Haverhill Cooperative School District October 2 Bond Hearing Presentation

60
Haverhill Cooperative School District Bond Hearing and Informational Meeting October 2, 2008 6 pm Dr. John A. Bagonzi Woodsville Community Building

description

Presentation made to the taxpayers of the town of Haverhill regarding the special school district meeting October 23.

Transcript of Haverhill Cooperative School District October 2 Bond Hearing Presentation

Page 1: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Haverhill Cooperative School District Bond Hearing and

Informational Meeting

October 2, 2008

6 pm

Dr. John A. Bagonzi

Woodsville Community Building

Page 2: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 3: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 4: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 5: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 6: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 7: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 8: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 9: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 10: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 11: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 12: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 13: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 14: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 15: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 16: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 17: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 18: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 19: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 20: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 21: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 22: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 23: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 24: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 25: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 26: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 27: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 28: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 29: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 30: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 31: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 32: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 33: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 34: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 35: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 36: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 37: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 38: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 39: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 40: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 41: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 42: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 43: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 44: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 45: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 46: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 47: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 48: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 49: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 50: Haverhill Cooperative School District October 2 Bond Hearing Presentation
Page 51: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Project Scope

• Adding Roof Trusses

• Replacing Drywall

• Upgrade Electrical to Current Code

• Ventilate Entire Roof

Page 52: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Project Partners

• Architect – Mac Rood

• Structural Engineer – Bruce Stewart

• Contractor – Fenn-Way Builders

• Fire Engineer – Nick Cricenti Jr.

• District Clerk of the Works – To be determined

Page 53: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Project Cost

• Based on what know today

• Project is being updated based on information provided at weekly building team meeting

• Final cost will be available for special district meeting

Page 54: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Project Cost(as of 10/2/2008)

Total Project Estimate $2,450,016

Funds Already Budgeted - $239,532

Building Trust Fund Used - $80,392

Estimated Loan Required $2,130,092

Page 55: Haverhill Cooperative School District October 2 Bond Hearing Presentation

How are we going to Fund the Project

Estimated Loan Required $2,130,092

Quality Zone Academy Bonds $1,498,000

Loan for Balance $632,092

Page 56: Haverhill Cooperative School District October 2 Bond Hearing Presentation

QZAB Bonds

QZAB Bonds Available $1,498,000

Interest Earned over 15 years - $157,290

Building Aid to be received over 15 years

- $898,800

QZAB Net Cost to Tax Payers $441,910

Page 57: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Loan for Balance of Funds

Principal $632,092

Estimated Interest (4.25%) $70,655

Building Aid to be received over 5 years

- $379,255

Loan Net Cost to Tax Payers $323,492

Page 58: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Net Cost to the Taxpayer

QZAB Net Cost to Tax Payers $441,910

Loan Net Cost to Tax Payers $323,492

Building Aid to be Received on Funds already Spent

- $167,012

Net Future Cost to the Taxpayer $598,390

Page 59: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Impact on Your Taxes• 2009 / 2010 Tax Rate Estimate for this

Project is $0.16 per $1000.00

• Result is $16.00 for a $100,000 home

• Current Bonds for 1991 District Building Project are paid off at the end of 2011

• Based on today’s rate, the tax rate will decrease a total of $1.02 over the following five years

Page 60: Haverhill Cooperative School District October 2 Bond Hearing Presentation

Haverhill Cooperative School District

Special District Meeting

Thursday October 23

6 pm

Dr. John A. Bagonzi Woodsville Community Building

www.sau23.org