Hazop & Hazid Report - Cng Gas Plant - Tambak Lorok Rev b
-
Upload
denstar-ricardo-silalahi -
Category
Documents
-
view
1.834 -
download
139
Transcript of Hazop & Hazid Report - Cng Gas Plant - Tambak Lorok Rev b
Approved as Noted
DOCUMENT STATUS
Not Approved
:
Approved:
Project Title :
ENGINEERING PROCUREMENT AND CONSTRUCTION COMPRESSED NATURAL GAS - TAMBAK LOMBOK
HAZOP AND HAZID STUDIES REPORT
B 24 JUL 2013 REISSUED FOR REVIEW YS MTH MEF
A 28 JUN 2013 ISSUED FOR REVIEW YS MTH MEF
REV DATE D E S C R I P T I O N PREPARED CHECKED APPROVED COMPANY
PT. Enviromate Technology International PT Pertadaya Gas HAZOP/HAZID of CNG PLANT TAMBAK LOROK
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
TABLE OF CONTENTS
1 INTRODUCTION 7
1.1 BACKGROUND 7 1.2 STUDY OBJECTIVES 7 1.3 SCOPE OF HAZOP/HAZID STUDY 8 1.4 REPORT LAYOUT 8
2 PROJECT DESCRIPTION 9
2.1 OVERVIEW 9 2.1.1 Inlet scrubber (V-100) 9 2.1.2 Station Inlet metering (M-100 A/B) 9 2.1.3 Dryer Unit (D-100 A/B) 10 2.1.4 Compressor (K-101 / … / K-109) 10 2.1.5 CNG Cooler ( E-100) 11 2.1.6 CNG storage cylinders (V-200 1/../ 82) 11 2.1.7 Double pipe Exchanger 12 2.1.8 CNG Heat Exchanger (E-200) 12 2.1.9 Pressure reducing system (PV-0501 A/B) 12 2.1.10 Storage and Decanting process 12 2.1.11 Station Outlet Metering (M-200 A/B) 13 2.1.12 Waste Heat recovery Unit (E-300) 13 2.1.13 Fuel Gas 13 2.1.14 Instrument air 13 2.1.15 Cooling water (E-400) 14 2.1.16 Fire water system 14 2.1.17 Water treatment system (W-001) 14 2.1.18 Insulation 14 2.1.19 Vent System 14
3 STUDY METHODOLOGY 16
3.1 HAZOP 16 3.1.1 Overview 16 3.1.2 Worksheet Definition 16 3.2 HAZID 16 3.2.1 Overview 16 3.2.2 Worksheet Definitions 17
4 HAZOP/HAZID REVIEW SESSIONS 18
4.1 INTRODUCTION 18 4.2 THE HAZOP/HAZID TEAM 18 4.3 GUIDE WORDS 18 4.4 DRAWINGS REVIEWED 19 4.5 SELECTED NODES 20
PT. Enviromate Technology International PT Pertadaya Gas HAZOP/HAZID of CNG PLANT TAMBAK LOROK
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
5 HAZOP/HAZID RESULTS 21
5.1 ACTIONS/RECOMMENDATIONS 21 5.2 MAJOR HAZARD SCENARIO 23
6 HAZOP/HAZID FOLLOW-UP 25
7 REFERENCES 26
APPENDIX A HAZOP/HAZID SUMMARY RECOMMENDATIONS APPENDIX B HAZOP REVIEW WORKSHEETS APPENDIX C HAZID REVIEW WORKSHEETS APPENDIX D DRAWINGS
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
4
EXECUTIVE SUMMARY
The PT Perta Daya Gas has awarded to PT. Enviromate Technology International (PT. ETI) to conduct and construction of Compressed Natural Gas (CNG) facility. The plant will be located at Tambak Lorok, Central Java, Indonesia. The CNG facility is consisting of following equipment: Gas-Liquid separation system, Gas Drying & H2S adsorption system, Gas Compression system, CNG Cylinders storage package, Heat Exchangers and Metering systems.
The Utility for supporting CNG Plant are consisting Fuel Gas System, Gas power generation, Air Instrument Package, Waste Heat Recovery Unit, Pumps, Cooling towers, Water treatment Package and Sump system.
The incoming gas is taken from existing pipe then being compressed to CNG storage cylinders by CNG Compressors. Storage CNG will be performed maximum at 20 hours/day and decanting phase will be performed on the peak load within 4 hours/day (18.00 to 23.00). The design capacity of CNG Plant is 19.88 MMSCFD gas to the CNG storage cylinders.
Waste heat recovery Unit is provided to utilize the energy from exhaust compressor gas engine to reduce Joule Thompson effect on the pressure reducing system. The WHRU will heat water from tank which will be utilized as heating media of the CNG gas on CNG heat exchanger.
Cooling water system which consisting of Cooling Tower, Circulation pumps and CNG cooler will be pro-vided to optimize the requirement of CNG cylinders.
The HAZOP/HAZID review sessions were carried out at the Istana Karang Laut office in Plaza Citivew Kemang, Jakarta, utilizing 2 days for review, over the period 17th, and 21st June 2013.
The study identified 40 HAZOP recommendations and 18 HAZID recommendations. The recommendations would reduce potential safety or operability problems associated with the process or improve the clarity of the process drawings.
HAZOP
Design
It was noted in the HAZOP It identified during the review and also with discussion with Tambak Lorok, some of the valve arrangement need to be lock open to ensure that it doesn’t block due to human error (eg. at upstream BDV, by pass line). General comments also noted to provide setting for all the instrumentation system (e.g. PIC, PSHH, PSV)
It’s been reviewed that gas from suction compressor can be directed to downstream of E-200 to metering M-200 resulting in double counting of sales gas from Gundih meter with M-100. It was recommended to install additional check valve to PG-2"-3C-027 to prevent that case.
It recommended to provide SOP to accommodate gas release from vent of sump tank due to gas blow by from V-100, to ensure equipment purchase suitable as per hazardous area classification and also to nsure vent stack at sump tank is located high enough to prevent exposure to personnel/operator at Incoming Scrubber System.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
5
In the Waste Heat Recovery Unit, it was recommended to provide PSHH at downstream P-500A/B to trip P-500A/B in the case of manual valve at upstream E-300 inadvertenly close resulting in overpressure of the system.
The existing fire water capacity need to be reviewed to ensure source of water and its amount is adequate to handle fire on the CNG plant in addition with existing fire water requirement in Tambak Lorok.
It was discussed also that the design of floating valve T-600 to be radar type.
Maintenance and Operational
Based on the discussion raised up, it’s required to develop operating manual for delivery gas including showing correlation between pressure and flow at storage period and operation of redundant equipment such as compressor.
To control corrosion at basin cooling tower, it was recommended to provide SOP to control PH at cooling tower periodically.
HAZID
In the HAZID session, location of the lightning stack has not identified yet, therefore it is recommended to review the location of the lightning stack to be away from the venting stack to reduce the probability of fire on the vent stack
It was reviewed also that high noise level around the compressor area will potentially injured the personnel who operate the plant in daily basis. It was recommended to have noise study and provide warning sign the area to use ear plug protection.
Fire and Gas detection was also reviewed in the HAZID, it is recommended to provide the philosophy of the fire and gas detection system of the plant in formal documentation and provide clear actions of each detector, which one create alarm or shut down/blowdown of the plant. Fire detection philosophy was not provided in the building, specifically in the electrical room such as control room/MCC/batery room. It is recommended to provide clear philosophy, e.g. providing early warning system for smoke detection in electrical room (High Sensitivity Smoke Detector), including fire suppression system such as portable fire extinguisher or automatic fire suppresion system (e.g. FM-200,etc)
The scenario of fire and explosion in the CNG plant was not established yet during the review especially in relation position of the processing facility to location where stand by personnel available such as control room. Therefore, review of this scenario is recommended to justify design and location of the control room building. It is include also the fire and explosion impact to surrounding facility at Tambak Lorok. In the discussion also identified that the control room will not provided with glass windows to avoid explosion effect from the plant, hence that CCTV is recommended to be provided in the control room to monitor the plant.
During the review, location of the vent stack has not been identified yet. Therefore, dispersion and radiation analysis need to be done to define safe location and height required for the vent stack.
Consideration for emergency situation was also reviewed, and it is recommended to review emergency evacuation plan including emergency route, muster point location, safety equipment lay out and emergency lighting.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
6
Good communication among parties involved (Tambak Lorok and Gundih) also important to make sure operability and deliverability of the process plant, especially to handle emergency situation. Therefore a procedure defining internal and external communication need to be established among parties to make sure the plant is operated safely.
MAJOR HAZARD SCENARIO
The Major Hazard of this plant is :
• Process Hazard : 1. High Pressure Gas containment in the CNG Storage Tanks 2. Gas Compression System 3. Hot water circulation system 4. Cold Venting
• Non Process Hazard :
1. Control Room located in hazardous area 2. Human Error - Alarm 3. Communication between ETI, IP, Gundih 4. Transportation
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
7
1 INTRODUCTION
1.1 BACKGROUND
PT. Perta Daya Gas is planning to develop CNG Plant Project. The plant will be located at Tambak Lorok, Central Java province, Indonesia.
PT. Perta Daya Gas therefore commissioned an independent Chairman and Scribe for a series of safety studies to review and identify hazards and operability issues related to operation of Compressed Natural Gas Plant Project.
This report details the Hazard and Operability (HAZOP) and Hazard Identification (HAZID) review and includes a summary of the recommendations identified during the review, as well as the HAZOP/HAZID review worksheets.
1.2 STUDY OBJECTIVES
The objectives of the HAZOP study are to:
• Identify safety related hazards and operability problems related to the process that could directly threaten the safety of production personnel or cause operational problems;
• Determine the seriousness of the consequences for the identified problems;
• Identify engineering and procedural safeguards already incorporated into the design that will reduce the likelihood or the severity of consequences related to the identified problem;
• Evaluate the adequacy of existing engineering and procedural safeguards; and
• Recommend additional safeguards or operational procedures where necessary.
The objectives of the HAZID study include:
• Assess changes and consider new requirements that have emerged since the last PHA;
• Identification of new hazard causes or initiating factors associated with the modifications with a potential to result in major accident events (MAEs), which may give rise to serious and immediate risk to health and safety of personnel;
• Assessment of the consequences of these new MAEs;
• Determination of risk based on the likelihood and the severity of the consequences for each identified MAEs;
• Identification of existing safeguards that may include engineering or operational controls and measures included in the design for prevention and/or mitigation of the MAEs;
• Evaluation of the residual risk taking into account the existing control and mitigation measures; and
• Recommendation of additional safeguards or procedures, where necessary to demonstrate as Low as Reasonable Practicable (ALARP).
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
8
1.3 SCOPE OF HAZOP/HAZID STUDY
The HAZOP/HAZID study covers these packages in detail:
1. Main Proces System:
· V-100 : Gas Scrubber
· M -100A/B & M -200A/B : Station Inlet & Outlet Metering
· D-100A/B : Gas Dryer
· K-101 to K109 : CNG Compressors
· E-100 : CNG Cooler & E-200 : CNG Heat Exchager
· V-200-1 to V-200-80 : CNG Compartement
· V-400 : Sump Tank
2. Utilities
· WHRU and Hot Water circulation
· Water Treatment Facilities and Cold water circulation
· Open & Close Drains
· Venting system
· Instrument Air System
· Fuel Gas System
· Fire Water Ring
· Engine Generator
1.4 REPORT LAYOUT
This HAZOP/HAZID report is structured as follows:
• Section 1 gives an introduction, defining the objectives and scope of the study;
• Section 2 describes the process;
• Section 3 describes the HAZOP/HAZID methodology;
• Section 4 describes the HAZOP/HAZID workshops;
• Section 5 lists the references given in the report;
• Appendix A presents the summary HAZOP & HAZID recommendations;
• Appendix B presents the HAZOP review worksheets;
• Appendix C presents the HAZID review worksheets; and
• Appendix D presents the Drawings used, outlining the nodes.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
9
2 PROJECT DESCRIPTION
2.1 OVERVIEW
The CNG facility is consisting of following equipment: Gas-Liquid separation system, Gas Drying
& H2S adsorption system, Gas Compression system, CNG Cylinders storage package, Heat
Exchangers and Metering systems.
The Utility for supporting CNG Plant are consisting Fuel Gas System, Gas power generation, Air
Instru-ment Package, Waste Heat Recovery Unit, Pumps, Cooling towers, Water treatment Package
and Sump system.
The incoming gas is taken from existing pipe then being compressed to CNG storage cylinders by
CNG Compressors. Storage CNG will be performed maximum at 20 hours/day and decanting phase
will be performed on the peak load within 4 to 5 hours/day (18.00 to 23.00). The design capacity of
CNG Plant is 19.88 MMSCFD gas to the CNG storage cylinders.
Waste heat recovery Unit is provided to utilize the energy from exhaust compressor gas engine to
reduce Joule Thompson effect on the pressure reducing system. The WHRU will heat water from
tank which will be utilized as heating media of the CNG gas on CNG heat exchanger.
Cooling water system which consisting of Cooling Tower, Circulation pumps and CNG cooler will
be pro-vided to optimize the requirement of CNG cylinders.
2.1.1 Inlet scrubber (V-100)
The gas scrubber (V-100) will be installed on incoming gas to remove any hydrocarbon liquid from
upstream facility. The liquid level on the gas scrubber will be controlled by control valve LV-0101
to avoid liquid carried over to the CNG Plant. High liquid level on the scrubber will initiate the
valve to open, then if liquid level has reached normal condition valve will be closed, so the valve
will be as on/off mode.
The gas scrubber is provided with PSV-0101A/B with set pressure of 34 barg for overpressure
protection, One PSV will be on operation and another one as spare.
Inlet line will be provided with SDV-0101 in order to isolate the plant in emergency condition. The
initiators of SDV-0101 closing refer to Cause & effect diagram.
2.1.2 Station Inlet metering (M-100 A/B)
The metering will measure natural gas inlet to CNG plant. Total gas inlet is 19.88 MMSCFD. Gas
inlet would be 19.88 MMSCFD and flows to inlet compressor and 1.1 MMSCFD flows to auxiliary
fuel gas. Metering type is 2x100% custody orifice meter. Metering will be operated in continous
operation. Flow and accumulation flow should be monitored by flow computer. Gas inlet to
metering tends to consist of high moisture. Orifice should be designed for wet gas condition.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
10
2.1.3 Dryer Unit (D-100 A/B)
The outlet gas from gas scrubber (V-100) will be dried through Gas Drying Unit (D-100A/B). Unit
consist of two Gas Dryer + H2S absorber, i.e D-100A/B and D-200A/B. These will be operated on
parallel configuration. Maximum capacity of drying Unit is 10 MMSCFD. The range of inlet
pressure is 20.6-25 barg. One bed will be on drying mode and the other one is on regenerating
mode. Gas dryer will remove water and H2S content on the feed gas to produce moisture dew point
to -40oC and maximum 3 ppm H2S. Dew point meter and H2S meter should be installed within
Dryer package unit. Adsorption time is 4-8 hours and the regeneration time is 4-8 hours (heating,
cooling and standby).
Gas dryer pre filter (F-100) will be provided at upstream of desiccant gas dryer (D-100A/B) to
ensure that gas goes to molecular sieve is clean and no hydrocarbon liquid carried over. One filter
will be operated and bypass line opened during filter maintenance, pressure differential indicator
will be provided across the filter such that operator will able to determine the switching operation.
Gas dryer after filter (F-110) will be provided on the downstream of desiccant gas dryer (D-100A/B)
to ensure that are there is no solid particle carried over on the gas before entering the CNG
compressor. One filter will be operated and bypass line opened during filter maintenance, pressure
differential indicator will be provided across the filter such that operator will able to determine the
switching operation.
Blower, electric heater, air cooler and liquid knocked out drum will be provided on the regeneration
line. A portion of dried gas will be utilized as regeneration gas. The regeneration gas will be heated
by an electric heater then after removing the water on the desiccants, the regent gas will be cooling
downed via the air cooler then liquid will be removed on the liquid knocked out drum. After
removing liquid on the knocked out drum, regent gas will be re-injected on the main gas line.
The valve sequences on the dryer unit will be controlled by a microprocessor on the dryer unit
package. Running and fault status on the dryer package will be transferred to Plant Control System
(PCS) for monitoring only.
This system is auto mode. No interlock system to main PCS.
2.1.4 Compressor (K-101 / … / K-110)
The dry gas from dryer with operating pressure of 20.6-25 barg at 26.7-51.7 oCwill be transferred to
the storage cylinder at pressure of 250 barg through CNG compressors (K-
101/102/103/104/105/106/107/108/109/110). There are 10 (ten) compressor trains with 9 (nine)
compressors will be operated in parallel and 1 (one) compressor on standby mode.
Each compressor will be operated with outlet capacity of 2.3 MMSCFD at inlet pressure of 24 barg.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
11
The compressor is reciprocating type in three stages compression, air coolers will be provided on
each discharge stage to enhance the efficiency of compressor.
The maximum discharge pressure and temperature from CNG compressor are 250 barg and 48OC
respectively. The compressor will be supplied by vendor as a skid including electrical and
instrumentation inside. Control system of CNG compressor is provided with PLC by vendor, the
operating parameter will be transferred to Plant Control System (PCS) for monitoring purpose.
Shutdown system of the compressors will be managed by PLC, trigger of shutdown such as lube oil
pressure low, suction pressure low, discharge pressure high, discharge temperature high and High
vibration will be further developed by vendor.
Compressors are driven by Gas Engine drive with fuel gas that supplied from upstream of dryer
skid.
2.1.5 CNG Cooler ( E-100)
Compressed gas from CNG compressor with temperature of 48oC will be cooled down to 35oC
before entering to CNG cylinders. Cooling water system is closed loop cooling system which
involving CNG cooler (E-100), Cooling water circulation pump (P-200A/B) and Cooling Tower (E-
400). The compressed natural gas need to be cooled down to 35oC for optimizing the requirement of
cylinder storage capacity. The temperature of cooling water inlet to CNG cooler (E-100) is 30oC and
temperature cooling water outlet at 39oC. To avoid prolonged overpressure due to tube rupture,
CNG Compressor would be shut downed by PSHH-0503 then CNG gas would be release to cooling
water return line to Cooling tower (E-400).
DURING DECANTING PERIOD:
Cooling water to CNG Cooler will be discontinued to produce CNG stream with temperature 48oC
and it will be commingled with CNG stream from compartment (Temperature 35 oC).
If pressure decreases and disturbing performance of CNG compressor then CNG stream could be
flowed through E-100 bypass line. Restriction orifice installed in this bypass line to giving sufficient
backpressure for CNG compressor.
2.1.6 CNG storage cylinders (V-200 1/../ 82)
CNG from E-200 will be stored at CNG storage cylinders. The CNG storage cylinders are consisting
of 95 compartment (base on 20 hours storage time at 18.7 MMSCFD CNG inlet). Each
compartment is consisting of 8 tube cylinders. One cylinder has capacity of 2.38 m3. Three CNG
compartment will be arranged in 1 (one) bank. Each bank will be provided 1 unit manual valve for
incoming and outgoing CNG. Pressure relief device (PSV) protect respectives cylinders. Discharge
PSV will be released to atmosphere and no additional pipe is required for PSV discharge line.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
12
2.1.7 Double pipe Exchanger
Double pipe exchanger would be installed at downstream of PV-0501 to minimize temperature
drop during CNG depressuring by PV-0501 A/B. Heating media is using Hot water in outer pipe
side and CNG stream in inner pipe. Timer valve (KV) would be opened to supply hot water to outer
pipe of double pipe exchanger. Restriction orifice (RO) is provided on hot water inlet to restrict
capacity of hot water to exchanger.
If temperature at downstream PV-0501 close with -25o C, Hot water supply could be discontinued
this condition occur when pressure in compartments was dropped.
2.1.8 CNG Heat Exchanger (E-200)
The CNG Heat exchanger is required during decanting stage, this is to reheat CNG on the
downstream of pressure reducing valve. The temperature decrease due to large pressure drop in
PV0501A/B, this is called Joule Thompson effect. Temperature on the downstream can be lower
than the dew point of CNG such that condensation may occurs.
The CNG heat exchanger (E-200) maximum duty is 4100 kW (basis 4 hours decanting time) then
duty will decrease gradually as the upstream pressure is reduced during decanting process. The
initial stage of decanting, the temperature of CNG will be increased from -38oC to about 30oC. The
heating media for this heat exchanger is hot water system with temperature of 90oC. Hot water
circulation flowrate is 140 m3/hr and the flowrate to E-200 will be controlled by (TV0502).
Temperature control Valve (TV-0502) will manipulate hot water flowrate to E-200 to maintain CNG
export to the pipeline at temperature of 30oC. Temperature control is using cascade with TIC-0502.
2.1.9 Pressure reducing system (PV-0501 A/B)
The pressure of CNG outlet to PLN will be maintained at 28 barg and temperature of 30oC. PIC-
0501A/B are used for controlling CNG outlet pressure. Pressure reducing system will be provided
by two control valves ( PV0501A/B) with one operating and one standby.
This valve is designed base on 4 hours decanting time (96 MMSCFD).
2.1.10 Storage and Decanting process
The storage and decanting process will be performed by opening and closing delivery valve (KV-
0501A/B) downstream of CNG storage cylinders. Storage CNG will be carried out fixed maximum
20 hours per day and decanting will be performed 4 to 5 hours per day. During decanting period the
CNG Cooler (E-100) will be bypassed to reduced joule thomphson effect on the downstream of PV-
0501A/B.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
13
Duration of decanting can be resetted from the control room, but changing setting time shall refer to
operating pressure on the CNG storage cylinders. Over pressure on the CNG cylinders will initiate
high pressure on the discharge compressor then process shutdown can be triggered.
2.1.11 Station Outlet Metering (M-200 A/B)
The metering system with 2x100% with crossover will measure natural gas outlet from CNG plant.
Total gas outlet is 113 MMSCFD for 4 hours. Metering is used as custody meter. Flow and
accumulation flow should be monitored in main PLC. For Gas composition analysis, one sampling
connection is installed at the upstream of Outlet Metering (M200A/B).
Gas Flow would be measured for 4 hours per day during decanting time. Totalizer would count total
value base on measured gasflow.
2.1.12 Waste Heat recovery Unit (E-300)
The exhaust gas from gas engines ducting will be utilized as source of energy to increase the
temperature of hot water from 63oC to 90oC. Exhaust gas from each turbine will be commingled on
header before entering WHRU, and water will be heating up on the WHRU boiler.
Hot water from WHRU will be stored on the hot water storage Tank at temperature of 90oC.
During storage phase (20 hours), WHRU would heat water in Hot water tank (T-200) for
approximately 10 hours from 30o to 90o C. The water circulating pump (P-500 A/B) with capacity of
45m3/hr is used to circulate water from T-200 through WHRU heater (E-300) and back to T-200.
During decanting phase (4 hours), Hot water pump (P-300 A/B) with capacity of 140 m3/h will
circulate hot water from T-200 to E-200 and back to T-200. Temperature of hot water in the Hot
water tank (T-200) is controlled by manipulating damper position on each exhaust gas Turbine of
CNG compressors.
2.1.13 Fuel Gas
Fuel gas is supplied for two (2) units gas engine generators (1 operation & 1 stand by) thru Fuel gas
strainer and for ten (10) units gas engine compressors (9 operation and 1 unit standby). The fuel gas
strainer is designed based on capacity of less than 1.5 MMSCFD.
Fuel Gas metering (FQI-0901) is provided to measure auxilary fuel gas consumption in CNG
facility.
2.1.14 Instrument air
The instrument air will be provided on CNG plant to enhace the overall reliability of the Plant.
Instrument air requirement is calculated based on the number of control valves and on-off control
valves plus a design margin of 20%. Three (3) Air compressors will be provided with two operating
as lead and lag basis and one compressor as a standby.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
14
Instrument air system will be provided with a drying unit such that the dew point of instrument air is
less than -40oC.
2.1.15 Cooling water (E-400)
Water as cooling media will be utilized for CNG Cooler (E-100) before storage stage, The CNG
from gas compressor with temperature of 48oC will be cooled down to 35oC using cooled water.
Cooling water is supplied to the heat exchangers through the Cooling Tower Pump (P-200 A/B) at
flowrate of 35m3/hr. After taking heat of CNG, cooling water leaves heat exchanger at temperature
of 30oC is re-circulated to the Cooling Tower ( E-400) for cooling down and reused. Make-up water
will be provided to compensate water losses on the Cooling Tower (E-400).
2.1.16 Fire water system
Fire water will be taken from existing fire water system in front of CNG plant.
Fire hydrants and monitors will be located based on equipment layout during detail engineering.
2.1.17 Water treatment system (W-001)
Auxiliary water for CNG plant will be taken from well in plant. Well water will be treated by
Reverse osmisis (RO) technology prior to be used as make up water. Total consumption for make
up water is 3.2 m3/h. The feedwater to the RO unit will be design accordingly based on input from
vendor.
2.1.18 Insulation
Personnel Protection Insulation (PP) shall be specified on all lines with normal operating
temperatures above 70°C. This will be applied only to sections of pipe that personnel could come
into contact with during normal operation.
Heat Conservation Insulation (HC) shall be specified for heated systems above 65°C (e.g. hot water
from WHRU).
Noise Abatement Insulation (NI) shall be specified on compressor suction and discharge lines,
subject to vendor confirmation.
2.1.19 Vent System
Relief Gas from Pressure safety valves and Blow down system would be collected to vent header
then to vent stack. Automatic drain would be provided to controlling liquid level at bottom vent
stack.
Flame arrester would be installed at upstream of vent stack to avoid flame due to lightning or other
fire source.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
15
Relief gas from CNG cylinders would be free vent to atmosphere instead of to vent header line as
per client and manufacture requirement.
The vent stack with providing water seal at the bottom of the vent stack to prevent air ingress.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
16
3 STUDY METHODOLOGY
3.1 HAZOP
3.1.1 Overview
The study was carried out using the traditional HAZOP Guide Word method, where the system is broken down into manageable sections and a set of standard Guide Words applied. The methodology requires exhaustive consideration of each process activity to determine if there are any potential problems in relation to safety or operations that may arise due to deviations in the process. The Causes and Consequences of each deviation are identified. The HAZOP team evaluates the severity of the problem and adequacy of existing safeguards, and where necessary, recommends additional safeguards as Actions. The hazard and operability problems highlighted in the course of the review were captured in the HAZOP Review worksheets (Appendix A).
3.1.2 Worksheet Definition
All concerns raised are documented in the HAZOP Review Worksheets, which include the column headers as described in Table 3.2a.
Table 3.1a HAZOP Review Worksheet
Column Heading Description No. Reference Number
Guide word/Deviation A set of standard guide words used to analyse and determine
potential problems that arise
Possible Causes Causes or problems identified
Possible Consequences Description of the consequences of the possible impact of the cause
Type Types of issues that are involved, either Drawing Error/Comment, Engineering, Operability, Safety, Financial and Regulatory
Safeguard Description of the safeguards in place
Recommendations/Comment Description of the recommendation(s) that could be in place
Action Party Relevant party taking responsibility for action(s) identified
The completed HAZOP review worksheets are attached in Appendix A.
3.2 HAZID
3.2.1 Overview
HAZID review is used as a means to identifying potential hazards, determining the associated consequences and evaluating means of preventing the hazard or controlling the consequences. They should not be confused with a HAZOP review which looks at specific areas of the process to identify potential design/operating problems and determine ways of improving the process design to
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
17
prevent such incidents from occurring. A HAZID review is based on a combination of identification, analysis and brainstorming activities. The technique exhaustively considers each review area, by reference to an agreed set of guidewords. During the review, each facility was considered in turn with the facility broken down according to specific areas or enclosed buildings, e.g., Main Deck.
3.2.2 Worksheet Definitions
All findings during the HAZID sessions are recorded by the scribe using HAZID worksheets. These worksheets contain the column headings given in Table 3.3b.
Table 3.3b HAZID Record Sheet Headings
Column Heading Description
No. Reference number
Category / Guideword Initiating event and guideword used to generate hazard scenario
Event Description Description of scenario and mode of realization
Consequence Description of the consequences of the hazard or possible impact and escalation of the scenario
Prevention Existing measures to prevent the hazard from occurring
Control Existing measures to control or mitigate the hazard to prevent escalation
Recommendation / Comments
Actions generated during the review. Comments on the protective systems in place, justification of the design are also included in italics.
Action Party Responsibility for addressing each action item will be assigned to the design team or to the project team
Ranking Qualitative ranking of the frequency and consequence of the hazard (carried out after the review is completed to save time during the review itself)
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
18
4 HAZOP/HAZID REVIEW SESSIONS
4.1 INTRODUCTION
The HAZOP/HAZID review sessions were carried out at the Istana Karang Laut office in Plaza Citiview Kemang, Jakarta, utilizing 2 days for review, over the period 17th and 21st June 2013.
4.2 THE HAZOP/HAZID TEAM
The HAZOP/HAZID team comprises a multidisciplinary team of personnel involved with the design and operation of the facilities, led by a safety consultant from PT PROSIM The names and attendance records of the HAZOP/HAZID team members for each of the systems are tabulated in Table 4.2a.
Table 4.2a HAZOP/HAZID Team Attendance
Name Co. Role June 2013
June 2013
17 21
Margaretha T PT PROSIM Chairman Ö Ö Yulia Tirtasiwi PT PROSIM Scribe Ö Ö Sugiyanto PT ETI Process Engineer Ö Ö Bernardo PT ETI Ö Ö
Rudolf S PT ETI Ö Ö Suarno PT ETI Ö Ö
Cut Julia PT IKL Project Manager Ö Ö
Warno Abdullah PT IKL Engineering Manager Ö Ö Suseno PT IKL Process Engineer Ö Ö Irvan N PT IKL Ö Ö Haidar PT IKL Ö Ö Gigin Ginanjar PT IKL Ö Ö Isa PT IKL Process Engineer Ö Ö
4.3 GUIDE WORDS
The full set of Guide Words used in the HAZOP/HAZID Review is listed in Table 4.3a & b. It should be noted that if not found to be applicable or not to produce any problem of concern that had not already been raised, the Guide Word was not recorded in the Worksheets for that node.
Table 4.3a HAZOP Guide Words
No. Guide Word 1 No Flow 2 Less Flow 3 More Flow 4 Reverse Flow 5 Misdirected Flow 6 Less Level 7 More Level
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
19
8 Less Pressure 9 More Pressure 10 Less Temperature 11 More Temperature 12 Contaminants 13 Composition 14 Corrosion / Erosion 15 Instrumentation 16 Relief 17 Personnel Safety 18 External Factors 19 Operations 20 Maintenance 21 Drawing
Table 4.3b HAZID Guide Words
Safety System Guide Word No. Comments
Non Process Structural Failures 1 Extreme weather/subsidence/fatigue
Events Impact 2 Collisions
Transportation 3 Helicopter/personnel baskets/vessels
Lifting 4 Dropped Objects
Non Process Fires 5 Fires/escalated fires
Toxic Release 6 Chemical spill
Security 7 Pirates/fishermen
Noise 8 High noise areas/vibration
Health hazards 9 Diseases/working condition/chemicals
Loss of containment
Ignition 1 Fires from individual process systems
Safety Systems Ignition Sources 1 —
Escape/ Refuge 2 Personnel escape to TR
Communication 3 Hotlines/radio, etc
Emergency Lighting 4 Lighting during escape/ evacuation
Environmental Hazards
Discharge to air 1 Vent/ flare/ relief, etc
Discharge to water 2 Produced water, etc
Discharge to soil 3 Gas/ water injection , etc
Waste disposal 4 Hazardous material/ solids/ sanitary waste, etc.
4.4 DRAWINGS REVIEWED
A basic Piping and Instrumentation (P&ID) for the process acted as a basis for discussion during the review, along with the operating procedures. The drawings used are attached in Appendix B.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
20
4.5 SELECTED NODES
The process was initially broken down according to the step and then by each action comprising the step. Each action was considered separately with the full list of Guide Words applied. Thus each action becomes a “node”, so, for instance, each feed line into a reactor was considered as a separate node. The nodes used are presented in Table 4.5a & b while the associated worksheets are given in Appendix A (HAZOP) and Appendix B (HAZID).
Table 4.5a Nodes Reviewed in HAZOP
Node Section Drawing Number Rev
N1 Incoming Gas from Gundih field through Gas Scrubber V-100 to Station Inlet Metering M100A/B
TS78-P-PID-001 B TS78-P-PID-002 B N2 Outlet Station Inlet Metering to Gas Dryer Prefilter F-100,
Gas Dryer 100A/B, Gas Dryer After Filter F-110 including Regenerator Filter
TS78-P-PID-003 B
B N2R Regeneration System TS78-P-PID-003 B N3 Compression System K101 (typical for K102 to K109),
including Blowdown Tank VE301A TS78-P-PID-004 B
N4 Inlet CNG Cooler E-100 to CNG Compartment (STORAGE TIME)
TS78-P-PID-005 Sheet 1 of 2 B
N5 Inlet CNG Heat Exchanger E-200 to Station Outlet Metering M-200A/B (DECANTING)
TS78-P-PID-005 Sheet 2 of 2 B TS78-P-PID-006 B N6 Hot water circulation including Hot Water Tank T-200,
Hot Water Pump P300A/B and circulation to E-100 and E-200
TS78-P-PID-007 TS78-P-PID-005 sheet 2 of 2
B
N7 Waste Heat Recovery Unit include Water circulation pump P-500A/B and WHRU
TS78-P-PID-007 B
N8 Water Treatment Plant TS78-P-PID-012 B
N9 Cooling System, including Make up Water Tank T-400, Make Up Water Pump P-100, Cooling Tower E-400 and Cooling Tower Pump P-200 A/B
TS78-P-PID-011
B
N10 Sump Tank V-400 including Sump Tank P-400 TS78-P-PID-010 B
N11 Fuel Gas System TS78-P-PID-009 B N12 Instrument Air System TS78-P-PID-008 Sheet 1 of 2
TS78-P-PID-008 Sheet 2 of 2 B
N13 Fire Water System TS78-P-PID-013 B N14 Power Generation system TS78-P-PID-014 B N15 Vent Gas System, including discharge of pressure
relieving device and BDVs vent header, KO Drum V-600, up to Vent Stack VS-100
TS78-P-PID-015 B
Table 4.5b Node Reviewed in HAZID
Node Section Drawing Number Rev
N1 CNG Plant – Tambak Lorok TS78-L-LY-001 B1
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
21
5 HAZOP/HAZID RESULTS
5.1 ACTIONS/RECOMMENDATIONS
A total of 40 HAZOP recommendations and 18 HAZID recommendations were generated during the review. The recommendations would reduce potential safety or operability problems associated with the process or improve the clarity of the process drawings (P&ID’s). A complete list of the recommendations made by the team during the review itself is tabulated in Appendix A. A unique number is assigned to each recommendation and the node identification number is included so that it may easily be traced back to the review worksheets (Appendix B & C). Brief summary of highlighted recommendations are presented below.
HAZOP
Design
It was noted in the HAZOP It identified during the review and also with discussion with Tambak Lorok, some of the valve arrangement need to be lock open to ensure that it doesn’t block due to human error (eg. at upstream BDV, by pass line). General comments also noted to provide setting for all the instrumentation system (e.g. PIC, PSHH, PSV)
It’s been reviewed that gas from suction compressor can be directed to downstream of E-200 to metering M-200 resulting in double counting of sales gas from Gundih meter with M-100. It was recommended to install additional check valve to PG-2"-3C-027 to prevent that case.
It recommended to provide SOP to accommodate gas release from vent of sump tank due to gas blow by from V-100, to ensure equipment purchase suitable as per hazardous area classification and also to nsure vent stack at sump tank is located high enough to prevent exposure to personnel/operator at Incoming Scrubber System.
In the Waste Heat Recovery Unit, it was recommended to provide PSHH at downstream P-500A/B to trip P-500A/B in the case of manual valve at upstream E-300 inadvertenly close resulting in overpressure of the system.
The existing fire water capacity need to be reviewed to ensure source of water and its amount is adequate to handle fire on the CNG plant in addition with existing fire water requirement in Tambak Lorok.
It was discussed also that the design of floating valve T-600 to be radar type.
Maintenance and Operational
Based on the discussion raised up, it’s required to develop operating manual for delivery gas including showing correlation between pressure and flow at storage period and operation of redundant equipment such as compressor.
To control corrosion at basin cooling tower, it was recommended to provide SOP to control PH at cooling tower periodically.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
22
HAZID
In the HAZID session, location of the lightning stack has not identified yet, therefore it is recommended to review the location of the lightning stack to be away from the venting stack to reduce the probability of fire on the vent stack
It was reviewed also that high noise level around the compressor area will potentially injured the personnel who operate the plant in daily basis. It was recommended to have noise study and provide warning sign the area to use ear plug protection.
Fire and Gas detection was also reviewed in the HAZID, it is recommended to provide the philosophy of the fire and gas detection system of the plant in formal documentation and provide clear actions of each detector, which one create alarm or shut down/blowdown of the plant. Fire detection philosophy was not provided in the building, specifically in the electrical room such as control room/MCC/batery room. It is recommended to provide clear philosophy, e.g. providing early warning system for smoke detection in electrical room (High Sensitivity Smoke Detector), including fire suppression system such as portable fire extinguisher or automatic fire suppresion system (e.g. FM-200,etc)
The scenario of fire and explosion in the CNG plant was not established yet during the review especially in relation position of the processing facility to location where stand by personnel available such as control room. Therefore, review of this scenario is recommended to justify design and location of the control room building. It is include also the fire and explosion impact to surrounding facility at Tambak Lorok. In the discussion also identified that the control room will not provided with glass windows to avoid explosion effect from the plant, hence that CCTV is recommended to be provided in the control room to monitor the plant.
During the review, location of the vent stack has not been identified yet. Therefore, dispersion and radiation analysis need to be done to define safe location and height required for the vent stack.
Consideration for emergency situation was also reviewed, and it is recommended to review emergency evacuation plan including emergency route, muster point location, safety equipment lay out and emergency lighting.
Good communication among parties involved (Tambak Lorok and Gundih) also important to make sure operability and deliverability of the process plant, especially to handle emergency situation. Therefore a procedure defining internal and external communication need to be established among parties to make sure the plant is operated safely.
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
23
5.2 MAJOR HAZARD SCENARIO
The Major Hazard of this plant is :
• Process Hazard : 1. High Pressure Gas containment in the CNG Storage Tanks 2. Gas Compression System 3. Hot water circulation system 4. Cold Venting
• Non Process Hazard :
5. Control Room located in hazardous area 6. Human Error - Alarm 7. Communication between ETI, IP, Gundih 8. Transportation
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
24
The hazard management plant can be shown as follow:
PT. Enviromate Technology International PT. PROSIM PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
25
6 HAZOP/HAZID FOLLOW-UP
The project, design and operation team should conduct a HAZOP/HAZID follow up session to response the HAZOP/HAZID recommendations. The response and action plan shall be back up with the relevant data and justification whether the recommendation is agreed or rejected. At the end, the team shall formulate action plans, steward all action items and ensure that the relevant changes are made to the design to address hazard and operability concerns identified as part of this HAZOP/HAZID.
PT. Enviromate Technology International HAZOP/HAZID of CNG PLANT TAMBAK LOROK
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BA26 JULY 2013
7 REFERENCES
/1/ Process Plan Description - TS78 - P - BD - 001 /2/ Drawing List : No Drawing Title Drawing Number Rev
1 PID - Incoming Scrubber System TS78-P-PID-001 B 2 PID - Station Inlet Metering (M-100A/B) TS78-P-PID-002 B 3 PID - Gas Dryer (Vendor Package) TS78-P-PID-003 B 4 PID - Compressor System / K-101 (Vendor Package) TS78-P-PID-004 B 5 PID - Storage and Decanting System TS78-P-PID-005 Sheet 1
of 2 B
6 PID - CNG Heat Exchanger TS78-P-PID-005 Sheet 2 of 2
B
7 PID - Station Outlet Metering (M-200A/B) TS78-P-PID-006 B 8 PID - Waste Heat Recovery Unit TS78-P-PID-007 B 9 PID - Instrument Air System TS78-P-PID-008 Sheet 1
of 2 B
10 PID - Instrument Air Network TS78-P-PID-008 Sheet 2 of 2
B
11 PID - Fuel Gas System TS78-P-PID-009 B 12 PID - Sump System TS78-P-PID-010 B 13 PID - Cooling System TS78-P-PID-011 B 14 PID - Water Treatment Plant TS78-P-PID-012 B 15 PID - Fire Water System TS78-P-PID-013 B 16 PID - Power Generator System TS78-P-PID-014 B 17 PID - Vent Gas System TS78-P-PID-015 B 18 General Plant Lay Out TS78-L-LY-001 B1 19 PFD – Inlet Metering and Dryer TS78-P-PFD-001 B 20 PFD – Gas Compression System TS78-P-PFD-002 B 21 PFD – CNG Storage and Pressure Reducing System TS78-P-PFD-003 B 22 PFD – Waste Heat Recovery Unit TS78-P-PFD-004 B 23 PFD – Cooling Water System TS78-P-PFD-005 B 24 PFD – Heat Material Balance TS78-P-PFD-006 B 19 UFD – Fuel Gas System TS78-P-UFD-001 B 20 UFD – Instrument air system TS78-P-UFD-002 B
PT. Enviromate Technology International HAZOP/HAZID of CNG PLANT TAMBAK LOROK
Appendix A
HAZOP/HAZID Summary Recommendation
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT ISTANA KARANG LAUT
NODE Causes / Concerns Consequences Comments / Recommendations Rec Number1 SDV 0101 at upstream V-100
close due to failurePotential overpresurization of upstream plant (Santos Facility ) resulting in hydrocarbon release leading to fire or fatality
Ensure existing pipeline design pressure is higher than maximum discharge pressure from Gundih facility
CNG-HP-1
1 SDV 0101 at upstream V-100 close due to failure
Loss of Production Review availability of isolation valve (SDV) from Gundih facility in the case of overpressure from pipeline
CNG-HP-2
1 Any of manual valve at incoming line to V-100 inadvertently close
Potential overpresurization of upstream plant (Santos Facility ) resulting in hydrocarbon release leading to fire or fatality
Provide operating manual for delivery gas CNG-HP-3
1 PV 0105 stuck close or manual valve around the PV 0105 inadvertently close
Potential overpressurization of V-100 resulting in hydrocarbon release leading to fire or fatality
Provide setting pressure PIC-0105 to show at PID TS78-P
CNG-HP-4
1 Control loop malfunction causing LV-0101 to open fully
Gas blowby to Sump Tank V-400 leading to potential vessel damage (design pressure 3.5 barG), fire and explosion
Provide SOP to accommodate gas release from vent of sump tank due to gas blow by from V-100
CNG-HP-5
1 Control loop malfunction causing LV-0101 to open fully
Gas blowby to Sump Tank V-400 leading to potential vessel damage (design pressure 3.5 barG), fire and explosion
Ensure equipment purchase suitable as per hazardous area classification
CNG-HP-6
1 Control loop malfunction causing LV-0101 to open fully
Gas blowby to Sump Tank V-400 leading to potential vessel damage (design pressure 3.5 barG), fire and explosion
Ensure vent stack at sump tank is located high enough to prevent exposure to personnel/operator
CNG-HP-7
1 Sour Gas (H2S) and water content in the production gas
Internal corrosion of piping and vessel leading to release of hydrocarbon gas and potential fire
Consider to provide corrosion coupon at upstream V-100
CNG-HP-8
2 Manual by pass valve at downstream line PG-10-30-053 from metering M100A/B to Compressor unit unit is inadvertenly open
Potential wet gas to Gas Compression system resulting in equipment damage
LC by pass manual valve 10" at downstream line PG-10-30-053 and update PID
CNG-HP-9
2 Manual valve upstream BDV-0301 inadvertenly close in the event of ESD and BDV-0301 required to open
Overpresurization of upstream equipment leading to fire/fatality
Provide Lock Open (LO) at manual valve upstream BDV-0301
CNG-HP-10
2R Blower E-101 at regeneration unit damage/ not in operation
No regeneration process causing wet gas going to compressor
Ensure interlock system install to prevent overtemperature/overpressure in the case P-101 shutdown, Electric Heater should also shutdown (Check with vendor)
CNG-HP-11
2R D-200 A-B shutdown Potential reverse flow leading to equipment damage Ensure D-200 A-B including regeneration system has adequate design to accomadate reverse flow
CNG-HP-12
3 Switch operation between Potential human error to operate manual valve and Provide operating manual for operating redundant CNG-HP-13
SUMMARY HAZOP RECOMMENDATION
3 Switch operation between compressors
Potential human error to operate manual valve and safety devices
Provide operating manual for operating redundant equipments, including compressors
CNG-HP-13
4 One of running compressor fails to operate
Less of CNG production Review sizing of manual valve incoming CNG compartment to be available at market or provide spare manual valve in the case of maintenance required
CNG-HP-14
4 Fouling/Plugging at E-100 or loss of cooling water
Inefficiency in cooling resulting in high temperature leading to less CNG production
Provide portable temperature detector to check skin temperature of CNG compartment
CNG-HP-15
4 Loss of containment/piping leak due to corrosion
Tube leak at E-100 Provide SOP to control PH at cooling tower periodically
CNG-HP-16
5 SDV0601 fails close or manual valve in the metering station inadvertenly closed
Potential overpressurization of CNG HE E-200 leading to hydrocarbon release and potential fire
Show setting point of PV 0501A/B CNG-HP-17
5 Gas from suction compressor going to downstream of E-200 to metering M-200
Double counting of sales gas from Santos meter with M-100
Install additional check valve at line PG-2"-3C-027 CNG-HP-18
5 Manual valve upstream BDV-0505 inadvertenly close in the event of ESD and BDV-0505 required to open
Overpresurization of upstream equipment leading to fire/fatality
Provide Lock Open (LO) manual valve at upstream BDV-0505
CNG-HP-19
6 Hot Water Pump P-300A/B stop due to failure OR Strainer at upstream P-300A/B blockage
Loss of hot water supply leading to inefficient heat transfer and lower gas sales temperature
Provide low temperature switch at line PG-12"-3C-021 to close KV-0503 A to prevent low temperature in the gas sales
CNG-HP-20
6 Hot Water Pump P-300A/B stop due to failure OR Strainer at upstream P-300A/B blockage
High temperature in the circulation water around the waste heat recovery unit
Provide low temperature alarm at line PG-12"-3C-021 to alert operator
CNG-HP-21
6 Three way valve TV-0502 to E-200 is inadvertenly close
Loss of hot water supply leading to inefficient heat transfer and lower gas sales temperature
Provide Temperature Control Valve at bypass line of E-200
CNG-HP-22
7 Any manual valve at upstream E-300 inadvertenly close or check
Potential overpressure of downstream pump Vendor to provide minimum flow recycle line at P-500A/B
CNG-HP-23
7 One or more gas engine driver shutdown
Less of flue gas to E-300 resulting in lower temperature generated for water circulation
Review requirement set point of TIA-0704 CNG-HP-25
7 Start up Low gas temperature from exhaust gas compressor to WHRU resulting condensation at gas ducting E-300
Provide drain line at lowest point gas ducting E-300 CNG-HP-26
7 Condense water from flue gas at E-300
Corrosion at E-300 leading to equipment damage Review requirement TIA-0705 CNG-HP-27
CNG PLANT TAMBAK LOROK Page 1 of 2 SUMMARY HAZOP RECOMMENDATION
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT ISTANA KARANG LAUT
NODE Causes / Concerns Consequences Comments / Recommendations Rec Number7 Drawing Revise drawing TS78-P-PID-007 to show setting
point of all instrumentation alarm and tripCNG-HP-28
9 Manual valve at outlet T-100 is inadvertenly close or strainer blocked
Loss of pump suction and potential pump damage Provide lock open (LO) for manual valve upstream P-100 and P-600
CNG-HP-29
9 Manual valve or strainer at inlet Basin cooling water is inadvertently close
Potential overflow at T-600 Review design of floating valve T-600 to be radar type
CNG-HP-30
9 Manual valve at upstream P-200A/B inadvertenly close or strainer blocked
Loss of pump suction and potential pump damage Provide lock open (LO) for manual valve upstream P-200
CNG-HP-31
10 Liquid control valve failure at individual equipments (V-300, Compressor K-101-109, V-100)
Build up pressure in Sump Tank V-400 leading to potential overpressurization
Review outlet line at venting V-400 to be sufficient for case high pressure gas introduced from upstream equipment to this vessel
CNG-HP-32
11 3" Manual valves at incoming/outgoing line Fuel Gas filter is inadvertently closed
Loss of fuel gas supply leading to compressor shutdown
Provide lock open (LO) for 3" manual valves at upstream and downstream Fuel Gas Filter
CNG-HP-33
12 Manual valve upstream of Instrument Air Receiver V-300 inadvertently closed
Potential overpressurization of upstream piping Confirm availability of high pressure trip at internal of Air Compressor C300A/B/C package to shut down compressor in the case of block of discharge
CNG-HP-34
12 Manual valve downstream Instrument Air Receiver V-310 inadvertently closed
Loss of instrument air supply potentially leading to PSD
Lock Open (LO) for manual valve downstream Instrument Air Receiver V-310
CNG-HP-35
13 Operation Review existing Tambak Lorok’s fire water capacity to be adequate for fire water handling in CNG Plant
CNG-HP-36
13 Operation Consider to provide additional flowmeter to measure fire water consumption for Tambak Lorok
CNG-HP-37
14 Any manual valve down stream GE-100A to cooling system inadvertenly close
Overheating at GE-100A leading to equipment damage
Confirm availability of TSHH to trip Gas Generator GE-100A in case of high temperature has been included in the generator package.
CNG-HP-38
14 Any manual valve down stream GE-100A to cooling system inadvertenly close
Overheating at GE-100A leading to equipment damage
Lock Open (LO) for manual valve downstream GE-100A
CNG-HP-39
15 Lighting struck during PSV/BDV release
Fire at vent stack Consider to install CO2 snuffing system at VS-100 to extinguish fire at vent stack completed with fusible plug
CNG-HP-40
CNG PLANT TAMBAK LOROK Page 2 of 2 SUMMARY HAZOP RECOMMENDATION
PT. ENVIROMATE TECHNOLOGY INTERNATIONAL Appendix A SUMMARY HAZOP/HAZID PT ISTANA KARANG LAUT
HAZID No.
Hazard Description Consequences Prevention Control Recommendation/ Comment Co. Pr Ri Type
4.1.3 Lightning Possible damage to the equipment and potential fire
- Grounding provided for each equipment
Update EQL drawing to show Lightning protection at CNG compartment area (lightning stack) in process/utility area
CNG-HD- 1 S (4)C(3)
4 S (H16)C(H12)
Design
4.3.1 Light vehicles impact e.g. Car
Potential impact to piping/equipment leading to hydrocarbon release, fire, personnel injury/fatality and asset damage
- vehicle park area away from process area
Operation cars shall be equipped with flame arrestor and diesel engine
CNG-HD- 2 S (4)C(4)
2 S (H8)C(H8)
Operation / Maintenance
4.7.1 High noise level from compressor and gas engine area
Potential personnel ear injury
- Provide SOP to wear ear plug around noise area
CNG-HD- 3 S (1)C(-)
3 S (H3)C(-)
Design
4.8.1 Toxic Material during handling chemical: for cooling water, corrosion inhibitor e.g. oxygen scavanger
Personnel injury MSDS provided in the storage facility
Ensure portable eye wash station provided during chemical handling (e.g : at control room, loading area and water treatment area)
CNG-HD- 4 S (1)C(-)
3 S (H3)C(-)
Design
4.8.3 Hazardous waste disposal
Personnel injury during handling waste disposal
PPE - hand gloves, face shield
- Alocate waste disposal resulting from operation/construction activity in safe area (third party)
CNG-HD- 5 S (1)C(-)
3 S (H3)C(-)
Operation / Maintenance
4.9.6 Hot Surfaces at exhaust gas, WHRU and heat exchanger (E-200)
Potential injury due to exposure to heat
personal protection insulation provided
PPE Provide warning sign around hot surface equipment and pipings
CNG-HD- 6 S (2)C(-)
2 S (M4)C(-)
Design
4.10.1 Leak from Process Equipment
Release of hydrocarbon resulting in potential fire/explosion leading to injury/fatality
Unit SD by low pressure trip
Gas detection system at process area
Define philosophy of fire and gas detection system and develop fire and gas detection area at process plant
CNG-HD- 7 S (4)C(4)
2 S (H8)C(H8)
Design
Loss of Containment Release of hydrocarbon resulting in potential fire/explosion leading to injury/fatality
NA Fire hydrant provided with source from existing IP
Regularly to check temperature in the MCC cabinet and DCS panel to monitor short circuit and provide portable fire extinguisher
CNG-HD- 8 S (4)C(4)
2 S (H8)C(H8)
Operation / Maintenance
4.11.1 Battery Fire/explosion in the event of hydrocarbon release.
Battery room is located in non hazardous area
Heat & Smoke detector, Portable Fire Extinguisher provided at control room & MCC room
Regularly to check temperature in the MCC cabinet and DCS panel to monitor short circuit and provide portable fire extinguisher
CNG-HD- 9 S (4)C(4)
2 S (H8)C(H8)
Operation / Maintenance
4.11.2 Vent Fire/explosion in the event of hydrocarbon release in process area if stroke by lightning
- Lightning protection provided at CNG compartment area
Define safe location and minimum height required for vent stack and vent location to be suitable with wind directions so that dispersed gas will not be
CNG-HD- 10 S (4)C(4)
2 S (H8)C(H8)
Design
Rec Number
SUMMARY HAZID RECOMMENDATION
so that dispersed gas will not be exposed to process plan
4.12.1 Fire on Plant area Personnel trap/ unable to evacuate leading to injury/fatality
ERP - Provide emergency evacuation risk analysis to determine safe evacuation route and location of muster area
CNG-HD- 11 S (4)C(4)
3 S (H8)C(H8)
Design
- - Form emergency response team (ERT) and conduct emergency drill
CNG-HD- 12 S (4)C(4)
4 S (H8)C(H8)
Operation / Maintenance
4.14.1 Control room Fire or explosion from process area impact to control room leading to potential personnel injury/fatality
- Heat and Smoke detector
Review scenario of fire and explosion from gas plant to the area of standby personnel such as control room and provide mitigation plan (design and location of the building) to anticipate fire/explosion
CNG-HD- 13 S (4)C(4)
2 S (H8)C(H8)
Design
- - Define safety requirement on control room specification to accommodate fire/explosion scenario e.g. door, wall and window specifications
CNG-HD- 14 S (4)C(4)
3 S (H8)C(H8)
Design
Inability to monitor process area
- - Consider to provide CCTV in the control room for monitoring purpose
CNG-HD- 15 S (4)C(4)
5 S (H8)C(H8)
Design
4.15.1 Inability to contact control room within emergency
Inability to coordinate response leading to potential major accident leading to personnel injury/fatality and asset loss
Each operator provided with hand held radio
F&G alarm system Define internal and external communication system (PABX) for connecting operator in the control room to outside parties
CNG-HD- 16 S (4)C(4)
2 S (H8)C(H8)
Design
4.16.1 Inability to initiate ESD
Inability to control fire leading to potential major accident leading to personnel injury/fatality and asset loss
Local ESD push button at control room
- Define safety layout at CNG plant to show ESD push button, fire hydrant, etc
CNG-HD- 17 S (4)C(4)
2 S (H8)C(H8)
Design
4.18.3 Blowdown of water from cooling tower, discharge RO
Potential contamination from process fluid
Discharge water is connected to existing canal (IP)
Define Sampling point to monitor discharge water
Define Sampling point to monitor discharge water
CNG-HD- 18
CNG PLANT TAMBAK LOROK Page 1 of 1 HAZID Worksheet Summary
PT. Enviromate Technology International HAZOP/HAZID of CNG PLANT TAMBAK LOROK
Appendix B
HAZOP Review Worksheets
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown
H,M,L Co Consequence
Pr ProbabilityRi RiskS Safety RiskC Commercial Risk
CommentDesign Intent
Design Conditions:
Opt. Conditions
Capacity Flowrate : 20 MMSCFD
Drawing TS78-P-PID-001 BTS78-P-PID-002 B
DT: 65 deg C
OP : 20.6-30.9 barG OT : 26.7-51.7 deg C
PID - Incoming Scrubber System
DP : 34 barG
PID - Station Inlet Metering (M-100A/B)
To remove any hydrocarbon liquid from upstream facility and measure natural gas inlet to CNG plant
117-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONAL
Incoming Gas from Gundih field through Gas Scrubber V-100 to Station Inlet Metering M100A/B
Compressed Natural Gas PlantTambak Lorok
High, Medium, Risk
RiNo. Guide
WordsDeviation Causes / Concerns Consequences Safeguards Initiating
LCo Pr Ri Comments / Recommendations Rec. No.
1.1.1 No No Flow SDV 0101 at upstream V-100 close due to failure
Potential overpresurization of upstream plant (Gundih Facility ) resulting in hydrocarbon release leading to fire or fatality
Pressure regulator (PV) at upstream facility to adjust discharge pressure
S (4)C(4)
1 S (M4)C(M4)
Ensure existing pipeline design pressure is higher than maximum discharge pressure from Gundih facility
CNG-HP-1
Loss of Production Review availability of isolation valve (SDV) from Gundih facility in the case of overpressure from pipeline
CNG-HP-2
1.1.2 No No Flow Any of manual valve at incoming line to V-100 inadvertently close
Potential overpresurization of upstream plant (Gundih Facility ) resulting in hydrocarbon release leading to fire or fatality
Pressure regulator (PV) at upstream facility to adjust discharge pressure
S (4)C(4)
1 S (M4)C(M4)
Provide operating manual for delivery gas
CNG-HP-3
Loss of Production
Parameter: Flow
CNG PLANT TAMBAK LOROK Page 1 of 53 HAZOP Node N1
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Rec. No.
1.1.3 No No Flow PV 0105 stuck close or manual valve around the PV 0105 inadvertently close
Potential overpressurization of V-100 resulting in hydrocarbon release leading to fire or fatality
PIH-0103 set at 31 barg as high pressure alarm to alert operator
S (4)C(4)
1 S (M4)C(M4)
Provide setting pressure PIC-0105 to show at PID TS78-P
CNG-HP-4
PIHH-0103 set at 33 barG to close SDV-0101PSV 0101A/B set at 34 barG is sized for fire case
Note : maximum upstream pressure from Gundih is not more than 34 barG
1.1.4 No No Flow Any of manual valves at Station Inlet Metering M100A/B inadvertently close
Potential overpresurization of upstream M-100A/B resulting to fire or fatality
PIH-0103 set at 30 barg as high pressure alarm to alert operator
S (4)C(4)
1 S (M4)C(M4)
PIHH-0103 set at 33 barG to close SDV-0101PSV 0101A/B set at 34 barG is sized for block discharge
1.2.1 Less Less Flow Refer to No Flow - manual valves partially closed
1.3.1 More More Flow Slugging High level at V-100 leading Slug Catcher provided at S (-) 1 S (-)1.3.1 More More Flow Slugging High level at V-100 leading to liquid carry over to metering skid M-100 and downstream equipment
Slug Catcher provided at Gundih facility
S (-)C(2)
1 S (-)C(L2)
LV-0101 will maintain level in Gas Scrubber V-100LIH-0102 as high level alarm to alert operatorLIHH-0102 will close SDV-0102
1.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
1.5.1 Part of Misdirected Flow No additional significant issues of concerns identified
1.5.1 Part of Misdirected Flow No additional significant issues of concerns identified
Parameter: Level
CNG PLANT TAMBAK LOROK Page 2 of 53 HAZOP Node N1
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Rec. No.
1.6.1 Less Less Level Control loop malfunction causing LV-0101 to open fully
Gas blowby to Sump Tank V-400 leading to potential vessel damage (design pressure 3.5 barG), fire and explosion
LIL-0102 alarm to alert Operator
S (4)C(4)
1 S (M4)C(M4)
Provide SOP to accommodate gas release from vent of sump tank due to gas blow by from V-100
CNG-HP-5
LILL-0102 to initiate shutdown of SDV-0102
Ensure equipment purchase suitable as per hazardous area classification
CNG-HP-6
Sump Tank open to atmosphere
Ensure vent stack at sump tank is located high enough to prevent exposure to personnel/operator
CNG-HP-7
1.6.2 Less Less Level Manual valve at bypass line LV-0101 or manual drain valves inadvertently open, leak at liquid lines
Gas blowby to Sump Tank V-400 leading to potential vessel damage (design pressure 3.5 barG), fire and explosion
LIL-0102 alarm to alert Operator
S (4)C(4)
1 S (M4)C(M4)
LILL-0102 to initiate shutdown of SDV-0102Sump Tank open to atmosphere
1.7.1 More More Level Control loop malfunction causing LV-0101 to stuck close
High level at V-100 leading to liquid carry over to metering skid M-100 and
LIH-0102 as high level alarm to alert Operator to open by pass line
S (-)E (2)C(2)
1 S (-)E (L2)C(L2)metering skid M-100 and
downstream equipmentopen by pass line C(2) C(L2)
LIHH-0102 to initiate shutdown of SDV-0101
1.7.2 More More Level Any of manual valve upstream/downstream LV-0101 inadvertently close
High level at V-100 leading to liquid carry over to metering skid M-100 and downstream equipment
LIH-0102 as high level alarm to alert Operator to open by pass line
S (-)C(2)
1 S (-)C(L2)
LIHH-0102 to initiate shutdown of SDV-0101
1.7.3 More More Level SDV-0102 fails closed High level at V-100 leading to liquid carry over to metering skid M-100 and downstream equipment
LIH-0102 as high level alarm to alert Operator to open by pass line
LIHH-0102 to initiate shutdown of SDV-0101
1.7.4 More More Level Slugging High level at V-100 leading to liquid carry over to metering skid M-100 and downstream equipment
LIH-0102 as high level alarm to alert Operator to open by pass line
S (-)C(2)
1 S (-)C(L2)
CNG PLANT TAMBAK LOROK Page 3 of 53 HAZOP Node N1
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Rec. No.
LIHH-0102 to initiate shutdown of SDV-0101
1.8.1 Less Less Pressure Loss of containment/piping leak due to corrosion
Release of hydrocarbon leading to environmental pollution and potential fire
PIL-0102 as low pressure alarm at incoming V-100 to alert operator
S (4)C(4)
1 S (M4)C(M4)
PILL-0102 at incoming V-100 will initiate closure of SDV 0101Fire and Gas Detector at V-100
1.8.2 Less Less Pressure Refer to Misdirected Flow 1.5.11.9.1 More More Pressure Refer to No Flow 1.1.1, 1.1.2, 1.1.3,
1.1.4 ; Less Level 1.6.1, 1.6.2
PV-0105 stuck open Potential overpressure at Metering M100A/B and downstream equipment
PIH-S01 set at 30 bar as high pressure alarm to alert operator
S (-)E (2)C(2)
1 S (-)E (L2)C(L2)
PSH 0301A/B at 32 barG to close SDV-0101
Manual valve at by pass line PV-0105 inadvertently open
Potential overpressure at Metering M100A/B and
PIH-S01 set at 30 bar as high pressure alarm to
S (-)C(2)
1 S (-)C(L2)
as
0105 inadvertently open Metering M100A/B and downstream equipment
high pressure alarm to alert operator
C(2) C(L2)
PSH 0301A/B at 32 barG to close SDV-0101
1.10.1 Less Less Temperature No additional significant issues of concerns identified
1.11.1 More More temperature No additional significant issues of concerns identified
1.12.1 As Well As
Contamination No additional significant issues of concerns identified
1.13.1 Other Than
Composition No additional significant issues of concerns identified
1.14.1 Other Than
Corrosion / Erosion
Sour Gas (H2S) and water content in the production gas
Internal corrosion of piping and vessel leading to release of hydrocarbon gas and potential fire
Wall thickness of piping and equipment already considered sour gas condition
S (4)C(4)
1 S (M4)C(M4)
Consider to provide corrosion coupon at upstream V-100
CNG-HP-8
Parameter: Temperature
Parameter: Contamination
Parameter: Composition
Parameter: Corrosion / Erosion
Parameter: Instrumentation
CNG PLANT TAMBAK LOROK Page 4 of 53 HAZOP Node N1
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Rec. No.
1.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
1.16.1 Other Than
Relief No additional significant issues of concerns identified
1.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
1.18.1 Other Than
External Factors Fire at plant Overpresurization of piping leading to equipment damage
Fire and Gas Detector at V-100
S (-)C(2)
1 S (-)C(L2)
1.19.1 Other Than
Operations No additional significant issues of concerns identified
1.20.1 Other Than
Maintenance Single isolation valve for Maintenance of PSV-0101A/B
Potential exposure of high pressure to personnel during maintenance of PSV-0101A/B
NA Note: Certification/testing of PSV is conducted during online operation without dismantle of PSV itself. Dismantle of PSV can only be conducted if there is a risk assessment for single valve at upstream of the PSV
Parameter: Safety
Parameter: External Factor
Parameter: Operation & Maintenance
Parameter: Relief
for single valve at upstream of the PSV
1.20.2 Other Than
Maintenance No additional significant issues of concerns identified
1.21.1 Other Than
DrawingParameter: Drawing
CNG PLANT TAMBAK LOROK Page 5 of 53 HAZOP Node N1
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating Procedures
Review date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown
H,M,L Co Consequence
Pr ProbabilityRi RiskS Safety RiskC Commercial Risk
CommentDesign Intent
Design Conditions:Opt. Conditions
Capacity Flowrate : 20 MMSCFD
Drawing Drawing No. TS78-P-PID-003 Rev: B
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Action Party Rec. No.
2.1.1 No No Flow Any of manual valve at Gas Dryer package is inadvertenly close
Potential overpressurization of upstream equipment of D-100 leading to rupture and potential fire event
PIH 0102 alarm set at 30 barG to alert Operator
S (4)C(4)
1 S (M4)C(M4)
PIHH 0102 set at 33 barG to initiate closure of SDV 0101
PSV 0101A/B set at 33 barg
2.2.1 Less Less Flow F-100 Blockage Potential overpressurization of upstream equipment of D-100 leading to rupture and potential fire event
PIH 0102 alarm set at 30 barG to alert Operator
S (4)C(4)
1 S (M4)C(M4)
PIHH 0102 set at 33 barG to initiate closure of SDV 0101
PSV 0101A/B set at 33 barg
PDI at F-100 as local indicator for operator
Compressed Natural Gas Plant
High, Medium, Risk
To remove water and H2S content on the feed gas to produce moisture dew point to -40 deg C and max 3 ppm H2S
2
17-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONAL
Outlet Station Inlet Metering to Gas Dryer Prefilter F-100, Gas Dryer 100A/B, Gas Dryer After Filter F-110 including Regenerator Filter
OP : 20.6-30.9 barG OT : 26.7-51.7 deg C
One bed of dryer will be on drying mode and the other one is on regenerating mode. Adsorption time is 4-8 hours and the regeneration time 4-8 hours (heating, cooling and standby)
Tambak Lorok
DT: 250 deg C
PID - Gas Dryer (Vendor Package)
Parameter: Flow
DP : 34 barG
CNG PLANT TAMBAK LOROK Page 6 of 53 HAZOP Node N2
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Action Party Rec. No.
Potential wet gas to Gas Compression system resulting in equipment damage
AIH (dew point alarm) at downstream of Dryer unit
2.2.2 Less Less Flow D-100A/B Blockage (caking) Potential overpressurization of upstream equipment of D-100 leading to rupture and potential fire event
PSH 0301A set at 32 bar at Gas Dryer D-100A/B to close SDV-0101
S (4)C(4)
1 S (M4)C(M4)
PSV 0301A set at 34 barG is sized for block discharge
PDSH for Local indicator at D-100A/B for operator
Potential wet gas to Gas Compression system resulting in equipment damage
AIH (dew point alarm) at downstream of Dryer unit
2.2.3 Less Less Flow F-110 Blockage Potential overpressurization of upstream equipment of D-100 leading to rupture and potential fire event
PSV 0301A set at 34 barG is sized for block discharge
S (4)C(4)
1 S (M4)C(M4)
PDI at F-110 as local indicator for operator
Potential wet gas to Gas Compression system resulting in equipment damage
AIH (dew point alarm) at downstream of Dryer unit
2.2.4 Less Less Flow see No Flow 2.1.1 For partial blockage
2.3.1 More More Flow BDV-0301 open due to failure Depressurization of the system, loss of gas to flare and loss of production
BDV position indication and alarm
S (-)C(3)
1 S (-)C(M3)
2.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
2.5.1 Part of Misdirected Flow Refer to More Flow 2.3.1
2.5.2 Part of Misdirected Flow Manual valve at 1/2-in drain line inadvertently open/leak or liquid trap at F-100 and F-110 stuck open
Gas blowby to Sump Tank leading to gas cloud and potential fire and explosion
SOP/Maintenance of liquid trap
S (4)C(4)
1 S (M4)C(M4)
2.5.3 Part of Misdirected Flow Manual bypass line of F-100 is inadvertenly open
Potential condense liquid carry over to D-100 resulting in equipment damage
SOP
CNG PLANT TAMBAK LOROK Page 7 of 53 HAZOP Node N2
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Action Party Rec. No.
2.5.4 Part of Misdirected Flow Manual bypass line of F-110 is inadvertenly open
Potential condense liquid carry over to compressor unit resulting in equipment damage
SOP
2.5.5 Part of Misdirected Flow Manual valve to regeneration unit is inadvertenly open
Ineffective regeneration process in Gas Dryer D-100A/B
PSV 0301B set at 34 barG is sized for block discharge
2.5.6 Part of Misdirected Flow Manual by pass valve at downstream line PG-10-30-053 from metering M100A/B to Compressor unit unit is inadvertenly open
Potential wet gas to Gas Compression system resulting in equipment damage
SOP S (-)C(3)
2 S (-)C(M6)
LC by pass manual valve 10" at downstream line PG-10-30-053 and update PID
CNG-HP-9
2.6.1 Less Less Level Refer to Misdirected Flow 2.5.22.7.1 More More Level Liquid trap of F-100 stuck close High level at F-100 leading
to liquid carry over to Gas Dryer D-100A/B
SOP to open by pass manual valve 1/2"
2.8.1 Less Less Pressure Loss of containment/leak on D-100 due to corrosion
Release of hydrocarbon leading to environmental damage and potential fire
Fire and gas detection system
S (4)C(4)
1 S (M4)C(M4)
2.8.2 Less Less Pressure Refer to More Flow 2.3.12.9.2 More More Pressure See No Flow 2.1.1, 2.1.2, 2.2.1,
Misdirected Flow 2.5.2
2.9.1 More More Pressure Liquid trap of F-100 stuck open Low level at F-100 leading to gas blow by to Sump Tank
Sump tank connected to atmospheric
2.9. More More Pressure Manual valve upstream BDV-0301 inadvertenly close in the event of ESD and BDV-0301 required to open
Overpresurization of upstream equipment leading to fire/fatality
NA S (4)C(4)
1 S (M4)C(M4)
Provide Lock Open (LO) at manual valve upstream BDV-0301
CNG-HP-10
2.10.1 Less Less Temperature No additional significant issues of concerns identified
2.11.1 More More temperature No additional significant issues of concerns identified
2.12.1 As Well As
Contamination No additional significant issues of concerns identified
2.13.1 Other Than
Composition No additional significant issues of concerns identified
Parameter: Corrosion / Erosion
Parameter: Level
Parameter: Pressure
Parameter: Temperature
Parameter: Contamination
Parameter: Composition
CNG PLANT TAMBAK LOROK Page 8 of 53 HAZOP Node N2
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Action Party Rec. No.
2.14.1 Other Than
Corrosion / Erosion
Sour Gas (H2S) and water content in the production gas
Internal corrosion of piping and vessel leading to release of hydrocarbon gas and potential fire
Wall thickness of piping and equipment already considered sour gas condition
S (3)C(4)
1 S (M3)C(M4)
2.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
2.16.1 Other Than
Relief No additional significant issues of concerns identified
2.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
2.18.1 Other Than
External Factors Fire Overpresurization of drier leading to equipment damage
F & G S (-)C(2)
2 S (-)C(M4)
2.19.1 Other Than
Operations No additional significant issues of concerns identified
2.20.1 Other Than
Maintenance No additional significant issues of concerns identified
2.21.1 Other Than
Drawing No additional significant issues of concerns identified
Parameter: Operation & Maintenance
Parameter: Drawing
Parameter: Safety
Parameter: Relief
Parameter: External Factor
Parameter: Instrumentation
CNG PLANT TAMBAK LOROK Page 9 of 53 HAZOP Node N2
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown
H,M,L Co Consequence
Pr ProbabilityRi RiskS Safety RiskC Commercial Risk
CommentDesign Intent
Design Opt. Capacity Flowrate : 20 MMSCFDDrawing Drawing No. TS78-P-PID-003 Rev: B
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Action Party Rec. No.
Parameter: Flow
OP : 20.6-30.9 barG OT : 26.7-51.7 deg CPID - Gas Dryer (Vendor Package)
Regeneration SystemHigh, Medium, Risk
One bed of dryer will be on drying mode and the other one is on regenerating mode. Adsorption time is 12 hours and the regeneration time 12 hours (heating, cooling and standby)To collect water from the dryer and refresh molecular sieves to be ready to absorb
DP : 34 barG DT: 250 deg C
2R17-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak Lorok
2R.1.1 No No Flow Manual valve to regeneration system inadvertenly close
No regeneration process causing wet gas going to compressor
F-101 to collect any condense liquid
S (-)C(3)
1 S (-)C(M3)
AIH (dew point alarm) at downstream of Dryer unit
Back up dryer available
2R.1.2 No No Flow Blower E-101 at regeneration unit damage/ not in operation
No regeneration process causing wet gas going to compressor
F-102 to collect any condense liquid
S (-)C(3)
1 S (-)C(M3)
Ensure interlock system install to prevent overtemperature/overpressure in the case P-101 shutdown, Electric Heater should also shutdown (Check with vendor)
CNG-HP-11
Potential overtemperature/overpressure at gas regeneration system
AIH (dew point alarm) at downstream of Dryer unit
Back up dryer available2R.1.3 No No Flow F-102 blockage Pump cavitation Regular Filter mainentance S (-)
C(3)1 S (-)
C(M3)
Overpressurization of equipment upstream of F-102 leading to equipment damage
PSH-0301B alarm to alert Operator
Parameter: Flow
CNG PLANT TAMBAK LOROK Page 10 of 53 HAZOP Node N2R
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Action Party Rec. No.
2R.2.1 Less Less Flow F-102 partially blocked Pump cavitation Regular Filter maintenance S (-)C(3)
1 S (-)C(M3)
Overpressurization of equipment upstream of F-102 leading to equipment damage
PSH-0301B alarm to alert Operator
2R.2. Less Less Flow2R.3.1 More More Flow No additional significant issues of
concerns identified2R.4.1 Reverse Reverse Flow D-200 A-B shutdown Potential reverse flow
leading to equipment damage
S (-)C(3)
1 S (-)C(M3)
Ensure D-200 A-B including regeneration system has adequate design to accomadate reverse flow
CNG-HP-12
potential more flow at D-100 A-B resulting potential offspec to compressor leading to compressor damage
AIH (dew point alarm) at downstream of Dryer unit
PIL 501 at SS-101 as Low pressure alarm to alert operatorPILL 501 at SS-101 to shutdown SDV-151
2R.5.1 Part of Misdirected Flow Manual valve at drain line of F-102 or separator after cooler inadvertently open/leak
Gas blowby to Sump Tank leading to gas cloud and potential fire and explosion
Sump Tank connected to Atmospheric
S (4)C(4)
1 S (M4)C(M4)
inadvertently open/leak potential fire and explosion
2R.5. Part of Misdirected Flow Liquid trap at F-102 or at separator after cooler stuck open
Gas blowby to Sump Tank leading to gas cloud and potential fire and explosion
Sump Tank connected to Atmospheric
S (4)C(4)
1 S (M4)C(M4)
#N/A Part of Liquid trap maintenance
2R.6.1 Less Less Level See Misdirected flow 2R.5.22R.7. More More Level Liquid trap of F-102 or at drain line
of separator stuck closeHigh level at F-102 leading to liquid carry over to Gas Dryer D-100A/B
Manual by pass valve on around liquid trap
S (-)C(3)
1 S (-)C(M3)
Second liquid trap provided on the pipe to Sump Tank
AIH (dew point alarm)-0301 at downstream of F-101
2R.8.1 Less Less Pressure Loss of containment/leak on regeneration system due to corrosion
Release of hydrocarbon leading to environmental damage and potential fire
F & G system S (4)C(4)
1 S (M4)C(M4)
2R.8.2 Less Less Pressure See Misdirected flow 2R.5.1
Parameter: Level
Parameter: Pressure
CNG PLANT TAMBAK LOROK Page 11 of 53 HAZOP Node N2R
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Initiating L
Co Pr Ri Comments / Recommendations Action Party Rec. No.
2R.8.3 Less Less Pressure Regeneration pump loss of power due to mechanical problem
gas cannot circulate to regeneration system resulting in wet gas to compressor
AIH (dew point alarm) at downstream of Dryer unit
S (-)C(3)
1 S (-)C(M3)
2R.9.1 More More Pressure See Now Flow 2R.1.3
2R.10.1 Less Less Temperature Electric heater stop due to mechanical failure
In efficient heat absorbtion to D-100
Maintenance S (-)C(3)
1 S (-)C(M3)
AIH (dew point alarm) at downstream of Dryer unit
2R.11.1 More More temperature Cooler stop due to motor failure liquid cannot be condense and separated to the separator
AIH (dew point alarm) at downstream of Dryer unit
S (-)C(3)
1 S (-)C(M3)
2R.12.1 As Well As
Contamination No additional significant issues of concerns identified
2R.13.1 Other Than
Composition No additional significant issues of concerns identified
2R.14.1 Other Than
Corrosion / Erosion
Sour Gas (H2S) and water content in the production gas
Internal corrosion of piping and vessel leading to release of hydrocarbon gas and potential fire
Wall thickness of piping and equipment already considered sour gas condition
S (4)C(4)
1 S (M4)C(M4)
Parameter: Composition
Parameter: Corrosion / Erosion
Parameter: Temperature
Parameter: Contamination
2R.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
2R.16.1 Other Than
Relief No additional significant issues of concerns identified
2R.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
2R.18.1 Other Than
External Factors No additional significant issues of concerns identified
2R.19.1 Other Than
Operations No additional significant issues of concerns identified
2R.20.1 Other Than
Maintenance No additional significant issues of concerns identified
2R.21.1 Other Than
Drawing No additional significant issues of concerns identified
Parameter: Operation & Maintenance
Parameter: Drawing
Parameter: Instrumentation
Parameter: Relief
Parameter: Safety
Parameter: External Factor
CNG PLANT TAMBAK LOROK Page 12 of 53 HAZOP Node N2R
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown
H,M,L Co Consequence
Pr ProbabilityRi RiskS Safety RiskC Commercial Risk
CommentDesign Intent
Design Conditions:
Design Capacity: 2.17 MMSCFD each compressor
Opt. Conditions
Flowrate : 20 MMSCFDPower : TBA KW (each compressor)
Drawing Drawing No. TS78-P-PID-004 Rev: B
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
3.1.1 No No Flow SDV W151 fails close Potential overpressurization of upstream equipment and piping leading to loss of integrity and fire event
PSH-0301A at Gas Dryer D-100A/B to close SDV-0101
PSV 0301A/B at dryer unit
Low suction pressure to compressor leading to compressor damage and production loss
PT-501 displayed in control room
PIL 501 at SS-101 as Low pressure alarm to alert operator
Tambak LorokCompression System K101 (typical for K102 to K110), including Blowdown Tank VE301
317-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas Plant
High, Medium, Risk
Nine (9) compressor online and One (1) stand by; reciprocating type compressor, three-stages
Suction Pressure : 26 barGDischarge Pressure : 250 barG
To compress natural gas and transfer to the storage cylinder
Shut Off Pressure :
PID - Compressor System / K-101 (Vendor Package)
Parameter: Flow
CNG PLANT TAMBAK LOROK Page 13 of 53 HAZOP Node N3
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
PILL 501 at SS-101 to shutdown SDV-151
3.2.1 Less Less Flow Blockage of filter FF-201 Potential overpressurization of upstream equipment and piping leading to loss of integrity and fire event
PSH-0301A at Gas Dryer D-100A/B to close SDV-0101
PDI - S01 provided around FF 201PSV 0301A/B at dryer unit
CNG PLANT TAMBAK LOROK Page 14 of 53 HAZOP Node N3
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating Procedures
Review date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown
H,M,L Co Consequence
Pr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
Duty CNG Cooler: 201 kW
Opt. Conditions
2.38 m3 each cylinder
Drawing Drawing No. TS78-P-PID-005 Sheet 1 of 2 Rev: B
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
4.1.1 No No Flow Manual valves at inlet CNG Compartement inadvertenly close
Less of CNG production Local pressure indicator provided each compartment
4.2.1 Less Less Flow See no flow partially
PID - Storage and Decanting System
Parameter: Flow
CNG Cooler : Storage Period (Inlet /Outlet Shell side) : OP : 3 barGCNG Cooler : Storage Period (Inlet /Outlet tube side) : OP : 249 barG
CNG Cooler : Storage Period (Inlet /Outlet Shell side) : OT : 30 deg C/ 39 deg CCNG Cooler : Storage Period (Inlet /Outlet tube side) : OT : 48 deg C/35 deg C
To cooling down compressed gas and storage to CNG compartment
CNG Cooler : DP (shell) : 7 barG; (tube) : 263 barGCNG Compartment : DP : 374 barG
CNG Cooler DT : 65 deg CCNG Compartment DT : 70 deg C
Compressed Natural Gas PlantTambak LorokInlet CNG Cooler E-100 to CNG Compartment (STORAGE TIME)
CNG Storage cylinder consist of 95 compartments. 5 compartments will be arranged in 1 bank (each has 40 tubes).Operation : 19-20 hours storage time, 4-5 hours decanting time
4
17-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONAL
High, Medium, Risk
CNG PLANT TAMBAK LOROK Page 15 of 53 HAZOP Node N4
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
4.2.2 Less Less Flow One of running compressor fails to operate
Less of CNG production Indicator of online compressor in control room
Review sizing of manual valve incoming CNG compartment to be available at market or provide spare manual valve in the case of maintenance required
CNG-HP-14
Standby compressor available
Indication of pressure and flow of storage period by graph to shown loss of production
4.3.1 More More Flow No additional significant issues of concerns identified
4.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
4.5.1 Part of Misdirected Flow KV-0503A leak or fails open (storage condition)
No adverse consequence PV-0501A/B will hold the pressurePIHH 0509 set at 33 barG will open XV-0506 and circulate gas to suction compressor
4.6.1 Less Less Level Not relevant4.7.1 More More Level Not relevant
4.8.1 Less Less Pressure Refer to Less Flow 4.9.1 More More Pressure Refer to No Flow 4.9.2 More More Pressure Storage time more than 20 hours Potential over pressure at
overall plant
PIH-S01 set 30 barG alarm to alert Operator PIHH-S01 set 32 barG to close SDV-SV-101/102/103 set@ 78/165/294 barg
Parameter: Level
Parameter: Pressure
CNG PLANT TAMBAK LOROK Page 16 of 53 HAZOP Node N4
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Maximum discharge pressure of Compressor 255 barG is less than MAWP Tube storage design 373 barG
4.10.1 Less Less Temperature No additional significant issues of concerns identified
4.11.1 More More Temperature
Fouling/Plugging at E-100 or loss of cooling water
Inefficiency in cooling resulting in high temperature leading to less CNG production
TIH-0503/TIH 0508/TIH 0509 alarm will alert operator
Provide portable temperature detector to check skin temperature of CNG compartment
CNG-HP-15
4.12.1 As Well As
Contamination Tube leak at E-100 Gas contamination to cooling water system leading to gas release at cooling tower
Gas detector at cooling tower fan
Provide SOP to control PH at cooling tower periodically
CNG-HP-16
Explosion-proof motor of cooling tower
Gas trapped at shell side resulting in eficient heat transfer
TIH-0503/TIH 0508/TIH 0509 alarm will alert operator
4.13.1 Other Than
Composition No additional significant issues of concerns identified
4.14.1 Other Than
Corrosion / Erosion
See contamination
4.15.1 Other Than
Instrumentation Instrument air failure Unable to supply gas to customer
Nitrogen back up is provided to open KV-0501 to deliver gas from CNG compartement to tambak lorok
4.16.1 Other Than
Relief No additional significant issues of concerns identified
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Relief
Parameter: Composition
Parameter: Temperature
Parameter: Contamination
CNG PLANT TAMBAK LOROK Page 17 of 53 HAZOP Node N4
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
4.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
4.18.1 Other Than
External Factors No additional significant issues of concerns identified
4.19.1 Other Than
Operations No additional significant issues of concerns identified
4.20.1 Other Than
Maintenance No additional significant issues of concerns identified
4.21.1 Other Than
Drawing No additional significant issues of concerns identified
Parameter: Drawing
Parameter: Safety
Parameter: External Factor
Parameter: Operation & Maintenance
CNG PLANT TAMBAK LOROK Page 18 of 53 HAZOP Node N4
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown
H,M,L Co Consequence
Pr ProbabilityRi RiskS Safety RiskC Commercial Risk
CommentDesign Intent
Design Conditions:
Opt. Conditions
Decanting : 113 MMSCFD
Drawing TS78-P-PID-005 Sheet 2 of 2 Rev: B
TS78-P-PID-006 B
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
5.1.1 No No Flow Any of manual valves on the decanting line to E-200 inadvertenly close or PV0501A/B stuck close
Compressor shut off pressure is 255 barg vs design pressure of equipment is 263 barg - no adverse consequence identified
PIH 0502 set at 250psig to alert operator
Inlet CNG Heat Exchanger E-200 to Station Outlet Metering M-200A/B (DECANTING)
E-200 and M-200A/B will be operated during decanting time only. Decanting Time 4-5 hours.To avoid condensation on the upstream of pressure reducing valve and to measure natural gas outlet from CNG Plant
CNG Heat Exchanger : DP (shell) : 5.5 barG; (tube) : 34 barGM-200A/B : DP : 34 barG
CNG Heat Exchanger DT : 120 deg CM-200A/B DT : 65 deg C
Parameter: Flow
CNG Heat Exchanger : Inlet /Outlet Shell side : OT : 90 deg C / 65 deg CCNG Heat Exchanger : Inlet /Outlet tube side : OT- 38 deg C / 30 deg C
PID - CNG Heat Exchanger
PID - Station Outlet Metering (M-200A/B)
Duty CNG Heat Exchanger 3860 kWCapacity M-200A/B: 113 MMSCFD
CNG Heat Exchanger : Inlet /Outlet Shell side : OP : 2 barG / 1.4 barGCNG Heat Exchanger : Inlet /Outlet tube side : OP : 26.7 barG / 26 barG
517-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak Lorok
High, Medium, Risk
CNG PLANT TAMBAK LOROK Page 19 of 53 HAZOP Node N5
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
PIHH 0502 set at 255 psig to shutdown compressor
Loss of gas to customer FT-0601A/B at M-200A/B displayed at control room
FILL 0601 A/Bset at 5 MMSCFD for alarm to alert operator
5.1.2 No No Flow SDV0601 fails close or manual valve in the metering station inadvertenly closed
Potential overpressurization of CNG HE E-200 leading to hydrocarbon release and potential fire
PV0501 A/B to regulate the pressure
Show setting point of PV 0501A/B CNG-HP-17
PIH 0509 set at 31 psig to alert operator PSHH 0509 set at 33 barG to close KV 0501A
5.2.1 Less Less Flow Refer to No Flow - valve partially closed
5.3.1 More More Flow PV0501A/B stuck open Potential overpressurization of CNG HE E-200 and downstream piping
PIH 0509 set at 31 psig to alert operator
PSHH 0509 set at 33 barG to close KV 0501A
5.4.2 Reverse Reverse Flow Gas from suction compressor going to downstream of E-200 to metering M-200
Double counting of sales gas from Gundih meter with M-100
Install additional check valve at line PG-2"-3C-027
CNG-HP-18
5.5.1 Part of Misdirected Flow BDV-0505 fails open Loss of gas to vent BDV position indicator and alarm in control room
5.5.2 Part of Misdirected Flow XV-0506 fails open Loss of gas back to system instead to customer
Valve position indicator and alarm in control room
5.6.1 Less Less Level No additional significant issues of concerns identified
Parameter: Level
CNG PLANT TAMBAK LOROK Page 20 of 53 HAZOP Node N5
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
5.7.1 More More Level No additional significant issues of concerns identified
5.8.1 Less Less Pressure Loss of containment/leak on Decanting Line
Release of hydrocarbon leading to environmental damage and potential fire
F & G
5.9.1 More More Pressure see no flow and more flow5.9. More More Pressure Manual valve upstream BDV-0505
inadvertenly close in the event of ESD and BDV-0505 required to open
Overpresurization of upstream equipment leading to fire/fatality
NA Provide Lock Open (LO) manual valve at upstream BDV-0505
CNG-HP-19
5.10.1 Less Less Temperature No additional significant issues of concerns identified
5.11.1 More More temperature No additional significant issues of concerns identified
5.12.1 As Well As
Contamination Tube leak at E-200 Gas contamination to hot water system leading to gas release at WHRU
Atmospheric venting at Hot Water Tank T-200
5.13.1 Other Than
Composition No additional significant issues of concerns identified
5.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
5.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
5.16.1 Other Than
Relief No additional significant issues of concerns identified
5.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
Parameter: External Factor
Parameter: Pressure
Parameter: Temperature
Parameter: Contamination
Parameter: Composition
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Relief
Parameter: Safety
CNG PLANT TAMBAK LOROK Page 21 of 53 HAZOP Node N5
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
5.18.1 Other Than
External Factors No additional significant issues of concerns identified
5.19.1 Other Than
Operations No additional significant issues of concerns identified
5.20. Other Than
Maintenance No additional significant issues of concerns identified
5.21.1 Other Than
Drawing No additional significant issues of concerns identified
Parameter: Operation & Maintenance
Parameter: Drawing
CNG PLANT TAMBAK LOROK Page 22 of 53 HAZOP Node N5
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
T-200 : 290 m3P-300 : 140 m3/hrE-500 : 127 kW
Opt. Conditions
Power : 36.8 kW
Drawing Drawing No. TS78-P-PID-007 Rev:TS78-P-PID-005 sheet 2 of 2
617-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak LorokHot water circulation including Hot Water Tank T-200, Hot Water Pump P300A/B and circulation to E-200
Circulation to E-200 will be on decanting time only
To heat compressed gas from storage facility to be ready for sales gas
E-500 DP : 2 barGT-200 DP : 0.17 barG
Temperature: 120 deg C
Source Pressure : atm; Discharge Pump : 3.35 barG CNG Heat Exchanger : Inlet /Outlet Shell side : OT : 90 deg C / 65 deg C
High, Medium, Risk
PID - Waste Heat Recovery UnitPID - CNG Heat Exchanger
BB
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
6.1.1 No No Flow Hot Water Pump P-300A/B stop due to failure OR Strainer at upstream P-300A/B blockage
Loss of hot water supply leading to inefficient heat transfer and lower gas sales temperature
TT-0512 as low temperature alarm to alert operator
S (-)C(2)
1 S (-)C(L2)
Provide low temperature switch at line PG-12"-3C-021 to close KV-0503 A to prevent low temperature in the gas sales
High temperature in the circulation water around the waste heat recovery unit
TIC 0703 set at 85 deg C to control exhaust gas supply from compressor
Provide low temperature alarm at line PG-12"-3C-021 to alert operator
TAH 0703 set at 85 deg C alarm to alert operatorTAH 0706 set at 85 deg C alarm to alert operator
Low discharge pressure for hot water circulation leading to inefficient heat transfer
SOP to operate standby pump P-300B
6.1.2 No No Flow Manual valve on the downstream P300A/B inadvertently closed
Loss of hot water supply leading to inefficient heat transfer and lower gas sales temperature
TT-0512 as low temperature alarm to alert operator
S (-)C(2)
1 S (-)C(L2)
Rec. No.
Parameter: FlowCNG-HP-20
CNG-HP-21
CNG PLANT TAMBAK LOROK Page 23 of 53 HAZOP Node N6
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
High temperature in the circulation water around the waste heat recovery unit
TIC 0703 set at 85 deg C to control exhaust gas supply from compressor
TAH 0703 set at 85 deg C alarm to alert operatorTAH 0706 set at 95 deg C alarm to alert operator
Potential overpressurization of upstream piping
PSHH 0703A set at 4.5 barG to close P-300A/B
6.2.1 Less Less Flow Three way valve TV-0502 to E-200 is inadvertenly close
Loss of hot water supply leading to inefficient heat transfer and lower gas sales temperature
TT-0512 as low temperature alarm to alert operator
S (-)C(2)
1 S (-)C(L2)
Provide Temperature Control Valve at bypass line of E-200
High temperature in the circulation water around the waste heat recovery unit
TIC 0703 set at 85 deg C to control exhaust gas supply from compressor
TAH 0703 set at 85 deg C alarm to alert operator
Three way valve TV-0502 to by pass line E-200 is inadvertenly close
Not adverse consequence
6.3.1 More More Flow Hot Water Pump P-300A andB running simultaneously
Excess hot water supply to E-200 resulting in potential
TIC-0502 as high temperature alarm to alert
S (-)C(2)
1 S (-)C(L2)
CNG-HP-22
running simultaneously E-200 resulting in potential overheating
temperature alarm to alert operator
C(2) C(L2)
Pump running status indication at control room
6.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
6.5.1 Part of Misdirected Flow 2-in manual valve at T-200 to open drain inadvertently open
Loss of hot water supply leading to inefficient heat transfer
SOP S (-)C(2)
1 S (-)C(L2)
Overheating of water to E-300 system
LSL-0702 to shutdown P-500A/B
6.6.1 Less Less Level see misdirected flow 6.5.16.6.2 Less Less Level More evaporation with less make up
waterLoss of hot water supply leading to inefficient heat transfer
Vapor Condenser E-500 provided
S (-)C(2)
1 S (-)C(L2)
LSL 0701 to start P-600 pump for make up water
Overheating of water to E-300 system
LSL-0702 to shutdown P-500A/B
6.7.1 More More Level Make up water activated Potential overflow to open drain
LSH 0701 to stop make up water and provide warning to operator
S (-)C(2)
1 S (-)C(L2)
Overflow line to Open Drain
Parameter: Level
CNG PLANT TAMBAK LOROK Page 24 of 53 HAZOP Node N6
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
6.8.1 Less Less Pressure refer to No Flow 6.1.16.9.1 More More Pressure Refer to No Flow
6.10.1 Less Less Temperature Leak at hot water system at discharge P-300A/B
Loss of hot water supply leading to inefficient heat transfer and lower gas sales temperature
TT-0512 as low temperature alarm to alert operator
S (-)C(2)
1 S (-)C(L2)
High temperature in the circulation water around the waste heat recovery unit
TIC 0703 set at 85 deg C to control exhaust gas supply from compressor
TAH 0703 set at 85 deg C alarm to alert operatorTAH 0706 set at 85 deg C alarm to alert operator
6.10.2 Less Less Temperature Fouling/Plugging at E-200 Inefficiency in heating resulting in lower gas temperature
TT-0512 as low temperature alarm to alert operator
S (-)C(2)
1 S (-)C(L2)
6.10.3 Less Less Temperature Refer to No Flow
6.11.1 More More Temperature
Refer to More Flow
Parameter: Pressure
Parameter: Temperature
Temperature
6.12.1 As Well As
Contamination E-200 Tube/tube sheet leak Gas introduce to hot water system leading to potential overpressure of hot water system
T-200 is venting to atmosphere
S (-)C(2)
1 S (-)C(L2)
6.13.1 Other Than
Composition No additional significant issues of concerns identified
6.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
6.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
6.16.1 Other Than
Relief No additional significant issues of concerns identified
6.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
6.18.1 Other Than
External Factors No additional significant issues of concerns identified
Parameter: Contamination
Parameter: Relief
Parameter: Composition
d
Parameter: Safety
Parameter: External Factor
Parameter: Instrumentation
CNG PLANT TAMBAK LOROK Page 25 of 53 HAZOP Node N6
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
6.19.1 Other Than
Operations No additional significant issues of concerns identified
6.20.1 Other Than
Maintenance No additional significant issues of concerns identified
6.21.1 Other Than
Drawing No additional significant issues of concerns identified
Parameter: Operation & Maintenance
Parameter: Drawing
CNG PLANT TAMBAK LOROK Page 26 of 53 HAZOP Node N6
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
P-500 : 48 m3/hr
Opt. Conditions
Power : 1283 kW
Drawing Drawing No. TS78-P-PID-007 Rev:
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
7.1.1 No No Flow Water Circulation Pump P-500A/B stop due to failure OR Strainer at upstream P-500A/B blockage
Loss of water circulation leading to overheating of hot water circulation to T-200
TIC-0703 to close dampener from compressor flue gas
S (-)C(2)
1 S (-)C(L2)
TIC-0703 as high temperature alarm to alert operatorPSV-0701 as thermal relief routed to open drain
Pump running status indication at control room
Low discharge pressure for water circulation leading to inefficient heat transfer
SOP to operate standby pump P-500B
717-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak LorokWaste Heat Recovery Unit include Water circulation pump P-500A/B and WHRU
To recover heat from exhaust gas of compressor and heating water for heating media E-100 and E-200
Pressure: WHRU : 18 Barg Temperature: WHRU : 545 deg C
Shell / Coil : 0.03 barG / 3 barG Shell / Coil OT : 490 deg C / 63 to 90 deg C
High, Medium, Risk
PID - Waste Heat Recovery Unit
Rec. No.
B
Parameter: Flow
CNG PLANT TAMBAK LOROK Page 27 of 53 HAZOP Node N7
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
7.1.2 No No Flow Any manual valve at upstream E-300 inadvertenly close or check valve blockage
Loss of water circulation leading to overheating of hot water circulation to T-200
TIC-0703 to close dampener from compressor flue gas
S (-)C(2)
1 S (-)C(L2)
TIC-0703 as high temperature alarm to alert operatorPSV-0701 as thermal relief
Potential overpressure of downstream pump
Vendor to provide minimum flow recycle line at P-500A/B
7.2.1 Less Less Flow Any manual valve on the water circulation line at WHRU system partially closed
Loss of water circulation leading to overheating of hot water circulation to T-200
TIC-0703 to close dampener from compressor flue gas
S (-)C(2)
1 S (-)C(L2)
TIC-0703 as high temperature alarm to alert operatorPSV-0701 as thermal relief
7.3.1 More More Flow Water Circulation Pump P-500A/B running simultaneously
Excess water circulation to E-300/T-200 - no safety consequence
Pump running status indication at control room
7.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
7.5.1 Part of Misdirected Flow 3/4" manual valve to open drain inadvertenly open
Loss of water circulation leading to overheating of hot water circulation to T-200
TIC-0703 to close dampener from compressor flue gas
S (-)C(2)
1 S (-)C(L2)
TIC-0703 as high temperature alarm to alert operatorPSV-0701 as thermal relief
7.5.2 Part of Misdirected Flow Manual valve to venting open Loss of water circulation leading to overheating of hot water circulation to T-200
TIC-0703 to close dampener from compressor flue gas
S (-)C(2)
1 S (-)C(L2)
TIC-0703 as high temperature alarm to alert operatorPSV-0701 as thermal relief
7.6.1 Less Less Level No additional significant issues of concerns identified
7.7.1 More More Level No additional significant issues of concerns identified
Parameter: Level
CNG-HP-23
CNG PLANT TAMBAK LOROK Page 28 of 53 HAZOP Node N7
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
7.8.1 Less Less Pressure Refer to No Flow 6.1.17.9.1 More More Pressure Refer to No Flow
7.10.1 Less Less Temperature Refer to No Flow
One or more gas engine driver shutdown
Less of flue gas to E-300 resulting in lower temperature generated for water circulation
TIA 0704 to alert operator S (-)C(2)
1 S (-)C(L2)
Review requirement set point of TIA-0704
Start up Low gas temperature from exhaust gas compressor to WHRU resulting condensation at gas ducting E-300
Provide drain line at lowest point gas ducting E-300
7.11.1 More More Temperature
Refer to No Flow, Less Flow, Misdirected Flow
7.12.1 As Well As Contamination No additional significant issues of concerns identified
7.13.1 Other Than
Composition No additional significant issues of concerns identified
7.14.1 Other Than
Corrosion / Erosion
Condense water from flue gas at E-300
Corrosion at E-300 leading to equipment damage
Check with vendor the requirement of TIA-0705 as low temperature alarm
S (-)C(2)
2 S (-)C(M6)
Review requirement TIA-0705
7.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
7.16.1 Other Than
Relief No additional significant issues of concerns identified
7.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
7.18.1 Other Than
External Factors No additional significant issues of concerns identified
7.19.1 Other Than
Operations No additional significant issues of concerns identified
7.20.1 Other Than
Maintenance No additional significant issues of concerns identified
CNG-HP-26
Parameter: External Factor
Parameter: Operation & Maintenance
Parameter: Pressure
Parameter: Temperature
Parameter: Contamination
Parameter: Composition
CNG-HP-25
CNG-HP-27
Parameter: Drawing
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Relief
Parameter: Safety
CNG PLANT TAMBAK LOROK Page 29 of 53 HAZOP Node N7
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
7.21.1 Other Than
Drawing
7.21.2 Other Than
Drawing
7.21.3 Other Than
Drawing Revise drawing TS78-P-PID-007 to show setting point of all instrumentation alarm and trip
CNG-HP-28
CNG PLANT TAMBAK LOROK Page 30 of 53 HAZOP Node N7
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
Flow : 3.2 m3/hr
Opt. Conditions
Drawing Drawing No. TS78-P-PID-012 Rev:
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
8.1.1 No No Flow Manual valve at inlet Feed Pump P701 inadvertenly close
No make up water supply for cooler/heater leading to low performance of heat transfer
SOP to monitor Water Treatment Plant (WTP)
S (-)C(1)
2 S (-)C(L2)
Low suction pressure of P702 resulting in pump damage
PSL1209 to stop P702
8.1.2 No No Flow Pump P701 stop due to failure No make up water supply for cooler/heater leading to low performance of heat transfer
Pump maintenance S (-)C(1)
2 S (-)C(L2)
Low suction pressure of P702 resulting in pump damage
PSL1209 to stop P702
8.1.3 No No Flow MOV-1201 (valve on duty) inadvertenly close
No make up water supply for cooler/heater leading to low performance of heat transfer
SOP to monitor Water Treatment Plant (WTP)
S (-)C(1)
2 S (-)C(L2)
Low suction pressure of P702 resulting in pump damage
PSL1209 to stop P702
817-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak LorokWater Treatment Plant
to treat sea water and provide potable water for cooling media
Pressure : 7 barG Temperature: 65 deg C
Pressure : 4 barG Temperature : ambient
High, Medium, Risk
PID - Water Treatment Plant
Rec. No.
B
Parameter: Flow
CNG PLANT TAMBAK LOROK Page 31 of 53 HAZOP Node N8
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
8.1.4 No No Flow High Pressure Pump P702 failure No make up water supply for cooler/heater leading to low performance of heat transfer
Pump maintenance S (-)C(1)
2 S (-)C(L2)
8.1.5 No No Flow Manual valve downstream P702 inadvertenly close
No make up water supply for cooler/heater leading to low performance of heat transfer
SOP to monitor Water Treatment Plant (WTP)
Potential overpressure of upstream equipment
PSH 1211 to stop P702 and P701
8.1.6 No No Flow Manual valve downstream Buffer Tank TK-02 inadvertenly close
Potential overfilling TK02 LS-1201 to stop Feed Pump P701
S (-)C(1)
1 S (-)C(L1)
LS-1201 to stop Hi press Pump PU-201
8.1.7 No No Flow High Pressure Pump PU-201 failure No make up water supply for cooler/heater leading to low performance of heat transfer
Pump maintenance S (-)C(1)
2 S (-)C(L2)
Manual valve downstream PU-201 inadvertenly close
No make up water supply for cooler/heater leading to low performance of heat transfer
SOP to monitor Water Treatment Plant (WTP)
S (-)C(1)
2 S (-)C(L2)
Potential overpressure of upstream equipment
PSH 1216 to stop PU-201
8.2.1 Less Less Flow Filter F-1A//B blockage Potential overpressure of upstream equipment
PI 1201, PI 1202 and PI 1203 to monitor differential pressure
S (-)C(1)
2 S (-)C(L2)
8.2.2 Less Less Flow Filter FX-01/02 blockage Potential overpressure of upstream equipment
PDI 1201 to monitor differential pressure
S (-)C(1)
2 S (-)C(L2)
8.2.3 Less Less Flow RO-A blockage Potential overpressure of upstream equipment
PSH 1211 to stop P702 and P701
S (-)C(1)
2 S (-)C(L2)
8.3.1 More More Flow Control valve upstream FM 1205 stuck open
Potential overflow to TK01 LS01 to stop FEED pump P701
S (-)C(1)
1 S (-)C(L1)
8.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
8.5.1 Part of Misdirected Flow Manual valve for sample inadvertenly open
Loss of make up water to environment
SOP
8.5.2 Part of Misdirected Flow Manual drain valve from RO-A to open ditch inadvertenly open
Loss of make up water to environment
SOP
8.6.1 Less Less Level No additional significant issues of concerns identified
8.7.1 More More Level see more flow
8.8.1 Less Less Pressure see no flow
Parameter: Level
Parameter: Pressure
CNG PLANT TAMBAK LOROK Page 32 of 53 HAZOP Node N8
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
8.9.1 More More Pressure see no flow and less flow
8.10.1 Less Less Temperature No additional significant issues of concerns identified
8.11.1 More More Temperature
No additional significant issues of concerns identified
8.12.1 As Well As
Contamination No additional significant issues of concerns identified
8.13.1 Other Than
Composition Manual valve from chemical source inadvertenly close
Low make up water quality leading to scale
SOP
8.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
8.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
8.16.1 Other Than
Relief No additional significant issues of concerns identified
8.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
8.18.1 Other Than
External Factors No additional significant issues of concerns identified
8.19.1 Other Than
Operations No additional significant issues of concerns identified
8.20.1 Other Than
Maintenance No additional significant issues of concerns identified
8.21.1 Other Than
Drawing
Parameter: Temperature
Parameter: Contamination
Parameter: Composition
Parameter: Drawing
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Relief
Parameter: Safety
Parameter: External Factor
Parameter: Operation & Maintenance
CNG PLANT TAMBAK LOROK Page 33 of 53 HAZOP Node N8
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
Capacity T-100 : 54 m3
Opt. Conditions
Power P-100 : 0.85 kW; P-200A/B : 5.88 kW
Drawing Drawing No. TS78-P-PID-011 Rev:
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
9.1.1 No No Flow Manual valve at inlet T-100 is inadvertenly close
Low level at T-100 leading to loss of pump suction and potential pump damage
LSL 1101 to shutdown Pump P-600
S (-)C(2)
2 S (-)C(M4)
Loss of make up water for cooling media and make up T-200 leading to ineffective heat transfer
Temperature alarm at WHRU, E-100 and E-200
9.1.2 No No Flow Manual valve at outlet T-100 is inadvertenly close or strainer blocked
Loss of pump suction and potential pump damage
S (-)C(2)
2 S (-)C(M4)
Provide lock open (LO) for manual valve upstream P-100 and P-600
Loss of make up water for cooling media and make up T-200 leading to ineffective heat transfer
Temperature alarm at WHRU, E-100 and E-200
9.1.3 No No Flow Make up water pump P-100 broken or stop
Loss of make up water for cooling media leading to ineffective heat transfer
Pump running status indication at control room
S (-)C(2)
1 S (-)C(L2)
917-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak LorokCooling System, including Make up Water Tank T-100, Make Up Water Pump P-100, Cooling Tower E-400 and Cooling Tower Pump P-200 A/B
To provide cooling media for E-100
Pressure: Cooling Tower : 3.5 Barg Temperature: 65 deg C
Pressure : ATM Temperature : 30 - 45 deg C
PID - Cooling System
Rec. No.
B
Parameter: Flow
CNG-HP-29
High, Medium, Risk
CNG PLANT TAMBAK LOROK Page 34 of 53 HAZOP Node N9
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Pump maintenance9.1.4 No No Flow Manual valve or strainer at inlet
Basin cooling water is inadvertently close
Loss of make up water for cooling media leading to ineffective heat transfer
Temperature alarm at E-100 S (-)C(2)
1 S (-)C(L2)
Potential overflow at T-600 Floating valve at T-600 to start/stop pump P-100
Review design of floating valve T-600 to be radar type
9.1.5 No No Flow Cooling water pump P-200A/B broken or not in operation
Loss of make up water for cooling media leading to ineffective heat transfer
Pump running status indication at control room
S (-)C(2)
1 S (-)C(L2)
9.1.6 No No Flow Manual valve at upstream P-200A/B inadvertenly close or strainer blocked
Loss of pump suction and potential pump damage
Strainer Maintenance periodically
S (-)C(2)
2 S (-)C(M4)
Provide lock open (LO) for manual valve upstream P-200
Loss of make up water for cooling media leading to ineffective heat transfer
9.1.7 No No Flow Manual valve at downstream P-200A/B inadvertently close
Potential overpressurization of piping at pump discharge
PSH 1108A to stop P-200A/B
S (-)C(2)
1 S (-)C(L2)
9.2.1 Less Less Flow Refer to No Flow - valve partially closed
9.3.1 More More Flow Cooling Tower Pump P-200 A and B running simultenaously
More of water cooling media - no adverse consequence
Pump running status indication at control room
9.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
9.5.1 Part of Misdirected Flow 3" manual valve at T-100/E-400 to open drain inadvertenly open
Low level at T-100 leading to loss of pump suction and potential pump damage
LSL 1101 to shutdown Pump P-600
9.5.1 Part of Misdirected Flow 2" manual valve at E-400 to open drain inadvertenly open
Low level at E-400 leading to loss of pump suction and potential pump damage
Floating valve will flow water from T-600
9.6.1 Less Less Level see no flow 9.1.1, 9.1.2,9.1.3,9.5.1 Loss of water for cooling media resulting insufficent heat absorbed during heat transfer leading to CN gas offspec
9.6.2 Less Less Level Make up water pump P-100 fails to stop
Low level at T-100 leading to loss of pump suction and potential pump damage
LSL 1101 to shutdown Pump P-100
S (-)C(2)
2 S (-)C(M4)
CNG-HP-31
CNG-HP-30
Parameter: Level
CNG PLANT TAMBAK LOROK Page 35 of 53 HAZOP Node N9
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
High level at Cooling Tower basin T-600
Float valve will stop incoming flow to cooling tower
9.7.1 More More Level Float valve at Cooling Tower basin E-400 failure
Potential overflow to open drain
SOP S (-)C(2)
1 S (-)C(L2)
9.8.1 Less Less Pressure Leak in water supply line to E-100 Loss of water for cooling media resulting insufficent heat absorbed during heat transfer leading to CN gas offspec
S (-)C(2)
2 S (-)C(M4)
9.9.1 More More Pressure see no flow 9.1.1, 9.1.2,9.1.3
9.10.1 Less Less Temperature No additional significant issues of concerns identified
9.11.1 More More Temperature
Motor at E-400 fails to run high temperature of water supply to E-100 leading to less production
TT-0503 at E-100 as high temperature alarm to alert operator
S (-)C(2)
1 S (-)C(L2)
9.12.1 As Well As Contamination No additional significant issues of concerns identified
9.13.1 Other Than
Composition No additional significant issues of concerns identified
9.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
9.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
9.16.1 Other Than
Relief No additional significant issues of concerns identified
9.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
9.18.1 Other Than
External Factors No additional significant issues of concerns identified
9.19.1 Other Than
Operations No additional significant issues of concerns identified
9.20.1 Other Than
Maintenance No additional significant issues of concerns identified
Parameter: Pressure
Parameter: Temperature
Parameter: Contamination
Parameter: Composition
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Relief
Parameter: Safety
Parameter: External Factor
Parameter: Operation & Maintenance
CNG PLANT TAMBAK LOROK Page 36 of 53 HAZOP Node N9
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
9.21.1 Other Than
DrawingParameter: Drawing
CNG PLANT TAMBAK LOROK Page 37 of 53 HAZOP Node N9
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
P-400 Capacity : 1.2 m3/hr
Opt. Conditions
Power P-400 : 0.3 kW
Drawing Drawing No. TS78-P-PID-010 Rev:
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
10.1.1 No No Flow 4" manual valve at inlet V-400 inadvertenly closed
High level at source vessel Safeguards at source vessel S (-)C(1)
1 S (-)C(L1)
10.2.1 Less Less Flow No additional significant issues of concerns identified
10.3.1 More More Flow Liquid control valve failure at individual equipments (V-300, Compressor K-101-109, V-100)
Build up pressure in Sump Tank V-400 leading to potential overpressurization
Open venting to atmosphere S (-)C(1)
1 S (-)C(L1)
Review outlet line at venting V-400 to be sufficient for case high pressure gas introduced from upstream equipment to this vessel
10.3.2 More More Flow Manual drain valves at individual equipments inadvertently open during online operation
Build up pressure in Sump Tank V-400 leading to potential overpressurization
Open venting to atmosphere S (-)C(1)
1 S (-)C(L1)
Loss of level at the source vessel
LT at individual equipment as low level alarm to alert operator; and as low level trip to initiate USD
1017-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak LorokSump Tank V-400 including Sump Tank P-400
To collect liquid drain from vessel (closed drain system)
Pressure : 3.5 barG Temperature: 45 deg C
Tank Ops Pressure : ATM; PPump Suc Pressure : Atm, Disch Pressure : 2 barG
Temperature : AMB
High, Medium, Risk
PID - Sump System
Rec. No.
B
CNG-HP-32
Parameter: Flow
CNG PLANT TAMBAK LOROK Page 38 of 53 HAZOP Node N10
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Double-valve provided at drain line of the individual equipments
10.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
10.5.1 Part of Misdirected Flow No additional significant issues of concerns identified
10.6.1 Less Less Level Sump Pump P-400 fails to stop due to LT-1001 failure to function
Loss of liquid level leading to Sump Pump P-400 damage due to cavitation
Pump will be stopped during no signal (FC)
S (-)C(1)
1 S (-)C(L1)
10.7.1 More More Level Pump stopped due to no power supply or pump damage
Overfilling of Sump Tank V-400 and liquid release from vent to environment
LAH 1001 as high level alarm to alert operator
S (-)C(1)
1 S (-)C(L1)
SOP - draining activity is attended by operatorStandby portable pump will be provided and connected to available spare nozzle
10.8.1 Less Less Pressure No additional significant issues of concerns identified
10.9.1 More More Pressure Refer to More flow10.9.2 More More Pressure Blockage of flame arrestor at vent
linePotential overpressurization of V-400
Bug screen provided
10.10.1 Less Less Temperature No additional significant issues of concerns identified
10.11.1 More More Temperature
No additional significant issues of concerns identified
10.12.1 As Well As Contamination No additional significant issues of concerns identified
10.13.1 Other Than
Composition No additional significant issues of concerns identified
10.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
10.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
Parameter: Composition
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Level
Parameter: Pressure
Parameter: Temperature
Parameter: Contamination
CNG PLANT TAMBAK LOROK Page 39 of 53 HAZOP Node N10
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
10.16.1 Other Than
Relief No additional significant issues of concerns identified
10.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
10.18.1 Other Than
External Factors No additional significant issues of concerns identified
10.19.1 Other Than
Operations No additional significant issues of concerns identified
10.20.1 Other Than
Maintenance No additional significant issues of concerns identified
10.21.1 Other Than
Drawing
Parameter: Operation & Maintenance
Parameter: Drawing
Parameter: Relief
Parameter: Safety
Parameter: External Factor
CNG PLANT TAMBAK LOROK Page 40 of 53 HAZOP Node N10
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
Capacity : 1.5 m3
Opt. ConditionsDrawing Drawing No. TS78-P-PID-009 Rev:
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
11.1.1 No No Flow 3" Manual valves at incoming/outgoing line Fuel Gas filter is inadvertently closed
Loss of fuel gas supply leading to compressor shutdown
PT-0902 as low pressure alarm to alert operator
S (-)C(4)
1 S (-)C(M4)
Provide lock open (LO) for 3" manual valves at upstream and downstream Fuel Gas Filter
11.1.2 No No Flow PCV-0901A/B stuck closed Loss of fuel gas supply leading to compressor shutdown
PT-0902 as low pressure alarm to alert operator
S (-)C(4)
1 S (-)C(M4)
Standby PCV available11.2.1 Less Less Flow Pump N4 stop due to failure Less of fuel gas supply
leading to compressor shutdown
PDI 0901A/B to monitor differential pressure
S (-)C(2)
1 S (-)C(L2)
Back up fuel gas filter availablePT-0902 as low pressure alarm to alert operator
11.3.1 More More Flow PCV-0901A/B stuck open Potential overpressurization of downstream equipment
PT-0902 as high pressure alarm to alert operator
S (-)C(1)
1 S (-)C(L1)
11.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
Fuel Gas System
1117-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak Lorok
High, Medium, Risk
To provide fuel to compressor
Pressure : 13.5 barG Temperature: 45 deg C
Pressure : 10 barG Temperature : 21 deg C
PID - Fuel Gas System B
Rec. No.
Parameter: FlowCNG-HP-33
CNG PLANT TAMBAK LOROK Page 41 of 53 HAZOP Node N11
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
11.5.1 Less Misdirected Flow No additional significant issues of concerns identified
11.6.1 Less Less Level No additional significant issues of concerns identified
11.7.1 More More Level No additional significant issues of concerns identified
11.8.1 Less Less Pressure Refer to No Flow and Less Flow11.9.1 More More Pressure Refer to More Flow
11.10.1 Less Less Temperature No additional significant issues of concerns identified
11.11.1 More More Temperature
No additional significant issues of concerns identified
11.12.1 As Well As Contamination No additional significant issues of concerns identified
11.13.1 Other Than
Composition No additional significant issues of concerns identified
11.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
11.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
11.16.1 Other Than
Relief No additional significant issues of concerns identified
11.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
11.18.1 Other Than
External Factors No additional significant issues of concerns identified
11.19.1 Other Than
Operations No additional significant issues of concerns identified
11.20.1 Other Than
Maintenance No additional significant issues of concerns identified
11.21.1 Other Than
Drawing
Parameter: Level
Parameter: Pressure
Parameter: Contamination
Parameter: Corrosion / Erosion
Parameter: Relief
Parameter: External Factor
Parameter: Operation & Maintenance
Parameter: Drawing
Parameter: Temperature
Parameter: Composition
Parameter: Instrumentation
Parameter: Safety
CNG PLANT TAMBAK LOROK Page 42 of 53 HAZOP Node N11
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
Capacity 183.63 SCFM (each)
Opt. Conditions
Power: 30 kW (each)
Drawing Drawing No. TS78-P-PID-008 Sheet 1 of 2 Rev:TS78-P-PID-008 Sheet 2 of 2
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
12.1.1 No No Flow Manual valve upstream of Instrument Air Receiver V-300 inadvertently closed
Loss of instrument air supply potentially leading to PSD
Instrument air supply from Instrument Air Receiver V-300 is provided for 5 minutes in operation
S (-)C(2)
1 S (-)C(L2)
PT-0803 set at 7 barg as low pressure alarm to alert Operator
Potential overpressurization of upstream piping
NA Confirm availability of high pressure trip at internal of Air Compressor C300A/B/C package to shut down compressor in the case of block of discharge
12.1.2 No No Flow Any manual valve upstream of Air Dryer Prefilter F300A/B inadvertently closed
Loss of instrument air supply potentially leading to PSD
Instrument air supply from Instrument Air Receiver V-300 is provided for 5 minutes in operation
S (-)C(2)
1 S (-)C(L2)
1217-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak Lorok
Pressure : 12 barG Temperature: 45 deg C
Pressure : 6 - 10 barG Temperature : AMB - 40 deg C
High, Medium, Risk
PID - Instrument Air System
Instrument Air System
To provide instrument air for instrumented system
PID - Instrument Air Network
Rec. No.
BB
Parameter: Flow
CNG-HP-34
CNG PLANT TAMBAK LOROK Page 43 of 53 HAZOP Node N12
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Potential overpressurization of upstream piping
PSV 0801 set at 12 barG release air to atmosphere
12.1.3 No No Flow Any manual valve upstream of Air Dryer D300A/B inadvertently closed
Loss of instrument air supply potentially leading to PSD
Instrument air supply from Instrument Air Receiver V-300 is provided for 5 minutes in operation
Potential overpressurization of upstream piping
PSV 0801 set at 12 barG release air to atmosphere
12.1.4 No No Flow Any manual valve upstream Air Dryer after filter F301A/B inadvertently closed
Loss of instrument air supply potentially leading to PSD
Instrument air supply from Instrument Air Receiver V-300 is provided for 5 minutes in operation
S (-)C(2)
1 S (-)C(L2)
Potential overpressurization of upstream piping
PSV 0802 release air to atmosphere
12.1.5 No No Flow Any manual valve downstream Air Dryer after filter F301A/B inadvertently closed
Loss of instrument air supply potentially leading to PSD
Instrument air supply from Instrument Air Receiver V-300 is provided for 5 minutes in operation
Potential overpressurization of upstream piping
PSV 0802 release air to atmosphere
12.1.6 No No Flow Air Compressors package trip/broken
Loss of instrument air supply potentially leading to PSD
Auto start of standby compressor by PSLL-0803
S (-)C(2)
1 S (-)C(L2)
Nitrogen back up at downstream F-310A/B
12.1.7 No Flow Manual valve downstream Instrument Air Receiver V-310 inadvertently closed
Loss of instrument air supply potentially leading to PSD
Instrument air supply from Instrument Air Receiver V-310 is provided for 5 minutes in operation
S (-)C(2)
1 S (-)C(L2)
Lock Open (LO) for manual valve downstream Instrument Air Receiver V-310
Potential overpressurization of upstream piping
12.2.1 Less Less Flow Air Dryer Prefilter F300A/B blockage
Less of instrument air supply potentially leading to PSD
PDI 0801 to monitor differential pressure
S (-)C(2)
1 S (-)C(L2)
Wet instrument air quality resulting in instrumentation damage leading to potential shutdown
Dew Point Meter D0801
Spare Air Dryer Prefilter available
CNG-HP-35
CNG PLANT TAMBAK LOROK Page 44 of 53 HAZOP Node N12
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
12.2.2 Less Less Flow Air Dryer D-200A/B blockage Less of instrument air supply potentially leading to PSD
PDI 0802A/B to monitor differential pressure
S (-)C(2)
1 S (-)C(L2)
Wet instrument air resulting in instrumentation damage leading to potential shutdown
Dew Point Meter DE 0801
Spare Air Dryer available12.2.3 Less Less Flow Air Dryer After Filter F301A/B
blockageLess of instrument air supply potentially leading to PSD
PDI 0802 to monitor differential pressure
S (-)C(2)
1 S (-)C(L2)
Wet instrument air quality resulting in instrumentation damage leading to potential shutdown
Dew Point Meter D0801
Spare Air Dryer After filter available
12.3.1 More More Flow All Air Compressor running simultaneously - no adverse consequence
12.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
12.5.1 Part of Misdirected Flow 3/4" manual drain valve at V-300 inadvertently close
High pressure air blowby to sump tank V-400
Sump Tank V-400 is open to atmosphere
S (-)C(2)
1 S (-)C(L2)
Less of instrument air supply potentially leading to PSD
12.6.1 Less Less Level No additional significant issues of concerns identified
12.7.1 More More Level Water condensation in V-300 and lube oil entrainment from compressors
Low quality of instrument air leading to potential instrument damage and shutdown
SOP to monitor LG 0801 S (-)C(2)
1 S (-)C(L2)
12.8.1 Less Less Pressure see no flow, less flow, misdirected flow
12.9.1 More More Pressure see no flow
12.10.1 Less Less Temperature No additional significant issues of concerns identified
12.11.1 More More Temperature
No additional significant issues of concerns identified
Parameter: Temperature
Parameter: Contamination
Parameter: Level
Parameter: Pressure
CNG PLANT TAMBAK LOROK Page 45 of 53 HAZOP Node N12
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
12.12.1 As Well As
Contamination No additional significant issues of concerns identified
12.13.1 Other Than
Composition No additional significant issues of concerns identified
12.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
12.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
12.16.1 Other Than
Relief No additional significant issues of concerns identified
12.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
12.18.1 Other Than
External Factors No additional significant issues of concerns identified
12.19.1 Other Than
Operations No additional significant issues of concerns identified
12.20.1 Other Than
Maintenance No additional significant issues of concerns identified
12.21.1 Other Than
Drawing No additional significant issues of concerns identified
12.21.2 Other Than
Drawing No additional significant issues of concerns identified
Parameter: Composition
Parameter: Drawing
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Relief
Parameter: Safety
Parameter: External Factor
Parameter: Operation & Maintenance
CNG PLANT TAMBAK LOROK Page 46 of 53 HAZOP Node N12
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
Opt. Conditions
Drawing Drawing No. TS78-P-PID-013 Rev:
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
13.1.1 No No Flow Any of manual valve at fire water ring inadvertently close/stuck close
Lack of fire water supply resulting in inadequate water to extinguishing fire
SOP S (3)C(3)
1 S (M3)C(M3)
13.1.2 No No Flow Existing fire water pump inoperation Fail to supply fire water in case of fire leading to fire escalation
S (3)C(3)
1 S (M3)C(M3)
13.2.1 Less Less Flow Any of manual valve at fire water ring partially close
Lack of fire water supply resulting in inadequate water to extinguishing fire
SOP S (3)C(3)
1 S (M3)C(M3)
13.3.1 More More Flow No additional significant issues of concerns identified
13.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
13.5.1 Part of Misdirected Flow No additional significant issues of concerns identified
13.6.1 Less Less Level No additional significant issues of concerns identified
1317-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak LorokFire Water System
Fire water is supplied from existing facility
to provide cooling system and extinguish fire from the process plant and building
Pressure : ATM Temperature: 45 deg C
Pressure : ATM Temperature : ambient
High, Medium, Risk
PID - Fire Water System
Rec. No.
B
Parameter: Flow
Parameter: Level
CNG PLANT TAMBAK LOROK Page 47 of 53 HAZOP Node N13
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
13.7.1 More More Level No additional significant issues of concerns identified
13.8.1 Less Less Pressure see less flow13.9.1 More More Pressure No additional significant issues of
concerns identified
13.10.1 Less Less Temperature No additional significant issues of concerns identified
13.11.1 More More Temperature
No additional significant issues of concerns identified
13.12.1 As Well As Contamination No additional significant issues of concerns identified
13.13.1 Other Than
Composition No additional significant issues of concerns identified
13.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
13.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
13.16.1 Other Than
Relief No additional significant issues of concerns identified
13.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
13.18.1 Other Than
External Factors No additional significant issues of concerns identified
13.19.1 Other Than
Operations Review existing Tambak Lorok’s fire water capacity to be adequate for fire water handling in CNG Plant
13.19.2 Other Than
Operations Consider to provide additional flowmeter to measure fire water consumption for Tambak Lorok
13.20.1 Other Than
Maintenance No additional significant issues of concerns identified
13.21.1 Other Than
Drawing
Parameter: Instrumentation
Parameter: Relief
Parameter: Corrosion / Erosion
Parameter: Pressure
Parameter: Temperature
Parameter: Contamination
Parameter: Composition
CNG-HP-36
CNG-HP-37
Parameter: Safety
Parameter: External Factor
Parameter: Operation & Maintenance
Parameter: Drawing
CNG PLANT TAMBAK LOROK Page 48 of 53 HAZOP Node N13
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
Capacity : 600 kW
Opt. ConditionsDrawing Drawing No. TS78-P-PID-014 Rev:
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
14.1.1 No No Flow Power Generator unable to operate due to damage
No power generated leading to plant shutdown
Standby Generator provided
S (-)C(3)
1 S (-)C(M3)
Back up power supply from PLN available
XV 1401 or XV 1402 or XV - 1403 inadvertenly closePV 1401 or PV-1402 stuck closeManual valve up stream GE-100A inadvertenly close
14.2.1 Less Less Flow No additional significant issues of concerns identified
14.3.1 More More Flow No additional significant issues of concerns identified
14.4.1 Reverse Reverse Flow No additional significant issues of concerns identified
14.5.1 Part of Misdirected Flow 2-in manual valve to drain system open
Hydrocarbon gas release to environment
14.6.1 Less Less Level No additional significant issues of concerns identified
1417-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak LorokPower Generation system
GE-100 A is main generator and GE-100B is back up generator (emergency???)
to provide power for CNG plant
Pressure : Temperature:
Pressure : Temperature :
High, Medium, Risk
PID - Power Generator System
Rec. No.
B
Parameter: Flow
v
CNG PLANT TAMBAK LOROK Page 49 of 53 HAZOP Node N14
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
14.7.1 More More Level No additional significant issues of concerns identified
14.8.1 Less Less Pressure see less flow14.9.1 More More Pressure see more flow
14.10.1 Less Less Temperature No additional significant issues of concerns identified
14.11.1 More More Temperature
Any manual valve down stream GE-100A to cooling system inadvertenly close
Overheating at GE-100A leading to equipment damage, plant shutdown
S (-)C(3)
1 S (-)C(M3)
Confirm availability of TSHH to trip Gas Generator GE-100A in case of high temperature has been included in the generator package.Lock Open (LO) for manual valve downstream GE-100A
14.12.1 As Well As Contamination No additional significant issues of concerns identified
14.13.1 Other Than
Composition No additional significant issues of concerns identified
14.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
14.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
14.16.1 Other Than
Relief No additional significant issues of concerns identified
14.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
14.18.1 Other Than
External Factors No additional significant issues of concerns identified
14.19.1 Other Than
Operations No additional significant issues of concerns identified
14.20.1 Other Than
Maintenance No additional significant issues of concerns identified
14.21.1 Other Than
Drawing No additional significant issues of concerns identified
CNG-HP-38
Parameter: Pressure
Parameter: Temperature
Parameter: Contamination
CNG-HP-39
Parameter: Operation & Maintenance
Parameter: Drawing
Parameter: Composition
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Relief
Parameter: Safety
Parameter: External Factor
CNG PLANT TAMBAK LOROK Page 50 of 53 HAZOP Node N14
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
Node Abbreviations SOP Standard Operating ProceduresReview date IM Inspection & Maintenance
Client PM Preventative MaintenanceProject USD Unit ShutdownFacility PSD Process ShutdownSection ESD Emergency Shutdown H,M,L
Co ConsequencePr ProbabilityRi RiskS Safety RiskC Commercial Risk
Comment
Design Intent
Design Conditions:
Capacity Vent Stack : 12.5 MMSCFD
Opt. Conditions
Drawing Drawing No. TS78-P-PID-015 Rev:
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party
15.1.1 No No Flow No additional significant issues of concerns identified
15.2.1 Less Less Flow No additional significant issues of concerns identified
15.3.1 More More Flow PSV or BDV passing Loss of gas to atmosphere resulting gas cloud around process area and potential fire if ignited
Flame arrestor installed S (4)C(4)
1 S (M4)C(M4)
15.4.1 Reverse Reverse Flow Air ingress to venting system Potential fire/explosion inside piping
Water seal at bottom of vent stack to prevent air ingress to venting system
S (4)C(4)
1 S (M4)C(M4)
15.5.1 Part of Misdirected Flow No additional significant issues of concerns identified
1517-Jun-13
PT ENVIROMATE TECHNOLOGY INTERNATIONALCompressed Natural Gas PlantTambak LorokVent Gas System, including discharge of pressure relieving device and BDVs vent header, KO Drum V-600, up to Vent Stack VS-100
Normally Flare system has no hydrocarbon gas flowingDrain and liquid outlet of Vent Stack is normally close
To gather release gas from process relief valves and BDV and routing gas to safe area
Pressure : 5.5 barG Temperature: 85 deg C
Pressure : ATM - 2 barG Temperature : 10-60 deg C
High, Medium, Risk
PID - Vent Gas System
Rec. No.
B
Parameter: Flow
CNG PLANT TAMBAK LOROK Page 51 of 53 HAZOP Node N15
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
15.6.1 Less Less Level No additional significant issues of concerns identified
15.7.1 More More Level Liquid carry over from PSV/BDV release of hydrocarbon liquid to environment
Vent stack is equipped by dead leg to collect liquid and drain to Sump Tank V-400
S (-)C(2)
1 S (-)C(L2)
15.8.1 Less Less Pressure No additional significant issues of concerns identified
15.9.1 More More Pressure No additional significant issues of concerns identified
15.10.1 Less Less Temperature No additional significant issues of concerns identified
15.11.1 More More Temperature
No additional significant issues of concerns identified
15.12.1 As Well As Contamination No additional significant issues of concerns identified
15.13.1 Other Than
Composition No additional significant issues of concerns identified
15.14.1 Other Than
Corrosion / Erosion
No additional significant issues of concerns identified
15.15.1 Other Than
Instrumentation No additional significant issues of concerns identified
15.16.1 Other Than
Relief No additional significant issues of concerns identified
15.17.1 Other Than
Occupational Safety
No additional significant issues of concerns identified
15.18.1 Other Than
External Factors Lighting struck during PSV/BDV release
Fire at vent stack S (4)C(3)
1 S (M4)C(M3)
Consider to install CO2 snuffing system at VS-100 to extinguish fire at vent stack completed with fusible plug
15.19.1 Other Than
Operations No additional significant issues of concerns identified
15.20.1 Other Than
Maintenance No additional significant issues of concerns identified
Parameter: Operation & Maintenance
Parameter: Drawing
Parameter: Level
Parameter: Temperature
Parameter: Contamination
Parameter: Composition
Parameter: Corrosion / Erosion
Parameter: Instrumentation
Parameter: Relief
Parameter: Safety
CNG-HP-40Parameter: External Factor
Parameter: Pressure
CNG PLANT TAMBAK LOROK Page 52 of 53 HAZOP Node N15
PT ENVIROMATE TECHNOLOGY INDONESIA Appendix B - HAZOP Review Worksheet PT. ISTANA KARANG LAUT
No. Guide Words
Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
15.21.1 Other Than
Drawing
15.21.2 Other Than
Drawing
CNG PLANT TAMBAK LOROK Page 53 of 53 HAZOP Node N15
PT. Enviromate Technology International HAZOP/HAZID of CNG PLANT TAMBAK LOROK
Appendix C
HAZID Review Worksheets
PT. ENVIROMATE TECHNOLOGY INDONESIA Appendix C HAZID Review Worksheet PT ISTANA KARANG LAUT
Node Abbreviations SAAReview date
Co
Client PProject RiArea Rec
SC
H,M,LDrawing Drawing No. Rev. B1
No. Category/ Guideword
Hazard Description Consequences Prevention Control Recommendation/ Comment
Action Party Co. Pr Ri
4.1.1 Natural Events Earthquake Potential of loss of plant integrity leading to damage and hydrocarbon release
- Plant, equipment, building and foundation design anticipated to accommodate earthquake factor (0.15G), referring to UBC-1997 and soil investigation result
4.1.2 Natural Events Rob in process area Potential damage to process equipment
Plant is designed above Rob posistion (80 cm above average ground level vs 70 cm average rob) and in high position
NA
4.1.3 Natural Events Lightning Possible damage to the equipment and potential fire
- Grounding provided for each equipment
Update EQL drawing to show Lightning protection at CNG compartment area (lightning stack) in process/utility area
CNG-HD- 1 S (4)C(3)
4 S (H16)C(H12)
Lightning protection at CNG compartment area (lightning stack) in process/utility area
Rec Number
1 17-Jun-13 Consequency
PT. ENVIROMATE TECHNOLOGY INTERNATIONAL ProbabitliyCOMPRESSED NATURAL GAS PLANT RiskTAMBAK LOROK Recommendation
Comment The plan is located beside Indonesia Power Company. The North side is sea side. The South side is Turbine Generator belong by IP.
Safety RiskCommercial RiskHigh, Medium, Low
General Lay Out CNG Plant TS78-L-LY-001
CNG PLANT TAMBAK LOROK Page 1 of 7 HAZID Worksheet Node 1
PT. ENVIROMATE TECHNOLOGY INDONESIA Appendix C HAZID Review Worksheet PT ISTANA KARANG LAUT
No. Category/ Guideword
Hazard Description Consequences Prevention Control Recommendation/ Comment
Action Party Co. Pr RiRec Number
4.1.4 Natural Events Settlement Possible damage to the equipment and potential fire
- Pile foundation (block design) provided to withstand settlement
4.1.5 Natural Events Land slide No major concern -4.2.1 External Events External corrosion Damage to the
equipment, loss of production
Painting & coating for piping and equipment
Periodic maintenance and inspection for all surface vessels and pipings
S (-)C(3)
2 S (-)C(H9)
-4.3.1 Transportation Light vehicles impact
e.g. CarPotential impact to piping/equipment leading to hydrocarbon release, fire, personnel injury/fatality and asset damage
- vehicle park area away from process area
Operation cars shall be equipped with flame arrestor and diesel engine
CNG-HD- 2 S (4)C(4)
2 S (H8)C(H8)
4.3.2 Transportation Heavy equipment to gas plant e.g. mobile crane
Potential impact to piping/equipment leading to hydrocarbon release, fire, personnel injury/fatality and asset damage
Concrete road Pipe bridge provided to connect each equipment across road
S (4)C(4)
2 S (H8)C(H8)
4.4.1 Lifting Lifting equipment (mobile crane, forklift) failure
Potential damage to pipeline and equipment
SOP for lifting activity including certified personnel to conduct the lifting
- S (-)C(2)
2 S (-)C(M4)
4.5.1 Non Process Fires Bush fire No additional significant issues of concerns identified
- S (4)C(4)
2 S (H8)C(H8)
4.6.1 Security Theft/sabotage Loss of production. Potential major accident leading to personnel injury/fatality
Fence line around the plant area
Security's Officer stand by 24 hrs at plant area
S (4)C(4)
2 S (H8)C(H8)
CNG PLANT TAMBAK LOROK Page 2 of 7 HAZID Worksheet Node 1
PT. ENVIROMATE TECHNOLOGY INDONESIA Appendix C HAZID Review Worksheet PT ISTANA KARANG LAUT
No. Category/ Guideword
Hazard Description Consequences Prevention Control Recommendation/ Comment
Action Party Co. Pr RiRec Number
SOP for control personnel incoming to the plant
- S (4)C(4)
2 S (H8)C(H8)
4.6.2 Security Vandalism No additional significant issues of concerns identified
- -
4.6.3 Security Wild animals (tiger, crocodile and snake)
No additional significant issues of concerns identified
- -
4.7.1 Noise High noise level from compressor and gas engine area
Potential personnel ear injury
- Provide SOP to wear ear plug around noise area
CNG-HD- 3 S (1)C(-)
3 S (H3)C(-)
4.8.1 Health Hazards Toxic Material during handling chemical: for cooling water, corrosion inhibitor e.g. oxygen scavanger
Personnel injury MSDS provided in the storage facility
Ensure portable eye wash station provided during chemical handling (e.g : at control room, loading area and water treatment area)
CNG-HD- 4 S (1)C(-)
3 S (H3)C(-)
PPE - hand gloves, face shield
- S (1)C(-)
3 S (H3)C(-)
SOP for chemical handling
4.8.2 Health Hazards Handling molecular sieve at dryer system
Personnel exposure to H2S resulting in personnel injury
PPE - hand gloves, face shield
JSA S (1)C(-)
3 S (H3)C(-)
SOP for handling molecular sieve at dryer system
4.8.3 Health Hazards Personnel hygiene and living activity
Health impact to operator
Toilet and pantry are provided in control room building
Medical emergency provided (clinic) for operation personnel
S (1)C(-)
4 S (M4)C(-)
CNG PLANT TAMBAK LOROK Page 3 of 7 HAZID Worksheet Node 1
PT. ENVIROMATE TECHNOLOGY INDONESIA Appendix C HAZID Review Worksheet PT ISTANA KARANG LAUT
No. Category/ Guideword
Hazard Description Consequences Prevention Control Recommendation/ Comment
Action Party Co. Pr RiRec Number
4.8.3 Health Hazards Hazardous waste disposal
Personnel injury during handling waste disposal
PPE - hand gloves, face shield
- Alocate waste disposal resulting from operation/construction activity in safe area (third party)
CNG-HD- 5 S (1)C(-)
3 S (H3)C(-)
4.9.1 Maintenance/ construction
Working at high location such as lightning pole, WHRU
Fall and slip resulting in injury/fatality
Maintenance access provided at WHRU
Permit to works system S (4)C(-)
2 S (H8)C(-)
SOP for working at height during maintenance and construction, including competent personnel
4.9.2 Maintenance/ construction
Hot/cold Work Fire and potential fatality
SOP for hot/cold work activity during construction, including competent personnel
permit to works system S (4)C(4)
2 S (H8)C(H8)
4.9.3 Maintenance/ construction
Confined Space Entry Potential fatality due to asphyxiation
SOP for confined space entry during maintenance and construction, including
permit to works system S (4)C(-)
2 S (H8)C(-)
4.9.5 Maintenance/ construction
Electrical Hazards Potential electrocution resulting in injury/fatality
Proper insulation for cabling/wiring
ELCB (Earth Leakage Circuit Breaker) provided for electrical equipment/devices e.g. welding machine
S (4)C(-)
2 S (H8)C(-)
4.9.6 Maintenance/ construction
Hot Surfaces at exhaust gas, WHRU and heat exchanger (E-200)
Potential injury due to exposure to heat
personal protection insulation provided
PPE Provide warning sign around hot surface equipment and pipings
CNG-HD- 6 S (2)C(-)
2 S (M4)C(-)
CNG PLANT TAMBAK LOROK Page 4 of 7 HAZID Worksheet Node 1
PT. ENVIROMATE TECHNOLOGY INDONESIA Appendix C HAZID Review Worksheet PT ISTANA KARANG LAUT
No. Category/ Guideword
Hazard Description Consequences Prevention Control Recommendation/ Comment
Action Party Co. Pr RiRec Number
4.10.1 Loss of Containment
Leak from Process Equipment
Release of hydrocarbon resulting in potential fire/explosion leading to injury/fatality
Unit SD by low pressure trip
Gas detection system at process area
Define philosophy of fire and gas detection system and develop fire and gas detection area at process plant
CNG-HD- 7 S (4)C(4)
2 S (H8)C(H8)
- Fire hydrant provided with source from existing IP
Regularly to check temperature in the MCC cabinet and DCS panel to monitor short circuit and provide portable fire extinguisher
CNG-HD- 8
4.10.2 Loss of Containment
Diesel Leak No additional significant issues of concerns identified
4.11.1 Ignition Sources Battery Fire/explosion in the event of hydrocarbon release.
Battery room is located in non hazardous area
Heat & Smoke detector, Portable Fire Extinguisher provided at control room & MCC room
Regularly to check temperature in the MCC cabinet and DCS panel to monitor short circuit and provide portable fire extinguisher
CNG-HD- 9 S (4)C(4)
2 S (H8)C(H8)
4.11.2 Ignition Sources Vent Fire/explosion in the event of hydrocarbon release in process area if stroke by lightning
- Lightning protection provided at CNG compartment area
Define safe location and minimum height required for vent stack and vent location to be suitable with wind directions so that dispersed gas will not be exposed to process plan
CNG-HD- 10 S (4)C(4)
2 S (H8)C(H8)
S (4)C(4)
2 S (H8)C(H8)
4.11.3 Ignition Sources Static electricity from external vehicle
Fire/explosion in the event of hydrocarbon release.
- vehicle park area away from process area
S (4)C(4)
2 S (H8)C(H8)
CNG PLANT TAMBAK LOROK Page 5 of 7 HAZID Worksheet Node 1
PT. ENVIROMATE TECHNOLOGY INDONESIA Appendix C HAZID Review Worksheet PT ISTANA KARANG LAUT
No. Category/ Guideword
Hazard Description Consequences Prevention Control Recommendation/ Comment
Action Party Co. Pr RiRec Number
4.12.1 Escape/ Refuge Fire on Plant area Personnel trap/ unable to evacuate leading to injury/fatality
ERP - Provide emergency evacuation risk analysis to determine safe evacuation route and location of muster area
CNG-HD- 11 S (4)C(4)
3 S (H8)C(H8)
- - Form emergency response team (ERT) and conduct emergency drill
CNG-HD- 12 S (4)C(4)
4 S (H8)C(H8)
- - S (4)C(4)
5 S (H8)C(H8)
4.13.1 Emergency Lighting
Personnel trap in wrong way
Personnel injury/fatality
Emergency lighting for evacuation is provided in control room and evacuation route
- S (4)C(4)
6 S (H8)C(H8)
4.14.1 Manned Building Control room Fire or explosion from process area impact to control room leading to potential personnel injury/fatality
- Heat and Smoke detector
Review scenario of fire and explosion from gas plant to the area of standby personnel such as control room and provide mitigation plan (design and location of the building) to anticipate fire/explosion
CNG-HD- 13 S (4)C(4)
2 S (H8)C(H8)
- - Define safety requirement on control room specification to accommodate fire/explosion scenario e.g. door, wall and window specifications
CNG-HD- 14 S (4)C(4)
3 S (H8)C(H8)
- - S (4)C(4)
4 S (H8)C(H8)
Inability to monitor process area
- - Consider to provide CCTV in the control room for monitoring purpose
CNG-HD- 15 S (4)C(4)
5 S (H8)C(H8)
CNG PLANT TAMBAK LOROK Page 6 of 7 HAZID Worksheet Node 1
PT. ENVIROMATE TECHNOLOGY INDONESIA Appendix C HAZID Review Worksheet PT ISTANA KARANG LAUT
No. Category/ Guideword
Hazard Description Consequences Prevention Control Recommendation/ Comment
Action Party Co. Pr RiRec Number
4.15.1 Communication Inability to contact control room within emergency
Inability to coordinate response leading to potential major accident leading to personnel injury/fatality and asset loss
Each operator provided with hand held radio
F&G alarm system Define internal and external communication system (PABX) for connecting operator in the control room to outside parties
CNG-HD- 16 S (4)C(4)
2 S (H8)C(H8)
4.16.1 Shutdown Inability to initiate ESD
Inability to control fire leading to potential major accident leading to personnel injury/fatality and asset loss
Local ESD push button at control room
- Define safety layout at CNG plant to show ESD push button, fire hydrant, etc
CNG-HD- 17 S (4)C(4)
2 S (H8)C(H8)
4.16.2 Shutdown Loss of power Plant shutdown resulting loss of production
ESD is fail safe action
UPS is provided S (-)C(4)
2 S (-)C(H8)
Uncontrolled process upset
- Alternative power source from PLN for emergency equipment
S (-)C(4)
3 S (-)C(H8)
4.17.1 Other Plant layout - - S (-)C(-)
- S (-)C(-)
4.18.1 Discharge to air Note: venting only for emergency situation
- -
4.18.3 Discharge to water
Blowdown of water from cooling tower, discharge RO
Potential contamination from process fluid
- Discharge water is connected to existing canal (IP)
Define Sampling point to monitor discharge water
CNG-HD- 18
4.18.4 Discharge to soil No additional significant issue of concern identified
4.18.5 Waste disposal Disposal of operation/ construction waste e.g. plant, log
Potential environmental disturbance
- - Alocate waste disposal resulting from operation/construction activity in safe area (third party)
CNG-HD- 5 S (-)C(-)
4 S (-)C(-)
CNG PLANT TAMBAK LOROK Page 7 of 7 HAZID Worksheet Node 1
PT. Enviromate Technology International HAZOP/HAZID of CNG PLANT TAMBAK LOROK
Appendix D
Drawings Reviewed