Haverhill Cooperative School District October 2 Bond Hearing Presentation
description
Transcript of Haverhill Cooperative School District October 2 Bond Hearing Presentation
![Page 1: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/1.jpg)
Haverhill Cooperative School District Bond Hearing and
Informational Meeting
October 2, 2008
6 pm
Dr. John A. Bagonzi
Woodsville Community Building
![Page 2: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/2.jpg)
![Page 3: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/3.jpg)
![Page 4: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/4.jpg)
![Page 5: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/5.jpg)
![Page 6: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/6.jpg)
![Page 7: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/7.jpg)
![Page 8: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/8.jpg)
![Page 9: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/9.jpg)
![Page 10: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/10.jpg)
![Page 11: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/11.jpg)
![Page 12: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/12.jpg)
![Page 13: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/13.jpg)
![Page 14: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/14.jpg)
![Page 15: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/15.jpg)
![Page 16: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/16.jpg)
![Page 17: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/17.jpg)
![Page 18: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/18.jpg)
![Page 19: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/19.jpg)
![Page 20: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/20.jpg)
![Page 21: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/21.jpg)
![Page 22: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/22.jpg)
![Page 23: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/23.jpg)
![Page 24: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/24.jpg)
![Page 25: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/25.jpg)
![Page 26: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/26.jpg)
![Page 27: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/27.jpg)
![Page 28: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/28.jpg)
![Page 29: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/29.jpg)
![Page 30: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/30.jpg)
![Page 31: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/31.jpg)
![Page 32: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/32.jpg)
![Page 33: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/33.jpg)
![Page 34: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/34.jpg)
![Page 35: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/35.jpg)
![Page 36: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/36.jpg)
![Page 37: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/37.jpg)
![Page 38: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/38.jpg)
![Page 39: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/39.jpg)
![Page 40: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/40.jpg)
![Page 41: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/41.jpg)
![Page 42: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/42.jpg)
![Page 43: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/43.jpg)
![Page 44: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/44.jpg)
![Page 45: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/45.jpg)
![Page 46: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/46.jpg)
![Page 47: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/47.jpg)
![Page 48: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/48.jpg)
![Page 49: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/49.jpg)
![Page 50: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/50.jpg)
![Page 51: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/51.jpg)
Project Scope
• Adding Roof Trusses
• Replacing Drywall
• Upgrade Electrical to Current Code
• Ventilate Entire Roof
![Page 52: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/52.jpg)
Project Partners
• Architect – Mac Rood
• Structural Engineer – Bruce Stewart
• Contractor – Fenn-Way Builders
• Fire Engineer – Nick Cricenti Jr.
• District Clerk of the Works – To be determined
![Page 53: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/53.jpg)
Project Cost
• Based on what know today
• Project is being updated based on information provided at weekly building team meeting
• Final cost will be available for special district meeting
![Page 54: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/54.jpg)
Project Cost(as of 10/2/2008)
Total Project Estimate $2,450,016
Funds Already Budgeted - $239,532
Building Trust Fund Used - $80,392
Estimated Loan Required $2,130,092
![Page 55: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/55.jpg)
How are we going to Fund the Project
Estimated Loan Required $2,130,092
Quality Zone Academy Bonds $1,498,000
Loan for Balance $632,092
![Page 56: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/56.jpg)
QZAB Bonds
QZAB Bonds Available $1,498,000
Interest Earned over 15 years - $157,290
Building Aid to be received over 15 years
- $898,800
QZAB Net Cost to Tax Payers $441,910
![Page 57: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/57.jpg)
Loan for Balance of Funds
Principal $632,092
Estimated Interest (4.25%) $70,655
Building Aid to be received over 5 years
- $379,255
Loan Net Cost to Tax Payers $323,492
![Page 58: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/58.jpg)
Net Cost to the Taxpayer
QZAB Net Cost to Tax Payers $441,910
Loan Net Cost to Tax Payers $323,492
Building Aid to be Received on Funds already Spent
- $167,012
Net Future Cost to the Taxpayer $598,390
![Page 59: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/59.jpg)
Impact on Your Taxes• 2009 / 2010 Tax Rate Estimate for this
Project is $0.16 per $1000.00
• Result is $16.00 for a $100,000 home
• Current Bonds for 1991 District Building Project are paid off at the end of 2011
• Based on today’s rate, the tax rate will decrease a total of $1.02 over the following five years
![Page 60: Haverhill Cooperative School District October 2 Bond Hearing Presentation](https://reader037.fdocuments.net/reader037/viewer/2022103109/54582661af7959de728b71a2/html5/thumbnails/60.jpg)
Haverhill Cooperative School District
Special District Meeting
Thursday October 23
6 pm
Dr. John A. Bagonzi Woodsville Community Building
www.sau23.org