Heitor Moura 2007 Risk Management for private equity investments

download Heitor Moura 2007 Risk Management for private equity investments

of 27

Transcript of Heitor Moura 2007 Risk Management for private equity investments

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    1/27

    Heitor Moura

    A RISK MANAGEMENT PLANA RISK MANAGEMENT PLAN

    UNICONSULT SERVIOS TCNICOS LTDA. RIO DE JANEIRO

    January 2007

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    2/27

    Risk and its managementRisk and its management

    Risk is the possibility that an event will occur, which adverselyaffects the achievement of objectives.

    Risk management is: an on-going process, a means to an end; carried out through plans, policies, surveys, controls, information and

    fundamentally by people;

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 2

    applied in a strategic setting, that is, directed towards objectives; applied throughout the organization, at all hierarchical levels and regional units; aimed at identifying and managing potential adverse events and situations; designed to offer reasonable assurance to its management and board of the

    organization's understanding of risks and of its capability of minimizing their

    effect.

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    3/27

    Risk Management ProcessRisk Management Process

    RISK MANAGEMENT

    PLANNING

    RISK MANAGEMENT

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 3

    MONITORING

    RISK OCCURRENCE

    RESPONSE

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    4/27

    Risk Management ProcessRisk Management Process -- PlanningPlanning

    RISK IDENTIFICATION

    RISK ASSESSMENT

    RISK OF DELAY IN

    INVESTMENT DECISION

    RISK MANAGEMENT

    PLANNING

    RISK MANAGEMENT

    MONITORING

    RISK OCCURRENCE

    RESPONSE

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 4

    RISK-RESPONSE PLAN

    MITIGATION OF

    LIKELIHOOD

    MITIGATION OF

    EVENTUAL IMPACT

    LIKELIHOOD: IMPROBABLE

    IMPACT: SMALLTIME-FRAME: SHORT-TERM

    PROJECT SCHEDULE

    SIMULTANEOUS PROJECTS

    PARTIAL-DECISION PROCESS

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    5/27

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    6/27

    Risk Management ProcessRisk Management Process -- ResponseResponse

    OCCURRENCE OF

    RISK EVENT

    RESPONSE

    TO SITUATION

    DECISION IS DELAYED

    RISK MANAGEMENTPLANNING

    RISK MANAGEMENT

    MONITORING

    RISK OCCURRENCE

    RESPONSE

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 6

    CONTROLOF RESPONSE

    ASSESSMENT OF

    SITUATION POST-EVENT

    ACTION TO SPEEDEN DECISION

    ACTION TO SUBSTITUTE PROJECT

    FOLLOW-UP ON

    ACTIONS

    REVIEW OF PLAN

    REVIEW OF RESPONSE

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    7/27

    Risk componentsRisk components

    DECISION TO TAKE

    ON RISK

    POSSIBILITY OF REDUCING

    LIKELIHOOD

    EXPECTED IMPACT OF

    OCCURRENCE

    LIKELIHOOD OF

    OCCURRENCE

    TIME-FRAME

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 7

    INTENSITY OF EFFECT EXPECTED RESIDUAL RISK

    POSSIBILITY OF

    COVERAGEEFFECT OF RISK

    PLANNED RESPONSE TO

    EVENTUAL OCCURRENCE

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    8/27

    Risk components 2Risk components 2

    Likelihood of occurenceProbability Likelihood

    0% to 1% : highly improbable

    over 1% to 5%: improbable over 5% to 20%: eventual over 20% to 50%: probable over 50% to 100%: highly probable

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 8

    Time-frame for this occurence within 2 years after investment:

    short-term, i.e. there is little time to change risk conditions until 8 years after investment:

    medium term. i.e. there is some time to change risk conditions

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    9/27

    Risk components 3Risk components 3

    Effect of risk Delay in operations Increase in cost Loss of revenue

    Loss of assets Increase in liabilities

    Intensity of effect

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 9

    ow

    medium high

    Result of occurence

    small: affects standard IRR by less than 1% p.a. medium: affects standard IRR by over 1% up to 3% p.a. great: affects standard IRR by over 3% up to 5% p.a. drastic: affects standard IRR by over 5% p.a.

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    10/27

    Risk coverageRisk coverage

    MITIGATION OF

    EVENTUAL IMPACT

    INSURANCE

    HEDGE

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 10

    ABSORTION OF

    RESIDUAL RISK

    GUARANTEE

    OTHER CONTRACTUAL

    TRANSFER

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    11/27

    Risk categories combined with resultsRisk categories combined with results

    100 200 400 800 3200 100 200 400 1600

    50 100 200 400 1600 50 100 200 800

    20 40 80 160 640 20 40 80 320

    10 20 40 80 320 10 20 40 160

    5 10 20 40 160 5 10 20 80

    2 4 8 16 64 2 4 8 32

    1 2 4 8 32 1 2 4 16

    2 4 8 32 1 2 4 16

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 11

    Small Medium Great Drastic Small Medium Great Drastic

    SHORT TERM MEDIUM TERMRISK CLASSIFICATION

    From 1 to 7 Acceptable

    From 8 to 19 Acceptable

    From 20 to 31Acceptable

    From 21 to 63 Acceptable

    From 64 to 99 Only acceptable if covered

    From 100 to 299 Only acceptable if covered

    From 300 to 499 Only acceptable if covered

    500 or over Not acceptable

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    12/27

    Decision parametersDecision parameters

    Acceptable risks Define risks Analyse possible reduction of likelihood and mitigation of impact Include cost of these counter-measures in investment analysis

    Risks acceptable only if covered Define risks Analyse possible reduction of likelihood and mitigation of impact

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 12

    s a s coverage nsurance, e ge, secur y

    Include cost of these counter-measures and coverage in investment analysis

    Non-acceptable risks Define risks

    Analyse if possible counter-measures or coverage can change their classification Reject investment if this is not feasible and efficient (investment phase) or Take drastic counter-measures or divest operation (after investment phase)

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    13/27

    Main risks in each phaseMain risks in each phase ofof ProjectProject

    Investment decisions Delayed decision Competition for each investment Unprofitable choice

    Entry into each local business

    Resistance from local groups Delay in establishing management procedures and controls

    Operation of each local business Technical risks Regulatory and tax context

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 13

    Management efficiency

    Joint operation of all businesses Market fluctuations Lack of or reduced synergy among operations

    Divestment of each business Market

    Protracted negotiations Competition for new investors

    Post-divestment Outstanding liabilities

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    14/27

    Risks in the investment phaseRisks in the investment phase

    An exampleAn example

    Risk identification

    Type

    Level

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 14

    Likelihood

    Impact

    Time-frame

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    15/27

    RISK TYPE LEVEL LIKELIHOOD IMPACT TIME-FRAME

    1 Delay in identifying prospects OrganizationHuman factor

    1-Project 2-improbable 1-small 3-short-term

    2Delay and/or non supply of information bysellers

    Human factor 1-Project 3-eventual 1-small 3-short-term

    3 Delay in making decision OrganizationHuman factor

    1-Project 2-improbable 1-small 3-short-term

    4 Delay in concluding negotiations EconomicHuman factor

    1-Project 3-eventual 2-medium 3-short-term

    5 Back-trading by sellers EconomicHuman factor 1-Project 4-probable 2-medium 3-short-term

    6 Change in country market context Economic 2-Country 5-highly probable 3-great 2-medium-term

    7 Change in world market context Economic 3-Organization 5-highly probable 3-great 3-short-term

    8 Change in country business context Economic 2-Country 3-eventual 3-great 2-medium-term

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 15

    9 Change in world business context Economic 3-Organization 3-eventual 3-great 3-short-term

    10Delay in establishing and executingdocuments

    Organization

    Human factor1-Project 2-improbable 1-small 3-short-term

    11 Inclusion of undesirable/incorrect clause OrganizationHuman factor

    1-Project 1-highly improbable 2-medium 3-short-term

    12 Non delivery of mandatory licensesRegulatory

    Human factor1-Project 2-improbable 2-medium 3-short-term

    13 Delay in delivery of mandatory licenses RegulatoryHuman factor

    1-Project 3-eventual 1-small 3-short-term

    14Non discovery of unacceptable risks orliabilities

    Organization

    Human factor1-Project 2-improbable 4-critical 2-medium-term

    15 Fraud in delivered information Criminal 1-Project 2-improbable 4-critical 2-medium-term

    16Resistance from local management /labour

    Cultural

    Human factor1-Project 4-probable 1-small 3-short-term

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    16/27

    RISK REDUCING LIKELIHOOD MITIGATION OF IMPACTINSURANCE

    POSSIBILITIES

    HEDGE

    POSSIBILITIES

    GUARANTEE

    POSSIBILITIE

    S

    RESIDUAL

    RISK

    1 Delay in identifying prospects Pro-active search Simultaneous projects None None None Low

    2Delay and/or non supply of information

    by sellers

    Documentation list

    Local follow-up

    Expliciting the requirement

    Expliciting consequences

    Partial-decision process None None None Medium

    3 Delay in making decision Project scheduleSimultaneous projects

    Partial-decision processNone None None Low

    4 Delay in concluding negotiations Project schedule Simultaneous projects None None None Medium

    5 Back-trading by sellersClear negotiation

    Reputable partners

    Simultaneous projects

    Competitive negotiationNone None None Medium

    6 Change in country market context NoneAnalysis parameters with

    expected time-frame averageCountry risk Price hedge None Medium

    7 Change in world market context NoneAnalysis parameters within

    expected time-frame averageNone Price hedge None Low

    Sensibility analysis within

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 16

    expected parameter range

    9 Change in world business context None Sensibility analysis withinexpected parameter range None Price hedge None High

    10Delay in establishing and executingdocuments

    Competent legal advisors

    Internal reviewSimultaneous projects None None None Medium

    11 Inclusion of undesirable/incorrect clauseCompetent legal advisors

    Internal reviewNone None None None Low

    12 Non delivery of mandatory licensesCompetent legal advisors

    Local representatives

    Contractual obligation to deliver

    correct informationNone None

    Contractual

    obligationLow

    13 Delay in delivery of mandatory licensesCompetent legal advisors

    Local representatives

    Contractual obligation to deliver

    correct informationNone None

    Contractual

    obligationMedium

    14Non discovery of unacceptable risks or

    liabilitiesComprehensive due dilligence Contractual generic guarantees None None

    Contractual

    obligationLow

    15 Fraud in delivered information Comprehensive due dilligenceContractual obligation to deliver

    correct informationNone None

    Contractual

    obligationLow

    16Resistance from local management /labour

    procedures

    Winning local management

    Communication program with local

    Contractual generic guarantees None None None High

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    17/27

    List of potential risksList of potential risks 11

    Commercial - Sourcing Performance: non delivery of raw materials Performance: late delivery of raw materials Performance: raw material off specifications

    Change in availability of raw materials

    Commercial - Sales Credit: Non-receipt of sales

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 17

    re : a e rece p o sa es

    Performance: non acceptance of products by buyer Performance: delay in acceptance of products by buyer Performance: raw material off specifications

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    18/27

    List of potential risksList of potential risks 22

    Commodity markets Cost of raw materials

    Materials not yet purchased Materials purchased but not fixed Materials in inventory

    Sale prices of produced goods Unsold products Products sold but not fixed

    Price fluctuations in straight commercial open positions (purchases and sales

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 18

    unre a e o pro uc on

    Exchange markets Exchange rate fluctuation as to investments

    investment in USD x earnings in local currencies

    Exchange rate fluctuation in current operations foreign sales x domestic costs

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    19/27

    List of potential risksList of potential risks 33

    Agriculture Climate rain Water (availability, investment for sourcing, cost) Labour (quality, possibility of strikes, cost)

    Agricultural management (quality, availability, cost)

    Industry Equipment (unplanned maintenances, delays, costs)

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 19

    Supply of equipments (availability, delay, cost) Necessity of increasing industrial facilities Necessity of changing industrial process Labour (quality, possibility of strikes, cost) Industrial management (quality, availability, cost)

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    20/27

    List of potential risksList of potential risks 44

    Logistics Availability of transportation vehicles

    Third parties Own investment Financing for third parties

    Availability of routes Availability of storage capacity

    Third parties Own investment

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 20

    Financing for third parties

    Availability of maritime terminal time Availability of ships within required regularity Cost of land transportation Cost of storage Cost of maritime terminal Cost of maritime freight

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    21/27

    List of potential risksList of potential risks 55

    Financial Interest rates fluctuations Existing and expected bank debts Other existing and expected financial debts

    Existing and expected tax liabilities Existing and expected labour liabilities

    Management

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 21

    Implementation and maintenance of required controls agriculture, industry, logistics, sales, markets accounting, taxes, labour IT infrastructure and hardware

    Implementation and maintenance of reporting process Implementation and maintenance of risk management process Motivation of local management and labour

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    22/27

    List of potential risksList of potential risks 66

    Environment Existing environmental liabilities (in agriculture, industry and logistics)

    known, but not evaluated evaluated but without payment obligation evaluated with payment obligation

    Potential environmental liabilities (in agriculture, industry and logistics) Environment-related licenses (delays, cost)

    Re ulator risks

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 22

    Labour regulations Taxes regulations and compliance (on agriculture, industry, logistics, domestics

    sales, exports, earnings, assets) Accounting regulations and compliance Labour relations compliance

    Other regulations compliance

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    23/27

    List of potential risksList of potential risks 77

    Corporate risks in local operations Conflict with previous owners Conflict with remaining partners Conflict with government

    Conflict with competitors

    Country risks General political risk

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 23

    n eres ra e eren a rom coun ry ra ng

    Social turmoil, acts of God Countries:

    with local operations sources of raw materials and products sales markets

    General corporate risks

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    24/27

    Agenda for a risk management planAgenda for a risk management plan 11

    Review and establish parameters for: risk identification (list of risks in each phase of Project) organizational levels involved time-frame likelihood of occurrence

    impact (type of effect, monetary and non-monetary consequences) levels of risk tolerance (acceptance, acceptance with coverage, rejection)

    Define, for each risk listed:

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 24

    the risk

    possible impacts how it will be assessed (statistics, market talk, model estimation etc.) who will supply basic input, who will carry out analysis time-frame for this analysis (daily, weekly, monthly,...) process flow of the risk analysis (local level >> country level >> corporate level)

    possible likelihood-reduction strategies possible impact mitigation strategies initial response plan to eventual occurrence

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    25/27

    Agenda for a risk management planAgenda for a risk management plan 22

    Define documentation on risk management For each project, during investment phase For each operation, after investment phase For each type of occurrence, during life-time of Project

    To be delivered to local management To be delivered to country management To be delivered to corporate management

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 25

    To be delivered to investors To local authorities

    Define functions/persons responsible for Establishment of risk management plan Assessment of risks in each project, during investment phase Assessment of risks in each operation after investment phase Assessment of corporate risks

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    26/27

    Agenda for a risk management planAgenda for a risk management plan 33

    Month 1 Define persons/functions responsible for the establishment of a Preliminary Risk

    Management Plan (valid until First Closing)

    Establish and approve this Preliminary Risk Management Plan

    Months 2 and 3 Include extract of Preliminary Plan in presentations to possible Investors

    PROJECTPROJECTPROJECTPROJECT jANUARY 2007 26

    Work on Risk Management Plan for investment process

    After First Closing (or on assurance of go-ahead) Establish and approve the Risk Management Plan for the investment process Define responsibilities for the execution of the Risk Management Plan during the

    investment process Organize the means and resources for this execution Beginning discussing and drafting the Operational Risk Management Plan

  • 8/14/2019 Heitor Moura 2007 Risk Management for private equity investments

    27/27

    Heitor Moura

    A RISK MANAGEMENT PLANA RISK MANAGEMENT PLAN

    January 2007