independently verified that all data and information is reliable or accurate. CSA Global accepts no liability for the accuracy or completeness of that data and information, even if that data and information has been incorporated into or relied upon in creating this Report.

    Results are estimates and subject to change

    The interpretations and conclusions reached in this Report are based on current scientific understanding and the best evidence available to the authors at the time of writing. It is the nature of all scientific conclusions that they are founded on an assessment of probabilities and, however high these probabilities might be, they make no claim for absolute certainty.

    The ability of any person to achieve forward-looking production and economic targets is dependent on numerous factors that are beyond CSA Globals control and that CSA Global cannot anticipate. These factors include, but are not limited to, site-specific mining and geological conditions, management and personnel capabilities, availability of funding to properly operate and capitalise the operation, variations in cost elements and market conditions, developing and operating the mine in an efficient manner, unforeseen changes in legislation and new industry developments. Any of these factors may substantially alter the performance of any mining operation.

  • III

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    1 Executive Summary

    CSA Global Pty Ltd (CSA Global) was engaged by NQ Mineral Plc (NQM) to compile a Competent Persons

    Report (CPR) setting out, in addition to background information, the Mineral Resource estimate and Ore

    Reserve estimate relating to the Hellyer Tailings Retreatment Project (Hellyer or Hellyer Project), located

    in Tasmania, Australia.

    1.1 Tenure

    NQM holds a consolidated granted mining leases CML103M/1987 over the area including the tailings dam

    and the processing plant. This lease covers all the areas required for the proposed tailings reclaim

    operations. The mining lease is held by Hellyer Gold Mines Pty Limited, a wholly owned subsidiary of NQM.

    The lease was granted on 24 February 1988 and was renewed and extended in June 2009 until 30 June

    2020. The lease can then be further extended, for as long as the mine is operated, as advised by Mineral

    Resources Tasmania. The annual permit has been paid in full until 15 February 2018.

    1.2 Project Location, Access and Climate

    The Hellyer Mine is located in north-western Tasmania 80 km south of Burnie, just off the main highway

    between Burnie and Queenstown and four hours drive northwest of the capital, Hobart. The area

    surrounding the project is mainly forest reserve with farmland. There has been extensive historical mining

    activity in the area. The licence area has a polymetallic (Cu-Pb-Zn-Au-Ag) deposit and associated ore

    processing facility at Hellyer, adjacent to the tailings dam.

    This part of Tasmania lies in a high rainfall area with annual average precipitation of 2,180 mm (Bureau of

    Meteorology Waratah) falling all year although higher falls and snowfall occur over winter months.

    1.3 Geology and Nature of the Deposit

    The Hellyer deposit is a volcanic hosted polymetallic massive sulphide deposit located within the Mount

    Read volcanic arc of western Tasmania. This region also hosts similar deposits such as Hercules, Que River,

    Roseberry and Mount Lyell. Mineralisation is sulphide hosted and comprised predominantly of pyrite,

    with lesser sphalerite, galena and arsenopyrite. The pyrite must be carefully managed when exposed to

    air to prevent its potential for oxidation and consequent and potential acid mine drainage issues. The

    economic metals mined at Hellyer were lead, zinc, copper, gold and silver. The Hellyer deposit was mined

    by underground methods during the period 1989 to 2000. The Fossey deposit extends down plunge from

    the Hellyer deposit and was mined by Bass Metals Pty Ltd (Bass Metals) between 2010 and 2012.

    Tailings from the mill were deposited in a depression approximately 1 km to the west of the Hellyer mill.

    The tails were simultaneously inundated with water to prevent oxidation of the sulphide species present

    in the tails. The tails were partially dredged by Polymetals Group (Polymetals) and retreated between

    2006 and 2008, with the reprocessed tails deposited in the Shale Pit and Western Arm. Tails from

    processed Fossey deposit ore were also discharged into the Western Arm.

    1.4 Mineral Resource Estimate

    The Mineral Resource estimate for the Hellyer Tailings Storage Facility (TSF) is presented in Table 1. The

    Mineral Resource estimate is reported in accordance with the JORC Code1. Table 2 presents the metal

    totals, as calculated from Table 1 (only gross totals are presented).

    1 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. The JORC Code, 2012 Edition. Prepared by: The Joint Ore Reserves Committee of The Australasian Institute of Mining and Metallurgy, Australian Institute of Geoscientists and Minerals Council of Australia (JORC).

  • IV

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    CSA Global considers that data collection techniques are consistent with industry good practice and

    suitable for use in the preparation of a Mineral Resource estimate. Vibracore drill samples were used to

    interpolate grades into blocks using ordinary kriging. Several methods were used to validate the block

    model, including visual review and a comparison of sampling and block model grades. A three-dimensional

    block model representing the mineralisation was created using Datamine software.

    The Mineral Resource is considered to have reasonable prospects for eventual economic extraction (a

    required condition under JORC) due to the volume and grade of mineralisation, the tailings are readily

    amenable for extraction by dredging, and the project has access to critical infrastructure, including a

    processing plant. The potential economic viability has also been assessed with respect to the preparation

    of Ore Reserves and economic analysis (see Sections 10 and 11 of this report).

    Table 1: Hellyer Tailings Storage Facility, Mineral Resource estimate

    JORC classification

    Gross Net attributable

    Operator Tonnage (Mt)

    Zn %

    Pb %

    Ag g/t

    Au g/t

    Cu %

    Tonnage (Mt)

    Zn %

    Pb %

    Ag g/t

    Au g/t

    Cu %

    Measured 2.05 3.31 3.35 94 2.63 0.2 2.05 3.31 3.35 94 2.63 0.2

    NQM Indicated 5.99 2.29 2.95 93 2.55 0.18 5.99 2.29 2.95 93 2.55 0.18

    Inferred 1.21 1.00 2.60 86 2.57 0.19 1.21 1.00 2.60 86 2.57 0.19

    Total 9.25 2.35 2.99 92 2.57 0.19 9.25 2.35 2.99 92 2.57 0.19

    Note: No lower cut-off reporting grade has been applied. Differences may occur due to rounding. (Datamine model: hel717md.dm).

    Table 2: Hellyer Tailings Storage Facility, Mineral Resource estimate metal tonnes and ounces, gross total only, all attributable to NQM

    JORC classification Gross

    Tonnage Zn (t) Pb (t) Ag (oz) Au (oz) Cu (t)

    Measured 2,050,000 67,900 68,700 6,195,400 173,300 4,100

    Indicated 5,990,000 137,200 176,700 17,910,200 491,100 10,800

    Inferred 1,210,000 12,100 31,500 3,345,600 100,000 2,300

    Total 9,250,000 217,400 276,600 27,360,300 764,300 17,600

    Note: Metal tonnages and ounces rounded from calculated values.

    1.5 Previous Mining Studies

    During the period 2006 to 2008, Polymetals successfully dredged and processed approximately 2 million

    tonnes (Mt) of tailings at Hellyer, targeting the Zn value through the sale of a bulk Zn/Pb concentrate.

    Operations ceased in September 2008.

    In 2010, CSA Global prepared a Resource Report for the Hellyer tailings as part of a Resource Estimate and

    Mining Study (CSA Global, 2010). This report was used by Como Engineers Pty Ltd (Como) as a part of a

    broader project evaluation for the then owners of Hellyer, Bass Metals.

    In 2013, Ivy Resources Pty Ltd (Ivy Resources) acquired Hellyer and in November 2013 completed a

    Feasibility Study of the Hellyer Tailings Retreatment Project, which presented results including marketing

    studies, geology, Mineral Resource estimation, mining, mineral processing, infrastructure, permitting, and

    financial analysis (Ivy Resources, 2013). The mining technology considered in the study was dredging.

    As part of the Ivy Resources Feasibility Study, Como completed a Definitive Feasibility Study (DFS) on

    the project with a specific scope related to direct cyanide leach and leaching of the Albion process product

    (Como, 2013). This was updated in 2015 to include costs for various feed rates to the cyanide leach circuit

    and subsequent processes (Como, 2016).

  • V

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    In 2016, Ausenco produced a report on the tailings treatment restart cost estimate following a request by

    NQM based on a refined processing flowsheet for sequential flotation of the tailings (Ausenco, 2016).

    NQM also requested Pitt & Sherry to prepare a report in November 2016 to assess the status of

    metallurgical testwork in connection with the sequential flotation of the Hellyer tailings (Pitt & Sherry,

    2016).

    A relevant study was also conducted by Commodity and Mining Insight Ltd (CM Insight, 2016) that

    included preliminary economic modelling of the potential reprocessing of the Hellyer tailings.

    1.6 Current Mining Study

    In 2017, AusGEMCO Pty Ltd (AusGEMCO) were engaged by NQM to complete an Ore Reserve estimate

    over the Hellyer Tailings Project. This study is documented in a report titled Hellyer Tailings Retreatment

    Project Tasmania, Ore Reserve Estimate dated September 2017. This report, along with supporting data

    and information compiled during the study was made available to CSA Global for review and CSA Global

    completed a gap analysis and peer review of this study prior to inclusion of the study contents in this

    report as current material information.

    A summary of this study is presented in the body of this CPR, referenced as appropriate and augmented

    by CSA Global independent comment as appropriate.

    1.6.1 Mine Design and Planning

    The mine design for the Hellyer Tailings Retreatment Project has been developed by AusGEMCO by

    modelling the profit from the exploitation of each block of the Mineral Resource block model (CSA Global,

    2017) and by assessment of the Net Smelter Return from selling concentrates as final products of the mine

    production. For the purpose of this study three types of concentrate are planned as final products: lead

    concentrate, zinc concentrate and pyrite/gold/silver concentrate.

    The Block Profit Modelling is organised for each impoundment area comprising the Hellyer TSF. The

    economic inputs and mining and processing assumptions are based on those used in the financial model

    described in Section 10. Two criteria are used in the block modelling: Block Unit Profit per dry metric tonne

    of in-situ tailings (US$/dmt) of a block and Block Profit (US$) per block of the geological model.

    The results obtained for the Main Dam consider the tails topography to the terrain bottom after the

    dredging operations that were conducted by Polymetals during the period November 2006 to August

    2008. A further variant covers the full Mineral Resource including the reprocessed tailings deposited in

    the Shale Pit as a result of this previous dredging.

    The average Block Unit Profit estimate is US$51.84/dmt of tails and the standard deviation is US$5.25/dmt.

    The results of the Block Profit (US$) vary within a range from US$100,000 up to US$1,400,000 per block

    of the geological model. The (X, Y) size of a block is 25 m x 25 m while block height is variable. The entire

    area of Main Dam is characterised with positive estimates for both the economic criteria used.

    For the purposes of mining, the sequencing of panels is based on the analysis of the Block Unit Profit

    model of the dam.

    Dredging is the major mining method for the extraction of Hellyer tailings. Hydraulic mining with slurry

    pumps mounted on a platform and water cannon wash are the other mining methods to be used.

    Production scheduling of Hellyer Tailings Dam is organised using the dredging assumptions as follows:

    dredging rate = 3,234 dmt/day or 154 dmt/hour (21 hours per day); resources time of dredging = 355 days

    per year (10 days for planned maintenance); number of shifts = two shifts per day (each shift = 12 hours);

    and working days per week = seven days/week. These assumptions are based on analysis of the dredge

    performance during the 2006 to 2008 dredging period.

  • VI

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    1.6.2 Environmental, Law Compliance and Permits

    Caloundra Environmental Pty Ltd and Hellyer Gold Mine Pty Ltd (HGM) have conducted preliminary

    assessments to identify key environmental aspects associated with the proposed development.

    Emission limits have been set by the Environmental Protection Authority (EPA) to manage the point source

    pollution (the TSF outflow), and the environmental authority for the tailings reprocessing operation, PCE

    7386, sets emission limits from the Main Dam in its condition EF2.

    Historically, zinc has been the most difficult limit to meet at the TSF outfall. Since the Aberfoyle Resources

    Ltd operation ceased production in June 2000 and closed in 2003, sulphidic tailings have been left

    exposed in the upper reaches of the eastern arm of the Main Dam and in Mill Creek. The acidity generated

    from these sulphides caused ongoing issues with pH in the Main Dam. The pH in the Main Dam is

    important due to the relationship between a pH above 8.0 and total zinc concentrations at the TSF outfall.

    HGMs improved management protocols, such as adding a lime slurry directly into the eastern arm

    spillway before it overflows into the main TSF, have been responsible for most of the improvements seen

    since 2016.

    Environmental licence conditions for the site since 2006 have required a minimum pH of 8.0 and a

    maximum Total Zn of 0.8 mg/L at the TSF outfall. A review of long-term water quality records indicates

    that with good management procedures and the remediation proposed by HGM, this should be readily

    achievable going forward.

    HGM holds the consolidated mining lease, CML 103M/87 and the environmental licences PCE 7386

    (tailings mining and reprocessing) and PCE 7759 (Fossey underground mine). HGM plans to reprocess

    tailings under PCE 7386.

    The mining lease encompasses the area at Hellyer where the tailings impoundment and the processing

    plant are situated. The original lease (CML 103M/1987) was granted on 24 February 1988. It was renewed

    and extended in June 2009. It is currently valid until 20 June 2020. An application for an extension of the

    lease can only be made no more than three months before and one month after the lease ceases to be

    effective.

    In October 2017, following submission by HGM, the EPA of Tasmania approved the Environmental

    Management Plan (EMP) for implementation of the Hellyer Project, which was prepared and submitted

    by Caloundra Environmental Pty Ltd in accordance with the Condition G7 of Permit Conditions

    Environmental (PCE) No. 7386.

    1.6.3 Mineral Processing

    A processing plant exists at Hellyer with all the relevant equipment required to reprocess tailings. The

    plant was used previously to produce a range of concentrates from mined ore and a bulk concentrate

    from previous tailings reprocessing.

    The plant is a relatively modern base metals processing facility that was commissioned in early 1989 and

    designed to treat the complex Hellyer fine grained copper-silver-lead-zinc orebody. Its initial capacity was

    for 1.0 million tonnes per annum (Mt/a) with a circuit consisting of a semi-autogenous grind (SAG) mill,

    ball mill and sequential copper, lead, zinc and bulk flotation circuits. The plant was expanded to 1.25 Mt/a

    in early 1990 with the addition of pebble crushing, DSM screens in the SAG mill circuit and extra lead and

    bulk circuit flotation capacity.

    Early processing performance was typified by low metal recoveries to concentrates, but these improved

    during subsequent operation.

  • VII

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    This plant is in reasonable condition and currently under a maintenance program that includes some

    activities focused on preparation for the proposed retreatment project. However further refurbishment

    will be required before it can be brought back into production.

    The processing plant is expected to operate at an average tailings feed rate of 154 dmt/hour with

    availability of 92%. This performance was achieved during the previous dredging operations (2006 to

    2008). The plant is already equipped with a high degree of instrumentation, automation and process

    control equipment enabled by online, real-time measurement and recording.

    The metallurgical processing characteristics of the Hellyer ore have been extensively tested and are well

    known. Recent tests have been conducted by ALS Laboratories (ALS) in Burnie and reviewed by Pitt &

    Sherry Group (2016) with the objective of defining a new flowsheet for the reprocessing of Hellyer tailings

    and optimising metal recoveries.

    Based on the analysis of these test results, understanding of the potential reprocessing characteristics has

    been improved and a number of options to optimise the process identified.

    Arsenic (As) is the only significant deleterious element in the proposed concentrate production. NQM

    advised that it will target As grades below 1% in the planned concentrate products and/or use the blending

    capabilities of marketing agents to enable product saleability.

    Table 3 below summarises the assumptions about concentration production in the current study.

    Table 3: Planned parameters of concentrate production

    Parameter Unit Lead concentrate Zinc concentrate Au/Ag/pyrite concentrate

    Pb grade % 37 5

    Pb recovery % 47

    Zn grade % 6 45

    Zn recovery % 38

    Au grade g/t 6.9 2 2.77

    Ag grade g/t 850 160 64

    Concentrate mass recovery % 51

    The residuals from tailings retreatment in the Hellyer plant need additional storage capacity due to the

    specific characteristics of the residuals and the proposed use of dredging for mining. The Hellyer residue

    will be stored underwater to prevent potential oxidisation and acid formation.

    The total quantity of residue that will be released from the processing plant after the treatment of the

    tailings (9.7 Mt) is 4.2 Mt.

    A new TSF (TSF2) will be built and ready for storage of the residue by April 2019 (Longey, 2017). The

    embankment is proposed to be located approximately 550 m downstream of the Hellyer Main Dam,

    located approximately 2 km northwest of the Mill Site. The initial phase will hold 3.0 Mt, with a planned

    lift, scheduled for 2024, that will provide storage for the remaining 1.2 Mt. The new TSF2 footprint is

    shown in Figure 1.

  • VIII

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Figure 1: New TSF2 downstream of Main Dam (after Longey, 2017)

    For the period from April 2018 until March 2019, a quantity of 0.49 Mt residue will need to be temporarily

    stored in accordance with the planned schedule detailed in Section 9. The Finger Pond will be used for

    this purpose and to enable this the tailings that are currently located in the Finger Pond will be transferred

    to the Main Dam during the pre-production period. The quantity of 0.49 Mt residue temporarily stored in

    the Finger Pond will be transferred to TSF2 by using slurry pumps prior to lowering the water level in the

    Main Dam and Finger Pond as described in the mining plan.

    The transport of the residue from the processing plant to the storage dams will be done with a slurry

    pump. Deposition of residuals into the storage areas will be sub-aqueous. This approach will minimise any

    risks associated due to contact with oxygen in the air and potential oxidation.

    1.6.4 Economic Evaluation

    All capital cost estimates for the project were supplied to AusGEMCO by NQM. The total estimate is

    US$31,253,570. All costs are projected over the LOM period of 114 months (March 2017 until September

    2026 for the purposes of evaluation). Most of the capex is allocated over the first two years of the project

    commencement. The highest component of the capital expenditure is the cost for building a new TSF

    (US$16,136,364).

    NQM supplied the operating costs for the Hellyer Tailings Project. Table 4 below reflects a summary of

    some operating costs per unit product and run of mine (ROM) tailings.

  • IX

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Table 4: Hellyer Tailings Project operating expenditure

    Cost Unit Value

    Dredging A$/dmt 2.84

    Hydraulic mining A$/dmt 2.84

    Processing A$/dmt 18.5

    Logistics EXW to FOB A$/wmt 18.55

    Logistics FOB to CIF A$/wmt 25

    Sales and marketing A$/month 20,000

    Shutdown maintenance A$/month 400,000

    General and administration A$/LOM 12,234,527

    Royalty Percent net revenue 5

    Mine closure/rehabilitation A$ 2,000,000

    Two variants of the economic evaluation of Hellyer Tailings Retreatment Project have been assessed.

    The first variant reflects a discounted cash flow (DCF) model based on the Ore Reserve estimate of the

    Hellyer Project. The basic metrics of the analysis are presented in Table 5 below. The NPV is positive

    (US$113.2 million) for the case that incorporates the acquisition cost of the Project. The Discounted Cash

    Flow Internal Rate of Return (DCFIRR) is 91% which is higher than the project discount rate of 10%. The

    NPV calculated without the acquisition cost is US$128.5 million and the DCFIRR is 197%. This gives grounds

    to accept the Hellyer Tailings Retreatment Project as economically effective, which is a precondition for

    reporting its Ore Reserve in accordance with the JORC Code (2012).

    Table 5: Summary of the DCF model results based on Ore Reserve estimate

    Parameters Unit Value

    Net revenue US$M 628

    Operating expenses US$M 343

    Cash flows before tax US$M 285

    Cash flows after tax and acquisition US$M 183

    With Acquisition Cost

    NPV US$M 113.2

    DCFIRR % 90.94

    DCFPBP months 28

    Without Acquisition Cost

    NPV US$M 128.4

    DCFIRR % 197.42

    The second variant is an option of the evaluation of the Hellyer Project with the inclusion of the Inferred

    Mineral Resource of Shale Pit which could be extracted at the end of the life of mine (LOM). This

    assessment is a requirement of the 2012 JORC Code, Table 1 Modifying Factors or Assumptions about

    the manner in which the Inferred Mineral Resources are utilised and the sensitivity of the outcome of

    their inclusion. The resource of Shale Pit is 1.2 Mt and the total quantity of tailings included in the DCF

    model for this variant is 9.7 Mt.

    The basic metrics of the DCF model are summarised in Table 6. The NPV is positive (US$124.7 million) for

    the case that incorporates the acquisition cost of the Project. The DCFIRR is 91% which is higher than the

    project discount rate of 10%. This give grounds to accept the Hellyer Tailing Project as economically

    effective. The Discounted Cash Flow Payback Period (DCFPBP) is 28 months. The NPV calculated without

    the acquisition cost is US$139.9 million and the DCFIRR is 197%.

  • X

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Table 6: Summary of the DCF model results with inclusion of the Shale Pit resource

    Parameters Unit Value

    Net revenue US$M 708

    Operating expenses US$M 388

    Cash flows before tax US$M 320

    Cash flows after tax and acquisition US$M 209

    With Acquisition Cost

    NPV US$M 124.7

    DCFIRR % 91.26

    DCFPBP months 28

    Without Acquisition Cost

    NPV US$M 139.9

    DCFIRR % 197.46

    1.7 Ore Reserve Estimate

    The Hellyer TSF Ore Reserve estimate is reported in Table 7 and was compiled for NQM as a part of the

    mine planning study undertaken by AusGEMCO. This study followed a process of detailed mine

    optimisation using AusGEMCOs original method that incorporated Geological Block Profit Modelling,

    mine design, sequencing, production scheduling economic evaluation and mine project risk assessment.

    The resulting Ore Reserve estimate was prepared using the Guidelines of the Australasian Code for

    Reporting of Ore Reserves (JORC Code, 2012).

    The Ore Reserve estimate relates specifically to the conversion of Measured and Indicated Mineral

    Resources of the Hellyer TSF Project and includes consideration of the modifying factors documented in

    Appendix 1 JORC Code Table 1.

    No cut-off grade(s) has been used in the reserve estimation due to the specific nature of mining the tailings

    by dredging. Details on the implementation of other modifying factors are presented in Section 3 of the

    AusGEMCO technical report (AusGEMCO, 2017), and are summarised in Section 7 of this report.

    All material classified as Measured Mineral Resources in the Hellyer TSF has translated into Proved Ore

    Reserves while all material classified as Indicated Mineral Resources has translated to Probable Ore

    Reserves. The reserve conversion is based on the CSA Global Mineral Resource estimate updated 24

    August 2017 (CSA Global, 2017).

  • XI

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Table 7: Hellyer TSF Ore Reserve estimate* (6 September 2017)

    Ore Reserves

    Gross Operator

    Tonnage (Mt)

    Grade Contained metal

    NQM

    Zn % Pb % Ag g/t Au g/t Cu % Zn (t) (00)

    Pb (t) (00)

    Ag (oz) (000)

    Au (oz) (000)

    Cu (t) (00)

    Proved 2.05 3.31 3.35 94 2.63 0.21 679 687 6,212 173 43

    Probable 5.99 2.29 2.95 93 2.55 0.18 1,372 1,767 17,941 491 108

    Total 8.04 2.55 3.05 93 2.57 0.19 2,050 2,454 24,153 664 151

    Net attributable

    Tonnage (Mt)

    Grade Contained metal

    Zn % Pb % Ag g/t Au g/t Cu %

    Zn (t) (00)

    Pb (t) (00)

    Ag (oz) (000)

    Au (oz) (000)

    Cu (t) (00)

    Proved 2.05 3.31 3.35 94 2.63 0.21 679 687 6,212 173 43

    Probable 5.99 2.29 2.95 93 2.55 0.18 1,372 1,767 17,941 491 108

    Total 8.04 2.55 3.05 93 2.57 0.19 2,050 2,454 24,153 664 151

    * Mt tonnes and Zn, Ag, Au and Cu grades are rounded to two decimal places, Ag to the nearest whole number. Contained metal tonnes are reported to nearest hundred, and ounces to nearest thousand tonnes.

    Table 8: Hellyer TSF non-JORC Reserve deposited material (6 September 2017)

    Non-JORC Reserves

    Gross Operator

    Tonnage (Mt)

    Grade Contained metal

    NQM

    Zn % Pb % Ag g/t Au g/t Cu % Zn (t) (00)

    Pb (t) (00)

    Ag (oz) (000)

    Au (oz) (000)

    Cu (t) (00)

    Fossey 0.45 1.84 1.37 35 1.80 0.03 83 62 512 26 1

    Shale Pit 1.21 1.00 2.60 86 2.57 0.19 121 315 3,346 100 23

    Total 1.66 1.23 2.27 72 2.36 0.15 204 376 3,857 126 24

    * Mt and Zn, Ag, Au and Cu grades are rounded to two decimal places, Ag to the nearest whole number. Contained metal tonnes are reported to nearest hundred, and ounces to nearest thousand tonnes.

  • XII

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Table 8 above shows the estimates of additional deposited tailings material at Hellyer. This is not classified

    as a JORC Code Ore Reserve category. The Fossey tailings were deposited on top of the existing tailings in

    the Western Arm Dam after preparation of the 2010 CSA Global Mineral Resource estimate. At present,

    the Fossey tailings are unclassified while the tailings beneath them are classified as a Probable Reserve.

    However, the extraction of the Probable Reserve of the Western Arm Dam is possible only after the

    extraction of Fossey tailings which lie above them. For this reason, the Fossey tailings have been taken

    into account in the mine plan and financial model of Hellyer Project.

    Additional deposited tailings materials are located in the Shale Pit. The recent update of the Hellyer

    Resource model in 2017 has classified these tailings as an Inferred Mineral Resource, which is insufficient

    for their translation into a JORC Ore Reserve category. These tailings have an economic potential and have

    been analysed in the aforementioned variant to mine plan and financial model for the Hellyer Project.

    1.8 Risk Assessment

    Ore Reserve Risk has been assessed by using the Monte Carlo method to generate randomly distributed

    sample estimates for geological parameters such as in-situ Pb grade, Zn grade, Au grade, Ag grade and

    tailings density. This risk evaluation used a similar cash flow model to that developed for the economic

    evaluation of the Hellyer Tailings Retreatment Project in Section 10 of the Report. However, because this

    risk model applied a simplified assumption to the timing of tax payments it resulted in a slightly different

    deterministic Project NPV (US$118.9 million) from the Project NPVs referenced above.

    For the purpose of Ore Reserve Risk, all other inputs to the cash flow model are assumed to be constant.

    Two variants were used for the assessment of the standard deviations of the geological variables:

    Variant 1 used the monthly estimates of the grades in the production schedule to determine the

    standard deviation.

    Variant 2 assessed standard deviations by using the results of CSA Global variogram modelling of the

    Hellyer Mineral Resource (CSA Global, 2010), which captures the short-range variability.

    Estimates of variation of tailings density were obtained using a standard deviation of 10% around the

    assumed constant tailings density (1.93 t/m3) as applied in the Geological Block Model.

    Two criteria are used for assessing the Ore Reserve Risk:

    Risk that the stochastic NPV is less than the deterministic NPV.

    Risk that the stochastic NPV is less than zero.

    1.8.1 Variant 1

    The estimates of the Ore Reserve Risk are presented in Table 9. The criteria using the stochastic project

    NPV (US$122.5 million) relative to the deterministic Project NPV (US$118.9 million) as a critical level of the

    Ore Reserve risk shows a risk estimate of 32%, which means that the stochastic NPV is higher than the

    deterministic NPV for 68% of estimates. In other words, this also means that the deterministic NPV, using

    only average estimates of the tonnage and grades of Ore Reserves, is an underestimate. The results using

    the second criterion of the risk analysis (Table 9) indicate a zero Ore Reserve Risk because the stochastic

    Project NPV (US$122.5 million) is much higher than zero.

    These results give ground to conclude that the current estimates of the variability of the tailings grades

    and density will not have a significant negative impact on the successful and profitable exploitation of

    Hellyer tailings.

  • XIII

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Table 9: Ore Reserve Risk estimates Variant 1

    NPV mean (US$) NPV Std Dev (US$) Critical level (US$) Probability (%) Risk (%)

    122,494,493 7,724,451 118,901,024 67.91 32.09

    122,084,493 7,724,451 0 100 0

    1.8.2 Variant 2

    The estimates of the Ore Reserve Risk using Variant 2 are summarised in Table 10.

    The risk that the stochastic Project NPV (US$120.9 million) is less than the deterministic NPV

    (US$118,901,024) is 35.24%, while the risk that the stochastic Project NPV is less than zero is 0%. These

    estimates confirm the validity of the conclusions made for Variant 1 that:

    The stochastic NPV is higher than the deterministic NPV, which indicates an underestimation of the

    deterministic NPV.

    The stochastic NPV is significantly higher than zero.

    The estimates of ore grades and density will not have a significant negative impact on the profitable

    exploitation of Hellyer tailings.

    Table 10: Ore Reserve Risk estimates Variant 2

    NPV mean (US$) NPV Std Dev (US$) Critical level (US$) Probability (%) Risk (%)

    120,940,367 5,381,536 118,901,024 64.76 35.24

    120,940,367 5,381,536 0 100 0

    The Mining Project Risk assessment followed the methodology described in the references (Halatchev et

    al., 2005; Halatchev, 2007; Davis et al., 2007). This methodology deals with the concept of the

    development of a stochastic DCF model over LOM and treatment of all parameters of the mining project

    as random quantities or functions depending on available input data.

    The criterion for defining the Mining Project Risk are the DCFs of the mining project assessed with the

    discounted cash flow model. This criterion is based on the risk of not achieving positive discounted cash

    flows at each time step of the DCF analysis, which is a logical requirement of mining business. Such a

    formulation of the Mining Project Risk model means that a strategy for achieving positive DCFs over the

    LOM is set by the mining company.

    To assess the Mining Project Risk, 300 Monte Carlo simulations were run, and their analysis indicates a

    negative cash flow for the first period till the 14th month. After that period all cash flows are positive except

    for the 23rd and 83rd months, which are affected by the increase of capex and mine closure bond costs

    (23rd) and the increase in mining costs because of using water cannon washing technology and additional

    capex (83rd).

    The payback period of the stochastic cash flows profile is 28 months. As noted above, it is important to

    note that the cash flows are assessed with income tax paid every month of the year.

    The results of the Mining Project Risk assessment indicate that the risk is 100% for the period until the 14th

    month. This is to be expected because the planned cash flows are negative for that period. After that

    period the risk varies within the range from 0 to 10%. There are three short periods of higher risk after

    the 14th month, the first two are due to the negative cash flow months mentioned above, and the third

    during shutdown of the mining operations and mine closure.

    Generally, the predicted profile of the Mining Project Risk is attractive for investment and useful for the

    decision-making process. It can also help the management of NQM in shaping a strategy about the

    mitigation of Mining Project Risk and achieving sustainable exploitation of the Hellyer tailings.

  • XIV

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Contents

    Report prepared for ............................................................................................................................................ I

    Report issued by ................................................................................................................................................. I

    Report information ............................................................................................................................................. I

    Author and Reviewer Signatures ........................................................................................................................ I

    DISCLAIMERS ......................................................................................................................................................... II

    Purpose of this document ................................................................................................................................. II

    Notice to third parties ....................................................................................................................................... II

    Results are estimates and subject to change .................................................................................................... II

    1 EXECUTIVE SUMMARY ............................................................................................................................... III

    1.1 Tenure ................................................................................................................................................ III

    1.2 Project Location, Access and Climate ................................................................................................. III

    1.3 Geology and Nature of the Deposit .................................................................................................... III

    1.4 Mineral Resource Estimate................................................................................................................. III

    1.5 Previous Mining Studies ..................................................................................................................... IV

    1.6 Current Mining Study .......................................................................................................................... V 1.6.1 Mine Design and Planning .......................................................................................................... V 1.6.2 Environmental, Law Compliance and Permits ........................................................................... VI 1.6.3 Mineral Processing .................................................................................................................... VI 1.6.4 Economic Evaluation ............................................................................................................... VIII

    1.7 Ore Reserve Estimate .......................................................................................................................... X

    1.8 Risk Assessment ................................................................................................................................ XII 1.8.1 Variant 1 ................................................................................................................................... XII 1.8.2 Variant 2 .................................................................................................................................. XIII

    2 INTRODUCTION ........................................................................................................................................... 1

    2.1 Context, Scope and Terms of Reference ............................................................................................. 1

    2.2 Compliance with the JORC Code ......................................................................................................... 1

    2.3 Principal Sources of Information ......................................................................................................... 1

    2.4 Authors of the Report Qualifications, Experience and Competence ................................................ 2

    2.5 Independence ...................................................................................................................................... 3

    2.6 Declarations ......................................................................................................................................... 3

    2.7 Results are Estimates and Subject to Change...................................................................................... 3

    2.8 About this Report ................................................................................................................................ 4

    2.9 Competent Person Statement ............................................................................................................. 4

    3 PROPERTY DESCRIPTION AND TENURE........................................................................................................ 5

    3.1 Property Location and Climate ............................................................................................................ 5

    3.2 Property Description ........................................................................................................................... 6

    3.3 Tenure ................................................................................................................................................. 7

    4 GEOLOGY AND PROJECT HISTORY ............................................................................................................... 8

    4.1 Geology ................................................................................................................................................ 8

  • XV

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    4.2 Project History ..................................................................................................................................... 8 4.2.1 Hellyer Base Metals Mine ........................................................................................................... 8 4.2.2 Metallurgical Accounting ............................................................................................................ 8 4.2.3 Retreatment of Tails ................................................................................................................... 8 4.2.4 Fossey Base Metals Mine ........................................................................................................... 9

    5 MINERAL RESOURCE ESTIMATE ................................................................................................................. 11

    5.1 Exploration History ............................................................................................................................ 11

    5.2 Mineral Resource Estimate................................................................................................................ 12

    6 PREVIOUS MINING STUDIES ...................................................................................................................... 15

    7 CURRENT MINING STUDY .......................................................................................................................... 17

    7.1 Mine Design and Planning ................................................................................................................. 17 7.1.1 Mine Design based on Block Profit Modelling .......................................................................... 17 7.1.2 Production Scheduling.............................................................................................................. 22

    8 ENVIRONMENTAL, LAW COMPLIANCE AND APPROVED PERMITS ............................................................. 27

    8.1 Key Environmental Aspects and their Management ......................................................................... 27

    8.2 Relevant Legislation, Regulations, Codes and Polices ....................................................................... 30

    8.3 Environmental Licences and Permits................................................................................................. 31

    8.4 Environmental Permitting History ..................................................................................................... 32

    9 MINERAL PROCESSING .............................................................................................................................. 33

    9.1 Prior Processing Plant Preparation .................................................................................................... 33

    9.2 Current Plant Configuration .............................................................................................................. 34

    9.3 Planned Plant Operation ................................................................................................................... 35

    9.4 Planned Concentrate Production ...................................................................................................... 37

    9.5 Tailings Residue Storage .................................................................................................................... 42

    10 ECONOMIC EVALUATION .......................................................................................................................... 46

    10.1 Capital Cost Estimates ....................................................................................................................... 46

    10.2 Operating Cost Estimates .................................................................................................................. 47

    10.3 Financial Model Assumptions ............................................................................................................ 47

    10.4 Discounted Cash Flow Model ............................................................................................................ 48 10.4.1 Discounted Cash Flow Model based on the Ore Reserves Estimate ........................................ 48 10.4.2 Discounted Cash Flow Model with Inclusion of Shale Pit Inferred Mineral Resource .............. 48

    11 ORE RESERVE ESTIMATE ............................................................................................................................ 53

    12 RISK ASSESSMENT ..................................................................................................................................... 57

    12.1 Ore Reserve Risk Assessment ............................................................................................................ 57

    12.2 Mining Project Risk Assessment ........................................................................................................ 59

    13 CONCLUSIONS ........................................................................................................................................... 64

    14 REFERENCES .............................................................................................................................................. 66

    15 GLOSSARY ................................................................................................................................................. 67

  • XVI

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    16 ABBREVIATIONS AND UNITS OF MEASUREMENT ...................................................................................... 69

    Figures Figure 1: New TSF2 downstream of Main Dam (after Longey, 2017) ...................................................................... VIII Figure 2: Project location ............................................................................................................................................ 5 Figure 3: Site layout .................................................................................................................................................... 6 Figure 4: Collar plan for Hellyer TSF .......................................................................................................................... 11 Figure 5: Zn % grade variation with depth, by year of drilling .................................................................................. 12 Figure 6: Block Unit Profit spatial distribution of Main Dam .................................................................................... 18 Figure 7: Block Profit spatial distribution of Main Dam ............................................................................................ 18 Figure 8: Block Profit spatial distribution of Finger Pond Dam ................................................................................. 19 Figure 9: Block Profit spatial distribution of Western Arm Dam ............................................................................... 19 Figure 10: Block Profit spatial distribution of Shale Pit ............................................................................................... 20 Figure 11: Mine sequence of Main Dam for benches B1 and B2 ................................................................................ 22 Figure 12: Monthly tails production schedule ............................................................................................................ 23 Figure 13: Monthly Zn head grade distribution .......................................................................................................... 24 Figure 14: Monthly Pb head grade distribution .......................................................................................................... 24 Figure 15: Monthly Au head grade distribution .......................................................................................................... 25 Figure 16: Monthly Ag head grade distribution .......................................................................................................... 25 Figure 17: TSF outflow pH versus total zinc (operations compared with closure) ................................................... 28 Figure 18: Emission improvement since 2016 ............................................................................................................ 29 Figure 19: TSF discharge pH and Total Zn since January 2016 .................................................................................... 29 Figure 20: TSF discharge pH versus Total Zn ............................................................................................................... 30 Figure 21: Hellyer mining lease ................................................................................................................................... 32 Figure 22: Hellyer Tailings lead and zinc grades by year ............................................................................................. 33 Figure 23: Inside view of the processing plant ............................................................................................................ 35 Figure 24: Flowsheet of the Hellyer processing plant ................................................................................................. 36 Figure 25: Tailings storage tanks behind the mill ........................................................................................................ 37 Figure 26: Schematic view of the proposed flotation technology .............................................................................. 38 Figure 27: Schedule of zinc production in concentrate............................................................................................... 40 Figure 28: Schedule of lead production in concentrate .............................................................................................. 40 Figure 29: Schedule of gold production in concentrate .............................................................................................. 41 Figure 30: Schedule of silver production in concentrate ............................................................................................ 41 Figure 31: Schedule of monthly tailings residues over LOM ....................................................................................... 43 Figure 32: New TSF2 downstream of Main Dam ........................................................................................................ 45 Figure 33: Histogram of NPV estimates Variant 1 .................................................................................................... 58 Figure 34: Histogram of NPV estimates Variant 2 .................................................................................................... 59 Figure 35: Stochastic DCFs profile ............................................................................................................................... 61 Figure 36: Mining Project Risk profile over LOM ........................................................................................................ 61

    Tables Table 1: Hellyer Tailings Storage Facility, Mineral Resource estimate ..................................................................... IV Table 2: Hellyer Tailings Storage Facility, Mineral Resource estimate metal tonnes and ounces, gross total

    only, all attributable to NQM ...................................................................................................................... IV Table 3: Planned parameters of concentrate production........................................................................................ VII Table 4: Hellyer Tailings Project operating expenditure ........................................................................................... IX Table 5: Summary of the DCF model results based on Ore Reserve estimate ......................................................... IX Table 6: Summary of the DCF model results with inclusion of the Shale Pit resource .............................................. X Table 7: Hellyer TSF Ore Reserve estimate* (6 September 2017) ............................................................................ XI Table 8: Hellyer TSF non-JORC Reserve deposited material (6 September 2017) .................................................... XI

  • XVII

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Table 9: Ore Reserve Risk estimates Variant 1 .................................................................................................... XIII Table 10: Ore Reserve Risk estimates Variant 2 .................................................................................................... XIII Table 11: Summary table of assets .............................................................................................................................. 7 Table 12: Metallurgical accounting, Hellyer .............................................................................................................. 10 Table 13: Hellyer Tailings Storage Facility, Mineral Resource estimate .................................................................... 14 Table 14: Hellyer Tailings Storage Facility, Mineral Resource estimate metal tonnes and ounces (gross total

    only, all attributable to NQM) .................................................................................................................... 14 Table 15: Parameters of mine design of all dams ...................................................................................................... 21 Table 16: TSF discharge emission limits ..................................................................................................................... 27 Table 17: Planned parameters of concentrate production........................................................................................ 39 Table 18: Schedule of residues storage ..................................................................................................................... 43 Table 19: Residue storage capacities ......................................................................................................................... 44 Table 20: Hellyer Tailings Project capital expenditure ............................................................................................ 46 Table 21: Hellyer Tailings Project operating expenditure ....................................................................................... 47 Table 22: Forecasting of Zn, Pb, Au and Ag prices ..................................................................................................... 48 Table 23: Summary of the DCF model results for Ore Reserve estimate .................................................................. 50 Table 24: Summary of the DCF model results including Shale Pit Inferred Mineral Resource .................................. 50 Table 25: DCF model of Hellyer Project based on Ore Reserve estimate .................................................................. 51 Table 26: DCF model of Hellyer Project with inclusion of Inferred Mineral Resource............................................... 52 Table 27: Hellyer TSF Ore Reserve estimate* (6 September 2017) ........................................................................... 54 Table 28: Hellyer Non-JORC Reserves (31 August 2017) of Fossey tails in the Western Arm and Shale Pit tails ...... 54 Table 29: Hellyer Ore Reserve Datamine files ........................................................................................................... 55 Table 30: Hellyer Ore Reserve Grid Datamine files .................................................................................................... 55 Table 31: Statistical input parameters of Ore Reserve Risk assessment ................................................................... 58 Table 32: Input parameters of variogram modelling ................................................................................................. 58 Table 33: Ore Reserve Risk estimates Variant 1 ..................................................................................................... 59 Table 34: Ore Reserve Risk estimates Variant 2 ..................................................................................................... 59 Table 35: Results of Mining Project Risk assessment ................................................................................................ 62

    Appendices Appendix 1: JORC Code (2012 Edition) Table 1

  • 1

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    2 Introduction

    2.1 Context, Scope and Terms of Reference

    CSA Global Pty Ltd (CSA Global) was engaged by NQ Mineral Plc (NQM) to compile a Competent Persons

    Report (CPR) setting out, in addition to required background information, the Mineral Resource estimate

    and Ore Reserve estimate relating to the Hellyer Tailings Retreatment Project (Hellyer or Hellyer Project),

    located in Tasmania, Australia.

    This report was prepared exclusively for NQM by CSA Global. The quality of information, conclusions and

    estimates contained in this report are consistent with the level of the work carried out by CSA Global to

    date on the assignment, in accordance with the assignment specification agreed between CSA Global and

    NQM.

    In preparing this report, CSA Global has:

    1. Adhered to the JORC Code2.

    2. Relied on the accuracy and completeness of the data provided to it by NQM, and that NQM made

    CSA Global aware of all material information in relation to the project asset.

    3. Relied on the accuracy and completeness of the data, information and reporting provided to it by

    AusGEMCO Pty Ltd (AusGEMCO) where this relates to the Ore Reserve Study, having completed

    appropriate gap analysis and peer review of this work prior to inclusion of this study in this report.

    4. Relied on NQMs representation that it will hold adequate security of tenure for assessment of the

    project to proceed.

    5. Has independently verified the data used to prepare this report and concludes that the data provide

    reasonable grounds for CSA Globals conclusions reached in this report.

    6. Required that NQM provide an indemnity to the effect that NQM would compensate CSA Global in

    respect of preparing the report against any and all losses, claims, damages and liabilities to which

    CSA Global or its Associates may become subject under any applicable law or otherwise arising from

    the preparation of the report to the extent that such loss, claim, damage or liability is a direct result

    of NQM or any of its directors or officers knowingly providing CSA Global with any false or misleading

    information, or NQ Minerals, or its directors or officers knowingly withholding material information.

    7. Required an indemnity that NQM would compensate CSA Global for any liability relating to any

    consequential extension of workload through queries, questions or public hearings arising from the

    reports.

    2.2 Compliance with the JORC Code

    This report has been prepared in accordance with the JORC Code (2012 Edition), which is binding upon

    Members of the Australian Institute of Geoscientists (AIG) and the Australasian Institute of Mining and

    Metallurgy (AusIMM) for the reporting of Mineral Resources and Ore Reserves.

    2.3 Principal Sources of Information

    CSA Global has based its review based on information made available to the authors by NQM, along with

    technical reports prepared by consultants, previous tenement holders and other relevant published and

    unpublished data.

    2 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. The JORC Code, 2012 Edition. Prepared by: The Joint Ore Reserves Committee of The Australasian Institute of Mining and Metallurgy, Australian Institute of Geoscientists and Minerals Council of Australia (JORC).

  • 2

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    CSA Global has relied upon discussions with NQMs management, as well as previous company and

    consultants reports for information contained within this assessment.

    CSA Global visited the Project on 17 July 2017, reviewing the project setting, infrastructure and discussing

    the Projects history with the Resident Manager, Mr Bob Quilliam.

    This report has been based upon information available up to and including 7 September 2017.

    CSA Global has endeavoured, by making all reasonable enquiries, to confirm the authenticity, accuracy,

    and completeness of the technical data upon which this report is based. Unless otherwise stated,

    information and data contained in this technical report or used in its preparation has been provided by

    NQM in the form of documentation, and from data obtained and observations made during the site visits.

    NQM was provided a final draft of this report and requested to identify any material errors or omissions

    prior to its lodgement.

    Descriptions of the mineral tenure; tenure agreements, encumbrances and environmental liabilities were

    provided to CSA Global by NQM. NQM has warranted to CSA Global that the information provided for

    preparation of this report correctly represents all material information relevant to the mineral assets. Full

    details on the tenement is provided in Section 3.

    2.4 Authors of the Report Qualifications, Experience and Competence

    CSA Global is a privately owned, mining industry consulting company headquartered in Perth, Western

    Australia, with regional offices throughout the world. CSA Global provides geological, resource, mining,

    management and corporate consulting services to the international resources sector and has done so for

    more than 30 years.

    This report has been prepared by a team of consultants sourced from CSA Globals Perth and Horsham

    (UK) offices. The individuals who have provided input to the report have extensive experience in the

    mining industry and are members in good standing of appropriate professional institutions. The

    Consultants preparing this report are specialists in the fields of geology, exploration and Mineral Resource

    estimation, in particular relating to tailings dam deposits.

    The following individuals, by virtue of their education, experience and professional association, are

    considered Competent Persons, as defined in the JORC Code (2012), for this report. The Competent

    Persons individual areas of responsibility are presented below:

    Coordinating author David Williams (Principal Resource Geologist) is responsible for Sections 1.1 to

    1.4 and 2 to 5 of the report.

    Contributing author Peter Cranfield (Associate Principal Mining Engineer) is responsible for Sections

    1.5 to 1.8 and 6 to 12 of the report.

    Peer reviewer Mr Galen White (Director Europe and Africa) has peer reviewed all sections of this

    report.

    David Williams, CSA Global Principal Resource Geologist, is a resource geologist with 25 years experience

    in Mineral Resource estimation and mine geology. He has worked on a variety of commodities including

    gold, iron ore, uranium, nickel laterite, graphite and base metals in Australia, Indonesia and Namibia.

    David is a Competent Person for JORC reporting of Mineral Resources and is also a Qualified Person for

    Canadian NI 43-101 reporting for gold and base metals. David is able to provide advice on due diligence

    studies, JORC and NI 43-101 reporting and Independent Geologist Reports.

    Peter Cranfield, Associate Principal Mining Engineer is an engineer with over 40 years experience in the

    mining industry throughout South-East Asia and Australia, specialising in alluvial mining and tailings

    projects. He has 10 years experience operating and managing narrow vein underground mines and 30

  • 3

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    years experience in alluvial and tailings mining and processing, covering exploration, development and

    production for tin, wolfram, gold, mineral sands and diamonds. Alluvial resource evaluation, feasibility

    studies, planning and development of new mines. Exploration and evaluation through drilling, bulk

    sampling, and pilot plants to generate sufficient data for mine planning.

    Galen White, CSA Global (UK) Director and Principal Geologist, is a geologist with over 20 years

    experience in the mining industry, with the last 12 years spent in consulting. He has experience in mineral

    exploration, Mineral Resource estimation and mine geology in a variety of geological settings and in

    relation to a variety of mineral commodities including gold, silver, base metals, uranium and iron ore

    across Europe, Africa, Australia, Asia and the Americas. He has completed project reviews, Mineral

    Resource estimates and audits, due diligence reviews, project management and formal stock exchange

    reporting. He is a Competent Person as defined in the JORC Code (2012) and a Qualified Person in relation

    to CIM compliance and NI 43-101 Technical Reporting.

    2.5 Independence

    Neither CSA Global, nor the authors of this report, has or has had previously, any material interest in

    NQM, or the mineral properties in which NQM has an interest. CSA Globals relationship with NQM is

    solely one of professional association between client and independent consultant.

    CSA Global is an independent geological consultancy. Fees are being charged to NQM at a commercial

    rate for the preparation of this report, the payment of which is not contingent upon the conclusions of

    the report.

    No member or employee of CSA Global is, or is intended to be, a director, officer or other direct employee

    of NQM. No member or employee of CSA Global has, or has had, any shareholding in NQM.

    CSA Global has completed technical work previously for Bass Metals Pty Ltd (Bass Metals), the previous

    owners of the Project, and as such disclosure is required including declaration of any previous reports that

    the Practitioner has prepared relating to the Mineral Assets being assessed. To meet this requirement,

    the reader is advised that CSA Global completed the following work for Bass Metals:

    CSA Global prepared the Mineral Resource estimate for the Hellyer Tailings Retreatment Project in

    2010.

    CSA Global prepared a Mining Study for the Project in 2010.

    This report was not influenced by NQM, and reflects CSA Globals objective critical analysis and

    professional judgement.

    2.6 Declarations

    This report has been prepared by CSA Global at the request of, and for the sole benefit of NQM. Its

    purpose is to provide a technical assessment of the Hellyer Tailings Retreatment Project. It is not intended

    to serve any purpose beyond that stated and should not be relied upon for any other purpose.

    The statements and opinions contained in this report are given in good faith and in the belief that they

    are not false or misleading. The conclusions are based on the reference date of 31 July 2017 and could

    alter over time depending on exploration results, mineral prices and other relevant market factors.

    2.7 Results are Estimates and Subject to Change

    The interpretations and conclusions reached in this report are based on current scientific understanding

    and the best evidence available to the authors at the time of writing. It is the nature of all scientific

    conclusions that they are founded on an assessment of probabilities and, however high these probabilities

    might be, they make no claim for absolute certainty.

  • 4

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    The ability to achieve forward-looking production and economic targets is dependent on numerous

    factors that are beyond CSA Globals control and that CSA Global cannot anticipate. These factors include,

    but are not limited, to changes to site-specific mining and geological conditions, management and

    personnel capabilities, availability of funding to properly operate and capitalise the operation, variations

    in cost elements and market conditions, developing and operating the mine in an efficient manner,

    unforeseen changes in legislation and new industry developments. Any of these factors may substantially

    alter the performance of any mining operation.

    2.8 About this Report

    This report discusses the Mineral Resource estimate of the tailings material impounded in the Hellyer

    Tailings Retreatment Project. The geology and mineralisation are discussed, as well as the drilling activities

    completed which support the Mineral Resource estimate. The Project has been part of the Hellyer and

    Fossey polymetallic underground mine, which operated from 1989 to 2000 and 2010 to 2102 respectively.

    Management of the tailings facility has continued to the present day. No discussion is provided concerning

    the Hellyer or Fossey underground orebodies, apart from a discussion on the grades of ore feed into the

    Hellyer mill, and tailings subsequently discharged.

    2.9 Competent Person Statement

    The information that relates to Mineral Resources is based on information compiled by Mr David Williams,

    a Competent Person, who is a Member of the Australasian Institute of Mining and Metallurgy. Mr Williams

    is employed by CSA Global Pty Ltd, an independent consulting company. Mr Williams has sufficient

    experience, which is relevant to the style of mineralisation and type of deposit under consideration, and

    to the activity he is undertaking, to qualify as a Competent Person as defined in the 2012 Edition of the

    Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.

    Mr Williams consents to the inclusion of the matters relating to Mineral Resources, based on his

    information in the form and context in which it appears.

    The information that relates to Ore Reserves is based on information received and reviewed by Mr Peter

    Cranfield, a Competent Person, who is a Member of the Institute of Materials, Minerals and Mining.

    Mr Cranfield is an Associate of CSA Global Pty Ltd, an independent consulting company. Mr Cranfield has

    sufficient experience, which is relevant to the style of mineralisation and type of deposit under

    consideration, and to the activity he is undertaking, to qualify as a Competent Person as defined in the

    2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore

    Reserves. Mr Cranfield consents to the inclusion of the matters relating to Ore Reserves, based on his

    information in the form and context in which it appears.

  • 5

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    3 Property Description and Tenure

    3.1 Property Location and Climate

    Hellyer is located in north-western Tasmania 80 km south of Burnie, just off the main highway between

    Burnie and Queenstown and four hours drive northwest of the capital, Hobart. The area surrounding the

    project is mainly forest reserve with farmland. There has been extensive historical and recent mining

    activity in the area, including the Hellyer base metals mine located adjacent to the Hellyer. The project

    location is presented in Figure 2.

    This part of Tasmania lies in a high rainfall area with annual average precipitation of 2,180 mm (Bureau of

    Meteorology, Waratah) falling all year although higher falls, and snowfall, occur over winter months.

    Average daytime temperatures range from 7C (winter) to 18C (summer).

    Figure 2: Project location

  • 6

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    3.2 Property Description

    The property under study is a tailings dam with a capacity of approximately 10 Mt at an in-situ density of

    approximately 1.9 t/m3. The tailings are the waste product from the Hellyer mill and comprise fine sands

    containing significant values of zinc, lead, copper, gold and silver, a portion of which can possibly be

    recovered by further milling and retreatment by flotation and other means.

    The depth of the tailings varies from 1 m below water level to approximately 20 m below water level at

    the deepest point beside the dam wall. There is an environmental constraint to maintain a minimum water

    cover of 1 m over the surface of the tailings. The tailings contain sulphides susceptible to oxidation and

    the formation of acids if exposed to the atmosphere. This imposes a constraint on the mining method,

    resulting in the choice of a dredge as the most suitable means of mining. A Seabird III 300 kW Electric

    Drive Cutter Suction Dredge is currently moored on the tails dam and has been used in the past to mine

    approximately 2 Mt of the tails material for retreatment in the Hellyer mill. Figure 3 presents a map

    showing the site layout.

    Figure 3: Site layout

  • 7

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    3.3 Tenure

    NQM holds a consolidated granted mining leases CML103M/1987 over the area including the tailings dam

    and the processing plant. This lease covers all the areas required for the proposed tailings reclaim

    operations. The mining lease is held by Hellyer Gold Mines Pty Ltd (HGM), a wholly owned subsidiary of

    NQM. The lease was granted on 24 February 1988 and was renewed and extended in June 2009 until

    30 June 2020. The lease can then be further extended, for as long as the mine is operated, as advised by

    Mineral Resources Tasmania. The annual permit has been paid in full until 15 February 2018.

    Tenure details are presented in Table 11, and the tenement outline is shown in Figure 2 and Figure 3.

    In relation to further extension of the lease beyond June 2020, NQM has been in direct communication

    with the Inspection Team at Mineral Resources Tasmania. The Inspection Team undertakes mining lease

    renewal assessments whose manager reports directly to the Director of Mines (Tasmania), who then

    makes recommendations to the Minister for Mines. NQM was provided with the following email advice

    on 30 August 2016 from the Manager, Inspection Team, as follows:

    Under Section 97(2) of the MRDA, the Minister must grant the application if satisfied that:

    o The lessee has submitted a mining plan for the renewal period;

    o The lessee has complied with the conditions of the lease and provisions of this Act;

    o A failure to comply with any conditions of a lease was exempted under section 86; and

    o The lessee has provided a security deposit.

    The legislation is worded in favour of ongoing security of tenure as long as a lessee provides the

    information, security deposit and has demonstrated compliance.

    The proposed Hellyer Project requires government approvals to operate and, as such, a permit currently

    exists for the reprocessing of tailings (2 Mt/a) at Hellyer (PCE No. 7386). In October 2017, following a

    request by HGM the Environmental Protection Authority (EPA) of Tasmania approved the 2017

    Environmental Management Plan (EMP) for implementation of the Hellyer Project, in accordance with the

    Condition G7 of Permit Conditions Environmental (PCE) No. 7386, as contained in Permit No. DA

    138/2006. As a result, all permits and approvals required for the tailings reclaim and retreatment

    operation are either in place or can be obtained by NQM within the necessary timeframe.

    Table 11: Summary table of assets

    Asset Holder Interest

    (%) Status

    Lease expiry date

    Lease area

    Comments

    Australia, Hellyer Gold Mine

    Hellyer Gold Mines Pty Ltd

    100 Production 30 June

    2020 16.95 km2

    Final permitting for retreatment complete.

  • 8

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    4 Geology and Project History

    4.1 Geology

    The Hellyer deposit is a volcanic hosted polymetallic massive sulphide deposit located within the Mount

    Read volcanic arc of western Tasmania. This region also hosts similar deposits such as Hercules, Que River,

    Roseberry and Mount Lyell. Mineralisation is sulphide hosted and comprised predominantly of pyrite,

    with lesser sphalerite, galena and arsenopyrite. The pyrite must be carefully managed when exposed to

    air to prevent its oxidation and potential to form acid mine drainage issues. The economic metals mined

    at Hellyer were lead, zinc, copper, gold and silver. The Hellyer deposit was mined by underground

    methods during the period 1989 to 2000. The Fossey deposit extends down plunge from the Hellyer

    deposit and was mined by Bass Metals between 2010 and 2012.

    Tailings from the mill were deposited in a depression approximately 1 km to the west of the Hellyer mill.

    The tails were inundated with water to prevent oxidation of the sulphide species present in the tails. The

    tails are typically stratified, having been deposited from discharge pipes set around the dam. The

    sedimentary stratification is also reflected in a mild gradient in grades of Zn and Pb, with grades typically

    higher in the deeper parts of the tails and decreasing as the depth of the tails sediments shallow. The tails

    sediments are unconsolidated.

    4.2 Project History

    4.2.1 Hellyer Base Metals Mine

    The Hellyer base metals mine was operated by Aberfoyle Resources Ltd (Aberfoyle), then Western Metals

    Ltd (Western Metals) between 1989 and 2000. Tails were deposited in a storage facility constructed to

    the west of the mine site, making use of a broad valley. The dam wall is of earth construction.

    4.2.2 Metallurgical Accounting

    Aberfoyle and Western Metals produced a metallurgical account of the materials that were treated

    through their operation during the life of the operation. Table 12 presents the inventory of tails deposited

    in the tailings dam between 1989 and 2000. Table 12 shows the tails deposited in the earlier years

    contained higher grades of Cu, Zn, Pb, Ag and Au than in later years. These higher-grade tails are located

    in the deeper parts of the tailings dam, as discussed in Section 5.2.

    4.2.3 Retreatment of Tails

    The tailings dam was partially dredged between November 2006 and August 2008, for a total of 2.026 Mt

    of tails. These tails were treated at the Hellyer mill. The tails were sourced from the following areas of the

    tails dam, which are depicted in Figure 3:

    Western Arm

    Eastern Arm

    Main Dam.

    The retreated tails were redeposited into the following locations:

    Shale Pit (1.31 Mt)

    Western Arm Dam (0.605 Mt).

    No tails were deposited into the Eastern Arm (Mill Creek) because it was set aside as an environmental

    remediation dam to submerge legacy beached tails mainly emanating from operations during the 1990s

    (Bolger, 2007).

  • 9

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    4.2.4 Fossey Base Metals Mine

    Bass Metals mined the Fossey underground deposit between 2010 and 2012. The tails were discharged

    into the Western Arm of the tailings dam. Table 12 presents the inventory of tails deposited in the tailings

    dam, from ore sourced from Fossey, between 2010 and 2012. No mining production statistics for mill ore

    feed were provided to CSA Global.

  • 10

    NQ MINERALS PLC HELLYER TAILINGS RETREATMENT PROJECT, TASMANIA

    CSA-Report N: R301.2017

    Table 12: Metallurgical accounting, Hellyer

    Year Mill Ore Feed Tails

    Tonnes % Cu % Zn % Pb g/t Ag g/t Au Tonnes % Cu % Zn % Pb g/t Ag g/t Au

    1989 582,022 0.38 13.05 7.08 150.00 2.67 440,503 0.24 5.90 3.66 92.18 2.89

    1990 995,087 0.36 13.12 7.24 166.00 2.63 744,267 0.21 5.18 4.18 105.62 2.33

    1991 1,248,881 0.37 13.78 7.39 178.00 2.77 878,240 0.16 3.39 3.83 101.70 3.13

    1992 1,355,658 0.32 12.55 7.08 170.00 2.80 1,001,451 0.19 3.16 3.93 119.69 3.13

    1993 779,256 0.31 12.33 6.70 157.00 2.41 576,366 0.15 3.23 3.50 99.56 2.71

    1994 1,305,946 0.32 13.07 6.55 165.00 2.43 942,371 0.16 2.97 3.67 102.76 2.76

    1995 1,322,518 0.36 13.14 6.38 155.00 2.30 945,779 0.16 2.45 3.48 94.07 2.69

    1996 1,335,749 0.29 12.57 5.66 148.00 2.23 978,643 0.12 2.54 2.86 85.56 2.54

    1997 1,392,528 0.32 11.94 6.01 155.00 2.47 1,017,928 0.15 2.17 2.57 85.68 2.80

    1998 1,436,210 0.29 10.60 4.91 130.00 2.03 1,105,009 0.14 2.08 2.01 71.00 2.23

    1999 1,491,888 0.32 10.46 5.14 114.00 1.96 1,150,603 0.16 1.99 2.06 66.92 2.17

    2000 1,368,980 0.27 8.63 4.57 106.00 1.89 1,101,027 0.13 1.48 1.71 58.39 1.98

    Total 14,615,210 0.32 11.97 6.11 148.03 2.35 10,882,187 0.16 2.80 3.00 88.42 2.58

    2010-2012 447,798 0.03 1.84 1.37 35.38 1.80